CN207673022U - A kind of new type of light gauge steel composite concrete wallboard hanging apparatus - Google Patents
A kind of new type of light gauge steel composite concrete wallboard hanging apparatus Download PDFInfo
- Publication number
- CN207673022U CN207673022U CN201721880820.XU CN201721880820U CN207673022U CN 207673022 U CN207673022 U CN 207673022U CN 201721880820 U CN201721880820 U CN 201721880820U CN 207673022 U CN207673022 U CN 207673022U
- Authority
- CN
- China
- Prior art keywords
- supporting cell
- mounting bracket
- composite concrete
- concrete wallboard
- new type
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of new type of light gauge steel composite concrete wallboard hanging apparatus, including playing hanging piece, lift by crane mounting bracket and supporting cell guide, top at the top of the lifting mounting bracket has been provided with hanging piece, the middle position of the lifting mounting bracket bottom is symmetrically installed with supporting cell guide, the centre position of described two supporting cell guides is all provided with outer tube, and the side of supporting cell guide and outer tube is provided with the round thread hole being mutually matched, it is all evenly arranged with positioning bolt on round thread hole on the outer tube, and positioning bolt is on outer tube and the round thread hole that is fixed on supporting cell guide, the opposite side of described two outer tubes is symmetrically installed with hydraulic cylinder, the output end of the hydraulic cylinder is all provided with fixation kit.The utility model is equipped with fixation kit, and when being lifted to different size of lightgage steel joist composite concrete wallboard, fixed effect is more preferable, reduces the probability that safety accident occurs for factory.
Description
Technical field
The utility model is related to equipment technical field for building, specially a kind of new type of light gauge steel composite concrete wallboard
Hanging apparatus.
Background technology
Lightgage steel joist is a kind of novel construction material, and with the development of China's modernization construction, lightgage steel joist is used extensively
In hotel, terminal, Che Yunzhan, station, recreation ground, market, factory, office building, old building remodeling, interior decoration setting, top
The places such as canopy, lightgage steel joist composite concrete wallboard is with light-weight, intensity is high, adapts to waterproof, shockproof, dust-proof, sound insulation, suction
Sound, constant temperature and other effects, while also having many advantages, such as short time limit, easy construction, by the preference of people, it is well known that existing
When technology carries out the architecture constructions such as building, hanging apparatus is a kind of essential mechanical equipment, and whole work greatly improved
Make efficiency, to obtain extensive promotion and application, lightgage steel joist composite concrete wallboard hanging apparatus knot currently on the market
Structure is relatively simple, and when being lifted to different size of keel, fixed effect is bad, and in uphill process, keel may be sent out
Raw sliding is fallen, and causes some potential safety problems to constructor, while applicable effect is poor, can not be hung to irregular keel
Dress, in addition when being lifted to larger keel, lifting rate is relatively low, time-consuming and laborious, seriously drags slow construction speed, in consideration of it,
The designer is actively subject to research and innovation to found a kind of new type of light gauge steel composite concrete wallboard hanging apparatus, makes it
With more the utility value in industry.
Utility model content
The purpose of this utility model is to provide a kind of new type of light gauge steel composite concrete wallboard hanging apparatus, to solve
The problems mentioned above in the background art.
To achieve the above object, the utility model provides the following technical solutions:A kind of new type of light gauge steel composite concrete
Wallboard hanging apparatus, including hanging piece, lifting mounting bracket and supporting cell guide are played, the top at the top of the lifting mounting bracket has been provided with
The bottom of hanging piece, described hanging piece is provided with rigid rope rope, and the other end of the rigid rope rope is fixedly mounted on lifting mounting bracket, institute
The middle position for stating lifting mounting bracket bottom is symmetrically installed with supporting cell guide, and the centre position of described two supporting cell guides is all set
Outer tube is equipped with, and the side of supporting cell guide and outer tube is provided with the round thread hole being mutually matched, on the outer tube
Positioning bolt is all evenly arranged on round thread hole, and positioning bolt through outer tube and is fixed on the circle on supporting cell guide
On threaded hole, the opposite side of described two outer tubes is symmetrically installed with hydraulic cylinder, and the output end of the hydraulic cylinder is all provided with
Fixation kit, the fixation kit include fixed plate, pneumatic cylinder, upper limit plate, buffer unit, latch, lower limiting board, described
Fixed plate is provided with lower limit far from being equipped with upper limit plate above hydraulic cylinder side in fixed plate below upper limit plate
Plate, pneumatic cylinder is equipped at the top of the upper limit plate, and the output end of the pneumatic cylinder through upper limit plate and extends to lower limit
Above the plate of position, and latch is installed, the junction of the pneumatic cylinder and latch is provided with buffer unit, the lifting installation
The both ends of frame bottom are symmetrically installed with Toolbox, and the bottom of the Toolbox is equipped with vacuum by reinforcing prop and inhales
Disk is connected between the supporting cell guide and Toolbox by reinforcing bar, and lift by crane mounting bracket bottom two supporting cell guides it
Between be provided with hook, the bottom of the supporting cell guide is all provided with the second electromagnet, and the bottom of second electromagnet is all arranged
There is spring, and the other end of spring is provided with the first electromagnet, second electromagnet is identical as the first electromagnet polarity.
