CN204381021U - A kind of coal gasification wastewater pipe line cleaning device - Google Patents
A kind of coal gasification wastewater pipe line cleaning device Download PDFInfo
- Publication number
- CN204381021U CN204381021U CN201420858492.3U CN201420858492U CN204381021U CN 204381021 U CN204381021 U CN 204381021U CN 201420858492 U CN201420858492 U CN 201420858492U CN 204381021 U CN204381021 U CN 204381021U
- Authority
- CN
- China
- Prior art keywords
- receiving station
- station
- pipe
- coal gasification
- way valve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000004140 cleaning Methods 0.000 title claims abstract description 36
- 239000003245 coal Substances 0.000 title claims abstract description 19
- 238000002309 gasification Methods 0.000 title claims abstract description 19
- 239000002351 wastewater Substances 0.000 title claims 4
- 239000010865 sewage Substances 0.000 abstract description 28
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 11
- 239000010797 grey water Substances 0.000 description 9
- 238000000034 method Methods 0.000 description 6
- 241000282887 Suidae Species 0.000 description 5
- 238000005554 pickling Methods 0.000 description 3
- 239000000126 substance Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000004065 wastewater treatment Methods 0.000 description 2
- 239000000654 additive Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000001704 evaporation Methods 0.000 description 1
- 230000008020 evaporation Effects 0.000 description 1
- 150000002500 ions Chemical class 0.000 description 1
- 238000004062 sedimentation Methods 0.000 description 1
- 238000003786 synthesis reaction Methods 0.000 description 1
- 238000005406 washing Methods 0.000 description 1
Landscapes
- Sewage (AREA)
Abstract
本实用新型涉及石油化工设备技术领域,尤其是一种煤气化污水管线清洗装置,包括清管器、发射站、接收站、第一三通阀和第二三通阀,发射站上设置有发射站进管、发射站放空管和发射站倒空线,接收站上设置有接收站进管、接收站放空管和接收站倒空线,发射站与第一三通阀连接,接收站与第二三通阀连接。采用本专利的煤气化污水管线清洗装置,结构简单,可对现有污水管线直接改建,在待清洗管线两端直接加装本实用新型的装置即可,成本低廉,适于推广。
The utility model relates to the technical field of petrochemical equipment, in particular to a coal gasification sewage pipeline cleaning device, which includes a pipe pig, a transmitting station, a receiving station, a first three-way valve and a second three-way valve. Station inlet pipe, launch station vent pipe and launch station emptying line. The receiving station is equipped with receiving station inlet pipe, receiving station vent pipe and receiving station emptying line. The launching station is connected to the first three-way valve. Connect with the second three-way valve. The coal gasification sewage pipeline cleaning device of this patent has a simple structure, can directly rebuild the existing sewage pipeline, and directly install the device of the utility model at both ends of the pipeline to be cleaned, which is low in cost and suitable for popularization.
Description
技术领域 technical field
本发明涉及石油化工设备技术领域,尤其是一种煤气化污水管线清洗装置。 The invention relates to the technical field of petrochemical equipment, in particular to a coal gasification sewage pipeline cleaning device.
背景技术 Background technique
煤制合成气的灰水,经过四级闪蒸,充分回收热量,然后灰水与添加剂一并送至沉淀池中,使细灰沉降下来,而上部灰水溢流进入低压灰水槽,为了保持灰水中溶解物的平衡,部分灰水需要送往废水处理系统。 The gray water of the coal-to-synthesis gas undergoes four-stage flash evaporation to fully recover the heat, and then the gray water and additives are sent to the sedimentation tank to settle the fine ash, and the upper gray water overflows into the low-pressure gray water tank. The balance of dissolved substances in gray water, part of which needs to be sent to the wastewater treatment system.
由于这部分灰水含有Ca2+、Mg2+、CO3 2-等离子,当超过离子浓度超过其饱和溶度,易出现CaCO3和MgCO3沉淀,最后以垢的形式附着在污水管的管壁,严重时将影响管道的输送的流量。 Since this part of gray water contains Ca 2+ , Mg 2+ , and CO 3 2- ions, when the ion concentration exceeds its saturation solubility, CaCO 3 and MgCO 3 are prone to precipitate, and finally adhere to the sewage pipe in the form of scale In severe cases, it will affect the transport flow of the pipeline.
