CN205171378U - Assembling lifting type construction platform for pier column construction - Google Patents
Assembling lifting type construction platform for pier column construction Download PDFInfo
- Publication number
- CN205171378U CN205171378U CN201520919418.2U CN201520919418U CN205171378U CN 205171378 U CN205171378 U CN 205171378U CN 201520919418 U CN201520919418 U CN 201520919418U CN 205171378 U CN205171378 U CN 205171378U
- Authority
- CN
- China
- Prior art keywords
- layer frame
- pier stud
- construction
- frame
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
- 238000010276 construction Methods 0.000 title claims abstract description 57
- 229910000831 Steel Inorganic materials 0.000 claims description 49
- 239000010959 steel Substances 0.000 claims description 49
- 238000009415 formwork Methods 0.000 claims description 45
- 230000003028 elevating effect Effects 0.000 claims description 7
- 230000001174 ascending effect Effects 0.000 claims description 6
- 239000000758 substrate Substances 0.000 claims description 2
- 230000006835 compression Effects 0.000 claims 3
- 238000007906 compression Methods 0.000 claims 3
- 230000008602 contraction Effects 0.000 claims 2
- 238000007596 consolidation process Methods 0.000 claims 1
- 238000012856 packing Methods 0.000 claims 1
- 230000008093 supporting effect Effects 0.000 claims 1
- 238000000034 method Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 125000004122 cyclic group Chemical group 0.000 description 2
- 238000004904 shortening Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域:Technical field:
本实用新型涉及一种墩柱施工使用的组装升降式施工平台。The utility model relates to an assembled lifting type construction platform used for pier column construction.
背景技术:Background technique:
目前,在墩柱的施工过程中,特别是桥梁墩柱的施工,一般采用如图1或2所述的技术,如第1图所示,为一种习知的桥梁墩柱土木施工法,每一推升阶段皆由移动式吊车辅助吊装、拆钢模板,施工架搭设于墩柱之四侧,每一推升阶段皆由人力位于最上缘之高处组立钢模板及施工架,拆除时以移动式吊车吊装拆除位于高处最上缘之钢模板,施工架以人力由上至下拆除,期间辅以移动式吊车吊放拆除后之施工架至地面放置。At present, in the construction process of pier columns, especially the construction of bridge pier columns, the technology described in Figure 1 or 2 is generally used. As shown in Figure 1, it is a known civil construction method for bridge pier columns. Each lifting stage is assisted by a mobile crane to lift and dismantle the steel formwork. The construction frame is erected on the four sides of the pier column. In each lifting stage, the steel formwork and construction frame are assembled by manpower at the top of the uppermost edge, and the construction frame is removed. The steel formwork at the uppermost edge of the high place is hoisted and removed by a mobile crane, and the construction frame is removed from top to bottom by manpower. During this period, the removed construction frame is lifted to the ground by a mobile crane.
如第2图所示,为另一种习知的桥梁墩柱土木施工法,每一推升阶段皆由移动式吊车辅助吊装、拆钢模板,在施工墩柱之一侧搭设人员上下设备,每一推升阶段皆由人力位于最上缘之高处组立钢模板及人员上下设备,拆除时以移动式吊车吊装拆除位于高处最上缘之钢模板,人员上下设备以人力由上至下拆除,期间辅以移动式吊车吊放拆除后之设备至地面放置。As shown in Figure 2, it is another known civil construction method for bridge pier columns. At each lifting stage, a mobile crane is used to assist in hoisting and dismantling the steel formwork. In each lifting stage, the steel formwork and the equipment for personnel to go up and down are assembled by manpower on the uppermost edge. When dismantling, the steel formwork located on the uppermost edge of the high place is hoisted and dismantled by a mobile crane, and the equipment for personnel to go up and down is removed by manpower from top to bottom During the period, a mobile crane is used to hoist the dismantled equipment to the ground.
