[go: up one dir, main page]

CN206090653U - Anchor rod static pressure pile slip casting structure - Google Patents

Anchor rod static pressure pile slip casting structure Download PDF

Info

Publication number
CN206090653U
CN206090653U CN201621099018.2U CN201621099018U CN206090653U CN 206090653 U CN206090653 U CN 206090653U CN 201621099018 U CN201621099018 U CN 201621099018U CN 206090653 U CN206090653 U CN 206090653U
Authority
CN
China
Prior art keywords
pile
slip casting
pipe
casting structure
structure according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621099018.2U
Other languages
Chinese (zh)
Inventor
顾国荣
李晓勇
刘冬
李明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Survey Design And Research Institute Group Co ltd
Original Assignee
Shanghai Geotechnical Investigations and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Geotechnical Investigations and Design Institute Co Ltd filed Critical Shanghai Geotechnical Investigations and Design Institute Co Ltd
Priority to CN201621099018.2U priority Critical patent/CN206090653U/en
Application granted granted Critical
Publication of CN206090653U publication Critical patent/CN206090653U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides an anchor rod static pressure pile slip casting structure, including a pipe, still include a slip casting pipe, the pipe wall evenly distributed of stake socle portion has a plurality of injected holes, the slip casting pipe is inserted and is located the stake is intraductal. The utility model discloses an anchor rod static pressure pile slip casting structure has and bears the weight of dynamic height, advantage that pile body rigidity is strong.

