CN207003707U - Prefabricating coping structure wall - Google Patents

Prefabricating coping structure wall Download PDF

Info

Publication number
CN207003707U
CN207003707U CN201720132273.0U CN201720132273U CN207003707U CN 207003707 U CN207003707 U CN 207003707U CN 201720132273 U CN201720132273 U CN 201720132273U CN 207003707 U CN207003707 U CN 207003707U
Authority
CN
China
Prior art keywords
wall
prefabricating coping
prefabricating
coping
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720132273.0U
Other languages
Chinese (zh)
Inventor
管仁彪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Weixian Shichuang Building Materials Technology Co ltd
Original Assignee
Hebei Crystal Building Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Crystal Building Polytron Technologies Inc filed Critical Hebei Crystal Building Polytron Technologies Inc
Priority to CN201720132273.0U priority Critical patent/CN207003707U/en
Application granted granted Critical
Publication of CN207003707U publication Critical patent/CN207003707U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of prefabricating coping structure wall, is related to technical field of civil, including prefabricating coping and wall, and the prefabricating coping lower end is fixedly connected by attachment structure with wall, and the cross section of the prefabricating coping is T-shaped.It is that T-shaped prefabricating coping is fixedly connected by attachment structure with lower section wall by cross section prefabricated in advance, reduces the tedious steps of site operation, accelerate construction speed, in the assembled architecture that is particularly suitable for use in construction, quick construction is convenient.

