[go: up one dir, main page]

CN208121552U - A kind of reverse increasing layer construction underpinning structure in overpass pier base underground - Google Patents

A kind of reverse increasing layer construction underpinning structure in overpass pier base underground Download PDF

Info

Publication number
CN208121552U
CN208121552U CN201820120141.0U CN201820120141U CN208121552U CN 208121552 U CN208121552 U CN 208121552U CN 201820120141 U CN201820120141 U CN 201820120141U CN 208121552 U CN208121552 U CN 208121552U
Authority
CN
China
Prior art keywords
viaduct
underpinning
steel pipe
column
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820120141.0U
Other languages
Chinese (zh)
Inventor
孙沈鹏
谷志旺
龙毅华
戴森
陶海灵
张波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 4 Group Co Ltd
Original Assignee
Shanghai Construction No 4 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 4 Group Co Ltd filed Critical Shanghai Construction No 4 Group Co Ltd
Priority to CN201820120141.0U priority Critical patent/CN208121552U/en
Application granted granted Critical
Publication of CN208121552U publication Critical patent/CN208121552U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型提供一种高架桥柱墩基础地下逆向增层施工托换结构,包括:设置于高架桥下方地下空间的围护结构和工程桩,设置于工程桩上的地下室顶板梁,设置于地下室顶板梁上的托换临时结构,以及安装于托换临时结构与高架桥梁之间的用于主动托换高架桥梁的液压千斤顶,液压千斤顶的顶部伸出端与高架桥梁固定连接,托换临时结构包括两对平行设置的支撑梁以及用于支撑支撑梁的若干支撑柱,所述支撑柱的下端与地下室顶板梁固定连接,所述支撑梁与所述高架桥的纵向平行,每对支撑梁设置于高架桥柱的两侧。通过液压千斤顶不断补偿高架桥梁托换受荷沉降变形,消除高架桥梁在地下空间开发施工中的不均匀变形沉降,保证高架桥梁地下增层施工时能正常运营下。

The utility model provides an underpinning structure for reverse layer-increasing underground construction of viaduct pier foundations, comprising: an enclosure structure and engineering piles arranged in the underground space below the viaduct, a basement roof beam arranged on the engineering piles, and a basement roof beam arranged on the engineering piles. The underpinning temporary structure above, and the hydraulic jack installed between the underpinning temporary structure and the viaduct for actively underpinning the viaduct, the top extension of the hydraulic jack is fixedly connected with the viaduct, and the underpinning temporary structure includes two For the support beams arranged in parallel and several support columns for supporting the support beams, the lower ends of the support columns are fixedly connected to the basement roof beams, the support beams are parallel to the longitudinal direction of the viaduct, and each pair of support beams is arranged on the viaduct column on both sides. The hydraulic jack continuously compensates the underpinning and load settlement deformation of the viaduct, eliminates the uneven deformation and settlement of the viaduct during the development and construction of the underground space, and ensures the normal operation of the viaduct during the construction of underground layer addition.

Description

一种高架桥柱墩基础地下逆向增层施工托换结构An underpinning structure for underground reverse layer-adding construction of viaduct pier foundation

技术领域technical field

本实用新型涉及一种高架柱墩基础地下增层方法,尤其适用于在运营状态下的高架柱墩基础地下增层方法。The utility model relates to an underground layer-increasing method for elevated column pier foundations, which is especially suitable for the underground layer-increasing method for elevated column pier foundations in an operating state.

背景技术Background technique

目前,开发与利用城市地下空间已成为城市更新发展新的方向,在新建工程项目地下空间面向大面积、深层次、全面化发展的同时,既有建筑地下空间的缺位逐渐成为影响城市发展的短板。At present, the development and utilization of urban underground space has become a new direction for urban renewal and development. While the underground space of new construction projects is facing large-scale, deep-level, and comprehensive development, the absence of underground space in existing buildings has gradually become a problem that affects urban development. short board.

例如,许多重要交通枢纽站、大型场馆以及住宅小区出现停车难等问题,这些问题已日益凸显,严重影响城市的可持续发展。For example, many important transportation hubs, large venues and residential areas have problems such as parking difficulties. These problems have become increasingly prominent and have seriously affected the sustainable development of cities.

在地下空间开发与利用过程中,往往由于规划需求,道路条件限制,一些地下空间开发边线横穿运营高架桥的投影线,将涉及到在运营状态高架桥下进行地下空间开发,面临着运营状态下高架柱墩基础地下增层施工的高风险难题。In the process of underground space development and utilization, often due to planning requirements and road conditions, some underground space development sidelines cross the projection line of the viaduct in operation, which will involve the development of underground space under the viaduct in the operating state. High-risk problems in the construction of underground layer additions to pier foundations.

实用新型内容Utility model content

本实用新型的目的在于提供一种高架桥柱墩基础地下逆向增层施工托换结构,解决高架桥柱墩基础地下逆向增层过程中高架桥梁的沉降变形影响高架桥安全运营的问题,同时解决了高架桥在新开发的地下室顶板上复建永久高架桥柱的沉降变形。The purpose of the utility model is to provide an underpinning structure for the underground reverse layer increase construction of the viaduct pier foundation, which solves the problem that the settlement deformation of the viaduct affects the safe operation of the viaduct in the process of underground reverse layer increase of the viaduct pier foundation, and at the same time solves the problem of Settlement deformation of reconstructed permanent viaduct columns on newly developed basement roof.

为解决上述技术问题,本实用新型提供如下技术方案:In order to solve the above technical problems, the utility model provides the following technical solutions:

一种高架桥柱墩基础地下逆向增层施工托换结构,包括:An underpinning structure for underground reverse layer-adding construction of viaduct column pier foundations, comprising:

设置于高架桥下方地下空间的围护结构和工程桩,设置于工程桩上的地下室顶板梁,设置于地下室顶板梁上的托换临时结构,以及安装于托换临时结构以及高架桥梁之间的用于主动托换高架桥梁的液压千斤顶,所述液压千斤顶的顶部伸出端与高架桥梁固定连接,所述托换临时结构包括两对平行设置的支撑梁以及用于支撑所述支撑梁的若干支撑柱,所述支撑柱的下端与地下室顶板梁固定连接,所述支撑梁与所述高架桥的纵向平行,每对支撑梁设置于高架桥柱的两侧。The enclosure structure and engineering piles installed in the underground space under the viaduct, the basement roof beams installed on the engineering piles, the underpinning temporary structures installed on the basement roof beams, and the underpinning temporary structures installed between the viaducts It is used to actively underpin the hydraulic jack of the elevated bridge, the top extension of the hydraulic jack is fixedly connected with the elevated bridge, and the underpinning temporary structure includes two pairs of supporting beams arranged in parallel and several supports for supporting the supporting beams The lower end of the support column is fixedly connected to the basement roof beam, the support beam is parallel to the longitudinal direction of the viaduct, and each pair of support beams is arranged on both sides of the viaduct column.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,在地下室顶板梁上安装支撑柱位置预埋用于安装支撑柱的埋件,所述支撑柱的下端与地下室顶板梁上的埋件相连接。Preferably, in the underpinning structure of the above-mentioned viaduct column pier foundation underground reverse layer-adding construction, the position of the supporting column installed on the basement roof beam is pre-embedded for installing the embedded part of the supporting column, and the lower end of the supporting column is connected to the basement roof beam The embedded parts on it are connected.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,在高架桥梁和支撑梁之间对应每个液压千斤顶安装限位装置,所述限位装置能够限制高架桥梁与支撑梁之间相对水平方向位移,所述限位装置分布于液压千斤顶四周。Preferably, in the above-mentioned viaduct pier foundation underground reverse layer construction underpinning structure, a limit device is installed between the viaduct and the supporting beam corresponding to each hydraulic jack, and the limiting device can limit the viaduct and the supporting beam. The relative horizontal displacement between them, the limit device is distributed around the hydraulic jack.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述限位装置包括预埋板以及安装于预埋板下方的上限位件,所述下限位件固定设置于所述支撑梁上,所述下限位件形成供上限位件伸入的凹槽,所述上限位件的高度小于所述凹槽的深度,所述预埋板能够搁置于所述下限位件上。Preferably, in the underpinning structure of the above-mentioned underground reverse layer-adding construction of viaduct pier foundation, the limiting device includes a pre-embedded plate and an upper limiting member installed under the embedded plate, and the lower limiting member is fixedly arranged on the On the support beam, the lower limiter forms a groove for the upper limiter to extend into, the height of the upper limiter is smaller than the depth of the groove, and the embedded plate can rest on the lower limiter .

