Utility model content
In view of the foregoing, the utility model provides a kind of cladding glass installation self-control electric hoist hanger, structure letter
It is single, it is easy to disassemble.
To achieve the above object, the utility model discloses a kind of cladding glass to install self-control electric hoist hanger, comprising:
The hanging holder set being removably mounted in the girder construction at the position to be installed of cladding glass, the hanging holder set packet
Include the supporting beam for being connected to the girder construction and being located above the girder construction;
The electric block being removably mounted in the foundation structure below the girder construction, the electric block are matched
Pouring weight;
The pulley being installed in the supporting beam;And
The first end of lifting rope, the lifting rope around the pulley and is connected to the electric block, and the second of the lifting rope
End is connected to the cladding glass to be lifted.
The utility model has the beneficial effects that:
1., will be electronic by the way that hanging holder set to be mounted in the girder construction at the position to be installed of cladding glass
Cucurbit is mounted in foundation structure, convenient for the dismounting of electric hoist hanger system;Supporting beam is installed on girder construction
Top, electric block is installed in the foundation structure below girder construction, is easy to implement and is treated lifting curtain wall glass and hung
Dress;The stability in cladding glass hoisting process can be improved by configuring clump weight to electric block.
2. realizing the lifting for treating lifting object by electric block and lifting rope, structure is simple, convenient for operation.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: the girder construction
Including first crossbeam and second cross beam, the first linking beam, the support are connected between the supporting beam and the first crossbeam
The second linking beam is connected between beam and the second cross beam.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: described first connects
Binder is removably connected to the first crossbeam by the first connection structure, and first connection structure includes being support on described the
First fixed plate of the bottom end of one crossbeam is support on the top of the first crossbeam and is fixed in the second of first linking beam
Fixed plate and the first locking member for being connected to first fixed plate and second fixed plate.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: described second connects
Binder is removably connected to the second cross beam by the second connection structure, and second connection structure includes being support on described the
The third fixed plate of the bottom end of two crossbeams is support on the top of the second cross beam and is fixed in the 4th of second linking beam
Fixed plate and the second locking member for being connected to the third fixed plate and the 4th fixed plate.
A kind of further improvement of cladding glass installation self-control electric hoist hanger of the utility model is: the support
Ribs is equipped between beam and second linking beam.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: the supporting beam
It is removably connected to first linking beam by third connection structure, the third connection structure includes being support on the support
It 5th fixed plate on the top of beam and is support on the bottom end of the supporting beam and is fixed in the 6th fixed of first linking beam
Plate and the third locking member for being connected to the 5th fixed plate and the 6th fixed plate.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: further include being used for
The electric block is installed on the stationary fixture in the foundation structure, the stationary fixture is fixed in the foundation structure
On.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: the supporting beam
Cloth set direction perpendicular to the cladding glass position to be installed cloth set direction.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: the configuration block
Weight be greater than the cladding glass weight.
A kind of the utility model cladding glass installation self-control electric hoist hanger further improvement lies in that: further include connection
Cladding glass after being promoted in place and the drawstring for being pulled to the cladding glass at position to be installed.
Specific embodiment
For the benefit of to the understanding of the utility model, it is illustrated with reference to the accompanying drawings and embodiments.
Refering to fig. 1 to Fig. 3 it is found that the utility model provide it is a kind of using cladding glass installation self-control electric hoist hanger,
Including in the girder construction (including first crossbeam 41, second cross beam 42) that is removably mounted at the position to be installed of cladding glass
Hanging holder set 1, the electric block 2 in the foundation structure 7 being removably mounted to below girder construction, pulley 5 and lifting rope 3;Wherein, it hangs
Frame component 1 includes the supporting beam 11 for being connected to girder construction and being located above girder construction, and electric block is configured with clump weight 63, pulley
5 are installed in supporting beam 11, and the first end of lifting rope 3 around pulley 5 and is connected to electric block 2, and the second end of lifting rope 3 is connected to
Object to be lifted.In the present embodiment, by hanging holder set 1 is removably mounted in girder construction and by electric block it is detachable
It is installed in foundation structure, the dismounting of self-control electric hoist hanger system is installed convenient for cladding glass;Supporting beam 11 is located at beam knot
Lifting curtain is treated in combination with electric block 2 and lifting rope 3 realization being installed in the foundation structure below girder construction in the top of structure
The lifting of wall glass;The change that pulley 5 realizes force direction is installed;The purpose of configuration configuration block is to play electric block 2
To the effect of reinforcing, guarantee the safety and stability of hoisting process.Foundation structure in the present embodiment can be floor construction, beam
Structure (including first crossbeam 41, second cross beam 42) can be roof steel structure beam, and hanging holder set 1 is installed on roof steel structure beam
On.
