- CN209565776U CN209565776U CN201822115934.6U CN201822115934U CN209565776U CN 209565776 U CN209565776 U CN 209565776U CN 201822115934 U CN201822115934 U CN 201822115934U CN 209565776 U CN209565776 U CN 209565776U
- Authority
- CN
- China
- Prior art keywords
- roller
- section
- arc
- forming
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000003466 welding Methods 0.000 claims abstract description 54
- 239000002184 metal Substances 0.000 claims abstract description 47
- 238000000034 method Methods 0.000 claims abstract description 17
- 230000008569 process Effects 0.000 claims abstract description 14
- 238000007493 shaping process Methods 0.000 claims description 44
- 238000013000 roll bending Methods 0.000 claims description 34
- 238000005096 rolling process Methods 0.000 claims description 28
- 238000001816 cooling Methods 0.000 claims description 25
- 238000005520 cutting process Methods 0.000 claims description 20
- 230000005540 biological transmission Effects 0.000 claims description 17
- 238000009423 ventilation Methods 0.000 claims description 14
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 14
- 239000007921 spray Substances 0.000 claims description 11
- 238000009434 installation Methods 0.000 claims description 9
- 238000003698 laser cutting Methods 0.000 claims description 9
- 238000005452 bending Methods 0.000 claims description 8
- 230000007246 mechanism Effects 0.000 claims description 7
- 230000009471 action Effects 0.000 claims description 5
- 238000010008 shearing Methods 0.000 claims description 5
- 238000004519 manufacturing process Methods 0.000 claims description 4
- 238000003860 storage Methods 0.000 claims description 3
- 238000009740 moulding (composite fabrication) Methods 0.000 description 71
- 238000012545 processing Methods 0.000 description 10
- 238000010586 diagram Methods 0.000 description 6
- 238000012546 transfer Methods 0.000 description 6
- 229910000797 Ultra-high-strength steel Inorganic materials 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000010438 heat treatment Methods 0.000 description 2
- 210000001503 joint Anatomy 0.000 description 2
- 206010039203 Road traffic accident Diseases 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000001035 drying Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009499 grossing Methods 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 238000010791 quenching Methods 0.000 description 1
- 230000000171 quenching effect Effects 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 230000032258 transport Effects 0.000 description 1
- 238000009966 trimming Methods 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Landscapes
- Bending Of Plates, Rods, And Pipes (AREA)
Abstract
本实用新型提供了一种汽车上的A柱的连续成形装置,包括若干个成形辊轮组,用于将金属板材两边缘以纵向地沿金属板材同一侧逐渐成形两条相对称的凸起部分,两凸起部分的一端向同一侧弯曲形成弧形段且两弧形段端面接触,金属板材的中部形成水平段,两凸起部分在成形过程中由若干个成形辊轮组将两凸起部分与水平段之间形成弧形连接段以形成大体呈三角形的连续梁;焊接装置,该焊接装置安装在若干个成形辊轮组的尾端,用于将两弧形段相接触的端面焊接在一起;所述焊接装置的焊接端与两弧形段的端面或两弧形段的端面的延长线相接。本实用新型提出的汽车上的A柱的连续成形装置,用于高效生产汽车A柱,产品质量高,提高A柱的强度。
The utility model provides a continuous forming device for an A-pillar on an automobile, which comprises a plurality of forming roller groups, which are used to form two symmetrical convex parts along the same side of the metal plate along the two edges of the metal plate longitudinally. , one end of the two convex parts is bent to the same side to form an arc section and the end faces of the two arc sections are in contact, the middle part of the metal sheet forms a horizontal section, and the two convex parts are formed by several forming roller groups during the forming process. An arc-shaped connection section is formed between the part and the horizontal section to form a generally triangular continuous beam; the welding device is installed at the tail end of several forming roller groups for welding the end faces of the two arc-shaped sections in contact together; the welding end of the welding device is in contact with the end faces of the two arc-shaped segments or the extension lines of the end faces of the two arc-shaped segments. The continuous forming device for the A-pillar on the automobile provided by the utility model is used for efficiently producing the A-pillar of the automobile, the product quality is high, and the strength of the A-pillar is improved.
Description
技术领域technical field
本实用新型涉及交通运输工具技术领域,具体涉及一种汽车A柱的成形装置。The utility model relates to the technical field of transportation tools, in particular to a forming device for an automobile A-pillar.
背景技术Background technique
A柱作为汽车的骨架,在汽车左前方和右前方用于连接车顶和前舱的连接柱,在发动机舱和驾驶舱之间,左右后视镜的上方,会遮挡一部分的转弯视界即盲区,盲区的存在是由于车身结构决定的,A柱盲区的大小,由于驾驶座是在左边,所以左边A柱的盲区是较右边的大很多,为了保证强度,一般A柱较宽,将会形成的左边的盲区是6.8度左右,右边的是2.3度左右,盲区较大,将会影响驾驶员的视野,存在交通事故的风险,而现有的汽车部件大多采用冲压成形的方式而成,如中国专利CN101288889公开了《一种超高强度钢热冲压成型工艺及成型模具》、中国专利CN101486062A公开了一种《高强度钢零件的热成形和切边一体化工艺及模具》、中国专利CN101717850A公开了《一种超高强度钢板冲压前的热处理拼接工艺及装置》、中国专利CN101961744A《拼焊板的成形方法及其装置》及中国专利CN202297712U《超高强钢高温拼接淬火成形装置》,上述现有技术中所提工艺及模具结构生产的汽车零件虽具有高强度,但由于是冲压成形,只能先冲压出两块半块,再焊接形成截面为长方形或矩形的A柱主体,无法满足小尺寸A柱的加工,零件存在多次转,生产效率较低。As the skeleton of the car, the A-pillar is used to connect the roof and the front cabin at the left and right front of the car. Between the engine compartment and the cockpit, above the left and right rearview mirrors, it will block part of the turning vision, that is, the blind spot. , the existence of the blind area is determined by the body structure. The size of the blind area of the A-pillar, since the driver's seat is on the left, the blind area of the left A-pillar is much larger than that of the right. In order to ensure the strength, the A-pillar is generally wider, which will form a The blind area on the left is about 6.8 degrees, and the one on the right is about 2.3 degrees. The blind area is large, which will affect the driver's vision and the risk of traffic accidents. Most of the existing auto parts are formed by stamping, such as Chinese patent CN101288889 discloses "a hot stamping forming process and forming die for ultra-high strength steel", Chinese patent CN101486062A discloses a "integrated process and mold for hot forming and trimming of high-strength steel parts", and Chinese patent CN101717850A discloses "A heat treatment splicing process and device before ultra-high-strength steel plate stamping", Chinese patent CN101961744A "forming method and device for tailor-welded blanks" and Chinese patent CN202297712U "high-temperature splicing and quenching forming device for ultra-high-strength steel", the above-mentioned existing Although the auto parts produced by the process mentioned in the technology and the mold structure have high strength, because they are stamped and formed, two and a half pieces can only be stamped out first, and then welded to form the main body of the A-pillar with a rectangular or rectangular cross-section, which cannot meet the small size requirements. In the processing of the A-pillar, the parts have multiple rotations, and the production efficiency is low.
另外,CN2016104822235公开的一种汽车A柱内板总成,该A柱内板总成的支撑强度较大,在出现意外事故时,A柱内板能很好的保护驾驶舱内的人员。主体结构较为稳定,抗硬力冲击较好,但其截面大体呈长方形,在汽车应用时也存在视野遮挡较大的问题。从驾驶员的视野考虑,则希望A柱越小越好,但从车身角度考虑,A柱作为汽车的骨架,强度足够大才能保证驾驶员的安全。因此,急需一种加工装置用于小尺寸A柱的加工。In addition, CN2016104822235 discloses an automobile A-pillar inner panel assembly, the A-pillar inner panel assembly has relatively high support strength, and in the event of an accident, the A-pillar inner panel can well protect the occupants in the cockpit. The main structure is relatively stable and has good resistance to hard impacts, but its cross-section is generally rectangular, and there is also a problem of large visual obstruction in automotive applications. From the perspective of the driver, it is hoped that the smaller the A-pillar, the better, but from the perspective of the body, the A-pillar is the skeleton of the car, and its strength is strong enough to ensure the safety of the driver. Therefore, there is an urgent need for a processing device for processing small-sized A-pillars.
