[go: up one dir, main page]

CN205444722U - External gutter structure of eaves mouth - Google Patents

External gutter structure of eaves mouth Download PDF

Info

Publication number
CN205444722U
CN205444722U CN201521100765.9U CN201521100765U CN205444722U CN 205444722 U CN205444722 U CN 205444722U CN 201521100765 U CN201521100765 U CN 201521100765U CN 205444722 U CN205444722 U CN 205444722U
Authority
CN
China
Prior art keywords
cornice
fixed
side wall
external gutter
trough
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201521100765.9U
Other languages
Chinese (zh)
Inventor
多跃刚
王越
刘旭东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sharp Technology Beijing Co ltd
Original Assignee
BEIJING OHC STEELWORK ENGINEERING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING OHC STEELWORK ENGINEERING CO LTD filed Critical BEIJING OHC STEELWORK ENGINEERING CO LTD
Priority to CN201521100765.9U priority Critical patent/CN205444722U/en
Application granted granted Critical
Publication of CN205444722U publication Critical patent/CN205444722U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

本实用新型提供了一种檐口外挂天沟结构,能够有效防止屋内漏水,并且结构组合方便,便于安装。天沟结构包括:主体钢架;檐口檩条位于墙面的内侧,并固定在主体钢架上;螺钉将保温层固定在檐口檩条的檩条上端;檐口折弯角钢为长槽型,长槽型的横截面具有左侧壁、右侧壁和顶部平面;右侧壁位于墙面的内侧并与檐口檩条固定;左侧壁位于墙面的外侧;顶部平面高出檩条上端一个预定距离;屋面板的波谷支撑在顶部平面上,螺钉位于所述波谷的下方并且与所述波谷相分离;在墙面的外侧,屋面板的波谷通过螺栓固定在檐口折弯角钢的顶部平面,外挂天沟通过支撑组件安装在檐口折弯角钢的左侧壁。

The utility model provides a gutter structure hanging outside the cornice, which can effectively prevent water leakage in the house, and has convenient structure combination and installation. The gutter structure includes: the main steel frame; the eaves purlins are located on the inner side of the wall and fixed on the main steel frame; the insulation layer is fixed on the upper end of the eaves purlins by screws; The cross-section has a left side wall, a right side wall, and a top plane; the right side wall is located on the inside of the wall and is fixed to the cornice purlin; the left side wall is located on the outside of the wall; the top plane is a predetermined distance above the upper end of the purlin; the roof panel The trough is supported on the top plane, and the screws are located below the trough and separated from the trough; on the outside of the wall, the trough of the roof panel is fixed to the top plane of the cornice bending angle steel by bolts, and the external sky communication passes through the support assembly Installed on the left side wall of the cornice bending angle steel.

Description

一种檐口外挂天沟结构A eaves hanging gutter structure

技术领域technical field

本实用新型涉及建筑钢结构领域,特别是涉及一种檐口外挂天沟结构。The utility model relates to the field of building steel structures, in particular to a gutter structure with external cornices.

背景技术Background technique

目前很多厂房采用钢结构的形式,钢结构厂房特点有:1、钢结构建筑质量轻,强度高,跨度大;2、钢结构建筑施工工期短,相应降低投资成本;3、钢结构建筑防火性高,防腐蚀性强;4、钢结构建筑搬移方便,回收无污染。At present, many factories adopt the form of steel structure. The characteristics of steel structure factory buildings are as follows: 1. Steel structure buildings are light in weight, high in strength and large in span; 2. The construction period of steel structure buildings is short, which reduces investment costs accordingly; 3. Fire resistance of steel structure buildings High, strong corrosion resistance; 4. The steel structure building is easy to move, and the recycling is pollution-free.

图1为钢结构厂房的示意图,如图1所示,厂房顶部为具有一定坡度的向左右两侧倾斜延伸的金属屋面板101,左右两侧为山墙103,正面为檐口102,厂房内部具有主体钢架等支撑结构。其中,金属屋面板101并非平面,如图2所显示,屋面板具有周期性的波峰211波谷结构212。Figure 1 is a schematic diagram of a steel structure factory building. As shown in Figure 1, the top of the factory building is a metal roof panel 101 with a certain slope extending to the left and right sides, the left and right sides are gables 103, and the front is a cornice 102. There is a main body inside the factory building Supporting structures such as steel frames. Wherein, the metal roof panel 101 is not flat. As shown in FIG. 2 , the roof panel has periodic crests 211 and troughs 212 .