现有的桥梁墩柱的施工由完成的墩柱部分之上缘处向上依序组立模板及施工架之方式施工,期间施工人员需位于高处组装作业并辅以移动式吊车吊装,拆除时亦同,不但施工效率不佳,使施工人员曝露于高处作业之危险性次数增加。The construction of the existing bridge pier column is constructed by sequentially erecting formwork and construction frame from the upper edge of the completed pier column part. In the same way, not only the construction efficiency is not good, but also the number of times the construction workers are exposed to the danger of high-altitude operations increases.
实用新型内容:Utility model content:
本实用新型的目的在于克服上述现有技术的缺点,提供一种墩柱施工使用的组装升降式施工平台,以油压升降设备系统驱动作业层架及模板系统上升及下降,作业层架与通道层架皆位于地面部组拆装,可免除施工人员位于高处拆组装作业,有效缩短施工周期。The purpose of this utility model is to overcome the shortcomings of the above-mentioned prior art, and provide an assembled lifting construction platform for pier column construction. The hydraulic lifting equipment system drives the working layer frame and the formwork system to rise and fall, and the working layer frame and the channel The shelves are all assembled and disassembled on the ground, which can save the construction personnel from disassembling and assembling at high places, effectively shortening the construction period.
为达成上述目的,本实用新型采用如下技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:
墩柱施工使用的组装升降式施工平台,包括一作业层架、一或多数个通道层架、一升降设备系统及一模板系统;其中,模板系统设置在墩柱与作业层架之间,升降设备系统推动作业层架举升至定位高度,在墩柱两侧地面以水平方向推置入通道层架并在地面部与作业层架组装。The assembled elevating construction platform used in pier column construction includes a working layer frame, one or more channel layers, a lifting equipment system and a formwork system; wherein, the formwork system is arranged between the pier column and the operating layer frame, and the lifting The equipment system pushes the working shelf up to the positioning height, pushes the passage shelf horizontally on the ground on both sides of the pier column, and assembles it with the working shelf on the ground.
进一步,作业层架及通道层架的每一层架均分为A单元与B单元,A、B单元为相对应的模组化制作成框架结构,A、B单元钢梁相应接合处设有接合基板通过螺栓锁固接合。Further, each floor of the operation shelf and the channel shelf is divided into A unit and B unit. The A and B units are correspondingly modularized to form a frame structure. The corresponding joints of the steel beams of the A and B units are equipped with The joining substrates are joined by bolt locking.
进一步,所述的作业层架上设有固定式楼梯连接施工平台,平台外沿设有栏杆,通道层架上设有活动楼梯连接通道踏板,通道踏板外沿设有护栏,通道踏板及活动楼梯通过螺栓及插销与通道层架接合固定,作业层架和通道层架与墩柱间设有滚轮保持间距以利升降作业的进行及避免与模板系统与墩柱磨损。Further, the working floor frame is provided with a fixed staircase connected to the construction platform, railings are provided on the outer edge of the platform, a movable staircase is provided on the passage floor frame to connect the passage pedal, a guardrail is provided on the outer edge of the passage pedal, the passage pedal and the movable staircase The bolts and pins are fixed to the channel frame, and there are rollers between the operation frame, the channel frame and the pier to maintain the distance to facilitate the lifting operation and avoid wear and tear on the formwork system and the pier.
进一步,作业层架与墩柱间设有模板系统,所述模板系统为具有伸缩油压杆钢模板系统,包括二或多数个伸缩控制箱、八或多数个伸缩油压杆及四或多数个钢模板所组成,钢模板分为帽梁模板与墩柱模板,钢模板组立时由伸缩控制箱操作两侧先后同时向墩柱方向伸出迫紧,并通过螺栓及插销固结钢模板;脱模时伸缩油压杆向钢框施工架方向缩回至定位,完成脱模。Further, a formwork system is provided between the working layer frame and the pier column. The formwork system is a steel formwork system with telescopic oil pressure rods, including two or more telescopic control boxes, eight or more telescopic oil pressure rods and four or more Composed of steel formwork, the steel formwork is divided into cap beam formwork and pier column formwork. When the steel formwork is assembled, the two sides of the telescopic control box are operated to extend and tighten toward the pier column at the same time, and the steel formwork is consolidated by bolts and bolts; When molding, the telescopic oil pressure rod is retracted to the direction of the steel frame construction frame to the position, and the demoulding is completed.