实用新型内容Utility model content
本实用新型提供了一种汽车上的A柱的连续成形装置,用于高效的生产汽车A柱,使产品加工质量一致,提高A柱的强度,转运次数少。The utility model provides a continuous forming device for an A-pillar on an automobile, which is used for efficiently producing the A-pillar of the automobile, so that the processing quality of the product is consistent, the strength of the A-pillar is improved, and the number of transfers is small.
为实现上述目的,本实用新型采用了如下的技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:
一种汽车上的A柱的连续成形装置,包括成形辊轮组,用于将金属板材两边缘以纵向地沿金属板材同一侧逐渐成形两条相对称的凸起部分,两凸起部分的一端向同一侧弯曲形成弧形段且两弧形段端面接触,金属板材的中部形成水平段,两凸起部分在成形过程中由若干个成形辊轮组将两凸起部分与水平段之间形成弧形连接段以形成大体呈三角形的连续梁;A continuous forming device for an A-pillar on an automobile, including a forming roller set, which is used to gradually form two symmetrical raised parts longitudinally along the same side of the metal sheet at both edges of the metal sheet, and one end of the two raised parts Bending to the same side to form an arc section and the end faces of the two arc sections are in contact, the middle part of the metal sheet forms a horizontal section, and the two convex parts are formed between the two convex parts and the horizontal section by several forming roller sets during the forming process. Arc-shaped connecting segments to form a generally triangular continuous beam;
焊接装置,该焊接装置安装在若干个成形辊轮组的尾端,用于将两弧形段相接触的端面焊接在一起;所述焊接装置的焊接端与两弧形段的端面或两弧形段的端面的延长线相接;Welding device, which is installed at the tail end of several forming roller groups, is used to weld together the end faces of the two arc-shaped segments in contact; the welding end of the welding device is connected to the end faces of the two arc-shaped segments or the two arcs The extension line of the end face of the shape segment is connected;
冷却装置,该冷却装置安装于焊接装置之后,用于冷却经焊接后的连续梁,以增加连续梁的抗弯强度和抗剪切力;A cooling device, which is installed after the welding device, is used to cool the welded continuous beam, so as to increase the bending strength and shearing force of the continuous beam;
切断装置,将冷却后的连续梁以产品需求长度切断形成梁柱。The cutting device cuts the cooled continuous beam to the length required by the product to form a beam column.
辊弯装置,用于将梁柱的中部进行辊弯。Roll bender for roll bending the middle of beams and columns.
进一步的,成形辊轮组、焊接装置、冷却装置及切断装置依次连接成一条生产线。Further, the forming roller set, the welding device, the cooling device and the cutting device are sequentially connected to form a production line.
进一步的,所述成形辊轮组包括第一辊轮段及第二辊轮段,第二辊轮段位于第一辊轮段的末端,其中第一辊轮段及第二辊轮段均由多个辊轮架组依次布置而成,第一辊压段用于将金属板材的两边缘向金属板材同一侧逐渐辊压出弧形段,第一辊压段的末端辊轮将弧形段成形为7.2mm的半径;第二辊压段的首端对弧形段的进行整形,并保持弧形段的半径R为9.45mm,第二辊压段的首端至尾端均用于对金属板材的板面成形,将金属板材的板面逐渐形成两条凸起段及一条水平段,水平段两侧分别与两条凸起段之间形成弧形连接段,且两条凸起段分别与弧形段连接,第二辊压段的尾端用于将两条凸起段、水平段、弧形连接段及弧形段成型为三角形,且两边缘的弧形段相对接触。Further, the forming roller set includes a first roller segment and a second roller segment, and the second roller segment is located at the end of the first roller segment, wherein the first roller segment and the second roller segment are composed of A plurality of roller frame groups are arranged in sequence. The first rolling section is used to gradually roll out the arc section from the two edges of the metal sheet to the same side of the metal sheet. The end rollers of the first rolling section press the arc section It is formed into a radius of 7.2mm; the head end of the second rolling section is shaped to the arc section, and the radius R of the arc section is kept at 9.45mm, and the head end to the tail end of the second rolling section are used to shape the arc section. The surface of the metal sheet is formed, and the surface of the metal sheet is gradually formed into two raised sections and a horizontal section. The two sides of the horizontal section form arc-shaped connecting sections with the two raised sections, and the two raised sections They are respectively connected with the arc sections, and the tail end of the second rolling section is used to shape the two raised sections, the horizontal section, the arc connecting section and the arc section into a triangle, and the arc sections at the two edges are in relative contact.
进一步的,所述第一辊轮段包括十二个辊轮架组,十二个辊轮架组依次安装在基座上,第一位辊轮与动力机连接,用于传送金属板材,前第二至第四位辊轮架组用于对金属板材边缘初成形,第五至第十二位辊轮均设置有对金属板材边缘逐渐成形为弧形段的成形部,且第五和第九位辊轮连接有动力机。Further, the first roller section includes twelve roller frame groups, and the twelve roller frame groups are sequentially installed on the base, the first roller is connected with the power machine, and is used for conveying the metal sheet, and the former The second to fourth roller frame groups are used to initially form the edge of the metal sheet, the fifth to the twelfth rollers are all provided with a forming part that gradually forms the edge of the metal sheet into an arc segment, and the fifth and ninth The bit rollers are connected with a power machine.
进一步的,所述第二辊压段包括十个成形辊轮架组,其中,十个成形辊轮架组依次安装在基座上,第一位成形辊轮架组位于第一辊轮段的尾部,第二辊轮段与第一辊轮段呈“一”字形排列,第一位成形辊轮架组设置有对金属板材的板面成形为两条凸起段、一条水平段及弧形连接段的第二成形部,第二位成形辊轮架组至第十位成形辊轮架组均设置有将两条凸起段、一条水平段、弧形连接段及两边缘的弧形段成型为三角形的第三成形部。Further, the second rolling section includes ten forming roller frame groups, wherein the ten forming roller frame groups are installed on the base in sequence, and the first forming roller frame group is located at the At the tail, the second roller section and the first roller section are arranged in a "one" shape, and the first forming roller frame set is equipped with two convex sections, one horizontal section and an arc shape for the surface of the metal sheet. The second forming part of the connecting section, the second forming roller frame group to the tenth forming roller frame group are all provided with two convex sections, a horizontal section, an arc connecting section and arc sections on both edges Shaped into a triangular third shaped part.
进一步的,焊接装置包括高频焊机、焊机滑道、夹持辊轮组;夹持辊轮组包含推动辊轮和两个定位辊轮;两个定位辊轮用于支撑两凸起部分;推动辊轮用于将连续梁沿两个定位辊轮之间推动;所述焊机滑道设置在推动辊轮相对一侧;高频焊机沿连续梁延伸方向滑动设于焊机滑道上,其焊枪正对两弧形段对接处。Further, the welding device includes a high-frequency welder, a welder slide, and a clamping roller set; the clamping roller set includes a push roller and two positioning rollers; the two positioning rollers are used to support the two raised parts The push roller is used to push the continuous beam along the two positioning rollers; the welding machine slideway is arranged on the opposite side of the push roller; , the torch is facing the joint of the two arc segments.
进一步的,所述夹持辊轮组为两个;两个夹持辊轮组的同一侧定位辊轮分别转动连接在同一辊轮定位架上;两个推动辊轮连接在同一辊轮定位架上,且在伸缩气缸的作用下沿焊枪方向移动。Further, there are two clamping roller sets; the positioning rollers on the same side of the two clamping roller sets are respectively rotatably connected to the same roller positioning frame; the two pushing rollers are connected to the same roller positioning frame up, and move along the direction of the welding torch under the action of the telescopic cylinder.