Description

Anchor jacked pile slip casting structure
Technical field
This utility model is related to building engineering field, more particularly to a kind of anchor jacked pile slip casting structure.
Background technology
In the area that groundwater level is higher, supporting course is poor, existing building is as superstructure is transformed or itself is reached The reasons such as design life, construction foundation bearing capacity are not enough, cause differential settlement of buildings, local run-off the straight.If Take effective measures not in time and building lot is reinforced, improve foundation bearing capacity and control building deformation, inequality can be caused Even sedimentation continues increase, will cause superstructure problems of crack, affects the normal using the use for even threatening building of building Safety, it is therefore desirable to which strengthening of foundation is carried out to existing building.
Conventional anchor jacked pile combines the characteristics of anchor pole and stake, can be used for the correcting and then reinforcing of existing building.But it is existing There is the injected hole of anchor jacked pile generally using the borehole structure being directly opened on tube wall, be not provided with corresponding plugging structure, So that entering in steel pipe by injected hole in the outer silt of piling pile or subsoil water, and then later stage slip casting may be caused Blockage cannot slip casting problem.
A kind of existing anchor rod static pressure pilework refers to Fig. 1, and which includes:Pile pipe 1, pile crown 2, it is sheathed on outside pile pipe 1 Pile pipe set 3 and the concrete being filled in pile pipe 1 fill out core 4.Existing anchor rod static pressure pilework does not arrange grout hole in pile pipe 1, May there is certain gap between pile pipe 1 and the outside soil body, so as to affect the carrying of anchor jacked pile to a certain extent Power.
The content of the invention
For above-mentioned deficiency of the prior art, this utility model provides a kind of anchor jacked pile slip casting structure, with holding Carry the strong advantage of power height, column rigidity.
To achieve these goals, this utility model provides a kind of anchor jacked pile slip casting structure, including a pile pipe, also wraps A Grouting Pipe is included, the even tube wall of the pile pipe bottom is distributed with multiple injected holes, and the Grouting Pipe is inserted in the pile pipe.
Further improvement of the utility model is that the Grouting Pipe extends the inside bottom of the pile pipe.
Further improvement of the utility model is, also including a cover plate, the peripheral top with the pile pipe of the cover plate Ferrule is fixed, and the cover plate offers a Grouting Pipe installing hole and a steam vent, the Grouting Pipe plug be fixed on it is described In Grouting Pipe installing hole, and seal between the Grouting Pipe and the Grouting Pipe installing hole.
Further improvement of the utility model is that, also including an exhaustor, the exhaustor is fixed on the steam vent And coordinate with the vent hole seal, exhaustor is provided with valve.
Further improvement of the utility model is, is filled with cement grout and rubble is formed compound fills out in the pile pipe Core.
Further improvement of the utility model is that each injected hole is provided with a plugging structure.
Further improvement of the utility model is that the plugging structure includes a closure plug, and the closure plug is inserted in Coordinate in the injected hole and with injected hole sealing.
Further improvement of the utility model is that the closure plug adopts flexible material.
Further improvement of the utility model is that the plugging structure is also including a protection component, the protection component It is fixed on the pile pipe tube wall and covers at the closure beyond the Great Wall.
Further improvement of the utility model is that the protection component includes a cover body and a filling member, the cover body It is fixed on the pile pipe tube wall and covers at the closure beyond the Great Wall, the cover body cooperatively forms an opening with the pile pipe tube wall, The filling member is filled in the cover body and covers the closure plug.
This utility model is as a result of above technical scheme so as to have the advantages that:
The employing of injected hole and Grouting Pipe so that injection slurry can be injected on the outside of pile pipe in the soil body under pressure, be increased Big side friction and end resistance between stake and the soil body, so as to effectively improve bearing capacity of pile foundation.Grouting Pipe stretches into the bottom of pile pipe Portion, it is ensured that injection slurry from the bottom of pile pipe to top pour, it is ensured that grouting it is uniform.The cooperation of cover plate and Grouting Pipe, realizes After the completion of pouring inside pile pipe, the pressure inside pile pipe can be increased by blocking steam vent so that effect of the grouting liquid in pressure Under from outside injected hole injection pile pipe in the soil body, so as to increase side friction and end resistance between pile pipe and the peripheral soil body, So as to effectively improve the bearing capacity of anchor jacked pile.Exhaustor is used for aerofluxuss during slip casting inside pile pipe.Water is filled with pile pipe The compound rigidity filled out core, increased anchor jacked pile that slurry liquid is formed with rubble.Closure plug is used to prevent the mud on the outside of pile pipe Husky and subsoil water is entered into inside pile pipe from injected hole, prevents injected hole from being blocked by silt, it is ensured that in closure plug abjection grouting behind shaft or drift lining Hole it is unobstructed.Protection component is used to further protect injected hole, prevents outside silt compressing closure plug, affects the de- of closure plug Go out.Closure plug adopts flexible material, strengthens closure plug and injected hole sealing and connectivity robustness.Cover body is used to prevent in piling During the closure that injected hole is caused of outside sandy soil, opening be set to block plug abjection and the pouring of grouting liquid is reserved Passage.Filling member is used to prevent envelope from being produced loosening by water and soil disturbance during being blocked in piling.
