[go: up one dir, main page]

CN206266182U - Stone Vertical transport hanging basket in exterior wall scaffold - Google Patents

Stone Vertical transport hanging basket in exterior wall scaffold Download PDF

Info

Publication number
CN206266182U
CN206266182U CN201621231701.7U CN201621231701U CN206266182U CN 206266182 U CN206266182 U CN 206266182U CN 201621231701 U CN201621231701 U CN 201621231701U CN 206266182 U CN206266182 U CN 206266182U
Authority
CN
China
Prior art keywords
hanging basket
vertical
square tube
exterior wall
hoist engine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621231701.7U
Other languages
Chinese (zh)
Inventor
王辉平
王利雄
连珍
陈莹
马宇哲
郭佳俊
蒲聿聪
徐永刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Building Decoration Engineering Group Co Ltd
Original Assignee
Shanghai Building Decoration Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Building Decoration Engineering Group Co Ltd filed Critical Shanghai Building Decoration Engineering Group Co Ltd
Priority to CN201621231701.7U priority Critical patent/CN206266182U/en
Application granted granted Critical
Publication of CN206266182U publication Critical patent/CN206266182U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides Stone Vertical transport hanging basket in a kind of exterior wall scaffold, the utility model is in solution traditional construction, the stone material shipping yard of external wall of high-rise building stone material construction is narrow and small, vertical transport difficulty is big, safety is difficult to ensure that, the problem of labor intensive material resources, for the vertical transport of outer wall stone, innovated there is provided one kind, efficiently, Stone Vertical transport hanging basket in the exterior wall scaffold of safety, by fast-assembling bolster, hoist engine, hanging basket, the cooperating of the components such as vertical dragline, so that the stone material in scaffold in vertical direction transports the simple of change, safety, it is reliable, and install, dismounting is simple and quick.In addition, vertical dragline one end is directly connected by vertical dragline coupling assembly with the exterior wall scaffold, influence of the ground factor to vertical transport equipment is eliminated.

