CN209214431U - Convenient for the Pipe bundle structure of pressure testing - Google Patents
Convenient for the Pipe bundle structure of pressure testing Download PDFInfo
- Publication number
- CN209214431U CN209214431U CN201821522850.8U CN201821522850U CN209214431U CN 209214431 U CN209214431 U CN 209214431U CN 201821522850 U CN201821522850 U CN 201821522850U CN 209214431 U CN209214431 U CN 209214431U
- Authority
- CN
- China
- Prior art keywords
- pressure testing
- tube
- supporting guide
- several
- tube sheet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000012360 testing method Methods 0.000 title claims abstract description 65
- 238000003466 welding Methods 0.000 claims abstract description 15
- 238000007789 sealing Methods 0.000 claims abstract description 9
- 239000007787 solid Substances 0.000 claims description 2
- 238000004519 manufacturing process Methods 0.000 abstract description 6
- 238000001514 detection method Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 239000002893 slag Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)
- Monitoring And Testing Of Nuclear Reactors (AREA)
Abstract
The utility model discloses the Pipe bundle structures for being convenient for pressure testing, it include: tube sheet, several baffle plates, several heat exchanger tubes, heat exchanger tube, which is worn, to be fixed in several baffle plates, and the both ends of heat exchanger tube respectively with two pieces of tube sheet sealing weldings, a supporting guide is fixedly installed between two tube sheets, supporting guide is located at the lower section of tube sheet, supporting guide is also fixedly connected with baffle plate, several support wheels that can be freely rotated are provided on supporting guide, support wheel is downwardly projecting in supporting guide, is fixedly installed a pressure testing baffle ring respectively on two pieces of tube sheets.The utility model has the advantages that: carrying can be facilitated, and tube bank will not scratch cylinder inboard wall when passing in and out cylinder, so that tube bank is carried out work pressure test directly in cylinder, improve work efficiency, reduce production cost;In addition, during pressure testing, pressure testing baffle ring is mutually welded with cylinder and prevents from tube sheet and is damaged.
Description
Technical field
The utility model relates to the tube banks of heat exchange in large container.
Background technique
The tube bank of heat exchange needs to carry out pressure testing after finalization of the manufacture in large container, is then judged according to pressure testing result
Whether tube bank is qualified, and only up-to-standard tube bank could finally be put into the cylinder of large container.But it is changed in large container
The tube bank massiveness of heat is also not easy to carry, if carrying out pressure testing directly in cylinder, when that will restrain in threading cylinder
It is easy to scratch cylinder inboard wall;And if pressure testing result is unqualified, needs to restrain pulling out from cylinder, be easier in this way
Cylinder inboard wall is scratched.So currently used pressure testing mode is: need in addition manufacture to restrain matched pressure testing shell with pressure testing,
Then tube bank is sent into pressure testing shell, then tube sheet and pressure testing housing seal that both ends will be restrained, is then led into pressure testing shell
Enter pressure-air or high pressure water, so that the pressure in pressure testing shell is reached testing requirements, staff is to the pressure in pressure testing shell
It tests, if the intracorporal pressure of pressure testing shell remains unchanged within a certain period of time, illustrates in tube bank between exchanger tubes and tubesheets
Welding quality it is qualified, qualified tube bank can thus be put into the cylinder of large container;If pressure testing shell within a certain period of time
Intracorporal pressure is gradually reduced, then illustrates that the welding quality in tube bank between exchanger tubes and tubesheets is unqualified, need to exchange heat pipe
It is checked and is rewelded in welding position between tube sheet.Above-mentioned this pressure testing mode needs to be manufactured according to the tube bank of different size
Different pressure testing shells, a large amount of pressure testing shell not only increases production cost, but also also takes up a large amount of warehouse space.
Utility model content
The purpose of the utility model is to provide one kind, and carrying can be facilitated to restrain and tube bank is made to scratch cylinder inboard wall,
So as to make to restrain the Pipe bundle structure convenient for pressure testing for carrying out pressure testing in cylinder.
To achieve the above object, the technical scheme adopted by the utility model is being convenient for the Pipe bundle structure of pressure testing, comprising:
Tube sheet, several baffle plates, several heat exchanger tubes, heat exchanger tube, which is worn, to be fixed in several baffle plates, and the both ends difference of heat exchanger tube
With two pieces of tube sheet sealing weldings, a supporting guide is fixedly installed between two tube sheets, supporting guide is located under tube sheet
Side, supporting guide are also fixedly connected with baffle plate, and several support wheels that can be freely rotated, support wheel are provided on supporting guide
Downwardly projecting to be fixedly installed a pressure testing baffle ring respectively on two pieces of tube sheets in supporting guide, pressure testing baffle ring can be with cylinder
Inner wall sealing welding.
