CN209384604U - Up-side down triangle installation part and up-side down triangle mounting operation platform - Google Patents
Up-side down triangle installation part and up-side down triangle mounting operation platform Download PDFInfo
- Publication number
- CN209384604U CN209384604U CN201822099291.0U CN201822099291U CN209384604U CN 209384604 U CN209384604 U CN 209384604U CN 201822099291 U CN201822099291 U CN 201822099291U CN 209384604 U CN209384604 U CN 209384604U
- Authority
- CN
- China
- Prior art keywords
- brace
- side down
- triangle
- installation part
- down triangle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009434 installation Methods 0.000 title claims abstract description 47
- 238000003466 welding Methods 0.000 claims description 8
- 230000001681 protective effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 19
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 239000000463 material Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000010248 power generation Methods 0.000 description 2
- 241000251468 Actinopterygii Species 0.000 description 1
- 241000282414 Homo sapiens Species 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000446 fuel Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000007935 neutral effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model provides a kind of up-side down triangle installation part, it is made of horizon bar, the first brace, the second brace and middle upright bar;Horizon bar, the first brace and the second brace are interconnected with one another composition isosceles triangle;Middle upright bar is fixed in triangle, and one end is connected with vertex of a triangle, and the other end is connected with triangle base midpoint.The utility model also provides a kind of up-side down triangle mounting operation platform, if it is built by several up-side down triangle installation parts and a block pedal.The middle upright bar of up-side down triangle installation part is fixed on live tubular pole by anchor ear;Pedal is laid between adjacent inverted triangle installation part.Up-side down triangle installation part structure provided by the utility model is simple, easy to manufacture, at low cost.The job platform construction efficiency built using the up-side down triangle installation part is high, biggish operation side is provided for installer, and operation side is big and steady, the risk of photovoltaic panel installation is greatly reduced, it is ensured that the safety of construction personnel, construction speed are fast.
Description
Technical field
The utility model relates to a kind of up-side down triangle installation parts, and the up-side down triangle installation built using the installation part is made
Industry platform.The utility model belongs to aerial work platform technical field.
Background technique
Solar energy is a kind of clean energy resource, and solar energy power generating does not consume fuel, pollution-free, low cost, and traditional
Thermal power generation compare be a kind of most sustainable development, renewable energy generation technology, native land man advocates solar energy energetically
Photovoltaic power generation.But the disadvantage of solar energy power generating is: it takes up a large area, so, to reduce occupied area, country
It is required that must build agricultural greenhouse below solar energy photovoltaic panel or build fishing light complementation engineering (is fish i.e. below solar energy photovoltaic panel
The pool).
Currently, most 4 meters of ground level of solar energy photovoltaic panel mounting distances or more, apart from 2 meters of water surface elevation or more.
Land installation, worker generally use double ladder installation, and operation foothold is relatively narrow, and double ladder stability is bad, can not ensure construction
Safety, while again because being constructed using double ladder, it needs repeatedly up and down, seriously to restrict construction speed;Double ladder is carried repeatedly, is added
Big operation person works' load.To improve construction speed, job platform, this mounting means pair are also built using scaffold sometimes
Levelling of the land degree requires height, and material lease amount is bigger, it is long to build land period, while also needing multiple special operation workers
(scaffolder) is responsible for implementation, and installation cost is high, and unsuitable photovoltaic is constructed the fast feature of short frequency, and construction speed is difficult to ensure.The water surface
Upper installation solar energy photovoltaic panel generallys use ship and builds operation at sea platform, and ship is influenced by water wave, is easy to jolt or be moved
Dynamic, construction operation platform is unstable.The shallow region of water is met, ship is easy stranded.There are security risk height, construction speed is slowly waited and is lacked
Point.
Utility model content
In view of the foregoing, the purpose of the utility model is to provide a kind of up-side down triangle installation parts, and fall three using this
The up-side down triangle mounting operation platform that angel mountings are built.
To achieve the above object, the utility model uses following technical scheme: a kind of up-side down triangle installation part, it is by level
Bar, the first brace, the second brace and middle upright bar are constituted;
The horizon bar, the first brace and the second brace are interconnected with one another composition isosceles triangle;The middle upright bar
It is fixed on down in isosceles triangle, one end is connected with the vertex of isosceles triangle, the other end and the bottom edge of falling isosceles triangle
Midpoint is connected.
Preferably, one end that one end of the middle upright bar is connected with the first brace and the second brace is connected;Middle upright bar it is another
One end is connected with the midpoint of horizon bar.
Preferentially, the horizon bar, the first brace, the second brace and middle upright bar are each other using welding, fastener or spiral shell
It tethers and connects.
In the preferred embodiment of the utility model, adopted between the horizon bar, the first brace, the second brace and middle upright bar
It is fixedly connected with the mode of being fully welded.
Preferentially, the both ends of the horizon bar are equipped with guardrail, which is fixed on using welding, fastener or bolt mode
The end of horizon bar.