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述下限位件包括四块均匀分布于所述液压千斤顶四周的直角梯形楔形块,所述上限位件包括四块直角梯形楔形块,所述上限位件的直角梯形楔形块的直角腰与下限位件的直角梯形楔形块的直角腰相对设置。Preferably, in the underpinning structure of the above-mentioned underground reverse layer-adding construction of viaduct pier foundations, the lower limiting member includes four right-angled trapezoidal wedge blocks evenly distributed around the hydraulic jack, and the upper limiting member includes four A right-angled trapezoidal wedge, the right-angled waist of the right-angled trapezoidal wedge of the upper limiter is opposite to the right-angled waist of the right-angled trapezoidal wedge of the lower limiter.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述支撑柱与高架桥柱沿高架桥的纵向错开设置。Preferably, in the underpinning structure of the underground reverse layer-adding construction of the viaduct column pier foundation, the support column and the viaduct column are arranged staggered along the longitudinal direction of the viaduct.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,液压千斤顶为双作用千斤顶。Preferably, in the underpinning structure of the above-mentioned viaduct column pier foundation underground reverse layer-adding construction, the hydraulic jack is a double-acting jack.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,在支撑梁与地下室顶板梁之间设置若干对所述液压钢管撑,每对液压钢管撑位于对应高架桥柱的两侧,每对液压钢管撑与对应的高架桥柱沿着高架桥的横向设置。Preferably, in the above-mentioned reverse construction underpinning structure of the viaduct column pier foundation, several pairs of hydraulic steel pipe braces are arranged between the support beam and the basement roof beam, and each pair of hydraulic steel pipe braces is located on both sides of the corresponding viaduct column , each pair of hydraulic steel pipe braces and the corresponding viaduct columns are set along the transverse direction of the viaduct.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述液压钢管撑包括由上至下依次设置的钢管固定端、钢管撑筒体、两台液压千斤顶以及钢管伸缩端,所述两台液压千斤顶的一端均连接所述钢管撑筒体,另一端均连接所述钢管伸缩端,所述钢管伸缩端与地下室顶板梁固定连接,所述钢管固定端与支撑梁固定连接。Preferably, in the underpinning structure of the above-mentioned underground reverse layer-adding construction of viaduct pier foundation, the hydraulic steel pipe support includes a steel pipe fixed end, a steel pipe support cylinder, two hydraulic jacks and a steel pipe telescopic end arranged in sequence from top to bottom , one end of the two hydraulic jacks is connected to the steel pipe support cylinder, and the other end is connected to the telescopic end of the steel pipe, the telescopic end of the steel pipe is fixedly connected to the basement roof beam, and the fixed end of the steel pipe is fixedly connected to the support beam .

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述围护结构包括围护桩以及设置于围护桩外侧的止水帷幕。Preferably, in the underpinning structure of the above-mentioned underground reverse build-up construction of the viaduct pier foundation, the enclosure structure includes enclosure piles and a water-stop curtain arranged outside the enclosure piles.

由以上公开的技术方案可知,与现有技术相比,本实用新型的有益效果如下:It can be seen from the technical solutions disclosed above that, compared with the prior art, the beneficial effects of the utility model are as follows:

本实用新型提供的高架桥柱墩基础地下逆向增层施工托换结构,通过设置托换临时结构以及液压千斤顶,液压千斤顶安装于托换临时结构以及高架桥梁之间用于主动托换高架桥梁,所述液压千斤顶的顶部伸出端与高架桥梁固定连接,所述托换临时结构包括两对平行设置的支撑梁以及用于支撑所述支撑梁的若干支撑柱,所述支撑柱的下端与地下室顶板梁固定连接,所述支撑梁与所述高架桥的纵向平行,每对支撑梁设置于高架桥柱的两侧,在施工过程中通过液压千斤顶不断补偿高架桥梁托换受荷沉降变形,消除高架桥梁在地下空间开发施工中的不均匀变形沉降,保证高架桥梁地下增层施工时能够正常运营下。此外,此次托换增层利用新开发的地下空间结构作为临时托换体系的基础,节约了大量的托换桩基。再者,采用此种方式托换,能够利用新开发的地下室顶板作为高架桥柱的永久基础,减少了高架桥柱的桩基及承台,同时能够使地下空间轴网柱距更大,使用空间更宽广。The utility model provides the underpinning structure for the underground reverse layer-adding construction of the viaduct pier foundation. By setting the underpinning temporary structure and the hydraulic jack, the hydraulic jack is installed between the underpinning temporary structure and the viaduct for active underpinning of the viaduct. The top protruding end of the hydraulic jack is fixedly connected with the viaduct, and the underpinning temporary structure includes two pairs of supporting beams arranged in parallel and several supporting columns for supporting the supporting beams, and the lower ends of the supporting columns are connected to the basement roof. The beams are fixedly connected, the support beams are parallel to the longitudinal direction of the viaduct, and each pair of support beams is arranged on both sides of the viaduct columns. During the construction process, the hydraulic jacks are used to continuously compensate the settlement deformation of the viaduct underpinning under load, and eliminate the underpinning of the viaduct. The uneven deformation and settlement in the development and construction of the underground space can ensure the normal operation of the viaduct during the construction of the underground layer addition. In addition, the newly developed underground space structure was used as the basis of the temporary underpinning system for this underpinning and layer increase, which saved a lot of underpinning pile foundations. Furthermore, by using this method of underpinning, the newly developed basement roof can be used as the permanent foundation of the viaduct column, reducing the pile foundation and cap of the viaduct column, and at the same time, it can make the column distance of the axis network in the underground space larger and the usable space more efficient. broad.

本实用新型提供的高架桥柱墩基础地下逆向增层施工托换结构,通过在支撑梁与地下室顶板梁之间设置若干对所述液压钢管撑,每对液压钢管撑位于对应高架桥柱的两侧,每对液压钢管撑与对应的高架桥柱沿着高架桥的横向设置,在液压钢管撑在高架桥柱复建之前,利用液压钢管撑替换托换临时结构对高架桥梁进行托换支撑,液压钢管撑的伸缩作用补偿高架荷载作用于地下室顶板梁后的下挠变形引起的高架桥沉降变形,使高架桥保持在安全沉降变形范围内,接着在复建高架桥柱。由于地下室顶板梁对每对液压钢管撑的支撑位置尽可能靠近地下室顶板梁对复建后的高架桥柱的支撑位置,因此,复建后高架桥荷载作用在地下室顶板梁后下挠变形导致的高架桥沉降变形较小,从而有效减少地下增层施工后高架桥梁的沉降位移,保证高架桥梁的正常运营。The utility model provides an underpinning structure for reverse layer-adding underground construction of viaduct pier foundations. By setting several pairs of hydraulic steel pipe braces between the support beam and the basement roof beam, each pair of hydraulic steel pipe braces is located on both sides of the corresponding viaduct column. Each pair of hydraulic steel pipe braces and the corresponding viaduct columns are arranged along the transverse direction of the viaduct. Before the hydraulic steel pipe braces are rebuilt on the viaduct columns, the hydraulic steel pipe braces are used to replace the underpinning temporary structure to support the viaduct bridge. The expansion and contraction of the hydraulic steel pipe braces The action compensates the viaduct settlement deformation caused by the deflection deformation after the viaduct load acts on the basement roof beam, so that the viaduct remains within the safe settlement deformation range, and then rebuilds the viaduct column. Since the support position of the basement roof girder for each pair of hydraulic steel pipe braces is as close as possible to the support position of the basement roof girder for the reconstructed viaduct columns, the settlement of the viaduct caused by the deflection deformation of the viaduct load after the reconstruction is applied to the basement roof girder The deformation is small, thereby effectively reducing the settlement displacement of the viaduct after the construction of the underground layer addition, and ensuring the normal operation of the viaduct.