现常用方法用高压水清洗法和酸洗法。高压水洗清洗法耗时多且成本高;酸洗法存在管道腐蚀问题和酸洗水处理等问题。现在还有一些利用清管器(PIG)进行清理管道的技术,例如中国专利申请201310516180.4,喷射清淤清管器,再如200510132602.3,射流式清管器,都记载了不同的清管器,但是清管器在用于清理煤气化污水管线时,又存在无法清除各种化学沉淀等问题,因此目前急需提供一种合适的煤气化污水管线清理的解决方案。 The commonly used methods are high-pressure water cleaning and pickling. The high-pressure water washing cleaning method is time-consuming and costly; the pickling method has problems such as pipeline corrosion and pickling water treatment. There are still some technologies that use pipe pigs (PIG) to clean pipelines. For example, Chinese patent application 201310516180.4, jet dredging pipe pigs, and 200510132602.3, jet-type pipe pigs, all record different pipe pigs, but When the pipe pig is used to clean the coal gasification sewage pipeline, there are problems such as the inability to remove various chemical deposits. Therefore, it is urgent to provide a suitable solution for the cleaning of the coal gasification sewage pipeline.
发明内容 Contents of the invention
1.要解决的技术问题1. Technical problems to be solved
针对现有技术在清洗煤气化污水管道中存在清洗周期长、成本高、废水处理难等系列的问题,本发明提供了一种实用新型的煤气化污水管道清洗装置,可有效解决在清理管道中存在上述的问题。 Aiming at the problems of long cleaning cycle, high cost, and difficult wastewater treatment in the prior art in cleaning coal gasification sewage pipelines, the present invention provides a utility model cleaning device for coal gasification sewage pipelines, which can effectively solve the problems in cleaning pipelines. There are the above-mentioned problems.
2.技术方案2. Technical solution
本发明的目的通过以下技术方案实现。 The purpose of the present invention is achieved through the following technical solutions.
本发明的煤气化污水管线清洗装置,包括清管器2,还包括发射站1、接收站6、第一三通阀5和第二三通阀9,发射站1上设置有发射站进管3、发射站放空管4和发射站倒空线13,接收站6上设置有接收站进管7、接收站放空管8和接收站倒空线14,发射站1与第一三通阀5连接,接收站6与第二三通阀9连接。 The coal gasification sewage pipeline cleaning device of the present invention includes a pipe pig 2, and also includes a launching station 1, a receiving station 6, a first three-way valve 5 and a second three-way valve 9, and the launching station 1 is provided with a launching station inlet pipe 3. The emptying pipe 4 of the transmitting station and the emptying line 13 of the transmitting station. The receiving station 6 is provided with the inlet pipe 7 of the receiving station, the emptying pipe 8 of the receiving station and the emptying line 14 of the receiving station. The transmitting station 1 is connected to the first tee The valve 5 is connected and the receiving station 6 is connected with the second three-way valve 9 .
上述的煤气化污水管线清洗装置,更进一步,所述的发射站进管3、发射站放空管4、发射站倒空线13、接收站进管7、接收站放空管8和接收站倒空线14上,分别设置有阀门。 The above-mentioned coal gasification sewage pipeline cleaning device, further, the described launch station inlet pipe 3, launch station vent pipe 4, launch station empty line 13, receiving station inlet pipe 7, receiving station vent pipe 8 and receiving station Valves are respectively arranged on the emptying lines 14 .
上述的煤气化污水管线清洗装置,更进一步,发射站倒空线13和接收站倒空线14近出口位置设置有单向阀。 The above-mentioned coal gasification sewage pipeline cleaning device further includes a one-way valve near the outlet of the emptying line 13 of the transmitting station and the emptying line 14 of the receiving station.