为了防止雨水流溢,在檐口的金属屋面下方要设置外挂天沟,用来收集和导流雨水。图3为现有技术的檐口外挂天沟的结构图,如图3所示,屋面板具有波峰311和波谷312,主体钢架32上固定有檐口角钢33,螺钉34将玻璃棉35固定在檐口角钢33上,并且螺钉34贯穿屋面板的波谷312,外挂天沟36设置在墙体37的外侧。In order to prevent rainwater from overflowing, external gutters shall be set under the metal roof of the eaves to collect and divert rainwater. Fig. 3 is the structural diagram of the gutter outside the eaves of the prior art. As shown in Fig. 3, the roof panel has crests 311 and troughs 312, and eaves angle steel 33 is fixed on the main steel frame 32, and glass wool 35 is fixed on the eaves by screws 34 On the angle steel 33 , and the screw 34 penetrates the trough 312 of the roof panel, and the external gutter 36 is arranged on the outside of the wall 37 .

现有技术的这种结构,因为其固有的施工程序,螺钉34贯穿屋面板,虽然采用了一定的防水措施,但在热胀冷缩或长期风吹日晒后,贯穿处非常容易产生缝隙,而螺钉34又位于墙体之内,这导致渗漏的雨水进入厂房内部,给厂房内部的生产带来损失。In this structure of the prior art, because of its inherent construction procedure, the screw 34 runs through the roof panel. Although certain waterproof measures are adopted, gaps are easily formed at the penetration point after thermal expansion and contraction or long-term wind and sun exposure. And screw 34 is located in the body of wall again, and this causes the rainwater of seepage to enter inside factory building, brings loss to the production inside factory building.

实用新型内容Utility model content

本实用新型的目的是要提供一种檐口外挂天沟结构,能够有效防止屋内漏水,并且结构组合方便,便于安装。The purpose of the utility model is to provide a gutter structure hanging outside the cornice, which can effectively prevent water leakage in the house, and the structure is convenient to assemble and easy to install.

为了实现上述目的,本实用新型提供了一种檐口外挂天沟结构,包括:In order to achieve the above purpose, the utility model provides a gutter structure with an external cornice, including:

主体钢架411;Main steel frame 411;

檐口檩条413位于墙面42的内侧,并固定在所述主体钢架411上;The eaves purlin 413 is located on the inner side of the wall 42 and is fixed on the steel frame 411 of the main body;

螺钉43将保温层415固定在所述檐口檩条413的檩条上端;Screw 43 fixes the thermal insulation layer 415 on the purlin upper end of the cornice purlin 413;

檐口折弯角钢45为长槽型,所述长槽型的横截面具有左侧壁、右侧壁和顶部平面;所述右侧壁位于所述墙面42的内侧并与所述檐口檩条413固定;所述左侧壁位于所述墙面42的外侧;所述顶部平面高出所述檩条上端一个预定距离;屋面板的波谷44支撑在所述顶部平面上,所述螺钉43位于所述波谷44的下方并且与所述波谷相分离;The eaves bending angle steel 45 is a long trough, and the cross section of the long trough has a left side wall, a right side wall and a top plane; fixed; the left side wall is located on the outside of the wall 42; the top plane is a predetermined distance above the upper end of the purlin; the trough 44 of the roof panel is supported on the top plane, and the screw 43 is located on the top plane. below and separated from trough 44;

在所述墙面42的外侧,所述屋面板的所述波谷44通过螺栓48固定在所述檐口折弯角钢45的所述顶部平面,外挂天沟46通过支撑组件47安装在所述檐口折弯角钢45的所述左侧壁。On the outside of the wall surface 42, the trough 44 of the roof panel is fixed on the top plane of the cornice bending angle steel 45 by bolts 48, and the external gutter 46 is installed on the cornice corner through a support assembly 47. The left side wall of the angle steel 45 is bent.

优选的,上述的檐口外挂天沟结构中,所述螺栓48在水平面的投影位于所述外挂天沟46在水平面的投影的范围内。Preferably, in the aforementioned eaves hanging gutter structure, the projection of the bolt 48 on the horizontal plane is within the range of the projection of the external hanging gutter 46 on the horizontal plane.

优选的,上述的檐口外挂天沟结构中,还包括:Preferably, the above-mentioned eaves hanging gutter structure also includes:

天沟吊件49,一端固定在所述屋面板的波峰上,另一端固定在所述支撑组件47上从而形成三角形支撑结构。One end of the gutter hanger 49 is fixed on the crest of the roof panel, and the other end is fixed on the support assembly 47 to form a triangular support structure.