附图说明Description of drawings

图1为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-1时的平面示意图;Fig. 1 is the schematic plan view of the underpinning structure in step 1-1 of the underpinning construction of the viaduct pier foundation underground in an embodiment of the utility model;

图2为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-1时的纵立面示意图;Fig. 2 is a schematic diagram of the longitudinal elevation of the underpinning structure of the viaduct pier foundation underground reverse layer increase construction in step 1-1 according to an embodiment of the present invention;

图3为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-1时的横立面示意图;Fig. 3 is a schematic diagram of the horizontal elevation of the underpinning structure in step 1-1 of the underpinning construction of the viaduct pier foundation in an embodiment of the present invention;

图4为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-2时的纵立面示意图;Fig. 4 is a schematic diagram of the longitudinal elevation of the underpinning structure in steps 1-2 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图5为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-2时的横立面示意图;Fig. 5 is a schematic diagram of the horizontal elevation of the underpinning structure in steps 1-2 of the underpinning construction of the viaduct pier foundation in an embodiment of the present invention;

图6为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-4时的平面示意图;6 is a schematic plan view of the underpinning structure in steps 1-4 of the underpinning construction of the viaduct pier foundation in an embodiment of the present invention;

图7为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-4时的纵立面示意图;Fig. 7 is a schematic diagram of the vertical elevation of the underpinning structure of the viaduct pier foundation underground reverse layer increase construction in steps 1-4 according to an embodiment of the present invention;

图8为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-4时的横立面示意图;Fig. 8 is a schematic diagram of the horizontal elevation of the underpinning structure in steps 1-4 of the underpinning construction of the viaduct pier foundation in an embodiment of the present invention;

图9为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-5时的平面示意图;Fig. 9 is a schematic plan view of the underpinning structure in steps 1-5 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图10为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-5时的纵立面示意图;Fig. 10 is a schematic diagram of the vertical elevation of the underpinning structure of the viaduct pier foundation underground reverse layer increase construction in steps 1-5 according to an embodiment of the present invention;

图11为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-5时的横立面示意图;Fig. 11 is a schematic diagram of the horizontal elevation of the underpinning structure in steps 1-5 of the underpinning construction of the viaduct pier foundation in an embodiment of the present invention;

图12为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-6时的纵立面示意图即高架桥柱墩基础地下逆向增层施工托换结构的结构示意图;Fig. 12 is a schematic diagram of the longitudinal elevation of the underpinning structure of the viaduct pier foundation underground reverse layer increase construction in steps 1-6, that is, the structural representation of the viaduct column pier foundation underground reverse layer increase construction underpinning structure;

图13为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤1-6时的横立面示意图;Fig. 13 is a schematic diagram of the horizontal elevation of the underpinning structure in steps 1-6 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图14为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤2-1时的纵立面示意图;Fig. 14 is a schematic diagram of the longitudinal elevation of the underpinning structure in step 2-1 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图15为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤2-1时的横立面示意图;Fig. 15 is a schematic diagram of the horizontal elevation of the underpinning structure in step 2-1 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图16为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤3-1时的纵立面示意图;Fig. 16 is a schematic diagram of the longitudinal elevation of the underpinning structure in step 3-1 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图17为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤3-1时的横立面示意图;Fig. 17 is a schematic diagram of the horizontal elevation of the underpinning structure in step 3-1 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图18为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤3-2时的纵立面示意图;Fig. 18 is a schematic diagram of the longitudinal elevation of the underpinning structure in step 3-2 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图19为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤3-2时的横立面示意图;Fig. 19 is a schematic diagram of the horizontal elevation of the underpinning structure in step 3-2 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图20本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤3-3时的纵立面示意图;Fig. 20 is a schematic diagram of the longitudinal elevation of the underpinning structure in step 3-3 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图21为本实用新型一实施例的高架桥柱墩基础地下逆向增层施工托换结构在步骤3-3时的横立面示意图;Fig. 21 is a schematic diagram of the horizontal elevation of the underpinning structure in step 3-3 of the underpinning construction of the viaduct column pier foundation in an embodiment of the present invention;

图22为本实用新型一实施例中限位装置的结构示意图;Fig. 22 is a schematic structural view of a limiting device in an embodiment of the present invention;

图23为图22的A-A剖视示意图;Fig. 23 is a schematic cross-sectional view of A-A of Fig. 22;

图中:1-高架桥柱、2-高架桥梁、3-工程桩、4-地下室顶板梁、5-液压千斤顶、6-支撑梁、7-支撑柱、8-液压钢管撑、9-围护桩、10-止水帷幕、11-限位装置、111-预埋板、112-上限位件、113-下限位件、12-地下室地下一层结构梁板、13-高架柱墩。In the figure: 1- viaduct column, 2- viaduct bridge, 3- engineering pile, 4- basement roof beam, 5- hydraulic jack, 6- support beam, 7- support column, 8- hydraulic steel pipe support, 9- enclosure pile , 10-waterproof curtain, 11-limiting device, 111-embedded plate, 112-upper limit piece, 113-lower limit piece, 12-basement floor structure beam plate, 13-elevated column pier.

具体实施方式Detailed ways

以下结合附图和具体实施例对本实用新型作进一步详细说明。根据下面的说明和权利要求书,本实用新型的优点和特征将更清楚。以下将由所列举之实施例结合附图,详细说明本实用新型的技术内容及特征。需另外说明的是,附图均采用非常简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本实用新型实施例的目的。为叙述方便,下文中所述的“上”、“下”与附图的上、下的方向一致,但这不能成为本实用新型技术方案的限制。Below in conjunction with accompanying drawing and specific embodiment the utility model is described in further detail. According to the following description and claims, the advantages and features of the utility model will be more clear. The technical contents and features of the present utility model will be described in detail below by referring to the enumerated embodiments in conjunction with the accompanying drawings. It should be further noted that all the drawings are in very simplified form and use inaccurate scales, which are only used to facilitate and clearly assist the purpose of illustrating the embodiments of the present utility model. For the convenience of description, the "up" and "down" described below are consistent with the directions of up and down in the drawings, but this cannot be a limitation of the technical solution of the present utility model.

请参阅图16,并请结合参阅图1至15以及图17至23,本实施例提供了一种高架桥柱墩基础地下逆向增层施工托换结构,用于高架桥柱墩基础地下逆向增层施工。所述高架桥包括高架桥柱1以及由高架桥柱1支撑的高架桥梁2。所述高架桥柱墩基础地下逆向增层施工托换结构包括:设置于高架桥下方地下空间的围护结构和工程桩3,设置于工程桩上的地下室顶板梁4,设置于地下室顶板梁上的托换临时结构,以及安装于托换临时结构以及高架桥梁2之间的用于主动托换高架桥梁2的液压千斤顶5,所述液压千斤顶的顶部伸出端与高架桥梁固定连接,所述托换临时结构包括两对平行设置的支撑梁6以及用于支撑所述支撑梁6的若干支撑柱7,所述支撑柱7的下端与地下室顶板梁4固定连接,所述支撑梁6与所述高架桥的纵向平行,每对支撑梁6设置于高架桥柱1的两侧。所述围护结构包括围护桩9以及设置于围护桩9外侧的止水帷幕10。Please refer to Figure 16, and please refer to Figures 1 to 15 and Figures 17 to 23 in combination. This embodiment provides an underpinning structure for underground reverse layer addition construction of viaduct column pier foundations, which is used for underground reverse layer addition construction of viaduct column pier foundations. . The viaduct includes a viaduct column 1 and a viaduct 2 supported by the viaduct column 1 . The underpinning structure of the underground reverse layer-adding construction of the viaduct pier foundation includes: an enclosure structure and engineering piles 3 arranged in the underground space below the viaduct, a basement roof beam 4 arranged on the engineering pile, and a supporting structure arranged on the basement roof beam. Replace the temporary structure, and install the hydraulic jack 5 for actively underpinning the viaduct 2 between the underpinning temporary structure and the viaduct 2, the top extension of the hydraulic jack is fixedly connected with the viaduct, and the underpinning The temporary structure includes two pairs of supporting beams 6 arranged in parallel and several supporting columns 7 for supporting the supporting beams 6, the lower ends of the supporting columns 7 are fixedly connected with the basement roof beam 4, and the supporting beams 6 are connected with the viaduct Each pair of supporting beams 6 is arranged on both sides of the viaduct column 1. The enclosure structure includes an enclosure pile 9 and a water-stop curtain 10 arranged outside the enclosure pile 9 .

本实用新型提供的高架桥柱墩基础地下逆向增层施工托换结构,通过设置托换临时结构以及液压千斤顶5,液压千斤顶5安装于托换临时结构以及高架桥梁2之间用于主动托换高架桥梁2,所述液压千斤顶5的顶部伸出端与高架桥梁2固定连接,在施工过程中通过液压千斤顶不断补偿高架桥梁2托换受荷沉降变形,消除高架桥梁2在地下空间开发施工中的不均匀变形沉降,保证高架桥梁2地下增层施工时能够正常运营下。此外,此次托换增层利用新开发的地下空间结构作为临时托换体系的基础,节约了大量的托换桩基。再者,采用此种方式托换,能够利用新开发的地下室顶板作为高架桥柱1的永久基础,减少了高架桥柱1的桩基及承台,同时能够使地下空间轴网柱距更大,使用空间更宽广。The utility model provides the underpinning structure for the underpinning construction of the viaduct column pier foundation in the reverse direction, by setting the underpinning temporary structure and the hydraulic jack 5, and the hydraulic jack 5 is installed between the underpinning temporary structure and the viaduct 2 for actively underpinning the viaduct Beam 2, the top protruding end of the hydraulic jack 5 is fixedly connected to the viaduct 2, and the hydraulic jack is used to continuously compensate the viaduct 2 underpinning and settlement deformation under load during the construction process, so as to eliminate the viaduct 2 during the development and construction of the underground space. Uneven deformation and settlement ensure that the viaduct 2 can operate normally during the construction of underground layer addition. In addition, the newly developed underground space structure was used as the basis of the temporary underpinning system for this underpinning and layer increase, which saved a lot of underpinning pile foundations. Furthermore, by using this method of underpinning, the newly developed basement roof can be used as the permanent foundation of the viaduct column 1, reducing the pile foundation and cap of the viaduct column 1, and at the same time, the column spacing of the grid in the underground space can be made larger. The space is wider.

