CN209482246U - An unloading sheet pile seawall structure - Google Patents
An unloading sheet pile seawall structure Download PDFInfo
- Publication number
- CN209482246U CN209482246U CN201822105202.9U CN201822105202U CN209482246U CN 209482246 U CN209482246 U CN 209482246U CN 201822105202 U CN201822105202 U CN 201822105202U CN 209482246 U CN209482246 U CN 209482246U
- Authority
- CN
- China
- Prior art keywords
- sheet pile
- pile
- foundation
- wall
- seawall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 claims abstract description 26
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 26
- 239000002689 soil Substances 0.000 claims abstract description 6
- 239000004575 stone Substances 0.000 claims description 21
- 239000004567 concrete Substances 0.000 claims description 17
- 239000004568 cement Substances 0.000 claims description 8
- 239000002131 composite material Substances 0.000 claims description 6
- 239000004576 sand Substances 0.000 claims description 6
- 244000025254 Cannabis sativa Species 0.000 claims description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 8
- 229910000831 Steel Inorganic materials 0.000 abstract description 5
- 238000006073 displacement reaction Methods 0.000 abstract description 5
- 239000010959 steel Substances 0.000 abstract description 5
- 238000007569 slipcasting Methods 0.000 abstract 2
- 238000007599 discharging Methods 0.000 abstract 1
- 238000011065 in-situ storage Methods 0.000 abstract 1
- 239000011435 rock Substances 0.000 description 5
- 238000005260 corrosion Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 239000011513 prestressed concrete Substances 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000010438 granite Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000006115 industrial coating Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 229920000728 polyester Polymers 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000001568 sexual effect Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/11—Hard structures, e.g. dams, dykes or breakwaters
Landscapes
- Revetment (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及港口工程中复杂环境下的卸荷式板桩海堤结构,特别是一种带宽承台卸荷式板桩海堤结构,属于卸荷式板桩海堤结构的创新技术。The utility model relates to an unloading type sheet pile seawall structure in a complex environment in port engineering, in particular to an unloading type sheet pile seawall structure with a wide-band bearing platform, which belongs to the innovative technology of the unloading type sheet pile seawall structure.
背景技术Background technique
海堤是为防御风暴潮水和波浪对防护区的危害而修筑的堤防工程,同时也是围海工程的重要水工建筑物。海堤按结构型式在规范上分为斜坡式、陡墙式及混合式三种,均为传统的土石结构海堤。长期以来,海堤建设基本都沿用了传统土石结构,但随着沿海经济社会的发展、人们对生态环境的要求又或特殊的环境情况下,传统土石结构海提在建设和运行中也暴露出越来越多的弊端,主要体现在以下几大方面:(1)土石料用量巨大。(2)施工机械化程度低,建设工期长。(3)对沿海生态环境影响大。(4)工后沉降大,影响海堤正常使用功能的发挥。(5)土石料方量大,挤动地基土,对周边建筑位移影响大。本实用新型正是能解决传统海堤的各种缺点,为新型海堤结构提供了新的方向。The seawall is an embankment project built to defend against the hazards of storm tides and waves to the protected area, and it is also an important hydraulic structure for sea reclamation projects. According to the structural type, seawalls are divided into three types: slope type, steep wall type and mixed type, all of which are traditional earth-stone structure seawalls. For a long time, the traditional earth-rock structure has been basically used in seawall construction. However, with the development of coastal economy and society, people's requirements for the ecological environment, or special environmental conditions, the traditional earth-rock structure has also been exposed during construction and operation. More and more disadvantages are mainly reflected in the following aspects: (1) The amount of soil and stone is huge. (2) The degree of construction mechanization is low and the construction period is long. (3) Great impact on coastal ecological environment. (4) The settlement after construction is large, which affects the normal function of the seawall. (5) The volume of earth and stone is large, and the foundation soil is squeezed, which has a great impact on the displacement of surrounding buildings. The utility model can solve various shortcomings of the traditional seawall, and provides a new direction for the new seawall structure.
