[go: up one dir, main page]

CN205576990U - Cross section and wear bridge pier tunnel slip casting supporting construction - Google Patents

Cross section and wear bridge pier tunnel slip casting supporting construction Download PDF

Info

Publication number
CN205576990U
CN205576990U CN201620071681.5U CN201620071681U CN205576990U CN 205576990 U CN205576990 U CN 205576990U CN 201620071681 U CN201620071681 U CN 201620071681U CN 205576990 U CN205576990 U CN 205576990U
Authority
CN
China
Prior art keywords
underpinning
pile foundation
tunnel
layer
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620071681.5U
Other languages
Chinese (zh)
Inventor
郑世杰
张涛
郭树勋
姜谙男
武洪海
谭振
孙敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Maritime University
CCCC Tunnel Engineering Co Ltd
Original Assignee
Dalian Maritime University
CCCC Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Maritime University, CCCC Tunnel Engineering Co Ltd filed Critical Dalian Maritime University
Priority to CN201620071681.5U priority Critical patent/CN205576990U/en
Application granted granted Critical
Publication of CN205576990U publication Critical patent/CN205576990U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本实用新型公开了一种过河段穿桥桩隧道注浆支护结构,其包括:连接原有待施工浅埋暗挖隧道上方地质层的各个桩基结构的托换梁,其用于承载所述桩基结构承载的载荷;若干连接并支撑所述托换梁的托换柱,其用于承载所述托换梁承载的载荷;以及设置于待施工浅埋暗挖隧道的拱顶层的深孔注浆加固层。本实用新型通过托换梁将被托换桩基结构的荷载转移到托换梁上,再通过托梁传递到托换柱上,以实现不降低原有桩基结构上部结构承载力和整体刚度的前提下进行施工;同时加设深孔注浆加固层进一步提高桩基的承载能力;本实用新型具有节省空间、造价低、施工周期短、不影响上部交通、安全可靠、减少环境污染等优点。

The utility model discloses a grouting support structure for a bridge-crossing pile tunnel at a river crossing section, which comprises: an underpinning beam connecting each pile foundation structure above the geological layer of the shallow-buried underground excavation tunnel to be constructed, which is used to carry the The load carried by the pile foundation structure; several underpinning columns connected and supporting the underpinning beam, which are used to bear the load carried by the underpinning beam; Hole grouting reinforcement layer. The utility model transfers the load of the underpinned pile foundation structure to the underpinning beam through the underpinning beam, and then transfers it to the underpinning column through the underpinning beam, so as not to reduce the bearing capacity and overall rigidity of the upper structure of the original pile foundation structure Construction is carried out under the premise; at the same time, a deep hole grouting reinforcement layer is added to further improve the bearing capacity of the pile foundation; the utility model has the advantages of saving space, low cost, short construction period, not affecting the upper traffic, safe and reliable, and reducing environmental pollution. .

Description

一种过河段穿桥桩隧道注浆支护结构A grouting support structure for crossing bridge pile tunnels

技术领域technical field

本实用新型涉及隧道设计与施工技术,具体的说是涉及一种浅埋暗挖隧道用支护结构,特别是过河段穿桥桩隧道注浆支护结构。The utility model relates to tunnel design and construction technology, in particular to a support structure for shallow buried tunnels, in particular to a grouting support structure for tunnels crossing bridge piles.

背景技术Background technique

在我国城市向大型化和现代化方向发展时,大量高层建筑、地下隧道修建于人口高度集中的城市,因此对于交通、商业及其人民生活设施的修建提出了更高的要求。在修建地下铁道、商场和其他许多地下他设施中,往往要穿越部分高层建筑、桥梁结构或重要历史建筑物,这就需要对原有建(构)筑物的基础进行托换或加固处理;加之建(构)筑所需托换的数量繁多,原有建(构)筑物需进行改建、加层或加大使用荷载时,也同样需要采用托换技术;如在城市复杂环境中,若直接采用浅埋地铁隧道微爆开挖则会直接对隧道上方的桥桩产生扰动,进而对桥结构产生破坏以及对城市交通车辆日常通行产生很大影响。When cities in our country are developing towards large-scale and modernization, a large number of high-rise buildings and underground tunnels are built in cities with a high concentration of population, so higher requirements are put forward for the construction of transportation, commerce and people's living facilities. In the construction of underground railways, shopping malls and many other underground facilities, it is often necessary to pass through some high-rise buildings, bridge structures or important historical buildings, which requires underpinning or reinforcement of the foundations of the original buildings (structures); The number of underpinnings required for construction (structure) is large, and when the original buildings (structures) need to be rebuilt, added floors or increased loads, underpinning technology also needs to be used; for example, in a complex urban environment, if Direct micro-explosion excavation of shallow subway tunnels will directly disturb the bridge piles above the tunnel, which will damage the bridge structure and have a great impact on the daily traffic of urban traffic vehicles.

