CN205838391U - Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool - Google Patents

Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool Download PDF

Info

Publication number
CN205838391U
CN205838391U CN201620549492.4U CN201620549492U CN205838391U CN 205838391 U CN205838391 U CN 205838391U CN 201620549492 U CN201620549492 U CN 201620549492U CN 205838391 U CN205838391 U CN 205838391U
Authority
CN
China
Prior art keywords
fixed
fixed pulley
rope
winding
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620549492.4U
Other languages
Chinese (zh)
Inventor
肖辉
张金岗
林俊年
韩玉涛
田晖
吕婷婷
孟庆承
段立果
冀君
张世竞
孔祥国
胡彦泉
张文佳
郭雷
李颖慧
惠杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Maintenance Branch of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Maintenance Branch of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Maintenance Branch of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201620549492.4U priority Critical patent/CN205838391U/en
Application granted granted Critical
Publication of CN205838391U publication Critical patent/CN205838391U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool, including crane, oscillating bearing and the second fixed pulley are installed in the arm end of crane, the outer ring of oscillating bearing is connected with the arm of crane, the inner ring of oscillating bearing connects the first fixed pulley, and the first fixed pulley is installed stay cord, and the first fixed pulley is walked around at the middle part of stay cord, of the present utility model the hoisting mechanism of winding is separated with stabilizing mechanism, make winding can more stablize in hoisting process.This utility model optimizes the structure of traction apparatus, makes winding lifting convenient.Oscillating bearing of the present utility model can make what the first fixed pulley adapted to stay cord automatically to pull angle, it is to avoid the excessive stay cord caused of the angle of stay cord and the first fixed pulley separate.

Description

变压器套管吊装穿缆引线牵引调整专用工具Special tool for traction adjustment of transformer bushing hoisting and threading lead wire

技术领域technical field

本实用新型涉及一种穿缆引线牵引调整专用工具,具体地说是一种变压器套管吊装穿缆引线牵引调整专用工具。The utility model relates to a special tool for traction adjustment of cable threading lead wires, in particular to a special tool for traction adjustment of cable threading lead wires for hoisting transformer bushings.

背景技术Background technique

变压器套管如果发生故障,需要将其拆卸进行检修或更换。变压器套管是一种昂贵、精细的设备,吊装过程中如果出现套管设备损坏,不仅会造成巨大经济损失,而且会耽误工作进程,导致设备无法按时送电,进而影响电网的安全可靠运行。油纸电容穿缆式套管是变压器的重要的组件之一,它包括油纸电容式套管、干式套管等。油纸电容式套管主要用于电力变压器、换流变压器和高压油浸电抗器,不仅担负着将变压器内部的高、低压绕组通过引线接到油箱外部的出线装置,实现变压器与外部网络连接,同时还起着固定引线的作用。按照绕组引出方式又分为拆卸式(复合式)、穿缆式引出方式。If the transformer bushing fails, it needs to be disassembled for repair or replacement. Transformer bushing is a kind of expensive and delicate equipment. If the bushing equipment is damaged during hoisting, it will not only cause huge economic losses, but also delay the work process, resulting in the failure of the equipment to transmit power on time, which will affect the safe and reliable operation of the power grid. Oil-paper capacitor bushing is one of the important components of the transformer, which includes oil-paper capacitor bushing, dry bushing, etc. Oil-paper capacitive bushings are mainly used in power transformers, converter transformers and high-voltage oil-immersed reactors. They are not only responsible for connecting the high-voltage and low-voltage windings inside the transformer to the outlet device outside the oil tank through leads, so as to realize the connection between the transformer and the external network. It also acts as a fixed lead. According to the winding lead-out method, it is divided into disassembly type (composite type) and cable-through lead-out method.