Description

Stone Vertical transport hanging basket in exterior wall scaffold
Technical field
The utility model belongs to building decoration engineering construction field, Stone Vertical fortune in more particularly to a kind of exterior wall scaffold Defeated hanging basket.
Background technology
Conventional outer wall stone material is constructed, after alien invasion builds scaffold so that the transport of stone material is carried out in small space.Manpower Carry difficulty big, and security is difficult to ensure that, while easily causing the breakage of stone material.Goods lift is carried away from operation ground, and Need manpower rehandling, security, integrality, it is difficult to ensure.
Utility model content
The purpose of this utility model is to provide Stone Vertical transport hanging basket in a kind of exterior wall scaffold, can solve the problem that tradition In construction, the stone material shipping yard of external wall of high-rise building stone material construction is narrow and small, and vertical transport difficulty is big, is difficult to ensure that safely, consumes Take the problem of manpower and materials.
To solve the above problems, the utility model provides Stone Vertical transport hanging basket in a kind of exterior wall scaffold, including:
Exterior wall scaffold, is separated by predeterminable range, the bottom of the exterior wall scaffold between the exterior wall scaffold and wall It is provided with two vertical dragline coupling assemblies extended to the wall;
The fast-assembling bolster on the wall is arranged at, the fast-assembling bolster is relative with the top of the exterior wall scaffold;
Two spaced vertical draglines, the top of every vertical dragline is connected with the fast-assembling bolster, and every vertical The bottom of dragline vertical dragline coupling assembly described with is connected;
The hoist engine on the fast-assembling bolster is arranged at, and the Operation switch being connected with the hoist engine;
Move up and down and surround vertical space in the exterior wall scaffold, wall, hoist engine and vertical dragline coupling assembly Interior hanging basket, the hanging basket upper end is provided with hanger, and the hanger is connected with the serving on the hoist engine, the hanging basket both sides Two groups of slide guide wheels are provided with, every group of slide guide wheel is slided on a vertical dragline.
Further, in above-mentioned hanging basket, the fast-assembling bolster by 9 square tubes and 2 blocks of steel plates, wherein the first square tube and wall Body is be arranged in parallel, and the two ends of first square tube are vertical with one end of the second square tube and third party's pipe respectively to be connected, and described first The centre of square tube is vertical with one end of the 4th square tube and the 5th square tube respectively to be connected, second square tube, third party's pipe, four directions Pipe and the 5th square tube and the wall body vertical, the oblique other end with the 4th square tube in one end of the 6th square tube are connected, and the 6th The other end of square tube is connected with the first steel plate, first steel plate and the wall connecting, and one end of the 7th square tube is oblique and institute The other end connection of the 5th square tube is stated, the other end of the 7th square tube is connected with first steel plate, one end of eighth pipe and institute One end connection of the 4th square tube is stated, the other end of eighth pipe is connected with the second steel plate, one end of the 9th square tube and the described 5th One end connection of square tube, the other end of the 9th square tube is connected with the second steel plate, and second steel plate is connected on the wall, institute Hoist engine is stated to be fixed in the 4th square tube and the 5th square tube, two vertical draglines respectively with the second square tube and third party's pipe The other end is connected.
Further, in above-mentioned hanging basket, protective cover is provided with the hoist engine.
Further, in above-mentioned hanging basket, the Operation switch is arranged on the pre- of the exterior wall scaffold by extended line If on height.
Further, in above-mentioned hanging basket, mouth is additionally provided with stopping means, the spacing dress under the serving of the hoist engine Put and be connected with the power supply of hoist engine.
Further, in above-mentioned hanging basket, every group of slide guide wheel is made up of two pulleys, and every vertical dragline is from two Passed through between pulley, described two pulleys are slided on a vertical dragline simultaneously.
Further, in above-mentioned hanging basket, the hanging basket is L-shaped.
Further, in above-mentioned hanging basket, the hanging basket external coating has yellow black alternate striped.
Further, in above-mentioned hanging basket, safety belt is provided with the hanging basket.
Compared with prior art, the utility model for solve traditional construction in, external wall of high-rise building stone material construction stone material Shipping yard is narrow and small, and vertical transport difficulty is big, is difficult to ensure that safely, the problem of labor intensive material resources, for hanging down for outer wall stone Straight transport, there is provided Stone Vertical transport hanging basket in a kind of innovation, exterior wall scaffold efficiently, safe, by fast-assembling bolster, volume Raise the cooperating of the components such as machine, hanging basket, vertical dragline so that in scaffold in vertical direction stone material transport become it is simple, It is safe and reliable, and install, dismantle it is simple and quick.In addition, vertical dragline one end is by the way that vertical dragline coupling assembly is direct and institute Exterior wall scaffold connection is stated, influence of the ground factor to vertical transport equipment is eliminated.
Brief description of the drawings
Fig. 1 is the structure chart that Stone Vertical transports hanging basket in the exterior wall scaffold of the embodiment of the utility model one;
Fig. 2 is the Facad structure figure of the fast-assembling bolster of the embodiment of the utility model one;
Fig. 3 is the backside structure figure of the fast-assembling bolster of the embodiment of the utility model one;
Fig. 4 is the scheme of installation of the hoist engine of the embodiment of the utility model one;
Fig. 5 is the structure chart of the Operation switch of the embodiment of the utility model one;
Fig. 6 is the scheme of installation of the stopping means of the embodiment of the utility model one;
Fig. 7 is the connection diagram of the hanging basket of the embodiment of the utility model one;
Fig. 8 is the schematic diagram of the slide guide wheel of the embodiment of the utility model one;
Fig. 9 is the schematic diagram of the hanging basket for being brushed with yellow black alternate striped of the embodiment of the utility model one;
Figure 10 is the structure chart of the hanging basket of the embodiment of the utility model one;
Figure 11 is the profile of the hanging basket of the embodiment of the utility model one;
Figure 12 is the connection diagram of the vertical dragline coupling assembly of the embodiment of the utility model one;
Figure 13 is the structure chart of the scaffold fastenings of the embodiment of the utility model one;
Figure 14 is the structure chart of the vertical dragline connector of the embodiment of the utility model one;
Figure 15 is the connection diagram of the vertical dragline connector of the embodiment of the utility model one;
Figure 16 is the connection diagram of the vertical dragline of the embodiment of the utility model one;
Figure 17 is the connection enlarged drawing of the vertical dragline of the embodiment of the utility model one;
Figure 18 be the embodiment of the utility model one can folding and unfolding load-bearing operating platform structure chart;
Figure 19 be the embodiment of the utility model one can folding and unfolding load-bearing operating platform scheme of installation;
Figure 20 is the connection diagram of the platform coupling assembly of the embodiment of the utility model one;
Figure 21 is the schematic diagram of the platform coupling assembly of the embodiment of the utility model one;
Figure 22 be the embodiment of the utility model one can folding and unfolding hook pack up schematic diagram;
Figure 23 be the embodiment of the utility model one can folding and unfolding hook expanded schematic diagram;
Figure 24 be the embodiment of the utility model one can folding and unfolding load-bearing operating platform put down schematic diagram;