为了提高支撑柱与地下室顶板梁之间的连接强度,优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,在地下室顶板梁4上安装支撑柱位置预埋用于安装支撑柱7的埋件,所述支撑柱7的下端与地下室顶板梁4上的埋件相连接。In order to improve the connection strength between the support column and the basement roof beam, preferably, in the above-mentioned viaduct column pier foundation underground reverse layer construction underpinning structure, the position of the support column installed on the basement roof beam 4 is pre-buried for installation support The embedded part of the column 7, the lower end of the supporting column 7 is connected with the embedded part on the roof beam 4 of the basement.

为了保证高架桥梁2在地下增层施工中的稳定性,保证其正常运营,优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,在高架桥梁2和支撑梁6之间对应每个液压千斤顶5安装限位装置11,所述限位装置11能够限制高架桥梁2与支撑梁6之间相对水平方向位移,所述限位装置11分布于液压千斤顶5四周。In order to ensure the stability of the viaduct 2 in the construction of the underground layer increase and ensure its normal operation, preferably, in the above-mentioned underpinning structure for the underground reverse layer increase construction of the viaduct pier foundation, between the viaduct 2 and the support beam 6 A limit device 11 is installed corresponding to each hydraulic jack 5 , and the limit device 11 can limit the relative horizontal displacement between the viaduct 2 and the support beam 6 , and the limit device 11 is distributed around the hydraulic jack 5 .

优选的,所述限位装置11包括预埋板111以及安装于预埋板111下方的上限位件112,所述下限位件113固定设置于所述支撑梁6上,所述下限位件113形成供上限位件112伸入的凹槽,所述上限位件112的高度小于所述凹槽的深度,所述预埋板111能够搁置于所述下限位件113上。所述上限位件112始终位于所述下限位件113的凹槽,从而限制高架桥梁2相对支撑梁6进行水平方向位移。Preferably, the limiting device 11 includes an embedded board 111 and an upper limiting member 112 installed under the embedded board 111, the lower limiting member 113 is fixedly arranged on the support beam 6, and the lower limiting member 113 A groove is formed for the upper limit member 112 to protrude into. The height of the upper limit member 112 is smaller than the depth of the groove, and the embedded plate 111 can rest on the lower limit member 113 . The upper limiter 112 is always located in the groove of the lower limiter 113 , so as to limit the horizontal displacement of the viaduct 2 relative to the support beam 6 .

本实施例中,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述下限位件113包括四块均匀分布于所述液压千斤顶5四周的直角梯形楔形块,所述上限位件112包括四块直角梯形楔形块,所述上限位件112的直角梯形楔形块的直角腰与下限位件113的直角梯形楔形块的直角腰相对设置。所述上限位件112的直角梯形楔形块的直角腰只能相对下限位件113的直角梯形楔形块的直角腰上下移动,使得与上限位件112固定连接的高架桥梁2无法相对与下限位件113固定连接的支撑梁6进行水平移动和倾斜移动,从而保证高架桥梁2正常运营。In this embodiment, in the underpinning structure of the above-mentioned underground reverse layer-adding construction of viaduct pier foundation, the lower limit member 113 includes four right-angled trapezoidal wedge blocks evenly distributed around the hydraulic jack 5, and the upper limit The piece 112 includes four right-angled trapezoidal wedges, and the right-angled waist of the right-angled trapezoidal wedge of the upper limiter 112 is opposite to the right-angled waist of the right-angled trapezoidal wedge of the lower limiter 113 . The right-angled waist of the right-angled trapezoidal wedge of the upper limiter 112 can only move up and down relative to the right-angled trapezoidal wedge of the lower limiter 113, so that the viaduct 2 fixedly connected with the upper limiter 112 cannot be opposite to the lower limiter. 113 The fixedly connected support beam 6 moves horizontally and tilts, so as to ensure the normal operation of the viaduct 2 .

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述支撑柱7与高架桥柱1沿高架桥的纵向错开设置。Preferably, in the underpinning structure of the above-mentioned viaduct column pier foundation underground reverse layer-adding construction, the support column 7 and the viaduct column 1 are arranged staggered along the longitudinal direction of the viaduct.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,液压千斤顶5为双作用千斤顶。Preferably, in the underpinning structure of the above-mentioned viaduct column pier foundation underground reverse layer-adding construction, the hydraulic jack 5 is a double-acting jack.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,在支撑梁6与地下室顶板梁4之间设置若干对所述液压钢管撑8,每对液压钢管撑8位于对应高架桥柱1的两侧,每对液压钢管撑8与对应的高架桥柱1沿着高架桥的横向设置。通过在支撑梁6与地下室顶板梁4之间设置若干对所述液压钢管撑8,每对液压钢管撑8位于对应高架桥柱1的两侧,每对液压钢管撑与对应的高架桥柱1沿着高架桥的横向设置,在液压钢管撑8在高架桥柱1复建之前,利用液压钢管撑8替换托换临时结构对高架桥梁2进行托换支撑,液压钢管撑8的伸缩作用保证高架桥梁2位于预先设计的高度,使得地下室顶板预先进行形变,接着在复建高架桥柱1。由于地下室顶板梁4对每对液压钢管撑8的支撑位置尽可能靠近地下室顶板梁4对复建后的高架桥柱1的支撑位置,因此,复建后高架桥荷载作用在地下室顶板梁后下挠变形导致的高架桥沉降变形较小,从而有效减少地下增层施工后高架桥梁2的沉降位移,保证高架桥梁2的正常运营。Preferably, in the above-mentioned viaduct pier foundation underground reverse layer construction underpinning structure, several pairs of hydraulic steel pipe braces 8 are arranged between the support beam 6 and the basement roof beam 4, and each pair of hydraulic steel pipe braces 8 is located on the corresponding viaduct bridge. On both sides of the column 1, each pair of hydraulic steel pipe braces 8 and the corresponding viaduct column 1 are arranged along the transverse direction of the viaduct. By setting several pairs of hydraulic steel pipe braces 8 between the support beam 6 and the basement roof beam 4, each pair of hydraulic steel pipe braces 8 is located on both sides of the corresponding viaduct column 1, and each pair of hydraulic steel pipe braces and the corresponding viaduct column 1 are along the For the horizontal setting of the viaduct, before the hydraulic steel pipe brace 8 is rebuilt on the viaduct column 1, the hydraulic steel pipe brace 8 is used to replace the underpinning temporary structure to support the viaduct 2, and the expansion and contraction of the hydraulic steel pipe brace 8 ensures that the viaduct 2 is located The height of the design allows the basement roof to be deformed in advance, and then the viaduct column 1 is reconstructed. Since the support position of the basement roof beam 4 for each pair of hydraulic steel pipe braces 8 is as close as possible to the support position of the basement roof beam 4 for the reconstructed viaduct column 1, therefore, the viaduct load acts on the rear deflection deformation of the basement roof beam after reconstruction The resulting settlement and deformation of the viaduct is small, thereby effectively reducing the settlement displacement of the viaduct 2 after the construction of the underground layer addition, and ensuring the normal operation of the viaduct 2 .

具体的,在本实施例中的高架桥柱墩基础地下逆向增层施工托换结构中,所述液压钢管撑包括由上至下依次设置的钢管固定端、钢管撑筒体、两台液压千斤顶以及钢管伸缩端,所述两台液压千斤顶的一端均连接所述钢管撑筒体,另一端均连接所述钢管伸缩端,所述钢管伸缩端与地下室顶板梁固定连接,所述钢管固定端与支撑梁固定连接。Specifically, in the underpinning structure of the underground reverse layer-adding construction of the viaduct pier foundation in this embodiment, the hydraulic steel pipe brace includes a steel pipe fixed end, a steel pipe support cylinder, two hydraulic jacks and Steel pipe telescopic end, one end of the two hydraulic jacks is connected to the steel pipe support cylinder, the other end is connected to the steel pipe telescopic end, the steel pipe telescopic end is fixedly connected to the basement roof beam, and the steel pipe fixed end is connected to the support The beam is fixedly connected.

