CN204662950U - High tower hydraulic climbing scaffold main working platform installation suspension - Google Patents
High tower hydraulic climbing scaffold main working platform installation suspension Download PDFInfo
- Publication number
- CN204662950U CN204662950U CN201520304693.3U CN201520304693U CN204662950U CN 204662950 U CN204662950 U CN 204662950U CN 201520304693 U CN201520304693 U CN 201520304693U CN 204662950 U CN204662950 U CN 204662950U
- Authority
- CN
- China
- Prior art keywords
- high tower
- hydraulic climbing
- pin
- hook
- embedded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Movable Scaffolding (AREA)
Abstract
High tower hydraulic climbing scaffold main working platform installation suspension; It is constructed as follows: embedded quit (1), hook (2), hook fixation kit (3), suspension pin (4); Wherein: embedded quit (1) is provided with and respectively carries two junction plates (12) arranged in pairs that is hung pin installing hole (11), two the two levels of suspension pin installing hole (11) on two junction plates (12) are coaxially arranged; Hang pin (4) and hang pin installing hole (11) through two simultaneously; Hook (2) is fixed on high tower hydraulic climbing scaffold (8) to be hung by hook fixation kit (3), hook (2) is provided with the semi-circular recesses (21) of opening downwards; Semi-circular recesses (21) is articulated in and hangs on pin (4).The utility model has the advantages that: be convenient to industrialization of construction industry construction, in-site installation is very convenient, fixing reliable, effective; It has expected comparatively huge economic worth and social value.
Description
Technical field
The utility model relates to structure design and the applied technical field of the suspension structure of high tower hydraulic climbing scaffold, specifically provides a kind of high tower hydraulic climbing scaffold main working platform installation suspension.
Background technology
In prior art, high tower hydraulic climbing scaffold is normally designed by professional, adopt standard configurations, (form surfacing and climbing frame platform can be designed to be applicable to difform king-post and gradient can to adapt to the actual needs of various engineering, when Sarasota cross sectional shape changes, only need do form surfacing and platform and adjust on a small quantity).High tower hydraulic climbing scaffold can be made up of multilayer platform.Multilayer operation platform is respectively linked with in each direction of pier shaft or high tower, constructor independently can carry out various constructing operation (as assembling reinforcement, installation form, modification tower body etc.) on every layer of platform in each direction, both the engineering time had been saved, also for high tower construction provides enough construction spaces.
The main working platform installation of existing high tower hydraulic climbing scaffold is generally bolt by suspension and connects, rivets, ties up the forms such as fixing, but its technique effect is comparatively limited, and during construction, human cost is high.People urgently wish to obtain the excellent high tower hydraulic climbing scaffold main working platform installation suspension of a kind of technique effect.
Utility model content
Order of the present utility model is to provide the excellent high tower hydraulic climbing scaffold main working platform installation suspension of a kind of technique effect.
High tower hydraulic climbing scaffold described in the utility model main working platform installation suspension; Stiff skeleton 9 is fixed on for being hung by high tower hydraulic climbing scaffold 8; It is characterized in that: being constructed as follows of high tower hydraulic climbing scaffold main working platform installation suspension: embeddedly quit 1, hook 2, hook fixation kit 3, hang pin 4; Wherein: embedded quitting 1 is fixed on stiff skeleton 9, embedded quitting to be provided with two of respectively carrying on two junction plates arranged in pairs, 12, two junction plates 12 hanging pin installing hole 11 on 1 to hang pin both installing holes 11 levels coaxially arranged; Hang pin 4 and hang pin installing hole 11 through two simultaneously; Hook 2 is fixed on high tower hydraulic climbing scaffold 8 to be hung by hook fixation kit 3, hook 2 is provided with the semi-circular recesses 21 of opening downwards; The semi-circular recesses 21 that in hook 2, Open Side Down is articulated in and hangs on pin 4.