优选的,上述的檐口外挂天沟结构中,所述预定距离为7-10毫米。Preferably, in the above-mentioned cornice hanging gutter structure, the predetermined distance is 7-10 mm.

优选的,上述的檐口外挂天沟结构中,所述预定距离为8毫米。Preferably, in the above-mentioned cornice hanging gutter structure, the predetermined distance is 8 mm.

优选的,上述的檐口外挂天沟结构中,所述支撑组件47包括在对合后能组成长方体的上部件471和下部件472。Preferably, in the above-mentioned cornice hanging gutter structure, the support assembly 47 includes an upper part 471 and a lower part 472 that can form a cuboid after being combined.

优选的,上述的檐口外挂天沟结构中,所述上部件471在端部孔4711与所述檐口折弯角钢45的所述左侧壁的安装孔4511相固定;Preferably, in the above-mentioned eaves hanging gutter structure, the upper part 471 is fixed to the installation hole 4511 of the left side wall of the eaves bending angle steel 45 at the end hole 4711;

所述下部件472的第一孔4721、第二孔4722分别通过拉铆钉与所述外挂天沟46固定,所述下部件472的第三孔4723通过螺钉与所述外挂天沟46固定;The first hole 4721 and the second hole 4722 of the lower part 472 are respectively fixed to the external gutter 46 by rivets, and the third hole 4723 of the lower part 472 is fixed to the external gutter 46 by screws;

所述下部件472的第四孔4724、第五孔4725对应安装在所述上部件471的第一对应孔4712和第二对应孔4713。The fourth hole 4724 and the fifth hole 4725 of the lower part 472 are correspondingly installed in the first corresponding hole 4712 and the second corresponding hole 4713 of the upper part 471 .

优选的,上述的檐口外挂天沟结构中,所述第一对应孔4712和所述第二对应孔4713的孔径具有安装对准余量。Preferably, in the above-mentioned eaves hanging gutter structure, the diameters of the first corresponding hole 4712 and the second corresponding hole 4713 have an installation alignment margin.

优选的,上述的檐口外挂天沟结构中,所述螺栓48为压铆螺栓。Preferably, in the above-mentioned eaves hanging gutter structure, the bolts 48 are pressure riveting bolts.

本实用新型实施例具有以下技术效果:Embodiments of the utility model have the following technical effects:

1)实用新型实施例中,固定保温层415的螺钉43并不贯穿屋面板,这样,在墙面42的内侧,因为屋面板没有贯穿孔,不会产生室内漏雨的风险。1) In the embodiment of the utility model, the screws 43 for fixing the insulation layer 415 do not penetrate the roof panel. In this way, on the inner side of the wall 42, because the roof panel has no through holes, there is no risk of indoor rain leakage.

2)螺钉43位于由所述顶部平面的预定距离撑起的容置空间内,与所述波谷相分离,防止螺钉因为意外顶破屋面板的风险。2) The screw 43 is located in the accommodating space propped up by a predetermined distance from the top plane, and is separated from the trough, so as to prevent the screw from accidentally breaking the roof panel.

3)所述屋面板在所述墙面42的外侧通过螺栓48与檐口折弯角钢固定,即使螺栓处产生漏雨,也是漏到墙外,不会影响室内。3) The roof panel is fixed on the outside of the wall surface 42 by bolts 48 and cornice bending angle steel. Even if rain leakage occurs at the bolts, it will leak out of the wall and will not affect the interior.

4)所述螺栓48在水平面的投影位于所述外挂天沟46在水平面的投影的范围内。这样,螺栓48处即使漏水,也会流到外挂天沟中,防止直接冲刷墙面42。4) The projection of the bolt 48 on the horizontal plane is within the range of the projection of the external gutter 46 on the horizontal plane. In this way, even if water leaks at the bolt 48, it will flow into the external gutter to prevent the wall 42 from being directly washed.

5)所述支撑组件47包括在对合后能组成长方体的上部件471和下部件472,上部件固定后,下部件先和外挂天沟46固定,然后下部件和外挂天沟一起固定在上部件的第一对应孔4712和第二对应孔4713,这种安装方式更为有效便捷。5) The support assembly 47 includes an upper part 471 and a lower part 472 that can form a cuboid after being combined. After the upper part is fixed, the lower part is first fixed with the external gutter 46, and then the lower part and the external gutter are fixed together on the upper The first corresponding hole 4712 and the second corresponding hole 4713 of the component, this installation method is more effective and convenient.