近年来,运行中的套管事故次数逐年增加。故障主要表现型式有:结构或制造工艺不良、安装工艺不良等造成套管接头过热:瓷套外绝缘在恶劣自然缓解下发生雨中闪络或发生污闪:长期运行中避风垫圈老化裂纹,发生漏油、渗水,使电气绝缘性能下降,甚至发生套管爆炸,造成电力变压器停运事故,危急电力系统安全运行。因此,当发现套管出现隐患,影响安全运行时应及时更换。In recent years, the number of casing accidents in operation has increased year by year. The main manifestations of faults are: poor structure or manufacturing process, poor installation process, etc., causing overheating of casing joints; flashover in rain or pollution flashover of the outer insulation of porcelain sleeve under harsh natural relief; aging cracks of windshield gaskets during long-term operation, and leakage Oil and water seepage will reduce the electrical insulation performance, and even the bushing will explode, causing the power transformer to be out of service and endangering the safe operation of the power system. Therefore, when a hidden danger is found in the bushing, which affects safe operation, it should be replaced in time.

因为变压器套管重量大,瓷件容易损坏,在空中吊装时角度难以调整,套管吊装过程中晃动不稳等问题,所以变压器套管吊装是一项十分困难的工作。油纸电容穿缆式套管在套管更换过程中,既要保证快速高效更换套管,又要确保绕组穿缆引线不出现额外受力而出现缠绕断裂,引线缠绕的绝缘纸因套管吊装过程中易出现绝缘纸破损影响绝缘。套管内壁电容芯子高压电缆纸和导电铝箔也会因与绕组引线的抽动摩擦而会出现磨损划痕,降低绝缘性能影响主绝缘。因此在吊装套管过程中做到对绕组引线的保护是十分有必要的。Because the transformer bushing is heavy, the ceramic parts are easily damaged, the angle is difficult to adjust when hoisting in the air, and the bushing is shaken and unstable during hoisting, so the hoisting of the transformer bushing is a very difficult task. In the process of replacing the oil-paper capacitor cable-piercing bushing, it is necessary to ensure fast and efficient replacement of the bushing, and to ensure that the winding cable lead wire does not appear to be wound and broken due to additional force. Insulation paper is prone to breakage and affects insulation. The high-voltage cable paper and conductive aluminum foil of the capacitor core on the inner wall of the bushing will also be worn and scratched due to twitch friction with the winding lead, which will reduce the insulation performance and affect the main insulation. Therefore, it is very necessary to protect the winding leads in the process of hoisting the casing.

实用新型内容Utility model content

本实用新型的目的是提供一种变压器套管吊装穿缆引线牵引调整专用工具,能够解决上述问题。The purpose of the utility model is to provide a transformer bushing hoisting and threading lead wire traction adjustment special tool, which can solve the above problems.

本实用新型为实现上述目的,通过以下技术方案实现:一种变压器套管吊装穿缆引线牵引调整专用工具,包括吊车,吊车的吊臂端部安装关节轴承和第二定滑轮,关节轴承的外圈与吊车的吊臂连接,关节轴承的内圈连接第一定滑轮,第一定滑轮上安装拉绳,拉绳的中部绕过第一定滑轮,拉绳的一端连接连接杆,连接杆的下端连接绕组引出线,绕组引出线的下端连接绕组,第二定滑轮上安装固定绳,固定绳的中部绕过第二定滑轮,固定绳的两端连接挂钩,挂钩上安装挂绳,挂绳的中部与挂钩配合,挂绳的两端连接固定座,固定座为环形结构,固定座的下部安装固定管,固定座和固定管配合套在固定杆上,固定管的内径大于固定杆的直径,固定管的下部安装两个或两个以上固定杆,固定杆的下端连接固定环,固定环的侧部与固定杆连接,固定环的侧部套在绕组引出线上,固定杆的侧部安装摄像头。In order to achieve the above object, the utility model is realized through the following technical proposals: a special tool for lifting transformer bushings, threading cables, and leading wires for traction adjustment, including a crane, a joint bearing and a second fixed pulley installed on the end of the boom of the crane, and an outer joint bearing. The ring is connected to the boom of the crane, the inner ring of the joint bearing is connected to the first fixed pulley, and a pull rope is installed on the first fixed pulley, the middle part of the pull rope bypasses the first fixed pulley, and one end of the pull rope is connected to the connecting rod, and the connecting rod The lower end is connected to the winding lead-out wire, and the lower end of the winding lead-out wire is connected to the winding. A fixed rope is installed on the second fixed pulley. The middle part of the fixed rope bypasses the second fixed pulley. The middle part of the lanyard is matched with the hook, the two ends of the lanyard are connected to the fixed seat, the fixed seat is a ring structure, the lower part of the fixed seat is equipped with a fixed tube, the fixed seat and the fixed tube are fitted on the fixed rod, and the inner diameter of the fixed tube is larger than the diameter of the fixed rod , the lower part of the fixed pipe is installed with two or more fixed rods, the lower end of the fixed rod is connected with the fixed ring, the side of the fixed ring is connected with the fixed rod, the side of the fixed ring is set on the winding lead-out line, the side of the fixed rod Install the camera.