进一步的,在夹持辊轮组尾部设置有2-5组整形辊轮组,每组整形辊轮组包括板状整形板及三个整形轮,在板状整形板的中部设置有三角形通孔,三个整形轮均安装在三角形通孔入口处的板状整形板上,三个整形轮呈三角形布置,且三个整形轮围成可使三角形的连续梁通过的三角形空位。Further, there are 2-5 sets of shaping roller sets at the end of the clamping roller set, each set of shaping roller sets includes a plate-shaped shaping plate and three shaping wheels, and a triangular through hole is arranged in the middle of the plate-shaped shaping plate , the three shaping wheels are installed on the plate-shaped shaping plate at the entrance of the triangular through hole, the three shaping wheels are arranged in a triangle, and the three shaping wheels enclose a triangular space through which the triangular continuous beam can pass.
进一步的,冷却装置包括水冷箱及位于水冷箱出口的空冷箱,水冷箱位于焊接装置之后,水冷箱包含喷水管、冷流内腔及减速辊轮组;所述减速辊轮组用于连续梁在冷流内腔传送;喷水管的喷枪指向减速辊轮组上的连续梁;所述冷流内腔上设有低于连续梁的排水管;排水管一端连接有排水或蓄水装置;空冷箱包含送风机构和若干个通风管;所述通风管沿空冷箱侧壁设置且设有与空冷箱连通的若干出风孔,且通风管另一端与送风机构连通。Further, the cooling device includes a water-cooled box and an air-cooled box located at the outlet of the water-cooled box. The water-cooled box is located behind the welding device. The water-cooled box includes a water spray pipe, a cold flow inner cavity and a deceleration roller set; the deceleration roller set is used for continuous The beam is conveyed in the cold flow inner chamber; the spray gun of the water spray pipe is directed to the continuous beam on the deceleration roller set; the cold flow inner chamber is provided with a drain pipe lower than the continuous beam; one end of the drain pipe is connected with a drainage or water storage device The air-cooled box includes an air supply mechanism and several ventilation pipes; the ventilation pipe is arranged along the side wall of the air-cooled box and is provided with several air outlets connected with the air-cooled box, and the other end of the ventilation pipe is connected with the air supply mechanism.
进一步的,切断装置包含激光切割机和分段辊轮组;所述分段辊轮组连接有PLC控制器,用于控制连续梁的分段输送;激光切割机的切割枪指向分段辊轮组上的连续梁,且沿连续梁弧形段一侧向下切割;所述激光切割机的控制端与PLC控制器连接。Further, the cutting device includes a laser cutting machine and a segmented roller group; the segmented roller group is connected with a PLC controller for controlling the segmental delivery of the continuous beam; the cutting torch of the laser cutting machine points to the segmented roller The continuous beam on the group is cut downward along one side of the arc section of the continuous beam; the control end of the laser cutting machine is connected with the PLC controller.
进一步的,在切断装置与冷却装置之间安装有校直装置,用于将冷却后的连续梁进行校直并整形,该校直装置包括多组校直辊轮组,每组校直辊轮组主要由三个校直辊及辊轮架构成,三个校直辊轮均通过轮轴安装在辊轮架上且三个校直辊轮呈三角形布置,与连续梁的三条边相对应。Further, a straightening device is installed between the cutting device and the cooling device for straightening and shaping the cooled continuous beam. The straightening device includes multiple sets of straightening rollers, and each set of straightening rollers The group is mainly composed of three straightening rollers and a roller frame. The three straightening rollers are all installed on the roller frame through the axle and the three straightening rollers are arranged in a triangle, corresponding to the three sides of the continuous beam.
进一步的,辊弯装置包含沿辊弯装置出口依次设置的动辊轮组、定辊轮组和传送辊轮组,以及第一转动结构、第二转动结构;定辊轮组用于对连续梁定位;所述动辊轮组设于辊弯装置出口与定辊轮组相对;传送辊轮组用于传送梁柱;且动辊轮组分别通过第一转动结构和第二转动结构实现上下及左右摆动,以实现梁柱的辊弯。Further, the roll bending device includes a moving roll set, a fixed roll set, and a conveying roll set arranged in sequence along the exit of the roll bending device, as well as a first rotating structure and a second rotating structure; the fixed roll set is used to adjust the continuous beam Positioning; the moving roller set is set at the exit of the roll bending device and is opposite to the fixed roller set; the transmission roller set is used to transmit beams and columns; and the moving roller set realizes up and down and Swing left and right to achieve roll bending of beams and columns.
进一步的,第一转动结构为沿梁柱三角形环向转动连接在辊弯装置出口一侧的转动支架,且连接有控制其转动的驱动装置;第二转动结构为沿梁柱纵向转动连接在转动支架的连接板,由驱动装置控制其转动;动辊轮组连接在连接板中设有的安装通孔内;梁柱通过安装通孔在动辊轮组、定辊轮组和传送辊轮组之间传送。Further, the first rotating structure is a rotating bracket connected to the outlet side of the roll bending device along the triangular ring direction of the beam column, and is connected with a driving device to control its rotation; the second rotating structure is rotating along the longitudinal direction of the beam column and connected to the rotating The connecting plate of the bracket is controlled by the driving device to rotate; the moving roller group is connected in the installation through hole provided in the connecting plate; the beam column is connected to the moving roller group, the fixed roller group and the transmission roller group transfer between.
进一步的,所述动辊轮组包含三个夹紧辊轮;所述夹紧辊轮分别呈三角形布置,且三个夹紧辊轮横向围成可使梁柱通过的三角形空位,且两端通过轮轴连接在安装通孔内。Further, the moving roller set includes three clamping rollers; the clamping rollers are respectively arranged in a triangle, and the three clamping rollers laterally surround a triangular vacancy through which beams and columns can pass, and the two ends It is connected in the installation through hole through the wheel shaft.
进一步的,还包括开卷机及位于开卷机出料端的整平机,整平机的进料端设置有入料滚筒,整平机的出料端设置有出料滚筒,整平机出料端与成形辊轮组的入料端之间设置有传输滚筒。Further, it also includes an uncoiler and a leveler located at the discharge end of the uncoiler. The feed end of the leveler is provided with a feeding roller, and the output end of the leveler is provided with a discharge roller. A transmission roller is arranged between the feeding end of the forming roller group.
本实用新型提供的汽车上的A柱的连续成形装置,通过将金属板材加工成截面为大体呈三角形的连续梁,与液压成形相比,节约了加工成本,并且提高了连接柱的强度,减少驾驶时对视野上产生的屏障;由于本装置将成形、焊接、冷却、切断、辊弯一体化,减少了加工转运次数,加快了连接柱的加工效率,并且提高了连接柱的加工质量;通过成形辊轮组将金属板材逐步成形加工,加工精度高;焊接后迅速冷却,防止连续梁由于高温焊接后的不稳定性造成剪切面不平滑均匀或辊弯变形的问题。The continuous forming device for the A-pillar on the automobile provided by the utility model processes the metal sheet into a continuous beam with a substantially triangular cross-section. Compared with hydraulic forming, the processing cost is saved, and the strength of the connecting column is improved, reducing the Barriers to the field of view when driving; because the device integrates forming, welding, cooling, cutting, and roll bending, the number of processing and transfers is reduced, the processing efficiency of the connecting column is accelerated, and the processing quality of the connecting column is improved; through The forming roller set forms the metal sheet step by step with high processing precision; it cools rapidly after welding to prevent the continuous beam from being unstable after high-temperature welding and causing uneven shearing surface or roll bending deformation.
本实用新型的其它优点、目标和特征将部分通过下面的说明体现,部分还将通过对本实用新型的研究和实践而为本领域的技术人员所理解。Other advantages, objectives and features of the utility model will partly be embodied through the following description, and partly will be understood by those skilled in the art through the research and practice of the utility model.