6)本实用新型整体结构是针对檐口外挂天沟结构的整体改进,非常适合檐口的组装,组合方便,便于安装。6) The overall structure of the utility model is an overall improvement on the external gutter structure of the cornice, which is very suitable for the assembly of the cornice, and is easy to assemble and install.

根据下文结合附图对本实用新型具体实施例的详细描述,本领域技术人员将会更加明了本实用新型的上述以及其他目的、优点和特征。According to the following detailed description of specific embodiments of the utility model in conjunction with the accompanying drawings, those skilled in the art will be more aware of the above and other objectives, advantages and features of the utility model.

附图说明Description of drawings

后文将参照附图以示例性而非限制性的方式详细描述本实用新型的一些具体实施例。附图中相同的附图标记标示了相同或类似的部件或部分。本领域技术人员应该理解,这些附图未必是按比例绘制的。附图中:Hereinafter, some specific embodiments of the present utility model will be described in detail in an exemplary rather than restrictive manner with reference to the accompanying drawings. The same reference numerals in the drawings designate the same or similar parts or parts. Those skilled in the art will appreciate that the drawings are not necessarily drawn to scale. In the attached picture:

图1为钢结构厂房的示意图Figure 1 is a schematic diagram of a steel structure workshop

图2是屋面板波峰波谷示意图;Fig. 2 is a schematic diagram of roof panel peaks and valleys;

图3为现有技术的檐口外挂天沟的结构图;Fig. 3 is the structural diagram of the external gutter hanging from the cornice of the prior art;

图4为本实用新型实施例的檐口外挂天沟结构的结构图;Fig. 4 is a structural diagram of the external gutter structure of the cornice of the embodiment of the present invention;

图5为本实用新型实施例的檐口折弯角钢的立体图;Fig. 5 is the three-dimensional view of the cornice bending angle steel of the utility model embodiment;

图6为本实用新型实施例的檐口折弯角钢的主视图;Fig. 6 is the front view of the cornice bending angle steel of the utility model embodiment;

图7为本实用新型实施例的支撑组件的上部件的立体图;Fig. 7 is a perspective view of the upper part of the support assembly according to the embodiment of the present invention;

图8为本实用新型实施例的支撑组件的上部件的主视图;Fig. 8 is a front view of the upper part of the support assembly of the utility model embodiment;

图9为本实用新型实施例的支撑组件的下部件的立体图;Fig. 9 is a perspective view of the lower part of the support assembly according to the embodiment of the present invention;

图10为本实用新型实施例的支撑组件的下部件的主视图。Fig. 10 is a front view of the lower part of the support assembly of the embodiment of the present invention.

具体实施方式detailed description

图4为本实用新型实施例的檐口外挂天沟结构的结构图,如图4所示,本实用新型实施例提供一种檐口外挂天沟结构,包括:Fig. 4 is a structural diagram of the gutter structure hanging from the cornice of the embodiment of the present invention. As shown in Fig. 4, the embodiment of the present utility model provides a gutter structure hanging from the cornice, including:

主体钢架411;Main steel frame 411;

檐口檩条413位于墙面42的内侧,并固定在所述主体钢架411上;The eaves purlin 413 is located on the inner side of the wall 42 and is fixed on the steel frame 411 of the main body;

螺钉43将保温层415固定在所述檐口檩条413的檩条上端;Screw 43 fixes the thermal insulation layer 415 on the purlin upper end of the cornice purlin 413;

檐口折弯角钢45为长槽型,所述长槽型的横截面具有左侧壁、右侧壁和顶部平面;所述右侧壁位于所述墙面42的内侧并与所述檐口檩条413固定;所述左侧壁位于所述墙面42的外侧;所述顶部平面高出所述檩条上端一个预定距离;屋面板的波谷44支撑在所述顶部平面上,所述螺钉43位于所述波谷44的下方并且与所述波谷相分离;The eaves bending angle steel 45 is a long trough, and the cross section of the long trough has a left side wall, a right side wall and a top plane; fixed; the left side wall is located on the outside of the wall 42; the top plane is a predetermined distance above the upper end of the purlin; the trough 44 of the roof panel is supported on the top plane, and the screw 43 is located on the top plane. below and separated from trough 44;

在所述墙面42的外侧,所述屋面板的所述波谷44通过螺栓48固定在所述檐口折弯角钢45的所述顶部平面,外挂天沟46通过支撑组件47安装在所述檐口折弯角钢45的所述左侧壁。On the outside of the wall surface 42, the trough 44 of the roof panel is fixed on the top plane of the cornice bending angle steel 45 by bolts 48, and the external gutter 46 is installed on the cornice corner through a support assembly 47. The left side wall of the angle steel 45 is bent.