进一步,所述的升降设备系统为油压升降设备系统,油压升降设备系统包括四或多数组油压机及升降支柱、一个升降控制箱、四或多数个升降支承、四或多数个止滑煞车装置;施工平台升降时由升降控制箱控制同时四组或多数个油压机升降支柱作动带动作业层架上移。Further, the lifting equipment system is an hydraulic lifting equipment system, and the hydraulic lifting equipment system includes four or more groups of hydraulic machines and lifting pillars, one lifting control box, four or more lifting supports, four or more anti-skid brake devices ; When the construction platform is raised and lowered, it is controlled by the lifting control box, and at the same time four groups or more of the lifting pillars of the hydraulic press are actuated to drive the working layer to move up.
采用上述技术方案,本实用新型组装时,位于地面部作业,先组装油压升降设备系统以连结固定杆固定于预置的混凝土墩柱,作业层架A单元与B单元由相应之两侧推入通过螺栓固结。由上至下吊装钢模板与油压伸缩杆组合成钢模板系统,以螺栓固结。With the above-mentioned technical solution, when the utility model is assembled, it is located on the ground for operation, and the hydraulic lifting equipment system is first assembled to connect the fixed rod to the preset concrete pier column, and the A unit and B unit of the working floor frame are pushed by the corresponding two sides. Integrate with bolts. The steel formwork is hoisted from top to bottom and the hydraulic telescopic rod is combined to form a steel formwork system, which is consolidated with bolts.
上升时,位于地面部作业,先升起油压升降设备的升降支承至一定高度,与作业层架钢梁连结且固定,由升降控制箱操作油压升降设备将钢框施工架的作业平台升高至定位。由地面水平相应的两侧以移动设备推入通道层架A单元与B单元通过螺栓固结。下降作业层架与通道层架组合,并通过螺栓固结。When ascending, when working on the ground, first raise the lifting support of the hydraulic lifting equipment to a certain height, connect and fix it with the steel beam of the working layer frame, and operate the hydraulic lifting equipment to lift the working platform of the steel frame construction frame by the lifting control box. up to positioning. From the corresponding two sides of the ground level, the moving equipment is pushed into the channel shelf A unit and B unit are fixed by bolts. The descending operation layer frame is combined with the channel layer frame and fixed by bolts.
施工完成需拆除时,位于地面部作业,先升起油压升降设备系统的升降支承至一定高度,与作业层架钢梁连结且固定,拆卸上下及左右层架接合基板的螺栓,油压升降设备操作向上举起5公分使上下层架分离,使用移动设备将通道层架向外侧拉出移除,油压升降设备系统始操作向下降落钢框施工架平台至地面。When the construction is completed and needs to be dismantled, when the operation is on the ground, first raise the lifting support of the hydraulic lifting equipment system to a certain height, connect and fix it with the steel beam of the working layer frame, remove the bolts connecting the upper and lower layers and the left and right layers to the base plate, and then hydraulically lift Equipment operation Lift up 5 cm to separate the upper and lower frames, use the mobile device to pull out the channel frame to the outside and remove it, and the hydraulic lifting equipment system starts to operate and lower the steel frame construction platform to the ground.
本实用新型与现有技术相比,有效降低施工成本,降低施工人员位于高处组装作业次数;提供施工人员一完整安全作业平台环境及适当进出之上下通道;自动化的提高,使施工效率得以提高、品质稳定及施工周期有效的缩短。Compared with the prior art, the utility model can effectively reduce the construction cost and reduce the number of assembly operations of the construction personnel at high places; provide the construction personnel with a complete and safe working platform environment and proper access to the upper and lower passages; the improvement of automation improves the construction efficiency , stable quality and effective shortening of construction period.