Description

Prefabricating coping structure wall
Technical field
It the utility model is related to technical field of civil, more particularly to a kind of prefabricating coping structure wall.
Background technology
Covered mostly using bearing down on one at the top of outdoor wall, such as parapet or windowsill top, one be by bearing down on one Can be with the stability of enhancing structure, but can play a part of protecting lower wall body.Existing wall bears down on one usually in wall Body construction finish at the top of it using brick, watt, galvanized iron sheet, concrete or armored concrete etc. build up the coating that bears down on one, it is this Coping structure is constructed with wall split, and construction speed is slow, is not particularly suited for assembled architecture.
Utility model content
Technical problem to be solved in the utility model is to be directed to above-mentioned the deficiencies in the prior art, there is provided a kind of prefabricating coping Structure wall, it is possible to increase construction speed, be particularly suitable for use in assembled architecture.
In order to solve the above technical problems, technical solution adopted in the utility model is:
A kind of prefabricating coping structure wall, including prefabricating coping and wall, the prefabricating coping lower end pass through attachment structure It is fixedly connected with wall, the cross section of the prefabricating coping is T-shaped.
Preferably, the attachment structure is steel sheet connection structure, and the prefabricating coping bottom side is L-type provided with cross section Junction steel plate, the junction steel plate vertical component effect is embedded in prefabricating coping bottom, and the junction steel plate horizontal part is arranged below The inboard of wall, the wall is horizontally disposed and top corresponds to and pre-embedded steel slab is provided with junction steel plate horizontal part, the connection steel Plate level portion is welded and fixed with pre-embedded steel slab.
Further, the junction steel plate applies screed-coat outside, and extruded sheet and polymer sand are sequentially provided with outside the screed-coat Pulp layer, extruded sheet inboard circular arc is excessive, outside is two orthogonal straight flanges, and two straight flanges of the extruded sheet are put down respectively Row is in prefabricating coping and wall.
Preferably, the prefabricating coping bottom outside is wiped one's face with wall end with anticracking grout, and brushing aqueous polyurethane.
Preferably, the attachment structure is concrete connecting structure, and the wall body vertical is set, and the prefabricating coping is set At the top of wall, the inside and outside side of the prefabricating coping bottom is integrated with concrete and wall pouring.
Preferably, the neck coordinated with prefabricating coping bottom is provided with the top of the wall.
Preferably, the prefabricating coping is reinforced concrete structure.
It is using beneficial effect caused by above-mentioned technical proposal:Prefabricating coping prefabricated in advance is tied by connecting Structure is fixedly connected with lower section wall, is reduced the tedious steps of site operation, is accelerated construction speed, and be particularly suitable for use in assembled In construction, quick construction is convenient.
Brief description of the drawings
Fig. 1 is the structural representation for the prefabricating coping structure wall that the utility model embodiment 1 provides;
Fig. 2 is the structural representation for the prefabricating coping structure wall that the utility model embodiment 2 provides;
In figure:1- prefabricating copings, 2- walls, 3- junction steel plates, 4- pre-embedded steel slabs, 5- screed-coats, 6- extruded sheets, 7- polymerizations Thing screed, 8- anticracking grouts, 9- concrete.
Embodiment
In order that the purpose of this utility model, technical scheme and advantage are more clearly understood, below in conjunction with accompanying drawing and specifically Embodiment, the utility model is described in further detail.It should be appreciated that specific embodiment described herein only to The utility model is explained, is not used to limit the utility model.
Referring to Fig. 1,2, a kind of prefabricating coping structure wall provided by the utility model, including prefabricating coping 1 and wall 2, The lower end of prefabricating coping 1 is fixedly connected by attachment structure with wall 2, and the cross section of the prefabricating coping 1 is T-shaped.
Embodiment 1:As shown in figure 1, the attachment structure is steel sheet connection structure, the bottom side of prefabricating coping 1 is set There is the junction steel plate 3 that cross section is L-type, the vertical component effect of junction steel plate 3 is embedded in the bottom of prefabricating coping 1, the junction steel plate 3 Horizontal part is arranged below the inboard of wall 2, and the wall 2 is horizontally disposed and top corresponds to and is provided with the horizontal part of junction steel plate 3 Pre-embedded steel slab 4, the horizontal part of junction steel plate 3 are welded and fixed with pre-embedded steel slab 4.Prefabricating coping in the embodiment can be used as female Youngster's wall, can be prefabricated in advance, treats in-site installation after wall construction, accelerating construction progress.Be particularly suitable for use in assembling It is efficient and convenient in formula construction.
In order to further optimize above-mentioned technical proposal, when prefabricating coping installs, water-proofing treatment is further done, it is described Junction steel plate 3 applies screed-coat 5 outside, and extruded sheet 6 and polymer mortar layer 7, the extruded sheet 6 are sequentially provided with outside the screed-coat 5 Inboard circular arc is excessive, outside is two orthogonal straight flanges, and two straight flanges of the extruded sheet 6 are respectively parallel to prefabricating coping 1 And wall 2.
In addition, the bottom outside of prefabricating coping 1 is wiped one's face with the end anticracking grout 8 of wall 2, and brush water-based poly- ammonia Ester, exterior surface of wall processing is finally done again.
Embodiment 2:As shown in Fig. 2 the attachment structure is concrete connecting structure, the wall 2 is vertically arranged, described Prefabricating coping 1 is arranged on the top of wall 2, and the inside and outside side of the bottom of prefabricating coping 1 is cast for one with concrete 9 and wall 2 Body.The embodiment can be applicable to windowsill position, using prefabricating coping bearing down on one as windowsill.In addition, concrete 9 can also extend to It is convenient that protection processing is done to external and internal wall with the top boss lower contact of prefabricating coping 1.
In order that prefabricating coping and wall strong bonded below, the wall top is provided with and prefabricating coping bottom coordinates Neck.
Wherein, above-mentioned prefabricating coping 1 is reinforced concrete structure, can process in advance prefabricated, treats that wall construction finishes again Transport to job site to be installed, so operation reduces construction procedure, accelerates construction speed.
Specific case used herein is set forth to principle of the present utility model and embodiment, above example Explanation be only intended to help and understand method and its core concept of the present utility model.It should be pointed out that for the art For those of ordinary skill, on the premise of the utility model principle is not departed from, some change can also be carried out to the utility model Enter and modify, these are improved and modification is also fallen into the protection domain of the utility model claims.