为了进一步实现本实用新型的目的,还可以采用以下技术方案:所述挂钩上部安装挂钩座,挂钩座与固定绳配合。所述吊车上安装步进电机,步进电机的输出轴安装辊轮,辊轮与拉绳配合。In order to further realize the purpose of the utility model, the following technical solutions can also be adopted: a hook seat is installed on the upper part of the hook, and the hook seat cooperates with the fixed rope. A stepping motor is installed on the crane, and rollers are installed on the output shaft of the stepping motor, and the rollers cooperate with the stay rope.

本实用新型的优点在于:本实用新型的将绕组的吊装机构与稳定机构分离,使绕组在吊装过程中可以更加稳定。本实用新型优化了牵引装置的结构,使绕组吊装更加方便。本实用新型的关节轴承可以使第一定滑轮自动适应拉绳的拉动角度,避免拉绳的角度过大导致的拉绳与第一定滑轮分离。本实用新型的固定绳与第二定滑轮配合可以方便挂钩在出现摆动时保持与挂绳的牢固连接。本实用新型的固定座和固定管配合可以对固定座起到导向作用。本实用新型的固定环既可以对绕组引出线起到导向作用,又可以不占用过大的空间,使绕组吊装更加稳定。本实用新型的摄像头可以方便操作人员对吊装过程实时监测。本实用新型还具有结构简洁紧凑、制造成本低廉和使用简便的优点。The utility model has the advantages that: the utility model separates the hoisting mechanism of the winding from the stabilizing mechanism, so that the winding can be more stable during the hoisting process. The utility model optimizes the structure of the traction device and makes the hoisting of the winding more convenient. The joint bearing of the utility model can make the first fixed pulley automatically adapt to the pulling angle of the pull rope, and avoid separation of the pull rope from the first fixed pulley caused by the excessive angle of the pull rope. The combination of the fixed rope and the second fixed pulley of the utility model can facilitate the hook to maintain a firm connection with the hanging rope when swinging occurs. The cooperation between the fixing seat and the fixing pipe of the utility model can guide the fixing seat. The fixing ring of the utility model can not only play a guiding role for the lead-out wires of the winding, but also not occupy too much space, so that the hoisting of the winding is more stable. The camera of the utility model can facilitate the real-time monitoring of the hoisting process by operators. The utility model also has the advantages of simple and compact structure, low manufacturing cost and easy use.

附图说明Description of drawings

图1为本实用新型的结构示意图;图2为图1的Ⅰ部放大结构示意图。Fig. 1 is a structural schematic diagram of the utility model; Fig. 2 is a schematic structural diagram of the enlarged structure of part I of Fig. 1 .

