[go: up one dir, main page]

CN204676675U - A kind of power plant overflow-type drainage system - Google Patents

A kind of power plant overflow-type drainage system Download PDF

Info

Publication number
CN204676675U
CN204676675U CN201520382358.5U CN201520382358U CN204676675U CN 204676675 U CN204676675 U CN 204676675U CN 201520382358 U CN201520382358 U CN 201520382358U CN 204676675 U CN204676675 U CN 204676675U
Authority
CN
China
Prior art keywords
power plant
overfall
coal
sedimentation pond
drainage system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520382358.5U
Other languages
Chinese (zh)
Inventor
蒋方帅
郭劲松
周正一
李焱
谷秋成
李楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huadian Engineering Group Co Ltd
Original Assignee
China Huadian Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huadian Engineering Group Co Ltd filed Critical China Huadian Engineering Group Co Ltd
Priority to CN201520382358.5U priority Critical patent/CN204676675U/en
Application granted granted Critical
Publication of CN204676675U publication Critical patent/CN204676675U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a kind of power plant overflow-type drainage system, comprise coal yard, coal water sedimentation pond and ash disposal area, coal water sedimentation pond is set between coal yard and ash disposal area, the side in coal water sedimentation pond is provided with the first overfall, the periphery of ash disposal area arranges grey dam, and the side on grey dam is provided with the second overfall.The utility model eliminates buck drainage pump in traditional water-drawing type drainage system and mole, reduces construction cost and the running cost of power plant greatly; By arranging the first overfall in the side in coal water sedimentation pond and arranging the second overfall in the side on grey dam, long-pending rainwater in power plant is enable to enter sea in time; By arranging the laying area of do not seep water grey dam and expansion geomembrane, can effectively prevent seawater from infiltrating.

Description

A kind of power plant overflow-type drainage system
Technical field
The utility model relates to a kind of drainage system, particularly a kind of power plant overflow-type drainage system.
Background technology
In power plant, the draining of coal yard and grey field is the problem of a more complicated, especially for all the more so the power plant being seated in the very large area of amount of precipitation.At traditional power plant's drainage system many employings pumping for water pump formula drainage system, this water-drawing type drainage system needs to build buck draining pump house and mole at coal yard and ash disposal area periphery, this water-drawing type drainage system not only construction cost and running cost huge, and be located at the power plant in the very large area of amount of precipitation, once buck draining pump house has a power failure, drainage pump is out of service, and rainwater just cannot be discharged, and buck draining pump house just has the risk be submerged.
Utility model content
The purpose of this utility model is, provides a kind of power plant overflow-type drainage system, this drainage system not only construction cost and running cost little, and long-pending rainwater in power plant can be discharged in time.
The technical solution of the utility model: a kind of power plant overflow-type drainage system, comprise coal yard, coal water sedimentation pond and ash disposal area, coal water sedimentation pond is provided with between coal yard and ash disposal area, the side in coal water sedimentation pond is provided with the first overfall, the periphery of ash disposal area arranges grey dam, and the side on grey dam is provided with the second overfall.First overfall and the second overfall are all located at the side in sea, face, so that the ponding of discharging can flow into the sea in time.
Aforesaid this power plant overflow-type drainage system, the bottom on described ash disposal area and grey dam is all equipped with geomembrane.Geomembrane infiltrates ash disposal area in order to prevent seawater.
Aforesaid this power plant overflow-type drainage system, is provided with drainage pipe between described coal yard and coal water sedimentation pond.In coal yard, the long-pending rainwater of institute flows into the clarification of coal water sedimentation pond by drainage pipe.
Compared with prior art, the utility model eliminates buck drainage pump in traditional water-drawing type drainage system and mole, reduces construction cost and the running cost of power plant greatly; By arranging the first overfall in the side in coal water sedimentation pond and arranging the second overfall in the side on grey dam, long-pending rainwater in power plant is enable to enter sea in time; By arranging the laying area of do not seep water grey dam and expansion geomembrane, can effectively prevent seawater from infiltrating.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Being labeled as in accompanying drawing: 1-coal yard, 2-coal water sedimentation pond, 3-ash disposal area, 4-ash dam, 5-first overfall, 6-second overfall, 7-drainage pipe.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further described.
Embodiment 1 of the present utility model: a kind of power plant overflow-type drainage system, comprise coal yard 1, coal water sedimentation pond 2 and ash disposal area 3, coal water sedimentation pond 2 is set between coal yard 1 and ash disposal area 3, the side in coal water sedimentation pond 2 is provided with the first overfall 5, the periphery of ash disposal area 3 arranges grey dam 4, and the side on grey dam 4 is provided with the second overfall 6.First overfall 5 and the second overfall 6 are all located at the side in sea, face, so that the ponding of discharging can flow into the sea in time.The bottom on ash disposal area 3 and grey dam 4 is all equipped with geomembrane, and geomembrane infiltrates ash disposal area 3 in order to prevent seawater.Arrange drainage pipe 7 between coal yard 1 and coal water sedimentation pond 2, the interior long-pending rainwater of coal yard 1 flows into coal water sedimentation pond 2 by drainage pipe 7 and clarifies.Ash dam 4 adopts the grey dam that do not seep water, and infiltrates ash disposal area 3 to prevent seawater.
Embodiment 2 of the present utility model: a kind of power plant overflow-type drainage system, comprise coal yard 1, coal water sedimentation pond 2 and ash disposal area 3, coal water sedimentation pond 2 is set between coal yard 1 and ash disposal area 3, the side in coal water sedimentation pond 2 is provided with the first overfall 5, the periphery of ash disposal area 3 arranges grey dam 4, and the side on grey dam 4 is provided with the second overfall 6.First overfall 5 and the second overfall 6 are all located at the side in sea, face, so that the ponding of discharging can flow into the sea in time.The bottom on ash disposal area 3 and grey dam 4 is all equipped with HDPE geomembrane.HDPE geomembrane has very strong tensile strength and elongation at break in order to prevent seawater from infiltrating ash disposal area 3, HDPE geomembrane, can use under various different severe geology and weather conditions.Arrange drainage pipe 7 between coal yard 1 and coal water sedimentation pond 2, the interior long-pending rainwater of coal yard 1 flows into coal water sedimentation pond 2 by drainage pipe 7 and clarifies.Ash dam 4 adopts the grey dam that do not seep water, and infiltrates ash disposal area 3 to prevent seawater.
The course of work of the present utility model: coal yard 1 amass rainwater and flow into coal water sedimentation pond 2 by drainage pipe 7, converge with the ponding in coal water sedimentation pond 2, after the clarification of coal water sedimentation pond 2, ponding after clarification directly enters marine greatly by the first overfall 5, ash disposal area 3 amass second overfall 6 of rainwater on grey dam 4 and directly enter sea.