Figure 25 be the embodiment of the utility model one can folding and unfolding hook connection diagram;
Figure 26 be the embodiment of the utility model one can folding and unfolding load-bearing operating platform pack up front elevation;
Figure 27 be the embodiment of the utility model one can folding and unfolding load-bearing operating platform pack up back view.
Specific embodiment
To enable above-mentioned purpose of the present utility model, feature and advantage more obvious understandable, below in conjunction with the accompanying drawings and tool Body implementation method is described in further detail to the utility model.
As shown in figure 1, the utility model provides Stone Vertical transport hanging basket in a kind of exterior wall scaffold, including:
Exterior wall scaffold 1, is separated by predeterminable range, the bottom of the exterior wall scaffold between the exterior wall scaffold 1 and wall 5 Portion is provided with two vertical dragline coupling assemblies 2 extended to the wall;
It is arranged at the fast-assembling bolster 3 on the wall 5, the top phase of the fast-assembling bolster 3 and the exterior wall scaffold 1 It is right;
Two spaced vertical draglines 4, the top of every vertical dragline 4 is connected with the fast-assembling bolster 3, and every hangs down The bottom vertical dragline coupling assembly 2 described with of straight dragline 4 is connected;
The hoist engine 6 on the fast-assembling bolster 3 is arranged at, and the Operation switch 7 being connected with the hoist engine 6;Hoist engine 1~100 meter of hoisting depth of design;
Moving up and down, it is vertical to be surrounded in the exterior wall scaffold 1, wall 5, hoist engine 6 and vertical dragline coupling assembly 2 Hanging basket 8 in space, the hanging basket upper end is provided with hanger 9, and the hanger 9 is connected with the serving 10 on the hoist engine 6, institute State the both sides of hanging basket 8 and be provided with two groups of slide guide wheels 11, every group of slide guide wheel 11 is slided on a vertical dragline 4.Here, this Utility model is in solution traditional construction, the stone material shipping yard of external wall of high-rise building stone material construction is narrow and small, vertical transport difficulty Greatly, it is difficult to ensure that safely, labor intensive material resources, for the vertical transport of outer wall stone, there is provided one kind innovation, efficient, safety Exterior wall scaffold in Stone Vertical transport hanging basket, by the cooperation of the components such as fast-assembling bolster, hoist engine, hanging basket, vertical dragline Work so that it is simple, safe and reliable that the stone material transport in scaffold in vertical direction becomes, and install, dismantle simply soon Speed, in addition, vertical dragline one end by vertical dragline coupling assembly directly and exterior wall scaffold connection, eliminate ground because Influence of the element to vertical transport equipment, and install, dismantle quick and convenient, the other end and fast-assembling bolster are connected.As shown in figure 12, institute Vertical dragline coupling assembly 2 is stated by the scaffold fastenings 21 including being sequentially connected, extension framework 22, vertical dragline connector 23, the extension framework 22 is connected by scaffold fastenings 21 with exterior wall scaffold 1, and the extension framework 22 is by vertically leading Rope connector 23 is connected with the vertical dragline 4, and the part of the scaffold fastenings 21 is as shown in figure 13, described vertical As shown in figure 14, the extension framework 22 is vertical with described by vertical dragline connector 23 for the part of dragline connector 23 The enlarged drawing of the connection of dragline 4 is as shown in figure 15.
In the embodiment of the utility model one, may also include and be movably connected in the preset height of the exterior wall scaffold 1 Can folding and unfolding load-bearing operating platform 12, it is described can folding and unfolding load-bearing operating platform 12 guardrail of the exterior wall scaffold 1 is formed when packing up, It is described can folding and unfolding load-bearing operating platform 12 exterior wall scaffold 1 is extended to the wall 5 when putting down.
In the embodiment of the utility model one, as shown in Figures 2 and 3, the fast-assembling bolster 3 by 9 square tubes and 2 blocks of steel plates, its In the first square tube 31 be arranged in parallel with wall 5, the two ends of first square tube 31 respectively with the second square tube 32 and third party's pipe 33 One end vertically connect, the centre of first square tube 31 is vertical with one end of the 4th square tube 34 and the 5th square tube 35 respectively to be connected Connect, second square tube 32, third party's pipe 33, the 4th square tube 34 and the 5th square tube 35 are vertical with the wall 5, the 6th square tube 36 The oblique other end with the 4th square tube 34 in one end be connected, the other end of the 6th square tube 36 is connected with the first steel plate 38, institute State the first steel plate 38 to be connected with the wall 5, the oblique other end with the 5th square tube 35 in one end of the 7th square tube 37 is connected, The other end of the 7th square tube 37 is connected with first steel plate 38, one end of one end of eighth pipe 38 and the 4th square tube 34 Connection, the other end of eighth pipe 39 is connected with the second steel plate 41, one end of the 9th square tube 40 and the one of the 5th square tube 35 End connection, the other end of the 9th square tube 40 is connected with the second steel plate 41, and second steel plate 41 is connected on the wall 5, institute State hoist engine 6 to be fixed in the 4th square tube 34 and the 5th square tube 35, as shown in FIG. 16 and 17, two vertical draglines 4 are distinguished The other end with the second square tube 32 and third party's pipe 33 is connected.Here, fast-assembling bolster passes through weldering by 9 square steel and two blocks of steel plates Connect, bolt connection is constituted, as shown in figure 4, hoist engine 6 is connected by 4 flat head bolts with the 4th square tube 34 and the 5th square tube 35, By being welded to connect between square steel and steel plate, by welding and bolt connection between square steel and square steel, the first and second steel plates point Not Tong Guo 3 expansion bolts and wall connecting, install, dismantle it is simple and quick.
In the embodiment of the utility model one, as shown in figure 4, being provided with protective cover 13 on the hoist engine 6, hoist engine passes through 4 flat head bolts and fast-assembling bolster are connected, and protective cover is set on hoist engine, play a part of sun-proof rain-proof.This practicality is new In the embodiment of type one, hoist engine is maximum to carry 1000KG, and design carries 500KG.
In the embodiment of the utility model one, as shown in figure 5, the Operation switch 7 be arranged on by extended line 14 can folding and unfolding Near load-bearing operating platform 12, operating personnel are facilitated to operate hoist engine according to field condition, the Operation switch includes up pressing Button 71 and down button 72.Here, pinning up button, hoist engine is up lifted, and hoist engine stops lifting after the button that comes loose;Together Reason, pins down button, and hoist engine down declines, and hoist engine stops declining after the button that comes loose, and prevents the generation of maloperation event. Down button is pinned, hoist engine down declines, hoist engine stops declining after the button that comes loose, simple to operate to understand, prevents maloperation The generation of event.
In the embodiment of the utility model one, as shown in fig. 6, mouth is additionally provided with stopping means under the serving of the hoist engine 6 15, the stopping means 15 is connected with the power supply of hoist engine 6, here, setting stopping means as Anti-over-hoisting device, hoist engine is carried During rising, lower mouth stopping means is bumped against when hanger rises, then stopping means is connected with power supply can at once cut off the electricity of hoist engine Source, it is to avoid hoist engine is rushed to summit damage.
In the embodiment of the utility model one, every group of slide guide wheel is made up of two pulleys, and every vertical dragline is from two Passed through between pulley, described two pulleys are slided on a vertical dragline simultaneously.Here, hanging basket both sides respectively set double group slide guides Wheel, vertical dragline is passed through between two pulleys, and cooperating limits the movement locus of hanging basket, it is therefore prevented that hanging basket is in level Motion on direction and topple.