附图说明:Description of drawings:
图1为现有桥梁墩柱施工架平台一;Fig. 1 is existing bridge pier column construction frame platform one;
图2为现有桥梁墩柱施工架平台二;Fig. 2 is existing bridge pier column construction frame platform two;
图3为本实用新型的立体图;Fig. 3 is the perspective view of the utility model;
图4为本实用新型的前视图;Fig. 4 is the front view of the utility model;
图5为本实用新型的左视图;Fig. 5 is the left view of the utility model;
图6为本实用新型的后视图;Fig. 6 is the rear view of the utility model;
图7为本实用新型的右视图;Fig. 7 is the right view of the utility model;
图8为本实用新型的前剖视图;Figure 8 is a front sectional view of the utility model;
图9为本实用新型的后剖视图;Figure 9 is a rear sectional view of the utility model;
图10为本实用新型的立体分解图;Fig. 10 is a three-dimensional exploded view of the utility model;
图11为本实用新型的升降示意图。Fig. 11 is a schematic diagram of lifting of the utility model.
其中:in:
10a作业层架A单元10a Unit A of working shelf
10b作业层架B单元10b Unit B of the working shelf
11a通道层架A单元11a channel shelf A unit
11b通道层架A单元11b channel shelf A unit
10作业层架10 working layers
11通道层架11 channel shelves
12固定式楼梯12 fixed stairs
13组装式楼梯13 assembled stairs
14帽梁钢模板14 cap beam steel formwork
15墩柱钢模板15 pier column steel formwork
16栏杆16 Railings
17平台钢网踏板17 platform steel mesh pedal
18框架交叉钢系杆18 frame cross steel tie rods
19油压伸缩控制箱19 hydraulic telescopic control box
20伸缩油压杆20 telescopic oil pressure rod
21接合基板及螺栓21 Joint base plate and bolts
22油压升降支柱22 oil hydraulic lifting pillar
23油压机23 hydraulic press
24油压升降设备固定连结杆24 Oil hydraulic lifting equipment fixed connecting rod
25油压升降控制箱25 hydraulic lifting control box
26滚轮26 rollers
27连结电缆27 connecting cables
28升降支承28 lifting support
具体实施方式:detailed description:
为使本实用新型的目的,技术方案和优点更加清楚明了,下面通过附图中示出的具体实施例来描述本实用新型。但是应该理解,这些描述只是示例性的,而并非要限制本实用新型的范围。此外,在以下说明中,省略了对公知结构和技术的描述,以避免不必要的混淆本实用新型的概念。In order to make the purpose, technical solutions and advantages of the utility model clearer, the utility model is described below through specific embodiments shown in the accompanying drawings. However, it should be understood that these descriptions are only exemplary and not intended to limit the scope of the present invention. In addition, in the following description, descriptions of known structures and technologies are omitted to avoid unnecessary confusion of the concept of the present invention.
参阅图3-11所示为本实用新型的实施例,以桥梁墩柱施工使用的组装升降式施工平台为例,包括一作业层架、一或多数个通道层架、一升降设备系统及一模板系统;其中,模板系统设置在墩柱与作业层架之间,升降设备系统推动作业层架举升至定位高度,在墩柱两侧地面以水平方向推置入通道层架并在地面与作业层架组装。Referring to Fig. 3-11, it is an embodiment of the present utility model. Taking the assembled elevating construction platform used in bridge pier construction as an example, it includes a working shelf, one or more channel shelves, a lifting equipment system and a Formwork system; wherein, the formwork system is set between the pier column and the working layer frame, and the lifting equipment system promotes the operation layer frame to be lifted to the positioning height, and the ground on both sides of the pier column is pushed into the channel layer frame in a horizontal direction and placed between the ground and the working layer frame. Assembling the work shelf.