因此如何实现在不更改隧道线路、不拆除上部桥梁结构以及不出现重大安全事故的情况下,有效解决浅埋隧道暗挖施工引起地层移动和地表下沉的问题,进而防止地表及周边既有建筑物发生过量变形与破坏则是当前隧道设计与施工技术的重要研究课题。Therefore, how to effectively solve the problems of stratum movement and surface subsidence caused by the excavation construction of shallow tunnels without changing the tunnel line, without demolishing the upper bridge structure, and without major safety accidents, so as to prevent the existing buildings on the surface and surrounding Excessive deformation and destruction of objects is an important research topic in current tunnel design and construction technology.

发明内容Contents of the invention

鉴于已有技术存在的缺陷,本实用新型的目的是要提供一种过河段穿桥桩隧道注浆支护结构,该支护结构特别适用于隧道过河段穿桥桩隧道,其具有使原有桩基整体受力,减小了隧道上部桩基的荷载,进而减小局部应力集中,使浅埋暗挖隧道可以安全通过桥梁段,且能够提高地基土的强度、消除湿陷性及防渗堵漏等。In view of the defects existing in the prior art, the purpose of this utility model is to provide a kind of grouting support structure for crossing the bridge pile tunnel, which is especially suitable for the crossing pile tunnel of the river crossing section of the tunnel. The overall force of the original pile foundation reduces the load of the pile foundation on the upper part of the tunnel, thereby reducing the local stress concentration, so that the shallow buried tunnel can safely pass through the bridge section, and can improve the strength of the foundation soil, eliminate collapsibility and Anti-seepage and plugging, etc.

为了实现上述目的,本实用新型的技术方案:In order to achieve the above object, the technical scheme of the utility model:

一种过河段穿桥桩隧道注浆支护结构,其特征在于:A grouting support structure for crossing bridge pile tunnels, characterized in that:

包括include

连接原有待施工浅埋暗挖隧道上方地质层的各个桩基结构的托换梁,该托换梁用于承载各所述桩基结构承载的载荷;An underpinning beam connecting the various pile foundation structures of the geological layer above the shallow buried tunnel to be constructed, the underpinning beam is used to bear the load carried by each of the pile foundation structures;

若干连接并支撑所述托换梁的托换柱,该托换柱用于承载所述托换梁承载的载荷;a plurality of underpinning columns connected to and supporting the underpinning beam, the underpinning columns are used to carry the load carried by the underpinning beam;

以及设置于待施工浅埋暗挖隧道的拱顶层的深孔注浆加固层。And the deep hole grouting reinforcement layer arranged on the vault layer of the shallow buried tunnel to be constructed.

进一步的,所述托换梁与各所述桩基结构通过梁抱柱结构连接,所述梁抱柱结构是指各所述桩基结构分别自所述托换梁内部穿过,且各自通过若干植筋与所述托换梁固定为一体。Further, the underpinning beam and each of the pile foundation structures are connected through a beam-embracing column structure, and the beam-embracing column structure means that each of the pile foundation structures passes through the inside of the underpinning beam respectively, and each passes through several planting bars and The underpinning beam is fixed as a whole.

优选的,所述植筋自所述桩基结构边缘圆周方向均匀布设,且沿着所述桩基结构的径向方向均匀布设多层。Preferably, the planting bars are evenly arranged from the circumferential direction of the edge of the pile foundation structure, and are evenly arranged in multiple layers along the radial direction of the pile foundation structure.

进一步的,所述托换柱通过若干均匀布设于所述托换柱与所述托换梁接触面的纵筋连接所述托换梁。Further, the underpinning column is connected to the underpinning beam through a number of longitudinal ribs evenly arranged on the contact surface between the underpinning column and the underpinning beam.

进一步的,所述深孔注浆加固层是以待施工浅埋暗挖隧道的拱顶层的开挖基线为基准线,分别向基准线两端延伸设置。Further, the deep hole grouting reinforcement layer takes the excavation baseline of the vault layer of the shallow buried tunnel to be constructed as the reference line, and extends to both ends of the reference line respectively.

进一步的,所述深孔注浆加固层的加固深度以探测到待施工浅埋暗挖隧道的拱顶层内的卵石层的距离为准。Further, the reinforcement depth of the deep hole grouting reinforcement layer is based on the distance detected to the pebble layer in the vault layer of the shallow buried tunnel to be constructed.

进一步的,所述深孔注浆加固层上设置若干超前探孔,以便于使得所述深孔注浆加固层的加固深度通过在待施工浅埋暗挖隧道的拱顶层的开挖掌子面上设置若干超前探孔的探测结果进行校准调整。Further, several advanced probe holes are set on the deep hole grouting reinforcement layer, so that the reinforcement depth of the deep hole grouting reinforcement layer can pass through the excavation face of the vault layer of the shallow buried tunnel to be constructed. Calibrate and adjust the detection results of several advanced probe holes.