本实用新型是一种多排桩的宽承台卸荷式板桩海堤,也是一种新型无锚板桩海堤,该结构桩基采用预应力混凝土板桩和PHC桩,上部采用高强度混凝土宽承台(相当于重力式结构的卸荷板),能有效改善结构所受的主动土压力。The utility model is a wide bearing platform unloading sheet pile seawall with multiple rows of piles, and it is also a new anchorless sheet pile seawall. The pile foundation of this structure adopts prestressed concrete sheet piles and PHC piles, and the upper part adopts high-strength piles. The concrete wide cap (equivalent to the unloading plate of the gravity structure) can effectively improve the active earth pressure on the structure.
发明内容Contents of the invention
本实用新型的目的在于提供一种的卸荷式板桩海堤结构。本实用新型特别适用于打桩设备小、施工作业面狭窄、对邻近工程影响要求极小、地质条件差且不能换填、地面荷载大及防腐要求高等不利条件。本实用新型能满足经济合理、安全可靠等要求,值得在港工行业进行推广。The purpose of the utility model is to provide an unloading type sheet pile seawall structure. The utility model is especially suitable for unfavorable conditions such as small piling equipment, narrow construction work surface, minimal impact on adjacent projects, poor geological conditions and incapable of replacement, large ground load and high anti-corrosion requirements. The utility model can meet the requirements of reasonable economy, safety and reliability, and is worth popularizing in the port industry.
本实用新型的技术方案如下: 本实用新型的卸荷式板桩海堤结构,包括地基、桩基、板桩墙、注浆、海堤平台、钢筋混凝土承台,其中桩基固定在地基上,板桩墙也固定在地基上,在板桩墙与地基之间填充注浆;在桩基及板桩墙的顶部现浇钢筋混凝土承台,将桩基与板桩墙连为一体,海堤平台设在板桩墙的陆上一侧作为陆上施工平台。The technical scheme of the utility model is as follows: The unloading type sheet pile seawall structure of the utility model includes foundation, pile foundation, sheet pile wall, grouting, seawall platform, reinforced concrete cap, wherein the pile foundation is fixed on the foundation , the sheet pile wall is also fixed on the foundation, and the grouting is filled between the sheet pile wall and the foundation; the reinforced concrete cap is cast on the top of the pile foundation and the sheet pile wall, and the pile foundation and the sheet pile wall are connected as a whole. The embankment platform is set on the land side of the sheet pile wall as the land construction platform.
本实用新型为桩基直立式结构,且采用水泥搅拌桩对地基软土层进行加固处理,能最大限度减少对邻近工程产生的安全影响。所有桩型均可采用小型打桩船施工,满足通航孔的限制要求。挡土部位采用预应力U型砼板桩,比常规钢板桩耐腐蚀,能满足设计年限较长的工程要求。半叉桩PHC桩、板桩和第一阶段承台施工完毕形成三桩挡土承台结构,再在板桩陆侧回填中粗砂平台,为剩余的PHC桩和第二阶段承台提供陆上施工作业面,减少水上施工作业量,提高施工效率。板桩位于承台中部,前方有斜桩可分担水平力,承台很宽且底高程较低,起到了卸荷土压力作用。多排桩设计可提高结构整体稳定性,减少水平位移。The utility model is a pile foundation vertical structure, and cement mixing piles are used to reinforce the soft soil layer of the foundation, which can minimize the safety impact on adjacent projects. All types of piles can be constructed by small piling barges to meet the restriction requirements of navigable holes. Prestressed U-shaped concrete sheet piles are used for the retaining part, which is more corrosion-resistant than conventional steel sheet piles, and can meet the engineering requirements with a longer design period. After the half-pile PHC piles, sheet piles and caps of the first stage are constructed, a three-pile retaining cap structure is formed, and then the medium-coarse sand platform is backfilled on the land side of the sheet piles to provide land for the remaining PHC piles and the caps of the second stage. The upper construction work surface reduces the workload of water construction and improves construction efficiency. The sheet pile is located in the middle of the cap, and there is an inclined pile in front to share the horizontal force. The cap is very wide and the bottom elevation is low, which plays a role in unloading the earth pressure. The multi-row pile design can improve the overall stability of the structure and reduce horizontal displacement.
附图说明Description of drawings
图1为本实用新型的带宽承台卸荷式板桩的海堤结构的断面示意图。Fig. 1 is a schematic cross-sectional view of a seawall structure of a wide-band cap unloading type sheet pile of the present invention.
