CN205166419U - Steel pipe bracket - Google Patents
Steel pipe bracket Download PDFInfo
- Publication number
- CN205166419U CN205166419U CN201520882069.1U CN201520882069U CN205166419U CN 205166419 U CN205166419 U CN 205166419U CN 201520882069 U CN201520882069 U CN 201520882069U CN 205166419 U CN205166419 U CN 205166419U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- base
- regulating part
- picking
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 36
- 239000010959 steel Substances 0.000 title claims abstract description 36
- 230000001105 regulatory effect Effects 0.000 claims abstract description 20
- 230000002146 bilateral effect Effects 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 3
- 230000002950 deficient Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 238000003754 machining Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model provides a steel pipe bracket, hold up device and steel pipe including bottom plate, two, two hold up device bilateral symmetry and arrange on the bottom plate, with bottom plate sliding connection, the steel pipe is located in the middle of bottom plate top, two hold up the device, with two hold up the device and be connected, it includes base, regulating part and holder to hold up the device, base lower part and bottom plate sliding connection, it has the blind hole to open in the vertical direction in base upper portion, and it has the through -hole to open on the horizontal direction, the regulating part is located the top of base, with base sliding connection, the holder is located the regulating part top, with regulating part sliding connection. Adopt above -mentioned technical scheme, stretch into the steel pipe with the roller in, outside the steel pipe was placed in to the layer board, the steel pipe was stepped up between layer board and roller, had avoided adding diameter runout in man -hour, guaranteed processingquality, reduced the rejection rate.
Description
Technical field
The utility model relates to steel pipe mechanical processing technique field, particularly relates to a kind of Frame for supporting parallel pipes.
Background technology
In existing technology, when machining is carried out to steel pipe, need to arrange auxiliary support apparatus, but existing auxiliary support apparatus can not stop the circular runout of steel pipe, greatly have impact on the processing effect of steel pipe, such as during the processing of steel pipe mantle fiber, steel pipe transfer can cause random tooth, and tooth form is defective, coordinates phenomenons such as going wrong, easily there is waste product in processing, affects service life.In addition, the existing bracing or strutting arrangement scope of application is little, can not meet the secondary process of multiple diameter steel pipe.
Summary of the invention
For solving the problems of the technologies described above, the technical solution adopted in the utility model is: provide a kind of structure simple, easy to use, can limit steel pipe circular runout and be applicable to the Frame for supporting parallel pipes of plurality of specifications.
The technical solution adopted in the utility model is: relate to a kind of Frame for supporting parallel pipes and comprise base plate, two picking-up devices and steel pipe; Described two picking-up devices are symmetrically arranged on described base plate, are slidably connected with described base plate; Described steel pipe is positioned at above described base plate, in the middle of described two picking-up devices, is connected with described two picking-up devices; Described picking-up device comprises base, regulating part and holder; Described base bottom and described base plate are slidably connected, and described base Upper vertical direction has blind hole, horizontal direction has through hole; Described regulating part is positioned at the top of described base, is connected with described base sliding; Described holder is positioned at above described regulating part, is slidably connected with described regulating part.
Further, described regulating part comprises adjusting rod and supporting plate; Described supporting plate is in tilted layout, and described adjusting rod and described supporting plate lower end are connected; Described adjusting rod has the first slotted eye, described supporting plate has circular hole
Further, described adjusting rod lower end is placed in described blind hole, is connected with described first slotted eye by described through hole with described base.
Further, described holder comprises connecting rod and roller; Described roller is connected with described connecting rod is vertical; Described connecting rod has the second slotted eye, be connected with described supporting plate with described circular hole by described second slotted eye.
Further, described roller is placed in described steel pipe, and described supporting plate is placed in outside described steel pipe, and described connecting rod is placed in outside described Steel pipe end surface.
Further, described base plate has multiple uniform slideway.
The advantage that the utility model has and good effect are: stretched into by roller in steel pipe, and supporting plate is placed in outside steel pipe, and steel pipe is stepped up between supporting plate and roller, avoid and add circular runout in man-hour, ensure crudy, reduce percent defective.
