CN204212175U CN201420629639.1U CN201420629639U CN204212175U CN 204212175 U CN204212175 U CN 204212175U CN 201420629639 U CN201420629639 U CN 201420629639U CN 204212175 U CN204212175 U CN 204212175U
Authority
CN
China
Prior art keywords
embedded bolts
fixing bracket
embedded
auxiliary device
installing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420629639.1U
Other languages
Chinese (zh)
Inventor
李云龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Xinyuan Group Co Ltd
Technology Center of State Grid Xinyuan Group Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Xinyuan Group Co Ltd
Technology Center of State Grid Xinyuan Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Xinyuan Group Co Ltd, Technology Center of State Grid Xinyuan Group Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201420629639.1U priority Critical patent/CN204212175U/en
Application granted granted Critical
Publication of CN204212175U publication Critical patent/CN204212175U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型公开了一种安装预埋螺栓的定位辅助装置,包括:立体固定支架、预埋螺栓、垫片;其中,立体固定支架由十二块角钢组成;预埋螺栓焊接在立体固定支架内侧;垫片上设置有与预埋螺栓的直径匹配的孔,加装于立体固定支架上,用于固定预埋螺栓。本实用新型的安装预埋螺栓的定位辅助装置结构简单,成本小,效果显著,提高了安装预埋螺栓时的位置精度,利用该装置可缩短工程时间同时还能保证工程质量。

The utility model discloses a positioning auxiliary device for installing pre-embedded bolts, which comprises: a three-dimensional fixing bracket, a pre-embedded bolt and a spacer; wherein, the three-dimensional fixing bracket is composed of twelve pieces of angle steel; the pre-embedded bolts are welded on the inner side of the three-dimensional fixing bracket ; The spacer is provided with a hole matching the diameter of the embedded bolt, which is installed on the three-dimensional fixing bracket for fixing the embedded bolt. The positioning auxiliary device for installing pre-embedded bolts of the utility model has the advantages of simple structure, low cost and remarkable effect, and improves the position accuracy when installing pre-embedded bolts. The device can shorten the engineering time and ensure the engineering quality at the same time.

Description

一种安装预埋螺栓的定位辅助装置A positioning auxiliary device for installing embedded bolts

技术领域technical field

本实用新型涉及建筑施工技术领域,尤指一种安装预埋螺栓的定位辅助装置。The utility model relates to the technical field of building construction, in particular to a positioning auxiliary device for installing embedded bolts.

背景技术Background technique

现今,工程上有很多大型设备固定用螺栓在浇灌混凝土时采用预埋螺栓工艺,螺栓规格高、数量大且施工精度要求很高,一旦个别预埋螺栓的预埋产生了较大的偏差,将直接影响设备的正常安装和调试,提高预埋螺栓的位置精度是预埋螺栓工艺的重点和难点。Nowadays, there are many large-scale equipment fixing bolts that use pre-embedded bolt technology when pouring concrete. The bolts have high specifications, large quantities, and high construction accuracy requirements. It directly affects the normal installation and debugging of equipment, and improving the position accuracy of embedded bolts is the focus and difficulty of embedded bolt technology.

实用新型内容Utility model content

为了提高预埋螺栓的位置精度,本实用新型提出了一种辅助装置,能快速、准确的定位预埋螺栓,提高预埋螺栓安装的效率和质量,保证后续工作的正常开展。In order to improve the position accuracy of embedded bolts, the utility model proposes an auxiliary device, which can quickly and accurately locate embedded bolts, improve the efficiency and quality of embedded bolt installation, and ensure the normal development of follow-up work.

为达到上述目的,本实用新型提出了一种安装预埋螺栓的定位辅助装置,包括:立体固定支架、预埋螺栓、垫片;其中,所述立体固定支架由十二块角钢组成;所述预埋螺栓焊接在所述立体固定支架内侧;所述垫片上设置有与所述预埋螺栓的直径匹配的孔,加装于所述立体固定支架上,用于固定所述预埋螺栓。In order to achieve the above purpose, the utility model proposes a positioning auxiliary device for installing embedded bolts, including: a three-dimensional fixing bracket, embedded bolts, and gaskets; wherein, the three-dimensional fixing bracket is composed of twelve pieces of angle steel; The embedded bolts are welded on the inside of the three-dimensional fixing bracket; holes matching the diameter of the embedded bolts are arranged on the gasket, and are installed on the three-dimensional fixing bracket for fixing the embedded bolts.

进一步的,所述角钢的长度为50至200cm。Further, the length of the angle steel is 50 to 200 cm.

进一步的,所述预埋螺栓的直径为2至10cm。Further, the diameter of the embedded bolt is 2 to 10 cm.