标注说明:1关节轴承 2第一定滑轮 3拉绳 4第二定滑轮 5固定绳 6挂钩座 7挂钩 8挂绳 9连接杆 10固定座 11固定管 12固定杆 13固定环 14绕组引出线 15绕组 16吊车 17辊轮 18步进电机 19摄像头。Note: 1 joint bearing 2 first fixed pulley 3 pull rope 4 second fixed pulley 5 fixed rope 6 hook seat 7 hook 8 lanyard 9 connecting rod 10 fixing seat 11 fixing tube 12 fixing rod 13 fixing ring 14 winding lead wire 15 Winding 16 Crane 17 Roller 18 Stepping motor 19 Camera.

具体实施方式detailed description

变压器套管吊装穿缆引线牵引调整专用工具,如图1和图2所示,包括吊车16,吊车16的吊臂端部安装关节轴承1和第二定滑轮4,关节轴承1的外圈与吊车16的吊臂连接,关节轴承1的内圈连接第一定滑轮2,第一定滑轮2上安装拉绳3,拉绳3的中部绕过第一定滑轮2,拉绳3的一端连接连接杆9,连接杆9的下端连接绕组引出线14,绕组引出线14的下端连接绕组15,第二定滑轮4上安装固定绳5,固定绳5的中部绕过第二定滑轮4,固定绳5的两端连接挂钩7,挂钩7上安装挂绳8,挂绳8的中部与挂钩7配合,挂绳8的两端连接固定座10,固定座10为环形结构,固定座10的下部安装固定管11,固定座10和固定管11配合套在固定杆12上,固定管11的内径大于固定杆12的直径,固定管11的下部安装两个或两个以上固定杆12,固定杆12的下端连接固定环13,固定环13的侧部与固定杆12连接,固定环13的侧部套在绕组引出线14上,固定杆12的侧部安装摄像头19。The special tool for hoisting the transformer bushing, passing the cable, and leading the traction adjustment, as shown in Figure 1 and Figure 2, includes a crane 16, the end of the boom of the crane 16 is equipped with a joint bearing 1 and a second fixed pulley 4, and the outer ring of the joint bearing 1 and The boom of the crane 16 is connected, the inner ring of the joint bearing 1 is connected to the first fixed pulley 2, the first fixed pulley 2 is equipped with a stay rope 3, the middle part of the stay rope 3 bypasses the first fixed pulley 2, and one end of the stay rope 3 is connected to Connecting rod 9, the lower end of connecting rod 9 is connected to winding lead-out wire 14, the lower end of winding lead-out wire 14 is connected to winding 15, fixed rope 5 is installed on the second fixed pulley 4, the middle part of fixed rope 5 bypasses second fixed pulley 4, fixed The two ends of rope 5 connect hook 7, and hanging rope 8 is installed on the hook 7, and the middle part of hanging rope 8 cooperates with hook 7, and the two ends of hanging rope 8 connect fixing seat 10, and fixing seat 10 is ring structure, and the bottom of fixing seat 10 Install the fixed pipe 11, the fixed seat 10 and the fixed pipe 11 are fitted on the fixed rod 12, the inner diameter of the fixed pipe 11 is greater than the diameter of the fixed rod 12, two or more than two fixed rods 12 are installed on the bottom of the fixed pipe 11, the fixed rod The lower end of 12 is connected with fixed ring 13, and the side of fixed ring 13 is connected with fixed bar 12, and the side of fixed ring 13 is enclosed within on the winding lead-out line 14, and camera 19 is installed at the side of fixed bar 12.