图2为本实用新型的带宽承台卸荷式板桩的海堤结构的桩位布置示意图。Fig. 2 is a schematic diagram of the pile position layout of the seawall structure of the unloading type sheet pile with wide band cap of the present invention.
图3为本实用新型的带宽承台卸荷式板桩的海堤结构的先张法预应力U型混凝土板桩大样图。Fig. 3 is a large sample diagram of the pretensioned prestressed U-shaped concrete sheet pile of the seawall structure of the unloading type sheet pile with wide cap of the utility model.
具体实施方式Detailed ways
下面将结合实施例和附图对本实用新型作进一步的详细描述:The utility model will be described in further detail below in conjunction with embodiment and accompanying drawing:
图1为本实用新型的卸荷式板桩海堤结构的断面示意图,包括地基1、桩基2、板桩墙3、注浆4、海堤平台5、钢筋混凝土承台6,其中桩基2固定在地基1上,板桩墙3也固定在地基1上,在板桩墙3与地基1之间填充注浆4;在桩基2及板桩墙3的顶部现浇钢筋混凝土承台6,将桩基2与板桩墙3连为一体,海堤平台5设在板桩墙3的陆上一侧作为陆上施工平台。Fig. 1 is a cross-sectional schematic view of the unloading type sheet pile seawall structure of the present invention, including foundation 1, pile foundation 2, sheet pile wall 3, grouting 4, seawall platform 5, reinforced concrete cap 6, wherein the pile foundation 2 is fixed on the foundation 1, and the sheet pile wall 3 is also fixed on the foundation 1, and the grouting 4 is filled between the sheet pile wall 3 and the foundation 1; the reinforced concrete cap is cast in place on the top of the pile foundation 2 and the sheet pile wall 3 6. The pile foundation 2 and the sheet pile wall 3 are integrated, and the seawall platform 5 is set on the land side of the sheet pile wall 3 as an onshore construction platform.
本实施例中,上述板桩墙3的海上一侧泥面设有护底结构,护底结构是在泥面先铺设复合土工垫11,在复合土工垫11上抛填二片石垫层12,在二片石垫层12上抛镇块石护底13。In the present embodiment, the mud surface on the sea side of the above-mentioned sheet pile wall 3 is provided with a bottom protection structure, and the bottom protection structure is to lay a composite geotechnical mat 11 on the mud surface, and fill two stone cushions 12 on the composite geotechnical mat 11. Throw the block stone bottom protection 13 on two stone pads 12 .
本实施例中,上述现浇钢筋混凝土承台6上回填块石基础7,在现浇钢筋混凝土承台6与块石基础7接缝的一侧回填混合碎石倒滤层8,在块石基础7顶部现浇混凝土路面9,在块石基础7上、与混合碎石倒滤层8同一侧种植草坡面10。本实施例中,是在现浇钢筋混凝土承台6与块石基础7接缝的陆上一侧回填混合碎石倒滤层8。本实施例中,上述块石基础7在承台上部回填1~100kg块石至混凝土路面9的底部;上述混合碎石倒滤层8的厚度不小于600mm。In this embodiment, the block stone foundation 7 is backfilled on the above-mentioned cast-in-place reinforced concrete cap 6, and the mixed crushed stone filter layer 8 is backfilled on the side of the joint between the cast-in-place reinforced concrete cap 6 and the block stone foundation 7, The top of the base 7 is a cast-in-place concrete pavement 9, and a grass slope 10 is planted on the block stone base 7 on the same side as the mixed crushed stone filter layer 8. In this embodiment, the mixed crushed stone filter layer 8 is backfilled on the land side of the joint between the cast-in-place reinforced concrete cap 6 and the block stone foundation 7 . In this embodiment, the rock foundation 7 is backfilled with 1 to 100 kg of rock on the upper part of the cap to the bottom of the concrete pavement 9; the thickness of the mixed gravel filter layer 8 is not less than 600 mm.
