CN205476466U - 大跨度型钢混凝土转换桁架分段吊装支模体系 - Google Patents

大跨度型钢混凝土转换桁架分段吊装支模体系 Download PDF

Info

Publication number
CN205476466U
CN205476466U CN201620237318.6U CN201620237318U CN205476466U CN 205476466 U CN205476466 U CN 205476466U CN 201620237318 U CN201620237318 U CN 201620237318U CN 205476466 U CN205476466 U CN 205476466U
Authority
CN
China
Prior art keywords
truss
web member
lower boom
template
modular unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620237318.6U
Other languages
English (en)
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jaso Group Co ltd
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201620237318.6U priority Critical patent/CN205476466U/zh
Application granted granted Critical
Publication of CN205476466U publication Critical patent/CN205476466U/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型涉及一种大跨度型钢混凝土转换桁架分段吊装支模体系,包括支撑柱,所述支撑柱设有柱端预埋支座和支撑柱纵筋,所述柱端预埋支座上架设桁架下弦杆,所述桁架下弦杆上设有桁架竖向腹杆、桁架斜向腹杆和桁架上弦杆;所述桁架下弦杆上设有桁架下弦杆底模;所述桁架斜向腹杆上设有模板单元a、模板单元b和模板单元c;所述桁架上弦杆上设有桁架上弦杆面模。本实用新型具有操作简单,构件连接刚度大,并且拆装方便等优点,具有较好的经济技术效益。