In the embodiment of the utility model one, as shown in Fig. 7,8,9,10 and 11, the hanging basket 8 is L-shaped, is easy to load stone Material.Here, L-shaped hanging basket originally belongs to eccentric equipment, eccentric hanger is used as by increasing the upper end hanger 9 of hanging basket 8, and by with volume Raise under the orientation works status condition that machine 6 is connected and every group of slide guide wheel 11 is made up of two pulleys, eliminate the eccentric shadow of hanging basket Ring, reach antidumping effect.Hanging basket center of gravity and hanger, vertical dragline are in same vertical plane.Stone material is positioned in hanging basket When, oblique placement, its center of gravity and hanging basket center of gravity are in same vertical plane.
In the embodiment of the utility model one, as shown in figure 9, the external coating of the hanging basket 8 has yellow black alternate striped 82, Reach warning function, it is ensured that the safety in operating process.
In the embodiment of the utility model one, as shown in Fig. 7,9,10 and 11, safety belt 81 is provided with the hanging basket 8.This In the embodiment of utility model one, hanging basket 800-1000mm high, 1800mm long, 300mm wide are made up of steel frame and aluminium sheet, can be same When load the stone material high of 2-3 blocks 1600 wide 700, two retractable safety bands are set on hanging basket, fixing stone, limitation stone material is in water Square upward displacement, it is ensured that the security of transport hanging basket.
In the embodiment of the utility model one, as shown in Figure 18~27, it is described can folding and unfolding load-bearing operating platform 12, by steel frame Constituted with aluminium sheet, it is ensured that while its rigidity, alleviate its weight, it is described can folding and unfolding load-bearing operating platform 12 side by flat Platform coupling assembly 121 and the exterior wall scaffold 1 are flexibly connected, while can be provided with can the another both sides of folding and unfolding load-bearing operating platform 122 and pulling plug 123 are linked up with folding and unfolding, by can folding and unfolding link up with 122, platform coupling assembly 121 and pulling plug 123 so that can folding and unfolding hold Weight operating platform 12 and the hanging basket of the exterior wall scaffold 1 are combined as a whole, and during work, putting down can receive load-bearing operating platform, such as scheme 19th, shown in 24 and 25, can folding and unfolding hook 122 and the exterior wall scaffold 1 connect, play transfer stone material, load-bearing, active station people etc. and make With, now can folding and unfolding hook 122 state it is as shown in figure 23.Can folding and unfolding hook 122 and can folding and unfolding load-bearing operating platform 12 frame Frame is welded.As shown in figures 26 and 27, when not working, pack up can folding and unfolding hook, packing up can receive load-bearing operating platform, pulling plug and described Exterior wall scaffold is connected, and load-bearing operating platform can use as scaffold guard rail, now can folding and unfolding hook 122 state such as Figure 22 It is shown.And remove and install simple, quick, the rapid working face installed and need handling.Platform coupling assembly, and load-bearing operation Platform welding, scaffold is connected by flat head bolt.In addition, safety net can be set in lifting working face both sides, it is ensured that lifted Personal security in journey.
As shown in figure 1, Stone Vertical transports the installation and application of hanging basket in above-mentioned exterior wall scaffold, including:
Exterior wall scaffold 1 is set, is separated by predeterminable range between the exterior wall scaffold 1 and wall 5, in the outer foundation hand The bottom of frame 1 sets two vertical dragline coupling assemblies 2 extended to the wall 6;Here, according to construction speed, it is determined that outward Foundation hand cradle, fast-assembling bolster, can folding and unfolding load-bearing operating platform, vertical hoist cable installation site;In stone wall surface construction, it is desirable under Supreme construction;
Face is indulged according to stone material construction working, fast-assembling bolster 3 is fixed on the wall, the fast-assembling bolster 3 is outer with described The top of foundation hand cradle is relative, and hoist engine 6, and the Operation switch being connected with the hoist engine 6 are installed on the fast-assembling bolster 3 7, two vertical draglines 4 are installed, the top of every vertical dragline 4 is connected with the fast-assembling bolster 3, the every bottom of vertical dragline 4 End vertical dragline coupling assembly 2 described with is connected, and the Operation switch 7 is arranged on into the outer foundation hand by extended line Near stone material construction height on frame;
Hanging basket 8 is installed from the bottom of exterior wall scaffold 1, hanger 9 is set in the upper end of hanging basket 8, by the hanger 9 and the volume The serving 10 raised on machine 6 is connected, and two groups of slide guide wheels 11 are set in the both sides of the hanging basket 8, and every group of slide guide wheel 11 is described vertical at one Slided on straight dragline 4, the hanging basket 8 moves up and down in the exterior wall scaffold, wall, hoist engine and vertical dragline coupling assembly In surrounded vertical space;
Lifting group, every group of 2 people are set, and are equipped with intercom 2, wherein, ground handling operator 1, take charge stone The loading of material, after loading is finished, intercom notifies that scope of operation operating personnel are responsible for lifting operation, and is responsible for the peace during lifting Full monitoring, scope of operation operating personnel operate the button of the Operation switch to continue to put down hanging basket to job platform, are responsible for stone material Unloading, the ground and operation and operating personnel respectively at lifting bottom and the scope of operation can folding and unfolding load-bearing operating platform side be absorbed in it is whole Individual hoisting process, correction in time of pinpointing the problems, and keep in touch at any time, it is ensured that lifting safety;
The scope of operation operating personnel are down to the bottom of exterior wall scaffold by hanging basket 8, and the hook of hanging basket and hoist engine is all the time In connection status, toppling for hanging basket is prevented, be positioned over stone material on hanging basket by the ground handling operator, oblique placement, protected Card stone material center of gravity and hanging basket center of gravity are on a vertical plane;
The ground handling operator notifies the scope of operation operating personnel by the Operation switch, control by intercom Hoist engine lifts by crane the stone material in the hanging basket, and at the beginning, speed is slow, during lifting, at the uniform velocity carries out for lifting, during lifting, Lower work personnel forbid to enter lifting working region;
When hanging basket rises to the job platform, the scope of operation operating personnel are stopped by the release Operation switch The hoist engine drives the hanging basket to continue to lift by crane rising, and the scope of operation standing unloads stone on the job platform After material, the hoist engine is controlled to drive hanging basket to continue to drop to ground floor by the Operation switch.
In the embodiment of the utility model one, while installing two vertical draglines, always according to stone material construction height described Being installed on exterior wall scaffold 1 can folding and unfolding load-bearing operating platform 12.
In the embodiment of the utility model one,
Lifting group, every group of 2 people are set, and are equipped with intercom 2, wherein, ground handling operator 1, take charge stone The loading of material, after loading is finished, intercom notifies that scope of operation operating personnel are responsible for lifting operation, and is responsible for the peace during lifting Full monitoring, the button of the scope of operation operating personnel operation Operation switch makes hanging basket to job platform, is responsible for the unloading of stone material, institute State ground and operation and operating personnel respectively at lifting bottom and the scope of operation can folding and unfolding load-bearing operating platform side be absorbed in whole lifting Process, correction in time of pinpointing the problems, and keep in touch at any time, it is ensured that lifting safety;