请参阅图1至图23,本实施例公开了一种高架桥柱墩基础地下逆向增层施工托换结构的使用方法,用于高架桥柱墩基础地下逆向增层施工,所述高架桥柱墩基础地下逆向增层施工托换结构包括:Please refer to Figures 1 to 23. This embodiment discloses a method for using an underpinning structure for underground reverse layer-adding construction of viaduct column pier foundations, which is used for underground reverse layer-addition construction of viaduct column pier foundations. The viaduct column pier foundations are underground The underpinning structure of reverse build-up construction includes:

步骤1,在高架下方施工地下空间围护结构、工程桩3和地下室顶板梁4,在地下室顶板梁4上架设托换临时结构,在托换临时结构上安装液压千斤顶5,主动托换高架桥梁2,所述液压千斤顶5的顶部伸出端与高架桥梁2固定连接,所述托换临时结构包括两对平行设置的支撑梁6以及用于支撑所述支撑梁6的若干支撑柱7,所述支撑柱7的下端与地下室顶板梁4固定连接,所述支撑梁6与所述高架桥的纵向平行,每对支撑梁6设置于高架桥柱1的两侧。Step 1, construct the underground space enclosure structure, engineering piles 3 and basement roof beam 4 under the elevated, erect a temporary underpinning structure on the basement roof beam 4, install a hydraulic jack 5 on the underpinning temporary structure, and actively underpin the elevated bridge 2. The top protruding end of the hydraulic jack 5 is fixedly connected to the viaduct 2, and the underpinning temporary structure includes two pairs of supporting beams 6 arranged in parallel and several supporting columns 7 for supporting the supporting beams 6. The lower ends of the support columns 7 are fixedly connected to the basement roof beams 4, the support beams 6 are parallel to the longitudinal direction of the viaduct, and each pair of support beams 6 is arranged on both sides of the viaduct columns 1 .

步骤2,高架桥梁2托换完成后,开挖高架桥柱1基础,逆作开挖施工地下室,完成地下室主体结构,并补缺地下室顶板梁4,形成地下室顶板,施工过程中通过液压千斤顶5顶升和回油收缩作用进行高架桥梁2变形应力的调整,确保高架桥梁2在地下空间开发阶段处于安全运营状态。Step 2: After the underpinning of the viaduct 2 is completed, excavate the foundation of the viaduct column 1, excavate the basement in reverse, complete the main structure of the basement, and fill in the basement roof beam 4 to form the basement roof. During the construction process, use the hydraulic jack 5 to lift Adjust the deformation stress of the viaduct 2 by using oil return shrinkage to ensure that the viaduct 2 is in a safe operation state during the underground space development stage.

步骤3,在地下室顶板梁4与支撑梁6之间设置液压钢管撑8,液压钢管撑8的顶部伸出端与支撑梁6上靠近对应高架柱1的部位固定连接,通过液压钢管撑8对高架桥梁2进行二次托换,在新开发地下室顶板上复建高架柱1,消除高架桥梁2在地下室顶板上复建永久高架桥柱1引起的沉降变形。Step 3, install hydraulic steel pipe braces 8 between the basement roof beam 4 and the support beam 6, the top extension end of the hydraulic steel pipe brace 8 is fixedly connected to the part of the support beam 6 close to the corresponding elevated column 1, and the 8 pairs of hydraulic steel pipe braces The viaduct 2 is underpinned twice, and the viaduct column 1 is rebuilt on the roof of the newly developed basement to eliminate the settlement deformation caused by the viaduct 2 rebuilding the permanent viaduct column 1 on the basement roof.

本实用新型提供的高架桥柱墩基础地下逆向增层施工托换结构,对高架桥梁2采取两次主动托换,在施工过程中不断补偿高架桥梁2托换受荷沉降变形,消除高架桥梁2在地下空间开发施工和复建高架桥柱1永久使用中的不均匀变形沉降,保证高架桥梁2正常运营下的安全和稳定。此外,此次托换增层利用新开发的地下空间结构作为临时托换体系的基础,节约了大量的托换桩基。再者,采用此种方式托换,可以利用新开发的地下室顶板作为高架桥柱1的永久基础,减少了高架桥柱1的桩基及承台,同时能够使地下空间轴网柱距更大,使用空间更宽广。The utility model provides the underpinning structure for the underground reverse layer-adding construction of the viaduct pier foundation. The viaduct 2 is actively underpinned twice. Underground space development and construction and reconstruction of the uneven deformation and settlement of the viaduct column 1 in permanent use ensure the safety and stability of the viaduct 2 under normal operation. In addition, the newly developed underground space structure was used as the basis of the temporary underpinning system for this underpinning and layer increase, which saved a lot of underpinning pile foundations. Furthermore, with this method of underpinning, the newly developed basement roof can be used as the permanent foundation of the viaduct column 1, which reduces the pile foundation and cap of the viaduct column 1, and at the same time can make the column spacing of the underground space grid larger, and the use of The space is wider.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述步骤1具体包括:Preferably, in the above-mentioned viaduct column pier foundation underground reverse layer build-up construction underpinning structure, the step 1 specifically includes:

步骤1-1,在高架下方施工地下空间围护结构以及工程桩3,所述围护结构包括围护桩9以及设置于围护桩9外侧的止水帷幕10。Step 1-1, constructing an underground space enclosure structure and engineering piles 3 under the elevated, the enclosure structure includes enclosure piles 9 and water-stop curtains 10 arranged outside the enclosure piles 9 .

步骤1-2,开挖地下空间首皮土至高架柱墩13底标高位置。Step 1-2, excavate the first soil in the underground space to the elevation of the bottom of the elevated pier 13.

步骤1-3,以工程桩3及围护桩9为支撑柱,施工地下室顶板梁4,地下室顶板梁4与高架桥柱1相碰部位的梁板空缺,并预留插筋后期补缺,在浇筑地下室顶板梁4时,在地下室顶板梁4上安装支撑柱7位置预埋用于安装支撑柱7的埋件。地下室顶板梁4与高架桥柱1相碰的部位空缺,以便于高架桥柱1的截断与复建。Step 1-3, use the engineering pile 3 and the enclosure pile 9 as the support column, construct the basement roof beam 4, the beam slab vacancy at the contact position between the basement roof beam 4 and the viaduct column 1, and reserve the ribs to fill in the vacancy in the later stage. When the basement roof beam 4 is installed, the embedded parts for installing the support column 7 are pre-embedded at the position of the support column 7 on the basement roof beam 4 . The position where the basement roof beam 4 collides with the viaduct column 1 is vacant, so as to facilitate the truncation and reconstruction of the viaduct column 1 .

步骤1-4,在地下室顶板梁4上架设托换临时结构,所述支撑柱7的下端与地下室顶板梁4上的埋件相连接,所述支撑柱7的顶部架设支撑梁6,支撑梁6与支撑柱7之间铰接或固结连接,使得所述支撑梁6与所述高架桥的纵向平行,每对支撑梁6设置于高架桥柱1的两侧。为了提高托换临时结构的承载能力,不但在浇筑地下室顶板梁4时预埋用于安装支撑柱7的埋件,而且将所述支撑柱7的下端浇筑于地下室顶板梁4内,以进一步增加所述支撑柱7与地下室顶板梁4之间的咬合力。Step 1-4, set up a temporary underpinning structure on the basement roof beam 4, the lower end of the support column 7 is connected with the embedded parts on the basement roof beam 4, and the support beam 6 is erected on the top of the support column 7, and the support beam 6 and the support column 7 are hinged or fixedly connected, so that the support beam 6 is parallel to the longitudinal direction of the viaduct, and each pair of support beams 6 is arranged on both sides of the viaduct column 1 . In order to improve the bearing capacity of the underpinning temporary structure, not only the embedded parts for installing the support column 7 are pre-embedded when pouring the basement roof beam 4, but also the lower end of the support column 7 is poured in the basement roof beam 4 to further increase The bite force between the support column 7 and the basement roof beam 4 .

步骤1-5,在高架桥梁2和支撑梁6之间安装限位装置11及液压千斤顶5,所述限位装置11能够限制高架桥梁2与支撑梁6之间相对水平方向位移,所述限位装置11分布于液压千斤顶5四周。Step 1-5, installing a limit device 11 and a hydraulic jack 5 between the viaduct 2 and the support beam 6, the limit device 11 can limit the relative horizontal displacement between the viaduct 2 and the support beam 6, and the limit Bit device 11 is distributed around hydraulic jack 5.