与现有技术相比,本实用新型的有益效果:Compared with the prior art, the utility model has the beneficial effects:

本实用新型在不拆除原有桩基结构基础上,通过托换梁将被托换桩基结构的荷载转移到托换梁上,再通过托梁传递到托换柱上,以替代原来的桩基承受其上部的荷载,以实现不降低原有桩基结构上部结构承载力和整体刚度的前提下进行施工;同时加设深孔注浆加固层进一步提高地基土的强度、消除湿陷性,从而提高桩基的承载能力;因此本实用新型具有节省空间、造价低、施工周期短、不影响上部交通、安全可靠、减少环境污染等优点。On the basis of not removing the original pile foundation structure, the utility model transfers the load of the underpinned pile foundation structure to the underpinning beam through the underpinning beam, and then transfers it to the underpinning column through the underpinning beam to replace the original pile. The foundation bears the load on its upper part, so as to realize the construction without reducing the bearing capacity and overall rigidity of the upper part of the original pile foundation structure; at the same time, a deep hole grouting reinforcement layer is added to further improve the strength of the foundation soil and eliminate collapsibility. Therefore, the bearing capacity of the pile foundation is improved; therefore, the utility model has the advantages of space saving, low cost, short construction period, no influence on upper traffic, safety and reliability, and reduction of environmental pollution.

附图说明Description of drawings

图1为本实用新型所述桩基结构、托换梁及托换柱连接结构示意图;Fig. 1 is the schematic diagram of the connection structure of pile foundation structure, underpinning beam and underpinning column described in the utility model;

图2为本实用新型所述托换梁与所述桩基结构连接结构示意图;Fig. 2 is a schematic diagram of the connection structure between the underpinning beam and the pile foundation structure described in the utility model;

图3为图2剖面结构示意图;Fig. 3 is a schematic diagram of the cross-sectional structure of Fig. 2;

图4为本实用新型所述托换梁及托换柱连接结构示意图;Fig. 4 is a schematic diagram of the connection structure of the underpinning beam and the underpinning column described in the present invention;

图5为本实用新型所述桩基结构、托换梁及托换柱连接剖面结构示意图;Fig. 5 is a schematic diagram of the connection section structure of the pile foundation structure, the underpinning beam and the underpinning column described in the present invention;

图6为本实用新型所述深孔注浆加固层断面结构示意图;Fig. 6 is a schematic diagram of the section structure of the deep hole grouting reinforcement layer described in the present invention;

图7a为本实用新型所述的施工实施例的施工前原有结构示意图;Figure 7a is a schematic diagram of the original structure before the construction of the construction embodiment described in the utility model;

图7b为本实用新型所述的施工实施例的桩基托换结构开挖基槽施工示意图;Fig. 7b is a schematic diagram of excavating foundation trenches for the pile foundation underpinning structure according to the construction embodiment of the present invention;

图7c为本实用新型所述的施工实施例的桩基托换结构灌注托换桩施工示意图;Fig. 7c is a schematic diagram of the construction of the pile foundation underpinning structure perfusion underpinning pile construction according to the construction embodiment of the present invention;

图7d为本实用新型所述的施工实施例的桩基托换结构灌注托换梁施工示意图;Fig. 7d is a schematic diagram of the construction of the pile foundation underpinning structure poured underpinning beam according to the construction embodiment of the present invention;

图7e为本实用新型所述的施工实施例的桩基托换结构回填施工完成示意图。Fig. 7e is a schematic diagram of the completion of the backfilling construction of the pile foundation underpinning structure according to the construction embodiment of the present invention.

图中:1、原有待施工浅埋暗挖隧道上方地质层,2、桩基结构,3、托换梁,4、托换柱,5、植筋,6、纵筋,7、深孔注浆加固层,8、注浆孔,9、开挖基线。In the figure: 1. The geological stratum above the original shallow buried tunnel to be constructed, 2. Pile foundation structure, 3. Underpinning beam, 4. Underpinning column, 5. Planting reinforcement, 6. Longitudinal reinforcement, 7. Grout reinforcement layer, 8, grouting hole, 9, excavation baseline.

具体实施方式detailed description

为了使本实用新型的目的、技术方案及优点更加清楚明白,以下结合附图,对本实用新型进行进一步详细说明。In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model will be further described in detail below in conjunction with the accompanying drawings.

本实用新型所述的支护结构适用于浅埋暗挖隧道中临近建(构)筑物、地面条件限制、开挖影响桩底承载力、端承桩桩基侵入隧道拱顶、地层构造复杂、周围环境复杂、富水条件下的暗挖地下工程施工或类似工程施工等施工场合使用。The support structure described in the utility model is suitable for adjacent buildings (structures) in shallow buried tunnels, where ground conditions are limited, excavation affects the bearing capacity of pile bottoms, end-bearing pile foundations invade tunnel vaults, and stratum structures are complex. , The surrounding environment is complex, the construction of underground excavation under the condition of rich water or similar engineering construction and other construction occasions.

本实用新型主要设计要点包括:The main design points of the utility model include:

1.从桩基稳定性辅助结构进行设计:1. Design from the auxiliary structure of pile foundation stability:

当浅埋暗挖隧道穿越桥梁时,如图1、图5,设计了桩基托换结构以实现在不拆除原有桩基结构,不降低其上部结构承载力和整体刚度,进行荷载转移,及实现对上部结构的改造。同时所述桩基托换结构承担桥梁大部分荷载,从而减少桥桩底部荷载,使得隧道下穿桩基底时对上部桥梁的扰动减少。When the shallow-buried tunnel crosses the bridge, as shown in Figure 1 and Figure 5, the pile foundation underpinning structure is designed to realize the load transfer without demolishing the original pile foundation structure, without reducing the bearing capacity and overall stiffness of the superstructure. And realize the transformation of the superstructure. At the same time, the pile foundation underpinning structure bears most of the load of the bridge, thereby reducing the load at the bottom of the bridge pile, and reducing the disturbance to the upper bridge when the tunnel passes through the pile foundation.