本实用新型的将绕组15的吊装机构与稳定机构分离,使绕组15在吊装过程中可以更加稳定。本实用新型优化了牵引装置的结构,使绕组吊装更加方便。本实用新型的关节轴承1可以使第一定滑轮2自动适应拉绳3的拉动角度,避免拉绳3的角度过大导致的拉绳3与第一定滑轮2分离。本实用新型的固定绳5与第二定滑轮4配合可以方便挂钩7在出现摆动时保持与挂绳8的牢固连接。本实用新型的固定座10和固定管11配合可以对固定座10起到导向作用。本实用新型的固定环13既可以对绕组引出线14起到导向作用,又可以不占用过大的空间,使绕组15吊装更加稳定。本实用新型的摄像头19可以方便操作人员对吊装过程实时监测。The utility model separates the hoisting mechanism of the winding 15 from the stabilizing mechanism, so that the winding 15 can be more stable during the hoisting process. The utility model optimizes the structure of the traction device and makes the hoisting of the winding more convenient. The joint bearing 1 of the utility model can make the first fixed pulley 2 automatically adapt to the pulling angle of the stay rope 3, avoiding the separation of the stay rope 3 and the first fixed pulley 2 caused by the excessive angle of the stay rope 3. The cooperation between the fixed rope 5 and the second fixed pulley 4 of the present invention can facilitate the hook 7 to maintain a firm connection with the hanging rope 8 when swinging occurs. The cooperation between the fixing seat 10 and the fixing pipe 11 of the present utility model can guide the fixing seat 10 . The fixing ring 13 of the utility model can not only guide the winding lead wire 14, but also not occupy too much space, so that the hoisting of the winding 15 is more stable. The camera 19 of the utility model can facilitate the real-time monitoring of the hoisting process by the operator.

避免了变压器套管吊装时穿缆引线直接受力,实现了变压器吊装过程中对套管电容内壁的保护,实现了变压器套管吊装过程套管内部监控,随时调整吊装角度。避免穿缆引线因操作不当掉入变压器内部。It avoids the direct force of the cable lead wire when the transformer bushing is hoisted, realizes the protection of the inner wall of the bushing capacitor during the transformer hoisting process, realizes the inner monitoring of the bushing during the hoisting process of the transformer bushing, and adjusts the hoisting angle at any time. Avoid the cable lead wire falling into the inside of the transformer due to improper operation.

变压器穿缆由变压器绕组抽头引出一根电缆引线穿过套管电容内壁,作为一次导流线从套管穿出与变电站内一次线连接。在更换套管过程中如果穿缆引线受力过大,会造成穿缆引线铜丝缠绕断裂,变压器内部绕组的损坏,甚至穿缆引线与绕组断裂脱离,造成整个变压器的损坏。Transformer cable threading is a cable lead drawn from the transformer winding tap, which passes through the inner wall of the bushing capacitor, and passes through the bushing as a primary guide line to connect with the primary line in the substation. In the process of replacing the bushing, if the force on the cable lead wire is too large, the copper wire of the cable lead wire will be wound and broken, the internal winding of the transformer will be damaged, and even the cable lead wire will be broken and separated from the winding, resulting in damage to the entire transformer.

变压器电容式套管是以电容分压原理卷至而成,电容芯子作为主绝缘,它的外部是瓷绝缘,中间注入合格变压器油。变压器绕组穿缆由套管内部电容外壁穿出。设计可调节定滑轮调节器,可以调节吊装套管时的电缆角度,避免电容芯子高压电缆纸和导电铝箔也会因与绕组引线的抽动摩擦而会出现磨损划痕影响主绝缘。Transformer capacitive bushings are coiled based on the principle of capacitive voltage division. The capacitor core is used as the main insulation. Its exterior is porcelain insulated, and qualified transformer oil is injected into the middle. The transformer winding cable passes through the outer wall of the capacitor inside the bushing. The adjustable fixed pulley adjuster is designed to adjust the cable angle when hoisting the bushing, so as to prevent the high-voltage cable paper and conductive aluminum foil of the capacitor core from being worn and scratched due to the twitch friction with the winding lead wire and affecting the main insulation.

