[go: up one dir, main page]

CN204323346U - Railway truck and shipping loading and unloading system - Google Patents

Railway truck and shipping loading and unloading system Download PDF

Info

Publication number
CN204323346U
CN204323346U CN201420733739.9U CN201420733739U CN204323346U CN 204323346 U CN204323346 U CN 204323346U CN 201420733739 U CN201420733739 U CN 201420733739U CN 204323346 U CN204323346 U CN 204323346U
Authority
CN
China
Prior art keywords
floor
ramp
railway truck
railway
hinged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420733739.9U
Other languages
Chinese (zh)
Inventor
伊永峰
李华
吴荣坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Tf High Tech Co ltd
CRRC Qiqihar Rolling Stock Co Ltd
Original Assignee
BEIJING TF HIGH-TECH Co Ltd
Qiqihar Railway Rolling Stock Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING TF HIGH-TECH Co Ltd, Qiqihar Railway Rolling Stock Co Ltd filed Critical BEIJING TF HIGH-TECH Co Ltd
Priority to CN201420733739.9U priority Critical patent/CN204323346U/en
Application granted granted Critical
Publication of CN204323346U publication Critical patent/CN204323346U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Loading Or Unloading Of Vehicles (AREA)

Abstract

本实用新型提供了一种铁路货车以及货运装卸系统。其中,铁路货车包括底架和设置在底架下方的车轮,底架包括地板(10),地板(10)包括两个端部地板(11)和设置在两个端部地板(11)之间的中间地板(12),中间地板(12)具有低于端部地板(11)的凹槽部,铁路货车还包括两个坡板(20),各坡板(20)可摆动地设置在凹槽部内,各坡板(20)的第一端与凹槽部的中部可枢转的连接,各坡板(20)的第二端具有与凹槽部贴合的回收位置以及与对应的端部地板(11)配合的升起位置。本实用新型的技术方案能够有效地解决现有技术中的铁路货车不能运输大型卡车的问题。

The utility model provides a railway freight car and a freight loading and unloading system. Wherein, the railway wagon comprises an underframe and wheels arranged under the underframe, the underframe comprises a floor (10), and the floor (10) comprises two end floors (11) and a wheel arranged between the two end floors (11). The middle floor (12), the middle floor (12) has a groove portion lower than the end floor (11), and the railway wagon also includes two ramps (20), each ramp (20) is swingably arranged in the concave In the groove, the first end of each ramp (20) is pivotally connected to the middle of the groove, and the second end of each ramp (20) has a recovery position that fits with the groove and a corresponding end The raised position of the bottom floor (11). The technical scheme of the utility model can effectively solve the problem that the railway wagons in the prior art cannot transport large trucks.

Description

铁路货车以及货运装卸系统Railway wagons and freight handling systems

技术领域technical field

本实用新型涉及铁路车辆技术领域,具体而言,涉及一种铁路货车以及货运装卸系统。The utility model relates to the technical field of railway vehicles, in particular to a railway freight car and a freight loading and unloading system.

背景技术Background technique

目前,公路运输是我国货物运输的主要方式之一。但是,由于公路运输受天气、地形以及夜间行车等因素影响较大,工作人员通常将货运卡车开到专用的铁路货车上,并通过铁路将货运卡车运送到目的地。这种通过铁路进行长距离、全天候的运输方式既经济又安全可靠。At present, road transportation is one of the main modes of cargo transportation in our country. However, because road transportation is greatly affected by factors such as weather, terrain, and night driving, the staff usually drives the freight truck to a special railway freight car, and transports the freight truck to the destination by rail. This long-distance, round-the-clock transportation by rail is economical, safe and reliable.

在上述运输方式中,工作人员通常将铁路货车通过装载线路牵至装载点的指定位置,并将卡车1’通过站台开到铁路货车的地板10’上(如图1所示),完成装载过程。此后,通过铁路将卡车运送到目的地,并将卡车从铁路货车的地板10’上通过站台开下,再自行到达指定地点。In the above transportation mode, the staff usually leads the railway freight car to the designated position of the loading point through the loading line, and drives the truck 1' through the platform to the floor 10' of the railway freight car (as shown in Figure 1), and completes the loading process . Thereafter, the truck is transported to the destination by rail, and the truck is driven off from the floor 10' of the railway wagon through the platform, and then arrives at the designated place by itself.