所述桩基托换结构包括连接原有待施工浅埋暗挖隧道上方地质层1的各个桩基结构2,用于承载所述桩基结构2承载的载荷的托换梁3;The pile foundation underpinning structure includes each pile foundation structure 2 connected to the geological layer 1 above the shallow buried tunnel to be constructed, and an underpinning beam 3 for carrying the load carried by the pile foundation structure 2;

以及连接并支撑所述托换梁3,用于承载所述托换梁3承载的载荷的托换柱4;And connecting and supporting the underpinning beam 3, the underpinning column 4 for carrying the load carried by the underpinning beam 3;

所述托换梁3分别与所述桩基结构2通过梁抱柱结构连接,如图2所示,所述梁抱柱结构是指所述桩基结构2自所述托换梁3内部穿过,且通过若干植 筋5与所述托换梁3固定为一体。优选的,如图3所示,所述植筋5自所述桩基结构2边缘圆周方向均匀布设,且沿着所述桩基结构的径向方向均匀布设多层植筋,使得所述托换梁3与所述桩基结构2紧固为一体式结构。The underpinning beam 3 is respectively connected to the pile foundation structure 2 through a beam-embracing column structure, as shown in Figure 2, the beam-embracing column structure means that the pile foundation structure 2 passes through the underpinning beam 3 and passes Several planting bars 5 are fixed together with the underpinning beam 3 . Preferably, as shown in Figure 3, the planting bars 5 are evenly arranged from the circumferential direction of the edge of the pile foundation structure 2, and multi-layer planting bars are evenly arranged along the radial direction of the pile foundation structure, so that the support The changing beam 3 is fastened to the pile foundation structure 2 as an integral structure.

其中,托换梁3具体的结构分布特点是在原有待施工浅埋暗挖隧道上方地质层的原有桥桩(即所述桩基结构)之间建立起来一个横式梁构架,并与托换桩形成一个整体,用以承担其上部荷载,同时通过所述桩基结构,与所述桩基结构的植入式钢筋相结合,将所述桩基结构围绕在托换梁内,当上部荷载传递到所述桩基结构时,所述桩基结构将荷载转换到托换梁上,因此就形成了一个梁抱柱的工艺。Among them, the specific structural distribution feature of the underpinning beam 3 is that a horizontal beam frame is established between the original bridge piles (that is, the pile foundation structure) in the geological layer above the shallow buried excavation tunnel to be constructed, and is connected with the underpinning beam. The pile forms a whole to bear the upper load. At the same time, the pile foundation structure is combined with the implanted steel bars of the pile foundation structure to surround the pile foundation structure in the underpinning beam. When the upper load When it is transferred to the pile foundation structure, the pile foundation structure transfers the load to the underpinning beam, thus forming a beam-embracing-column process.

进一步的,如图4所示,所述托换柱4通过若干纵筋6连接所述托换梁3,所述纵筋6均匀布设于所述托换柱4与所述托换梁3接触面;即在所述托换梁上设置若干通孔,在通孔设置若干纵筋;同时在接触面(托换柱对应于托换梁的位置)打通孔,将托换梁的纵筋穿过所述托换柱并用化学植筋胶封孔。Further, as shown in Figure 4, the underpinning column 4 is connected to the underpinning beam 3 through several longitudinal ribs 6, and the longitudinal ribs 6 are evenly arranged on the underpinning column 4 in contact with the underpinning beam 3 That is, some through holes are set on the underpinning beam, and some longitudinal ribs are set in the through holes; at the same time, holes are opened on the contact surface (the position of the underpinning column corresponding to the underpinning beam), and the longitudinal ribs of the underpinning beam are penetrated. Pass through the underpinning column and seal the holes with chemical planting glue.

所述托换柱采用灌注混凝土,提前根据设计定点、打孔、下钢筋笼、灌注混凝土。The underpinning column adopts pouring concrete, and the points are fixed, holes are drilled, steel cages are lowered, and concrete is poured in advance according to the design.

托换梁的形成将托换柱与被托换柱连接成为整体,使桩基整体受力,减小了隧道上部桩基的荷载,减小局部应力集中,使浅埋暗挖隧道可以安全通过桥梁段。The formation of the underpinning beam connects the underpinning column and the underpinning column as a whole, so that the overall force of the pile foundation is reduced, the load of the pile foundation on the upper part of the tunnel is reduced, and the local stress concentration is reduced, so that the shallow buried tunnel can pass through safely bridge section.

其具体施做技术为:首先根据勘探以及设计要求,在现场进行定点打孔,由于钻孔灌注桩施工过程对原有桩承载力具有消弱作用,因此需要通过经验公式:来验算其承载力,其中d、D分别为待施工浅埋暗挖隧道内各个桩基结构桩径和托换桩的桩径。The specific implementation technology is as follows: first, according to the exploration and design requirements, drill holes at fixed points on site. Since the construction process of bored piles has a weakening effect on the bearing capacity of the original piles, it is necessary to use the empirical formula: To check and calculate its bearing capacity, where d and D are the pile diameters of each pile foundation structure and the pile diameter of the underpinning pile in the shallow buried tunnel to be constructed, respectively.