可见,实用新型实施例中,固定保温层415的螺钉43并不贯穿屋面板,这样,在墙面42的内侧,因为屋面板没有贯穿孔,不会产生室内漏雨的风险。并且,螺钉43位于由所述顶部平面的预定距离撑起的容置空间内,与所述波谷相分离,防止螺钉因为意外顶破屋面板的风险。进一步的,所述屋面板在所述墙面42的外侧通过螺栓48与檐口折弯角钢固定,即使螺栓处产生漏雨,也是漏到墙外,不会影响室内。It can be seen that in the embodiment of the utility model, the screws 43 fixing the insulation layer 415 do not penetrate the roof panel. In this way, on the inner side of the wall 42, because the roof panel has no through holes, there is no risk of indoor rain leakage. Moreover, the screw 43 is located in the accommodating space propped up by a predetermined distance from the top plane, and is separated from the trough, so as to prevent the screw from accidentally breaking the roof panel. Further, the roof panel is fixed on the outside of the wall surface 42 with the cornice bending angle steel by bolts 48, even if rain leakage occurs at the bolts, it will leak out of the wall and will not affect the interior.

其中,主体钢架411安装固定有檩托412;檐口檩条413是固定在所述檩托412上。Wherein, the steel frame 411 of the main body is installed and fixed with a purlin support 412; the eaves purlin 413 is fixed on the purlin support 412.

在本实用新型的另一个实施例中,所述螺栓48在水平面的投影位于所述外挂天沟46在水平面的投影的范围内。这样,螺栓48处即使漏水,也会流到外挂天沟中,防止直接冲刷墙面42。In another embodiment of the present invention, the projection of the bolt 48 on the horizontal plane is within the range of the projection of the external gutter 46 on the horizontal plane. In this way, even if water leaks at the bolt 48, it will flow into the external gutter to prevent the wall 42 from being directly washed.

在本实用新型的另一个实施例中,还包括:天沟吊件49,一端固定在所述屋面板的波峰上,另一端固定在所述支撑组件47上从而形成三角形支撑结构。天沟吊件49为多个,在每个波峰都固定一个,因为三角形支撑结构比较稳定,对于长长的外挂天沟46来说,有利于外挂件的稳定,防止外挂天沟松动或脱落。In another embodiment of the present invention, it further includes: a gutter hanger 49, one end of which is fixed on the peak of the roof panel, and the other end is fixed on the support assembly 47 to form a triangular support structure. There are multiple gutter hangers 49, one is fixed at each wave crest, because the triangular support structure is relatively stable, for the long external gutter 46, it is conducive to the stability of the external hanger and prevents the external gutter from loosening or coming off.

在本实用新型的另一个实施例中,所述预定距离为7-10毫米。所述预定距离优选为8毫米。该距离是长期实践中获得的,既能提供足够的容置空间容纳螺钉43,使得螺钉43不会顶抵屋面板波谷,有不会使得空间过大造成浪费。In another embodiment of the present utility model, the predetermined distance is 7-10 mm. The predetermined distance is preferably 8 mm. This distance is obtained in long-term practice, which can not only provide enough accommodating space to accommodate the screw 43, so that the screw 43 will not touch the trough of the roof panel, and will not make the space too large to cause waste.

图5为本实用新型实施例的檐口折弯角钢的立体图;图6为本实用新型实施例的檐口折弯角钢的主视图;如图所示,檐口折弯角钢为长槽型,所述长槽型的横截面具有左侧壁451、右侧壁452和顶部平面453;左侧壁451具有安装孔4511,多个螺栓48固定在顶部平面,螺栓48为压铆螺栓。Fig. 5 is the perspective view of the eaves bending angle steel of the utility model embodiment; Fig. 6 is the front view of the eaves bending angle steel of the utility model embodiment; As shown in the figure, the eaves bending angle steel is a long groove type, the long The cross section of the groove has a left side wall 451, a right side wall 452 and a top plane 453; the left side wall 451 has a mounting hole 4511, and a plurality of bolts 48 are fixed on the top plane, and the bolts 48 are pressure riveting bolts.

图7、图8为本实用新型实施例的支撑组件的上部件的立体图、主视图;图9、图10为支撑组件的下部件的立体图、主视图;如图所示,所述支撑组件47包括在对合后能组成长方体的上部件471和下部件472。7 and 8 are perspective views and front views of the upper part of the support assembly of the embodiment of the present invention; FIGS. 9 and 10 are perspective views and front views of the lower part of the support assembly; as shown in the figure, the support assembly 47 It includes an upper part 471 and a lower part 472 that can form a cuboid after being combined.