附图说明Description of drawings
图1为汽车上的A柱的连续成形装置侧视图;Fig. 1 is the side view of the continuous forming device of the A-pillar on the automobile;
图2为汽车上的A柱的连续成形装置俯视图;Fig. 2 is the top view of the continuous forming device of the A-pillar on the automobile;
图3为连续梁截面示意图;Figure 3 is a schematic diagram of a continuous beam section;
图4为本实用新型的流程工艺示意图;Fig. 4 is the schematic flow chart of the utility model;
图5为焊接装置示意图;Fig. 5 is the schematic diagram of welding device;
图6为板状整形板示意图;Fig. 6 is a schematic diagram of a plate shaped plate;
图7为辊弯装置示意图;Fig. 7 is a schematic diagram of a roll bending device;
图8为辊弯后的梁柱示意图。Fig. 8 is a schematic diagram of the beam and column after roll bending.
附图标记包含:第一辊压段1、第一辊压段2、焊接装置3、水冷箱4、空冷箱5、切断装置6、辊弯装置7、连续梁8、成形辊轮组9、高频焊机10、焊机滑道11、推动辊轮12、定位辊轮13、整形辊轮组14、板状整形板15、整形轮16、三角形通孔17、喷水管41、冷流内腔42、排水管43、减速辊轮组44、风干机51、通风管52、激光切割机61、分段辊轮组62、动辊轮组71、定辊轮组72、转动支架73、连接板74、传送辊轮组75、第一伸缩电机76、第二伸缩电机77、传送辊轮组78、凸起部分81、水平段82、弧形连接段83、弧形段84、连杆122、伸缩气缸123、辊轮定位架13。Reference signs include: first rolling section 1, first rolling section 2, welding device 3, water cooling box 4, air cooling box 5, cutting device 6, roll bending device 7, continuous beam 8, forming roller group 9, High-frequency welding machine 10, welding machine slideway 11, pushing roller 12, positioning roller 13, shaping roller group 14, plate shaping plate 15, shaping wheel 16, triangular through hole 17, water spray pipe 41, cold flow Inner cavity 42, drainage pipe 43, deceleration roller group 44, air dryer 51, ventilation pipe 52, laser cutting machine 61, segmented roller group 62, moving roller group 71, fixed roller group 72, rotating bracket 73, Connecting plate 74, transmission roller group 75, first telescopic motor 76, second telescopic motor 77, transmission roller group 78, raised part 81, horizontal section 82, arc connecting section 83, arc section 84, connecting rod 122, telescopic cylinder 123, roller spacer 13.
具体实施方式Detailed ways
为了使本实用新型实现的技术手段、创作特征、达成目的与作用更加清楚及易于了解,下面结合附图和具体实施方式对本实用新型作进一步阐述:In order to make the technical means, creative features, purpose and effect of the utility model realized clearer and easier to understand, the utility model will be further elaborated below in conjunction with the accompanying drawings and specific implementation methods:
如图1-2所示,汽车上的A柱的连续成形装置,包括若干个成形辊轮组9,用于将金属板材两边缘以纵向地沿金属板材同一侧逐渐成形两条相对称的凸起部分81,如图3所示,连续梁8截面示意图,两凸起部分81的一端向同一侧弯曲形成弧形段84且两弧形段84端面接触,金属板材的中部形成水平段82,两凸起部分81在成形过程中由若干个成形辊轮组9将两凸起部分81与水平段82之间形成弧形连接段83以形成大体呈三角形的连续梁8;As shown in Figure 1-2, the continuous forming device of the A-pillar on the automobile includes several forming roller sets 9, which are used to gradually form two symmetrical protrusions along the same side of the metal plate longitudinally along the two edges of the metal plate. Protruding part 81, as shown in Figure 3, the cross-sectional schematic view of continuous beam 8, one end of two protruding parts 81 is bent to the same side to form arcuate section 84 and two arcuate sections 84 end faces contact, and the middle part of sheet metal forms horizontal section 82, During the forming process of the two convex parts 81, several forming roller sets 9 form an arc-shaped connecting section 83 between the two convex parts 81 and the horizontal section 82 to form a substantially triangular continuous beam 8;
焊接装置3,该焊接装置3安装在若干个成形辊轮组9的尾端,用于将两弧形段84相接触的端面焊接在一起;所述焊接装置3的焊接端与两弧形段84的端面或两弧形段84的端面的延长线相接;Welding device 3, this welding device 3 is installed on the tail end of several forming roller groups 9, is used for welding together the end faces that two arcuate sections 84 contact; The end face of 84 or the extension line of the end face of two arcuate sections 84 joins;
冷却装置,该冷却装置安装于焊接装置3之后,用于冷却经焊接后的连续梁8,以增加连续梁8的抗弯强度和抗剪切力;Cooling device, this cooling device is installed behind the welding device 3, for cooling the continuous beam 8 after welding, to increase the bending strength and shearing force of the continuous beam 8;
切断装置6,将冷却后的连续梁8以产品需求长度切断形成梁柱。The cutting device 6 cuts the cooled continuous beam 8 to the length required by the product to form a beam column.
辊弯装置7,用于将梁柱的中部进行辊弯。The roll bending device 7 is used for roll bending the middle part of the beam column.
所述成形辊轮组9包括第一辊轮段及第二辊轮段,第二辊轮段位于第一辊轮段的末端,其中第一辊轮段及第二辊轮段均由多个辊轮架组依次布置而成,第一辊压段21用于将金属板材的两边缘向金属板材同一侧逐渐辊压出弧形段84,第一辊压段21的末端辊轮将弧形段84成形为7.2mm的半径;第二辊压段的首端对弧形段84的进行整形,并保持弧形段84的半径R为9.45mm,第二辊压段的首端至尾端均用于对金属板材的板面成形,将金属板材的板面逐渐形成两条凸起段及一条水平段82,水平段82两侧分别与两条凸起段之间形成弧形连接段83,且两条凸起段分别与弧形段84连接,第二辊压段的尾端用于将两条凸起段、水平段82、弧形连接段83及弧形段84成型为三角形,且两边缘的弧形段84相对接触。Described forming roller group 9 comprises first roller section and second roller section, and second roller section is positioned at the end of first roller section, and wherein first roller section and second roller section are all made of a plurality of Roller frame groups are arranged in sequence. The first rolling section 21 is used to gradually roll out the arc section 84 from the two edges of the metal sheet to the same side of the metal sheet. The end rollers of the first rolling section 21 will bend the arc Section 84 is formed into a radius of 7.2mm; the head end of the second rolling section is shaped to the arc section 84, and the radius R of the arc section 84 is kept to be 9.45mm, and the first end of the second rolling section is to the tail end Both are used for forming the surface of the metal sheet, gradually forming two raised sections and a horizontal section 82 on the surface of the metal sheet, and forming arc-shaped connecting sections 83 between the two sides of the horizontal section 82 and the two raised sections respectively , and the two raised sections are respectively connected with the arc section 84, and the tail end of the second rolling section is used to shape the two raised sections, the horizontal section 82, the arc connecting section 83 and the arc section 84 into a triangle, And the arc segments 84 of the two edges are in relative contact.