The scope of operation operating personnel are down to the bottom of exterior wall scaffold by hanging basket 8, and the hook of hanging basket and hoist engine is all the time In connection status, toppling for hanging basket is prevented, be positioned over stone material on hanging basket by the ground handling operator, oblique placement, protected Card stone material center of gravity and hanging basket center of gravity are on a vertical plane;
The ground handling operator notifies the scope of operation operating personnel by the Operation switch, control by intercom Hoist engine lifts by crane the stone material in the hanging basket, and at the beginning, speed is slow, during lifting, at the uniform velocity carries out for lifting, during lifting, Lower work personnel forbid to enter lifting working region;
When hanging basket rises to the job platform, the scope of operation operating personnel are stopped by the release Operation switch The hoist engine drives the hanging basket to continue to lift by crane rising, and the scope of operation standing unloads stone on the job platform After material, the hoist engine is controlled to drive hanging basket to continue to drop to ground floor by the Operation switch, including:
Lifting group, every group of 2 people are set, and are equipped with intercom 2, wherein, ground handling operator 1, take charge stone The loading of material, after loading is finished, intercom notifies that scope of operation operating personnel are responsible for lifting operation, and is responsible for the peace during lifting Full monitoring, after hanging basket is higher than job platform, scope of operation operating personnel unclamp the button of the Operation switch, stop lifting, put It is lower described can be after folding and unfolding load-bearing operating platform, scope of operation operating personnel operate the button of the Operation switch to continue to put down hanging basket extremely Can folding and unfolding load-bearing operating platform, be responsible for the unloading of stone material, the ground and operation and operating personnel respectively at lifting bottom and work Industry face can be absorbed in whole hoisting process by folding and unfolding load-bearing operating platform, correction in time of pinpointing the problems, and keep in touch at any time, it is ensured that Lifting safety;
The scope of operation operating personnel are down to the bottom of exterior wall scaffold by hanging basket 8, and the hook of hanging basket and hoist engine is all the time In connection status, toppling for hanging basket is prevented, be positioned over stone material on hanging basket by the ground handling operator, oblique placement, protected Card stone material center of gravity and hanging basket center of gravity are on a vertical plane;
The scope of operation operating personnel will it is described can folding and unfolding load-bearing operating platform set and be in collapsed state, the ground behaviour Make personnel notifies the scope of operation operating personnel by the Operation switch by intercom, and control hoist engine lifts by crane the hanging basket In stone material, at the beginning, speed is slow, during lifting, at the uniform velocity carries out for lifting, during lifting, lower work personnel forbid into Enter to lift working region;
When hanging basket rise to it is described can 1 meter of folding and unfolding load-bearing operating platform top when, the scope of operation operating personnel are by described Unclamp Operation switch, stop the hoist engine and drive the hanging basket to continue to lift by crane and rise, put down it is described can folding and unfolding load-bearing operation it is flat After platform, fall hanging basket extremely can folding and unfolding load-bearing operating platform, the scope of operation standing it is described can folding and unfolding load-bearing operation it is flat After unloading stone material on platform, by the Operation switch control the hoist engine drive hanging basket rise to it is described can folding and unfolding load-bearing operate it is flat Platform top 1 meter of height, pack up can folding and unfolding load-bearing operating platform, can folding and unfolding load-bearing operating platform used as scaffold guard rail, Hanging basket continues to drop to ground floor.
In the embodiment of the utility model one, after hanging basket is installed from the bottom of exterior wall scaffold, also include:
In the range of 1 meter of both sides of the vertical space, longitudinally disposed safety net, with during ensureing vertical transport, under Side passes through without personnel, it is ensured that construction safety.
In the embodiment of the utility model one, fast-assembling bolster is fixed on the wall, volume is installed on the fast-assembling bolster Machine is raised, including:
The fast-assembling bolster by 9 square tubes and 2 blocks of steel plates, wherein, the first square tube and wall are be arranged in parallel, by described The two ends of one square tube are vertical with one end of the second square tube and third party's pipe respectively to be connected, by the centre of first square tube respectively with One end of 4th square tube and the 5th square tube vertically connects, second square tube, third party's pipe, the 4th square tube and the 5th square tube and institute Wall body vertical is stated, the oblique other end with the 4th square tube in one end of the 6th square tube is connected, by the other end of the 6th square tube It is connected with the first steel plate, it is by first steel plate and the wall connecting, one end of the 7th square tube is oblique with the 5th side The other end connection of pipe, the other end of the 7th square tube is connected with the first steel plate, by one end of eighth pipe and the 4th square tube One end connection, the other end of eighth pipe is connected with the second steel plate, by one end of the 9th square tube and the 5th square tube One end is connected, and the other end of the 9th square tube is connected with the second steel plate, and the eighth pipe and the 9th square tube are parallel with wall, will Second steel plate is connected on the wall, the hoist engine is fixed in the 4th square tube and the 5th square tube, two The vertical other end of the dragline respectively with the second square tube and third party's pipe is connected.Here, fast-assembling bolster is by 9 square steel and two blocks of steel plates It is made up of welding, bolt connection, hoist engine is connected by 4 flat head bolts with the 4th square tube and the 5th square tube, square steel and steel By being welded to connect between plate, by welding and bolt connection between square steel and square steel, the first and second steel plates pass through 3 respectively Expansion bolt and wall connecting, install, dismantle it is simple and quick.
In the embodiment of the utility model one, after installation hoist engine on the fast-assembling bolster, also include:
Protective cover is set in the hoist engine, hoist engine is connected by 4 flat head bolts and fast-assembling bolster, hoist engine Upper setting protective cover, plays a part of sun-proof rain-proof.In the embodiment of the utility model one, hoist engine is maximum to carry 1000KG, if Meter carries 500KG.
In the embodiment of the utility model one, the Operation switch is arranged on the default of the exterior wall scaffold by extended line On height, operating personnel are facilitated to operate hoist engine according to field condition, the Operation switch includes up button and down button. Here, pinning up button, hoist engine is up lifted, and hoist engine stops lifting after the button that comes loose;Similarly, down button is pinned, Hoist engine down declines, and hoist engine stops declining after the button that comes loose, and prevents the generation of maloperation event.Down button is pinned, is rolled up Raise machine down to decline, hoist engine stops declining after the button that comes loose, simple to operate to understand, prevents the generation of maloperation event.
In the embodiment of the utility model one, after installation hoist engine on the fast-assembling bolster, also include:
Mouth sets stopping means under the serving of the hoist engine, and the stopping means is connected with the power supply of hoist engine, Here, setting stopping means as Anti-over-hoisting device, in hoist engine lifting process, lower mouth stopping means is bumped against when hanger rises, Then stopping means is connected with power supply can at once cut off the power supply of hoist engine, it is to avoid hoist engine is rushed to summit damage.