Claims (4)

1. power plant's overflow-type drainage system, comprise coal yard (1), coal water sedimentation pond (2) and ash disposal area (3), it is characterized in that: between coal yard (1) and ash disposal area (3), be provided with coal water sedimentation pond (2), the side in coal water sedimentation pond (2) is provided with the first overfall (5), the outer of ash disposal area (3) is arranged with grey dam (4), and the side of grey dam (4) is provided with the second overfall (6).
2. a kind of power plant according to claim 1 overflow-type drainage system, is characterized in that: the bottom of described ash disposal area (3) and grey dam (4) is all equipped with geomembrane.
3. a kind of power plant according to claim 1 overflow-type drainage system, is characterized in that: be provided with drainage pipe (7) between described coal yard (1) and coal water sedimentation pond (2).
4. a kind of power plant according to claim 1 overflow-type drainage system, is characterized in that: described grey dam (4) is not for seeping water grey dam.
CN201520382358.5U 2015-06-04 2015-06-04 A kind of power plant overflow-type drainage system Expired - Fee Related CN204676675U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520382358.5U CN204676675U (en) 2015-06-04 2015-06-04 A kind of power plant overflow-type drainage system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520382358.5U CN204676675U (en) 2015-06-04 2015-06-04 A kind of power plant overflow-type drainage system

Publications (1)

Publication Number Publication Date
CN204676675U true CN204676675U (en) 2015-09-30

Family

ID=54176380

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520382358.5U Expired - Fee Related CN204676675U (en) 2015-06-04 2015-06-04 A kind of power plant overflow-type drainage system

Country Status (1)

Country Link
CN (1) CN204676675U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107129073A (en) * 2017-06-23 2017-09-05 中国华电科工集团有限公司 The grey water treatment system and technique of a kind of permeation filtration bonus point batch throttling dosing

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107129073A (en) * 2017-06-23 2017-09-05 中国华电科工集团有限公司 The grey water treatment system and technique of a kind of permeation filtration bonus point batch throttling dosing
CN107129073B (en) * 2017-06-23 2023-12-08 中国华电科工集团有限公司 Grey water treatment system and process with osmotic filtration and batch throttling dosing

Similar Documents

Publication Publication Date Title
CN204690591U (en) A kind of bridge drainage system
CN101285397A (en) Submarine tunnel transverse water collecting tank
CN104782447A (en) Agricultural land initial stage runoff collection irrigation system and method thereof
CN204676675U (en) A kind of power plant overflow-type drainage system
CN206368389U (en) One kind backwash and sewage sucking system
CN203173911U (en) Precipitation device
CN105442668A (en) Roof rainwater recycling system
CN203114340U (en) Drainage device for constructing inclined shaft
CN207277486U (en) A kind of mill tailings storehouse is met an urgent need self-draining arrangement
CN204059538U (en) Underground garage water-tight device
CN206143737U (en) Novel return system in tailing storehouse
RU74927U1 (en) COMPLEX OF HYDROTECHNICAL STRUCTURES OF SHIPPING CHANNEL
CN201599226U (en) Vertical rain-proof cover structure of axial-flow pump
CN203961002U (en) Locomotive inspection and repair trench drainage system
CN203546817U (en) Modular floating dock pumping station
CN204023485U (en) A kind of landscape water recycle unit
CN104131602A (en) Water supply system for construction sites
CN203383327U (en) Vertical-type glass steel integrated pump station
CN208718044U (en) A kind of Novel inspection well
CN202850224U (en) Waterproof plate
CN202298863U (en) Pipe network rainwater collecting cellar
CN201578929U (en) Device for recycling back washing water in siphon filter tank
CN206829227U (en) A kind of relay type river arranges silt system
CN206873476U (en) A kind of construction Precipitation Structure
CN205223996U (en) Pontoon formula flexible hose is from supplying water and drainage device in tailing storehouse

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 100160 Beijing, Fengtai District Automobile Museum Road, No. 6, Ying Kun century A block, floor 11

Patentee after: CHINA HUADIAN ENGINEERING CO., LTD.

Address before: 100160 Beijing, Fengtai District Automobile Museum Road, No. 6, Ying Kun century A block, floor 11

Patentee before: China Huadian Engineering (Group) Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150930

Termination date: 20210604