在成形辊轮组9中,第一辊轮段及第二辊轮段中各辊轮架组均包括两个辊轮,两个辊轮分别安装在安装架上,其安装架固定在一基座上,安装架由两条竖直边和一条水平边构成,水平边固定在两条竖直边的上端,两条竖直边的下端与基座固定,形成倒U形的安装架,两个辊轮通过安装轴呈上下布置的方式安装在安装架的中部,其两个辊轮之间具有能使2cm的金属板材通过的间隙,在金属板材通过第一辊轮段及第二辊轮段时,由辊轮进行辊压成形,第一辊压段21中的各个辊轮具有可将金属板材的两边缘以图4中的S2-S12流程示意逐渐辊压出弧形段84的成形部位,第一辊轮段末端的辊轮的成形部位可将弧形段84成形为7.2mm的半径;In the forming roller group 9, each roller frame group in the first roller section and the second roller section includes two rollers, and the two rollers are installed on the mounting frame respectively, and the mounting frame is fixed on a base On the seat, the installation frame is composed of two vertical sides and a horizontal side. The two rollers are installed in the middle of the installation frame in a way that the installation shaft is arranged up and down. There is a gap between the two rollers that can allow the metal sheet of 2cm to pass through. When the metal sheet passes through the first roller segment and the second roller During the section, roll forming is carried out by the rollers, and each roller in the first rolling section 21 has the shape that the two edges of the metal sheet can be gradually rolled out of the arc section 84 according to the S2-S12 process in Fig. 4 . Position, the forming position of the roller at the end of the first roller segment can form the arc segment 84 into a radius of 7.2 mm;
其第二辊轮段首端的辊轮架组的辊轮具有的整形部和成形部,通过整形部可以将7.2mm半径的弧形段84整形为半径R为9.45mm,同时通过成形部将金属板材初步成形为两条凸起段及一条水平段82(参见图4中的S13),再由第二辊轮段首端至尾端的辊轮架组的辊轮成形部以图4中的S14-S23流程示意逐渐辊压两条凸起段及一条水平段82,并使两条凸起段上端的弧形段84对接以形成三角形的连续梁8,再由高频焊机10焊接弧形段84对接处,在焊接过程中,将会在焊接工序的前端或后端对三角形的连续梁8进行定位,使弧形段84对接处始终保持接触的状态,以便高频焊机10焊接。The rollers of the roller frame group at the head end of the second roller section have a shaping section and a forming section, through which the arc section 84 with a radius of 7.2mm can be shaped into a radius R of 9.45mm, and the metal is formed by the shaping section simultaneously. The plate is initially formed into two raised sections and a horizontal section 82 (see S13 in Figure 4), and then the roller forming part of the roller frame group from the head end to the tail end of the second roller section is followed by S14 in Figure 4 -S23 process indicates that two raised sections and one horizontal section 82 are gradually rolled, and the arc section 84 at the upper end of the two raised sections is butted to form a triangular continuous beam 8, and then the arc is welded by a high-frequency welding machine 10 At the butt joint of the section 84, during the welding process, the triangular continuous beam 8 will be positioned at the front end or the rear end of the welding process, so that the butt joint of the arc-shaped section 84 is always in a contact state, so that the high frequency welding machine 10 can weld.
所述第一辊轮段包括十二个辊轮架组,十二个辊轮架组依次安装在基座上,第一位辊轮与动力机连接,用于传送金属板材,前第二至第四位辊轮架组用于对金属板材边缘初成形,第五至第十二位辊轮均设置有对金属板材边缘逐渐成形为弧形段84的成形部,且第五和第九位辊轮连接有动力机。The first roller section includes twelve roller frame groups, and the twelve roller frame groups are installed on the base in turn, the first roller is connected with the power machine, and is used to convey the metal sheet, and the second to the first The four-position roller frame group is used for the preliminary forming of the edge of the metal sheet, the fifth to the twelfth rollers are all provided with a forming part that gradually forms the edge of the metal sheet into an arc segment 84, and the fifth and ninth rollers The wheel is connected with a power machine.
在每个辊轮架组的后端可连接用于整形的辊轮架组,以便提高成形质量,即第一辊轮段中的辊轮架组也可以大于十二个。通过第五和第九位辊轮连接动力机,为对应的辊轮提供输送动力,方便成形后连续梁8的输送。The rear end of each roller frame group can be connected with a roller frame group for shaping so as to improve the forming quality, that is, there can be more than twelve roller frame groups in the first roller segment. The fifth and ninth rollers are connected to the power machine to provide conveying power for the corresponding rollers, which facilitates the conveying of the continuous beam 8 after forming.
所述第二辊压段包括十个成形辊轮架组,其中,十个成形辊轮架组依次安装在基座上,第一位成形辊轮架组位于第一辊轮段的尾部,第二辊轮段与第一辊轮段呈“一”字形排列,第一位成形辊轮架组设置有对金属板材的板面成形为两条凸起段、一条水平段82及弧形连接段83的第二成形部,第二位成形辊轮架组至第十位成形辊轮架组均设置有将两条凸起段、一条水平段82、弧形连接段83及两边缘的弧形段84成形为三角形的第三成形部。The second rolling section includes ten forming roller frame groups, wherein the ten forming roller frame groups are installed on the base in sequence, the first forming roller frame group is located at the tail of the first roller segment, and the The second roller section and the first roller section are arranged in a "one" shape, and the first forming roller frame group is equipped with two convex sections, a horizontal section 82 and an arc-shaped connecting section for forming the surface of the metal sheet The second forming portion of 83, the second forming roller frame group to the tenth forming roller frame group are all provided with two raised sections, a horizontal section 82, an arc connecting section 83 and an arc of two edges. Section 84 is shaped as a triangular third shape.
第二辊压段的十个成形辊轮组9分别通过两个辊轮上下辊压,第一位成形辊轮架组上设置的第二成形部对具有弧形段84的金属板材中部上下辊压,逐渐形成两条凸起段、一条水平段82和弧形连接段83,第二位成形辊轮架组至第十位成形辊轮架组的第三成形部对弧形连接段83及凸起段逐步弯折,使其两凸起部分81向一侧靠近,且两端弧形段84接触,逐步成形为三角形,防止其弧形连接段83及凸起段过度弯折造成连续梁8撕裂。第三成形部对弧形连接段83辊压,第二辊压段的十个成形辊轮架组还可以设有第一辊压段21的成形部,用于保持对弧形段84的整形。The ten forming roller groups 9 of the second rolling section are respectively rolled up and down by two rollers, and the second forming part provided on the first forming roller frame group rolls up and down the middle part of the metal sheet with the arc section 84 Press, gradually form two raised sections, a horizontal section 82 and an arc-shaped connecting section 83, the third forming part of the second forming roller frame group to the tenth forming roller frame group is connected to the arc-shaped connecting section 83 and The protruding section is gradually bent so that the two protruding parts 81 are close to one side, and the arc sections 84 at both ends are in contact, and gradually formed into a triangle to prevent the arc-shaped connecting section 83 and the protruding section from being excessively bent to form a continuous beam. 8 torn. The third forming part rolls the arc connecting section 83, and the ten forming roll frame groups of the second rolling section can also be provided with the forming part of the first rolling section 21 for maintaining the shaping of the arc section 84 .
如图4所示,焊接装置3包括高频焊机10、焊机滑道11、夹持辊轮组;夹持辊轮组包含推动辊轮12和两个定位辊轮13;两个定位辊轮13用于支撑两凸起部分81;推动辊轮12用于将连续梁8沿两个定位辊轮13之间推动;所述焊机滑道11设置在推动辊轮12相对一侧;高频焊机10沿连续梁8延伸方向滑动设于焊机滑道11上,其焊枪正对两弧形段对接处。As shown in Figure 4, welding device 3 comprises high-frequency welder 10, welder slideway 11, clamping roller group; Clamping roller group comprises pushing roller 12 and two positioning rollers 13; Two positioning rollers Wheel 13 is used to support two raised parts 81; Push roller 12 is used to push continuous beam 8 along between two positioning rollers 13; Described welder slideway 11 is arranged on the opposite side of pushing roller 12; The frequency welding machine 10 slides along the extension direction of the continuous beam 8 and is arranged on the welding machine slideway 11, and its welding torch is directly facing the joint of the two arc sections.
通过夹持辊轮组对连续梁8定位后,高频焊机10沿连续梁8延伸方向滑动依次焊接两弧形段接触端面,防止两弧形段间距不稳定出现焊接不均的问题。After the continuous beam 8 is positioned by the clamping roller set, the high-frequency welding machine 10 slides along the extension direction of the continuous beam 8 to weld the contact end faces of the two arc segments in sequence, so as to prevent uneven welding due to unstable spacing between the two arc segments.