In the embodiment of the utility model one, two groups of slide guide wheels are set in the hanging basket both sides, every group of slide guide wheel is in an institute State and slided on vertical dragline, including:
Every group of slide guide wheel is set to be made up of two pulleys, the vertical dragline is passed through between two pulleys, institute Two pulleys are stated to be slided on the vertical dragline simultaneously.Here, hanging basket both sides respectively set double group slide guide wheels, vertical dragline is from two Passed through between individual pulley, cooperating, limit the movement locus of hanging basket, it is therefore prevented that hanging basket motion in the horizontal direction and inclined Cover.
In the embodiment of the utility model one, the hanging basket is L-shaped, to facilitate loading stone material.Here, L-shaped hanging basket belongs to originally Designed in bias, eccentric hanger be used as by increasing hanging basket upper end hanger, and by be connected with hoist engine and every group of slide guide wheel by Under two orientation works status conditions of pulley composition, the Influence from Eccentric of hanging basket is eliminated, reach antidumping effect.Hanging basket center of gravity It is in same vertical plane with hanger, vertical dragline.When stone material is positioned in hanging basket, oblique placement, its center of gravity and hanging basket weight The heart is in same vertical plane.
In the embodiment of the utility model one, before hanging basket is installed from the bottom of exterior wall scaffold, also include:
In the yellow black alternate striped of the hanging basket external coating, warning function has been reached, it is ensured that the safety in operating process.
In the embodiment of the utility model one, after hanging basket is installed from the bottom of exterior wall scaffold, also include:
Safety belt is set on the hanging basket;
After stone material is positioned on hanging basket, also include:
Using safety belt fixing stone position.In the embodiment of the utility model one, hanging basket 800-1000mm high is long 1800mm, 300mm wide, are made up of steel frame and aluminium sheet, can simultaneously load the stone material high of 2-3 blocks 1600 wide 700, are set on hanging basket Two retractable safety bands, fixing stone, limitation stone material displacement in the horizontal direction, it is ensured that the security of transport hanging basket.
In the embodiment of the utility model one, on the exterior wall scaffold install can folding and unfolding load-bearing operating platform, including:
By it is described can folding and unfolding load-bearing operating platform be set to be made up of steel frame and aluminium sheet, it is ensured that while its rigidity, subtract Light its weight, by it is described can folding and unfolding load-bearing operating platform side by platform coupling assembly and exterior wall scaffold activity Connection, at the same can folding and unfolding load-bearing operating platform another both sides set can folding and unfolding hook and pulling plug;
Put down it is described can folding and unfolding load-bearing operating platform, including:
Remove it is described can folding and unfolding load-bearing operating platform and the exterior wall scaffold pulling plug connection, put down can folding and unfolding hook, Put down it is described can folding and unfolding load-bearing operating platform, here, now hanger and the exterior wall scaffold are connected, play load-bearing effect, subsequently Hanging basket to load-bearing operating platform can be fallen, stone material is unloaded, home is transported to;
Pack up can folding and unfolding load-bearing operating platform, including:
Pack up it is described can folding and unfolding load-bearing operating platform, pack up it is described can folding and unfolding hook, will it is described can folding and unfolding load-bearing operation it is flat Platform is connected by pulling plug and the exterior wall scaffold, subsequently falls hanging basket to ground, transport of reloading.Specifically, removing is held Weight operating platform and the exterior wall scaffold pulling plug connection, put down can folding and unfolding hook, put down can folding and unfolding load-bearing operating platform, this When can folding and unfolding hook and the exterior wall scaffold connection, rise load-bearing effect.Fall hanging basket extremely can folding and unfolding load-bearing operating platform, it is described Second standing it is described can unload stone material on folding and unfolding load-bearing operating platform after, the volume is controlled by the Operation switch Raise machine drive hanging basket rise to it is described can the 1 meter of height in folding and unfolding load-bearing operating platform top, pack up can folding and unfolding load-bearing operating platform, pack up Can folding and unfolding hook, load-bearing operating platform connected by pulling plug and the exterior wall scaffold, can be used as scaffold guard rail.Fall Hanging basket to ground, transport of reloading.Here, by can folding and unfolding hook, platform coupling assembly and pulling plug so that load-bearing operation is flat Platform and the exterior wall scaffold hanging basket are combined as a whole, and during work, putting down can receive load-bearing operating platform, can folding and unfolding hook and it is described Exterior wall scaffold is connected, and plays transfer stone material, load-bearing, active station people etc..Can folding and unfolding hook and platform framework welding, do not work When, pack up can folding and unfolding hook, packing up can receive load-bearing operating platform, and pulling plug and the exterior wall scaffold are connected, load-bearing operating platform Can be used as scaffold guard rail, and remove and install simple, quick, the rapid working face installed and need handling.Platform connects Connected components, and the welding of load-bearing operating platform, scaffold is connected by flat head bolt.In addition, can be set in lifting working face both sides Safety net, it is ensured that the personal security in hoisting process.
In addition, in terms of hoist engine maintenance:(1) the braking hanging basket to hoist engine carries out regular adjustment, holds lotus situation Under, without lower sliding phenomenon after object of slinging shutdown.(2) weld seam between bolster answers the phenomenons such as flawless, displacement.(3) hoist engine with The connecting bolt of square steel answers non-loosening, by the phenomenon for cutting flexural deformation.(4) the hand-held switch of hoist engine, it is necessary to keep dry Dry, the rainy day is wrapped using application Nylon Bag, prevents electric leakage of making moist.(5) equipment is periodically checked weekly by full-time staff, adjusted It is whole.Adjustment braking hanging basket process should be debugged with peak load, have no lower sliding phenomenon.
In sum, the utility model is in solution traditional construction, the stone material of external wall of high-rise building stone material construction transports field Ground is narrow and small, and vertical transport difficulty is big, is difficult to ensure that safely, the problem of labor intensive material resources, for the vertical transport of outer wall stone, There is provided Stone Vertical transport hanging basket in a kind of innovation, exterior wall scaffold efficiently, safe, by fast-assembling bolster, hoist engine, hang The cooperating of the components such as basket, vertical dragline so that in scaffold in vertical direction stone material transport become it is simple, safe, can Lean on, and install, dismantle it is simple and quick.In addition, vertical dragline one end by vertical dragline coupling assembly directly with the exterior wall Scaffold is connected, and eliminates influence of the ground factor to vertical transport equipment.
Each embodiment is described by the way of progressive in this specification, and what each embodiment was stressed is and other The difference of embodiment, between each embodiment identical similar portion mutually referring to.
Obviously, those skilled in the art can carry out various changes to utility model and modification is new without deviating from this practicality The spirit and scope of type.So, if it is of the present utility model these modification and modification belong to the utility model claim and its Within the scope of equivalent technologies, then the utility model is also intended to including including these changes and modification.