进一步的,所述预埋螺栓的间距为50至180cm。Further, the distance between the embedded bolts is 50 to 180 cm.

进一步的,所述立体固定支架的六个面为矩形。Further, the six faces of the stereoscopic fixation bracket are rectangular.

进一步的,所述预埋螺栓之间保持平行,且垂直于所述立体固定支架的顶面。Further, the embedded bolts are kept parallel and perpendicular to the top surface of the three-dimensional fixing bracket.

进一步的,所述预埋螺栓分别与所述立体固定支架上部的一块角钢焊接以及下部相应的一块角钢焊接。Further, the embedded bolts are respectively welded to an angle steel on the upper part of the three-dimensional fixing bracket and a corresponding angle steel on the lower part.

进一步的,所述预埋螺栓分别与所述立体固定支架上部相邻的两块角钢焊接以及下部相应的两块角钢焊接。Further, the pre-embedded bolts are respectively welded to two adjacent angle steels on the upper part of the three-dimensional fixing bracket and to two corresponding angle steels on the lower part.

本实用新型的安装预埋螺栓的定位辅助装置结构简单,成本小,效果显著,提高了安装预埋螺栓时的位置精度,利用该装置可缩短工程时间同时还能保证工程质量。The positioning auxiliary device for installing pre-embedded bolts of the utility model has the advantages of simple structure, low cost and remarkable effect, and improves the position accuracy when installing pre-embedded bolts. The device can shorten the engineering time and ensure the engineering quality at the same time.

附图说明Description of drawings

此处所说明的附图用来提供对本实用新型的进一步理解,构成本申请的一部分,并不构成对本实用新型的限定。在附图中:The accompanying drawings described here are used to provide a further understanding of the utility model, constitute a part of the application, and do not constitute a limitation to the utility model. In the attached picture:

图1为本实用新型一实施例的预埋螺栓与立体固定支架的结构示意图。Fig. 1 is a structural schematic diagram of a pre-embedded bolt and a three-dimensional fixing bracket according to an embodiment of the present invention.

图2为本实用新型一实施例的安装预埋螺栓的定位辅助装置的结构示意图。Fig. 2 is a structural schematic diagram of a positioning auxiliary device for installing embedded bolts according to an embodiment of the present invention.

图3为本实用新型一实施例的安装预埋螺栓的定位辅助装置的侧视图。Fig. 3 is a side view of a positioning auxiliary device for installing embedded bolts according to an embodiment of the present invention.

图4为本实用新型一实施例的预埋螺栓与立体固定支架的焊接关系示意图。Fig. 4 is a schematic diagram of the welding relationship between the embedded bolt and the three-dimensional fixing bracket according to an embodiment of the present invention.

图5为本实用新型另一实施例的预埋螺栓与立体固定支架的焊接关系示意图。Fig. 5 is a schematic diagram of the welding relationship between the embedded bolt and the three-dimensional fixing bracket according to another embodiment of the present invention.

具体实施方式Detailed ways

以下配合图式及本实用新型的较佳实施例,进一步阐述本实用新型为达成预定实用新型目的所采取的技术手段。In the following, in conjunction with the drawings and preferred embodiments of the utility model, the technical means adopted by the utility model to achieve the intended purpose of the utility model are further described.

结合图1、图2及图3所示:Combined with Figure 1, Figure 2 and Figure 3:

图1为本实用新型一实施例的预埋螺栓与立体固定支架的结构示意图。Fig. 1 is a structural schematic diagram of a pre-embedded bolt and a three-dimensional fixing bracket according to an embodiment of the present invention.

图2为本实用新型一实施例的安装预埋螺栓的定位辅助装置的结构示意图。Fig. 2 is a structural schematic diagram of a positioning auxiliary device for installing embedded bolts according to an embodiment of the present invention.

图3为安装预埋螺栓的定位辅助装置的侧视图。Figure 3 is a side view of the positioning aid for installing embedded bolts.

该装置包括:立体固定支架1、预埋螺栓2、垫片3;其中,立体固定支架1由十二块角钢组成;预埋螺栓2焊接在立体固定支架1的内侧;垫片3上设置有与预埋螺栓2的直径匹配的孔,加装于立体固定支架1上,用于固定预埋螺栓2,同时可保证结构的强度与平整。The device includes: three-dimensional fixed bracket 1, embedded bolt 2, gasket 3; wherein, the three-dimensional fixed bracket 1 is composed of twelve pieces of angle steel; the embedded bolt 2 is welded on the inner side of the three-dimensional fixed bracket 1; the gasket 3 is provided with The hole matching the diameter of the embedded bolt 2 is additionally installed on the three-dimensional fixing bracket 1 for fixing the embedded bolt 2 while ensuring the strength and smoothness of the structure.