优选的,所述限位装置11包括预埋板111以及安装于预埋板111下方的上限位件112,所述下限位件113固定设置于所述支撑梁6上,所述下限位件113形成供上限位件112伸入的凹槽,所述上限位件112的高度小于所述凹槽的深度,所述预埋板111能够搁置于所述下限位件113上。所述上限位件112始终位于所述下限位件113的凹槽,从而限制高架桥梁2相对支撑梁6进行水平方向位移。Preferably, the limiting device 11 includes an embedded board 111 and an upper limiting member 112 installed under the embedded board 111, the lower limiting member 113 is fixedly arranged on the support beam 6, and the lower limiting member 113 A groove is formed for the upper limit member 112 to protrude into. The height of the upper limit member 112 is smaller than the depth of the groove, and the embedded plate 111 can rest on the lower limit member 113 . The upper limiter 112 is always located in the groove of the lower limiter 113 , so as to limit the horizontal displacement of the viaduct 2 relative to the support beam 6 .

本实施例中,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述下限位件113包括四块均匀分布于所述液压千斤顶5四周的直角梯形楔形块,所述上限位件112包括四块直角梯形楔形块,所述上限位件112的直角梯形楔形块的直角腰与下限位件113的直角梯形楔形块的直角腰相对设置。所述上限位件112的直角梯形楔形块的直角腰只能相对下限位件113的直角梯形楔形块的直角腰上下移动,使得与上限位件112固定连接的高架桥梁2无法相对与下限位件113固定连接的支撑梁6进行水平移动和倾斜移动,从而保证高架桥梁2正常运营。In this embodiment, in the underpinning structure of the above-mentioned underground reverse layer-adding construction of viaduct pier foundation, the lower limit member 113 includes four right-angled trapezoidal wedge blocks evenly distributed around the hydraulic jack 5, and the upper limit The piece 112 includes four right-angled trapezoidal wedges, and the right-angled waist of the right-angled trapezoidal wedge of the upper limiter 112 is opposite to the right-angled waist of the right-angled trapezoidal wedge of the lower limiter 113 . The right-angled waist of the right-angled trapezoidal wedge of the upper limiter 112 can only move up and down relative to the right-angled trapezoidal wedge of the lower limiter 113, so that the viaduct 2 fixedly connected with the upper limiter 112 cannot be opposite to the lower limiter. 113 The fixedly connected support beam 6 moves horizontally and tilts, so as to ensure the normal operation of the viaduct 2 .

步骤1-6,液压千斤顶5预顶高架桥梁2至托换临时结构及地下室顶板梁4变形稳定后,采取静力切割高架桥柱1,切割位置位于高架桥柱1上低于支撑梁6底部的位置。Steps 1-6: After the hydraulic jack 5 pre-jacks the viaduct 2 to underpin the temporary structure and the basement roof beam 4 is deformed and stabilized, the viaduct column 1 is cut statically, and the cutting position is located on the viaduct column 1 lower than the bottom of the support beam 6 .

步骤1-7,人工凿除高架桥柱1保留段钢筋,便于后期复建高架桥柱1时进行连接,即高架桥柱修补段与保留段之间的连接。Steps 1-7, manually chiseling away the reinforcement of the reserved section of the viaduct column 1, so as to facilitate the connection when the viaduct column 1 is rebuilt later, that is, the connection between the repaired section of the viaduct column and the reserved section.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述工程桩3采用钻孔灌注桩内插格构柱形式。Preferably, in the underpinning structure of the underground reverse layer-adding construction of the viaduct pier foundation, the engineering pile 3 is in the form of a bored cast-in-situ pile inserted into a lattice column.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述支撑柱7与高架桥柱1沿高架桥的纵向错开设置。Preferably, in the underpinning structure of the above-mentioned viaduct column pier foundation underground reverse layer-adding construction, the support column 7 and the viaduct column 1 are arranged staggered along the longitudinal direction of the viaduct.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,液压千斤顶5为双作用千斤顶。当高架桥梁2向下移动时,液压千斤顶5的伸出端伸长将高架桥梁2向上顶升;当高架桥梁2向上移动时,液压千斤顶5的伸出端回缩将高架桥梁2向下牵引。Preferably, in the underpinning structure of the above-mentioned viaduct column pier foundation underground reverse layer-adding construction, the hydraulic jack 5 is a double-acting jack. When the viaduct 2 moves downward, the extending end of the hydraulic jack 5 stretches to lift the viaduct 2 upward; when the viaduct 2 moves upward, the extending end of the hydraulic jack 5 retracts to pull the viaduct 2 downward .

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述步骤2具体包括:Preferably, in the above-mentioned viaduct column pier foundation underground reverse layer build-up construction underpinning structure, the step 2 specifically includes:

步骤2-1,开挖地下室第二批土,凿除高架柱墩13及用于支撑高架柱墩13的承载桩,施工地下室地下一层结构梁板12。Step 2-1, excavating the second batch of soil in the basement, removing the elevated pier 13 and the bearing piles used to support the elevated pier 13, and constructing the structural beam slab 12 of the basement first floor.

步骤2-2,继续开挖地下室第三批土,直至地下空间主体结构完成,在地下空间施工过程中密切关注高架桥梁2沉降变形及应力,并通过液压千斤顶5顶升和回油收缩作用进行高架桥梁2变形应力的调整,确保高架桥梁2处于安全运营状态。Step 2-2, continue to excavate the third batch of soil in the basement until the main structure of the underground space is completed, pay close attention to the settlement deformation and stress of the viaduct 2 during the construction of the underground space, and carry out the lifting and shrinkage of the hydraulic jack 5 through the hydraulic jack 5. The adjustment of the deformation stress of the viaduct 2 ensures that the viaduct 2 is in a safe operating state.

步骤2-3,地下室顶板梁4补缺施工,并在地下室顶板梁4对应的高架桥柱1位置预留用于后期高架桥柱1复建的预留插筋。In step 2-3, fill in the vacancy of the basement roof girder 4, and reserve the reserved ribs at the position of the viaduct column 1 corresponding to the basement roof girder 4 for later reconstruction of the viaduct column 1.

由上可见,在步骤2中,通过设置托换临时结构以及液压千斤顶5的收缩作用,可以确保在高架下方地下增层施工过程中,高架桥位于预定的高度,保证高架桥梁2处于安全运营状态。It can be seen from the above that in step 2, by setting the underpinning temporary structure and the contraction effect of the hydraulic jack 5, it can be ensured that the viaduct is at a predetermined height during the construction process of underground layer addition under the viaduct, ensuring that the viaduct 2 is in a safe operation state.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述液压钢管撑8包括由上至下依次设置的钢管固定端、钢管撑筒体、两台液压千斤顶以及钢管伸缩端,两台液压千斤顶的一端均连接所述钢管撑筒体,另一端均连接所述钢管伸缩端,所述钢管伸缩端与地下室顶板梁4固定连接,所述钢管固定端与支撑梁6固定连接。所述两台液压千斤顶分别能够对支撑梁6提供推力和拉力,所述两台液压千斤顶也能够对地下室顶板梁4提供推力和拉力。所述两台液压千斤顶为双作用千斤顶。Preferably, in the underpinning structure of the above-mentioned underground reverse layer-adding construction of viaduct pier foundations, the hydraulic steel pipe support 8 includes steel pipe fixed ends, steel pipe support cylinders, two hydraulic jacks and steel pipe telescopic One end of the two hydraulic jacks is connected to the steel pipe support cylinder, and the other end is connected to the telescopic end of the steel pipe. The telescopic end of the steel pipe is fixedly connected to the basement roof beam 4, and the fixed end of the steel pipe is fixed to the support beam 6. connect. The two hydraulic jacks can provide thrust and pull to the support beam 6 respectively, and the two hydraulic jacks can also provide push and pull to the basement roof beam 4 . The two hydraulic jacks are double-acting jacks.