在铁路运输过程中,为了确保卡车在铁路线路上的安全,防止其撞击邻近线路的建筑物和设备,通常会对铁路货车和接近线路的建筑物、设备规定不允许超越的轮廓尺寸线(图2所示的点化线部分示出了轮廓尺寸线)。上述轮廓尺寸线称为铁路限界。基本的铁路限界包括车辆限界和建筑接近限界。In the process of railway transportation, in order to ensure the safety of the truck on the railway line and prevent it from hitting the buildings and equipment adjacent to the line, the outline dimension line that is not allowed to be exceeded is usually stipulated for the railway wagon and the buildings and equipment close to the line (Fig. The dotted line portion shown in 2 shows the outline dimension line). The above outline dimension lines are called rail limits. Basic railway gauges include vehicle gauges and building approach gauges.

由于受到铁路限界的影响,当使用现有技术中的铁路货车运输卡车时,若卡车的尺寸较大,装有卡车的铁路货车整体尺寸很容易超出车辆限界(如图2所示)。这样就导致上述运输方式只能运输小型卡车,不能运输大型卡车。Due to the influence of the railway margin, when using the railway freight car in the prior art to transport the truck, if the size of the truck is large, the overall size of the railway freight car with the truck is easy to exceed the vehicle limit (as shown in Figure 2). This causes the above-mentioned transportation methods to only transport small trucks, but not large trucks.

实用新型内容Utility model content

本实用新型的主要目的在于提供一种铁路货车以及货运装卸系统,以解决现有技术中的铁路货车不能运输大型卡车的问题。The main purpose of the utility model is to provide a railway freight car and a freight loading and unloading system to solve the problem that the railway freight car in the prior art cannot transport large trucks.

为了实现上述目的,根据本实用新型的一个方面,提供了一种铁路货车,包括底架和设置在底架下方的车轮,底架包括地板,地板包括两个端部地板和设置在两个端部地板之间的中间地板,中间地板具有低于端部地板的凹槽部,铁路货车还包括两个坡板,各坡板可摆动地设置在凹槽部内,各坡板的第一端与凹槽部的中部可枢转的连接,各坡板的第二端具有与凹槽部贴合的回收位置以及与对应的端部地板配合的升起位置。In order to achieve the above object, according to one aspect of the present invention, a railway wagon is provided, which includes an underframe and wheels arranged under the underframe, the underframe includes a floor, the floor includes two end floors and The middle floor between the end floors, the middle floor has a groove portion lower than the end floor, and the railway freight car also includes two ramps, each ramp is swingably arranged in the groove, and the first end of each ramp is connected to the groove. The middle part of the groove part is pivotally connected, and the second end of each slope board has a recovery position fitted with the groove part and a raised position matched with the corresponding end floor.

进一步地,铁路货车还包括:第一铰接座,安装在凹槽部内,坡板的第一端铰接在第一铰接座上。Further, the railway freight car also includes: a first hinged seat installed in the groove, and the first end of the slope plate is hinged on the first hinged seat.

进一步地,铁路货车还包括:坡板驱动机构,坡板驱动机构包括液压缸,液压缸的缸体安装在凹槽部内,液压缸的活塞杆与坡板的第二端铰接。Further, the railway freight car also includes: a ramp drive mechanism, the ramp drive mechanism includes a hydraulic cylinder, the cylinder body of the hydraulic cylinder is installed in the groove, and the piston rod of the hydraulic cylinder is hinged to the second end of the ramp.

进一步地,铁路货车还包括:第二铰接座,安装在凹槽部的安装槽内,液压缸的缸体铰接在第二铰接座上;第三铰接座,安装在坡板的底部,液压缸的活塞杆铰接在第三铰接座上。Further, the railway freight car also includes: a second hinged seat, installed in the installation groove of the groove part, and the cylinder body of the hydraulic cylinder is hinged on the second hinged seat; a third hinged seat, installed at the bottom of the ramp, and the hydraulic cylinder The piston rod is hinged on the third hinge seat.

进一步地,坡板包括板体及沿板体横向布置的加强横梁。Further, the slope plate includes a plate body and reinforcing beams arranged transversely along the plate body.

进一步地,加强横梁为多根,其中一根加强横梁上设置有第三铰接座。Further, there are multiple reinforcing beams, and a third hinge seat is provided on one of the reinforcing beams.

进一步地,底架还包括:两个侧梁,两个侧梁间隔设置且相互平行,两个侧梁设置在地板的相对的两个侧边处。Further, the underframe further includes: two side beams, the two side beams are arranged at intervals and parallel to each other, and the two side beams are arranged at two opposite sides of the floor.

进一步地,端部地板上设置有可摆动的第一过渡板。Further, a swingable first transition board is arranged on the end floor.