所述上部件471在端部孔4711与所述檐口折弯角钢45的所述左侧壁的安装孔4511相固定;The upper part 471 is fixed to the installation hole 4511 of the left side wall of the cornice bending angle 45 at the end hole 4711;

所述下部件472的第一孔4721、第二孔4722分别通过拉铆钉与所述外挂天沟46固定,所述下部件472的第三孔4723通过螺钉与所述外挂天沟46固定;The first hole 4721 and the second hole 4722 of the lower part 472 are respectively fixed to the external gutter 46 by rivets, and the third hole 4723 of the lower part 472 is fixed to the external gutter 46 by screws;

所述下部件472的第四孔4724、第五孔4725对应安装在所述上部件471的第一对应孔4712和第二对应孔4713。The fourth hole 4724 and the fifth hole 4725 of the lower part 472 are correspondingly installed in the first corresponding hole 4712 and the second corresponding hole 4713 of the upper part 471 .

在本实用新型的一个实施例中,所述第一对应孔4712和所述第二对应孔4713的孔径具有安装对准余量。实际安装中,上部件固定后,下部件先和外挂天沟46固定,然后下部件和外挂天沟一起固定在上部件的第一对应孔4712和第二对应孔4713,为了安装的时候便于对准,第一对应孔4712和第二对应孔4713的孔径要大一些,也就是留有安装对准余量。In one embodiment of the present invention, the diameters of the first corresponding hole 4712 and the second corresponding hole 4713 have an installation alignment margin. In actual installation, after the upper part is fixed, the lower part is first fixed with the external gutter 46, and then the lower part and the external gutter are fixed together in the first corresponding hole 4712 and the second corresponding hole 4713 of the upper part, so as to facilitate alignment during installation. For alignment, the diameters of the first corresponding hole 4712 and the second corresponding hole 4713 are larger, that is, there is an installation alignment margin.

本实用新型实施例还提供了一种用于上述的檐口外挂天沟结构的安装方法,包括:The embodiment of the utility model also provides an installation method for the above-mentioned cornice hanging gutter structure, including:

步骤一,在所述檩托412上安装所述檐口檩条413;Step 1, installing the eaves purlin 413 on the purlin support 412;

步骤二,在所述檐口檩条413上安装所述檐口折弯角钢45;Step 2, installing the cornice bending angle steel 45 on the cornice purlin 413;

步骤三,铺设所述保温层415,并通过所述螺钉43和压棉板固定在所述檐口檩条413的所述檩条上端;Step 3, laying the thermal insulation layer 415, and fixing it on the upper end of the purlin of the cornice purlin 413 through the screw 43 and the cotton pressing board;

步骤四,在檐口挡水板上铺设通长胶泥,在所述通长胶泥上安装檐口堵头,在所述檐口堵头上铺设两遍胶泥;Step 4, laying long-length cement on the eaves retaining plate, installing cornice plugs on the long-length cement, and laying cement twice on the cornice plugs;

步骤五,对应所述檐口堵头安装所述屋面板,所述波谷44通过所述螺栓48和不锈钢压条固定在所述檐口折弯角钢45的所述顶部平面;Step 5, installing the roof panel corresponding to the eaves plug, the trough 44 is fixed on the top plane of the eaves bending angle steel 45 through the bolt 48 and stainless steel bead;

步骤六,将所述支撑组件47的上部件471固定在所述檐口折弯角钢45上;Step six, fixing the upper part 471 of the support assembly 47 on the cornice bending angle steel 45;

步骤七,将天沟吊件49的一端固定在所述屋面板的所述波峰上,另一端固定在所述上部件471上;Step 7, fixing one end of the gutter hanger 49 on the peak of the roof panel, and fixing the other end on the upper part 471;

步骤八,安装所述墙面42;Step 8, installing the wall surface 42;

步骤九,外挂天沟46安装在所述支撑组件47的下部件472上;Step 9, the external gutter 46 is installed on the lower part 472 of the support assembly 47;

步骤十,将所述下部件472安装在所述上部件471上。Step ten, install the lower part 472 on the upper part 471 .

采用该安装方法,能够使得檐口外挂天沟结构安装的更为顺畅、便捷。Adopting this installation method can make the installation of the external gutter structure on the cornice more smooth and convenient.

