CN206495682U - A kind of stand quickly handled for Tunnel Landslide - Google Patents
A kind of stand quickly handled for Tunnel Landslide Download PDFInfo
- Publication number
- CN206495682U CN206495682U CN201720106110.5U CN201720106110U CN206495682U CN 206495682 U CN206495682 U CN 206495682U CN 201720106110 U CN201720106110 U CN 201720106110U CN 206495682 U CN206495682 U CN 206495682U
- Authority
- CN
- China
- Prior art keywords
- shaped steel
- frame
- tunnel
- arch
- steel arch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
The utility model provides a kind of stand quickly handled for Tunnel Landslide, belong to construction engineering technical field, its structure includes the tunnel arch roof at shaped steel arch and door frame, the apical margin apical grafting landslide of shaped steel arch, and shaped steel arch and longitudinal reinforcement constitute overall arch support body;Door frame is arranged on the interior of shaped steel arch and enclosed, and the bottom of door frame is sat by jack to be located on Tunnel Landslide body;Door frame uses the frame shape door frame being made up of left frame, top frame, correct frame;Protection plate is provided between shaped steel arch and tunnel arch roof;The collapse bottom of chamber passes through concrete delivery pump pipe concrete of spraying and constitutes concrete curing layer;Collapse chamber top pass through light filler delivery pipe spray light filler constitute light filler cured layer.The stand is using protection plate combination supporting stand, and execute-in-place is simple, and preliminary preparation is few, it is to avoid the process such as a large amount of backfill holes slag stable landslide bodies, and small landslide in face can be handled rapidly.
Description
Technical field
The utility model is related to construction engineering technical field, specifically a kind of platform quickly handled for Tunnel Landslide
Frame.
Background technology
In recent years, in terms of constructing tunnel, arch and face cave in accident happen occasionally, and especially complicated geology is soft
Weak country rock location, although taking advance support measure, is influenceed by geology, design and construction many factors, and landslide is outstanding
It is that middle-size and small-size landslide is almost difficult to avoid that.The method for handling middle-size and small-size landslide at present is a lot, mainly have pipe shed method, slip casting method,
Combination of self-feeding anchor pile method and several method etc., but be all difficult to meet safe and efficient require.Sent out in face and vault
The most frequently used technology is during raw medium and small landslide:Collapse the stable landslide body of the basicly stable rear gunite concrete in cave, grouting reinforcement landslide body,
By the use of collapsing body slag or support is set up as job platform, the chamber that collapses on platform in the stable certain altitude of gunite concrete, from
The chamber that collapses distally starts to install steel arch-shelf, and sets Shed-pipe Advanced Support, and bow member sets dividing plate gunite concrete, drawn near by Pin behind
Closing, during according to cave height is collapsed and delivery pump pipe is buried in aperture, all support, pump are set after closing on the outside of supporting in the early stage
Certain thickness concrete formation consolidation circle is sent, then the cave that is not filled by more than consolidation circle collapsing is partially filled with the sand of adding coal ash
Slurry, dry husky or other light materials, form cushion, and the technology preferably resolves processing and collapsed difficulty present in work of spreading manuer in holes
Greatly, the problems such as big quality of coming to nothing behind is difficult to ensure that.But process cycle is longer, there is possibility of caving in again in work progress,
There is certain security risk.
Small sump remedy technology has that process is more, the cycle is longer, cost is larger, risk is higher etc. and asked in conventional tunnel
Topic.
The content of the invention
Technical assignment of the present utility model is to solve the deficiencies in the prior art quickly to handle for Tunnel Landslide there is provided one kind
Stand.
The technical solution of the utility model realizes that this is used for the stand that Tunnel Landslide is quickly handled in the following manner,
Its structure includes shaped steel arch and door frame,
Tunnel arch roof at the apical margin apical grafting landslide of shaped steel arch, two ends of shaped steel arch are along tunnel arch top
Wall extends downwardly and is fixed to landslide body edge part in end;
Longitudinal reinforcement is fixedly connected between adjacent two Pin shaped steel archs;
Shaped steel arch and longitudinal reinforcement constitute overall arch support body;
Door frame is arranged on the interior of shaped steel arch and enclosed, and the bottom of door frame is sat by jack to be located on Tunnel Landslide body;
Door frame uses the frame shape door frame being made up of left frame, top frame, correct frame;
Left position workbench is fixedly installed on the left of left frame;It is fixed between the inner edge of left position workbench and shaped steel arch to connect
It is connected to left position knighthead;
Right position workbench is fixedly installed on the right side of correct frame;It is fixed between the inner edge of right position workbench and shaped steel arch to connect
It is connected to right position knighthead;
Top position support bar is fixedly connected between at the top of top frame and shaped steel arch;
Stand diagonal brace has been respectively fixedly connected between left frame, correct frame and top frame;Stand diagonal brace and left frame, right frame
Horizontal brace has been respectively fixedly connected between frame;
Protection plate is provided between shaped steel arch and tunnel arch roof;
Top intracavitary of collapsing is provided with concrete delivery pump pipe and light filler below along the arch support body of tunnel inner chamber
Delivery pipe, the top of concrete delivery pump pipe is located at the lower section on light filler delivery pipe top;
The collapse bottom of chamber passes through concrete delivery pump pipe concrete of spraying and constitutes concrete curing layer;
Collapse chamber top pass through light filler delivery pipe spray light filler constitute light filler cured layer.
Two ends of shaped steel arch are fixedly connected with lock foot anchoring stock, and lock foot anchoring stock is anchored in the entity on the outside of tunnel.
Longitudinal reinforcement is fixedly connected between adjacent two Pin shaped steel archs;The cave scope ring welding of collapsing of longitudinal reinforcement outer rim is inserted
Connect guide ring, being installed in the ring of grafting guide ring along longitudinal direction in chamber ring scope of collapsing can be at the top of the protection plate formation of longitudinally-moving
Enclosed construction;It is fixedly connected between protection plate and shaped steel arch by grafting guide ring.
Light filler uses light-duty mortar.
Produced beneficial effect is the utility model compared with prior art:
This uses protection plate combination supporting stand for the stand that Tunnel Landslide is quickly handled, and execute-in-place is simple, preceding
Phase preparation is few, it is to avoid the process such as stable landslide bodies of a large amount of backfill holes slag, can handle small landslide in face rapidly.
Stand is in place using machinery in implementation process, and processing landslide operating personnel is applied under the protection of supporting stand
Work is speedily carried out rescue work, it is ensured that the security of personnel.
The general medium and small sump remedy cycle, the present invention can complete processing operation of speedily carrying out rescue work in 3 days, significantly more than 7 days
The working time is shortened, the multiplicating that landslide is avoided to greatest extent occurs and expanded.
The periphery supporting of supporting stand is used with designing identical bow member, be can be achieved to speedily carry out rescue work synchronous with permanent construction supporting, is subtracted
Working procedure is lacked.
Expense is saved more than 60% relative to conventional method, is truly realized the safe efficient and economic mesh of speedily carrying out rescue work that caves in
Mark.
Treat that landslide is basicly stable and this is moved into cave bottom of collapsing with excavator for the stand that Tunnel Landslide is quickly handled, utilize
Door frame jack fixes good position.Just manually hammer mode impacts each protection plate to watching close face.On the outside of plate
Gunite concrete formation preliminary bracing, is irrigated to vault above 2m using short pump line pump concrete, after concrete final set, is utilized
Long pump line irrigates light-duty mortar.When concrete strength reaches more than 10Mpa, stand is removed, spreading both sides bow member is completed all just
Phase supporting.
This is used for that the gantry designs that quickly handle of Tunnel Landslide to be reasonable, simple in construction, safe and reliable, easy to use, be easy to
Safeguard, have good value for applications.
Brief description of the drawings
Accompanying drawing 1 is the structural representation that combination protection stand of the present utility model makes;
Accompanying drawing 2 is the side structure schematic diagram for the step 1 that combination protection stand of the present utility model makes;
Accompanying drawing 3 is the protection of making step 2,3 stand of the present utility model structural representation in place and locking;
Accompanying drawing 4 is the protection of making step 2,3 stand of the present utility model side schematic view in place and locking;
Accompanying drawing 5 is that making step 4,5 of the present utility model sets lock foot anchoring stock, the structural representation of embedded delivery pump pipe;
Accompanying drawing 6 is that making step 4,5 of the present utility model sets lock foot anchoring stock, the side schematic view of embedded delivery pump pipe;
Accompanying drawing 7 is making step 6 of the present utility model, 7 concrete spraying supports, the structural representation for the chamber pump concrete that collapses
Figure;
Accompanying drawing 8 is the side signal of making step 6 of the present utility model, 7 concrete spraying supports, the chamber pump concrete that collapses
Figure;
Accompanying drawing 9 is that making step 8 of the present utility model collapses the structural representation of chamber pressure injection light material;
Accompanying drawing 10 is that making step 8 of the present utility model collapses the side schematic view of chamber pressure injection light material;
Accompanying drawing 11 is that construction procedure 9 of the present utility model removes the structural representation after stand;
Accompanying drawing 12 is that construction procedure 9 of the present utility model removes the side schematic view after stand.
Mark in accompanying drawing is represented respectively:
1st, shaped steel arch, 2, tunnel arch roof, 3, landslide body, 4, longitudinal reinforcement, 5, arch support body,
6th, door frame, 7, jack,
8th, left frame, 9, top frame, 10, correct frame,
11st, left position workbench, 12, left position knighthead,
13rd, right position workbench, 14, right position knighthead,
15th, position support bar is pushed up, 16, stand diagonal brace, 17, horizontal brace,
18th, plate is protected, 19, concrete delivery pump pipe, 20, light filler delivery pipe,
21st, collapse chamber, and 22, concrete curing layer, 23, light filler cured layer,
24th, lock foot anchoring stock,
25th, grafting guide ring.
Embodiment
A kind of stand quickly handled for Tunnel Landslide of the present utility model is said in detailed below below in conjunction with the accompanying drawings
It is bright.
As shown in drawings, a kind of stand quickly handled for Tunnel Landslide of the present utility model, its structure includes shaped steel
Bow member 1 and door frame,
Encircle along tunnel tunnel arch roof 2 at the apical margin apical grafting landslide of shaped steel arch 1, two ends of shaped steel arch 1
Shape roof extends downwardly and is fixed to the landslide edge part of body 3 in end;
Longitudinal reinforcement 4 is fixedly connected between adjacent two Pin shaped steel archs 1;
Shaped steel arch 1 and longitudinal reinforcement 4 constitute overall arch support body 5;
Door frame 6 is arranged on the interior of shaped steel arch 1 and enclosed, and the bottom of door frame 6 is sat by jack 7 to be located on Tunnel Landslide body 3;
Door frame 6 is using the frame shape door frame being made up of left frame 8, top frame 9, correct frame 10;
The left side of left frame 8 is fixedly installed left position workbench 11;It is solid between the inner edge of left position workbench and shaped steel arch
Surely it is connected with left position knighthead 12;
The right side of correct frame 10 is fixedly installed right position workbench 13;It is solid between the inner edge of right position workbench and shaped steel arch
Surely it is connected with right position knighthead 14;
Top position support bar 15 is fixedly connected between at the top of top frame 9 and shaped steel arch;
Stand diagonal brace 16 has been respectively fixedly connected between left frame 8, correct frame 10 and top frame 9;Stand diagonal brace 16 and a left side
Horizontal brace 17 has been respectively fixedly connected between framework, correct frame;
Protection plate 18 is provided between shaped steel arch and tunnel arch roof;
Below along the arch support body of tunnel inner chamber concrete delivery pump pipe 19 is provided with to top intracavitary of collapsing and lightweight is filled out
Material conveying tube 20, the top of concrete delivery pump pipe 19 is located at the lower section on the top of light filler delivery pipe 20;
The collapse bottom of chamber 21 passes through concrete delivery pump pipe concrete of spraying and constitutes concrete curing layer 22;
The collapse top of chamber 21 passes through the light filler of spraying of light filler delivery pipe and constitutes light filler cured layer 23.
Two ends of shaped steel arch are fixedly connected with lock foot anchoring stock 24, and lock foot anchoring stock is anchored at the entity on the outside of tunnel
It is interior.
Longitudinal reinforcement 4 is fixedly connected between adjacent two Pin shaped steel archs;Longitudinal reinforcement outer rim is collapsed the welding of cave scope ring
In grafting guide ring 25, the ring of grafting guide ring along longitudinal direction chamber ring scope of collapsing install can the protection plate of longitudinally-moving formed
Top seal structure;It is fixedly connected between protection plate and shaped steel arch by grafting guide ring.
Light filler uses light-duty mortar.
The processing for being used for the stand that Tunnel Landslide is quickly handled and construction procedure are:
In tunnel safety area, processing longitudinal length is longer than the cave length 0.5m that collapses, and ring shield arch scope is beyond chamber ring length of collapsing
Edge 0.8m, highly with board plug type supporting stand adaptable at the top of vault and the body that collapses.
Stand uses door type structure, and I20 I-steel welding fabrications erect column bottom per side door and set 5t small-sized machines very heavy
Top.Install and design supporting parameter identical I20 I-steel bow members, every Pin bow members and the stull of door frame column and crossbeam door frame periphery
Connected using steel welding, longitudinally connected reinforcing bar is set by design requirement between adjacent two Pin bow members, bow member steel arch-shelf outer rim is collapsed cave model
Collarette is to welding grafting guide ring, along longitudinal direction in chamber ring scope of collapsing in ring(Beyond 20cm)Install can longitudinally-moving 0.5mm
Thick embedded steel board formation top seal structure.In most deep position built-in length 4m and the 6m delivery pump pipes of Ф 125 that cave in.Base to be caved in
Supporting stand is moved to cave bottom of collapsing with excavator by this stabilization, and good position is fixed using door frame jack.Just manually hammering side
Formula impacts each plate to watching close face.The gunite concrete formation preliminary bracing on the outside of plate, is pumped mixed using short pump line
After concrete final set, light-duty mortar is irrigated using long pump line to vault above 2m for solidifying soil perfusion.Concrete strength reaches 10Mpa
During the above, stand is removed, spreading both sides bow member completes whole preliminary bracings.
(1)Step 1 stand is processed
Place of safety processing supporting stand after landslide, stand is by portal frame system, steel arch-shelf and longitudinally connected reinforcing bar, vault
Embedded steel board and Auxiliary support positioner composition.Supporting platform is determined according to landslide body upper space size and landslide area's ring scope
The height and width of frame portal frame system, crossbeam, column, the diagonal brace of door frame etc. use I-steel weld assembly(I-shaped steel pattern number according to
Landslide height, door frame width and height etc. are comprehensive to be determined)Door frame periphery is according to the bow member model and spacing after former design or change
Arrangement, entirety is connected between bow member and door frame in succession using steel welding.Surpass at the top of bow member in landslide area's ring scope per side
Go out 1m arrangement above embedded steel boards, the closed inserting plate hole of steel plate solid matter, steel are being used on wing plate on the outside of every Pin bow members in the range of the chamber that collapses
Plate is passed through from hole, embedded steel board 30~40cm of width, 5~10mm of thickness of slab.In the vertically arranged small-sized machine of door frame column bottom
Jack is used for the vertical positioning of door frame.
(2)Step 2 stand is in place and locks
Using excavator by body top surface moderately smooth compacting of caving in, placing bulk steel plate in stand column Position Approximate is used for
Increase the supporting force on stand basis.Stand is moved integrally to bottom of chamber portion of collapsing using excavator, manually being aided in stand bottom will
Stand is substantially in place, and column is placed at the top of supporting steel plate.Both sides symmetry operation jack, makes stand and the big densification of tunnel palisades
Patch, locks jack.
(3)Step 3 plate is in place
Promote embedded steel board and face country rock to hold out against piecewise using excavator, have compared with being welded with the sealing of small steel plate at big gap,
And fill in the materials such as Anchor Agent, it is ensured that will not a large amount of spillage.Ring welded reinforcement is linked to be entirety on the inside of neighbouring face embedded steel board.
(4)Step 4 sets lock pin anchor tube(Bar)
4 lock pin anchor tubes are set at steel arch-shelf footing above 30cm(Bar), it is welded into using L-type steel muscle and steel arch-shelf whole
Body, and slip casting locking.
(5)Step 5 buries delivery pump pipe
In landslide area extreme higher position, 2 delivery pump pipes, a length 3~4 are buried for support perforate using gantry beam
Rice, another extends at the 20~30cm of top of chamber that collapses.
(6)Step 6 gunite concrete
According to the thickness of design or design for change in bow member scope gunite concrete, to reduce injection springback capacity, it can insert
One layer of reinforced mesh of welding on the outside of plate.
(7)Step 7 is collapsed chamber pump concrete
Connect short delivery pump pipe pumping more than C20 concrete, concrete height to more than vault at least 2m.In casting process
Bow member, the deformation of stand are observed at any time, and graded is poured when amount of concrete is larger.
(8)Step 8 pressure injection light material
After the pump concrete final set phase, using long delivery pump pipe to collapse intracavitary pumping or slip casting machine irrigate sand+flyash+
The light mortar of cement, can irrigate the lightweight materials such as lightweight balloon concrete as cushion when having ready conditions.
(9)Step 9 removes stand
Intracavitary of collapsing concrete strength is reached after more than 10Mpa, removes combination supporting stand, stand is moved to outside hole or torn open
Solution.
(10)Spreading abutment wall bow member, suspended net shotcrete
Cleaning landslide body, spreading abutment wall bow member sets system anchor bolt, hangs bar-mat reinforcement, gunite concrete forms complete
Preliminary bracing.
(11)Monitoring measurement and excavation driving
In work progress and after the completion of persistently carry out the monitoring of Vault settlement and perimeter convergence, will according to design and specification
Ask, recover the excavation driving of face.
Claims (4)
1. a kind of stand quickly handled for Tunnel Landslide, it is characterised in that including shaped steel arch and door frame,
Tunnel arch roof at the apical margin apical grafting landslide of shaped steel arch, two ends of shaped steel arch along tunnel arch roof to
Lower extension is simultaneously fixed to landslide body edge part in end;
Longitudinal reinforcement is fixedly connected between adjacent two Pin shaped steel archs;
Shaped steel arch and longitudinal reinforcement constitute overall arch support body;
Door frame is arranged on the interior of shaped steel arch and enclosed, and the bottom of door frame is sat by jack to be located on Tunnel Landslide body;
Door frame uses the frame shape door frame being made up of left frame, top frame, correct frame;
Left position workbench is fixedly installed on the left of left frame;It is fixedly connected between the inner edge of left position workbench and shaped steel arch
Left position knighthead;
Right position workbench is fixedly installed on the right side of correct frame;It is fixedly connected between the inner edge of right position workbench and shaped steel arch
Right position knighthead;
Top position support bar is fixedly connected between at the top of top frame and shaped steel arch;
Stand diagonal brace has been respectively fixedly connected between left frame, correct frame and top frame;Stand diagonal brace and left frame, correct frame it
Between be respectively fixedly connected with horizontal brace;
Protection plate is provided between shaped steel arch and tunnel arch roof;
It is provided with concrete delivery pump pipe and light filler to top intracavitary of collapsing below along the arch support body of tunnel inner chamber and conveys
Pipe, the top of concrete delivery pump pipe is located at the lower section on light filler delivery pipe top;
The collapse bottom of chamber passes through concrete delivery pump pipe concrete of spraying and constitutes concrete curing layer;
Collapse chamber top pass through light filler delivery pipe spray light filler constitute light filler cured layer.
2. a kind of stand quickly handled for Tunnel Landslide according to claim 1, it is characterised in that:Shaped steel arch
Two ends are fixedly connected with lock foot anchoring stock, and lock foot anchoring stock is anchored in the entity on the outside of tunnel.
3. a kind of stand quickly handled for Tunnel Landslide according to claim 1, it is characterised in that:Adjacent two Pin types
Longitudinal reinforcement is fixedly connected between steel arch-shelf;Longitudinal reinforcement outer rim is collapsed cave scope ring welding grafting guide ring, and grafting is oriented to
In the ring of ring along longitudinal direction chamber ring scope of collapsing install can longitudinally-moving protection plate formation top seal structure;Protect plate
It is fixedly connected between shaped steel arch by grafting guide ring.
4. a kind of stand quickly handled for Tunnel Landslide according to claim 1, it is characterised in that:Light filler is adopted
Use light-duty mortar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720106110.5U CN206495682U (en) | 2017-02-03 | 2017-02-03 | A kind of stand quickly handled for Tunnel Landslide |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720106110.5U CN206495682U (en) | 2017-02-03 | 2017-02-03 | A kind of stand quickly handled for Tunnel Landslide |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206495682U true CN206495682U (en) | 2017-09-15 |
Family
ID=59804093
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720106110.5U Expired - Fee Related CN206495682U (en) | 2017-02-03 | 2017-02-03 | A kind of stand quickly handled for Tunnel Landslide |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206495682U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107435543A (en) * | 2017-09-19 | 2017-12-05 | 北京建工土木工程有限公司 | IV grade of step construction method of three step of country rock large section five |
CN108533274A (en) * | 2018-04-28 | 2018-09-14 | 四川公路桥梁建设集团有限公司 | Intelligent protection excavation trolley |
CN109209440A (en) * | 2018-10-31 | 2019-01-15 | 中建隧道建设有限公司 | large-span tunnel vault settlement processing method |
CN113107536A (en) * | 2021-04-20 | 2021-07-13 | 中国安能集团第三工程局有限公司 | Side roof arch cavity collapse supporting system and method for fault fracture zone diversion tunnel |
WO2021179508A1 (en) * | 2020-03-11 | 2021-09-16 | 山东科技大学 | Method for treating tunnel collapse by using roof-contacted shield plate support |
WO2021179507A1 (en) * | 2020-03-11 | 2021-09-16 | 山东科技大学 | Method for treating tunnel collapse by using pavilion-type support |
CN116446887A (en) * | 2023-06-20 | 2023-07-18 | 湖南省交通规划勘察设计院有限公司 | Tunnel construction method for existing partial collapse position of primary support section |
-
2017
- 2017-02-03 CN CN201720106110.5U patent/CN206495682U/en not_active Expired - Fee Related
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107435543A (en) * | 2017-09-19 | 2017-12-05 | 北京建工土木工程有限公司 | IV grade of step construction method of three step of country rock large section five |
CN108533274A (en) * | 2018-04-28 | 2018-09-14 | 四川公路桥梁建设集团有限公司 | Intelligent protection excavation trolley |
CN108533274B (en) * | 2018-04-28 | 2024-01-23 | 四川公路桥梁建设集团有限公司 | Intelligent protection excavation trolley |
CN109209440A (en) * | 2018-10-31 | 2019-01-15 | 中建隧道建设有限公司 | large-span tunnel vault settlement processing method |
WO2021179508A1 (en) * | 2020-03-11 | 2021-09-16 | 山东科技大学 | Method for treating tunnel collapse by using roof-contacted shield plate support |
WO2021179507A1 (en) * | 2020-03-11 | 2021-09-16 | 山东科技大学 | Method for treating tunnel collapse by using pavilion-type support |
AU2020385366B2 (en) * | 2020-03-11 | 2021-10-28 | China Communications Construction Co., Ltd. | Method of treating tunnel collapse using pavilion support |
CN113107536A (en) * | 2021-04-20 | 2021-07-13 | 中国安能集团第三工程局有限公司 | Side roof arch cavity collapse supporting system and method for fault fracture zone diversion tunnel |
CN113107536B (en) * | 2021-04-20 | 2024-05-03 | 中国安能集团第三工程局有限公司 | Supporting system and method for side-roof arch collapse cavity of fracture-zone diversion tunnel |
CN116446887A (en) * | 2023-06-20 | 2023-07-18 | 湖南省交通规划勘察设计院有限公司 | Tunnel construction method for existing partial collapse position of primary support section |
CN116446887B (en) * | 2023-06-20 | 2023-09-01 | 湖南省交通规划勘察设计院有限公司 | Tunnel construction method for existing partial collapse position of primary support section |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206495682U (en) | A kind of stand quickly handled for Tunnel Landslide | |
CN111365044B (en) | A method for dealing with tunnel collapse by using top-mounted shield support | |
CN205742213U (en) | Foundation pit supporting construction | |
CN105697033B (en) | A kind of construction method of Tunnel Engineering without template punishment rock mass cavity | |
JP7257086B2 (en) | Comprehensive Construction Method for Low Overburden Sections of Tunnels | |
CN109026026B (en) | Construction method of large-section multi-line multi-arch underground excavation tunnel group penetrating existing pipe gallery | |
CN113153308B (en) | Construction method for collapse section of double-arch tunnel | |
CN109519197B (en) | Sliding-mode primary lining excavation and support dual-purpose trolley and application thereof | |
CN114483056B (en) | Method for treating collapse roof caving hole of high-speed railway shallow-buried tunnel within 15m of height of collapse cavity | |
CN107130609A (en) | Without the basement supporting to support | |
CN107218062B (en) | A kind of construction method of contrary sequence method processing Tunnel Collapse | |
CN106050277A (en) | Strengthening process for soft-plastic collapsing body karst tunnel | |
CN114382509A (en) | Section tunnel collapse construction method and support device | |
CN112855225B (en) | Soft rock tunnel supporting construction method with high safety | |
CN114562289A (en) | Rapid treatment method for large-scale cavity collapse of soft broken surrounding rock tunnel vault | |
CN113803092A (en) | Supporting device and method for broken soft rock roadway based on concrete filled steel tube support | |
CN205977233U (en) | Tunnel lock foot spouts pilework soon | |
CN115653617A (en) | Construction method of covering layer shallow-buried tunnel | |
CN116479907A (en) | Inclined strut pile supporting structure and construction method thereof | |
CN112663636B (en) | Non-panel reinforced soil ecological slope protection system and construction method thereof | |
CN210530848U (en) | Large-span small-clear-distance asymmetric section tunnel supporting structure in loess region | |
CN106703815A (en) | Construction method of inner excavated abutment | |
CN113236290A (en) | Construction process of steel frame mold for tunnel portal arch protection section | |
CN111549794A (en) | Miniature supporting method and miniature pile supporting structure suitable for soft foundation treatment | |
CN113430964B (en) | In-situ suspension protection construction method for box culvert spanning foundation pit in long distance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170915 |
|
CF01 | Termination of patent right due to non-payment of annual fee |