Description of the drawings
Structural representations of the Fig. 1 for the anchor jacked pile slip casting structure of prior art;
Structural representations of the Fig. 2 for the anchor jacked pile slip casting structure of this utility model embodiment;
Mplifying structure schematic diagrams of the Fig. 3 for the plugging structure of this utility model embodiment.
Specific embodiment
Below according to accompanying drawing 1-2, preferred embodiment of the present utility model is given, and is described in detail, enabled preferably Understand function of the present utility model, feature.
Refer to Fig. 2, a kind of anchor jacked pile slip casting structure of this utility model embodiment, including a pile pipe 1, be fixed on The pile top 2 of 1 bottom of pile pipe, a plurality of sleeve pipes 3, a Grouting Pipe 4, a cover plate 5 and an exhaustor 6.
In the present embodiment, pile pipe 1 includes a plurality of pile pipe sections, passes through outer hoop and to weld sleeve 3 close between adjacent studs pipeline section Envelope connection.The even tube wall of one pile pipe section of the neighbouring pile top 2 of 1 bottom of pile pipe is distributed with multiple injected holes 11, and injected hole 11 has Body position and quantity can be determined according to stratum and grouting amount.Grouting Pipe 4 stretches into the bottom of pile pipe 1, in the present embodiment, Grouting Pipe 4 Including multiple slip casting pipeline sections, the silk mouth structure that cooperates is formed between adjacent tubular segments and is tightly connected by silk mouth structure.
The employing of injected hole 11 and Grouting Pipe 4 so that injection slurry can be injected the 1 outside soil body of pile pipe under pressure In, the side friction and end resistance between stake and the soil body is increased, so as to effectively improve bearing capacity of pile foundation, sedimentation is reduced.Slip casting Pipe 4 stretches into the bottom of pile pipe 1, it is ensured that injection slurry from the bottom of pile pipe 1 to top pour, it is ensured that grouting it is uniform.
The 5 peripheral top ferrule with pile pipe 1 of cover plate is fixed, and cover plate 5 offers a Grouting Pipe installing hole and an aerofluxuss Hole, Grouting Pipe 4 plug and are fixed in Grouting Pipe installing hole, seal between Grouting Pipe 4 and Grouting Pipe installing hole.Exhaustor 6 is fixed on Steam vent is simultaneously coordinated with vent hole seal, and exhaustor 6 is provided with valve.(scheme filled with the compound core of filling out of concrete crushed stone in pile pipe 1 In do not show).
Exhaustor 6 is used for aerofluxuss during slip casting inside pile pipe 1.The cooperation of cover plate 5 and Grouting Pipe 4, realizes inside pile pipe 1 After the completion of pouring, the pressure inside pile pipe 1 can be increased by blocking steam vent so that grouting liquid is under the effect of the pressure from slip casting In the injection of the hole 11 1 outside soil body of pile pipe, so as to increase side friction and end resistance between pile pipe 1 and the peripheral soil body, so as to The bearing capacity of anchor jacked pile is effectively improved, sedimentation is reduced.It is filled with cement grout in pile pipe 1 and rubble is formed compound fills out Core, increased the rigidity of anchor jacked pile.
Fig. 3 is referred to, each injected hole 11 is provided with a plugging structure 12.Plugging structure 12 includes 121 He of a closure plug One protection component 122, closure plug 121 are inserted in injected hole 11 and are coordinated with the sealing of injected hole 11.In the present embodiment, closure plug 121 adopt flexible material.Protection component 122 is fixed on 1 tube wall of pile pipe and covers at outside closure plug 121.
Closure plug 121 is used to prevent silt and subsoil water on the outside of pile pipe 1 from entering into inside pile pipe 1 from injected hole 11, prevents Only injected hole 11 is blocked by silt, it is ensured that deviate from the unobstructed of grouting behind shaft or drift lining hole 11 in closure plug 121.Closure plug 121 is using flexible material Material, strengthens closure plug 121 and 11 sealing of injected hole and connectivity robustness.
Protection component 122 includes a cover body 1221 and a filling member 1222, and cover body 1221 is fixed on 1 tube wall of pile pipe and cover sets Outside closure plug 121, cover body 1221 cooperatively forms an opening 1223 with 1 tube wall of pile pipe, and filling member 1222 is filled in cover body 1221 It is interior and cover closure plug 121.
Cover body 1221 is used for the closure for preventing outside sandy soil during pile pipe 1 is pushed and buried from causing to injected hole 11, 121 abjection of closure plug that is set to of opening 1223 has reserved passage with the pouring of grouting liquid.Filling member 1222 is used to prevent closure Plug 121 is produced loosening by water and soil disturbance during piling.
Fig. 2 is referred to, work progress of the present utility model is as follows:
First, the perforate on the base plate on building basis 7, is buried a plurality of anchor poles 8, is matched somebody with somebody with anchor pole 8 using press device The pressure for producing is closed, pile pipe 1 is pressed in soil layer.After pile pipe 1 is depressed into predetermined depth, Grouting Pipe 4 is put into 1 bottom of pile pipe simultaneously Backfill rubble in 1 welded top cover plate 5 of pile pipe, and arranges exhaustor 6 on cover plate 5 to pile pipe 1.Pass through Grouting Pipe 4 again Concrete slurry is injected into pile pipe 1, when injection slurry is overflowed from exhaustor 6, close the valve of exhaustor 6, continue pressurization, treat Plug grouting behind shaft or drift lining is opened to grouting amount is designed, after the Grouting Pipe 4 and exhaustor 6 of cutting off cover plate more than 5, envelope stake is carried out.Above in association with accompanying drawing Embodiment has been described in detail to this utility model, and those skilled in the art can be new to this practicality according to the above description Type makes many variations example.Thus, some of embodiment details should not be constituted to restriction of the present utility model, this utility model By the scope defined using appended claims as protection domain of the present utility model.