Claims (9)

1. Stone Vertical transports hanging basket in a kind of exterior wall scaffold, it is characterised in that including:
Exterior wall scaffold, is separated by predeterminable range between the exterior wall scaffold and wall, the bottom of the exterior wall scaffold is set There are two vertical dragline coupling assemblies extended to the wall;
The fast-assembling bolster on the wall is arranged at, the fast-assembling bolster is relative with the top of the exterior wall scaffold;
Two spaced vertical draglines, the top of every vertical dragline is connected with the fast-assembling bolster, every vertical dragline Bottom vertical dragline coupling assembly described be connected;
The hoist engine on the fast-assembling bolster is arranged at, and the Operation switch being connected with the hoist engine;
Move up and down and surrounded in vertical space in the exterior wall scaffold, wall, hoist engine and vertical dragline coupling assembly Hanging basket, the hanging basket upper end is provided with hanger, and the hanger is connected with the serving on the hoist engine, and the hanging basket both sides are set There are two groups of slide guide wheels, every group of slide guide wheel is slided on a vertical dragline.
2. in exterior wall scaffold as claimed in claim 1 Stone Vertical transport hanging basket, it is characterised in that the fast-assembling bolster by 9 square tubes and 2 blocks of steel plates, wherein the first square tube be arranged in parallel with wall, the two ends of first square tube respectively with the second square tube One end with third party's pipe vertically connects, and the one end of the centre of first square tube respectively with the 4th square tube and the 5th square tube is vertical Connection, second square tube, third party's pipe, the 4th square tube and the 5th square tube and the wall body vertical, one end of the 6th square tube is oblique It is connected to the other end with the 4th square tube, the other end of the 6th square tube is connected with the first steel plate, first steel plate and institute Wall connecting is stated, the oblique other end with the 5th square tube in one end of the 7th square tube is connected, the other end of the 7th square tube and institute The connection of the first steel plate is stated, one end of eighth pipe is connected with one end of the 4th square tube, the other end of eighth pipe and second Steel plate is connected, and one end of the 9th square tube is connected with one end of the 5th square tube, and the other end of the 9th square tube and the second steel plate connect Connect, second steel plate is connected on the wall, the hoist engine is fixed in the 4th square tube and the 5th square tube, two The vertical other end of the dragline respectively with the second square tube and third party's pipe is connected.
3. Stone Vertical transports hanging basket in exterior wall scaffold as claimed in claim 1, it is characterised in that set on the hoist engine It is equipped with protective cover.
4. Stone Vertical transports hanging basket in exterior wall scaffold as claimed in claim 1, it is characterised in that the Operation switch is led to Extended line is crossed to be arranged in the preset height of the exterior wall scaffold.
5. Stone Vertical transports hanging basket in exterior wall scaffold as claimed in claim 1, it is characterised in that the volume of the hoist engine The lower mouth of rope is additionally provided with stopping means, and the stopping means is connected with the power supply of hoist engine.
6. Stone Vertical transports hanging basket in exterior wall scaffold as claimed in claim 1, it is characterised in that every group of slide guide wheel It is made up of two pulleys, every vertical dragline is passed through between two pulleys, described two pulleys are simultaneously in a vertical dragline Upper slip.
7. Stone Vertical transports hanging basket in exterior wall scaffold as claimed in claim 1, it is characterised in that the hanging basket is L-shaped.
8. Stone Vertical transports hanging basket in exterior wall scaffold as claimed in claim 1, it is characterised in that the hanging basket surface applies It is brushed with yellow black alternate striped.
9. Stone Vertical transports hanging basket in exterior wall scaffold as claimed in claim 1, it is characterised in that set on the hanging basket There is safety belt.
CN201621231701.7U 2016-11-16 2016-11-16 Stone Vertical transport hanging basket in exterior wall scaffold Expired - Fee Related CN206266182U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621231701.7U CN206266182U (en) 2016-11-16 2016-11-16 Stone Vertical transport hanging basket in exterior wall scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621231701.7U CN206266182U (en) 2016-11-16 2016-11-16 Stone Vertical transport hanging basket in exterior wall scaffold