具体的,一作业层架10由单元A10a与单元B10b组合而成,一或多数个通道层架11由单元A11a与单元B11b组合而成;油压升降设备系统包括一油压升降控制箱25,一连结电缆27,四或多数个油压机23,四或多数个油压升降支柱22,四或多数个升降支承28;钢模板系统包括二或多数个油压伸缩控制箱19,四或多数个帽梁钢模板14,四或多数个墩柱钢模板15,每片钢模板由八或多数个伸缩油压杆20控制;作业层架10设有固定式楼梯12可达最上层平台;作业层架10与通道层架11或上下层通道层架11间设有组装式楼梯13连结;作业层架单元A10a与单元B10b、通道层架单元A11a与单元B11b或上下层架组合时,对齐相应之接合基板21使用螺栓固定。Specifically, a working shelf 10 is composed of unit A10a and unit B10b, and one or more channel shelves 11 are composed of unit A11a and unit B11b; the hydraulic lifting equipment system includes a hydraulic lifting control box 25, One connection cable 27, four or more hydraulic presses 23, four or more hydraulic lifting columns 22, four or more lifting supports 28; the steel formwork system includes two or more hydraulic telescopic control boxes 19, four or more caps Beam steel formwork 14, four or more pier steel formwork 15, each piece of steel formwork is controlled by eight or more telescopic oil pressure rods 20; work layer frame 10 is provided with fixed stairs 12 to reach the uppermost platform; work layer frame 10 is connected with the passage shelf 11 or the upper and lower passage shelves 11 with an assembled staircase 13; when the working shelf unit A10a is combined with the unit B10b, the passage shelf unit A11a is combined with the unit B11b or the upper and lower shelves, align the corresponding joints The base plate 21 is fixed using bolts.
施工时:During construction:
先期作业1:墩柱施工使用的组装升降式施工平台各部件皆于工厂内预制完成,再载运至现场组装。Preliminary work 1: All components of the assembled elevating construction platform used for pier column construction are prefabricated in the factory and then transported to the site for assembly.
先期作业2:桥梁墩柱基础完成回填后,须预先浇置完成混凝土墩柱露出地面高程1公尺。Preliminary work 2: After the backfill of the bridge pier foundation is completed, the concrete pier must be pre-cast to an elevation of 1 meter above the ground.
施工步骤:Construction steps:
步骤1:于现场1公尺墩柱四周组装完成油压机升降设备支柱及各部件。Step 1: Assemble the pillars and various components of the hydraulic press lifting equipment around the 1-meter pier column on site.
步骤2:作业层架对应油压机升降支柱的位置,由墩柱两侧使用移动设备向墩柱中心之地面水平方向推入,以螺栓固结A、B单元。Step 2: The working layer frame corresponds to the position of the lifting pillar of the hydraulic machine, and is pushed in from both sides of the pier column to the horizontal direction of the ground in the center of the pier column using mobile equipment, and the A and B units are consolidated with bolts.
步骤3:以移动式吊车吊装钢模板,由上至下放入作业层架与墩柱间的空间,钢模板与伸缩油压杆对应,以螺栓固结。Step 3: Hoist the steel formwork with a mobile crane, and place it into the space between the working layer frame and the pier column from top to bottom. The steel formwork corresponds to the telescopic hydraulic rod and is fixed with bolts.
步骤4:升降支承上升至对应的钢梁位置,以插销连结。Step 4: Lift the support up to the position of the corresponding steel beam and connect it with a bolt.
步骤5:以模板伸缩控制箱操作左钢模板与右钢模板油压伸缩杆向墩柱中心方向迫紧,续操作前钢模板与后钢模板油压伸缩杆向墩柱中心方向迫紧,以螺栓固结相邻的钢模板。Step 5: Use the formwork expansion control box to operate the left steel formwork and the right steel formwork hydraulic telescopic rod to tighten toward the center of the pier column. Bolts secure adjacent steel formwork.