Preferably, the hook is detachable setting.
Preferably, it is provided with rubber pad at the top of the lower limiting board, and is evenly arranged with anti-skid chequer at the top of rubber pad.
Preferably, the buffer unit is buffer spring.
Preferably, it is evenly arranged with ribs on the Toolbox.
Preferably, the upper limit plate is identical with the size of lower limiting board.
Compared with prior art, the utility model has the beneficial effects that:The new type of light gauge steel composite concrete wallboard is hung
Assembling device is equipped with fixation kit, when being lifted to different size of lightgage steel joist composite concrete wallboard, fixed effect
More preferably, buffer unit plays buffer protection function to the process of being locked, and prevents lightgage steel joist from being deformed upon because stress is excessive,
Ensure the aesthetics of keel, while also ensuring in uphill process and will not be fallen since keel tilt, has ensured and applied
The life security of work person reduces the probability that safety accident occurs for factory, highly practical, outer tube and positioning bolt and housing
The setting in round thread hole on pipe, can adjust the height of fixation kit so that lifting operation is more convenient, while being provided with the
One electromagnet and the second electromagnet, and the first electromagnet and the second electromagnetism ferromagnetism are identical, repel each other effect after energization, to dress
Set a upward initial velocity so that lifting efficiency greatly improves, in addition, device is provided with Toolbox, can place letter
Easy lifting device is conveniently operated in construction, which promotes the use of compared to similar product practicability higher convenient for factory.
Description of the drawings
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the fixation kit structural schematic diagram of the utility model.
In figure:1, hanging piece is played;2, rigid rope rope;3, reinforcing bar;4, mounting bracket is lifted by crane;5, Toolbox;6, fixation kit;
601, fixed plate;602, pneumatic cylinder;603, upper limit plate;604, buffer unit;605, latch;606, lower limiting board;7,
One electromagnet;8, spring;9, the second electromagnet;10, supporting cell guide;11, outer tube;12, positioning bolt;13, ribs;14、
Vacuum cup;15, hydraulic cylinder;16, it links up with.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
The every other embodiment obtained, shall fall within the protection scope of the present invention.
- 2 are please referred to Fig.1, a kind of embodiment provided by the utility model:A kind of new type of light gauge steel composite concrete wallboard
Hanging apparatus, including hanging piece 1, lifting mounting bracket 4 and supporting cell guide 10 are played, the top at 4 top of lifting mounting bracket is provided with lifting
Part 1, the bottom for playing hanging piece 1 are provided with rigid rope rope 2, and the other end of rigid rope rope 2 is fixedly mounted on lifting mounting bracket 4, lifting peace
The middle position for shelving 4 bottoms is symmetrically installed with supporting cell guide 10, and the centre position of two supporting cell guides 10 is all provided with outside
Casing 11, and supporting cell guide 10 and the side of outer tube 11 are provided with the round thread hole being mutually matched, the circle on outer tube 11
Positioning bolt 12 is all evenly arranged on shape threaded hole, and positioning bolt 12 through outer tube 11 and is fixed on supporting cell guide 10
Round thread hole on, two opposite sides of outer tube 11 are symmetrically installed with hydraulic cylinder 15, and the output end of hydraulic cylinder 15 is all set
It is equipped with fixation kit 6, fixation kit 6 includes fixed plate 601, pneumatic cylinder 602, upper limit plate 603, buffer unit 604, latch
605, lower limiting board 606, fixed plate 601 above 15 side of hydraulic cylinder far from being equipped with upper limit plate 603, and fixed plate 601
The lower section of upper upper limit plate 603 is provided with lower limiting board 606, and the top of upper limit plate 603 is equipped with pneumatic cylinder 602, pneumatic cylinder
602 output end is through upper limit plate 603 and extends to 606 top of lower limiting board, and is equipped with latch 605, pneumatic cylinder 602
The junction of latch 605 is provided with buffer unit 604, the both ends of 4 bottom of lifting mounting bracket are symmetrically installed with tool storage
The bottom of case 5, Toolbox 5 is equipped with vacuum cup 14 by reinforcing prop, leads between supporting cell guide 10 and Toolbox 5
The connection of reinforcing bar 3 is crossed, and hook 16, the bottom of supporting cell guide 10 are provided between two supporting cell guides 10 of 4 bottom of lifting mounting bracket
Portion is all provided with the second electromagnet 9, and the bottom of the second electromagnet 9 is all provided with spring 8, and the other end of spring 8 is provided with
One electromagnet 7, the second electromagnet 9 are identical as 7 polarity of the first electromagnet.