Claims (2)

  1. A kind of 1. prefabricating coping structure wall, it is characterised in that:Including prefabricating coping (1) and wall (2), the prefabricating coping (1) lower end is fixedly connected by attachment structure with wall (2), and the cross section of the prefabricating coping (1) is T-shaped, the connection knot Structure is steel sheet connection structure or concrete connecting structure;
    The attachment structure is steel sheet connection structure, and prefabricating coping (1) bottom side is provided with the connection steel that cross section is L-type Plate (3), junction steel plate (3) vertical component effect are embedded in prefabricating coping (1) bottom, and junction steel plate (3) horizontal part is arranged on The inboard of lower section wall (2), the wall (2) is horizontally disposed and top corresponds to and is provided with pre-buried steel at junction steel plate (3) horizontal part Plate (4), junction steel plate (3) horizontal part are welded and fixed with pre-embedded steel slab (4);The junction steel plate (3) applies screed-coat outside (5) extruded sheet (6) and polymer mortar layer (7), the inboard circular arc mistake of extruded sheet (6), are sequentially provided with outside the screed-coat (5) Degree, outside are two orthogonal straight flanges, and two straight flanges of the extruded sheet (6) are respectively parallel to prefabricating coping (1) and wall (2);Prefabricating coping (1) bottom outside is wiped one's face with wall (2) end with anticracking grout (8), and brushing aqueous polyurethane;
    The attachment structure is concrete connecting structure, and the wall (2) is vertically arranged, and the prefabricating coping (1) is arranged on wall At the top of body (2), the inside and outside side of prefabricating coping (1) bottom is integrated with concrete (9) and wall (2) cast;The wall The neck coordinated with prefabricating coping (1) bottom is provided with the top of body (2).
  2. 2. prefabricating coping structure wall according to claim 1, it is characterised in that:The prefabricating coping (1) is mixed for reinforcing bar Xtah Crude Clay structure.
CN201720132273.0U 2017-02-14 2017-02-14 Prefabricating coping structure wall Active CN207003707U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720132273.0U CN207003707U (en) 2017-02-14 2017-02-14 Prefabricating coping structure wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720132273.0U CN207003707U (en) 2017-02-14 2017-02-14 Prefabricating coping structure wall

Publications (1)

Publication Number Publication Date
CN207003707U true CN207003707U (en) 2018-02-13

Family

ID=61428287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720132273.0U Active CN207003707U (en) 2017-02-14 2017-02-14 Prefabricating coping structure wall

Country Status (1)

Country Link
CN (1) CN207003707U (en)

Similar Documents

Publication Publication Date Title
CN201087490Y (en) Novel steel reinforced concrete superimposed sheet
CN104358341B (en) A kind of building masonry and construction masonry method
CN201280725Y (en) Post-casting construction precast slab for basement of buildings
CN108589986A (en) One kind being based on bolted assembled composite wall structure and its construction method
CN209194768U (en) A kind of lightweight concrete slat door separation structure of the window
CN101787801A (en) Installation structure of building exhaust pipes and construction method thereof
CN104790436A (en) High-rise building basement roof settlement post-pouring joint advanced water stop construction method
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN104631513A (en) Construction method for closing basement exterior wall post-cast strip
CN105780976A (en) Compound concrete shear wall structure and concrete pouring method thereof
CN208023601U (en) A kind of prefabricated pile foundation support table side form of mutual buckle type
CN103206088A (en) Shear wall structural wall and slab integral pouring construction method
CN103615076A (en) Concrete construction method for big-gradient sloping roof
CN209686857U (en) Deep basal pit outer wall of basement shape steel bracket diagonal brace single side formwork system
CN107605107A (en) A kind of method for controlling pitched roof concrete construction quality
CN215563552U (en) Vertical joint construction of prefabricated wallboard based on ultra high performance concrete form
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN206859272U (en) The interim block structure of outer wall of basement pouring after settlement
CN102433894B (en) Construction method for station side wall by covered top-down excavation method
CN109750832A (en) A kind of construction method of constructional column concrete self-compaction
CN207003707U (en) Prefabricating coping structure wall
CN202865996U (en) Room modular structure for nuclear power plant
CN211646906U (en) Assembly type superposed component node optimization structure
CN204418691U (en) A kind of for cast-in-place vertical member and horizontal member junction concrete blocking apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240912

Address after: 056800 workshop 3, No. 11 Chuangye street, Weixian Economic Development Zone, Handan City, Hebei Province

Patentee after: Weixian Shichuang Building Materials Technology Co.,Ltd.

Country or region after: China

Address before: 056800 11 Chuang Chuang street, Weixian Economic Development Zone, Handan, Hebei

Patentee before: HEBEI JINGTONG BUILDING TECHNOLOGY Corp.

Country or region before: China