借助我们设计的变压器油纸电容式套管吊装穿缆引线固定调整专用工具专业连接头上方固定一个小型针孔式摄像头,可观察套管内部的磨损划痕及穿缆是否有打搅缠绕和绝缘纸磨损现象,及时调整吊装角度,避免引线受力损坏和套管内部电容绝缘层。With the help of our designed transformer oil-paper capacitive bushing hoisting, cable lead fixing and adjustment special tool, a small pinhole camera is fixed on the top of the professional connector to observe the wear and tear inside the bushing and whether there is any disturbance, winding and insulation paper wear on the cable. Phenomenon, adjust the lifting angle in time to avoid stress damage to the lead wire and the capacitor insulation layer inside the bushing.

根据穿缆引线连接头结构,巧妙设计专用连接头与穿缆引线连接头通过螺栓插接固定,将整个吊装过程对穿缆引线控制在现场操作人员手中,避免吊装过程中穿缆引线滑落到变压器本体内。According to the structure of the cable lead wire connector, the special connector and the cable lead wire connector are ingeniously designed and fixed by bolt insertion, so that the cable lead wire is controlled in the hands of the on-site operator during the entire hoisting process, and the cable lead wire is prevented from slipping into the transformer during the hoisting process In the ontology.

设计一个专用连接头与变压器套管穿缆引线接头通过螺栓嵌入式相固定确保不会脱开,吊车吊装套管时,确保穿缆引线不会因受到额外的应力使引线扭曲、变形、磨损。专用连接头用防滑耐磨阻燃绳固定连接。防滑耐磨阻燃绳另一头设计一个定滑轮,防滑耐磨阻燃绳缠绕在定滑轮上负责套管穿缆引线牵引调整角度确保不受外力作用。定滑轮与吊车连接方式采用可万向调节方向的万向轴与吊车固定在吊臂前沿,便于操作和调整角度。专业连接头上方固定一个小型针孔式摄像头,观察套管内部的磨损划痕及穿缆是否有打搅缠绕和绝缘纸磨损现象。A special connector is designed to be fixed with the cable lead joint of the transformer bushing through the embedded bolt to ensure that it will not be disengaged. When the bushing is hoisted by a crane, it is ensured that the lead wire will not be twisted, deformed or worn due to additional stress. The special connector is fixedly connected with a non-slip, wear-resistant and flame-retardant rope. The other end of the non-slip, wear-resistant and flame-retardant rope is designed with a fixed pulley, and the non-slip, wear-resistant and flame-retardant rope is wound on the fixed pulley, which is responsible for casing threading, cable lead traction, and adjustment angle to ensure that it is not affected by external forces. The connection between the fixed pulley and the crane adopts the cardan shaft that can adjust the direction in all directions and the crane is fixed on the front edge of the boom, which is convenient for operation and angle adjustment. A small pinhole camera is fixed above the professional connector to observe the wear and scratches inside the casing and whether there is any disturbance, winding and abrasion of insulating paper in the cable.

所述挂钩7上部安装挂钩座6,挂钩座6与固定绳5配合。本实用新型的挂钩座6可以使挂钩7更加稳定。The hook seat 6 is installed on the top of the hook 7, and the hook seat 6 cooperates with the fixed rope 5. The hook seat 6 of the utility model can make the hook 7 more stable.

所述吊车16上安装步进电机18,步进电机18的输出轴安装辊轮17,辊轮17与拉绳3配合。本实用新型的步进电机18可以更加精确地控制牵引距离,提高绕组15吊装的精确性。Stepping motor 18 is installed on the described crane 16, and the output shaft of stepping motor 18 is installed roller 17, and roller 17 cooperates with stay cord 3. The stepping motor 18 of the utility model can control the traction distance more accurately, and improve the accuracy of hoisting of the winding 15 .

本实用新型的技术方案并不限制于本实用新型所述的实施例的范围内。本实用新型未详尽描述的技术内容均为公知技术。The technical solution of the utility model is not limited within the scope of the embodiments described in the utility model. The technical contents not described in detail in the utility model are all known technologies.