由上可知,本实用新型具有以下优势:As can be seen from the above, the utility model has the following advantages:

1)实用新型实施例中,固定保温层415的螺钉43并不贯穿屋面板,这样,在墙面42的内侧,因为屋面板没有贯穿孔,不会产生室内漏雨的风险。1) In the embodiment of the utility model, the screws 43 for fixing the insulation layer 415 do not penetrate the roof panel. In this way, on the inner side of the wall 42, because the roof panel has no through holes, there is no risk of indoor rain leakage.

2)螺钉43位于由所述顶部平面的预定距离撑起的容置空间内,与所述波谷相分离,防止螺钉因为意外顶破屋面板的风险。2) The screw 43 is located in the accommodating space propped up by a predetermined distance from the top plane, and is separated from the trough, so as to prevent the screw from accidentally breaking the roof panel.

3)所述屋面板在所述墙面42的外侧通过螺栓48与檐口折弯角钢固定,即使螺栓处产生漏雨,也是漏到墙外,不会影响室内。3) The roof panel is fixed on the outside of the wall surface 42 by bolts 48 and cornice bending angle steel. Even if rain leakage occurs at the bolts, it will leak out of the wall and will not affect the interior.

4)所述螺栓48在水平面的投影位于所述外挂天沟46在水平面的投影的范围内。这样,螺栓48处即使漏水,也会流到外挂天沟中,防止直接冲刷墙面42。4) The projection of the bolt 48 on the horizontal plane is within the range of the projection of the external gutter 46 on the horizontal plane. In this way, even if water leaks at the bolt 48, it will flow into the external gutter to prevent the wall 42 from being directly washed.

5)所述支撑组件47包括在对合后能组成长方体的上部件471和下部件472,上部件固定后,下部件先和外挂天沟46固定,然后下部件和外挂天沟一起固定在上部件的第一对应孔4712和第二对应孔4713,这种安装方式更为有效便捷。5) The support assembly 47 includes an upper part 471 and a lower part 472 that can form a cuboid after being combined. After the upper part is fixed, the lower part is first fixed with the external gutter 46, and then the lower part and the external gutter are fixed together on the upper The first corresponding hole 4712 and the second corresponding hole 4713 of the component, this installation method is more effective and convenient.

6)本实用新型整体结构是针对檐口外挂天沟结构的整体改进,非常适合檐口的组装,组合方便,便于安装。6) The overall structure of the utility model is an overall improvement on the external gutter structure of the cornice, which is very suitable for the assembly of the cornice, and is easy to assemble and install.

至此,本领域技术人员应认识到,虽然本文已详尽示出和描述了本实用新型的多个示例性实施例,但是,在不脱离本实用新型精神和范围的情况下,仍可根据本实用新型公开的内容直接确定或推导出符合本实用新型原理的许多其他变型或修改。因此,本实用新型的范围应被理解和认定为覆盖了所有这些其他变型或修改。So far, those skilled in the art should recognize that although a number of exemplary embodiments of the present invention have been shown and described in detail herein, they can still be used according to the present invention without departing from the spirit and scope of the present invention. Many other variations or modifications that conform to the principles of the utility model are directly determined or derived from the disclosed content of the new model. Therefore, the scope of the present invention should be understood and deemed to cover all such other variations or modifications.

Claims (9)