Further, the Pipe bundle structure above-mentioned convenient for pressure testing a, wherein spacing is vertically connected on one piece of tube sheet
Pull rod, is provided with several locating slots on controlled interval pull rod, and the spacing between each adjacent two locating slot is exactly each adjacent two folding
Spacing between flowing plate, baffle plate are fixed on corresponding locating slot one by one respectively.
Further, the Pipe bundle structure above-mentioned convenient for pressure testing, wherein solid on the baffle plate being fixed on controlled interval pull rod
Surely several fixed plates are provided with, fixed plate can fix with each other adjacent baffle plate.
Further, the Pipe bundle structure above-mentioned convenient for pressure testing, wherein be located between per two adjacent baffle plates
A support wheel is provided on supporting guide.
Further, the Pipe bundle structure above-mentioned convenient for pressure testing, wherein connected between pressure testing baffle ring and tube sheet by welding
It connects.
The utility model has the advantages that: support wheel is provided with below tube bank can facilitate tube bank disengaging cylinder, Er Qie
Cylinder inboard wall will not be scratched when passing in and out cylinder, additionally prepares pressure testing shell so there is no need to damage cylinder inboard wall in order to prevent
Body carries out work pressure test, and staff can carry out work pressure test to tube bank directly in cylinder, not only increase working efficiency,
Also reduce production cost;In addition, during pressure testing, pressure testing baffle ring is mutually welded with cylinder and prevents from tube sheet and is damaged.
Detailed description of the invention
Fig. 1 is the schematic perspective view of the Pipe bundle structure described in the utility model convenient for pressure testing.
Fig. 2 is the enlarged structure schematic diagram in the direction A in Fig. 1.
Fig. 3 is the part planar structural representation of the Pipe bundle structure described in the utility model convenient for pressure testing.
Specific embodiment
With reference to the accompanying drawing and preferred embodiment is further described technical solution described in the utility model.
As shown in Figure 1, Figure 2, Figure 3 shows, the Pipe bundle structure described in the utility model convenient for pressure testing, comprising: tube sheet 1, several
Baffle plate 2, several heat exchanger tubes 3 are vertically fixedly connected with a controlled interval pull rod 11, on controlled interval pull rod 11 on one piece of tube sheet 1
Several locating slots are provided with, the spacing between each adjacent two locating slot is exactly the spacing between each adjacent two baffle plate 2, folding
Flowing plate 2 is fixed on corresponding locating slot one by one respectively, to guarantee baffle plate 2 and baffling in the installation process of baffle plate 2
Spacing between plate 2 is not in deviation, is fixedly installed several fixed plates on the baffle plate 2 being fixed on controlled interval pull rod 11
21, fixed plate 21 can fix with each other adjacent baffle plate 2, and the both ends of heat exchanger tube 3 pass through after several baffle plates 2 respectively with two
1 sealing welding of block tube sheet, is fixedly installed a supporting guide 4 between two pieces of tube sheets 1, and supporting guide 4 is located under tube sheet 1
Side, supporting guide 4 are also fixedly connected with baffle plate 2, are set on the supporting guide 4 being located between per two adjacent baffle plates 2
It is equipped with a support wheel 41, support wheel 41 is downwardly projecting in supporting guide 4, is respectively welded on two pieces of tube sheets 1 and is fixed with one
Pressure testing baffle ring 12, pressure testing baffle ring 12 can be with cylinder inboard wall sealing weldings.When needing to carry out work pressure test to tube bank, work people
Tube bank can be easily advanced in cylinder by member by support wheel 41, and the support wheel 41 on supporting guide 4 rolls in cylinder
Shi Buhui causes to damage to cylinder inboard wall, and after tube bank enters in cylinder, the pressure testing baffle ring 12 being located on two tube sheets 1 is divided
Not with cylinder inboard wall sealing welding, and the cylinder being located between two pressure testing baffle rings 12 is made to form sealing space, is then tried
Whether pressure work is qualified to detect tube bank, if detection tube bank is qualified, under pressure testing baffle ring 12 is dismantled from cylinder and tube sheet 1 respectively
Come, and welding slag on cylinder is subjected to grinding process, tube sheet 1 and cylinder are then sealed welding;If detection tube bank is unqualified,
Pressure testing baffle ring 12 is disassembled from cylinder, and the welding slag on cylinder is subjected to grinding process, then by underproof tube bank
Cylinder is released, then is done over again to tube bank, carries out pressure testing again after the completion of doing over again, until tube bank detection is qualified.
The utility model has the advantages that: support wheel is provided with below tube bank can facilitate tube bank disengaging cylinder, Er Qie
Cylinder inboard wall will not be scratched when passing in and out cylinder, additionally prepares pressure testing shell so there is no need to damage cylinder inboard wall in order to prevent
Body carries out work pressure test, and staff can carry out work pressure test to tube bank directly in cylinder, not only increase working efficiency,
Also reduce production cost;In addition, during pressure testing, pressure testing baffle ring is mutually welded with cylinder and prevents from tube sheet and is damaged.