根据本实用新型的另一方面,提供了一种货运装卸系统,包括站台以及铁路货车,铁路货车为上述的铁路货车。According to another aspect of the present utility model, a freight loading and unloading system is provided, including a platform and a railway freight car, and the railway freight car is the above-mentioned railway freight car.

进一步地,货运装卸系统还包括第二过渡板,第二过渡板的一端与站台可枢转连接,第二过渡板的另一端与底架的端部地板配合。Further, the freight handling system further includes a second transition board, one end of the second transition board is pivotally connected to the platform, and the other end of the second transition board is matched with the end floor of the chassis.

应用本实用新型的技术方案,底架的地板包括两个端部地板和设置在两个端部地板之间的中间地板,并且中间地板具有凹槽部。两个坡板可摆动地设置在上述凹槽部内,并且各坡板的第一端与凹槽部的中部可枢转的连接。当对大型卡车进行装载作业时,靠近卡车车头位置的坡板的第二端由与凹槽部贴合的回收位置移动到与对应的端部地板配合的升起位置,形成坡度。在将卡车完全开到铁路货车的地板上后,使坡板的第二端由升起位置移动到回收位置,卡车随之完全落入铁路货车内,从而完成装载过程。同样地,当对大型卡车进行卸载作业时,靠近卡车车头位置的坡板的第二端由回收位置移动到升起位置,形成坡度。待将卡车从铁路货车的地板上开下后,使坡板的第二端由升起位置移动到回收位置,从而完成卸载过程。由于大型卡车落入铁路货车内,卡车顶面的高度降低,装有大型卡车的铁路货车整体尺寸不会超出车辆限界,从而有效地解决了铁路货车不能运输大型卡车的问题。Applying the technical solution of the utility model, the floor of the chassis includes two end floors and a middle floor arranged between the two end floors, and the middle floor has a groove. The two ramps are swingably arranged in the groove, and the first ends of each ramp are pivotally connected to the middle of the groove. When loading a large truck, the second end of the slope plate close to the front of the truck moves from a recovered position fitted with the groove to a raised position matched with the corresponding end floor to form a slope. After the truck is fully driven onto the floor of the railway wagon, the second end of the ramp is moved from the raised position to the recovery position, and the truck is then completely dropped into the railway wagon, thereby completing the loading process. Similarly, when unloading a large truck, the second end of the ramp near the front of the truck moves from the recovery position to the raised position to form a slope. After the truck is driven off the floor of the railway wagon, the second end of the ramp is moved from the raised position to the recovered position, thereby completing the unloading process. Since the large truck falls into the railway freight car, the height of the top surface of the truck is reduced, and the overall size of the railway freight car equipped with the large truck will not exceed the vehicle limit, thereby effectively solving the problem that the railway freight car cannot transport large trucks.

附图说明Description of drawings

构成本申请的一部分的说明书附图用来提供对本实用新型的进一步理解,本实用新型的示意性实施例及其说明用于解释本实用新型,并不构成对本实用新型的不当限定。在附图中:The accompanying drawings constituting a part of this application are used to provide a further understanding of the utility model, and the schematic embodiments of the utility model and their descriptions are used to explain the utility model and do not constitute improper limitations to the utility model. In the attached picture:

图1示出了现有技术中铁路货车的装载示意图;Fig. 1 shows the loading schematic diagram of railway wagon in the prior art;

图2示出了现有技术中铁路运输中的车辆限界的示意图;Fig. 2 shows the schematic diagram of the vehicle limit in the railway transportation in the prior art;

图3示出了根据本实用新型的实施例的铁路货车的主视示意图;Fig. 3 shows a schematic front view of a railway freight car according to an embodiment of the present invention;

图4示出了根据本实用新型的实施例的铁路货车的俯视示意图;Fig. 4 shows a schematic top view of a railway freight car according to an embodiment of the present invention;

图5示出了根据本实用新型的实施例的坡板驱动机构的结构示意图;Fig. 5 shows a schematic structural view of a ramp driving mechanism according to an embodiment of the present invention;

图6示出了根据本实用新型的实施例的铁路货车的装载初始状态示意图;Fig. 6 shows the schematic diagram of the loading initial state of the railway freight car according to the embodiment of the present invention;

图7示出了根据本实用新型的实施例的铁路货车的装载中间状态示意图;Fig. 7 shows a schematic diagram of a loading intermediate state of a railway freight car according to an embodiment of the present invention;

图8示出了根据本实用新型的实施例的铁路货车的装载结束状态示意图;以及Figure 8 shows a schematic diagram of the loading end state of a railway freight car according to an embodiment of the present invention; and

图9示出了根据本实用新型的实施例的铁路货车的卸载状态示意图。Fig. 9 shows a schematic diagram of an unloading state of a railway freight car according to an embodiment of the present invention.