所述夹持辊轮组为两个;两个夹持辊轮组的同一侧定位辊轮13分别转动连接在同一辊轮定位架13上;两个推动辊轮12通过连杆122在伸缩气缸123的作用下沿焊枪方向移动并固定连续梁8。夹持辊轮组通过三个辊轮分别固定连续梁8两端,进一步加强连续梁8的稳定性,使两弧形段更稳定,从而使焊接强度提高。There are two clamping roller groups; the positioning rollers 13 on the same side of the two clamping roller groups are respectively rotatably connected to the same roller positioning frame 13; 123 moves along the welding torch direction and fixes the continuous beam 8 under the action of 123. The clamping roller group uses three rollers to respectively fix the two ends of the continuous beam 8, further strengthening the stability of the continuous beam 8, making the two arc sections more stable, thereby improving the welding strength.
在夹持辊轮组尾部设置有2-5组整形辊轮组14,每组整形辊轮组14包括板状整形板15及三个整形轮16,如图5所示,板状整形板15示意图,在板状整形板15的中部设置有三角形通孔17,三个整形轮16均安装在三角形通孔17入口处的板状整形板15上,三个整形轮16呈三角形横向布置,且三个整形轮16围成可使三角形的连续梁8通过的三角形空位。2-5 groups of shaping roller groups 14 are arranged at the end of the clamping roller group, and each group of shaping roller groups 14 includes a plate-shaped shaping plate 15 and three shaping wheels 16, as shown in Figure 5, the plate-shaped shaping plate 15 Schematic diagram, a triangular through-hole 17 is arranged in the middle of the plate-shaped shaping plate 15, and three shaping wheels 16 are installed on the plate-shaped shaping plate 15 at the entrance of the triangular through-hole 17, and the three shaping wheels 16 are arranged in a triangular transverse direction, and The three shaping wheels 16 enclose a triangular space through which the triangular continuous beam 8 can pass.
整形板上的三角形通孔17一周设有沿三角形通孔17三个侧边设置的槽,三个整形轮16的轮轴分别横向连接在整形板的槽内,三个整形轮16围绕成小于三角形通孔17的三角形空位,连续梁8经过焊接后进入三角形空位,多组整形辊轮组14的三个整形轮16上分别设有对应的成形部、第二成形部、第三成形部,用于辊压调整连续梁8外壁的两个凸起部、弧形段、弧形连接段83及水平段82,并且通过整形轮16的间距设置,对两个弧形段的焊接进一步加固。The triangular through hole 17 on the shaping plate is provided with grooves arranged along the three sides of the triangular through hole 17, and the axles of the three shaping wheels 16 are respectively transversely connected in the grooves of the shaping plate. The triangular vacancy of the through hole 17, the continuous beam 8 enters the triangular vacancy after being welded, and the three shaping wheels 16 of the multi-group shaping roller group 14 are respectively provided with a corresponding forming part, a second forming part, and a third forming part. Adjust the two protrusions, the arc section, the arc connection section 83 and the horizontal section 82 on the outer wall of the continuous beam 8 by rolling, and set the distance between the shaping wheels 16 to further strengthen the welding of the two arc sections.
冷却装置包括水冷箱4及位于水冷箱4出口的空冷箱5,水冷箱4位于焊接装置3之后,水冷箱4包含喷水管41、冷流内腔42及减速辊轮组44;所述减速辊轮组44用于连续梁8在冷流内腔42传送;喷水管41的喷枪指向减速辊轮组44上的连续梁8;所述冷流内腔42上设有低于连续梁8的排水管43;排水管43一端连接有排水或蓄水装置;空冷箱5包含送风机构和若干个通风管52;所述通风管52沿空冷箱5侧壁设置且设有与空冷箱5连通的若干出风孔,且通风管52另一端与送风机构连通。Cooling device comprises water-cooled box 4 and the air-cooled box 5 that is positioned at water-cooled box 4 outlets, and water-cooled box 4 is positioned after welding device 3, and water-cooled box 4 comprises water spray pipe 41, cold flow inner cavity 42 and deceleration roller group 44; The roller set 44 is used for the transmission of the continuous beam 8 in the cold flow inner cavity 42; the spray gun of the water spray pipe 41 points to the continuous beam 8 on the deceleration roller set 44; drainpipe 43; drainpipe 43 one end is connected with drainage or water storage device; air-cooled box 5 comprises air supply mechanism and several ventilation pipes 52; A number of air outlets communicated, and the other end of the ventilation pipe 52 is communicated with the air supply mechanism.
焊接后的连续梁8经整形轮16整形后冷却定型,防止高温焊接造成连续梁8弧度变形,减速辊轮组44将连续梁8缓慢传入冷流内腔42,喷水管41对焊接处和整体连续梁8进行多次喷水降温,排水管43将加温后的水排出,针对连续梁8冷水迅速降温后,将连续梁8送入空冷箱5低温环境下,同时风干机51对连续梁8表面进行干燥处理,提高连续梁8整体性能,防止在剪切和辊弯时发生严重变形。The welded continuous beam 8 is cooled and shaped by the shaping wheel 16 to prevent the arc deformation of the continuous beam 8 caused by high temperature welding. Carry out multiple water spray cooling with the integral continuous beam 8, drain pipe 43 discharges the water after heating, after cooling the cold water for the continuous beam 8 rapidly, send the continuous beam 8 to the low temperature environment of the air cooling box 5, and at the same time, 51 pairs of air dryers The surface of the continuous beam 8 is dried to improve the overall performance of the continuous beam 8 and prevent severe deformation during shearing and roll bending.
通风管52为多个且分别设置在空冷箱5顶部内壁和底部内壁,送风机构为两个分别与空冷箱5顶部和底部的通风管52连通的风干机51。优选的,空冷箱5上层/下层的通风管52互相平行且互为连通,空冷箱5上层和下层的通风管52组合成网格状。通风管52上下分布利于对空冷箱5内部环境降温,并且形成隔离防止外界气温干扰,达到更好的降温干燥效果。There are a plurality of ventilation pipes 52 and they are respectively arranged on the top inner wall and the bottom inner wall of the air cooling box 5 , and the air supply mechanism is two air dryers 51 communicating with the ventilation pipes 52 on the top and bottom of the air cooling box 5 respectively. Preferably, the ventilation pipes 52 on the upper/lower floors of the air-cooled box 5 are parallel to each other and communicate with each other, and the ventilation pipes 52 on the upper and lower floors of the air-cooled box 5 are combined into a grid. The upper and lower distribution of the ventilation pipe 52 is conducive to cooling the internal environment of the air-cooled box 5, and forms an isolation to prevent the interference of the external air temperature, so as to achieve a better cooling and drying effect.
切断装置6包含激光切割机61和分段辊轮组62;所述分段辊轮组62连接有PLC控制器,用于控制连续梁8的分段输送;激光切割机61的切割枪指向分段辊轮组62上的连续梁8,且沿连续梁8弧形段84一侧向下切割;所述激光切割机61的控制端与PLC控制器连接。The cutting device 6 comprises a laser cutter 61 and a segmented roller group 62; the segmented roller group 62 is connected with a PLC controller for controlling the segmental delivery of the continuous beam 8; the cutting torch of the laser cutter 61 points to the segmented The continuous beam 8 on the section roller group 62 is cut downward along one side of the arc section 84 of the continuous beam 8; the control end of the laser cutting machine 61 is connected with the PLC controller.
