CN207363110U - Novel concrete supporting beam - Google Patents
Novel concrete supporting beam Download PDFInfo
- Publication number
- CN207363110U CN207363110U CN201721062432.0U CN201721062432U CN207363110U CN 207363110 U CN207363110 U CN 207363110U CN 201721062432 U CN201721062432 U CN 201721062432U CN 207363110 U CN207363110 U CN 207363110U
- Authority
- CN
- China
- Prior art keywords
- sleeve
- beam body
- supporting beam
- connecting pole
- suspension hook
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a kind of novel concrete supporting beam, its key points of the technical solution are that including beam body, the both ends of the beam body are each provided with a hooking assemblies, the hooking assemblies include suspension hook, connecting pole and sleeve, suspension hook is fixedly connected at the top of connecting pole, external screw thread is provided with the outer wall of connecting pole and is connected with bush whorl, sleeve is fixedly connected in beam body and end face is less than or flushes in the upper surface of beam body thereon.The suspension hook that the utility model is solved in existing cement supporting beam is pounding the curved upper surface that can be also significantly larger than cement supporting beam later, causes to take the problem of building board put is not smooth enough thereon.
Description
Technical field
Construction material is the utility model is related to, more particularly to a kind of novel concrete supporting beam.
Background technology
Cement supporting beam is a kind of more common construction material, is usually used in building as floor, cover board etc. under construction
The supporter of plate.The weight of cement supporting beam is larger, carries for convenience, installation, and in joints cement supporting beam, work people
Member can be after each pre-buried suspension hook in the both ends of cement supporting beam, cement supporting beam solidification, and suspension hook and cement supporting beam connect into
One entirety, coordinates suspension hook conveniently to carry, installs cement supporting beam by hanging apparatus.
After cement supporting beam is installed on construction wall, to take put the building boards such as floor, cover board thereon, in order to avoid hanging
Hook influence building board flatness, staff suspension hook can be pounded using weight it is curved, but even if pound it is curved after, suspension hook also can be remote
Far above the upper surface of cement supporting beam, cause to take the building board put thereon not smooth enough.
Utility model content
The purpose of this utility model is to provide a kind of novel concrete supporting beam, it can conveniently remove hanging thereon
Hook so that cement supporting beam keeps smooth.
The above-mentioned purpose of the utility model technical scheme is that:A kind of novel concrete supporting beam,
Including beam body, the both ends of the beam body are each provided with a hooking assemblies, the hooking assemblies include suspension hook, connecting pole with
And sleeve, suspension hook are fixedly connected at the top of connecting pole, are provided with external screw thread on the outer wall of connecting pole and are connected with bush whorl, are covered
Cylinder is fixedly connected in beam body and end face is less than or flushes in the upper surface of beam body thereon.
By using above-mentioned technical proposal, when branch sleeve and beam body, sleeve is put vertically before beam body pours
Enter to pour in mould, in order to avoid concrete enters sleeve inner, connecting pole is being screwed into sleeve before pouring, is then being carried out
Pour, the upper surface for pouring after sleeve is less than or flushes in the upper surface of beam body, and after the solidification of beam body and sleeve forms one
A entirety.
During lifting, suspension hook is coordinated to carry, cement supporting beam is installed using hanging apparatus.After the completion of lifting, by connecting pole
Back-out sleeve, the upper surface of sleeve is less than or flushes in the upper surface of beam body, therefore there is no convex for the upper surface of beam body
Go out thing, smooth working face can be showed, and then take the building board being placed on thereon can also keep smooth.In hooking assemblies, hang
Separating for hook is more laborsaving, and then using more convenient.
The utility model is further arranged to:Two hooking assemblies are symmetrical arranged.
By using above-mentioned technical proposal so that when cement supporting beam is sling stress evenly, and then cement supporting beam
Lifting is more convenient.
The utility model is further arranged to:Embedded ribs are fixedly connected with the outer wall of the sleeve, embedded ribs integrally pour
Build in beam body.
By using above-mentioned technical proposal, embedded ribs mating sleeve plays the role of increase and beam body connection area,
So that the connection of sleeve and beam body is more firm, and then hooking assemblies can be suitably used for the beam body of weight bigger.
The utility model is further arranged to:The embedded ribs are made of more reinforcing bars, and reinforcing bar is symmetrical around sleeve,
One end of reinforcing bar is fixedly connected with sleeve and the axis of reinforcing bar is vertical with the axis of sleeve.
By using above-mentioned technical proposal, embedded ribs are uniformly connected in the beam body of all around stems so that sleeve and beam
The connection of body is more firm.
The utility model is further arranged to:Suspension hook is integrally C-shaped, and the both ends of suspension hook are fixedly connected on connecting pole.
By using above-mentioned technical proposal so that the connection of suspension hook and connecting pole is more firm.
The utility model is further arranged to:The cement supporting beam further includes plug assembly, and the plug assembly includes
Stick harness and the counterbore for being opened in stick harness top surface, are provided with the external screw thread coordinated with sleeve on the outer wall of stick harness, when stick harness is positioned at set
When in cylinder, the top surface of stick harness and the either flush of beam body.