其中,上述附图包括以下附图标记:Wherein, the above-mentioned accompanying drawings include the following reference signs:

1’、卡车;10’、地板;1、卡车;10、地板;11、端部地板;12、中间地板;20、坡板;21、板体;22、加强横梁;31、第一铰接座;33、第三铰接座;32、第二铰接座;40、液压缸;50、侧梁;61、第一过渡板;62、第二过渡板。1', truck; 10', floor; 1, truck; 10, floor; 11, end floor; 12, middle floor; 20, ramp; 21, board body; 22, reinforcing beam; 31, first hinged seat ; 33, the third hinge seat; 32, the second hinge seat; 40, the hydraulic cylinder; 50, the side beam; 61, the first transition plate; 62, the second transition plate.

具体实施方式detailed description

需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。下面将参考附图并结合实施例来详细说明本实用新型。It should be noted that, in the case of no conflict, the embodiments in the present application and the features in the embodiments can be combined with each other. The utility model will be described in detail below with reference to the accompanying drawings and in conjunction with the embodiments.

如图3和图4所示,本实施例的铁路货车包括底架和设置在底架下方的车轮。底架包括地板10,地板10包括两个端部地板11和设置在两个端部地板11之间的中间地板12,中间地板12具有低于端部地板11的凹槽部。铁路货车还包括两个坡板20,各坡板20可摆动地设置在凹槽部内,各坡板20的第一端与凹槽部的中部可枢转的连接,各坡板20的第二端具有与凹槽部贴合的回收位置以及与对应的端部地板11配合的升起位置。As shown in Fig. 3 and Fig. 4, the railway freight car of this embodiment includes an underframe and wheels arranged under the underframe. The chassis includes a floor panel 10 including two end panels 11 and an intermediate panel 12 disposed between the two end panels 11 , the intermediate panel 12 having a recessed portion lower than the end panels 11 . The railway wagon also includes two ramps 20, each ramp 20 is swingably arranged in the groove, the first end of each ramp 20 is pivotably connected to the middle of the groove, the second of each ramp 20 The ends have a retracted position that fits into the recessed portion and a raised position that fits into the corresponding end floor 11 .

应用本实施例的铁路货车,底架的地板10包括两个端部地板11和设置在两个端部地板11之间的中间地板12,并且中间地板12具有凹槽部。两个坡板20可摆动地设置在上述凹槽部内,并且各坡板20的第一端与凹槽部的中部可枢转的连接。当对大型卡车进行装载作业时,靠近卡车车头位置的坡板20的第二端由与凹槽部贴合的回收位置移动到与对应的端部地板11配合的升起位置,形成坡度。在将卡车完全开到铁路货车的地板10上后,使坡板20的第二端由升起位置移动到回收位置,卡车随之完全落入铁路货车内,从而完成装载过程。同样地,当对大型卡车进行卸载作业时,靠近卡车车头位置的坡板20的第二端由回收位置移动到升起位置,形成坡度。待将卡车从铁路货车的地板10上开下后,使坡板20的第二端由升起位置移动到回收位置,从而完成卸载过程。由于大型卡车落入铁路货车内,卡车顶面的高度降低,装有大型卡车的铁路货车整体尺寸不会超出车辆限界,从而有效地解决了铁路货车不能运输大型卡车的问题。With the railway freight car of the present embodiment, the floor 10 of the chassis includes two end floors 11 and an intermediate floor 12 provided between the two end floors 11, and the intermediate floor 12 has a recessed portion. The two ramps 20 are swingably disposed in the groove, and the first ends of each ramp 20 are pivotally connected to the middle of the groove. When loading a large truck, the second end of the slope plate 20 near the front of the truck moves from a retracted position in contact with the groove to a raised position in cooperation with the corresponding end floor 11 to form a slope. After the truck is fully driven onto the floor 10 of the railway wagon, the second end of the ramp 20 is moved from the raised position to the recovery position, and the truck falls completely into the railway wagon thereupon, thereby completing the loading process. Similarly, when unloading a large truck, the second end of the ramp 20 close to the front of the truck moves from the recovery position to the raised position, forming a slope. After the truck is driven off the floor 10 of the railway wagon, the second end of the ramp 20 is moved from the raised position to the recovered position, thereby completing the unloading process. Since the large truck falls into the railway freight car, the height of the top surface of the truck is reduced, and the overall size of the railway freight car equipped with the large truck will not exceed the vehicle limit, thereby effectively solving the problem that the railway freight car cannot transport large trucks.

