CN207418036U - Cable sheave device - Google Patents
Cable sheave device Download PDFInfo
- Publication number
- CN207418036U CN207418036U CN201721394594.4U CN201721394594U CN207418036U CN 207418036 U CN207418036 U CN 207418036U CN 201721394594 U CN201721394594 U CN 201721394594U CN 207418036 U CN207418036 U CN 207418036U
- Authority
- CN
- China
- Prior art keywords
- pulley
- stud shaft
- hook support
- cable
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000007704 transition Effects 0.000 claims description 4
- 238000005096 rolling process Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 3
- 238000005259 measurement Methods 0.000 description 2
- 238000005457 optimization Methods 0.000 description 2
- 238000005299 abrasion Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000003129 oil well Substances 0.000 description 1
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
The utility model is related to the technical fields of pulley, it is a kind of cable sheave device, it includes big hook support, pulley bracket, pulley, big hook support and pulley bracket are all frame assembly, and pulley bracket is fixedly connected on the lower section of big hook support, the first stud shaft is provided in big hook support, the right end of first stud shaft is provided with the first nut, the second stud shaft is provided in pulley bracket, pulley is arranged on the second stud shaft, and the right end of the second stud shaft is provided with the second nut.The utility model reasonable and compact in structure, the utility model is fixed on hook by the first stud shaft and the first nut, utilize the pulley in pulley bracket, it can make cable smoothly into flowline, the sliding friction between original cable and hook is replaced with the rolling friction of cable and pulley room, reduces frictional force, not only saves a large amount of manpowers, and the degree of wear of cable is also reduced, it greatly reduces and generates the probability of security incident since cable is worn.
Description
Technical field
The utility model is related to the technical fields of pulley, are a kind of cable sheave devices.
Background technology
As shown in Figure 3, in the work progress of oil well, it is often necessary to instrument is sent in well by oil pipe 1 and is carried out
The measurement of data parameters, and the handling of oil pipe 1 then needs to use the hook 2 on workover rig, the hanging ring 3 on hook 2 slings oil pipe 1
On elevator 4, the handling of oil pipe 1 can be realized, since one end of measuring instrument is often all connected with the electricity of transmission measurement signal
Cable 5, therefore in handling oil pipe 1, in order to avoid hanging ring 3 or elevator 4 damage cable 5 of the relaxation outside well by pressure, field worker is past
Toward the well outer portion of cable 5 being wound on can in advance on hook 2, then tensed again by worker and restrain this one end, so as to avoid
Squeeze, the situation of damage cable, due to there are larger frictional force, so done between hook 2 and cable 5 also there are two it is larger
The shortcomings that, first, being pulled in the process, it is necessary to consume substantial amounts of manpower, second is that cable 5 can be because larger between hook 2
Frictional resistance, the insulated hull of cable 5 can generate larger abrasion, can not only influence the service life of cable 5, but also be easy to make
Into security risk.
The content of the invention
The utility model provides a kind of cable sheave device, overcomes the deficiency of the above-mentioned prior art, can effectively solve
Certainly current cable leads to the problem of larger frictional force when into flowline between meeting and hook, and then solves worker's work during this period
Industry heavy load, cable are because the problem of frictionally damage causes security risk.
The technical solution of the utility model is realized by following measures:A kind of cable sheave device includes hook branch
Frame, pulley bracket, pulley, big hook support and pulley bracket are all frame assembly, and pulley bracket is fixedly connected on big hook support
Lower section, the first stud shaft of the left and right frame of big hook support is provided through on big hook support, the right end of the first stud shaft is provided with
The first nut first stud shaft being fixed on big hook support is provided through the left and right frame of pulley bracket on pulley bracket
The second stud shaft, pulley is arranged on the second stud shaft, and the right end of the second stud shaft is provided with is fixed on pulley bracket by the second stud shaft
On the second nut.