需要说明的是:本实用新型在施工过程中需要先完成托换桩的施工后再进行托换梁的施工,同时为保证柱轴力的传递顺利,应使托换梁和待施工浅埋暗挖隧道上方的各个桩基结构连为一体,即托换梁与各所述桩基结构连接形式采用梁抱柱的形式。为保证施工中不会使柱发生破坏,在打孔时应遵循随打随锚的原则,打孔完成后将孔内碎渣吹尽,立即锚入钢筋并注胶,待胶体强度达到100%时才能进行下一个钻孔。钢筋全部锚固完后即绑扎托换梁钢筋及浇筑混凝土,完成托换梁;如图7a—7e(图中出现隧道标识是为了显示桥梁的相对位置,而非实际隧道结构)所示施工实施例,桩基托换结构施工工艺为:基坑开挖→施工托换桩(人工挖孔桩)及预顶承台→在各桩基结构上植筋、进行界面处理 →绑扎托换梁钢筋→浇注托换梁→预顶→浇注托换桩和托换梁之间的微膨胀混凝土→回填。It should be noted that: in the construction process of this utility model, the construction of the underpinning pile needs to be completed before the construction of the underpinning beam. The various pile foundation structures above the excavated tunnel are connected as a whole, that is, the connection form between the underpinning beam and each of the pile foundation structures adopts the form of a beam holding a column. In order to ensure that the column will not be damaged during construction, the principle of drilling and anchoring should be followed when drilling. After the drilling is completed, the debris in the hole should be blown out, and the reinforcement should be anchored immediately and glue should be injected until the strength of the glue reaches 100%. Only then can the next hole be drilled. After all the steel bars are anchored, the steel bars of the underpinning beam are bound and concrete is poured to complete the underpinning beam; as shown in Figure 7a-7e (the tunnel marks appear in the figure to show the relative position of the bridge, not the actual tunnel structure) as shown in the construction example The construction process of the pile foundation underpinning structure is: excavation of the foundation pit → construction of underpinning piles (manual excavation piles) and pre-jack caps → planting reinforcement on each pile foundation structure and performing interface treatment → binding underpinning beam reinforcement → Pouring the underpinning beam → pre-topping → pouring the micro-expansion concrete between the underpinning pile and the underpinning beam → backfilling.

2.桩基托换结构结合定向深孔注浆加固层用以控制渗、涌水处理隧道周围土体及结构稳定性。2. The pile foundation underpinning structure combined with the directional deep hole grouting reinforcement layer is used to control seepage and water gushing to treat the soil and structure stability around the tunnel.

即在采用桩基托换结构的待施工浅埋暗挖隧道的拱顶层设置深孔注浆加固层7。That is, the deep hole grouting reinforcement layer 7 is set on the vault layer of the shallow-buried tunnel to be constructed using the pile foundation underpinning structure.

具体:specific:

设置深孔注浆加固层即采用定向深孔注浆技术,即利用气压或液压将各种有机或无机化学浆液注入土中,具有使地基固化,提高地基土的强度、消除湿陷性及防渗堵漏等作用,因此对于采用了桩基托换技术的待施工浅埋暗挖隧道,其可通过孔注浆加固层与桩基托换结构相结合,很大程度上提高浅埋暗挖隧道拱顶及上部的原有桩基持力层承载力,使构筑物产生的变形与沉降大幅度减小,可进一步增加了桩基的稳定性,提高了桩基的承载能力。Setting the deep hole grouting reinforcement layer means adopting directional deep hole grouting technology, that is, injecting various organic or inorganic chemical grouts into the soil by air pressure or hydraulic pressure, which can solidify the foundation, improve the strength of the foundation soil, eliminate collapsibility and prevent Therefore, for shallow-buried underground tunnels to be constructed using pile foundation underpinning technology, the hole grouting reinforcement layer can be combined with the pile foundation underpinning structure to greatly improve the performance of shallow buried underground excavation. The bearing capacity of the original pile foundation bearing layer on the tunnel vault and the upper part greatly reduces the deformation and settlement of the structure, which can further increase the stability of the pile foundation and improve the bearing capacity of the pile foundation.

所述深孔注浆加固层是以待施工浅埋暗挖隧道的拱顶层上的开挖基线9为基准线,分别向基准线两端延伸设置,如可以以开挖基线为基准线,分别向内0.4m范围,向外2m,注浆加固长度为12m范围设置,并要求加固后其渗透系数达到:10-6-10-7cm/sec,地基承载力≥300KPa,单轴无侧限抗压强度≥0.5MPa,整体无侧限抗压强度≥2.8MPa。The deep hole grouting reinforcement layer is based on the excavation baseline 9 on the vault layer of the shallow buried tunnel to be constructed as the reference line, and is extended to the two ends of the reference line respectively. If the excavation baseline can be used as the reference line, respectively 0.4m inward and 2m outward, the grouting reinforcement length is set within 12m, and the permeability coefficient after reinforcement is required to reach: 10-6-10-7cm/sec, the bearing capacity of the foundation is ≥300KPa, and the uniaxial unconfined resistance Compressive strength ≥ 0.5MPa, overall unconfined compressive strength ≥ 2.8MPa.