优选的,在上述的高架桥柱墩基础地下逆向增层施工托换结构中,所述步骤3具体包括:Preferably, in the above-mentioned viaduct column pier foundation underground reverse layer build-up construction underpinning structure, the step 3 specifically includes:

步骤3-1,在支撑梁6与地下室顶板梁4之间设置若干对所述液压钢管撑8,每对液压钢管撑8位于托换的高架桥柱1的两侧,每对液压钢管撑8与对应的高架桥柱1沿着高架桥的横向设置,即每对液压钢管撑8与对应的高架桥柱1位于与高架桥梁2的纵向相垂直的水平线上,从而使得每对液压钢管撑8尽可能的靠近高架桥柱1,即使得地下室顶板梁4对每对液压钢管撑8的支撑位置尽可能靠近地下室顶板梁4对复建后的高架桥柱1的支撑位置。Step 3-1, set several pairs of hydraulic steel pipe braces 8 between the support beam 6 and the basement roof beam 4, each pair of hydraulic steel pipe braces 8 is located on both sides of the underpinned viaduct column 1, and each pair of hydraulic steel pipe braces 8 and The corresponding viaduct column 1 is arranged along the transverse direction of the viaduct, that is, each pair of hydraulic steel pipe braces 8 and the corresponding viaduct column 1 are located on a horizontal line perpendicular to the longitudinal direction of the viaduct 2, so that each pair of hydraulic steel pipe braces 8 is as close as possible The viaduct column 1 is to make the supporting position of each pair of hydraulic steel pipe braces 8 of the basement roof beam 4 as close as possible to the supporting position of the basement roof beam 4 pair of the reconstructed viaduct column 1 .

步骤3-2,液压钢管撑8安装完成后进行液压预顶托换替代支撑柱,切割支撑柱,运营下的高架桥荷载直接通过液压钢管撑8传递到地下室顶板梁4上。Step 3-2: After the installation of the hydraulic steel pipe brace 8 is completed, perform hydraulic pre-jacking to replace the support column, cut the support column, and the viaduct load under operation is directly transmitted to the basement roof beam 4 through the hydraulic steel pipe brace 8 .

步骤3-3,加载液压钢管撑8,补偿高架荷载作用于地下室顶板梁4后的下挠变形引起的高架桥沉降变形,使高架桥保持在安全沉降变形范围内,当液压钢管撑加载荷载恒定,高架桥变形稳定后,在高架桥柱1位置绑扎钢筋,在地下室顶板梁4上浇筑混凝土复建高架桥柱1。Step 3-3, load the hydraulic steel pipe brace 8 to compensate the settlement deformation of the viaduct caused by the deflection deformation after the elevated load acts on the basement roof girder 4, so that the viaduct remains within the safe settlement deformation range. When the hydraulic steel pipe brace is loaded with a constant load, the viaduct After the deformation is stable, steel bars are bound at the viaduct column 1, and concrete is poured on the basement roof beam 4 to rebuild the viaduct column 1.

步骤3-4,待复建后的高架桥柱1达到混凝土强度后,拆除托换临时结构及液压钢管撑8,完成高架桥柱1墩基础地下增层施工。Step 3-4, after the reconstructed viaduct column 1 reaches the concrete strength, remove the underpinning temporary structure and the hydraulic steel pipe support 8, and complete the construction of the underground layer addition of the viaduct column 1 pier foundation.

在步骤3中,由于在支撑梁6与高架桥梁2之间设置若干对所述液压钢管撑8,每对液压钢管撑8位于高架桥柱1的两侧,每对液压钢管撑8与对应的高架桥柱1沿着高架桥的横向设置,从而使得每对液压钢管撑8尽可能的靠近高架桥柱1,即使得地下室顶板梁4对每对液压钢管撑8的支撑位置尽可能靠近地下室顶板梁4对复建后的高架桥柱1的支撑位置。因而,在高架桥柱1复建之前,利用液压钢管撑8替换托换临时结构对高架桥梁2进行托换支撑,液压钢管撑8的伸缩作用保证高架桥梁2位于预先设计的高度,使得地下室顶板预先进行形变,接着在复建高架桥柱1。由于地下室顶板梁4对每对液压钢管撑8的支撑位置尽可能靠近地下室顶板梁4对复建后的高架桥柱1的支撑位置,因此,复建后高架桥荷载作用在地下室顶板梁后下挠变形导致的高架桥沉降变形较小,从而有效减少地下增层施工后高架桥梁2的沉降位移,保证高架桥梁2的正常运营。In step 3, since several pairs of hydraulic steel pipe braces 8 are set between the support beam 6 and the viaduct 2, every pair of hydraulic steel pipe braces 8 is located on both sides of the viaduct column 1, and every pair of hydraulic steel pipe braces 8 is connected to the corresponding viaduct The column 1 is arranged along the transverse direction of the viaduct, so that each pair of hydraulic steel pipe braces 8 is as close as possible to the viaduct column 1, that is, the supporting position of each pair of hydraulic steel pipe braces 8 for the basement roof beams is as close as possible to the basement roof beams 4 pairs. The supporting position of viaduct column 1 after construction. Therefore, before the reconstruction of the viaduct column 1, the viaduct 2 is underpinned by using the hydraulic steel pipe brace 8 to replace the underpinning temporary structure. Carry out deformation, and then rebuild viaduct column 1. Since the support position of the basement roof beam 4 for each pair of hydraulic steel pipe braces 8 is as close as possible to the support position of the basement roof beam 4 for the reconstructed viaduct column 1, therefore, the viaduct load acts on the rear deflection deformation of the basement roof beam after reconstruction The resulting settlement and deformation of the viaduct is small, thereby effectively reducing the settlement displacement of the viaduct 2 after the construction of the underground layer addition, and ensuring the normal operation of the viaduct 2 .

综上所述,本实用新型提供的高架桥柱墩基础地下逆向增层施工托换结构,通过两次主动托换方式进行运营下高架桥柱墩基础地下逆向增层施工,先行施工地下空间围护结构及工程桩和地下室顶板梁,在地下室顶板梁上架设托换临时结构,通过在托换临时结构上安装液压千斤顶,主动托换高架桥梁。施工过程中通过液压千斤顶顶升和回油收缩作用进行高架桥变形应力的调整,确保高架桥在地下空间开发阶段处于安全运营状态。地下空间增层施工完成后,架设液压钢管撑对原高架桥梁进行二次托换,消除高架桥在新开发地下室顶板上复建永久高架桥柱的沉降变形,利用地下室顶板梁作为高架桥柱永久基础,恢复原高架桥柱,完成运营下的高架桥柱墩基础增层托换施工。In summary, the underpinning construction of the underground reverse layer-adding construction of the viaduct pier foundation provided by the utility model uses two active underpinning methods to carry out the underground reverse layer-adding construction of the viaduct pier foundation under operation, and the underground space enclosure structure is constructed first As well as engineering piles and basement roof beams, a temporary underpinning structure is erected on the basement roof beam, and a hydraulic jack is installed on the underpinning temporary structure to actively underpin the elevated bridge. During the construction process, the deformation stress of the viaduct is adjusted through the lifting of the hydraulic jack and the contraction of the oil return to ensure that the viaduct is in a safe operation state during the development of the underground space. After the completion of the construction of the underground space, hydraulic steel pipe braces are erected to underpin the original viaduct to eliminate the settlement and deformation of the viaduct on the roof of the newly developed basement when the permanent viaduct column is rebuilt, and the basement roof beam is used as the permanent foundation of the viaduct column to restore For the original viaduct column, the underpinning construction of the viaduct column pier foundation under operation was completed.

上述描述仅是对本实用新型较佳实施例的描述,并非对本实用新型范围的任何限定,本实用新型领域的普通技术人员根据上述揭示内容做的任何变更、修饰,均属于权利要求书的保护范围。The above description is only a description of the preferred embodiments of the present utility model, and is not any limitation to the scope of the present utility model. Any changes and modifications made by those of ordinary skill in the field of the utility model according to the above disclosures all belong to the protection scope of the claims .

Claims (10)