The invention also discloses a kind of up-side down triangle mounting operation platform, it by several up-side down triangle installation parts and
If a block pedal is built,
The up-side down triangle installation part is made of horizon bar, the first brace, the second brace and middle upright bar;The horizon bar,
First brace and the second brace are interconnected with one another composition isosceles triangle;The middle upright bar is fixed on down isosceles triangle
Interior, one end is connected with the vertex of isosceles triangle, and the other end is connected with the bottom edge of falling isosceles triangle midpoint;
The middle upright bar of the up-side down triangle installation part is fixed on live tubular pole by anchor ear;
The pedal is laid between the adjacent inverted triangle installation part.
The up-side down triangle mounting operation platform further includes several pieces of protective plates, which is mounted on the horizon bar both ends
Guard rail position.
Detailed description of the invention
Fig. 1 is the utility model up-side down triangle installation part structural schematic diagram;
Fig. 2 is the utility model up-side down triangle installation part scheme of installation;
Fig. 3 is the utility model up-side down triangle mounting operation platform structural schematic diagram;
Fig. 4 is the utility model up-side down triangle mounting operation platform structural representation Fig. 2.
Specific embodiment
The structure of the utility model and feature are described in detail with reference to the accompanying drawings and examples.It needs to illustrate
It is that disclosed embodiments can be made with various modifications, therefore, embodiment disclosed in specification should not be considered as to this
The limitation of utility model, and only as the example of embodiment, the purpose is to keep the feature of the utility model apparent.
As shown in Figure 1, up-side down triangle installation part disclosed by the utility model is by horizon bar 1, the first brace 2, the second brace 3
It is constituted with middle upright bar 4.Horizon bar 1, the first brace 2 and the second brace 3 are fixed each other to constitute isosceles triangle.Middle upright bar
4 are fixed on down in isosceles triangle, and one end is connected with the vertex A of isosceles triangle, the other end and the bottom of falling isosceles triangle
Side midpoint B is connected.As shown, one end A that one end of middle upright bar 4 is connected with the first brace 2 and the second brace 3 is connected;It is neutral
The other end of bar 4 is connected with the midpoint B of horizon bar 1.
Horizon bar 1, the first brace 2 and the second brace 3 using welding, fastener or can be bolted each other.At this
In the preferred embodiment of utility model, connect between the horizon bar 1 and the first brace 2, the second brace 3 using the mode that is fully welded is fixed
It connects;It is also fixedly connected using being fully welded mode between first brace 2 and the second brace 3.
To improve construction efficiency, up-side down triangle installation part disclosed by the utility model can be finished in factory's overall package, existing
Field installation.As shown in Fig. 2, being transported to construction site after up-side down triangle installation part factory overall package.In general, existing in construction
Tubular pole 5 has been buried at interval of 3 meters in field, and the middle upright bar 4 of inverted triangle installation part is fixed on tubular pole 5 by anchor ear 6, entirely falls
Triangle installation part is fixed on tubular pole.
As shown in figure 3, being laid with pedal 7 between adjacent inverted triangle installation part, that is, form job platform.
To guarantee safety, as shown in Figure 1, it can be separately installed with guardrail 8 at the both ends of up-side down triangle installation part horizon bar 1,
The end that welding, fastener or bolt mode are fixed on horizon bar 1 can be used in the guardrail 8.
As shown in figure 4, protective plate 9 is installed at the guardrails of both sides 8 for the effect platform put up, to ensure that construction operation is pacified
Entirely.
Up-side down triangle installation part structure provided by the utility model is simple, easy to manufacture, at low cost.Three are fallen using this
The job platform construction efficiency that angel mountings are built is high, provides biggish operation side, construction operation for installer
Face is big and steady, the risk of photovoltaic panel installation can be greatly reduced, it is ensured that the safety of construction personnel, construction cost is low, construction speed
Fastly.
In addition, up-side down triangle installation part disclosed by the utility model is processed and formed at one time, it can have enough to meet the need and be used for multiple times, construction cost
It reduces, material lease is less.The up-side down triangle mounting operation platform put up does not need worker's upper and lower and materials hauling repeatedly, subtracts
Light operating personnel's workload.Up-side down triangle installation part is in addition to prefabricated processing needs welder to carry out, in-site installation common laborer
It is achievable, special operation workers are put into and are reduced.
Finally, it should be noted that above-described each embodiment is merely to illustrate the technical solution of the utility model, rather than
It is limited;Although the utility model is described in detail with reference to the foregoing embodiments, those skilled in the art
It is understood that it can still modify to technical solution documented by previous embodiment, or to part of or whole
Technical characteristic is equivalently replaced;And these modifications or substitutions, it does not separate the essence of the corresponding technical solution the utility model
The range of each embodiment technical solution.
Claims (10)
1. a kind of up-side down triangle installation part, it is characterised in that: it is made of horizon bar, the first brace, the second brace and middle upright bar;
The horizon bar, the first brace and the second brace are interconnected with one another composition isosceles triangle;
The middle upright bar 4 is fixed on down in isosceles triangle, and one end is connected with the vertex of isosceles triangle, the other end with fall etc.
Lumbar triangle shape bottom edge midpoint is connected.