Claims (5)
1. be convenient for pressure testing Pipe bundle structure, comprising: tube sheet, several baffle plates, several heat exchanger tubes, heat exchanger tube wear be fixed on it is several
In baffle plate, and the both ends of heat exchanger tube respectively with two pieces of tube sheet sealing weldings, it is characterised in that: it is fixed between two tube sheets
It is provided with a supporting guide, supporting guide is located at the lower section of tube sheet, and supporting guide is also fixedly connected with baffle plate, leads in support
Several support wheels that can be freely rotated are provided on rail, support wheel is downwardly projecting in supporting guide, solid respectively on two pieces of tube sheets
Surely it is provided with a pressure testing baffle ring, pressure testing baffle ring can be with cylinder inboard wall sealing welding.
2. the Pipe bundle structure according to claim 1 convenient for pressure testing, it is characterised in that: be vertically connected on one piece of tube sheet
A piece controlled interval pull rod, is provided with several locating slots on controlled interval pull rod, and the spacing between each adjacent two locating slot is exactly every phase
Spacing between adjacent two baffle plates, baffle plate are fixed on corresponding locating slot one by one respectively.
3. the Pipe bundle structure according to claim 2 convenient for pressure testing, it is characterised in that: in the folding being fixed on controlled interval pull rod
Several fixed plates are fixedly installed in flowing plate, fixed plate can fix with each other adjacent baffle plate.
4. the Pipe bundle structure according to claim 1 or 2 or 3 convenient for pressure testing, it is characterised in that: be located at per adjacent two
A support wheel is provided on supporting guide between a baffle plate.
5. the Pipe bundle structure according to claim 1 or 2 or 3 convenient for pressure testing, it is characterised in that: pressure testing baffle ring and tube sheet it
Between pass through welded connecting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821522850.8U CN209214431U (en) | 2018-09-18 | 2018-09-18 | Convenient for the Pipe bundle structure of pressure testing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821522850.8U CN209214431U (en) | 2018-09-18 | 2018-09-18 | Convenient for the Pipe bundle structure of pressure testing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209214431U true CN209214431U (en) | 2019-08-06 |
Family
ID=67454225
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821522850.8U Active CN209214431U (en) | 2018-09-18 | 2018-09-18 | Convenient for the Pipe bundle structure of pressure testing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209214431U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108871035A (en) * | 2018-09-18 | 2018-11-23 | 张化机(苏州)重装有限公司 | Convenient for the Pipe bundle structure of pressure testing |
-
2018
- 2018-09-18 CN CN201821522850.8U patent/CN209214431U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108871035A (en) * | 2018-09-18 | 2018-11-23 | 张化机(苏州)重装有限公司 | Convenient for the Pipe bundle structure of pressure testing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107401175B (en) | A kind of method of construction of the upper guide pipe support of six pile leaders frame | |
CN204944242U (en) | The detachable combination exchanger of a kind of heat exchanger tube | |
CN105091634A (en) | Baffle rod type heat exchanger with built-in expansion joint | |
CN207961749U (en) | A kind of top duct suspension and support for building | |
CN209214431U (en) | Convenient for the Pipe bundle structure of pressure testing | |
CN109210967A (en) | A kind of Multi-stage sleeve heat exchanger for reactor fuel Test loop | |
CN108871035A (en) | Convenient for the Pipe bundle structure of pressure testing | |
CN205669953U (en) | The heavy floating head type vertical bushing device of heat exchanger tube tread assembly | |
CN205860851U (en) | The heat exchanger tube pipe bundle mounting structure of fast demountable | |
CN110697653A (en) | Safety structure for improving reliability of high-temperature collecting furnace tube and operation method | |
CN103063075B (en) | Tube box structure of tube type heat exchanger | |
CN210944856U (en) | Safety structure for improving reliability of high-temperature collecting furnace tube | |
CN201497400U (en) | Reactor internal module type heat exchanger | |
CN203495494U (en) | Cylindrical body assembly tool | |
CN202740795U (en) | Tangential feeding efficient falling film evaporator | |
CN202614479U (en) | Pressure testing fixture for floating head type heat exchangers | |
CN205079651U (en) | Novel integrated shell and tube type heat exchanger | |
CN203100525U (en) | Tube box structure for tube type heat exchanger | |
CN101844965B (en) | Heat exchange device for methanol synthesis reactor | |
CN203772103U (en) | Coil fixing structure of positive displacement heat exchanger | |
CN205605808U (en) | Novel pressure container | |
CN203772070U (en) | Positive displacement heat exchanger | |
CN203704735U (en) | Frame type tubular heat exchanger | |
CN202547440U (en) | Coil pipe heat exchanger | |
CN205718637U (en) | The removable pass partition structure of heat exchanger |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |