[go: up one dir, main page]

CN206319317U - Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time - Google Patents

Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time Download PDF

Info

Publication number
CN206319317U
CN206319317U CN201621362587.1U CN201621362587U CN206319317U CN 206319317 U CN206319317 U CN 206319317U CN 201621362587 U CN201621362587 U CN 201621362587U CN 206319317 U CN206319317 U CN 206319317U
Authority
CN
China
Prior art keywords
anchor
steel strand
strand wires
dynamometer
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621362587.1U
Other languages
Chinese (zh)
Inventor
汪小刚
赵宇飞
林兴超
王玉杰
姜龙
刘立鹏
孙平
段庆伟
曹瑞琅
郑理峰
安新赞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Institute of Water Resources and Hydropower Research
Original Assignee
China Institute of Water Resources and Hydropower Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Institute of Water Resources and Hydropower Research filed Critical China Institute of Water Resources and Hydropower Research
Priority to CN201621362587.1U priority Critical patent/CN206319317U/en
Application granted granted Critical
Publication of CN206319317U publication Critical patent/CN206319317U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Force Measurement Appropriate To Specific Purposes (AREA)

Abstract

A kind of intelligent anchor cable system for being applied to rock side slope supporting and monitored over time, including Inner bolt head and outer anchor head, it is fixedly connected by steel strand wires therebetween, each steel strand wires are arranged in Inner bolt head, and the inner of each steel strand wires is provided with heading, the first dynamometer is provided between heading and Inner bolt head inner face;First dynamometer is set in steel strand wires periphery, and the cable of the first dynamometer is arranged in corresponding wire guide;Outer anchor head is located at anchor cable drilling outer end, including anchor pier, and anchor pier is close to anchor cable drilling outer wall, and anchor pier lateral surface is sequentially provided with backing plate and anchor slab, and the second dynamometer is provided between backing plate and anchor slab;Steel strand wires sequentially pass through anchor pier, backing plate, the second dynamometer, and outer end is fixed on anchor slab;Positioned at the part of anchor cable bore inner, spacer sleeve is provided with several pulling force sensors to each steel strand wires along its length, and each stretching force sensor external is covered with protective cover, and the cable of tensioning force snesor is passed by protective cover outer end.

Description

Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time
Technical field
The utility model belongs to Geotechnical Engineering field, more particularly to a kind of to be applied to rock side slope supporting and whole prison The novel intelligent anchor cable system of survey.
Background technology
Prestress anchorage cable is currently most common technological means in slope retaining in Geotechnical Engineering, and prestress anchorage cable can be led It is dynamic to reinforce Rock And Soil, effectively increase Rock Slide Stability safety coefficient, it is ensured that the safety of engineering construction and runtime.For example, typical Non-bonded anchorage cable structure is as shown in figure 1, its main feature has the following aspects:
1) non-bonding prestress tendon uses non-bending steel cable 1 ', has covered one layer of PE's outside common steel strand wires Plastic bushing, inside fills butter, can effectively prevent steel strand wires to corrode;
2) due to having one layer of plastic bushing outside steel strand wires, steel strand wires can be moved freely in sleeve pipe, special using this Property, Inner bolt head 2 ' is installed under the heading of steel strand wires end, when prestressed stretch-draw is carried out, steel strand wires termination is pressed in Inner bolt head On, it is that Inner bolt head forms compression on rock mass, belongs to pressure anchor cable;
3) anchor cable of application non-bending steel cable, typically all uses the form of construction work of once grouting, with caking property anchor cable phase Than, non-bonded anchorage cable easy construction, quick, efficiency high, can side slope reinforced in time;
4) there is one layer of plastic sheath because non-bonded anchorage cable is employed outside non-bending steel cable, steel strand wires so that steel strand wires Stress relief can be carried out with rock mass deformation.
At present, the monitoring of the prestress anchorage cable employed in rock side slope supporting mainly uses the anchor installed in outer anchor head Rope dynamometer carries out the monitoring of prestressd anchor cable, but is due to the construction work that non-bonded anchorage cable mainly uses once grouting Skill, just carries out the tensioning of prestress anchorage cable after total length slip casting, prestressed transmission is acted on due to duct frictional resistance, causes deep anchor Stretching force suffered by rope is less than the stretching force of anchor cable near outer anchor head, and as anchor cable depth is bigger, stretching force is got over suffered by anchor cable It is small.Therefore, the result that current anchor dynamometer is monitored is difficult the actual working state for reacting prestress anchorage cable.Therefore, Need a kind of new prestress anchorage cable monitoring device of exploitation badly, can effectively monitor the whole stress deformation of prestress anchorage cable special Levy, prestress anchorage cable working property, and the deformation of indirect reaction slope rock mass are grasped in time, is the safety and reliability of engineering operation Important Appreciation gist is provided.
Utility model content
The purpose of this utility model is to provide a kind of suitable for rock side slope supporting and the anchor cable system of monitored over time, its energy The whole stress deformation of enough steel strand wires to prestress anchorage cable during long service is monitored, and can be taken with actual response anchor cable Use as a servant the deformation of character and slope rock mass in the range of length of prestress anchor cable.
To achieve the above object, the utility model takes following technical scheme:
It is a kind of that suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time, it includes Inner bolt head and outer anchor head, Therebetween it is fixedly connected by some steel strand wires, the steel strand wires are arranged with the sleeve pipe of filling anti-corrosive grease, wherein:
The Inner bolt head is located at anchor cable drilling the inner, through provided with some twisted wire holes and wire guide;Each steel strand wires are arranged in pair In the twisted wire hole answered, and the inner of each steel strand wires is provided with heading, and the first dynamometry is provided between the heading and the Inner bolt head inner face Meter;First dynamometer is set in the steel strand wires periphery, and the cable of first dynamometer is arranged in corresponding wire guide;
The outer anchor head is located at anchor cable drilling outer end, including anchor pier, and the anchor pier is close to anchor cable drilling outer wall, the anchor pier Lateral surface is sequentially provided with backing plate and anchor slab, and the second dynamometer is provided between the backing plate and anchor slab;The steel strand wires sequentially pass through the anchor Pier, backing plate, the second dynamometer, outer end is fixed on the anchor slab;
Positioned at the part of the anchor cable bore inner, spacer sleeve is provided with several pulling force sensors to each steel strand wires along its length, Each stretching force sensor external is covered with protective cover, and the cable of the tensioning force snesor is passed by the protective cover outer end.
Further, the section of the Inner bolt head and the anchor pier is in isosceles trapezoid.
Further, described Inner bolt head the inner is provided with interior protective cover, the inner of the heading, the first dynamometer and steel strand wires It is respectively positioned on inside the interior protective cover.
Further, it is provided with outer protective cover on the outside of the anchor pier, the backing plate, the second dynamometer, anchor slab and steel strand wires Outer end is respectively positioned on inside the outer protective cover.
The beneficial effects of the utility model are:Implemented by of the present utility model, the prestress anchorage cable in slope retaining A part not exclusively in slope reinforcement measure, and the whole ess-strain of prestress anchorage cable can be carried out using the anchor cable Monitoring, can also understand the deformation of side slope different depth rock mass in terms of another, so as to really understand answering for side slope Force deformation, is that anchored slope operation safety proposes important technical support with reliable.
Brief description of the drawings
Fig. 1 is the structural representation of existing non-bonding prestress tendon.
Fig. 2 is the structural representation for the intelligent anchor cable system that the utility model is applied to rock side slope supporting and monitored over time Figure.
Fig. 3 is the first dynamometer of the intelligent anchor cable system that the utility model is applied to rock side slope supporting and monitored over time The structural representation at place.
Fig. 4 is the second dynamometer of the intelligent anchor cable system that the utility model is applied to rock side slope supporting and monitored over time The structural representation at place.
Fig. 5 is that the stretching force for the intelligent anchor cable system that the utility model is applied to rock side slope supporting and monitored over time is sensed Structural representation at device.
Embodiment
Coordinate accompanying drawing that the utility model is further detailed below, but and be not used to limit of the present utility model Practical range.
As shown in Fig. 2 the utility model provides a kind of suitable for rock side slope supporting and the intelligent anchor cable body of monitored over time System, it includes Inner bolt head 1 and outer anchor head 2, is fixedly connected by some steel strand wires 3 therebetween, the steel strand wires 3 are arranged with filling The sleeve pipe of anti-corrosive grease.
As shown in figure 3, the Inner bolt head 1 is located at the inner of anchor cable drilling 4, through provided with some twisted wire holes 11 and wire guide 12. Each steel strand wires 3 are arranged in corresponding twisted wire hole 11, and the inner of each steel strand wires 3 is provided with heading 31, the heading 31 and the interior anchor The first dynamometer 5 is provided between first 1 inner face.First dynamometer 5 is set in the periphery of steel strand wires 3, and first dynamometer 5 Cable be arranged in corresponding wire guide 12.The Inner bolt head 1 is inner to be provided with interior protective cover 13, the heading 31, the first dynamometer 5 It is respectively positioned on the inner of steel strand wires 3 inside the interior protective cover 13, to prevent the inner of heading 31, the first dynamometer 5 and steel strand wires 3 Corroded.
As shown in figure 4, the outer anchor head 2 is located at 4 outer ends of anchor cable drilling, including anchor pier 21, the anchor pier 21 is bored with the anchor cable The outer wall of hole 4 is close to, and the lateral surface of anchor pier 21 is sequentially provided with backing plate 22 and anchor slab 23, and second is provided between the backing plate 22 and anchor slab 23 Dynamometer 6.The steel strand wires 3 sequentially pass through the anchor pier 21, backing plate 22, the second dynamometer 6, and outer end is fixed on the anchor slab 23.Enter One step, the section of the Inner bolt head 1 and the anchor pier 21 is in isosceles trapezoid.In addition, the outside of anchor pier 21 is provided with outer protective cover 24, The backing plate 22, the second dynamometer 6, the outer end of anchor slab 23 and steel strand wires 3 are respectively positioned on inside the outer protective cover 24, to prevent backing plate 22nd, the outer end of the second dynamometer 6, anchor slab 23 and steel strand wires 3 is corroded.
As shown in figure 5, spacer sleeve is provided with some along its length for part of each steel strand wires 3 inside anchor cable drilling 4 Tensioning force snesor 7, each outer cup of tensioning force snesor 7 is provided with protective cover 71, and the cable of the tensioning force snesor 7 is by the protection 71 outer ends are covered to pass.
The cable of first dynamometer 5 of the present utility model, the second dynamometer 6 and tensioning force snesor 7 is connected to outer anchor head External equipment, be acquired with the data to the first dynamometer 5, the second dynamometer 6 and tensioning force snesor 7.
The utility model on the basis of novel pre-stressed anchor cable Inner bolt head structure, integrate new prestressing force Inner bolt head by Anchor head corrosion protection system and monitoring sensing inside and outside the whole stress deformation monitoring technology of power monitoring device, steel strand wires, prestress anchorage cable Device long durability guard technology, forms new intelligent prestress anchor cable system, prestress anchorage cable can be taken for a long time The whole stress deformation of steel strand wires during labour is monitored, on the one hand can be with actual response anchor cable military service character, on the other hand Deformation of the slope rock mass in the range of length of prestress anchor cable can also be reacted.
The utility model also provides a kind of suitable for rock side slope supporting and the fixation of the intelligent anchor cable system of monitored over time Method, it comprises the following steps:
A. several pulling force sensors 7 of installation are arranged along its length outside steel strand wires 3 and are tested, and at each The outside of pulling force sensor 7 is installed by protective cover 71;
B. the steel strand wires 3 for installing tensioning force snesor 7 are carried out in volume rope, the twisted wire hole 11 for penetrating Inner bolt head 1, and inside First dynamometer 5 is installed between the heading 31 of the inner side end of anchor head 1 and steel strand wires 3, and packages interior protective cover 13;
C., anchor cable is integrally put into anchor cable drilling 4 positioning is installed, the slip casting into anchor cable drilling 4;
D. in anchor cable drilling 4 after grout cures, anchor pier 21 is installed in anchor cable 4 outer walls of drilling, and in the outside of anchor pier 21 Backing plate 22, the second dynamometer 6 and anchor slab 23 are installed successively, and steel strand wires 3 is sequentially passed through anchor pier 21, backing plate 22, the second dynamometry Meter 6 and anchor slab 23;
E. steel strand wires 3 are carried out with prestressed anchor cable stretching, and writes down the first dynamometer 5, the second dynamometer 6 and stretching force passing The data that with stretching process produce of the sensor 7 at same time point;
F. the number of 7 devices is sensed according to the first dynamometer 5, the second dynamometer 6 and stretching force collected in stretching process According to it is determined that monitoring initial value, is used as the initial value in prestress anchorage cable running;
G. the outer end of steel strand wires 3 is fixed on anchor slab 23, checks the first dynamometer 5, the second dynamometer 6 and stretching force sensing After the cable of device 7, outer protective cover 24 is installed in the outside of anchor pier 21.
In addition, it is above-mentioned suitable for rock side slope supporting and the fixing means of the anchor cable system of monitored over time, also including step H. prestress anchorage cable diverse location is monitored in real time by the data of the first dynamometer 5, the second dynamometer 6 and tensioning force snesor 7 Stressing conditions.
It is applied to rock side slope supporting and the intelligent anchor cable system of long-term monitored over time designed by the utility model, not only The branch protective function of normal anchor cable can be realized, and the steel strand wires in anchor cable can also be utilized, steel strand wires in prestress anchorage cable are carried out Whole stress deformation character monitoring, grasps the running status of prestress anchorage cable during service, and then can utilize these monitorings Data side slope support system reliability is evaluated.
On the other hand, can using the whole stress deformation character monitoring materials of steel strand wires in obtained prestress anchorage cable It is whole with reference to the prestressing force that several are new in side slope region to obtain the deformation characteristic of slope reinforcement region rock mass different depth Anchor cable is monitored, the different depth displacement field of whole rock side slope can be obtained using high-precision differential analysis, so as to utilize the letter The safe operation state of breath side slope is reliably evaluated.
It is of the present utility model to propose, the problem of current prestress anchorage cable monitoring is solved, makes prestress anchorage cable level monitoring There is larger lifting.Therefore, the utility model patent is applied in actual rock side slope supporting, can obtains significant Economic benefit and social benefit.
It is pointed out that above-mentioned embodiment is only possible embodiment, it is new in order to which this practicality is expressly understood The principle of type and propose.Can be in the case of without departing substantially from the utility model principle and scope to above-mentioned reality of the present utility model The mode of applying carries out many and changed and modifications.All such modifications and variations are included in the scope of the utility model announcement, and And protected by appended claims.

Claims (4)

1. a kind of suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time, it includes Inner bolt head and outer anchor head, two It is fixedly connected between person by some steel strand wires, the steel strand wires are arranged with the sleeve pipe of filling anti-corrosive grease, it is characterised in that:
The Inner bolt head is located at anchor cable drilling the inner, through provided with some twisted wire holes and wire guide;Each steel strand wires are arranged in corresponding In twisted wire hole, and the inner of each steel strand wires is provided with heading, and the first dynamometer is provided between the heading and the Inner bolt head inner face;Should First dynamometer is set in the steel strand wires periphery, and the cable of first dynamometer is arranged in corresponding wire guide;
The outer anchor head is located at anchor cable drilling outer end, including anchor pier, and the anchor pier is close to anchor cable drilling outer wall, on the outside of the anchor pier Face is sequentially provided with backing plate and anchor slab, and the second dynamometer is provided between the backing plate and anchor slab;The steel strand wires sequentially pass through the anchor pier, pad Plate, the second dynamometer, outer end is fixed on the anchor slab;
Positioned at the part of the anchor cable bore inner, spacer sleeve is provided with several pulling force sensors, each to each steel strand wires along its length Pulling force sensor outer cup is provided with protective cover, and the cable of the tensioning force snesor is passed by the protective cover outer end.
2. according to claim 1 suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time, its feature exists In:The section of the Inner bolt head and the anchor pier is in isosceles trapezoid.
3. it is according to claim 1 or 2 suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time, its feature It is:Described Inner bolt head the inner is provided with interior protective cover, and the inner of the heading, the first dynamometer and steel strand wires is respectively positioned on the interior guarantor Inside shield.
4. according to claim 3 suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time, its feature exists In:It is provided with outer protective cover on the outside of the anchor pier, the backing plate, the second dynamometer, that the outer end of anchor slab and steel strand wires is respectively positioned on this is outer Inside protective cover.
CN201621362587.1U 2016-12-13 2016-12-13 Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time Withdrawn - After Issue CN206319317U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621362587.1U CN206319317U (en) 2016-12-13 2016-12-13 Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621362587.1U CN206319317U (en) 2016-12-13 2016-12-13 Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time

Publications (1)

Publication Number Publication Date
CN206319317U true CN206319317U (en) 2017-07-11

Family

ID=59267618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621362587.1U Withdrawn - After Issue CN206319317U (en) 2016-12-13 2016-12-13 Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time

Country Status (1)