3.有益效果3. Beneficial effect
相比于现有技术,本发明的优点在于: Compared with the prior art, the present invention has the advantages of:
(1)采用本专利的煤气化污水管线清洗装置,结构简单,可对现有污水管线直接改建,在待清洗管线两端直接加装本实用新型的装置即可,成本低廉,适于推广。 (1) The coal gasification sewage pipeline cleaning device of this patent has a simple structure, and the existing sewage pipeline can be directly rebuilt, and the device of the utility model can be directly installed at both ends of the pipeline to be cleaned, which is low in cost and suitable for popularization.
(2)本专利的煤气化污水管线清洗装置,一次清洗工作能达到常用两种方式处理的同样效果,同时具有高压水清洗和化学清洗的效果;按照以往的清洗经验,采用高压水清洗一根1000m长、直径DN250的污水管线需1个月时间,所需成本超过十几万元;而采用本专利的装置清洗该管线,以清管器运行速度为0.7m/s,完成一个完整的清洗流程的时间不超过1小时,所需成本低于2000元。本实用新型的管道清洗装置可以明显的提高清洗效率,节约清洗成本。 (2) The coal gasification sewage pipeline cleaning device of this patent can achieve the same effect of the two commonly used methods in one cleaning operation, and has the effects of high-pressure water cleaning and chemical cleaning; It takes one month for a sewage pipeline with a length of 1000m and a diameter of DN250, and the required cost is more than 100,000 yuan; and the device of this patent is used to clean the pipeline, and the cleaning speed of the pig is 0.7m/s to complete a complete cleaning The process takes no more than 1 hour, and the required cost is less than 2,000 yuan. The pipeline cleaning device of the utility model can obviously improve cleaning efficiency and save cleaning cost.
附图说明 Description of drawings
图1为煤气化污水管线清洗装置使用时结构示意图。 Figure 1 is a schematic diagram of the structure of the coal gasification sewage pipeline cleaning device in use.
具体实施方式 Detailed ways
下面结合说明书附图和具体的实施例,对本发明作详细描述。 The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments.
实施例1Example 1
本实施例的煤气化污水管线清洗装置,包括清管器2,还包括发射站1、接收站6、第一三通阀5和第二三通阀9,发射站1上设置有发射站进管3、发射站放空管4和发射站倒空线13,接收站6上设置有接收站进管7、接收站放空管8和接收站倒空线14,发射站1与第一三通阀5连接,接收站6与第二三通阀9连接,在发射站进管3、发射站放空管4、发射站倒空线13、接收站进管7、接收站放空管8和接收站倒空线14上,分别设置有阀门、通过阀门控制管线的开闭。 The coal gasification sewage pipeline cleaning device of this embodiment includes a pig 2, and also includes a launching station 1, a receiving station 6, a first three-way valve 5 and a second three-way valve 9, and the launching station 1 is provided with a launching station inlet Pipe 3, sending station emptying pipe 4 and sending station emptying line 13, receiving station 6 is provided with receiving station inlet pipe 7, receiving station emptying pipe 8 and receiving station emptying line 14, sending station 1 and the first three The through valve 5 is connected, the receiving station 6 is connected with the second three-way valve 9, the inlet pipe 3 at the launching station, the emptying pipe 4 at the launching station, the emptying line 13 at the launching station, the inlet pipe 7 at the receiving station, and the emptying pipe 8 at the receiving station On the emptying line 14 of the receiving station and the receiving station, valves are respectively arranged, and the opening and closing of the pipeline are controlled by the valves.
图1为煤气化污水管线清洗装置使用时结构示意图,如图1所示,一般的污水管线,包括灰水罐10,灰水罐10通过泵11连接污水管线和污水池12。需要清洗污水管线时,将第一三通阀5、第二三通阀9分别连接在待清洗管线两端,即第一三通阀5、第二三通阀9之间为待清洗污水管线。 Fig. 1 is a schematic structural diagram of a coal gasification sewage pipeline cleaning device in use. As shown in Fig. 1, a general sewage pipeline includes a gray water tank 10, which is connected to a sewage pipeline and a sewage tank 12 through a pump 11. When the sewage pipeline needs to be cleaned, connect the first three-way valve 5 and the second three-way valve 9 to both ends of the pipeline to be cleaned, that is, the sewage pipeline to be cleaned is between the first three-way valve 5 and the second three-way valve 9 .