Here is the further optimization and/or improvements to above-mentioned utility model technical solution:
Above-mentioned big hook support is the rectangle frame that downside lacks lower frame, and pulley bracket is the rectangle that upside lacks upper side frame
Frame, the downside of big hook support is corresponding with the upside of pulley bracket, and the left frame of big hook support and the left frame of pulley bracket are consolidated
Fixed connection, the Right Border of big hook support and the left frame of pulley bracket are dislocatedly distributed, the upper surface of pulley bracket left frame with
Gap is provided between the lower end of second stud shaft.
At least provided with two cushion blocks on the inside of big hook support above above-mentioned first stud shaft, cushion block respectively with big hook support
Left frame is fixedly connected with left frame.
Clamp is provided on the first stud shaft on the right side of above-mentioned first nut.
The bearing that can drive pulley rotation is provided on second stud shaft of above-mentioned pulley left and right ends.
The both sides that the groove of arc-shaped, groove or so are provided in the middle part of above-mentioned pulley all use slope and arc transition.
The utility model is fixed on hook by the utility model reasonable and compact in structure by the first stud shaft and the first nut
On, using the pulley in pulley bracket, cable can be made smoothly into flowline, to be replaced with the rolling friction of cable and pulley room
The originally sliding friction between cable and hook, reduces frictional force, not only saves a large amount of manpowers, and also reduce cable
The degree of wear greatly reduces and generates the probability of security incident since cable is worn.
Description of the drawings
Attached drawing 1 is the main structure diagram of the best embodiment of the utility model.
Attached drawing 2 is the left view structural representation of attached drawing 1.
When attached drawing 3 is does not have the utility model on hook, the structure diagram of cable incoming-outgoing oil pipe.
When attached drawing 4 is is equipped with the utility model on hook, the structure diagram of cable incoming-outgoing oil pipe.
Coding in attached drawing is respectively:1 is oil pipe, and 2 be hook, and 3 be hanging ring, and 4 be elevator, and 5 be cable, and 6 be hook branch
Frame, 7 be pulley bracket, and 8 be the first stud shaft, and 9 be the second stud shaft, and 10 be pulley, and 11 be the first nut, and 12 be the second nut, 13
It is clamp for cushion block, 14,15 be bearing, and 16 be groove.
Specific embodiment
The utility model, can technical solution according to the present utility model and actual conditions from the limitation of following embodiments
Determine specific embodiment.
In the utility model, for ease of description, the description of the relative position relation of each component is according to specification
The Butut mode of attached drawing 1 is described, such as:The position relationship of upper and lower, left and right etc. is the Butut according to Figure of description 1
Direction is come definite.
The utility model is further described with reference to embodiment and attached drawing:
As shown in attached drawing 1,2,4, which includes big hook support 6, pulley bracket 7, pulley 10, big hook support
6 and pulley bracket 7 all for frame assembly, pulley bracket 7 is fixedly connected on the lower section of big hook support 6, is set on big hook support 6
The first stud shaft 8 through big 6 left and right frame of hook support is equipped with, the right end of the first stud shaft 8, which is provided with, is fixed on the first stud shaft 8
The first nut 11 on big hook support 6 is provided through the second stud shaft 9 of 7 left and right frame of pulley bracket on pulley bracket 7,
Pulley 10 is arranged on the second stud shaft 9, and the right end of the second stud shaft 9 is provided be fixed on the second stud shaft 9 on pulley bracket 7
Two nuts 12.Big 6 and first stud shaft 8 of hook support forms the gap of a rectangle, this gap is just big with the size of hook
Cause matches, then tightens the first nut 11, so that it may so that the utility model is more clamped securely on hook, when in use,
The cable being exposed at outside well head can be directly wound in pulley bracket 7 on pulley 10, without as before, being wound on hook
On, frictional resistance is significantly reduced, such worker is not only time saving and energy saving in drag cable, but also can extend cable
Service life.