Country Link
CN (1) CN206319317U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759318A (en) * 2016-12-13 2017-05-31 中国水利水电科学研究院 Suitable for rock side slope supporting and the intelligent anchor cable system and its fixing means of monitored over time
CN108193678A (en) * 2018-01-24 2018-06-22 中冶沈勘工程技术有限公司 The computational methods of rockwork anchor pole interaction boundary spacing and the ultimate pullout capacity computational methods of rockwork anchor pole
CN110749495A (en) * 2019-11-28 2020-02-04 中国水利水电科学研究院 Device and method for testing mechanical properties of anchor cable and inner anchor head
CN111337178A (en) * 2020-04-03 2020-06-26 广西大学 Polymer strain gauge sensor and intelligent cable manufacturing method
CN111442735A (en) * 2020-04-03 2020-07-24 广西大学 Fabrication method of polymer skin fiber grating strain sensor and smart cable

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759318A (en) * 2016-12-13 2017-05-31 中国水利水电科学研究院 Suitable for rock side slope supporting and the intelligent anchor cable system and its fixing means of monitored over time
CN108193678A (en) * 2018-01-24 2018-06-22 中冶沈勘工程技术有限公司 The computational methods of rockwork anchor pole interaction boundary spacing and the ultimate pullout capacity computational methods of rockwork anchor pole
CN108193678B (en) * 2018-01-24 2019-10-29 中冶沈勘工程技术有限公司 The calculation method of rockwork anchor pole interaction boundary spacing and the ultimate pullout capacity calculation method of rockwork anchor pole
CN110749495A (en) * 2019-11-28 2020-02-04 中国水利水电科学研究院 Device and method for testing mechanical properties of anchor cable and inner anchor head
CN111337178A (en) * 2020-04-03 2020-06-26 广西大学 Polymer strain gauge sensor and intelligent cable manufacturing method
CN111442735A (en) * 2020-04-03 2020-07-24 广西大学 Fabrication method of polymer skin fiber grating strain sensor and smart cable
CN111442735B (en) * 2020-04-03 2022-05-31 广西大学 Fabrication method of polymer skin fiber grating strain sensor and smart cable

Similar Documents

Publication Publication Date Title
CN206319317U (en) Suitable for rock side slope supporting and the intelligent anchor cable system of monitored over time
CN106759318B (en) Intelligent anchor cable system and its fixing means suitable for rock side slope supporting and monitored over time
CN100570067C (en) Prestressed method of suspension bridge anchoring changeable formula and device
CN205224129U (en) Single pile basis vertical bearing capacity's experiment detection device
US9963852B2 (en) Test method for friction resistance at inner and outer sidewalls of pipe pile
CN107655755A (en) A kind of test method of drag-line cord clip assembly resistant slide bearing capacity
Gage et al. Validation and implementation of a new method for monitoring in situ strain and temperature in rock masses using fiber-optically instrumented rock strain and temperature strips
CN103215974A (en) Foundation pile deflection measurement method based on distributed fiber sensing technique
CN108716227A (en) Analysis method for axial force and displacement distribution of full-length bonded GFRP anti-floating anchor rod
CN114297767B (en) Active anchoring optimization design method for deep mine excavation slope
Jardine et al. Axial capacity design practice for North European wind-turbine projects
Kim et al. Equivalent head-down load vs. Movement relationships evaluated from bi-directional pile load tests
KR100698540B1 (en) Settlement measuring device and settlement measurement reinforcement system using the same
CN104763001B (en) A kind of assay device suitable in anchorage cable anchoring section creep properties and test method
CN211037082U (en) Uplift pile stress and strain automatic monitoring device based on optical fiber sensing technology
CN110514812B (en) Landslide thrust monitoring and early warning method based on stability coefficient
CN107860496A (en) Method for testing shear stress on surface of full-length bonded steel bar anchor rod body
CN106906824A (en) Distribution type fiber-optic prestressing force intellectual monitoring anchor cable
CN204988572U (en) Skin friction testing arrangement in prefabricated opening concrete pipe pile pile body
CN2510840Y (en) Single-string respective tension anchoring test apparatus of multi-string steel strand-cable prestressed anchoring rope
KR20100039008A (en) Measurement system and method for measuring of the same
CN203479435U (en) Stress testing device for non-metal anti-floating anchor rod body
CN112228155B (en) Arrangement method and structure of multi-parameter monitoring sensors for overlying rock strata in coal mining subsidence areas
Babu et al. Soil nails field pullout testing: evaluation and applications
CN207147677U (en) A kind of Blade fence injection stage force testing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20170711

Effective date of abandoning: 20190326

AV01 Patent right actively abandoned