在本实施例中,所述角钢的长度为50至200cm,所述预埋螺栓2的直径为2至10cm,在实际中,可根据工程需要选取角钢的长度和预埋螺栓2的规格。In this embodiment, the length of the angle steel is 50 to 200 cm, and the diameter of the embedded bolt 2 is 2 to 10 cm. In practice, the length of the angle steel and the specifications of the embedded bolt 2 can be selected according to engineering requirements.

同样的,在实际工程中,可根据需要计算好预埋螺栓2的间距,再以此将其焊接至立体固定支架1内侧,一般相邻两个预埋螺栓2的间距为50至180cm。Similarly, in actual engineering, the distance between the embedded bolts 2 can be calculated according to the needs, and then welded to the inner side of the three-dimensional fixing bracket 1. Generally, the distance between two adjacent embedded bolts 2 is 50 to 180 cm.

本实用新型的辅助装置采用角钢材料做支撑构建立体固定支架1,将四根以上的预埋螺栓2焊接在立体固定支架1内侧,同时加装了垫片3,保证了预埋螺栓2的位置精度,同时提高了结构的强度。The auxiliary device of the utility model adopts angle steel material as a support to build a three-dimensional fixed bracket 1, and more than four embedded bolts 2 are welded on the inner side of the three-dimensional fixed bracket 1, and a gasket 3 is added at the same time to ensure the position of the embedded bolts 2 precision while increasing the strength of the structure.

在本实施例中,所述立体固定支架1的六个面为矩形,也可以都为正方形,具体形状可根据实际需要选择。In this embodiment, the six faces of the three-dimensional fixing bracket 1 are rectangular, or all may be square, and the specific shape can be selected according to actual needs.

在本实施例中,预埋螺栓2之间保持平行,且垂直于所述立体固定支架1的顶面。In this embodiment, the embedded bolts 2 are kept parallel and perpendicular to the top surface of the three-dimensional fixing bracket 1 .

应用本实用新型提出的辅助装置时,首先可计算预埋螺栓2的预埋位置,并以此位置将预埋螺栓2焊接到立体固定支架1上;When applying the auxiliary device proposed by the utility model, the pre-embedded position of the pre-embedded bolt 2 can be calculated first, and the pre-embedded bolt 2 can be welded to the three-dimensional fixing bracket 1 at this position;

然后将立体固定支架1固定到欲安装的位置,在浇筑立体固定支架1附近的混凝土时,要缓慢浇筑,保证立体固定支架1的位置不会变化,保证设备的安装精度。Then the three-dimensional fixed support 1 is fixed to the position to be installed. When pouring the concrete near the three-dimensional fixed support 1, pour it slowly to ensure that the position of the three-dimensional fixed support 1 will not change and ensure the installation accuracy of the equipment.

图4为本实用新型一实施例的预埋螺栓与立体固定支架的焊接关系示意图。如图4所示,预埋螺栓2分别与所述立体固定支架1上部的一块角钢焊接以及下部相应的一块角钢焊接。Fig. 4 is a schematic diagram of the welding relationship between the embedded bolt and the three-dimensional fixing bracket according to an embodiment of the present invention. As shown in FIG. 4 , the embedded bolts 2 are respectively welded to an angle steel on the upper part of the three-dimensional fixing bracket 1 and to a corresponding angle steel on the lower part.

图5为本实用新型另一实施例的预埋螺栓与立体固定支架的焊接关系示意图。如图5所示,预埋螺栓2分别与所述立体固定支架1上部相邻的两块角钢焊接以及下部相应的两块角钢焊接。Fig. 5 is a schematic diagram of the welding relationship between the embedded bolt and the three-dimensional fixing bracket according to another embodiment of the present invention. As shown in FIG. 5 , the pre-embedded bolts 2 are respectively welded to two adjacent angle steels on the upper part of the three-dimensional fixing bracket 1 and to two corresponding angle steels on the lower part.

本实用新型的安装预埋螺栓的定位辅助装置结构简单,成本小,效果显著,提高了安装预埋螺栓时的位置精度,利用该装置可缩短工程时间同时还能保证工程质量。The positioning auxiliary device for installing pre-embedded bolts of the utility model has the advantages of simple structure, low cost and remarkable effect, and improves the position accuracy when installing pre-embedded bolts. The device can shorten the engineering time and ensure the engineering quality at the same time.