如图5所示,在本实施例的铁路货车中,铁路货车还包括第一铰接座31,安装在凹槽部内,坡板20的第一端铰接在第一铰接座31上。上述结构可以使坡板20可摆动地设置在凹槽部内。在本实施例中,上述第一铰接座31设置在凹槽部的中部,利于安装,且可以使坡板20形成的坡度比较缓和。As shown in FIG. 5 , in the railway freight car of this embodiment, the railway freight car further includes a first hinge seat 31 installed in the groove portion, and the first end of the slope plate 20 is hinged on the first hinge seat 31 . The above structure enables the slope plate 20 to be swingably disposed in the groove portion. In this embodiment, the above-mentioned first hinge seat 31 is arranged in the middle of the groove portion, which is convenient for installation and can make the slope formed by the slope plate 20 relatively gentle.

如图5所示,在本实施例的铁路货车中,铁路货车还包括坡板驱动机构,坡板驱动机构包括液压缸40,液压缸40的缸体安装在凹槽部内,液压缸40的活塞杆与坡板20的第二端铰接。此外,铁路货车还包括第二铰接座32和第三铰接座33。第二铰接座32安装在凹槽部的安装槽内,液压缸40的缸体铰接在第二铰接座32上。第三铰接座33安装在坡板20的底部,液压缸40的活塞杆铰接在第三铰接座33上。As shown in Figure 5, in the railway freight car of this embodiment, the railway freight car also includes a ramp drive mechanism, the ramp drive mechanism includes a hydraulic cylinder 40, the cylinder body of the hydraulic cylinder 40 is installed in the groove, and the piston of the hydraulic cylinder 40 The rod is hinged to the second end of the ramp 20 . In addition, the railway freight car also includes a second articulated seat 32 and a third articulated seat 33 . The second hinged seat 32 is installed in the installation groove of the groove portion, and the cylinder body of the hydraulic cylinder 40 is hinged on the second hinged seat 32 . The third hinged seat 33 is installed on the bottom of the ramp 20 , and the piston rod of the hydraulic cylinder 40 is hinged on the third hinged seat 33 .

具体地,第二铰接座32固定设置在凹槽部的安装槽内,并与液压缸40的缸体铰接。当液压缸40的活塞杆伸出时,带动与液压缸40的活塞杆铰接的坡板20的第二端相对第三铰接座33转动。因为坡板20的第一端铰接在第一铰接座31上,坡板20绕第一铰接座31向上转动。当坡板20的第二端到达与对应的端部地板11配合的升起位置时,液压缸40停止动作。同样地,当液压缸40的活塞杆缩回时,带动与液压缸40的活塞杆铰接的坡板20的第二端相对第三铰接座33转动。因为坡板20的第一端铰接在第一铰接座31上,坡板20绕第一铰接座31向下转动。当坡板20的第二端到达与凹槽部贴合的回收位置时,液压缸40停止动作。上述结构可以驱动坡板20的第二端在与凹槽部贴合的回收位置和与对应的端部地板11配合的升起位置之间移动。Specifically, the second hinge seat 32 is fixedly disposed in the installation groove of the groove portion, and is hinged with the cylinder body of the hydraulic cylinder 40 . When the piston rod of the hydraulic cylinder 40 is stretched out, the second end of the slope plate 20 hinged to the piston rod of the hydraulic cylinder 40 is driven to rotate relative to the third hinge seat 33 . Because the first end of the ramp 20 is hinged on the first hinge seat 31 , the ramp 20 rotates upward around the first hinge seat 31 . When the second end of the ramp 20 reaches the raised position matched with the corresponding end floor 11 , the hydraulic cylinder 40 stops acting. Similarly, when the piston rod of the hydraulic cylinder 40 is retracted, the second end of the slope plate 20 hinged to the piston rod of the hydraulic cylinder 40 is driven to rotate relative to the third hinge seat 33 . Because the first end of the ramp 20 is hinged on the first hinge seat 31 , the ramp 20 rotates downward around the first hinge seat 31 . When the second end of the sloping plate 20 reaches the recovering position where it fits into the groove, the hydraulic cylinder 40 stops acting. The above-mentioned structure can drive the second end of the ramp 20 to move between the retracted position adjoining the groove portion and the raised position cooperating with the corresponding end floor 11 .