Described high tower hydraulic climbing scaffold main working platform installation suspension, is characterized in that: embedded quitting 1 uses in pairs, and often couple embedded two of quitting in 1 are embedded to quit and 1 to be arranged in parallel in the horizontal direction; Each embedded quitting on 1 is provided with a junction plate 12, each junction plate 12 is provided with both suspension pin installing holes 11 level hung on the embedded respective junction plate 12 of quitting on 1 of pin installing hole 11, two coaxially arranged.
Described high tower hydraulic climbing scaffold main working platform installation suspension, it is characterized in that: in described high tower hydraulic climbing scaffold main working platform installation suspension, be also provided with safety pin 5, described high tower hydraulic climbing scaffold main working platform installation suspension also meets following requirement: junction plate 12 is also provided with safety pin mounting hole 13, and safety pin 5 is arranged in the safety pin mounting hole 13 on two junction plates 12 of horizontal pair layout.
The utility model has the advantages that: be convenient to industrialization of construction industry construction, in-site installation is very convenient, fixing reliable, effective; It has expected comparatively huge economic worth and social value.
Accompanying drawing explanation
Fig. 1 is high tower hydraulic climbing scaffold main working platform installation suspension principle of compositionality schematic diagram.
Detailed description of the invention
Embodiment 1
High tower hydraulic climbing scaffold main working platform installation suspension; Stiff skeleton 9 is fixed on for being hung by high tower hydraulic climbing scaffold 8; Being constructed as follows of high tower hydraulic climbing scaffold main working platform installation suspension: embeddedly quit 1, hook 2, hook fixation kit 3, hang pin 4; Wherein: embedded quitting 1 is fixed on stiff skeleton 9, embedded quitting to be provided with two of respectively carrying on two junction plates arranged in pairs, 12, two junction plates 12 hanging pin installing hole 11 on 1 to hang pin both installing holes 11 levels coaxially arranged; Hang pin 4 and hang pin installing hole 11 through two simultaneously; Hook 2 is fixed on high tower hydraulic climbing scaffold 8 to be hung by hook fixation kit 3, hook 2 is provided with the semi-circular recesses 21 of opening downwards; The semi-circular recesses 21 that in hook 2, Open Side Down is articulated in and hangs on pin 4, thus high tower hydraulic climbing scaffold 8 suspension is fixed on stiff skeleton 9.
In described high tower hydraulic climbing scaffold main working platform installation suspension, embedded quitting 1 uses in pairs, and often couple embedded two of quitting in 1 are embedded to quit and 1 to be arranged in parallel in the horizontal direction; Each embedded quitting on 1 is provided with a junction plate 12, each junction plate 12 is provided with both suspension pin installing holes 11 level hung on the embedded respective junction plate 12 of quitting on 1 of pin installing hole 11, two coaxially arranged.
Safety pin 5 is also provided with in described high tower hydraulic climbing scaffold main working platform installation suspension, described high tower hydraulic climbing scaffold main working platform installation suspension also meets following requirement: junction plate 12 is also provided with safety pin mounting hole 13, and safety pin 5 is arranged in the safety pin mounting hole 13 on two junction plates 12 of horizontal pair layout.
The advantage of the present embodiment is: be convenient to industrialization of construction industry construction, in-site installation is very convenient, fixing reliable, effective; It has expected comparatively huge economic worth and social value.
Claims (3)
1. high tower hydraulic climbing scaffold main working platform installation suspension; Stiff skeleton (9) is fixed on for being hung by high tower hydraulic climbing scaffold (8); It is characterized in that: being constructed as follows of high tower hydraulic climbing scaffold main working platform installation suspension: embedded quit (1), hook (2), hook fixation kit (3), suspension pin (4); Wherein: embedded quit (1) is fixed on stiff skeleton (9), embedded quit (1) is provided with and respectively carries two junction plates (12) arranged in pairs that is hung pin installing hole (11), two the two levels of suspension pin installing hole (11) on two junction plates (12) are coaxially arranged; Hang pin (4) and hang pin installing hole (11) through two simultaneously; Hook (2) is fixed on high tower hydraulic climbing scaffold (8) to be hung by hook fixation kit (3), hook (2) is provided with the semi-circular recesses (21) of opening downwards; Semi-circular recesses (21) in hook (2) is articulated in and hangs on pin (4).