Further, girder construction includes first crossbeam 41 and second cross beam 42, is connected between supporting beam 11 and first crossbeam 41
It is connected to the first linking beam 12, the second linking beam 13 is connected between supporting beam 11 and the second cross beam 42.Further,
One crossbeam 41 and second cross beam 42 are arranged in parallel.In the present embodiment, first crossbeam 41 is steel I-beam, and second cross beam 42 is box
Beam.
As shown in Figure 3 to Figure 4, the first linking beam 12 is removably connected to first crossbeam 41 by the first connection structure 14,
First connection structure 14 include be support on first crossbeam 41 bottom end the first fixed plate, be support on first crossbeam 41 top and
It is fixed in the second fixed plate 141 of the first linking beam 12 and is connected to the first lock of the first fixed plate and the second fixed plate 141
Tight part 142.Further, first through hole is offered in the first fixed plate, and the second through-hole is offered in the second fixed plate 141, the
One locking member 142 is connected to first through hole and the second through-hole.In the present embodiment, bolt and attaching nut is can be selected in the first locking member
It uses.
As shown in Figure 3 and Figure 5, the second linking beam 13 is removably connected to second cross beam 42 by the second connection structure 15,
Second connection structure 15 include be support on second cross beam 42 bottom end third fixed plate, be support on second cross beam 42 top and
It is fixed in the 4th fixed plate 151 of the second linking beam 13 and is connected to the second lock of third fixed plate and the 4th fixed plate 151
Tight part 152.Further, third through-hole is offered in third fixed plate, offers fourth hole in the 4th fixed plate 151, the
Two locking members 152 are connected to third through-hole and fourth hole.In the present embodiment, the second locking member 152 can be selected bolt and cooperate
Nut uses.
As shown in Figure 1 to Figure 3, ribs 8 is equipped between supporting beam 11 and the second linking beam 13;For enhancing whole knot
Structure intensity.
As shown in Figure 3 and Figure 6, supporting beam 11 is removably connected to the first linking beam 12 by third connection structure 16, the
Three connection structures 16 include being support on the 5th fixed plate 161 on the top of supporting beam 11 and being support on the bottom end of supporting beam 11 and consolidate
It is connected to the 6th fixed plate of the first linking beam 12 and is connected to the third locking member of the 5th fixed plate 161 and the 6th fixed plate
162.Further, fifth hole is offered in the 5th fixed plate 161, and the 6th through-hole, third lock are offered in the 6th fixed plate
Tight part 162 is connected to fifth hole and the 6th through-hole.In the present embodiment, third locking member 162 also can be selected bolt and cooperate spiral shell
Mother uses.
As shown in Fig. 2, in the utility model, the cloth of the cloth set direction of supporting beam perpendicular to the position to be installed of cladding glass
Set direction;When being easy to lift, the lifting of cladding glass is carried out along the cloth set direction for the position to be installed for being parallel to cladding glass, i.e.,
Cladding glass is laid along the direction perpendicular to supporting beam in hoisting process, guarantees not needing to carry out curtain when the installation of later period cladding glass
The adjustment of wall glass cloth set direction, improves construction efficiency, reduces the workload of construction.In the utility model, the weight of configuration block
Amount is greater than the weight of cladding glass, guarantees the safety in cladding glass hoisting process, avoids not enough leading because of the weight of configuration block
Cause falling for cladding glass.
In the utility model, the first linking beam 12, the second linking beam 13 and supporting beam 11 select square tube component, specific to select
With 150mm × 100mm × 8mm square steel tube;
As shown in Figure 1, Figure 2 and Figure 7, further include stationary fixture 6 for being installed on electric block 2 in foundation structure 7.
Further, clump weight 63 is installed on stationary fixture 6.Specifically, stationary fixture 6 is removably mounted on floor 7;Fixing clamp
Tool 6 includes two vertical poles 61 of contraposition setting, the cross bar 62 for being connected to two vertical poles 61, and vertical pole 61 and the connection of cross bar 62 are formed for solid
Determine the stationary fixture 6 of electric block 2, the mounting base installation of electric block 2, which is connected on stationary fixture 6, realizes electric block 2 with this
Installation, the both ends of vertical pole 61 are separately installed with clump weight 63;Further, a fixed link 64, counterweight are connected on vertical pole 61
It is formed with a through-hole on block 63, by the way that fixed link 64 to be arranged in through-hole, realizes the positioning of clump weight 63.In the present embodiment,
By being welded to connect between vertical pole 61 and cross bar 62, vertical pole 61 and cross bar 62 select 80mm × 80mm × 5mm square steel tube, fixed
Fixture 6 is installed on floor 7 by expansion bolt.