如图4和图5所示,在本实施例的铁路货车中,坡板20包括板体21及沿板体21横向布置的加强横梁22。加强横梁22为多根,其中一根加强横梁22上设置有第三铰接座33。加强横梁22的设置可以增强坡板20的承载能力。上述第三铰接座33在坡板驱动机构工作时为主要承压部件,将第三铰接座33设置在加强横梁22上,可以有效地增强第三铰接座33与坡板20连接处的承载能力。As shown in FIG. 4 and FIG. 5 , in the railway freight car of this embodiment, the slope plate 20 includes a plate body 21 and a reinforcing beam 22 arranged laterally along the plate body 21 . There are multiple reinforcing beams 22 , and a third hinge seat 33 is arranged on one of the reinforcing beams 22 . The setting of the reinforcing beam 22 can enhance the bearing capacity of the slope plate 20 . The above-mentioned third hinged seat 33 is the main pressure-bearing part when the ramp drive mechanism is working, and the third hinged seat 33 is arranged on the reinforcing beam 22, which can effectively enhance the bearing capacity of the joint between the third hinged seat 33 and the ramp 20 .

如图3所示,在本实施例的铁路货车中,底架还包括两个侧梁50。两个侧梁50间隔设置且相互平行,两个侧梁50设置在地板10的相对的两个侧边处。两个侧梁50的设置可以在铁路货车的装载和卸载过程中,对卡车的行进路线起到定位的作用,并且可以增强铁路货车的底架的承载能力。As shown in FIG. 3 , in the railway freight car of this embodiment, the underframe further includes two side beams 50 . The two side beams 50 are arranged at intervals and parallel to each other, and the two side beams 50 are arranged at two opposite sides of the floor 10 . The arrangement of the two side beams 50 can position the traveling route of the railway freight car during the loading and unloading process of the railway freight car, and can enhance the bearing capacity of the underframe of the railway freight car.

如图3和图4所示,在本实施例的铁路货车中,端部地板11上设置有可摆动的第一过渡板61。上述第一过渡板61主要起到支撑的作用。优选地,第一过渡板61可以为可90度翻转的平板型钢结构,有效地增强第一过渡板61的承载力。As shown in FIG. 3 and FIG. 4 , in the railway freight car of this embodiment, a swingable first transition plate 61 is provided on the end floor 11 . The above-mentioned first transition plate 61 mainly plays a supporting role. Preferably, the first transition plate 61 can be a flat plate steel structure that can be turned over 90 degrees, so as to effectively enhance the bearing capacity of the first transition plate 61 .

本申请还提供了一种货运装卸系统,根据本申请的货运装卸系统的实施例包括站台以及上述铁路货车。The present application also provides a freight handling system. An embodiment of the freight handling system according to the present application includes a platform and the above-mentioned railway freight cars.

如图6所示,在本实施例的货运装卸系统中,货运装卸系统还包括第二过渡板62,第二过渡板62的一端与站台可枢转连接,第二过渡板62的另一端与底架的端部地板11配合。当对大型卡车进行装载或卸载作业时,可将端部地板11上设置的第一过渡板61翻转水平位置,并将站台上的第二过渡板62翻转,搭接到第一过渡板61上,方便卡车1通过。其中,第一过渡板61对第二过渡板62起到支撑的作用。As shown in Figure 6, in the freight handling system of this embodiment, the freight handling system also includes a second transition board 62, one end of the second transition board 62 is pivotably connected to the platform, and the other end of the second transition board 62 is connected to The end floors 11 of the chassis fit. When loading or unloading large trucks, the first transition plate 61 provided on the end floor 11 can be turned over to a horizontal position, and the second transition plate 62 on the platform can be turned over to overlap the first transition plate 61 , to facilitate the passage of truck 1. Wherein, the first transition board 61 supports the second transition board 62 .

在本实施例中,货运装卸系统的工作过程如下:当工作人员将铁路货车通过装载线路牵至装载点的指定位置时,靠近卡车车头位置的坡板20的第二端在坡板驱动机构的作用下处于与对应的端部地板11配合的升起位置,并将第一过渡板61和第二过渡板62翻转到水平位置(如图6所示)。此后,将卡车1完全开上铁路货车的坡板20(如图7所示)。待卡车1在铁路货车上停稳后,坡板20的第二端在坡板驱动机构的作用下由升起位置移动到回收位置,卡车随之完全落入铁路货车内,从而完成装载过程(如图8所示)。当铁路货车到达目的地时,靠近卡车车头位置的坡板20的第二端在坡板驱动机构的作用下由回收位置移动到升起位置,并将第一过渡板61和第二过渡板62翻转到水平位置,卡车1开出铁路货车的坡板20(如图9所示)。In this embodiment, the working process of the freight loading and unloading system is as follows: when the staff leads the railway freight car to the designated position of the loading point through the loading line, the second end of the ramp 20 close to the position of the truck head is on the ramp driving mechanism. Under action, it is in a raised position cooperating with the corresponding end floor plate 11, and turns the first transition plate 61 and the second transition plate 62 to a horizontal position (as shown in FIG. 6 ). Thereafter, the truck 1 is fully driven onto the ramp 20 of the railway wagon (as shown in FIG. 7 ). After the truck 1 stops on the railway freight car, the second end of the ramp 20 moves from the raised position to the recovery position under the action of the ramp drive mechanism, and the truck falls into the railway freight car completely, thereby completing the loading process ( as shown in Figure 8). When the railway freight car arrives at the destination, the second end of the ramp 20 near the head of the truck moves from the recovery position to the raised position under the action of the ramp drive mechanism, and the first transition plate 61 and the second transition plate 62 Overturned to a horizontal position, the truck 1 leaves the ramp 20 of the railway wagon (as shown in Figure 9).