其注浆孔8可按照与拱顶层成一定倾斜角进行打孔如沿拱顶层自下至上成150°进行打孔设置。Its grouting hole 8 can carry out punching according to becoming certain angle of inclination with the vault top layer such as forming 150 ° from bottom to top along the vault top layer to punch and set.

所述深孔注浆加固层的加固深度以探测到待施工浅埋暗挖隧道的拱顶层内的卵石层的距离为准。即以卵石层侵入拱顶范围为参考加固长度值,具体施做原理为通过钻孔向断层与涌水带、岩土洞穴、岩体颗粒的孔隙、岩土层的界面或岩土的裂隙以及细颗粒岩体内注入具有充填、胶结性能的浆液材料,断层与涌水带岩体进过浆体的充填、压密、渗透、劈裂、固结等作用后,使岩体强度、稳定性和隔水防水性能得以提高,保证隧道和地下工程的正常施工。The reinforcement depth of the deep hole grouting reinforcement layer is based on the distance detected to the pebble layer in the vault layer of the shallow buried tunnel to be constructed. That is to say, the scope of pebble layer intrusion into the vault is used as the reference reinforcement length value. The specific implementation principle is to drill holes to faults and water gushing zones, rock-soil caves, pores of rock particles, rock-soil interface or rock-soil cracks and fine-grained holes. The grout material with filling and cementing properties is injected into the granular rock body, and the rock mass in the fault and water gushing zone is filled, compacted, infiltrated, split, consolidated, etc., to make the rock mass strength, stability and isolation The water-proof performance can be improved to ensure the normal construction of tunnels and underground works.

所述深孔注浆加固层工艺特点:The technical characteristics of the deep hole grouting reinforcement layer:

(1)注浆范围:(1) Grouting scope:

注浆范围是根据地质情况、地下水压力大小和隧道施工方法等因素综合确定。一般来说,注浆加固层其施工半径应为隧道开挖半径的2~3倍,当地下水压力过大或在水下施工时,应为隧道开挖半径的4~6倍。The scope of grouting is comprehensively determined according to factors such as geological conditions, groundwater pressure, and tunnel construction methods. Generally speaking, the construction radius of the grouting reinforcement layer should be 2 to 3 times the tunnel excavation radius, and it should be 4 to 6 times the tunnel excavation radius when the groundwater pressure is too high or the construction is under water.

(2)注浆孔布设(2) Layout of grouting holes

注浆孔布设在结合单个注浆孔的注浆扩散半径以及待施工浅埋暗挖隧道的整体开挖参数进行均匀布设,如图6所示,沿着待施工浅埋暗挖隧道逐层均匀布设若干注浆孔直至各个注浆孔的注浆扩散半径能够完全覆盖待施工浅埋暗挖隧道范围;如可根据注浆试验确定注浆的扩散半径为1.0m,并通过现场对注浆压力、注入能力和注浆时间等情况确定其孔位布设。注浆时,先行钻注浆孔,之后在注浆孔内放入钢管,最后通过钢管向围岩注浆。The grouting holes are arranged evenly in combination with the grouting diffusion radius of a single grouting hole and the overall excavation parameters of the shallow buried tunnel to be constructed, as shown in Figure 6, along the shallow buried tunnel to be constructed layer by layer. Arrange a number of grouting holes until the grouting diffusion radius of each grouting hole can completely cover the scope of the shallow buried tunnel to be constructed; for example, the grouting diffusion radius can be determined to be 1.0m according to the grouting test, and the grouting pressure can be controlled by the site. , injection capacity and grouting time to determine the layout of the holes. When grouting, first drill the grouting hole, then put the steel pipe in the grouting hole, and finally grout the surrounding rock through the steel pipe.

(3)注浆压力(3) Grouting pressure

注浆压力是给予浆液在土层中渗透、扩散、劈裂及压实的能量,其大小决定着注浆效果的好坏和费用的高低。可采用注浆压力按照注浆处静水压力加上1-1.5MPa控制。实际施工时注浆压力、浆液配比、注浆速度等施工技术参数应根据深度及地质条件,通过现场试验确定。The grouting pressure is the energy given to the grout to penetrate, diffuse, split and compact in the soil layer, and its size determines the quality of the grouting effect and the cost. The grouting pressure can be controlled according to the hydrostatic pressure at the grouting place plus 1-1.5MPa. During actual construction, the construction technical parameters such as grouting pressure, grout ratio, and grouting speed should be determined through field tests according to the depth and geological conditions.