Claims (10)

1. a kind of anchor jacked pile slip casting structure, an including pile pipe, it is characterised in that also including a Grouting Pipe, the pile pipe bottom The even tube wall in portion is distributed with multiple injected holes, and the Grouting Pipe is inserted in the pile pipe.
2. anchor jacked pile slip casting structure according to claim 1, it is characterised in that the Grouting Pipe extends the pile pipe Inside bottom.
3. anchor jacked pile slip casting structure according to claim 2, it is characterised in that also including a cover plate, the cover plate The peripheral top ferrule with the pile pipe is fixed, and the cover plate offers a Grouting Pipe installing hole and a steam vent, described Grouting Pipe is plugged and is fixed in the Grouting Pipe installing hole, and is sealed between the Grouting Pipe and the Grouting Pipe installing hole.
4. anchor jacked pile slip casting structure according to claim 3, it is characterised in that also including an exhaustor, the row Trachea is fixed on the steam vent and is coordinated with the vent hole seal, and exhaustor is provided with valve.
5. anchor jacked pile slip casting structure according to claim 4, it is characterised in that cement mortar is filled with the pile pipe Liquid fills out core with the compound of rubble formation.
6. the anchor jacked pile slip casting structure according to any one of Claims 1 to 5, it is characterised in that each slip casting Hole is provided with a plugging structure.
7. anchor jacked pile slip casting structure according to claim 6, it is characterised in that the plugging structure includes a closure Plug, the closure plug are inserted in the injected hole and are coordinated with injected hole sealing.
8. anchor jacked pile slip casting structure according to claim 7, it is characterised in that the closure plug is using flexible material Matter.
9. anchor jacked pile slip casting structure according to claim 8, it is characterised in that the plugging structure is also protected including Protecting assembly, the protection component are fixed on the pile pipe tube wall and cover at the closure beyond the Great Wall.
10. anchor jacked pile slip casting structure according to claim 9, it is characterised in that the protection component includes a cover Body and a filling member, the cover body are fixed on the pile pipe tube wall and cover at the closure beyond the Great Wall, the cover body and the stake Tube wall cooperatively forms an opening, and the filling member is filled in the cover body and covers the closure plug.
CN201621099018.2U 2016-09-30 2016-09-30 Anchor rod static pressure pile slip casting structure Active CN206090653U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621099018.2U CN206090653U (en) 2016-09-30 2016-09-30 Anchor rod static pressure pile slip casting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621099018.2U CN206090653U (en) 2016-09-30 2016-09-30 Anchor rod static pressure pile slip casting structure

Publications (1)

Publication Number Publication Date
CN206090653U true CN206090653U (en) 2017-04-12

Family

ID=58482222

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621099018.2U Active CN206090653U (en) 2016-09-30 2016-09-30 Anchor rod static pressure pile slip casting structure

Country Status (1)