Description

大跨度型钢混凝土转换桁架分段吊装支模体系
技术领域
本实用新型涉及大跨度型钢混凝土桁架。
技术背景
高层建筑物使用功能的多样化,房间使用功能需要大空间、超楼层净高,通常采用结构转换来满足这一要求,型钢混凝土转换桁架是其中的一种特殊结构,通过实现上部与下部楼层不同柱网结构,从而满足房间使用功能。
型钢混凝土桁架刚度大,传力效果好,非常适合于大跨度转换结构的应用,但其在主体结构施工中占用工期较长,特别是水平型钢结构吊装、钢骨架外围密集排布的大直径钢筋绑扎和后续混凝土浇筑成为施工的主要难点和重点。
鉴于此,如何通过一些技术措施解决大跨度型钢混凝土转换桁架施工难题,是一个亟需解决的问题。
实用新型内容
本实用新型的目的在于提供一种大跨度型钢混凝土转换桁架分段吊装支模体系。
为实现上述目的,本实用新型采用了以下技术方案:
这种大跨度型钢混凝土转换桁架分段吊装支模体系,包括支撑柱,所述支撑柱设有柱端预埋支座和支撑柱纵筋,所述柱端预埋支座上架设桁架下弦杆,所述桁架下弦杆上设有桁架竖向腹杆、桁架斜向腹杆和桁架上弦杆;所述桁架下弦杆上设有桁架下弦杆底模;所述桁架斜向腹杆上设有模板单元a、模板单元b和模板单元c;所述桁架上弦杆上设有桁架上弦杆面模。
所述桁架下弦杆下架设钢管支撑。
模板单元b上安装有竖向爬梯和预制钢梯,模板单元c上安装有竖向爬梯,竖向爬梯两端均安装有爬梯垫板,爬梯垫板通过模板预焊栓钉与模板固定。
本实用新型具有以下的特点和有益效果:
(1)通过在预埋立柱支座以固定桁架下弦杆,为后续的安装提供准确定位,提高了安装质量。
(2)采用组合式腹杆模板,模板上设有竖向爬梯和预制钢梯,方便施工人员的安装拆除工作,腹杆模板为分离式模板,通过预埋栓钉的紧固和松开实现模板的安装和拆除,提高了施工效率。
附图说明
图1是大跨度型钢混凝土转换桁架分段吊装支模结构示意图;
图2是模板单元a装配图;
图3是模板单元b装配图;
图4是模板单元c装配图;
图中:1.支撑柱;2.钢管支撑;3.柱端预埋支座;4.支撑柱纵筋;5.桁架下弦杆底模;6.桁架下弦杆;7.桁架竖向腹杆;8.桁架斜向腹杆;9.桁架上弦杆;10.模板单元a;11.模板单元b;12.模板单元c;13.桁架上弦杆面模;14.贯通上层柱;15.非贯通上层柱;16.钢杆件预焊栓钉;17.竖向爬梯;18.预制钢梯;19.预制钢梯支撑梁;20.爬梯垫板;21.模板预焊栓钉;22.模板预焊垫板。
具体实施方式
本实施方式钢结构焊接工艺、螺栓连接施工工艺、模板设置工艺及混凝土浇筑施工工艺等本实施中就不在累述,重点阐述本实用新型涉及结构的实施方式。
大跨度型钢混凝土转换桁架分段吊装支模体系,包括:2.钢管支撑;3.柱端预埋支座;5.桁架下弦杆底模;6.桁架下弦杆;7.桁架竖向腹杆;8.桁架斜向腹杆;9.桁架上弦杆;10.模板单元a;11.模板单元b;12.模板单元c;13.桁架上弦杆面模;14.贯通上层柱;15.非贯通上层柱;16.钢杆件预焊栓钉;17.竖向爬梯;18.预制钢梯;19.预制钢梯支撑梁;20.爬梯垫板;21.模板预焊栓钉;22.模板预焊垫板。
参照图1所示,图中:桁架上弦杆6和桁架上弦杆9伸入柱端的长度按设计确定,柱端预埋支座3下部预埋筋伸入柱端长度按不小于40倍预埋筋直径确定。
参照图2所示,图中:竖向爬梯17焊接于爬梯垫板20上,竖向爬梯17可采用槽钢杆件通过螺栓连接而成,槽钢厚度可选4~6mm,预制钢梯18可采用工字钢梁上焊接踏步板,踏板厚度可选4~6mm。
本实用新型主要包括如下施工步骤:
1)柱端预埋支座3埋设:首先在支撑柱1浇筑前预埋钢筋,待支撑柱1强度达到设计要求后,在预埋筋钢筋上焊接钢板作为支座;
2)下部钢管支撑2搭设:采用钢管搭设,钢管之间采用扣件固定;
3)桁架下弦杆6吊装安装:桁架下弦杆6在地面组装完成,吊装桁架下弦杆6使其两端架在柱端预埋支座3之上并固定;
4)桁架腹杆吊装安装:桁架竖向腹杆7和桁架斜向腹杆8在地面组装成单元,在腹杆上安装栓钉,再分单元吊装至桁架下弦杆6上方,进行节点的安装固定;
5)桁架上弦杆9吊装安装:桁架上弦杆9在地面组装完成并在上弦杆上安装栓钉,吊装桁架上弦杆9至腹杆上部,进行节点的安装固定;
6)下弦杆底模安装:桁架下弦杆底模5在地面组装完成,并整体吊装至设计位置;
7)钢筋绑扎:钢筋绑扎按照先下线再腹杆后上弦的顺序进行,腹板钢筋绑扎时使箍筋放入栓钉之间,通过栓钉挂住箍筋。
8)腹杆模板安装:腹杆模板首先在地面上组合成单元,按设计要求分别组装成模板单元1、模板单元2和模板单元3,分别吊装模板单元至指定位置,通过腹杆上的栓钉固定模板单元;
9)上弦杆模板安装:桁架下弦杆面模13在地面组装完成,并整体吊装至设计位置;
10)混凝土浇筑:混凝土浇筑采用分层浇筑的方式进行,先进行下弦杆的浇筑,后进行腹杆和上弦杆的整体浇筑,下弦杆和下弦杆通过预留浇筑孔浇筑,腹杆通过腹杆和上弦杆节点处预留孔洞进行浇筑;
11)模板拆除:先进行腹杆模板单元的拆除,再进行上下弦杆模板的拆除,腹杆模板单元拆除先拧开模板预焊栓钉21螺帽分段拆除;
步骤1)中所述的在下层支撑柱顶设置柱端预埋支座3,桁架下弦杆6两端安装固定于柱端预埋支座3上;
步骤8)中所述的腹杆模板组合成腹板单元a、腹板单元b和腹板单元c,模板单元b11上安装有竖向爬梯17和预制钢梯18为施工安装提供便利,模板单元c12上安装有竖向爬梯17,竖向爬梯17两端均安装有爬梯垫板20,爬梯垫板20通过模板预焊栓钉21与模板固定;
步骤11)中所述的腹杆模板拆除通过松开模板预焊栓钉21将模板分段拆除。

Claims (3)