Publications (1)

Publication Number Publication Date
CN206266182U true CN206266182U (en) 2017-06-20

Family

ID=59039475

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621231701.7U Expired - Fee Related CN206266182U (en) 2016-11-16 2016-11-16 Stone Vertical transport hanging basket in exterior wall scaffold

Country Status (1)

Country Link
CN (1) CN206266182U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106586908A (en) * 2016-11-16 2017-04-26 上海市建筑装饰工程集团有限公司 Vertical stone conveying lifting basket inside external wall scaffold

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106586908A (en) * 2016-11-16 2017-04-26 上海市建筑装饰工程集团有限公司 Vertical stone conveying lifting basket inside external wall scaffold
CN106586908B (en) * 2016-11-16 2019-07-12 上海市建筑装饰工程集团有限公司 Stone Vertical transports hanging basket in exterior wall scaffold

Similar Documents

Publication Publication Date Title
CN106639287B (en) Stone Vertical transportation resources in exterior wall scaffold
CN204703746U (en) A kind of removable level-sensing device repairing platform device
CN206266182U (en) Stone Vertical transport hanging basket in exterior wall scaffold
CN204689430U (en) To Construction of Silo movable hoisting device
CN106586907B (en) The installation and application of Stone Vertical transport hanging basket in exterior wall scaffold
CN206309001U (en) Stone Vertical transportation system in exterior wall scaffold
CN103274310B (en) Self-lifting type cableway transporting device
CN111994820A (en) New energy automobile overhauls platform
CN106586908B (en) Stone Vertical transports hanging basket in exterior wall scaffold
CN110029807A (en) For installing the device of steel construction traverse colored steel
CN106639288A (en) Installing using method of vertical transporting platform of stone in outer wall scaffold
CN106592955A (en) Platform for vertically conveying stone material in exterior wall scaffolding
CN106522537B (en) Stone Vertical transportation system in exterior wall scaffold
CN208500144U (en) Bridge crane
CN206267514U (en) Stone Vertical shipping platform in exterior wall scaffold
CN207732338U (en) A kind of substation's cabinet installation hand push frame
CN206722431U (en) Discharging platform for high-rise building construction
CN216196814U (en) Adjustable horizontal entrance to a cave anti-falling device
CN212105183U (en) A safe unloading platform for high-rise buildings
CN210594973U (en) Multilayer indoor type arranges hoist and mount isolated plant who pulls pavilion dish cabinet of electric substation
CN203946779U (en) Loose steel pipe operation combined sling
CN208022620U (en) A kind of telescopic hoisting platform
CN214399682U (en) Hoisting device for building
CN205916997U (en) Mechanical and electrical installation movable tipping arrangement
CN206088904U (en) Guide tracked lift of guide rail detachable

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170620

Termination date: 20191116

CF01 Termination of patent right due to non-payment of annual fee