In this embodiment:Hook 16 is detachable setting, replaces, increases to it after facilitating its long-time service to wear
The service life of whole device is added, the top of lower limiting board 606 is provided with rubber pad, and is evenly arranged at the top of rubber pad
Anti-skid chequer prevents lightgage steel joist composite concrete wallboard when fixed, and bottom is skidded, to cause unnecessary safe thing
Therefore buffer unit 604 is buffer spring, use cost is relatively low, and ribs 13 is evenly arranged on Toolbox 5, is improved
The intensity of Toolbox 5, upper limit plate 603 is identical with the size of lower limiting board 606, and the effect that is fixedly clamped is more preferable.
Operation principle:The device consuming parts are powered by accumulator, in use, the height of outer tube 11 is adjusted,
It is positioned using positioning bolt 12, the axial height of entire fixation kit 6 can be adjusted, open hydraulic cylinder 15, pushed entire fixed
Component 6 moves horizontally, and lightgage steel joist composite concrete wallboard constantly, is placed on lower limit by the suitable position for placing wallboard to be achieved
It on the plate 606 of position, opens pneumatic cylinder 602 and pushes latch 605 that wallboard is fixed, buffer unit 604 is to fixed locking process
Buffer protection is carried out, prevents wallboard from deforming, boom hoisting is lifted by crane to playing a hanging piece 1, before lifting, to the first electromagnet 7 and the
Two electromagnet 9 are powered, and because its polarity is identical, generate mutually exclusive active force, have given hanging piece one upward initial velocity,
So that lifting lifting is more efficient, Toolbox 5 can place lifting tool, be used for constructor, and vacuum cup 14 also may be used
To be lifted by crane to wallboard, 16 setting is linked up with, the wallboard of irregular shape can be lifted by crane.
Although the utility model is described in detail with reference to the foregoing embodiments, those skilled in the art is come
Say, still can with technical scheme described in the above embodiments is modified, or to which part technical characteristic into
Row equivalent replacement, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should all
It is included within the scope of protection of this utility model.
Claims (6)
1. a kind of new type of light gauge steel composite concrete wallboard hanging apparatus, including play hanging piece (1), lifting mounting bracket (4) and branch
Support guide post (10), it is characterised in that:Top at the top of the lifting mounting bracket (4) has been provided with hanging piece (1), described hanging piece
(1) bottom is provided with rigid rope rope (2), and the other end of the rigid rope rope (2) is fixedly mounted on lifting mounting bracket (4), described
The middle position of lifting mounting bracket (4) bottom is symmetrically installed with supporting cell guide (10), in described two supporting cell guides (10)
Between position be all provided with outer tube (11), and supporting cell guide (10) and the side of outer tube (11) are provided with the circle being mutually matched
Threaded hole is all evenly arranged with positioning bolt (12), and positioning bolt (12) on the round thread hole on the outer tube (11)
On outer tube (11) and the round thread hole that is fixed on supporting cell guide (10), described two outer tubes (11) it is opposite one
Side is symmetrically installed with hydraulic cylinder (15), and the output end of the hydraulic cylinder (15) is all provided with fixation kit (6), the fixation kit
(6) include fixed plate (601), pneumatic cylinder (602), upper limit plate (603), buffer unit (604), latch (605), lower limit
Plate (606), the fixed plate (601) are equipped with upper limit plate (603), and fixed plate above separate hydraulic cylinder (15) side
(601) lower limiting board (606) is provided with below upper limit plate (603), gas is installed at the top of the upper limit plate (603)
The output end of cylinder pressure (602), the pneumatic cylinder (602) through upper limit plate (603) and extends to above lower limiting board (606),
And latch (605) is installed, the pneumatic cylinder (602) and the junction of latch (605) are provided with buffer unit (604),
The both ends of described lifting mounting bracket (4) bottom are symmetrically installed with Toolbox (5), and the bottom of the Toolbox (5) is logical
It crosses reinforcing prop and vacuum cup (14) is installed, between the supporting cell guide (10) and Toolbox (5) even by reinforcing bar (3)
It connects, and hook (16), the bottom of the supporting cell guide (10) is provided between two supporting cell guides (10) of lifting mounting bracket (4) bottom
Portion is all provided with the second electromagnet (9), and the bottom of second electromagnet (9) is all provided with spring (8), and spring (8) is another
One end is provided with the first electromagnet (7), and second electromagnet (9) is identical as the first electromagnet (7) polarity.