Accompanying drawing explanation
Fig. 1 is a kind of general illustration of Frame for supporting parallel pipes
Fig. 2 is a kind of schematic diagram of Frame for supporting parallel pipes picking-up device
Fig. 3 is a kind of top view of Frame for supporting parallel pipes
In figure:
1-base plate, 101-slideway; 2-picking-up device, 201-base, 2011-blind hole, 2012-through hole, 202-regulating part, 2021-adjusting rod, 2022-supporting plate, 2023-first slotted eye, 2024-circular hole, 203-holder, 2031-connecting rod, 2032-roller, 2033-second slotted eye; 3-steel pipe.
Detailed description of the invention
As shown in Figure 1, a kind of Frame for supporting parallel pipes comprises base plate 1, two picking-up devices 2 and steel pipe 3; Base plate 1 has four uniform slideways 101; Two picking-up devices 2 are symmetrically arranged on base plate 1, are slidably connected with base plate 1; Steel pipe 3 is positioned at above base plate, in the middle of two picking-up devices 2, is connected with two picking-up devices 2.
As shown in Figure 2, picking-up device 2 comprises base 201, regulating part 202 and holder 203; Base 201 bottom and base plate 1 are slidably connected; Regulating part 202 is positioned at the top of base 201, is slidably connected with base 201; Holder 203 is positioned at above regulating part 202, is slidably connected with regulating part 202.Direction has blind hole 2011 to base 201 Upper vertical, horizontal direction has through hole 2012.Regulating part 202 comprises adjusting rod 2021 and supporting plate 2022; Supporting plate 2022 is in tilted layout, and adjusting rod 2021 and supporting plate 2022 lower end are connected; Adjusting rod 2021 has the first slotted eye 2023, supporting plate 2022 has circular hole 2024.Adjusting rod 2021 lower end is placed in blind hole 2011, is connected with the first slotted eye 2023 by through hole 2012 with base 201.Holder 203 comprises connecting rod 2031 and roller 2032; Roller 2032 is connected with connecting rod 2031 is vertical; Connecting rod 2031 has the second slotted eye 2033, be connected with supporting plate 2022 with circular hole 2024 by the second slotted eye 2033.
Roller 2032 is placed in steel pipe 3, and supporting plate 2022 is placed in outside steel pipe 3, and connecting rod 2031 is placed in outside steel pipe 3 end face.
The course of work of the present utility model is: select two slideways 101 according to the specification of steel pipe 3, two picking-up devices 2 are placed in respectively the relevant position of two slideways 101, regulate regulating part 202 and the position of base 201, fix through through hole 2012 and the first slotted eye 2023 with bolt; Pipe is placed on two supporting plates 2022; Two rollers 2023 are placed in steel pipe 3, by the second slotted eye 2033 and circular hole 2024, connecting rod 2031 are fixed with supporting plate 2022 with bolt.
Above embodiment of the present utility model has been described in detail, but described content being only preferred embodiment of the present utility model, can not being considered to for limiting practical range of the present invention.All equalizations done according to the utility model scope change and improve, and all should still belong within this patent covering scope.
Claims (6)
1. a Frame for supporting parallel pipes, is characterized in that: comprise base plate (1), two picking-up devices (2) and steel pipe (3); Described two picking-up devices (2) are symmetrically arranged on described base plate (1), are slidably connected with described base plate (1); Described steel pipe (3) is positioned at above described base plate, in the middle of described two picking-up devices (2), is connected with described two picking-up devices (2); Described picking-up device (2) comprises base (201), regulating part (202) and holder (203); Described base (201) bottom and described base plate (1) are slidably connected; Described regulating part (202) is positioned at the top of described base (201), is slidably connected with described base (201); Described holder (203) is positioned at described regulating part (202) top, is slidably connected with described regulating part (202).
2. a kind of Frame for supporting parallel pipes according to claim 1, is characterized in that: described regulating part (202) comprises adjusting rod (2021) and supporting plate (2022); Described supporting plate (2022) is in tilted layout, and described adjusting rod (2021) and described supporting plate (2022) lower end are connected.