2. up-side down triangle installation part according to claim 1, it is characterised in that: one end of the middle upright bar and the first brace
The one end being connected with the second brace is connected;The other end of middle upright bar is connected with the midpoint of horizon bar.
3. up-side down triangle installation part according to claim 2, it is characterised in that: the horizon bar, the first brace, second are tiltedly
Bar and middle upright bar using welding, fastener or are bolted each other.
4. up-side down triangle installation part according to claim 3, it is characterised in that: the horizon bar, the first brace, second are tiltedly
It is fixedly connected between bar and middle upright bar using being fully welded mode.
5. up-side down triangle installation part described in one of -4 according to claim 1, it is characterised in that: install at the both ends of the horizon bar
There is guardrail, which is fixed on the end of the horizon bar using welding, fastener or bolt mode.
6. a kind of up-side down triangle mounting operation platform, it is characterised in that: if it is stepped on by several up-side down triangle installation parts and a block
Plate is built,
The up-side down triangle installation part is made of horizon bar, the first brace, the second brace and middle upright bar;The horizon bar, first
Brace and the second brace are interconnected with one another composition isosceles triangle;The middle upright bar is fixed on down in isosceles triangle,
One end is connected with the vertex of isosceles triangle, and the other end is connected with the bottom edge of falling isosceles triangle midpoint;
The middle upright bar of the up-side down triangle installation part is fixed on live tubular pole by anchor ear;
The pedal is laid between the adjacent up-side down triangle installation part.
7. up-side down triangle mounting operation platform according to claim 6, it is characterised in that: the horizon bar, the first brace,
Second brace and middle upright bar using welding, fastener or are bolted each other.
8. up-side down triangle mounting operation platform according to claim 7, it is characterised in that: the horizon bar, the first brace,
It is fixedly connected between second brace and middle upright bar using being fully welded mode.
9. the up-side down triangle mounting operation platform according to one of claim 6-8, it is characterised in that: the two of the horizon bar
End is equipped with guardrail, which is fixed on the end of the horizon bar using welding, fastener or bolt mode.
10. up-side down triangle mounting operation platform according to claim 9, it is characterised in that: it further includes several pieces of protection
Plate, the protective plate are mounted on the guard rail position at the horizon bar both ends.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822099291.0U CN209384604U (en) | 2018-12-13 | 2018-12-13 | Up-side down triangle installation part and up-side down triangle mounting operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822099291.0U CN209384604U (en) | 2018-12-13 | 2018-12-13 | Up-side down triangle installation part and up-side down triangle mounting operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209384604U true CN209384604U (en) | 2019-09-13 |
Family
ID=67871875
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822099291.0U Active CN209384604U (en) | 2018-12-13 | 2018-12-13 | Up-side down triangle installation part and up-side down triangle mounting operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209384604U (en) |
-
2018
- 2018-12-13 CN CN201822099291.0U patent/CN209384604U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201953134U (en) | Self supporting maritime wind measurement tower structure | |
CN206481251U (en) | A kind of photovoltaic bracket device of use truss string structure beam | |
CN206204986U (en) | A kind of civil construction retaining wall structure | |
CN203394685U (en) | Lattice wind turbine tower and wind turbine generator system comprising same | |
CN205779502U (en) | A kind of marine wind electric field vertical axis aerogenerator arch (bridge) type supporting construction | |
CN209384604U (en) | Up-side down triangle installation part and up-side down triangle mounting operation platform | |
CN105790679A (en) | Telescopic solar energy power generation device with lightning protection, wind power generation and light collecting mirror functions | |
CN205792361U (en) | Anti-lightning strike band wind-power electricity generation and the telescopic device of solar generating of condenser lens | |
CN207720056U (en) | Floatation type photovoltaic power station system | |
CN203701622U (en) | Sliding construction device for garbage storage span roof trusses of large-scale garbage incineration power plant | |
CN207553565U (en) | A kind of crosshead of truss | |
CN206801792U (en) | A kind of stable triangular type tension leg type base plate | |
CN202248995U (en) | Rapid integration communication device suitable for mountainous regions | |
CN207686323U (en) | Diamond shape installation part and diamond shape mounting operation platform | |
CN104278689A (en) | Foundation device shared by box-type transformer substation and wind power generation facility and construction method of foundation device | |
CN211645937U (en) | Lightweight bridge ETC plane truss structure | |
CN209211742U (en) | A kind of roof truss and roof with grid structure | |
CN206640531U (en) | Solar energy kinetic hydraulic energy integration generating device | |
CN205945605U (en) | Distributing type photovoltaic module ground mounting structure | |
CN220786084U (en) | Photovoltaic installation construction platform on water | |
CN219932344U (en) | Floating type fan foundation | |
CN206655778U (en) | Marine anemometer tower | |
CN222272310U (en) | Support structure of floating photovoltaic power generation system | |
CN207686243U (en) | Inverted T shaped installation part and inverted T shaped mounting operation platform | |
CN202645879U (en) | Steel frame on wind power generation bottom of wind tower |