步骤6:混凝土浇置。Step 6: Concrete Pour.
步骤7:卸除固结钢模板的螺栓,脱模。Step 7: Remove the bolts of the consolidated steel formwork and demould.
步骤8:以模板伸缩控制箱操作前钢模板与后钢模板油压伸缩杆向墩柱中心反方向收回至定位,续操作左钢模板与右钢模板油压伸缩杆向墩柱中心反方向收回至定位,完成脱模。Step 8: Use the formwork telescopic control box to operate the front steel formwork and the rear steel formwork hydraulic telescopic rod to retract to the position opposite to the center of the pier column, and continue to operate the left steel formwork and right steel formwork hydraulic telescopic rod to retract toward the opposite direction of the pier column center To the positioning, complete demoulding.
步骤9:确认升降支承与对应之钢梁位置连结状况。Step 9: Confirm the connection status of the lifting support and the corresponding steel beam position.
步骤10:以升降控制箱操作同时作动油压升降设备系统将作业层架举升至定位高度。Step 10: Use the lifting control box to operate and simultaneously activate the hydraulic lifting equipment system to lift the working shelf to the positioning height.
步骤11:通道层架对应油压机升降支柱之位置,由墩柱两侧使用移动设备向墩柱中心之地面水平之方向推入,以插销对准上下左右连结基座螺栓孔,下降层架以螺栓固结上下层架及A、B单元。Step 11: The channel shelf corresponds to the position of the lifting pillar of the hydraulic machine. Use mobile equipment on both sides of the pier column to push it in the direction of the ground level in the center of the pier column. Align the bolt holes of the upper, lower, left, and right connecting bases with the bolts, and use the bolts to lower the shelf. Consolidate the upper and lower shelves and units A and B.
步骤12:以螺栓固结上下层连结之楼梯。Step 12: Fix the stairs connecting the upper and lower floors with bolts.
步骤13:解除升降支承与层架钢梁连结,升降支承下降至最低位置。Step 13: Release the connection between the lifting support and the steel beam of the shelf, and lower the lifting support to the lowest position.
步骤14:以栏杆封闭作业层架或通道层架之开口。Step 14: Close the opening of the working shelf or the passage shelf with railings.
步骤15:钢模板组立同步骤5。Step 15: Steel template assembly is the same as step 5.
步骤16:混凝土浇置。Step 16: Concrete Pour.
步骤17:钢模板脱模同步骤7、步骤8。Step 17: Demoulding the steel formwork is the same as step 7 and step 8.
至此桥梁墩柱需往上继续施工,进入循环施工程序,从步骤9起至步骤16为一循环施工流程。At this point, the bridge piers need to continue construction upwards and enter a cyclic construction procedure, from step 9 to step 16 is a cyclic construction process.
本实用新型以油压升降设备系统驱动作业层架及模板系统上升及下降,作业层架与通道层架皆位于地面部组拆装,可免除施工人员位于高处拆组装作业,有效缩短施工周期。The utility model uses the oil pressure lifting equipment system to drive the working shelf and the formwork system to rise and fall. Both the working shelf and the channel shelf are assembled and disassembled on the ground, which can save the construction personnel from disassembling and assembling operations at high places, and effectively shorten the construction period. .