3. a kind of Frame for supporting parallel pipes according to claim 2, is characterized in that: described adjusting rod (2021) has the first slotted eye (2023); Described base (201) Upper vertical direction has blind hole (2011), horizontal direction has through hole (2012); Described adjusting rod (2021) lower end is placed in described blind hole (2011), is connected with described first slotted eye (2023) by described through hole (2012) with described base (201).
4. a kind of Frame for supporting parallel pipes according to claim 2, is characterized in that: described holder (203) comprises connecting rod (2031) and roller (2032); Described roller (2032) is connected with described connecting rod (2031) is vertical; Described connecting rod (2031) has the second slotted eye (2033), described supporting plate (2022) has circular hole (2024), described connecting rod (2031) is connected with described supporting plate (2022) with described circular hole (2024) by described second slotted eye (2033).
5. a kind of Frame for supporting parallel pipes according to claim 4, it is characterized in that: described roller (2032) is placed in described steel pipe (3), described supporting plate (2022) is placed in described steel pipe (3) outward, and described connecting rod (2031) is placed in outside described steel pipe (3) end face.
6. a kind of Frame for supporting parallel pipes according to claim 1, is characterized in that: described base plate (1) has multiple uniform slideway (101).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520882069.1U CN205166419U (en) | 2015-11-06 | 2015-11-06 | Steel pipe bracket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520882069.1U CN205166419U (en) | 2015-11-06 | 2015-11-06 | Steel pipe bracket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205166419U true CN205166419U (en) | 2016-04-20 |
Family
ID=55730452
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520882069.1U Expired - Fee Related CN205166419U (en) | 2015-11-06 | 2015-11-06 | Steel pipe bracket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205166419U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111717784A (en) * | 2020-07-03 | 2020-09-29 | 中交一航局第三工程有限公司 | A kind of large-diameter steel bar integral fine adjustment installation hanger and its application |
CN113319761A (en) * | 2021-06-02 | 2021-08-31 | 安徽信息工程学院 | Pneumatic fixing device for vehicle assembly |
-
2015
- 2015-11-06 CN CN201520882069.1U patent/CN205166419U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111717784A (en) * | 2020-07-03 | 2020-09-29 | 中交一航局第三工程有限公司 | A kind of large-diameter steel bar integral fine adjustment installation hanger and its application |
CN113319761A (en) * | 2021-06-02 | 2021-08-31 | 安徽信息工程学院 | Pneumatic fixing device for vehicle assembly |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204412824U (en) | A kind of stainless steel square tube machine straightening device | |
CN205166419U (en) | Steel pipe bracket | |
CN104108607A (en) | Glass rack | |
CN206868853U (en) | A kind of squeeze roller group of convenient regulation | |
CN204747881U (en) | Be used for large -scale oil tank welded positioner | |
CN105290828A (en) | Steel pipe supporting device | |
CN204262821U (en) | A kind of Digit Control Machine Tool three station clamps | |
CN203484677U (en) | Supporting device for engraved roller shaft head | |
CN203558439U (en) | Conveyor belt for bottle bodies | |
CN203237471U (en) | Paper laying device for flat glass | |
CN207981899U (en) | A kind of full-automatic bidirectional high-accuracy straightening machine | |
CN105173578A (en) | Crankshaft feeding frame | |
CN202324631U (en) | Pipeline arranging frame for civil engineering | |
CN203237575U (en) | Backrest frame for glass transportation | |
CN206550132U (en) | A kind of stainless steel tube is molded adjusting means | |
CN104400491A (en) | Three-workstation clamp for numerical control machine tool | |
CN204078890U (en) | Glass stand | |
CN204262844U (en) | A kind of Digit Control Machine Tool air-actuated jaw | |
CN202330940U (en) | Support device used on lamplighter | |
CN202255766U (en) | Simple static balance bracket for static balance test of transmission rollers in finishing zone and pre-finishing zone of seamless steel tube binding line | |
CN204262212U (en) | Origin positioning device of CNC turret punch press | |
CN104983334A (en) | Washing tool arrangement adjusting support | |
CN203900985U (en) | Supporting device for machining of pipe fittings | |
CN203862739U (en) | Finishing tube straightening machine | |
CN204173330U (en) | A kind of bracing frame of pipe lifting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160420 Termination date: 20171106 |