本实施例的工作原理具体如下: The working principle of this embodiment is specifically as follows:
正常工作状态下,灰水罐10内的灰水依次经过泵11、第一三通阀5、第二三通阀9输送到污水池12,清管器2位于发射站1内,发射站进管3、发射站放空管4、发射站倒空线13、接收站进管7、接收站放空管8和接收站倒空线14上的阀门均为关闭状态,以图1状态为准,此时第一三通阀5、第二三通阀9均为旁通状态,发射站倒空线13、接收站倒空线14和第二三通阀9的旁通连通后连接至污水池12。 Under normal working conditions, the gray water in the gray water tank 10 is transported to the sewage pool 12 through the pump 11, the first three-way valve 5, and the second three-way valve 9 in sequence. The pipe pig 2 is located in the launching station 1, and the launching station enters The valves on the pipe 3, the emptying pipe 4 of the launching station, the emptying line 13 of the launching station, the inlet pipe 7 of the receiving station, the emptying pipe 8 of the receiving station and the emptying line 14 of the receiving station are all closed, and the state in Figure 1 shall prevail , now the first three-way valve 5 and the second three-way valve 9 are in the bypass state, and the emptying line 13 of the transmitting station, the emptying line 14 of the receiving station and the bypass of the second three-way valve 9 are connected to the sewage Pool 12.
待清洗管线需要清洗时: When the pipeline to be cleaned needs to be cleaned:
(1)泵11停止,第一三通阀5变为直通状态,发射站进管3接通,清洗水由发射站进管3进入发射站,利用清洗水的水压将清管器2推送至第二三通阀9位置。 (1) The pump 11 stops, the first three-way valve 5 becomes straight-through, the inlet pipe 3 of the launch station is connected, the cleaning water enters the launch station from the inlet pipe 3 of the launch station, and the pig 2 is pushed by the hydraulic pressure of the clean water To the second three-way valve 9 position.
(2)第二三通阀9变为直通状态,打开接收站倒空线14,继续利用清洗水的水压将清管器2推送至接收站6。 (2) The second three-way valve 9 changes to the straight-through state, opens the emptying line 14 of the receiving station, and continues to push the pig 2 to the receiving station 6 by using the water pressure of the cleaning water.
(3)此时关闭发射站进管3和接收站倒空线14,打开接收站进管7和发射站倒空线13,清洗水由接收站进管7进入,并将清管器2推回至发射站1。 (3) At this time, close the inlet pipe 3 of the transmitting station and the emptying line 14 of the receiving station, open the inlet pipe 7 of the receiving station and the emptying line 13 of the transmitting station, the cleaning water enters from the inlet pipe 7 of the receiving station, and push the pig 2 Go back to launch station 1.
(4)关闭接收站进管7,打开发射站放空管4、接收站放空管8和接收站倒空线14,将发射站1和接收站6内的清洗水倒空。 (4) Close the inlet pipe 7 of the receiving station, open the emptying pipe 4 of the transmitting station, the emptying pipe 8 of the receiving station and the emptying line 14 of the receiving station, and empty the cleaning water in the sending station 1 and receiving station 6.