定向注浆加固层可根据超前地质探孔确定的注浆方位、深度及注浆量进行设置,即所述深孔注浆加固层上设置若干超前地质探孔,以便于使得所述深孔注浆加固层的加固深度通过在待施工浅埋暗挖隧道的拱顶层的开挖掌子面上设置若干超前地质探孔的探测结果进行校准调整。需要说明的是,定向注浆加固层的设置还需要考虑来自待施工浅埋暗挖隧道的拱顶层承载力(包括上部原有建筑体以及桩基托换结构的整理压力)。The directional grouting reinforcement layer can be set according to the grouting orientation, depth and grouting amount determined by the advanced geological exploration holes, that is, several advanced geological exploration holes are set on the deep hole grouting reinforcement layer, so as to make the deep hole grouting The reinforcement depth of the slurry reinforcement layer is calibrated and adjusted by setting the detection results of several advanced geological exploration holes on the excavation face of the vault layer of the shallow buried tunnel to be constructed. It should be noted that the setting of the directional grouting reinforcement layer also needs to consider the bearing capacity of the vault layer from the shallow buried tunnel to be constructed (including the finishing pressure of the original upper building and the pile foundation underpinning structure).

精确的深孔注浆加固止水能有效改善地层性状,防止河道淹灌、提高拱圈承载力并有效控制掌子面渗漏水,确保隧道施工安全。因此本实用新型所述的结构的施做不仅使隧道开挖能够安全通过危险地段,而且对隧道周围地层进行了很大改善,很大程度的提高了魏台桥的承载力与稳定性。Accurate deep hole grouting to strengthen and stop water can effectively improve the formation properties, prevent river flooding, increase the bearing capacity of the arch ring, effectively control the water leakage of the tunnel face, and ensure the safety of tunnel construction. Therefore, the implementation of the structure described in the utility model not only enables the excavation of the tunnel to safely pass through the dangerous section, but also greatly improves the strata around the tunnel, and greatly improves the bearing capacity and stability of the Weitai Bridge.

由此可见,采用桩基托换并辅助以定向注浆加固形成了一种新型、综合性处理复杂地质条件、复杂结构以及在复杂环境中施工的专业性技术。It can be seen that the use of pile foundation underpinning and directional grouting reinforcement has formed a new and comprehensive professional technology for dealing with complex geological conditions, complex structures and construction in complex environments.

以上所述,仅为本实用新型较佳的具体实施方式,但本实用新型的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本实用新型揭露的技术范围内,根据本实用新型的技术方案及其实用新型构思加以等同替换或改变,都应涵盖在本实用新型的保护范围之内。The above is only a preferred embodiment of the utility model, but the scope of protection of the utility model is not limited thereto. Any equivalent replacement or change of the new technical solution and the concept of the utility model shall be covered by the protection scope of the utility model.

Claims (7)

1.一种过河段穿桥桩隧道注浆支护结构,其特征在于:1. A bridge pile tunnel grouting support structure in the section of the river, characterized in that: 连接原有待施工浅埋暗挖隧道上方地质层的各个桩基结构的托换梁,该托换梁用于承载各所述桩基结构承载的载荷;An underpinning beam connecting the various pile foundation structures of the geological layer above the shallow buried tunnel to be constructed, the underpinning beam is used to bear the load carried by each of the pile foundation structures; 若干连接并支撑所述托换梁的托换柱,该托换柱用于承载所述托换梁承载的载荷;a plurality of underpinning columns connected to and supporting the underpinning beam, the underpinning columns are used to carry the load carried by the underpinning beam; 以及设置于待施工浅埋暗挖隧道的拱顶层的深孔注浆加固层。And the deep hole grouting reinforcement layer arranged on the vault layer of the shallow buried tunnel to be constructed. 2.根据权利要求1所述的过河段穿桥桩隧道注浆支护结构,其特征在于:2. The bridge pile tunnel grouting support structure in the river crossing section according to claim 1, characterized in that: 所述托换梁与各所述桩基结构通过梁抱柱结构连接,所述梁抱柱结构是指各所述桩基结构分别自所述托换梁内部穿过,且各自通过若干植筋与所述托换梁固定为一体。The underpinning beam is connected to each of the pile foundation structures through a beam-embracing column structure, and the beam-embracing column structure means that each of the pile foundation structures passes through the inside of the underpinning beam respectively, and is connected to the underpinning beam through several planting bars. The changing beam is fixed as a whole. 3.根据权利要求2所述的过河段穿桥桩隧道注浆支护结构,其特征在于:3. The bridge pile tunnel grouting support structure in the river crossing section according to claim 2, characterized in that: 所述植筋自所述桩基结构边缘圆周方向均匀布设,且沿着所述桩基结构的径向方向均匀布设多层。The planting bars are evenly arranged from the peripheral direction of the pile foundation structure, and are evenly arranged in multiple layers along the radial direction of the pile foundation structure. 4.根据权利要求1所述的过河段穿桥桩隧道注浆支护结构,其特征在于:4. The bridge pile tunnel grouting support structure in the river crossing section according to claim 1, characterized in that: 所述托换柱通过若干均匀布设于所述托换柱与所述托换梁接触面的纵筋连接所述托换梁。The underpinning column is connected to the underpinning beam through a number of longitudinal reinforcements evenly arranged on the contact surface between the underpinning column and the underpinning beam. 5.根据权利要求1所述的过河段穿桥桩隧道注浆支护结构,其特征在于:5. The bridge pile tunnel grouting support structure in the river crossing section according to claim 1, characterized in that: 所述深孔注浆加固层是以待施工浅埋暗挖隧道的拱顶层的开挖基线为基准线,分别向基准线两端延伸设置。The deep hole grouting reinforcement layer is based on the excavation baseline of the vault layer of the shallow buried tunnel to be constructed, and is extended to both ends of the baseline. 6.根据权利要求1所述的过河段穿桥桩隧道注浆支护结构,其特征在于:6. The bridge pile tunnel grouting support structure in the river crossing section according to claim 1, characterized in that: 所述深孔注浆加固层的加固深度以探测到待施工浅埋暗挖隧道的拱顶层内的卵石层的距离为准。The reinforcement depth of the deep hole grouting reinforcement layer is based on the distance detected to the pebble layer in the vault layer of the shallow buried tunnel to be constructed. 7.根据权利要求1-5任一项所述的过河段穿桥桩隧道注浆支护结构,其特征在于:7. The bridge pile tunnel grouting support structure for crossing the river according to any one of claims 1-5, characterized in that: 所述深孔注浆加固层上设置若干超前探孔。Several advanced probe holes are arranged on the deep hole grouting reinforcement layer.
CN201620071681.5U 2016-01-25 2016-01-25 Cross section and wear bridge pier tunnel slip casting supporting construction Expired - Fee Related CN205576990U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620071681.5U CN205576990U (en) 2016-01-25 2016-01-25 Cross section and wear bridge pier tunnel slip casting supporting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620071681.5U CN205576990U (en) 2016-01-25 2016-01-25 Cross section and wear bridge pier tunnel slip casting supporting construction

