CN207032046U - A kind of constructing tie beam steel platform for carrying bored concrete pile in liftable water - Google Patents
A kind of constructing tie beam steel platform for carrying bored concrete pile in liftable water Download PDFInfo
- Publication number
- CN207032046U CN207032046U CN201720680390.0U CN201720680390U CN207032046U CN 207032046 U CN207032046 U CN 207032046U CN 201720680390 U CN201720680390 U CN 201720680390U CN 207032046 U CN207032046 U CN 207032046U
- Authority
- CN
- China
- Prior art keywords
- stretching
- several
- shaped steel
- platform
- extension post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (10)
- A kind of 1. constructing tie beam steel platform for carrying bored concrete pile in liftable water, it is characterised in that:If by several studdles, Dry bearing beam, several shaped steel, several channel-section steels, construction platform and connection ladder composition, any studdle is by basis Post, several stretching, extension posts and support column composition, any stretching, extension post are located at the top of foundation columns, the stretching, extension post and foundation columns To be fixedly connected, the support column is to be fixedly connected with stretching, extension post positioned at the top of stretching, extension post, the support column, any pad Beam is located at the top of studdle, and for the bearing beam with studdle to be fixedly connected, any shaped steel is located at the top of bearing beam, For the shaped steel with bearing beam to be fixedly connected, any channel-section steel is located at the top of shaped steel, and the channel-section steel is to be flexibly connected with shaped steel, The construction platform is located at the side of studdle, and the construction platform is to be fixedly connected with studdle, the terraced position of connection In the side of construction platform, the connection ladder is to be fixedly connected with construction platform.
- A kind of 2. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1, it is characterised in that:Institute The quantity for stating several studdles is multiple, and is spiral steel pipe pile.
- A kind of 3. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1, it is characterised in that:Appoint Described stretch of anticipating is additionally provided with several stretching, extension post positioning holes, several stretching, extension post fixing holes and several stretching, extension posts fixation spiral shells on post Bolt, the stretching, extension post positioning hole, to be fixedly connected, are appointed positioned at the side of stretching, extension post bottom, the stretching, extension post positioning hole with stretching, extension post The stretching, extension post fixed hole position of anticipating, to be fixedly connected, is appointed in the side on stretching, extension post top, the stretching, extension post fixing hole with stretching, extension post The stretching, extension post fixing bolt of anticipating is fixed positioned at the side of stretching, extension post fixing hole, the stretching, extension post fixing bolt through stretching, extension post Hole, and be to be fixedly connected with stretching, extension post, support column through the support column fixing hole on support column, several described stretching, extension posts are determined The quantity in position hole is identical with the quantity of foundation columns fixing hole, quantity and the stretching, extension post positioning hole of several stretching, extension post fixing holes Quantity it is identical, it is described several stretching, extension post fixing bolts quantity with stretching, extension post fixing hole quantity it is identical.
- A kind of 4. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1, it is characterised in that:Institute The quantity for stating several stretching, extension posts is multiple.
- A kind of 5. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 3, it is characterised in that:Institute State and several foundation columns fixing holes and several foundation columns fixing bolts are additionally provided with foundation columns, any foundation columns fixing hole Positioned at the side on foundation columns top, for the foundation columns fixing hole with foundation columns to be fixedly connected, any foundation columns fix spiral shell Bolt is located at the side of foundation columns fixing hole, and the foundation columns fixing bolt passes through foundation columns fixing hole, and passes through on stretching, extension post Stretching, extension post positioning hole and foundation columns, stretching, extension post to be fixedly connected, the quantity of several foundation columns fixing holes is multiple, institute The quantity for stating several foundation columns fixing bolts is identical with the quantity of foundation columns fixing hole.
- 6. a kind of constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1 or claim 3, its It is characterised by:Several support column fixing holes and support platform are additionally provided with the support column, any support column fixing hole Positioned at the side on support column top, the support column fixing hole is with support column to be fixedly connected, and the support platform is positioned at support The top of post, the support platform, to be fixedly connected, are additionally provided with several support platforms and determined with support column in the support platform Position hole, any support platform positioning hole are located at the middle part of support platform, and the support platform positioning hole is with support platform It is fixedly connected, the quantity of several support column fixing holes is identical with the quantity for stretching post fixing hole.
- A kind of 7. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1, it is characterised in that:Institute The quantity for stating several bearing beams is 2, and is Two bors d's oeuveres bearing beam.
- A kind of 8. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1, it is characterised in that:Appoint Anticipate and be additionally provided with several bearing beam fixing bolts and several shaped steel positioning holes on the bearing beam, any bearing beam fixing bolt position In the side of bearing beam, the bearing beam fixing bolt is to be fixedly connected with studdle through bearing beam, any shaped steel positioning hole Positioned at the top of bearing beam, with bearing beam to be fixedly connected, the quantity of several bearing beam fixing bolts is the shaped steel positioning hole Multiple, the quantity of several shaped steel positioning holes is multiple.