(5)第一三通阀5、第二三通阀9都切换为旁通状态,完成待清洗管线的清洗工作,此时待清洗管线经过了清管器2和清洗水往复各一次的清洗工作,污水泵11可开启,重新启用污水管线。 (5) Both the first three-way valve 5 and the second three-way valve 9 are switched to the bypass state to complete the cleaning of the pipeline to be cleaned. At this time, the pipeline to be cleaned has been cleaned by the pig 2 and the cleaning water reciprocating once work, the sewage pump 11 can be opened, and the sewage pipeline is reactivated.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420858492.3U CN204381021U (en) | 2014-12-30 | 2014-12-30 | A kind of coal gasification wastewater pipe line cleaning device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420858492.3U CN204381021U (en) | 2014-12-30 | 2014-12-30 | A kind of coal gasification wastewater pipe line cleaning device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204381021U true CN204381021U (en) | 2015-06-10 |
Family
ID=53353777
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420858492.3U Expired - Lifetime CN204381021U (en) | 2014-12-30 | 2014-12-30 | A kind of coal gasification wastewater pipe line cleaning device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204381021U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112871906A (en) * | 2021-01-14 | 2021-06-01 | 上海森松制药设备工程有限公司 | Production system |
CN113481034A (en) * | 2021-07-07 | 2021-10-08 | 广东韶钢松山股份有限公司 | Crude benzene distillation oil washing device and oil washing method |
-
2014
- 2014-12-30 CN CN201420858492.3U patent/CN204381021U/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112871906A (en) * | 2021-01-14 | 2021-06-01 | 上海森松制药设备工程有限公司 | Production system |
CN113481034A (en) * | 2021-07-07 | 2021-10-08 | 广东韶钢松山股份有限公司 | Crude benzene distillation oil washing device and oil washing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105298510B (en) | Pipe replacing and slurry discharging device for slurry shield and slurry discharging mode | |
CN204381021U (en) | A kind of coal gasification wastewater pipe line cleaning device | |
CN205135644U (en) | Slurry shield tube replacement arranges thick liquid device | |
CN203002714U (en) | Tubular reactor cleaning structure | |
CN201807291U (en) | Conveying device by using lime coagulation treatment waste residue in thermal power plant as flue gas desulfurization absorbent | |
CN205918455U (en) | Hydrophobic recovery system device of steam power plant | |
CN206356334U (en) | A kind of transverse tube type coal gas primary cooler tube bank cleaning device | |
CN201760237U (en) | Offline reverse osmosis membrane cleaning equipment | |
CN103628913A (en) | Automatic cleaning system and method of dual-redundancy paste filling pipes | |
CN206725280U (en) | A kind of pressure piping sampling apparatus | |
CN202155331U (en) | Silicon material rinser | |
CN204454759U (en) | A kind of membrane concentration system | |
CN204554775U (en) | Boiler blow-off apparatus for recovering | |
RU89600U1 (en) | MOBILE INHIBITOR DOSAGE INSTALLATION (OPTIONS) | |
CN207076732U (en) | A kind of percolate conveyance conduit descaling rinsing device | |
CN201592065U (en) | Cleaning system for inorganic membrane water treatment device | |
CN2926196Y (en) | Apparatus for cleaning reverse osmosis or nanofiltration membrane elements | |
CN206997258U (en) | A kind of desulfurizing tower pipe cleaning device | |
CN101907530B (en) | Fluid sampling device and system | |
CN207237723U (en) | A kind of small-sized efficient activated sludge membrane filter system | |
CN201372239Y (en) | Reverse osmosis concentrated water reuse device | |
CN205825797U (en) | A kind of central air-conditioning single copper can washing apparatus | |
CN205055510U (en) | Sewage pipes structure convenient to wash | |
CN204702543U (en) | Softening agent connecting pipeline structure | |
CN216024028U (en) | Pretreatment device for liquid ammonia tank car inspection |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 210047 No. 118, Tai Fang Road, Nanjing chemical industry park, Jiangsu, Nanjing Patentee after: NANJING CHENGZHI CLEAN ENERGY Co.,Ltd. Address before: 210047 No. 118, Tai Fang Road, Nanjing chemical industry park, Jiangsu, Nanjing Patentee before: Nanjing Zhicheng clean energy Limited by Share Ltd. Address after: 210047 No. 118, Tai Fang Road, Nanjing chemical industry park, Jiangsu, Nanjing Patentee after: Nanjing Zhicheng clean energy Limited by Share Ltd. Address before: 210047 No. 118, Tai Fang Road, Nanjing chemical industry park, Jiangsu, Nanjing Patentee before: WISON (NANJING) CLEAN ENERGY CO.,LTD. |
|
CP01 | Change in the name or title of a patent holder | ||
CX01 | Expiry of patent term |
Granted publication date: 20150610 |
|
CX01 | Expiry of patent term |