By using above-mentioned technical proposal, when stick harness is located in sleeve, the top surface of stick harness and the either flush of beam body,
Impurity can be prevented to enter in sleeve.Size, the shape of counterbore can coordinate with existing allen wrench, when needing to remove again
When fortune, installation cement supporting beam, stick harness can be removed using allen wrench, connecting pole is then reconnected into sleeve
In.
In conclusion the utility model has the advantages that:During lifting, suspension hook is coordinated to remove using hanging apparatus
Fortune, installation cement supporting beam.After the completion of lifting, connecting pole is back-outed into sleeve, the upper surface of sleeve is less than or flushes in beam sheet
The upper surface of body, therefore ridge is not present in the upper surface of beam body, can show smooth working face, and then take and be placed on thereon
Building board can also keep smooth.In hooking assemblies, separating for suspension hook is more laborsaving, and then using more convenient.
Brief description of the drawings
Fig. 1 is the axonometric drawing of embodiment 1;
Fig. 2 is to represent explosive view that the fit structure of hooking assemblies and beam body is done in embodiment 1;
Fig. 3 is to represent explosive view that the fit structure of beam body and plug assembly is done in embodiment 2.
In figure, 1, beam body;2nd, hooking assemblies;20th, suspension hook;21st, connecting pole;22nd, sleeve;220th, embedded ribs;3rd, block
Component;30th, stick harness;31st, counterbore.
Embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment 1:A kind of novel concrete supporting beam, with reference to Fig. 1, including beam body 1, for the ease of the lifting of beam body 1,
One hooking assemblies 2 is respectively set at the both ends of beam body 1, it is contemplated that cement supports the uniformity of beam stress, two hooking assemblies 2
It is symmetrical arranged.
With reference to Fig. 2, hooking assemblies 2 include suspension hook 20, connecting pole 21 and sleeve 22, and three selects metal to manufacture.
Suspension hook 20 is fixedly connected on connecting pole 21, in order to make suspension hook 20 and the connection of connecting pole 21 more firm, by suspension hook
20 are arranged to C-shaped, and the both ends of suspension hook 20 are fixedly connected on connecting pole 21.
Sleeve 22 is fixedly connected with beam body 1, and the upper surface of sleeve 22 is less than or flushes in the upper surface of beam body 1.
Sleeve 22 is threadedly coupled with connecting pole 21, and internal thread is provided with the inner wall of sleeve 22, is coordinated on the outer wall of connecting pole 21
There is external screw thread.
When branch sleeve 22 and beam body 1, in sleeve 22 is put into vertically before beam body 1 pours pours mould, it is
Avoid concrete from entering inside sleeve 22, connecting pole 21 is being screwed into sleeve 22 before pouring, is then poured, poured
The top surface of connecting pole 21 is concordant with the upper surface holding of beam body 1 afterwards, and after beam body 1 solidifies and sleeve 22 forms an entirety.
In order to make the connection of sleeve 22 and beam body 1 more firm, embedded ribs are fixedly connected with the outer wall of sleeve 22
220.Embedded ribs 220 are made of more reinforcing bars, and reinforcing bar is symmetrical around sleeve 22, and one end of reinforcing bar is fixedly connected with sleeve 22
And the axis of reinforcing bar is vertical with the axis of sleeve 22.When pouring, embedded ribs 220 pour in beam body 1 together, embedded ribs 220
Mating sleeve 22 plays the role of increase and 1 connection area of beam body so that and sleeve 22 and the connection of beam body 1 are more firm,
And then hooking assemblies 2 can be suitably used for the beam body 1 of weight bigger.
During lifting, suspension hook is coordinated to carry, cement supporting beam is installed using hanging apparatus.After the completion of lifting, by connecting pole
21 back-out sleeve 22, and the upper surface of sleeve 22 is less than or flushes in the upper surface of beam body 1, therefore the upper surface of beam body 1
There is no ridge, can show smooth working face, and then takes the building board being placed on thereon and can also keep smooth.Hook group
During the use of part 2, separating for suspension hook 20 is more laborsaving, and use is more convenient.
Embodiment 2:Difference lies in reference to Fig. 3, the cement supporting beam later stage can also be related to the present embodiment with embodiment 1
Carry and install, so also needing to lift, in order to avoid debris blocks sleeve 22, after connecting pole 21 is removed, in sleeve 22
Plug assembly 3 is set.
Plug assembly 3 includes stick harness 30 and is opened in the counterbore 31 of 30 top surface of stick harness.Be provided with the outer wall of stick harness 30 with
The external screw thread that sleeve 22 coordinates.When stick harness 30 is located in sleeve 22, the top surface of stick harness 30 and the either flush of beam body 1 can
To prevent impurity from entering in sleeve 22.Size, the shape of counterbore 31 can coordinate with existing allen wrench, when need again
When carrying, cement supporting beam being installed, stick harness 30 can be removed using allen wrench, then reconnect to connecting pole 21
In sleeve 22.