Publications (1)

Publication Number Publication Date
CN205576990U true CN205576990U (en) 2016-09-14

Family

ID=56881880

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620071681.5U Expired - Fee Related CN205576990U (en) 2016-01-25 2016-01-25 Cross section and wear bridge pier tunnel slip casting supporting construction

Country Status (1)

Country Link
CN (1) CN205576990U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740446A (en) * 2017-10-16 2018-02-27 广州地铁设计研究院有限公司 Combined construction method of the passive supplement in existing building basis with underpining system in hole
CN108755669A (en) * 2018-06-26 2018-11-06 商洛学院 Across tunnel steel reinforced concrete bored concrete pile, conversion beam construction method
CN110847207A (en) * 2019-11-28 2020-02-28 中建八局轨道交通建设有限公司 Structure and construction method for newly-built bridge with subway tunnel passing through existing bridge piles
CN115787707A (en) * 2022-11-04 2023-03-14 中国铁路设计集团有限公司 A construction method of underground excavation pile foundation underpinning the existing structure closely

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740446A (en) * 2017-10-16 2018-02-27 广州地铁设计研究院有限公司 Combined construction method of the passive supplement in existing building basis with underpining system in hole
CN108755669A (en) * 2018-06-26 2018-11-06 商洛学院 Across tunnel steel reinforced concrete bored concrete pile, conversion beam construction method
CN110847207A (en) * 2019-11-28 2020-02-28 中建八局轨道交通建设有限公司 Structure and construction method for newly-built bridge with subway tunnel passing through existing bridge piles
CN115787707A (en) * 2022-11-04 2023-03-14 中国铁路设计集团有限公司 A construction method of underground excavation pile foundation underpinning the existing structure closely

Similar Documents

Publication Publication Date Title
CN102277867B (en) A construction method of collapsible loess foundation
CN109914456B (en) A design and construction method when a bridge and a subway tunnel are built adjacent to each other
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN103321234B (en) Constructing method of load-bearing structure built on high slope or geological complex area
CN103195076A (en) Method for constructing silt deep foundation pit tower crane foundation
CN104389315B (en) Consolidation grouting drilled pile wall and construction method thereof
CN205576990U (en) Cross section and wear bridge pier tunnel slip casting supporting construction
CN109578014A (en) Anti- dash forward of one kind gushes back cover structure and construction method
Wei et al. Seepage in Water‐Rich Loess Tunnel Excavating Process and Grouting Control Effect
Tan et al. Excavation of middle Huai-Hai road station of Shanghai metro line 13: Challenges, risks, countermeasures, and performance assessment
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
Xu et al. Influence of extreme shallow jacked box tunnelling on underlying metro tunnels: A case study
CN107100630A (en) Pile foundation type bored tunnel and construction method in deep backfill
CN113529830B (en) Shallow Buried Tunnel Adjacent Building Isolation-Underpinning Combination Reinforcement Structure and Its Construction Technology
CN201771514U (en) Concealed tunneling structure with pile foundation
Stirbys et al. Los Angeles metro rail project–geologic and geotechnical design and construction constraints
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN105178355B (en) The stratum pre-reinforcement processing method of underground space construction
CN206917655U (en) Pile foundation type bored tunnel in deep backfill
CN206477240U (en) A kind of trestle pile foundation for deep water drift net riverbed
CN112507424B (en) A construction method for shield tunneling under expansive soil strata to pass through railway tracks
CN212612517U (en) Micro steel pipe pile composite supporting structure for deep foundation pit in limited space

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

Termination date: 20170125

CF01 Termination of patent right due to non-payment of annual fee