上述说明示出并描述了本实用新型的优选实施例,如前所述,应当理解本实用新型并非局限于本文所披露的形式,不应看作是对其他实施例的排除,而可用于各种其他组合、修改和环境,并能够在本文所述实用新型构想范围内,通过上述教导或相关领域的技术或知识进行改动。而本领域人员所进行的改动和变化不脱离本实用新型的精神和范围,则都应在本实用新型所附权利要求的保护范围内。The above description shows and describes the preferred embodiments of the present utility model. As mentioned above, it should be understood that the present utility model is not limited to the forms disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various Various other combinations, modifications and environments can be made within the scope of the utility model concept described herein, through the above teachings or the technology or knowledge in the related field. However, changes and changes made by those skilled in the art do not depart from the spirit and scope of the utility model, and should all be within the protection scope of the appended claims of the utility model.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/CN2015/095773 WO2017084113A1 (en) | 2015-08-10 | 2015-11-27 | Assembled lifting construction platform for pier column construction and construction method thereof |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW104212832 | 2015-08-10 | ||
TW104212832U TWM527023U (en) | 2015-08-10 | 2015-08-10 | Lifting and descending type steel frame construction platform of bridge pillar work usage |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205171378U true CN205171378U (en) | 2016-04-20 |
Family
ID=55195401
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510793501.4A Expired - Fee Related CN105297635B (en) | 2015-08-10 | 2015-11-18 | Assembled lifting type construction platform for pier column construction and construction method thereof |
CN201520919418.2U Withdrawn - After Issue CN205171378U (en) | 2015-08-10 | 2015-11-18 | Assembling lifting type construction platform for pier column construction |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510793501.4A Expired - Fee Related CN105297635B (en) | 2015-08-10 | 2015-11-18 | Assembled lifting type construction platform for pier column construction and construction method thereof |
Country Status (3)
Country | Link |
---|---|
CN (2) | CN105297635B (en) |
TW (1) | TWM527023U (en) |
WO (1) | WO2017084113A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105297635A (en) * | 2015-08-10 | 2016-02-03 | 陈修缘 | Assembled lifting type construction platform for pier column construction and construction method thereof |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107119576A (en) * | 2017-06-28 | 2017-09-01 | 中交路桥华南工程有限公司 | Pier construction security protection platform |
CN107642048A (en) * | 2017-09-22 | 2018-01-30 | 宁夏桥多美路桥钢模板科技有限公司 | Pier stud high-altitude construction platform and high-altitude construction method |
CN109371822B (en) * | 2018-12-19 | 2020-06-23 | 中交二航局第三工程有限公司 | Linear rectangular pier maneuvering template and construction method |
CN109468963B (en) * | 2019-01-08 | 2024-07-05 | 云南省建设投资控股集团有限公司 | Hanging basket for overhead operation of bridge and overhead construction method of bridge |
CN110080235A (en) * | 2019-05-06 | 2019-08-02 | 中国一冶集团有限公司 | Foundation pit support construction slab column operation platform |
CN111236087A (en) * | 2020-03-23 | 2020-06-05 | 贵州省公路工程集团有限公司 | A sliding type high pier tied beam formwork support system and construction method |
CN111910521A (en) * | 2020-07-22 | 2020-11-10 | 中交第一航务工程局有限公司 | Supporting and dismantling method for bent cap formwork support |
CN112095486A (en) * | 2020-10-09 | 2020-12-18 | 李平 | Column climbing machine for bridge pier column construction |
CN113026565B (en) * | 2021-03-23 | 2023-06-27 | 凌振英 | Annular platform for bridge column laying construction and construction method |
CN114134813B (en) * | 2021-10-28 | 2024-03-01 | 中国建筑第六工程局有限公司 | Construction method of adjacent existing high-speed vase type pier column protection system |
CN114561873B (en) * | 2022-03-16 | 2023-08-08 | 杭州萧山交通建设管理有限公司 | Construction method of high bridge pier |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3692446A (en) * | 1971-02-11 | 1972-09-19 | Research Corp | Apparatus for forming and lifting multi-story columns in one story increments |
CN2434378Y (en) * | 2000-06-30 | 2001-06-13 | 唐玉霞 | Climbing formwork construction device for columnar building construction |