This specific embodiment is only explanation to the utility model, it is not the limitation to the utility model, ability
Field technique personnel as needed can make the present embodiment the modification of no creative contribution after this specification is read, but
As long as all protected in the right of the utility model be subject to Patent Law.
Claims (6)
1. a kind of novel concrete supporting beam, including beam body (1), it is characterised in that:The both ends of the beam body (1) are each provided with
One hooking assemblies (2), the hooking assemblies (2) include suspension hook (20), connecting pole (21) and sleeve (22), and suspension hook (20) is solid
Surely it is connected at the top of connecting pole (21), is provided with external screw thread on the outer wall of connecting pole (21) and is threadedly coupled with sleeve (22), covers
Cylinder (22) is fixedly connected in beam body (1) and end face is less than or flushes in the upper surface of beam body (1) thereon.
2. novel concrete supporting beam according to claim 1, it is characterised in that:Two hooking assemblies (2) symmetrically set
Put.
3. novel concrete supporting beam according to claim 2, it is characterised in that:It is fixed on the outer wall of the sleeve (22) to connect
Embedded ribs (220) are connected to, embedded ribs (220) formed by integrally casting is in beam body (1).
4. novel concrete supporting beam according to claim 3, it is characterised in that:The embedded ribs (220) are by more reinforcing bars
Composition, reinforcing bar is symmetrical around sleeve (22), and one end of reinforcing bar is fixedly connected with sleeve (22) and the axis and sleeve of reinforcing bar
(22) axis is vertical.
5. novel concrete supporting beam according to claim 4, it is characterised in that:Overall C-shaped, the suspension hook (20) of suspension hook (20)
Both ends be fixedly connected on connecting pole (21).
6. novel concrete supporting beam according to claim 5, it is characterised in that:The cement supporting beam further includes occlusion group
Part (3), the plug assembly (3) includes stick harness (30) and is opened in the counterbore (31) of stick harness (30) top surface, outside stick harness (30)
Be provided with wall with sleeve (22) coordinate external screw thread, when stick harness (30) be located in sleeve (22), the top surface of stick harness (30) and
The either flush of beam body (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721062432.0U CN207363110U (en) | 2017-08-23 | 2017-08-23 | Novel concrete supporting beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721062432.0U CN207363110U (en) | 2017-08-23 | 2017-08-23 | Novel concrete supporting beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207363110U true CN207363110U (en) | 2018-05-15 |
Family
ID=62422345
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721062432.0U Expired - Fee Related CN207363110U (en) | 2017-08-23 | 2017-08-23 | Novel concrete supporting beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207363110U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107355044A (en) * | 2017-08-23 | 2017-11-17 | 北京四方如钢混凝土制品有限公司 | Novel concrete support beam |
-
2017
- 2017-08-23 CN CN201721062432.0U patent/CN207363110U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107355044A (en) * | 2017-08-23 | 2017-11-17 | 北京四方如钢混凝土制品有限公司 | Novel concrete support beam |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211572573U (en) | Bottom template suspension structure of integral seam of two-way prefabricated superimposed sheet | |
CN106150055A (en) | Concrete embedded part essence flat hanging installment work stand and the installation method of built-in fitting | |
CN209907925U (en) | Casting device for supporting-free lifting mould and post-cast strip | |
CN102733608B (en) | Construction method for spray head layer of granulation tower | |
CN109732773B (en) | Mounting node and mounting method of support hinged concrete prefabricated part | |
CN110303577A (en) | A kind of prefabricated window production mould and assembly and disassembly method of floaing | |
CN207363110U (en) | Novel concrete supporting beam | |
CN202099933U (en) | Precast column and lifting appliance thereof | |
CN103552911B (en) | A kind of movable boom hoisting and the construction installation method of use thereof | |
CN205442393U (en) | Posture that falls suspension system | |
CN107355044A (en) | Novel concrete support beam | |
CN113802562B (en) | Steel reinforcement cage circulating hanging bar device and use method thereof | |
CN214195611U (en) | Be used for concrete wall body to pour couple formula operation platform | |
CN202401026U (en) | Construction equipment for installing flue elbow pipe through pulley lifting | |
CN206034922U (en) | A tumbling barrel device for high altitude (HA) vertical member concrete placement | |
CN206267520U (en) | A kind of self-supporting post-cast strip is poured with hanging mould | |
CN208455941U (en) | A kind of building precast beam | |
CN205314566U (en) | Cone makes up wall screw | |
CN210313146U (en) | Simple and easy panel hoist and mount and consolidate couple | |
CN210529735U (en) | Building steel structure platform base | |
CN202045351U (en) | Guide device for dummy bar of continuous casting machine | |
CN112627053A (en) | Hoisting structure for UHPC (ultra high performance polycarbonate) short-rib prefabricated slab | |
CN218323870U (en) | Die carrier system of section of pouring does not have pull rod | |
CN220283270U (en) | Cast-in-place concrete floor pours negative muscle protective layer square pipe support body hoisting structure | |
CN207498986U (en) | Pipe gallery Quick Release formwork erecting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180515 |