本实施例中,上述地基1采用水泥搅拌桩进行复合地基加固软土层,水泥搅拌桩为格栅状布置,为多排桩设计,采用搅拌船水上施工,多排桩设计可提高结构整体稳定性,减少水平位移。In this embodiment, the above-mentioned foundation 1 uses cement mixing piles to strengthen the soft soil layer. The cement mixing piles are arranged in a grid pattern and are designed with multiple rows of piles. The construction of the mixing boat is used on the water. The design of multiple rows of piles can improve the overall stability of the structure. resistance, reducing horizontal displacement.
本实施例中,上述海堤平台5是在板桩墙3的陆上一侧抛填砂形成施工平台,抛填的砂采用中粗砂,即细度模数为2.3~3.7,平均粒径为0.35mm以上。In this embodiment, the above-mentioned seawall platform 5 is formed by throwing and filling sand on the land side of the sheet pile wall 3 to form a construction platform. 0.35mm or more.
本实施例中,上述钢筋混凝土承台6是钢筋混凝土宽承台。一般港工行业的钢筋混凝土承台宽度在10米内,本钢筋混凝土承台6的宽度达17.5m,是一种宽承台。钢筋混凝土承台6分二阶段浇筑。承台很宽且底高程较低,起到了卸荷土压力作用。In this embodiment, the above-mentioned reinforced concrete platform 6 is a wide reinforced concrete platform. The reinforced concrete cap width of general harbor industry industry is within 10 meters, and the width of this reinforced concrete cap 6 reaches 17.5m, is a kind of wide cap. The reinforced concrete cap 6 is poured in two stages. The cap is very wide and the bottom elevation is low, which plays the role of unloading earth pressure.
本实施例中,上述桩基2采用PHC桩。上述板桩墙3的海上一侧设置1根PHC斜桩(4:1)和1根PHC直桩。斜桩可分担水平力。In this embodiment, the above-mentioned pile foundation 2 adopts PHC piles. One PHC inclined pile (4:1) and one PHC straight pile are arranged on the offshore side of the above-mentioned sheet pile wall 3 . The inclined pile can share the horizontal force.
本实施例中,板桩墙3的陆上一侧设置4根PHC直桩。板桩墙3采用先张法预应力U型混凝土板桩,板桩墙3布置在承台中间位置;在桩基2及板桩墙3的顶部现浇L型C40钢筋混凝土承台6,将桩基2与板桩墙3连为一体,承台分二阶段浇筑。上述板桩墙3采用先张法预应力U型混凝土板桩,比常规钢板桩耐腐蚀,板桩布置在承台中部,为进一步减少结构位移,在沉U型混凝土板桩后,在板桩墙3与水泥搅拌桩之间补钻旋喷桩达到填充注浆4的效果。In this embodiment, four PHC straight piles are arranged on the land side of the sheet pile wall 3 . The sheet pile wall 3 adopts the pre-tensioned prestressed U-shaped concrete sheet pile, and the sheet pile wall 3 is arranged in the middle of the cap; the L-shaped C40 reinforced concrete cap 6 is cast in place on the top of the pile foundation 2 and the sheet pile wall 3, and the The pile foundation 2 is integrated with the sheet pile wall 3, and the cap is poured in two stages. The above-mentioned sheet pile wall 3 adopts pre-tensioned prestressed U-shaped concrete sheet piles, which are more corrosion-resistant than conventional steel sheet piles. The sheet piles are arranged in the middle of the cap. Between the wall 3 and the cement mixing pile, the rotary grouting pile is re-drilled to achieve the effect of filling the grouting 4.
上述钢筋混凝土承台6将桩基2连为一体,承台分二阶段浇筑。板桩墙3海上一侧的PHC桩、板桩墙3及第一阶段的钢筋混凝土承台6水上施工后,形成三桩承台,在板桩后方回填中粗砂至水面以上形成海堤平台5,再进行剩余PHC桩及第二阶段钢筋混凝土承台6的陆上施工。The above-mentioned reinforced concrete cap 6 connects the pile foundation 2 as a whole, and the cap is poured in two stages. After the PHC piles on the sea side of sheet pile wall 3, sheet pile wall 3 and the reinforced concrete cap 6 of the first stage are constructed above water, three pile caps are formed, and medium-coarse sand is backfilled behind the sheet piles to above the water surface to form a seawall platform 5. Carry out the land construction of the remaining PHC piles and the reinforced concrete cap 6 of the second stage.