As shown in Figure 1, the both ends of supporting beam 11 are separately installed with a pulley 5;I.e. in the present embodiment, pass through two pulleys 5
It realizes the change of force direction, while avoiding lifting rope 3 and the contact of supporting beam 11 in lifting curtain wall glass process and generating friction,
Improve the smoothness and stability in hoisting process.
In the utility model, the anchor of M20 is can be selected in the first locking member 142, the second locking member 152 and third locking member 162
Bolt;First fixed plate, the second fixed plate 141, third fixed plate, the 4th fixed plate 151, the 5th fixed plate 161 and the 6th are fixed
The steel plate of 20mm thickness can be selected in plate.Electric block 2 selects the electric block 2 of 2T, and lifting rope 3 selects the wirerope of diameter 25mm.
In the utility model, pulley 5 is installed on the top of supporting beam 11 by free bearing.
As shown in figure 3, the plane to be installed of cladding glass 9 and first crossbeam 41 and second cross beam 42 are flat in the utility model
Row is laid.
As shown in Fig. 2, further including being connected to the cladding glass 9 after being promoted in place and being used for curtain wall glass in the utility model
Glass 9 is pulled to the drawstring 92 at position to be installed.
In practice of construction, the hanging holder set in the utility model can be installed on to the beam knot of building body top (roof)
, it can be achieved that lifting to different floors cladding glass to be installed 9 on structure.
It is hung the invention also discloses a kind of using cladding glass installation self-control electric hoist hanger progress cladding glass
The method of dress, comprising the following steps:
Cladding glass 9 to be lifted is provided;
The second end of lifting rope 3 is connected to cladding glass 9 to be lifted;
Start electric block 2, drives cladding glass 9 to be lifted to be up-shifted to curtain wall glass to be lifted by lifting rope 3
The height to be installed of glass.
Further, four angles of cladding glass 9 are connected to a drawstring 92 simultaneously, after promoting cladding glass 9 in place
It further comprises the steps of: and pulling force is applied to drawstring 92 along the direction for the position to be installed 91 for being directed toward cladding glass 9, until by cladding glass
9 are pulled at position 91 to be installed.In the present embodiment, drawstring 92 is connected to four angles of cladding glass 9 simultaneously, guarantees curtain wall glass
9 uniform stressed of glass improves the stationarity in 9 drawing process of cladding glass, and construction personnel is along the position to be installed for being directed toward cladding glass 9
Set 91 direction apply pulling force (cloth set direction of the direction of pulling force perpendicular to position 91 to be installed), i.e., to the left apply pulling force (with
Direction in Fig. 2 to the left is consistent);Specifically, including four ropes 93 at four angles for being connected to cladding glass 9, four
Rope 93 is connected to drawstring 92, applies active force to the left to drawstring 92, drives cladding glass 9 to be moved to by four ropes 93
At position 91 to be installed.In practice of construction, after the lifting to height to be installed of cladding glass 9, the installation of cladding glass 9 is being carried out
Before, construction personnel pulls drawstring 92 (on corresponding floor or the scaffold of respective heights) at the position 91 to be installed of cladding glass 9
So that cladding glass 9 is displaced at actually required installation site 91, the installation exercise of cladding glass 9 is then carried out again.
Further, in providing in the cladding glass step wait lift or also wrapped after cladding glass promotes step in place
Step is included, drawstring 92 is connected to four angles of cladding glass 9.
It can also be to be installed other conducive to the cladding glass installation self-control electric hoist hanger system in the utility model
Ornament materials is lifted, and cladding glass 9 is not limited only to.
A kind of beneficial effect of the utility model cladding glass installation self-control electric hoist hanger system includes:
1. electric block is mounted at basic knot by the way that hanging holder set to be mounted in girder construction
On structure, the dismounting of self-control electric hoist hanger system is installed convenient for cladding glass.
2. passing through the top that supporting beam is installed on to girder construction, it is ensured that support depth of beam is higher than curtain wall glass to be installed
The hoisting height of glass, and the electric block being installed in the foundation structure below girder construction is combined, realize the object for treating lifting
The lifting of (cladding glass).
Lifting object (curtain wall is treated 3. can fast implement by electric block, lifting rope and the pulley being installed in supporting beam
Glass) lifting, structure is simple, convenient for operation, reduce use cost.
4. electric block is mounted on the floor on roof using stationary fixture, convenient for tearing open for electric block
Dress;It is lifted by the way that electric block is configured clump weight, it can be achieved that stablizing, improves safety and stability when lifting.
Combine accompanying drawings and embodiments that the utility model is described in detail above, those skilled in the art can
Many variations example is made to the utility model according to the above description.Thus, certain details in embodiment should not be constituted to this reality
With novel restriction, the utility model will be using the range that the appended claims define as the protection scope of the utility model.