Claims (3)

1.变压器套管吊装穿缆引线牵引调整专用工具,其特征在于:包括吊车(16),吊车(16)的吊臂端部安装关节轴承(1)和第二定滑轮(4),关节轴承(1)的外圈与吊车(16)的吊臂连接,关节轴承(1)的内圈连接第一定滑轮(2),第一定滑轮(2)上安装拉绳(3),拉绳(3)的中部绕过第一定滑轮(2),拉绳(3)的一端连接连接杆(9),连接杆(9)的下端连接绕组引出线(14),绕组引出线(14)的下端连接绕组(15),第二定滑轮(4)上安装固定绳(5),固定绳(5)的中部绕过第二定滑轮(4),固定绳(5)的两端连接挂钩(7),挂钩(7)上安装挂绳(8),挂绳(8)的中部与挂钩(7)配合,挂绳(8)的两端连接固定座(10),固定座(10)为环形结构,固定座(10)的下部安装固定管(11),固定座(10)和固定管(11)配合套在固定杆(12)上,固定管(11)的内径大于固定杆(12)的直径,固定管(11)的下部安装两个或两个以上固定杆(12),固定杆(12)的下端连接固定环(13),固定环(13)的侧部与固定杆(12)连接,固定环(13)的侧部套在绕组引出线(14)上,固定杆(12)的侧部安装摄像头(19)。1. The special tool for traction adjustment of transformer bushing hoisting, threading and leading wires, characterized in that it includes a crane (16), and the joint bearing (1) and the second fixed pulley (4) are installed on the end of the boom of the crane (16), and the joint bearing The outer ring of (1) is connected with the boom of crane (16), and the inner ring of joint bearing (1) is connected with the first fixed pulley (2), and stay rope (3) is installed on the first fixed pulley (2). The middle part of (3) bypasses the first fixed pulley (2), one end of the stay rope (3) is connected to the connecting rod (9), the lower end of the connecting rod (9) is connected to the winding lead-out wire (14), and the winding lead-out wire (14) The lower end of the lower end is connected to the winding (15), the second fixed pulley (4) is equipped with a fixed rope (5), the middle part of the fixed rope (5) walks around the second fixed pulley (4), and the two ends of the fixed rope (5) are connected to the hook (7), hanging rope (8) is installed on the hook (7), the middle part of the hanging rope (8) cooperates with the hook (7), and the two ends of the hanging rope (8) are connected to the fixed seat (10), and the fixed seat (10) It is a ring structure, the bottom of the fixed seat (10) is equipped with a fixed pipe (11), and the fixed seat (10) and the fixed pipe (11) are fitted on the fixed rod (12), and the inner diameter of the fixed pipe (11) is larger than the fixed rod ( 12), the bottom of the fixed tube (11) is equipped with two or more fixed rods (12), the lower end of the fixed rods (12) is connected to the fixed ring (13), and the side of the fixed ring (13) is connected to the fixed rod (12) connection, the side portion of the fixed ring (13) is enclosed within on the winding lead-out wire (14), and the side portion of the fixed rod (12) is equipped with a camera (19). 2.根据权利要求1所述的变压器套管吊装穿缆引线牵引调整专用工具,其特征在于:所述挂钩(7)上部安装挂钩座(6),挂钩座(6)与固定绳(5)配合。2. The special tool for traction adjustment of transformer bushing lifting, threading and lead wires according to claim 1, characterized in that: the upper part of the hook (7) is equipped with a hook seat (6), and the hook seat (6) is connected with the fixed rope (5) Cooperate. 3.根据权利要求1所述的变压器套管吊装穿缆引线牵引调整专用工具,其特征在于:所述吊车(16)上安装步进电机(18),步进电机(18)的输出轴安装辊轮(17),辊轮(17)与拉绳(3)配合。3. The special tool for traction adjustment of transformer bushing hoisting, threading, and lead wires according to claim 1, characterized in that: a stepping motor (18) is installed on the crane (16), and the output shaft of the stepping motor (18) is installed Roller (17), roller (17) cooperates with stay cord (3).
CN201620549492.4U 2016-06-08 2016-06-08 Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool Expired - Fee Related CN205838391U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620549492.4U CN205838391U (en) 2016-06-08 2016-06-08 Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620549492.4U CN205838391U (en) 2016-06-08 2016-06-08 Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool

Publications (1)

Publication Number Publication Date
CN205838391U true CN205838391U (en) 2016-12-28

Family

ID=57623555

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620549492.4U Expired - Fee Related CN205838391U (en) 2016-06-08 2016-06-08 Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool

Country Status (1)

Country Link
CN (1) CN205838391U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107086474A (en) * 2017-06-26 2017-08-22 国网河南省电力公司濮阳供电公司 A meter box installation assist device
CN107720567A (en) * 2017-08-22 2018-02-23 国家电网公司 Cable lead traction adjustment specific purpose tool is worn in bushing shell for transformer lifting
CN113772573A (en) * 2020-12-28 2021-12-10 国网山东省电力公司莱西市供电公司 Pulley structure for avoiding rope winding
CN115353014A (en) * 2022-09-05 2022-11-18 深圳供电局有限公司 Method for hoisting power grid transformer bushing

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107086474A (en) * 2017-06-26 2017-08-22 国网河南省电力公司濮阳供电公司 A meter box installation assist device
CN107086474B (en) * 2017-06-26 2022-08-02 国网河南省电力公司濮阳供电公司 Meter box installation power assisting device
CN107720567A (en) * 2017-08-22 2018-02-23 国家电网公司 Cable lead traction adjustment specific purpose tool is worn in bushing shell for transformer lifting
CN113772573A (en) * 2020-12-28 2021-12-10 国网山东省电力公司莱西市供电公司 Pulley structure for avoiding rope winding
CN115353014A (en) * 2022-09-05 2022-11-18 深圳供电局有限公司 Method for hoisting power grid transformer bushing

Similar Documents

Publication Publication Date Title
CN205838391U (en) Bushing shell for transformer lifting is worn cable lead-in wire traction and is adjusted specific purpose tool
CN104466815A (en) Installing tool for bare conductor insulated protection sleeve
CN204441087U (en) Transformer high-voltage bushing lead-in wire mounting bracket
CN107720567A (en) Cable lead traction adjustment specific purpose tool is worn in bushing shell for transformer lifting
CN101026291A (en) Foldable synthetic insulator special ladder
CN104444766B (en) Electric power transformer insulated sleeve hoisting device
CN201868790U (en) Insulating gap bridge for repairing power lines
CN204391657U (en) A kind of transmission line insulator sheath
CN102412532A (en) Overhead line pulley device
CN102881440A (en) Transformer bushing outgoing line installation frame
CN207339089U (en) Line fixing device more than bypass cable
CN207194592U (en) A kind of adjustable for height tower bar of cross-arm
CN201234089Y (en) Protective interval for live operation on 1000kV AC very high voltage line
CN204258181U (en) A kind of plain conductor insulating sleeve erecting tools
CN202905452U (en) Transformer bushing coil out installation rack
CN103594988B (en) 500kV transformer substation tubular busbar deflection correction method
CN207150030U (en) Fixture for the only cross-arm shaft tower replacing insulator under electrified of 110kV straight lines
CN206878620U (en) A kind of motor down-lead of ceiling fan is plugged into attachment structure
CN205542375U (en) Device for connecting be used for transformer bushing when installation lead -out wire and carry instrument that draws
CN218507508U (en) Folding arm type wire lifting device
CN106992464B (en) A tension-resistant drainage lap ladder
CN206417780U (en) A kind of pre-branched cable derricking gear
CN105301295B (en) House cable inlet wire Transformer Winding short-circuit device
CN110844716A (en) Device convenient and fast to install cable
CN205419563U (en) A lift by crane translation device that condenser was changed on was used for pylon

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161228

Termination date: 20170608