2. according to high tower hydraulic climbing scaffold main working platform installation suspension described in claim 1, it is characterized in that: embedded quit (1) uses in pairs, often pair of embedded two of quitting in (1) embedded quit (1) is arranged in parallel in the horizontal direction; Each embedded quit (1) is provided with a junction plate (12), each junction plate (12) is provided with one and hangs pin installing hole (11), the two level of the suspension pin installing hole (11) on two embedded respective junction plates (12) of quitting on (1) is coaxially arranged.
3. according to high tower hydraulic climbing scaffold main working platform installation suspension described in claim 1 or 2, it is characterized in that: in described high tower hydraulic climbing scaffold main working platform installation suspension, be also provided with safety pin (5), described high tower hydraulic climbing scaffold main working platform installation suspension also meets following requirement: junction plate (12) is also provided with safety pin mounting hole (13), and safety pin (5) is arranged in the safety pin mounting hole (13) on two junction plates (12) of horizontal pair layout.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520304693.3U CN204662950U (en) | 2015-05-12 | 2015-05-12 | High tower hydraulic climbing scaffold main working platform installation suspension |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520304693.3U CN204662950U (en) | 2015-05-12 | 2015-05-12 | High tower hydraulic climbing scaffold main working platform installation suspension |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204662950U true CN204662950U (en) | 2015-09-23 |
Family
ID=54133345
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520304693.3U Expired - Fee Related CN204662950U (en) | 2015-05-12 | 2015-05-12 | High tower hydraulic climbing scaffold main working platform installation suspension |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204662950U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108166752A (en) * | 2017-11-23 | 2018-06-15 | 中国建筑股份有限公司 | Scalable supporting body and its application method |
-
2015
- 2015-05-12 CN CN201520304693.3U patent/CN204662950U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108166752A (en) * | 2017-11-23 | 2018-06-15 | 中国建筑股份有限公司 | Scalable supporting body and its application method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104088227A (en) | Rear pull rod | |
CN204662951U (en) | High tower hydraulic climbing scaffold | |
CN104099877A (en) | Connecting bar | |
CN204662950U (en) | High tower hydraulic climbing scaffold main working platform installation suspension | |
CN206308702U (en) | A kind of portable basis of derrick crane | |
CN205653104U (en) | Movable crane for installing unit plate curtain wall | |
CN204342306U (en) | A kind of novel roofing crane foundation | |
CN204529248U (en) | Vehicle-mounted mobile platform is installed in gobo lifting | |
CN103266572B (en) | A kind of Multifunctional construction platform for straining beam cast-in-place construction between double width bridge | |
CN203096620U (en) | Steel pipe arch rib operation platform | |
CN202689588U (en) | Safety rope cantilever support | |
CN205087776U (en) | Can dismantle otic placode device | |
CN203654698U (en) | Attached lifting scaffold structure provided with double guide rails | |
CN203684394U (en) | Supporting device for framework structure | |
CN202865743U (en) | Dragline device of large-scale bridge girder | |
CN205530326U (en) | Tower crane landing leg anchor | |
CN204251217U (en) | A kind of formwork hoisting strut bar | |
CN204703537U (en) | To build a wall servicing unit | |
CN203320976U (en) | Suspension device for safety plain net for construction of industrial factory buildings | |
CN204455846U (en) | The hoisting appliance of the prefabricated pier of a kind of large-tonnage | |
CN204728722U (en) | Construction formwork lifting device | |
CN204875557U (en) | Rhombus false work | |
CN205500545U (en) | Hoisting device for tower crane | |
CN204000615U (en) | A kind of lifting climbing frame | |
CN205171385U (en) | Rhombus false work for bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150923 Termination date: 20200512 |