PLC控制器通过输入编程代码,执行逻辑运算,顺序控制,定时,计数与算术操作等面向用户的指令,并通过数字或模拟式输入/输出控制各种类型的机械或生产过程。分段辊轮组62连接有动力机,其动力机通过PLC控制器控制分段辊轮组62在一定时间内停止运动,此时连续梁8在指定位置停下,接着激光切割机61沿弧形段84一端向下切割,使凸起部两侧切割均匀,切割后动力机启动,分段辊轮组62将切割加工成的梁柱运送到下一辊弯装置7。PLC控制器通过判断激光切割机61的工作信号,发出分段辊轮组62的驱动信号,以控制分段辊轮组62连续梁8切断后自动执行下一传输切断动作,The PLC controller executes logic operations, sequential control, timing, counting and arithmetic operations and other user-oriented instructions by inputting programming codes, and controls various types of machinery or production processes through digital or analog input/output. The segmented roller group 62 is connected with a power machine, and its power machine controls the segmented roller group 62 to stop moving within a certain period of time through the PLC controller. 84 cuts downwards at one end, so that both sides of the raised portion are cut evenly. After cutting, the power machine starts, and the segmented roller group 62 transports the beam column that is cut and processed to the next roll bending device 7 . The PLC controller judges the working signal of the laser cutting machine 61 and sends out the driving signal of the segmented roller group 62 to control the segmented roller group 62 to automatically execute the next transmission and cutting action after the continuous beam 8 is cut.
如图6所示,辊弯装置7包含沿辊弯装置7出口依次设置的动辊轮组71、定辊轮组72和传送辊轮组7875,以及第一转动结构、第二转动结构;定辊轮组72用于对连续梁8定位;所述动辊轮组71设于辊弯装置7出口与定辊轮组72相对;传送辊轮组7875用于传送梁柱;且动辊轮组71分别通过第一转动结构和第二转动结构实现上下及左右摆动,以实现梁柱的辊弯。As shown in Figure 6, the roll bending device 7 includes a moving roller group 71, a fixed roller group 72 and a transmission roller group 7875 arranged in sequence along the exit of the roll bending device 7, as well as a first rotating structure and a second rotating structure; The roller group 72 is used for positioning the continuous beam 8; the moving roller group 71 is arranged at the exit of the roll bending device 7 and is opposite to the fixed roller group 72; the transmission roller group 7875 is used to transmit the beam; and the moving roller group 71 realizes swinging up and down and left and right through the first rotating structure and the second rotating structure respectively, so as to realize the roll bending of beams and columns.
定辊轮组72和传送辊轮组7875分别通过辊轮架与动辊轮组71安装在同一水平线上,使梁柱随着传送辊轮组7875在动力机的带动下往定辊轮组72方向传送,动辊轮组71连接在第一转动结构上,第一转动结构左右两侧转动连接在第二转动结构上,第二转动结构上/下端与辊弯装置7出口转动连接,当第一转动结构相对辊弯装置7转动时,且第二转动结构保持不变,则梁柱一端由定辊轮组72固定,另一端随动辊轮组71上下摆动,并且随传送辊轮组7875沿传动方向依次向摆动一方辊弯;当第二转动结构转动时,且第一转动结构保持不变,则梁柱随动辊轮组71同时左、右摆动,并依次向摆动一侧呈一定弧度辊弯后伸出辊弯装置7出口;当第一转动结构和第二转动结构同时转动时,可以实现梁柱朝向左上方、左下方、右上方、右下方的辊弯,并且在第一转动结构和/或第二转动结构摆动至一定角度固定时,梁柱随着传送方向能够垂直折弯或形成指定半径的圆弧曲形。The fixed roller set 72 and the transmission roller set 7875 are respectively installed on the same horizontal line through the roller frame and the movable roller set 71, so that the beam column is transmitted to the direction of the fixed roller set 72 along with the transmission roller set 7875 driven by the power machine. The moving roller set 71 is connected to the first rotating structure, and the left and right sides of the first rotating structure are rotationally connected to the second rotating structure, and the upper/lower ends of the second rotating structure are rotationally connected to the exit of the roll bending device 7. When the first rotating structure When the relative roll bending device 7 rotates, and the second rotation structure remains unchanged, one end of the beam column is fixed by the fixed roller set 72, and the other end swings up and down with the moving roller set 71, and moves along the transmission direction with the transmission roller set 7875. Bending to one swinging side in sequence; when the second rotating structure rotates, and the first rotating structure remains unchanged, the beam column follower roller set 71 swings left and right at the same time, and rolls and stretches to the swinging side in a certain arc in turn. Out of the roll bending device 7 exit; when the first rotating structure and the second rotating structure rotate simultaneously, the roll bending of the beam column towards the upper left, lower left, upper right, and lower right can be realized, and in the first rotating structure and/or When the second rotating structure swings to a certain angle and is fixed, the beam column can be bent vertically or form an arc shape with a specified radius along with the conveying direction.
第一转动结构为沿梁柱三角形环向转动连接在辊弯装置7出口一侧的转动支架73,且连接有控制其转动的驱动装置;第二转动结构为沿梁柱纵向转动连接在转动支架73的连接板74,由驱动装置控制其转动;动辊轮组71连接在连接板74中设有的安装通孔内;梁柱通过安装通孔在动辊轮组71、定辊轮组72和传送辊轮组7875之间传送。转动支架73的摆动通过连接在其侧边的伸缩电机完成,转动支架73自由端随着第一伸缩电机76上下带动而摆动。连接板74转动通过连接在连接板74控制端的第二伸缩电机77作用实现。The first rotation structure is a rotation bracket 73 connected to the outlet side of the roll bending device 7 along the beam-column triangular ring direction, and is connected with a driving device to control its rotation; the second rotation structure is connected to the rotation bracket along the longitudinal rotation of the beam column. The connecting plate 74 of 73 is controlled by the driving device to rotate; the moving roller group 71 is connected in the installation through hole provided in the connecting plate 74; And transfer between the transfer roller set 7875. The swing of the rotating bracket 73 is completed by the telescopic motor connected to its side, and the free end of the rotating bracket 73 swings as the first telescopic motor 76 drives up and down. The rotation of the connecting plate 74 is realized by the action of the second telescopic motor 77 connected to the control end of the connecting plate 74 .
转动支架73的自由端转动一侧连接一由第一伸缩电机76带动的连杆122,转动支架73随着连杆122上下移动高度而摆动不同角度,连接板74转动一侧随着第二伸缩电机77控制不同转动角度,以实现不同辊弯参数的变化。The free end of the rotating bracket 73 rotates one side and connects a connecting rod 122 driven by the first telescopic motor 76. The rotating bracket 73 swings at different angles as the connecting rod 122 moves up and down. The motor 77 controls different rotation angles to realize the variation of different roll bending parameters.
所述动辊轮组71包含三个夹紧辊轮;所述三个夹紧辊轮分别呈三角形布置,横向围成可使梁柱通过的三角形空位,夹紧辊轮两端通过轮轴连接在安装通孔内。The moving roller set 71 includes three clamping rollers; the three clamping rollers are respectively arranged in a triangle, laterally enclosing a triangular space through which beams and columns can pass, and the two ends of the clamping rollers are connected to each other by axles. installed through-hole.
动辊轮组71的三个夹紧辊轮横向一面分别与梁柱的三个侧边对应夹持,防止在辊弯过程中由于压力改变弧形段及弧形连接段83的弯曲参数,并且通过定辊轮的弧面对梁柱定位,减少对梁柱辊弯的物理伤害。The lateral sides of the three clamping rollers of the moving roller set 71 are respectively clamped correspondingly to the three sides of the beam column, so as to prevent the bending parameters of the arc section and the arc connecting section 83 from being changed due to pressure during the roll bending process, and The beam and column are positioned by the arc surface of the fixed roller to reduce the physical damage to the roll bending of the beam and column.
还包括开卷机及位于开卷机出料端的整平机,整平机的进料端设置有入料滚筒,整平机的出料端设置有出料滚筒,整平机出料端与成形辊轮组9的入料端之间设置有传输滚筒。通过对金属板材开卷和平整处理,使成形后的质量进一步一致。It also includes an uncoiler and a leveler located at the discharge end of the uncoiler. The feed end of the leveler is provided with a feed roller, and the discharge end of the leveler is provided with a discharge roller. The discharge end of the leveler is connected to the forming roller. A transfer roller is arranged between the feeding ends of the wheel set 9 . By decoiling and smoothing the sheet metal, the quality after forming is further consistent.