Above-mentioned cable sheave device can be made further optimization and/or improvements according to actual needs:
As shown in attached drawing 1,2,4, big hook support 6 is the rectangle frame that downside lacks lower frame, and pulley bracket 7 is that upside lacks
The rectangle frame of upper side frame, the downside of big hook support 6 is corresponding with the upside of pulley bracket 7, the left frame and pulley of big hook support 6
The left frame of stent 7 is fixedly connected, and the left frame of the Right Border and pulley bracket 7 of big hook support 6 is dislocatedly distributed, pulley bracket
Gap is provided between the upper surface of 7 left frames and the lower end of the second stud shaft 9.Such notch design, can facilitate cable,
Pulley bracket 7 is quickly placed and taken out, execute-in-place is simple, saves the time.
As shown in attached drawing 1,2,4,6 inside of big hook support of 8 top of the first stud shaft is at least provided with two cushion blocks 13, cushion block
13 are fixedly connected respectively with the left frame of big hook support 6 and left frame.When having the presence of cushion block 13, then tightening the first stud shaft 8,
The downside of hook will make the utility model when worker pulls cable, it is not easy to shake, be more advantageous to by the tighter of card
Work.
As shown in Figure 1, it is provided with clamp 14 on first stud shaft 8 on 11 right side of the first nut.Since this position is in hook
Stress is larger during handling, therefore the first nut 11 has the presence of clamp 14, with regard to that can carry there are larger stripped thread risk
The security of high the utility model.
As shown in Figure 1, the bearing that can be rotated with movable pulley 10 is provided on the second stud shaft 9 of 10 left and right ends of pulley
15.The rotatably fluency of pulley 10 can be so improved, makes pulley 10 that card resistance phenomenon to be less likely to occur.
As shown in Figure 1, the middle part of pulley 10 is provided with the groove 16 of arc-shaped, and the both sides of groove 16 or so are all using oblique
Slope and arc transition.This groove 16 is half to the arc section between 3/4ths circles, so that cable is conveniently being put
While entering and take out, it is also possible to prevent that card resistance occurs because of job-hopping during cable pulls, if so can not only damage
Hinder cable, but also job schedule can be influenced.
More than technical characteristic constitutes the most preferred embodiment of the utility model, with stronger adaptability and optimal implementation
Effect can increase and decrease non-essential technical characteristic, to meet the needs of different situations according to actual needs.
Claims (10)
1. a kind of cable sheave device, it is characterised in that including big hook support, pulley bracket, pulley, big hook support and pulley branch
Frame is all frame assembly, and pulley bracket is fixedly connected on the lower section of big hook support, hook is provided through on big hook support
First stud shaft of the left and right frame of stent, the right end of the first stud shaft are provided be fixed on the first stud shaft on big hook support first
Nut is provided through the second stud shaft of the left and right frame of pulley bracket on pulley bracket, and pulley is arranged on the second stud shaft,
The right end of second stud shaft is provided with the second nut being fixed on the second stud shaft on pulley bracket.
2. cable sheave device according to claim 1, it is characterised in that big hook support is the square that downside lacks lower frame
Shape frame, pulley bracket are the rectangle frames that upside lacks upper side frame, and the downside of big hook support is corresponding with the upside of pulley bracket, greatly
The left frame of hook support is fixedly connected with the left frame of pulley bracket, the Right Border of big hook support and the left frame of pulley bracket
It is dislocatedly distributed, gap is provided between the lower end of the upper surface of pulley bracket left frame and the second stud shaft.
3. cable sheave device according to claim 1 or 2, it is characterised in that on the inside of the big hook support above the first stud shaft
At least provided with two cushion blocks, cushion block is fixedly connected respectively with the left frame of big hook support and left frame.
4. cable sheave device according to claim 1 or 2, it is characterised in that set on the first stud shaft on the right side of the first nut
It is equipped with clamp.
5. cable sheave device according to claim 3, it is characterised in that set on the first stud shaft on the right side of the first nut
There is clamp.