本实施例中,上述地基1的桩径为700mm,搭接200mm,加固深度10m,格栅状布置,在格栅状之间打桩,布置形式见图2。In this embodiment, the above foundation 1 has a pile diameter of 700 mm, an overlap of 200 mm, and a reinforcement depth of 10 m. It is arranged in a grid shape, and the piles are driven between the grid shapes. The layout is shown in Figure 2.
本实施例中,上述板桩墙3布置在钢筋混凝土承台6的中部,采用YUBZ-800预应力U型混凝土板桩,混凝土板桩前设置1根直径800mm PHC管桩斜桩(斜率4:1)和1根直径800mmPHC管桩直桩,混凝土板桩后设置4根直径600mm PHC管桩直桩,PHC管桩间距均为3m,为避免承台结构采用水泥搅拌桩地基处理对PHC管桩施打的影响,PHC管桩采用正方形布置(水泥搅拌桩采用格栅状布置)。桩基以全风化混合花岗岩层为持力层,入持力层不小于1.5倍桩径。为进一步减少结构位移,在沉U型混凝土板桩后,在板桩与水泥搅拌桩之间补钻旋喷桩达到注浆填充(4)的效果。In this embodiment, the above-mentioned sheet pile wall 3 is arranged in the middle of the reinforced concrete cap 6, and YUBZ-800 prestressed U-shaped concrete sheet piles are used, and a PHC pipe pile with a diameter of 800mm is arranged in front of the concrete sheet piles (slope 4: 1) and one straight PHC pipe pile with a diameter of 800mm, and four straight PHC pipe piles with a diameter of 600mm are arranged behind the concrete sheet pile, and the distance between the PHC pipe piles is 3m. Due to the impact of driving, the PHC pipe piles are arranged in a square shape (the cement mixing piles are arranged in a grid shape). The pile foundation takes the fully weathered mixed granite layer as the bearing layer, and the penetration into the bearing layer is not less than 1.5 times the pile diameter. In order to further reduce the structural displacement, after sinking the U-shaped concrete sheet pile, the rotary grouting pile is re-drilled between the sheet pile and the cement mixing pile to achieve the effect of grouting filling (4).
图3为YUBZ-800预应力U型混凝土板桩大样图,YUBZ-800预应力U型混凝土板桩截面特性具体参数为:800mm(截面高)×160mm(板厚)×1200mm(板宽),截面面积为342480mm2,有效预压应力5.06Mpa,抗裂弯矩437KN.m,抗弯弯矩700 KN.m,抗剪力566KN,竖向承载力设计值5380KN,竖向抗拉承载力设计值2010KN,理论重量874Kg/m。Figure 3 is a large sample diagram of the YUBZ-800 prestressed U-shaped concrete sheet pile. The specific parameters of the section characteristics of the YUBZ-800 prestressed U-shaped concrete sheet pile are: 800mm (section height) × 160mm (slab thickness) × 1200mm (slab width) , the cross-sectional area is 342480mm 2 , the effective precompression stress is 5.06Mpa, the cracking moment is 437KN.m, the bending moment is 700 KN.m, the shearing force is 566KN, the design value of vertical bearing capacity is 5380KN, and the vertical tensile bearing capacity is The design value is 2010KN, and the theoretical weight is 874Kg/m.
本实施例中,上述钢筋混凝土承台6兼作挡浪墙。半叉桩PHC桩、板桩和第一阶段承台施工完毕形成三桩挡土承台结构,再在板桩陆侧回填中粗砂形成海堤平台5,为剩余的PHC桩和第二阶段承台提供陆上施工作业面,减少水上施工作业量。In this embodiment, the above-mentioned reinforced concrete platform 6 is also used as a wave retaining wall. After the half-pile PHC piles, sheet piles and the caps of the first stage are constructed, a three-pile retaining cap structure is formed, and then the seawall platform 5 is formed by backfilling medium and coarse sand on the land side of the sheet piles, which is the remaining PHC piles and the second stage. The bearing platform provides a land construction work surface, reducing the amount of water construction work.