CN1354313A (en) * | 2000-11-20 | 2002-06-19 | 梁国基 | Climbing formwork for rapid building construction and corresponding methods |
US7258199B2 (en) * | 2004-05-27 | 2007-08-21 | Richard Hayes, Sr. | Modular multilevel access platform and method for erecting the same |
KR101243775B1 (en) * | 2010-01-06 | 2013-03-14 | 양준석 | Apparatus of Constructing Bridge and Method of Constructing Bridge by Using the Same |
CN201874233U (en) * | 2010-10-29 | 2011-06-22 | 中建三局建设工程股份有限公司 | Modular integral jacking steel platform formwork system with few support points at low position |
CN202519976U (en) * | 2012-01-19 | 2012-11-07 | 刘发清 | Lifting type construction formwork |
TWM527023U (en) * | 2015-08-10 | 2016-08-11 | Yuan Engineering Dev Co Ltd E | Lifting and descending type steel frame construction platform of bridge pillar work usage |
-
2015
- 2015-08-10 TW TW104212832U patent/TWM527023U/en unknown
- 2015-11-18 CN CN201510793501.4A patent/CN105297635B/en not_active Expired - Fee Related
- 2015-11-18 CN CN201520919418.2U patent/CN205171378U/en not_active Withdrawn - After Issue
- 2015-11-27 WO PCT/CN2015/095773 patent/WO2017084113A1/en active Application Filing
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105297635A (en) * | 2015-08-10 | 2016-02-03 | 陈修缘 | Assembled lifting type construction platform for pier column construction and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
TWM527023U (en) | 2016-08-11 |
WO2017084113A1 (en) | 2017-05-26 |
CN105297635A (en) | 2016-02-03 |
CN105297635B (en) | 2017-05-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205171378U (en) | Assembling lifting type construction platform for pier column construction | |
CN110230393B (en) | Large concrete tank dome climbing high formwork support system and installation method | |
CN205742991U (en) | A kind of truss-like hydraulic pressure integral steel platform jumping formwork | |
CN104695337B (en) | Self-lifting sliding and turnover construction system and construction method | |
CN106437130A (en) | Inner roof external climbing type formwork construction platform for super high-rise building construction | |
CN103741947B (en) | Tube-frame-supporting type hydraulic climbing integral steel platform formwork truss layer construction method | |
CN103758341A (en) | Steel column drum rack support type hydraulic lifting overall steel platform cross truss layer construction method | |
CN106759845A (en) | A kind of construction method of Steel corridor | |
CN108331336A (en) | The integrated lifting steel plateform system and its construction method of floor synchronous construction | |
CN102296808A (en) | Template hoisting system for building | |
CN113403946B (en) | Three leaf round pin hinge formula bridge column mound creeping formwork devices | |
CN114775806B (en) | Wall body and upper concrete structure construction platform utilizing jacking net rack and method thereof | |
JP3074765U (en) | Pillar building construction system equipment | |
CN205839594U (en) | Over-and-under type construction system that bridge superstructure construction used | |
US20130263549A1 (en) | Safety screen system for steel erection work | |
CN204386152U (en) | The sliding formwork system of large-diameter cylinder body structure | |
KR20120122800A (en) | Apparatus for forming underground dome structure by oil pressure type lift and constructing method using the same | |
CN106555472B (en) | Concave-shaped floor forming device's gluey formula of covering structure of zooming | |
CN205224045U (en) | Examine and repair gate slot second phase concrete construction device | |
CN108331326A (en) | Monoblock type mould bases and its construction method for Super High fission conjoined composite structure | |
JP3531111B2 (en) | Apparatus and method for constructing tower-like structure | |
CN111997382A (en) | Telescopic steel structure sliding mechanism and sliding method | |
KR20120122790A (en) | Apparatus for forming underground dome structure by oil pressure type lift and constructing method using the same | |
CN208152583U (en) | A kind of high-building construction ancillary equipment | |
JP2011241584A (en) | Multistage demolition method of building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20160420 Effective date of abandoning: 20170503 |
|
AV01 | Patent right actively abandoned |
Granted publication date: 20160420 Effective date of abandoning: 20170503 |