1. a cornice external gutter structure, it is characterised in that including:
Main body steelframe (411);
Cornice purlin (413) is positioned at the inner side of metope (42), and is fixed on described main body steelframe (411);
Heat-insulation layer (415) is fixed on the purlin upper end of described cornice purlin (413) by screw (43);
Cornice bending angle steel (45) is trough type, and the cross section of described trough type has left side wall, right side wall and top planes;Described right side wall is positioned at the inner side of described metope (42) and fixes with described cornice purlin (413);Described left side wall is positioned at the outside of described metope (42);Described top planes exceeds one, described purlin upper end preset distance;The trough (44) of roof boarding is supported in described top planes, and described screw (43) is positioned at the lower section of described trough (44) and is separated with described trough;
Outside in described metope (42), the described trough (44) of described roof boarding is fixed on the described top planes of described cornice bending angle steel (45) by bolt (48), and external gutter (46) is arranged on the described left side wall of described cornice bending angle steel (45) by a support component (47).
Cornice external gutter structure the most according to claim 1, it is characterised in that described bolt (48) is positioned at described external gutter (46) in the range of the projection of horizontal plane in the projection of horizontal plane.
Cornice external gutter structure the most according to claim 1, it is characterised in that also include:
Gutter hanging piece (49), one end is fixed on the crest of described roof boarding, and the other end is fixed on described support component (47) and above thus forms triangular support structure.
Cornice external gutter structure the most according to claim 1, it is characterised in that described preset distance is 7-10 millimeter.
Cornice external gutter structure the most according to claim 4, it is characterised in that described preset distance is 8 millimeters.
Cornice external gutter structure the most according to claim 1, it is characterised in that described support component (47) be included in involutory after can form upper-part (471) and the lower component (472) of cuboid.
Cornice external gutter structure the most according to claim 6, it is characterised in that
Described upper-part (471) fixes at the installing hole (4511) of end hole (4711) with the described left side wall of described cornice bending angle steel (45);
First hole (4721) of described lower component (472), the second hole (4722) are fixed with described external gutter (46) by pulling rivet respectively, and the 3rd hole (4723) of described lower component (472) is fixed with described external gutter (46) by screw;
4th hole (4724) of described lower component (472), the 5th hole (4725) correspondence are arranged on the first corresponding aperture (4712) and second corresponding aperture (4713) of described upper-part (471).
Cornice external gutter structure the most according to claim 7, it is characterised in that the aperture of described first corresponding aperture (4712) and described second corresponding aperture (4713) has installation alignment surplus.
Cornice external gutter structure the most according to claim 1, it is characterised in that
Described bolt (48) is pressing-riveting bolt.
CN201521100765.9U 2015-12-24 2015-12-24 External gutter structure of eaves mouth Expired - Fee Related CN205444722U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521100765.9U CN205444722U (en) 2015-12-24 2015-12-24 External gutter structure of eaves mouth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521100765.9U CN205444722U (en) 2015-12-24 2015-12-24 External gutter structure of eaves mouth

Publications (1)

Publication Number Publication Date
CN205444722U true CN205444722U (en) 2016-08-10

Family

ID=56579630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521100765.9U Expired - Fee Related CN205444722U (en) 2015-12-24 2015-12-24 External gutter structure of eaves mouth

Country Status (1)

Country Link
CN (1) CN205444722U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464298A (en) * 2015-12-24 2016-04-06 北京东方诚国际钢结构工程有限公司 Cornice plug-in gutter structure and installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464298A (en) * 2015-12-24 2016-04-06 北京东方诚国际钢结构工程有限公司 Cornice plug-in gutter structure and installation method

Similar Documents

Publication Publication Date Title
US8869478B2 (en) Modular roof system for a building
CN205444722U (en) External gutter structure of eaves mouth
CN204252425U (en) A kind of heat insulation type photovoltaic tile roof structure
CN102808481A (en) Steel structure cold-bridge-preventing roof system
CN111188465B (en) Metal roof system
CN204112529U (en) The residence outer wall plate of gas concrete
CN207499258U (en) Water blocking formula house expansion joint portion structure
CN105464298B (en) A kind of cornice external gutter structure and installation method
CN111549956A (en) Assembled integrated purlin roof for box-type modular house and mounting method
CN201221143Y (en) Metal thin case frame connecting components
CN205348608U (en) A general eaves mouth for building
CN211873592U (en) Waterproof treatment node structure of steel structure downslope dormer side and roofing planking
CN109386095A (en) A kind of overhead type tile batten
CN210563040U (en) Node structure of steel structure gutter
CN209353580U (en) A kind of overhead type tile batten
JP6129057B2 (en) Daylighting roofing equipment
CN208415708U (en) A kind of mounting structure of roof lighting board
CN202227596U (en) Roof longitudinal expansion joint connecting structure
KR101854032B1 (en) capping device of rooftop parapet
CN207296202U (en) A kind of roofing lightning protection structure
CN106049769A (en) Member type photovoltaic tile waterproof roof
CN219710791U (en) Archaize building slope roof gutter structure
CN205444726U (en) Gable waterproof construction
CN222595345U (en) A steel structure roof duct uphill waterproofing node structure
CN215483417U (en) Decoration integration pipe structure in water

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20161223

Address after: 100083 Beijing, Xueyuan Road, a number of 2 cottage B-1192 room

Patentee after: Changku (Beijing) Technology Co.,Ltd.

Address before: 100124 Beijing city Chaoyang District East Fourth Ring Road No. 195 building, room 1101, Huateng new world

Patentee before: BEIJING OHC STEELWORK ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100083 Beijing, Xueyuan Road, a number of 2 cottage B-1192 room

Patentee after: Sharp technology (Beijing) Co.,Ltd.

Address before: 100083 Beijing, Xueyuan Road, a number of 2 cottage B-1192 room

Patentee before: Changku (Beijing) Technology Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160810