1.一种大跨度型钢混凝土转换桁架分段吊装支模体系,其特征在于,包括支撑柱(1),所述支撑柱(1)设有柱端预埋支座(3)和支撑柱纵筋(4),所述柱端预埋支座(3)上架设桁架下弦杆(6),所述桁架下弦杆(6)上设有桁架竖向腹杆(7)、桁架斜向腹杆(8)和桁架上弦杆(9);所述桁架下弦杆(6)上设有桁架下弦杆底模(5);所述桁架斜向腹杆(8)上设有模板单元a(10)、模板单元b(11)和模板单元c(12);所述桁架上弦杆(9)上设有桁架上弦杆面模(13)。
2.根据权利要求1所示的大跨度型钢混凝土转换桁架分段吊装支模体系,其特征在于,所述桁架下弦杆(6)下架设钢管支撑(2)。
3.根据权利要求1所示的大跨度型钢混凝土转换桁架分段吊装支模体系,其特征在于,模板单元b(11)上安装有竖向爬梯(17)和预制钢梯(18),模板单元c(12)上安装有竖向爬梯(17),竖向爬梯(17)两端均安装有爬梯垫板(20),爬梯垫板(20)通过模板预焊栓钉(21)与模板固定。
CN201620237318.6U 2016-03-24 2016-03-24 大跨度型钢混凝土转换桁架分段吊装支模体系 Expired - Fee Related CN205476466U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620237318.6U CN205476466U (zh) 2016-03-24 2016-03-24 大跨度型钢混凝土转换桁架分段吊装支模体系

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620237318.6U CN205476466U (zh) 2016-03-24 2016-03-24 大跨度型钢混凝土转换桁架分段吊装支模体系

Publications (1)

Publication Number Publication Date
CN205476466U true CN205476466U (zh) 2016-08-17

Family

ID=56652921

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620237318.6U Expired - Fee Related CN205476466U (zh) 2016-03-24 2016-03-24 大跨度型钢混凝土转换桁架分段吊装支模体系

Country Status (1)

Country Link
CN (1) CN205476466U (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227715A (zh) * 2020-10-21 2021-01-15 贵州建工集团第一建筑工程有限责任公司 一种型钢混凝土转换桁架剪力墙施工方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227715A (zh) * 2020-10-21 2021-01-15 贵州建工集团第一建筑工程有限责任公司 一种型钢混凝土转换桁架剪力墙施工方法

Similar Documents

Publication Publication Date Title
CN105780922B (zh) 大跨度型钢混凝土转换桁架分段吊装支模体系施工方法
CN200975103Y (zh) 液压中心顶升爬模装置
CN202090591U (zh) 一种建筑施工升降式爬升模板
CN110878522B (zh) 主塔下横梁施工体系及施工方法
CN109914244B (zh) 一种适用于高塔钢混结合横梁钢结构安装及底、顶板混凝土浇筑的弱支架系统及其操作方法
CN102277836B (zh) 倾斜式混凝土塔座的施工方法
CN106320183A (zh) 一种装配式盖梁模板系统
CN113279582A (zh) 一种用于悬挑并下挂式现浇板的吊挂施工方法
CN109972512A (zh) 一种压型钢板-混凝土组合桥面板的现浇施工方法
CN203285050U (zh) 滑模携带升降的组合式贝雷架多功能平台
CN205476466U (zh) 大跨度型钢混凝土转换桁架分段吊装支模体系
CN101793012B (zh) 一种新型无支架建桥方法
CN115538678B (zh) 一种大角度悬挑观景平台侧面小平台施工方法
CN218061492U (zh) 一种在钢结构框架上浇筑砼平台的装置
CN216947881U (zh) 一种工字组合梁现浇桥面板的模板支撑
CN107700363B (zh) 一种自带提升系统的桥塔台架及施工方法
CN205296821U (zh) 大坡度现浇混凝土斜屋面支模体系
CN210798994U (zh) 混凝土结构墙体单侧模板结构
CN211922324U (zh) 一种预制盖梁湿接缝施工吊模系统
CN115559208A (zh) 双肢墩横系梁施工工法
CN210177367U (zh) 一种适用于高塔钢混结合横梁钢结构安装的弱支架系统
CN115045505A (zh) 一种在钢结构框架上浇筑砼平台的装置及施工方法
CN107815976B (zh) 一种多联连续梁或多联刚构梁边跨直线梁段的施工方法
CN206319622U (zh) 一种屋盖钢桁架滑移轨道
CN220166687U (zh) 一种索塔上横梁现浇施工拱架

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Wen Songsheng

Inventor after: Lian Hailiang

Inventor after: Cao Rui

Inventor after: Zhang Kankan

Inventor after: Chen Jun

Inventor after: Zhang Haijun

Inventor after: Zhang Qiwu

Inventor before: Wang Xinquan

COR Change of bibliographic data
TR01 Transfer of patent right

Effective date of registration: 20170116

Address after: 200000 Shanghai city Jiading District Cao Road No. 4800 Building No. 1 Jiashi

Patentee after: SHANGHAI JASO GROUP Co.,Ltd.

Address before: 310015 Hangzhou Wanda Commercial Center, Zhejiang, building 3, unit 1901, room 3

Patentee before: HANGZHOU JIANGRUN TECHNOLOGY Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160817