- A kind of 9. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1, it is characterised in that:Appoint Anticipate and be additionally provided with several shaped steel fixing holes, several Profiled fixing bolts and several barrier locating dowels on the shaped steel, arbitrarily The shaped steel fixed hole position is in the side of shaped steel, and the shaped steel fixing hole with shaped steel to be fixedly connected, fix by any shaped steel Bolt is located at the top of shaped steel fixing hole, and the Profiled fixing bolt is to be fixedly connected with bearing beam through shaped steel fixing hole, arbitrarily The barrier locating dowel is located at the top of shaped steel, and the barrier locating dowel with shaped steel to be fixedly connected, consolidate by several described shaped steel The quantity for determining hole is multiple, and the quantity of several Profiled fixing bolts is identical with the quantity of shaped steel fixing hole, described some The quantity of individual barrier locating dowel is multiple.
- A kind of 10. constructing tie beam steel platform for carrying bored concrete pile in liftable water according to claim 1, it is characterised in that: The quantity of several shaped steel is multiple, and the quantity of several channel-section steels is multiple.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720680390.0U CN207032046U (en) | 2017-06-13 | 2017-06-13 | A kind of constructing tie beam steel platform for carrying bored concrete pile in liftable water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720680390.0U CN207032046U (en) | 2017-06-13 | 2017-06-13 | A kind of constructing tie beam steel platform for carrying bored concrete pile in liftable water |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207032046U true CN207032046U (en) | 2018-02-23 |
Family
ID=61471162
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720680390.0U Expired - Fee Related CN207032046U (en) | 2017-06-13 | 2017-06-13 | A kind of constructing tie beam steel platform for carrying bored concrete pile in liftable water |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207032046U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107119571A (en) * | 2017-06-13 | 2017-09-01 | 天津第市政公路工程有限公司 | A kind of constructing tie beam steel platform and its assembling and application method for carrying bored concrete pile in liftable water |
-
2017
- 2017-06-13 CN CN201720680390.0U patent/CN207032046U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107119571A (en) * | 2017-06-13 | 2017-09-01 | 天津第市政公路工程有限公司 | A kind of constructing tie beam steel platform and its assembling and application method for carrying bored concrete pile in liftable water |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110512647B (en) | Structural design and construction method of a partially assembled subway station | |
CN210031842U (en) | Combined support system for adjacent deep foundation pits based on row piles, connecting beams and anchor cables | |
CN106049679A (en) | Super high-rise steel reinforced concrete framework core barrel structural system and construction method | |
CN112878354A (en) | Beam-slab assembled prestressed concrete foundation for onshore wind turbine generator | |
CN110468869B (en) | Reinforcing structure and method for P & H type rock anchor rod fan foundation | |
CN207143708U (en) | Hoisting type foundation pit-crossing comprehensive steel trestle | |
CN109184699B (en) | Construction method for passing existing river channel under open trench tunnel | |
CN105350503B (en) | Hydropower station underground powerhouse plant-to-traffic-hole structure and construction method thereof | |
CN107119571A (en) | A kind of constructing tie beam steel platform and its assembling and application method for carrying bored concrete pile in liftable water | |
CN106088120A (en) | Construction method is transferred in a kind of cofferdam | |
CN102704388A (en) | Anti-seismic and anti-flood semi-integral abutment seamless bridge and construction method thereof | |
CN207032046U (en) | A kind of constructing tie beam steel platform for carrying bored concrete pile in liftable water | |
CN108708290B (en) | Box bridge frame hollow structure of small-radius railway curve unit and cast-in-place construction method | |
CN102635061B (en) | Mountain stream river-crossing inclined zipper trestle and hoisting method thereof | |
CN111188275A (en) | Method for quickly erecting steel-concrete combined temporary bridge spanning existing tunnel U-shaped groove | |
CN116988481A (en) | Multiple inhaul cable supporting structure for old city reconstruction arc-shaped deep foundation pit and construction method | |
CN204401462U (en) | For the support of pier prestressed cap beam with extra length Construction Supporting System in water | |
CN210460676U (en) | Tunnel structure | |
CN204151662U (en) | A kind of one across the temporary trestle bridge crossing over river valley | |
CN209099202U (en) | A kind of scaffold for the construction of Wavelike steel webplate external prestressing | |
Nader et al. | Design and construction of the new Champlain bridge, Montreal, Canada | |
CN220079789U (en) | Combined support for bridge arch ring sleeve arch reinforcement construction of river-crossing bridge | |
CN104404884B (en) | For the support of pier prestressed cap beam with extra length Construction Supporting System in water | |
CN219240604U (en) | Novel prefabricated miniature foundation of piers of assembling of can strideing across city pipe network | |
CN220504665U (en) | Ectopic assembled H-shaped steel tower |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Li Weibo Inventor after: Xu Yi Inventor after: Duan Xiaojuan Inventor after: Xin Yanqing Inventor after: Cai Xiujiao Inventor after: Jing Yuge Inventor after: Liu Ruixia Inventor before: Li Weibo Inventor before: Xu Yi Inventor before: Duan Xiaojuan Inventor before: Bei Yanqing Inventor before: Cai Xiujiao Inventor before: Jing Yuge Inventor before: Liu Ruixia |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180223 Termination date: 20200613 |