2. a kind of new type of light gauge steel composite concrete wallboard hanging apparatus according to claim 1, it is characterised in that:Institute
It is detachable setting to state hook (16).
3. a kind of new type of light gauge steel composite concrete wallboard hanging apparatus according to claim 1, it is characterised in that:Institute
It states and is provided with rubber pad at the top of lower limiting board (606), and be evenly arranged with anti-skid chequer at the top of rubber pad.
4. a kind of new type of light gauge steel composite concrete wallboard hanging apparatus according to claim 1, it is characterised in that:Institute
It is buffer spring to state buffer unit (604).
5. a kind of new type of light gauge steel composite concrete wallboard hanging apparatus according to claim 1, it is characterised in that:Institute
It states and is evenly arranged with ribs (13) on Toolbox (5).
6. a kind of new type of light gauge steel composite concrete wallboard hanging apparatus according to claim 1, it is characterised in that:Institute
It is identical with the size of lower limiting board (606) to state upper limit plate (603).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721880820.XU CN207673022U (en) | 2017-12-28 | 2017-12-28 | A kind of new type of light gauge steel composite concrete wallboard hanging apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721880820.XU CN207673022U (en) | 2017-12-28 | 2017-12-28 | A kind of new type of light gauge steel composite concrete wallboard hanging apparatus |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207673022U true CN207673022U (en) | 2018-07-31 |
Family
ID=62971977
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721880820.XU Expired - Fee Related CN207673022U (en) | 2017-12-28 | 2017-12-28 | A kind of new type of light gauge steel composite concrete wallboard hanging apparatus |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207673022U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112502350A (en) * | 2020-11-25 | 2021-03-16 | 湖南江南钢构工程有限公司 | Fabricated building keel convenient to hoist and use method thereof |
-
2017
- 2017-12-28 CN CN201721880820.XU patent/CN207673022U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112502350A (en) * | 2020-11-25 | 2021-03-16 | 湖南江南钢构工程有限公司 | Fabricated building keel convenient to hoist and use method thereof |
CN112502350B (en) * | 2020-11-25 | 2021-11-05 | 湖南江南钢构工程有限公司 | Fabricated building keel convenient to hoist and use method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207673022U (en) | A kind of new type of light gauge steel composite concrete wallboard hanging apparatus | |
CN206705561U (en) | A kind of hanging apparatus for lifting sheet material | |
CN208378169U (en) | Battery type hydraulic vacuum suspender | |
CN204400421U (en) | A kind of gallows frame adopting electromagnet | |
CN206126699U (en) | Multi -functional portable lifting machine | |
CN206940257U (en) | Novel mechanical equipment hoisting frame | |
CN205733110U (en) | A kind of thin-walled aluminium car aperture apparatus | |
CN208700400U (en) | A kind of hanging apparatus of cladding glass | |
CN216785486U (en) | Hoisting tool for precast concrete member | |
CN201292225Y (en) | A shaped frame for crawler crane | |
CN205973449U (en) | Jack -up handling rigging of buffering pulley | |
CN204152219U (en) | Side fascia stone tongs | |
CN202333524U (en) | Hoisting support for overhaul of isolating switch | |
CN208603613U (en) | Mast type hoisting device for electromechanical equipment of super high-rise building | |
CN207582931U (en) | A kind of elevating scaffold lifting device | |
CN208008374U (en) | A kind of boom hoisting for building | |
CN110356957A (en) | A kind of assembly suspending protector for building | |
CN214834993U (en) | Building installation has protector of stability | |
CN205740111U (en) | A kind of electric pole gold utensil stringer used for operation maintenance of ascending a height | |
CN220033773U (en) | Wallboard hoist device for assembled building | |
CN201349102Y (en) | Suspension bracket for generally overhauling isolating switch | |
CN209876273U (en) | Spring support and hanger convenient to fix | |
CN222101333U (en) | A rock board composite board | |
CN217676569U (en) | Drop-proof safety mechanism for hanging beam of pneumatic hoist | |
CN219950196U (en) | Bracket type pipe piece transverse lifting clamp |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180731 Termination date: 20181228 |
|
CF01 | Termination of patent right due to non-payment of annual fee |