本装置使用时,将待加工的金属板材放入成形辊轮组9一端,经过第一辊压段21进行粗加工,使得金属板材两侧沿金属板材同一侧向内弯曲,形成弧形段84。然后进入第二辊压段细加工,两弧形段84端面保持圆弧形态并逐渐靠近,形成对称的两凸起部分81和两凸起部分81之间的水平段82,两弧形段84一端接触,两凸起部分81与水平段82之间均辊压成形有弧形连接段83,形成三角形的连续梁8。成形后的连续梁8进入焊接装置3后,推动辊轮12向两定位辊轮13之间伸入,将成形后的连续梁8固定在两个定位辊轮13和推动辊轮12之间,此时,高频焊机10沿连续梁8的两个弧形段84的接触端面依次焊接。焊接后的连续梁8已具连接柱的雏形,经水冷箱4和空冷箱5迅速冷却风干,增强了连续梁8的抗弯强度和抗剪切力,防止切断和辊弯造成焊缝裂开或强度降低的问题,提高了成品的质量。冷却后的连续梁8经推动辊轮12传送至特定位置后,激光切割机61沿两弧形段84一侧直切,切割面从小至大,防止两凸起部切割不均,产生毛刺。梁柱由传送辊轮组7875经过动辊轮组71后,通过动辊轮组71在垂直和水平方向上相对定辊轮组72移动,如图8所示,梁柱沿着其延伸方向伸出辊弯装置7出口形成不同辊弯弧度。When the device is in use, the metal sheet to be processed is put into one end of the forming roller group 9, and is roughly machined through the first rolling section 21, so that both sides of the metal sheet are bent inward along the same side of the metal sheet to form an arc section 84 . Then enter the second rolling section for fine processing, the end faces of the two arc sections 84 keep the arc shape and gradually approach to form two symmetrical raised parts 81 and the horizontal section 82 between the two raised parts 81, and the two arc sections 84 One end is in contact, and an arc-shaped connecting section 83 is rolled between the two convex parts 81 and the horizontal section 82 to form a triangular continuous beam 8 . After the formed continuous beam 8 enters the welding device 3, the push roller 12 is stretched between the two positioning rollers 13, and the formed continuous beam 8 is fixed between the two positioning rollers 13 and the pushing roller 12, At this time, the high-frequency welding machine 10 welds sequentially along the contact end faces of the two arc-shaped segments 84 of the continuous beam 8 . The welded continuous beam 8 has the prototype of the connecting column, and is rapidly cooled and air-dried by the water-cooled box 4 and the air-cooled box 5, which enhances the bending strength and shear resistance of the continuous beam 8, and prevents the welding seam from cracking caused by cutting and rolling Or the problem of reduced strength improves the quality of the finished product. After the cooled continuous beam 8 is transported to a specific position by the push roller 12, the laser cutting machine 61 cuts straight along the sides of the two arc sections 84, and the cutting surface is small to large to prevent uneven cutting of the two protrusions and burrs. After the beam and column pass through the moving roller set 71 by the conveying roller set 7875, the moving roller set 71 moves relative to the fixed roller set 72 in the vertical and horizontal directions. As shown in Figure 8, the beam extends out of the roller along its extension direction The outlet of bending device 7 forms different roll bending radians.
最后说明的是,以上实施例仅用以说明本实用新型的技术方案而非限制,可以对本实用新型的技术方案进行修改或者等同替换,而不脱离本实用新型技术方案的宗旨和范围,其均应涵盖在本实用新型的权利要求范围当中。Finally, it is noted that the above embodiments are only used to illustrate the technical solution of the utility model without limitation, and the technical solution of the utility model can be modified or equivalently replaced without departing from the purpose and scope of the technical solution of the utility model. It should be included in the scope of the claims of the present utility model.
Claims (15)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822115934.6U CN209565776U (en) | 2018-12-17 | 2018-12-17 | Continuous forming device for A-pillar on automobile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822115934.6U CN209565776U (en) | 2018-12-17 | 2018-12-17 | Continuous forming device for A-pillar on automobile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209565776U true CN209565776U (en) | 2019-11-01 |
Family
ID=68329979
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822115934.6U Expired - Fee Related CN209565776U (en) | 2018-12-17 | 2018-12-17 | Continuous forming device for A-pillar on automobile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209565776U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109500615A (en) * | 2018-12-17 | 2019-03-22 | 凌云西南工业有限公司 | A kind of progressive forming device for the connecting column being used to form on automobile |
CN114733944A (en) * | 2022-03-29 | 2022-07-12 | 绍兴建勇科技有限公司 | Preparation device for metal plate forming type goods shelf partition plate |
CN119426936A (en) * | 2025-01-10 | 2025-02-14 | 合肥工业大学 | Short-process manufacturing process and device for space roll bending of automobile A column |
-
2018
- 2018-12-17 CN CN201822115934.6U patent/CN209565776U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109500615A (en) * | 2018-12-17 | 2019-03-22 | 凌云西南工业有限公司 | A kind of progressive forming device for the connecting column being used to form on automobile |
CN109500615B (en) * | 2018-12-17 | 2024-02-06 | 凌云西南工业有限公司 | Continuous forming device for forming connecting column on automobile |
CN114733944A (en) * | 2022-03-29 | 2022-07-12 | 绍兴建勇科技有限公司 | Preparation device for metal plate forming type goods shelf partition plate |
CN114733944B (en) * | 2022-03-29 | 2024-04-02 | 绍兴建勇科技有限公司 | Preparation facilities of panel beating shaping formula goods shelves baffle |
CN119426936A (en) * | 2025-01-10 | 2025-02-14 | 合肥工业大学 | Short-process manufacturing process and device for space roll bending of automobile A column |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209565776U (en) | Continuous forming device for A-pillar on automobile | |
CN103101576B (en) | Front side member | |
CN102729048B (en) | Aluminium alloy bumper bar section bar bending forming method and device for automobile | |
CN109500615B (en) | Continuous forming device for forming connecting column on automobile | |
CN109676053B (en) | Method for forming a triangular continuous beam from sheet metal | |
CN205732691U (en) | A kind of straight curved flexible adjustable heat pressing forming device of Automotive Stabilizer Bar | |
CN104512470A (en) | Outer panel for pillar of vehicle, and method and rolling apparatus for manufacturing the same | |
CN211162541U (en) | Welding equipment after plate edge rolling | |
CN101637796B (en) | Method for processing hob blade of mower and device for molding helical curved surface of hob blade | |
CN103817422B (en) | Steel billet automatic flash butt welding machine | |
CN103537880A (en) | Method for welding high-strength steel through laser welding machine | |
CN107234443A (en) | The three-dimensional online pane bending apparatus of variable curvature section bar that robot is actively drawn | |
CN111168406B (en) | Embedded channel welding production line, riveting production line and production system | |
CN100415416C (en) | An online mold repairing device and repairing method for a roll type cross wedge rolling mill | |
CN115255640B (en) | High-strength steel laser welded pipe production line | |
CN108889870A (en) | Multi-functional full-automatic stirrup bender | |
CN114932672B (en) | Hat brim core forming and cutting production line | |
CN109482643A (en) | The milling method of 11 sections of Varying-thickness automobile rear floor front beam | |
CN203751508U (en) | Automatic flash butt welder for steel billet | |
CN105081192B (en) | The method that integral automobile steering section rough forging realizes hot extrusion forging | |
CN104249089B (en) | Method for manufacturing rectangular laser welded pipe | |
CN117681631A (en) | Volute section bar, volute car door anti-collision rod and machining method of volute car door anti-collision rod | |
CN201231270Y (en) | Arc bending device of hob blade of grass cutter | |
CN103386451B (en) | Forming process of large-diameter piston plug, step shaft or oil cylinder and processing equipment thereof | |
CN210754353U (en) | A hot-rolled strip steel endless rolling intermediate billet connecting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191101 |
|
CF01 | Termination of patent right due to non-payment of annual fee |