本实施例中,复合土工垫11能使块石护底13均匀铺设,减少差异沉降,复合土工垫的性能指标具体参数经向抗拉强度≥150 kN/m,纬向抗拉强度≥50 kN/m,经/纬向断裂伸长率≤12%,材质为高强聚酯。抛石护底采用民船抛填10~100kg块石。In this embodiment, the composite geotechnical mat 11 can make the block stone bottom protection 13 evenly laid, and reduce differential settlement. The specific parameters of the performance index of the composite geotechnical mat are ≥ 150 kN/m in the meridian direction and ≥ 50 kN in the weft direction. /m, warp/weft elongation at break ≤ 12%, made of high-strength polyester. 10~100kg of rocks are thrown and filled by civilian boats for the bottom protection of riprap.
本实用新型桩基采用的是预应力混凝土管桩(混凝土为C80)和预应力混凝土板桩(混凝土为C60)耐久性较钢管桩和钢板桩好,不需要特殊的防腐(仅需做海工涂层处理),造价相对较低,施工经验成熟可靠,施工设备要求相对较低。另外,本实用新型海侧直径800mmPHC管桩及预应力U型混凝土板桩水上沉桩结束并完成前上部分承台底板浇筑后,再考虑后方回填砂至水面以上形成陆上施工平台,接着进行直径600mm PHC管桩陆上施工,从而大大加快施工速度,有效节省工程投资;三是上部采用卸荷承台,既起到卸荷作用,减少主动土压力,可以使海堤的后方陆域能承受较大的使用荷载。The pile foundation of the utility model adopts prestressed concrete pipe piles (concrete is C80) and prestressed concrete sheet piles (concrete is C60). The durability is better than steel pipe piles and steel sheet piles, and no special anti-corrosion is required (only sea industrial coating treatment), the cost is relatively low, the construction experience is mature and reliable, and the requirements for construction equipment are relatively low. In addition, after the PHC pipe pile with a diameter of 800mm on the sea side of the utility model and the prestressed U-shaped concrete sheet pile are sinking in water and the bottom plate of the front upper part of the platform is poured, consider backfilling the sand above the water surface to form a land construction platform, and then carry out The onshore construction of PHC pipe piles with a diameter of 600mm greatly speeds up the construction speed and effectively saves engineering investment; the third is that the upper part adopts unloading caps, which not only play a role in unloading, but also reduce active earth pressure, and can make the land area behind the seawall energy-saving. Withstand heavy loads.
本实用新型涉及港口工程中复杂环境下的带宽承台卸荷式板桩的海堤结构,是一种新型的无锚板桩结构,能很好地解决海堤无法设锚碇设施的情况,其技术水平是在卸荷式板桩码头结构的基础上有所推进,采用的宽承台卸荷式板桩结构可广泛应用于围海造陆的海堤工程中。The utility model relates to a seawall structure of unloading sheet piles with wide-band caps in complex environments in port engineering, and is a new type of anchorless sheet pile structure, which can well solve the situation that anchorage facilities cannot be installed on seawalls. Its technical level is advanced on the basis of the unloading sheet pile wharf structure, and the wide cap unloading sheet pile structure adopted can be widely used in seawall projects for sea reclamation and land reclamation.