从以上的描述中,可以看出,本实用新型上述的实施例可以使大型卡车落入铁路货车内,卡车顶面的高度降低,进而使装有大型卡车的铁路货车整体尺寸不会超出车辆限界,从而有效地解决了铁路货车不能运输大型卡车的问题。From the above description, it can be seen that the above-mentioned embodiment of the utility model can make a large truck fall into the railway freight car, and the height of the top surface of the truck is reduced, so that the overall size of the railway freight car equipped with a large truck will not exceed the vehicle limit , thus effectively solving the problem that railway wagons cannot transport large trucks.

以上所述仅为本实用新型的优选实施例而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. For those skilled in the art, the present utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present utility model shall be included in the protection scope of the present utility model.

Claims (10)

1. a railway truck, comprise underframe and be arranged on the wheel below described underframe, it is characterized in that, described underframe comprises floor (10), described floor (10) comprises floor, two ends (11) and is arranged on the intermediate floor (12) between floor, two described ends (11), described intermediate floor (12) has the concave part lower than floor, described end (11), described railway truck also comprises two ramps (20), each described ramp (20) is arranged in described concave part swingably, the first end of each described ramp (20) is connected with the middle part of described concave part is pivotable, the recovery position that second end has with described concave part is fitted of each described ramp (20) and the raised position coordinated with corresponding floor, described end (11).
2. railway truck according to claim 1, is characterized in that, described railway truck also comprises:
First hinged seat (31), is arranged in described concave part, and the first end of described ramp (20) is hinged on described first hinged seat (31).
3. railway truck according to claim 1, is characterized in that, described railway truck also comprises:
Ramp driver train, described ramp driver train comprises hydraulic actuating cylinder (40), the cylinder body of described hydraulic actuating cylinder (40) is arranged in described concave part, the piston rod of described hydraulic actuating cylinder (40) and the second end of described ramp (20) hinged.
4. railway truck according to claim 3, is characterized in that, described railway truck also comprises:
Second hinged seat (32), is arranged in the mounting groove of described concave part, and the cylinder body of described hydraulic actuating cylinder (40) is hinged on described second hinged seat (32);
3rd hinged seat (33), is arranged on the bottom of described ramp (20), and the piston rod of described hydraulic actuating cylinder (40) is hinged on described 3rd hinged seat (33).
5. railway truck according to claim 4, is characterized in that, described ramp (20) comprises plate body (21) and the deep beam (22) along described plate body (21) lateral arrangement.
6. railway truck according to claim 5, is characterized in that, described deep beam (22) is many, wherein a described deep beam (22) is provided with described 3rd hinged seat (33).
7. railway truck according to claim 1, is characterized in that, described underframe also comprises:
Two curb girders (50), two described curb girder (50) intervals arrange and are parallel to each other, and described two curb girders (50) are arranged on two relative side edge on described floor (10).
8. railway truck according to claim 1, is characterized in that, floor, described end (11) is provided with swingable First Transition plate (61).
9. a shipping loading and unloading system, comprises platform and railway truck, it is characterized in that, the railway truck of described railway truck according to any one of claim 1 to 8.
10. shipping loading and unloading system according to claim 9, it is characterized in that, described shipping loading and unloading system also comprises the second rebound (62), one end of described second rebound (62) can pivotable be connected with described platform, and the other end of described second rebound (62) coordinates with the floor, end (11) of described underframe.
CN201420733739.9U 2014-11-28 2014-11-28 Railway truck and shipping loading and unloading system Expired - Lifetime CN204323346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420733739.9U CN204323346U (en) 2014-11-28 2014-11-28 Railway truck and shipping loading and unloading system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420733739.9U CN204323346U (en) 2014-11-28 2014-11-28 Railway truck and shipping loading and unloading system