6. according to the cable sheave device described in claim 1 or 2 or 5, it is characterised in that the second stud shaft of pulley left and right ends
On be provided with the bearing that can drive pulley rotation.
7. cable sheave device according to claim 3, it is characterised in that set on the second stud shaft of pulley left and right ends
The bearing of pulley rotation can be driven by having.
8. cable sheave device according to claim 4, it is characterised in that set on the second stud shaft of pulley left and right ends
The bearing of pulley rotation can be driven by having.
9. according to the cable sheave device described in claim 1 or 2 or 5 or 7 or 8, it is characterised in that be provided in the middle part of pulley
The both sides of the groove of arc-shaped, groove or so all use slope and arc transition.
10. cable sheave device according to claim 6, it is characterised in that the ditch of arc-shaped is provided in the middle part of pulley
The both sides of slot, groove or so all use slope and arc transition.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721394594.4U CN207418036U (en) | 2017-10-26 | 2017-10-26 | Cable sheave device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721394594.4U CN207418036U (en) | 2017-10-26 | 2017-10-26 | Cable sheave device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207418036U true CN207418036U (en) | 2018-05-29 |
Family
ID=62310016
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721394594.4U Active CN207418036U (en) | 2017-10-26 | 2017-10-26 | Cable sheave device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207418036U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109723431A (en) * | 2018-11-22 | 2019-05-07 | 中国石油天然气集团有限公司 | One kind can survey tension producing well pulley gear |
-
2017
- 2017-10-26 CN CN201721394594.4U patent/CN207418036U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109723431A (en) * | 2018-11-22 | 2019-05-07 | 中国石油天然气集团有限公司 | One kind can survey tension producing well pulley gear |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207418036U (en) | Cable sheave device | |
CN206712343U (en) | A kind of fast and easily double-hook wire grip | |
CN105977870A (en) | Power leading-down cable fixing device | |
CN201665475U (en) | Lifting hook and rope stop support thereof | |
CN207209844U (en) | A kind of discharge device of hoist engine | |
CN209367713U (en) | A kind of wireline winch | |
CN209658844U (en) | A kind of NLL type strain clamp for preventing conducting wire from wearing | |
CN203345975U (en) | Hoisting steel wire rope mounting device and tower crane | |
CN207398801U (en) | A kind of antiwind strain relief clamp of vertical | |
CN213622872U (en) | Be used for hoist wire rope rigging of being convenient for to fix | |
CN205829031U (en) | Electric power draws lower cable fixture | |
CN214031412U (en) | Aluminum coil lifting device | |
CN209571767U (en) | A kind of machete OK a karaoke club power test fixture | |
CN201090665Y (en) | Steel rope lengthening clamp device | |
CN203306959U (en) | Hoisting drum steel wire end fixing device and workover rig | |
CN103950817B (en) | There is the circular electromagnetic chunk device of anti-rotational equilibrium function | |
CN201914849U (en) | A device for preventing wire rope empty hooks from picking up messy ropes | |
CN208292511U (en) | A kind of steel part dome lid lifting tool | |
CN206811833U (en) | A kind of portable elevator reparing combination rope clamp | |
CN217676306U (en) | Hoisting connecting device | |
CN205724668U (en) | A kind of tightener for stringing | |
CN220393067U (en) | Anti-slip sling | |
CN218968610U (en) | Steel wire rope rigging capable of reducing abrasion degree | |
CN206708309U (en) | Tooth-like wire-rope connecting device | |
CN212315318U (en) | Lifting hook clamp convenient to use |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20201105 Address after: 100120 Beijing Xicheng District six laying Kang Patentee after: CHINA NATIONAL PETROLEUM Corp. Patentee after: CNPC Xibu Drilling Engineering Co.,Ltd. Address before: 830026 West Central Asia South Road, Urumqi Development Zone, the Xinjiang Uygur Autonomous Region, No. 326 drilling and directional well technical service company Patentee before: CNPC Xibu Drilling Engineering Co.,Ltd. |
|
TR01 | Transfer of patent right |