1.一种高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,包括:设置于高架桥下方地下空间的围护结构和工程桩,设置于工程桩上的地下室顶板梁,设置于地下室顶板梁上的托换临时结构,以及安装于托换临时结构以及高架桥梁之间的用于主动托换高架桥梁的液压千斤顶,所述液压千斤顶的顶部伸出端与高架桥梁固定连接,所述托换临时结构包括两对平行设置的支撑梁以及用于支撑所述支撑梁的若干支撑柱,所述支撑柱的下端与地下室顶板梁固定连接,所述支撑梁与所述高架桥的纵向平行,每对支撑梁设置于高架桥柱的两侧。1. A reverse construction underpinning structure for viaduct pier foundations, characterized in that it comprises: an enclosure structure and engineering piles arranged in the underground space below the viaduct, a basement roof beam arranged on the engineering piles, arranged in the basement The underpinning temporary structure on the roof girder, and the hydraulic jack installed between the underpinning temporary structure and the viaduct for actively underpinning the viaduct, the top protruding end of the hydraulic jack is fixedly connected with the viaduct, the The underpinning temporary structure includes two pairs of supporting beams arranged in parallel and several supporting columns for supporting the supporting beams, the lower ends of the supporting columns are fixedly connected with the basement roof beams, the supporting beams are parallel to the longitudinal direction of the viaduct, Each pair of supporting beams is arranged on both sides of the viaduct column. 2.如权利要求1所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,在地下室顶板梁上安装支撑柱位置预埋用于安装支撑柱的埋件,所述支撑柱的下端与地下室顶板梁上的埋件相连接。2. The underpinning structure of the underground reverse layer-adding construction of viaduct pier foundation as claimed in claim 1, characterized in that, on the basement roof beam, the supporting column position is pre-embedded for installing the embedded parts of the supporting column, and the supporting column The lower end of the basement is connected with the embedded parts on the roof beam of the basement. 3.如权利要求1所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,在高架桥梁和支撑梁之间对应每个液压千斤顶安装限位装置,所述限位装置能够限制高架桥梁与支撑梁之间相对水平方向位移,所述限位装置分布于液压千斤顶四周。3. The underpinning structure of the underground reverse layer-adding construction of the viaduct pier foundation as claimed in claim 1, wherein a spacer is installed corresponding to each hydraulic jack between the viaduct and the supporting beam, and the spacer can The relative horizontal displacement between the elevated bridge and the supporting beam is limited, and the limiting device is distributed around the hydraulic jack. 4.如权利要求3所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,所述限位装置包括预埋板以及安装于预埋板下方的上限位件,所述支撑梁上固定设有下限位件,所述下限位件形成供上限位件伸入的凹槽,所述上限位件的高度小于所述凹槽的深度,所述预埋板能够搁置于所述下限位件上。4. The underpinning structure for underground reverse layer-adding construction of viaduct pier foundations as claimed in claim 3, wherein the limiting device includes a pre-embedded plate and an upper limit member installed under the pre-embedded plate, and the support A lower limit piece is fixed on the beam, and the lower limit piece forms a groove for the upper limit piece to extend into. The height of the upper limit piece is smaller than the depth of the groove, and the embedded plate can rest on the on the lower limit piece. 5.如权利要求4所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,所述下限位件包括四块均匀分布于所述液压千斤顶四周的直角梯形楔形块,所述上限位件包括四块直角梯形楔形块,所述上限位件的直角梯形楔形块的直角腰与下限位件的直角梯形楔形块的直角腰相对设置。5. The underpinning structure for underground reverse layer-adding construction of viaduct pier foundations as claimed in claim 4, wherein said lower limiting member comprises four right-angled trapezoidal wedge blocks evenly distributed around said hydraulic jack, said The upper limiter includes four right-angled trapezoidal wedges, and the right-angled waist of the right-angled trapezoidal wedge of the upper limiter is opposite to the right-angled waist of the right-angled trapezoidal wedge of the lower limiter. 6.如权利要求1所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,所述支撑柱与高架桥柱沿高架桥的纵向错开设置。6. The underpinning structure for underground reverse layer-adding construction of viaduct pier foundations according to claim 1, characterized in that, the support columns and the viaduct columns are staggered along the longitudinal direction of the viaduct. 7.如权利要求1所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,液压千斤顶为双作用千斤顶。7. The underpinning structure for underground reverse layer-adding construction of viaduct pier foundations as claimed in claim 1, wherein the hydraulic jack is a double-acting jack. 8.如权利要求1所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,在支撑梁与地下室顶板梁之间设置若干对液压钢管撑,每对液压钢管撑位于对应高架桥柱的两侧,每对液压钢管撑与对应的高架桥柱沿着高架桥的横向设置。8. The underpinning structure for underground reverse layer-adding construction of viaduct pier foundations as claimed in claim 1, wherein several pairs of hydraulic steel pipe braces are arranged between the support beam and the basement roof beam, and each pair of hydraulic steel pipe braces is located on the corresponding viaduct bridge. On both sides of the column, each pair of hydraulic steel pipe braces and the corresponding viaduct column are arranged along the transverse direction of the viaduct. 9.如权利要求8所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,所述液压钢管撑包括由上至下依次设置的钢管固定端、钢管撑筒体、两台液压千斤顶以及钢管伸缩端,所述两台液压千斤顶的一端均连接所述钢管撑筒体,另一端均连接所述钢管伸缩端,所述钢管伸缩端与地下室顶板梁固定连接,所述钢管固定端与支撑梁固定连接。9. The underpinning structure for underground reverse layer-adding construction of viaduct pier foundations as claimed in claim 8, wherein the hydraulic steel pipe braces include steel pipe fixed ends, steel pipe support cylinders, two sets of Hydraulic jacks and steel pipe telescopic ends, one end of the two hydraulic jacks is connected to the steel pipe support cylinder, the other end is connected to the steel pipe telescopic end, the steel pipe telescopic end is fixedly connected to the basement roof beam, and the steel pipe is fixed The end is fixedly connected to the support beam. 10.如权利要求1所述的高架桥柱墩基础地下逆向增层施工托换结构,其特征在于,所述围护结构包括围护桩以及设置于围护桩外侧的止水帷幕。10 . The underpinning structure for underground reverse layer-adding construction of viaduct pier foundations according to claim 1 , wherein the enclosure structure includes enclosure piles and water-stop curtains arranged outside the enclosure piles. 11 .
CN201820120141.0U 2018-01-24 2018-01-24 A kind of reverse increasing layer construction underpinning structure in overpass pier base underground Expired - Fee Related CN208121552U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820120141.0U CN208121552U (en) 2018-01-24 2018-01-24 A kind of reverse increasing layer construction underpinning structure in overpass pier base underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820120141.0U CN208121552U (en) 2018-01-24 2018-01-24 A kind of reverse increasing layer construction underpinning structure in overpass pier base underground

Publications (1)

Publication Number Publication Date
CN208121552U true CN208121552U (en) 2018-11-20

Family

ID=64206293

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820120141.0U Expired - Fee Related CN208121552U (en) 2018-01-24 2018-01-24 A kind of reverse increasing layer construction underpinning structure in overpass pier base underground

Country Status (1)

Country Link
CN (1) CN208121552U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236311A (en) * 2020-03-06 2020-06-05 华东建筑设计研究院有限公司 Construction platform and construction method for underground space development of dense existing buildings
CN114875960A (en) * 2022-03-29 2022-08-09 中国水利水电第九工程局有限公司 Pile steel support construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236311A (en) * 2020-03-06 2020-06-05 华东建筑设计研究院有限公司 Construction platform and construction method for underground space development of dense existing buildings
CN111236311B (en) * 2020-03-06 2024-04-09 华东建筑设计研究院有限公司 Construction platform and construction method for developing underground space of dense existing building group
CN114875960A (en) * 2022-03-29 2022-08-09 中国水利水电第九工程局有限公司 Pile steel support construction method

Similar Documents

Publication Publication Date Title
CN105863287B (en) Frame structure building jacks increasing layer and shock isolation method
CN108265618B (en) A kind of underground reverse layer-adding construction method for viaduct column pier foundation
CN103437567B (en) Method for supporting existing building underground added storey through original pile foundations
US5174085A (en) Method of adding additional stories to an existing storied building
CN105926963B (en) A kind of existing skyscraper subinverse make the vertical support method of increasing layer
CN106351132B (en) A kind of bridge using corrugated sheet steel connector spells wide construction and its construction method
CN210067002U (en) A support-free prefabricated frame structure system
CN102864796B (en) Construction spreading foundation adaptive to filled ground settlement and construction method
CN112095495A (en) Bridge underpinning support structure and construction method
CN112879026A (en) Temporary backrest support structure for rectangular pipe jacking construction and construction method thereof
CN109403654B (en) Underpinning and reinforcing method for existing building structure
CN208121552U (en) A kind of reverse increasing layer construction underpinning structure in overpass pier base underground
CN110424246A (en) A kind of Long span bowstring arch bridge access bridge jack-up system and jack-up construction method
CN114561881A (en) Longitudinal deviation-rectifying and resetting method suitable for soft soil foundation bridge
CN210288419U (en) Reverse column diagonal bracing reinforcing system for large-span reverse foundation pit
CN111636464A (en) Bridge pile foundation conversion method and structure
CN112813852B (en) A repair and reinforcement method for bridge deck subsidence of in-service bridges
CN212452726U (en) Pile foundation conversion structure of bridge
CN213571600U (en) Bridge underpins bearing structure
CN103147591A (en) Construction method for adding earthquake-proof layer to brick concrete building
CN209194570U (en) Large-volume prestressed beam underpinning structure
CN222375224U (en) A temporary support device for bridge jacking construction on soft soil foundation
CN221523337U (en) A variable elevation bridge support conversion device
CN214657091U (en) Envelope bearing structure capable of being converted into basement structure beam column
CN204715219U (en) Distribution beam hanging apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181120