Publications (1)

Publication Number Publication Date
CN204323346U true CN204323346U (en) 2015-05-13

Family

ID=53159734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420733739.9U Expired - Lifetime CN204323346U (en) 2014-11-28 2014-11-28 Railway truck and shipping loading and unloading system

Country Status (1)

Country Link
CN (1) CN204323346U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017101683A1 (en) * 2015-12-17 2017-06-22 中车北京二七车辆有限公司 Railway wagon for transporting trucks and method for loading and unloading truck
CN109080713A (en) * 2018-08-16 2018-12-25 中车哈尔滨车辆有限公司 Pneumatic lifting depressed center car and coach transportation, discharging method
CN113879350A (en) * 2021-09-17 2022-01-04 中车长江运输设备集团有限公司 Road-rail combined transport system and railway transport vehicle

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017101683A1 (en) * 2015-12-17 2017-06-22 中车北京二七车辆有限公司 Railway wagon for transporting trucks and method for loading and unloading truck
US10569789B2 (en) 2015-12-17 2020-02-25 Crrc Qiqihar Rolling Stock Co., Ltd. Railway wagon for transporting trucks and method for loading and unloading truck
CN109080713A (en) * 2018-08-16 2018-12-25 中车哈尔滨车辆有限公司 Pneumatic lifting depressed center car and coach transportation, discharging method
CN113879350A (en) * 2021-09-17 2022-01-04 中车长江运输设备集团有限公司 Road-rail combined transport system and railway transport vehicle

Similar Documents

Publication Publication Date Title
US20130272827A1 (en) Container transport system
CN107757272A (en) A kind of road rail vehicle
CN204323346U (en) Railway truck and shipping loading and unloading system
CN104670349B (en) It is a kind of can Self-loading-unloading goods semitrailer
CN107336998A (en) Method and apparatus for intermodal container handling
CN103818395B (en) For supporting the device of the through freight rail vehicle with wide bottom rail wheel
CN109318921A (en) Multifunction station trolley and loading method
CN204323345U (en) Railway truck and shipping loading and unloading system
JP2006500269A (en) Vehicle adapted to different driving modes and driving method of such vehicle
US1786463A (en) Trailer construction
CN205990062U (en) Equipment for intermodal container handling
JP6267110B2 (en) Transportation and storage equipment for passenger cars
CN204341039U (en) Railway truck and shipping loading and unloading system
CN202827007U (en) Dual-purpose trailer used in highway and railway
CN103612584B (en) Self-discharging carriage is turned over after a kind of semi-mounted of heavier-duty
US2855115A (en) System for transferring vehicles to rail cars
DE102012008292A1 (en) Transportation system for land transportation of e.g. lorry, on track-bonded carrier vehicle i.e. rail vehicle, has stopping points provided close to main traffic paths of road traffic, and track sections extending parallel to traffic paths
CN107344682A (en) Car transverse direction handling facilities based on passenger train platform
CN104527670A (en) Railway freight car and cargo loading and unloading system
NL2002066C2 (en) TRAILER.
CN102700370A (en) Dual-purpose trailer for highways and railways
CN209159707U (en) Multifunction station trolley
KR102230791B1 (en) Piggyback Fratcar
US2815720A (en) Rail vehicles for transporting containers, vessels, street vehicles and the like
WO2011038475A1 (en) Improvement to double-deck railway wagons viii, typical lowered decks, optionally lowered double-decks with a reinforced structure and a floor for transporting different loads and containers, and bilevel railway wagons optionally combined with optionally lowered lowered bogies

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 161002 Qigihar City, Heilongjiang province Tiefeng District Plant Road No. 36

Patentee after: CRRC QIQIHAR ROLLING STOCK Co.,Ltd.

Patentee after: BEIJING TF HIGH-TECH Co.,Ltd.

Address before: 161002 Qigihar City, Heilongjiang province Tiefeng District Plant Road No. 36

Patentee before: QIQIHAR RAILWAY ROLLING STOCK Co.,Ltd.

Patentee before: BEIJING TF HIGH-TECH Co.,Ltd.

PP01 Preservation of patent right

Effective date of registration: 20241106

Granted publication date: 20150513

PP01 Preservation of patent right
CX01 Expiry of patent term

Granted publication date: 20150513

CX01 Expiry of patent term
PD01 Discharge of preservation of patent

Date of cancellation: 20241128

Granted publication date: 20150513

PD01 Discharge of preservation of patent