Country Link
CN (1) CN206090653U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190742A (en) * 2017-07-18 2017-09-22 上海岩土工程勘察设计研究院有限公司 For grouting method outside slip casting structure outside the stake of steel-pipe pile and stake
CN109595020A (en) * 2018-12-30 2019-04-09 浙江工业大学 A kind of slip casting bellows enlarged footing anchor pole and application method for tunnel correction
CN110172920A (en) * 2019-06-03 2019-08-27 北京安禹建设有限公司 One kind is novel to pour stake benefit paste-making method and device
CN110805030A (en) * 2019-11-13 2020-02-18 上海长凯岩土工程有限公司 Anchor rod static pressure pile
CN110835924A (en) * 2018-08-16 2020-02-25 云南华坤装配式建筑有限公司 Thin-wall light steel structure steel pile grouting raft composite foundation technology
CN110835926A (en) * 2018-08-16 2020-02-25 云南华坤装配式建筑有限公司 Thin-wall light steel structure steel pile strip foundation composite foundation technology
CN111779045A (en) * 2020-06-15 2020-10-16 广州市城市规划勘测设计研究院 A kind of foundation reinforcement rectification method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190742A (en) * 2017-07-18 2017-09-22 上海岩土工程勘察设计研究院有限公司 For grouting method outside slip casting structure outside the stake of steel-pipe pile and stake
CN110835924A (en) * 2018-08-16 2020-02-25 云南华坤装配式建筑有限公司 Thin-wall light steel structure steel pile grouting raft composite foundation technology
CN110835926A (en) * 2018-08-16 2020-02-25 云南华坤装配式建筑有限公司 Thin-wall light steel structure steel pile strip foundation composite foundation technology
CN109595020A (en) * 2018-12-30 2019-04-09 浙江工业大学 A kind of slip casting bellows enlarged footing anchor pole and application method for tunnel correction
CN109595020B (en) * 2018-12-30 2023-09-29 浙江工业大学 Grouting bag type enlarged head anchor rod for tunnel deviation correction and use method
CN110172920A (en) * 2019-06-03 2019-08-27 北京安禹建设有限公司 One kind is novel to pour stake benefit paste-making method and device
CN110805030A (en) * 2019-11-13 2020-02-18 上海长凯岩土工程有限公司 Anchor rod static pressure pile
CN111779045A (en) * 2020-06-15 2020-10-16 广州市城市规划勘测设计研究院 A kind of foundation reinforcement rectification method
CN111779045B (en) * 2020-06-15 2022-04-01 广州市城市规划勘测设计研究院 Foundation reinforcement deviation rectifying method

Similar Documents

Publication Publication Date Title
CN206090653U (en) Anchor rod static pressure pile slip casting structure
CN106638669B (en) Existing subway station building enclosure hardened system and method are worn under a kind of shield
CN206090655U (en) Injected hole block structure
CN104234055B (en) A kind of prefabricated pile post-grouting device and technique thereof
CN202124865U (en) Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN104499479B (en) It is a kind of to pass through the dug pile construction method that sand gravel backfills layer
CN106223341B (en) Marine large diameter steel pipe pile slip casting around pile device and its construction method
CN101245886B (en) Processing method for deep building pit piping
CN102776899B (en) Anti-floating structure of shallow-buried shield tunnel
CN102162255A (en) Method for reinforcing existing pile foundation in collapsed loess area by slip casting
CN102839691B (en) Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN106522252A (en) Seepage-proofing blocking mechanism and method for deep foundation pit raft dewatering well
CN102852141A (en) Rock-socketed pipe pile foundation with pile core by concrete pouring and pile side by static pressure grouting and construction method for rock-socketed pipe pile foundation
CN102953372A (en) Steel pipe pile and construction method thereof
CN106894428A (en) Multi-channel waterproof plugging method for dewatering well of thick and large raft foundation
CN105625420B (en) A kind of extension type support with manually dug piles construction and its construction method
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN119332672A (en) A high-bearing-capacity anchor static pressure steel pipe pile and grouting method thereof
CN101586341B (en) Water sealing method for civil engineering groundwork
CN206385557U (en) The water-impervious plugging mechanism of dewatering well on deep basal pit raft plate
CN108277813B (en) Hollow anti-slide pile with drainage structure and construction method thereof
CN103669333B (en) It is easy to the friction pile of vacuum-dewatering
CN208023598U (en) A kind of base pit dewatering pipe well
CN215669620U (en) Plugging structure of dewatering well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 202150 Xiushan Road 258, Chongming Industrial Park, Chongming County, Shanghai

Patentee after: Shanghai Survey, Design and Research Institute (Group) Co.,Ltd.

Country or region after: China

Address before: 202150 Xiushan Road 258, Chongming Industrial Park, Chongming County, Shanghai

Patentee before: SHANGHAI GEOTECHNICAL INVESTIGATIONS & DESIGN INSTITUTE Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address