尽管以上结合附图对本实用新型的实施方案进行了描述,但本实用新型并不局限于上述的具体实施方案和应用领域,上述的具体实施方案仅仅是示意性的、指导性的,而不是限制性的。本领域的普通技术人员在本说明书的启示下和在不脱离本实用新型权利要求所保护的范围的情况下,还可以做出很多种的形式,这些均属于本实用新型保护之列。Although the embodiments of the present utility model have been described above in conjunction with the accompanying drawings, the present utility model is not limited to the above-mentioned specific embodiments and application fields, and the above-mentioned specific embodiments are only illustrative, instructive, and not limiting sexual. Under the enlightenment of this specification and without departing from the protection scope of the claims of the present invention, those skilled in the art can make various forms, which all belong to the protection of the present invention.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822105202.9U CN209482246U (en) | 2018-12-14 | 2018-12-14 | An unloading sheet pile seawall structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822105202.9U CN209482246U (en) | 2018-12-14 | 2018-12-14 | An unloading sheet pile seawall structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209482246U true CN209482246U (en) | 2019-10-11 |
Family
ID=68127684
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822105202.9U Expired - Fee Related CN209482246U (en) | 2018-12-14 | 2018-12-14 | An unloading sheet pile seawall structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209482246U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111379204A (en) * | 2020-04-27 | 2020-07-07 | 浙江省交通规划设计研究院有限公司 | A kind of pile-slab roadbed structure and construction method thereof |
CN113047214A (en) * | 2021-03-19 | 2021-06-29 | 中交第二航务工程勘察设计院有限公司 | Reinforced concrete sheet pile breakwater structure with inclined struts |
CN114718012A (en) * | 2022-05-05 | 2022-07-08 | 中交第四航务工程勘察设计院有限公司 | Composite dyke body ecological sea dike structure on soft soil foundation and construction method thereof |
CN118932924A (en) * | 2024-10-12 | 2024-11-12 | 中交第四航务工程勘察设计院有限公司 | Assembled ecological breakwater structure suitable for deep soft soil foundation and construction method thereof |
-
2018
- 2018-12-14 CN CN201822105202.9U patent/CN209482246U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111379204A (en) * | 2020-04-27 | 2020-07-07 | 浙江省交通规划设计研究院有限公司 | A kind of pile-slab roadbed structure and construction method thereof |
CN111379204B (en) * | 2020-04-27 | 2025-06-24 | 浙江数智交院科技股份有限公司 | A pile-slab roadbed structure and construction method thereof |
CN113047214A (en) * | 2021-03-19 | 2021-06-29 | 中交第二航务工程勘察设计院有限公司 | Reinforced concrete sheet pile breakwater structure with inclined struts |
CN114718012A (en) * | 2022-05-05 | 2022-07-08 | 中交第四航务工程勘察设计院有限公司 | Composite dyke body ecological sea dike structure on soft soil foundation and construction method thereof |
CN114718012B (en) * | 2022-05-05 | 2024-07-19 | 中交第四航务工程勘察设计院有限公司 | Composite dyke body ecological sea wall structure on soft soil foundation and construction method thereof |
CN118932924A (en) * | 2024-10-12 | 2024-11-12 | 中交第四航务工程勘察设计院有限公司 | Assembled ecological breakwater structure suitable for deep soft soil foundation and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1837511B (en) | Double-rowed cofferdam and method for manufacturing the same | |
CN209482246U (en) | An unloading sheet pile seawall structure | |
CN105178245A (en) | Large filling bag ecological embankment and revetment building method for river lake channel | |
CN207760804U (en) | A kind of Multi-functional economy dike structure | |
CN103015367B (en) | High-efficiency economical construction method for revetment | |
CN103205951A (en) | Sludge-type soil combined secondary dike-back pressure diking method | |
CN105862659A (en) | High-frequency debris flow shore protection and diversion method | |
CN202170498U (en) | Reinforced concrete pile dike | |
CN110004876A (en) | Low stake gravity type quay and its construction method suitable for soft soil foundation | |
CN106854864A (en) | Port engineering platoon formula prestressed reinforced concrete Big Pipe Pile new construction | |
CN218540735U (en) | Marine anti-seepage cofferdam | |
CN113047215A (en) | Middle plate pile high pile wharf structure | |
CN207211073U (en) | A river anti-scour foot protector | |
CN215629710U (en) | Sheet pile shore-connection type high-pile wharf structure suitable for deep peat soil soft foundation | |
CN216041278U (en) | Novel pile foundation scour prevention structure | |
CN115419092A (en) | Seepage-proof cofferdam and construction method thereof | |
CN103821106B (en) | Small-sized fishing port and channel revetment structure | |
CN100590271C (en) | a vertical embankment | |
CN212052161U (en) | Embankment structure suitable for coastal areas | |
CN115110476A (en) | Assembled revetment structure of anti erosion toughness reinforcing of soft soil foundation wave-proof | |
CN204510181U (en) | A kind of phytal zone drilling platform | |
CN104195980B (en) | A kind of outfitting quay structure | |
CN113585168A (en) | Sheet pile shore-connection type high-pile wharf structure suitable for deep peat soil soft foundation and construction method | |
CN209958345U (en) | A kind of cement-soil mixing pile composite foundation for bank protection reinforcement | |
CN113737715A (en) | Counterfort type island wall structure for island and bridge joint part of artificial island |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191011 |