以上所述的具体实施例,对本实用新型的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本实用新型的具体实施例而已,并不用于限定本实用新型的保护范围,凡在本实用新型的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The specific embodiments described above further describe the purpose, technical solutions and beneficial effects of the present utility model in detail. Within the protection scope of the utility model, any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the utility model shall be included in the protection scope of the utility model.

Claims (8)

1.一种安装预埋螺栓的定位辅助装置,其特征在于,包括:立体固定支架、预埋螺栓、垫片;其中,1. A positioning aid for installing pre-embedded bolts, characterized in that it comprises: three-dimensional fixing brackets, pre-embedded bolts, gaskets; wherein, 所述立体固定支架由十二块角钢组成;所述预埋螺栓焊接在所述立体固定支架内侧;所述垫片上设置有与所述预埋螺栓的直径匹配的孔,加装于所述立体固定支架上,用于固定所述预埋螺栓。The three-dimensional fixing bracket is composed of twelve pieces of angle steel; the embedded bolts are welded on the inside of the three-dimensional fixing bracket; the gasket is provided with holes matching the diameter of the embedded bolts, and is installed on the The three-dimensional fixing bracket is used to fix the embedded bolts. 2.根据权利要求1所述的安装预埋螺栓的定位辅助装置,其特征在于,所述角钢的长度为50至200cm。2. The positioning auxiliary device for installing embedded bolts according to claim 1, wherein the length of the angle steel is 50 to 200 cm. 3.根据权利要求1所述的安装预埋螺栓的定位辅助装置,其特征在于,所述预埋螺栓的直径为2至10cm。3. The positioning auxiliary device for installing embedded bolts according to claim 1, characterized in that, the diameter of the embedded bolts is 2 to 10 cm. 4.根据权利要求2所述的安装预埋螺栓的定位辅助装置,其特征在于,所述预埋螺栓的间距为50至180cm。4 . The positioning auxiliary device for installing embedded bolts according to claim 2 , wherein the distance between the embedded bolts is 50 to 180 cm. 5.根据权利要求1所述的安装预埋螺栓的定位辅助装置,其特征在于,所述立体固定支架的六个面为矩形。5. The positioning auxiliary device for installing embedded bolts according to claim 1, wherein the six faces of the three-dimensional fixing bracket are rectangular. 6.根据权利要求1所述的安装预埋螺栓的定位辅助装置,其特征在于,所述预埋螺栓之间保持平行,且垂直于所述立体固定支架的顶面。6 . The positioning auxiliary device for installing embedded bolts according to claim 1 , wherein the embedded bolts are kept parallel and perpendicular to the top surface of the three-dimensional fixing bracket. 7 . 7.根据权利要求1所述的安装预埋螺栓的定位辅助装置,其特征在于,所述预埋螺栓分别与所述立体固定支架上部的一块角钢焊接以及下部相应的一块角钢焊接。7. The positioning auxiliary device for installing embedded bolts according to claim 1, wherein the embedded bolts are respectively welded to an angle steel on the upper part of the three-dimensional fixing bracket and a corresponding angle steel on the lower part. 8.根据权利要求1所述的安装预埋螺栓的定位辅助装置,其特征在于,所述预埋螺栓分别与所述立体固定支架上部相邻的两块角钢焊接以及下部相应的两块角钢焊接。8. The positioning auxiliary device for installing embedded bolts according to claim 1, wherein the embedded bolts are respectively welded to two adjacent angle steels on the upper part of the three-dimensional fixing bracket and welded to two corresponding angle steels on the lower part .
CN201420629639.1U 2014-10-28 2014-10-28 A kind of positioning auxiliary device installing pre-embedded bolt Expired - Lifetime CN204212175U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420629639.1U CN204212175U (en) 2014-10-28 2014-10-28 A kind of positioning auxiliary device installing pre-embedded bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420629639.1U CN204212175U (en) 2014-10-28 2014-10-28 A kind of positioning auxiliary device installing pre-embedded bolt

Publications (1)

Publication Number Publication Date
CN204212175U true CN204212175U (en) 2015-03-18

Family

ID=52980861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420629639.1U Expired - Lifetime CN204212175U (en) 2014-10-28 2014-10-28 A kind of positioning auxiliary device installing pre-embedded bolt

Country Status (1)

Country Link
CN (1) CN204212175U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107816055A (en) * 2016-09-14 2018-03-20 复凌科技(上海)有限公司 A kind of built-in fitting and preparation method thereof
CN108149866A (en) * 2017-12-26 2018-06-12 中国十七冶集团有限公司 PC stair cast-in-place node pre-cast bolt positioning devices and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107816055A (en) * 2016-09-14 2018-03-20 复凌科技(上海)有限公司 A kind of built-in fitting and preparation method thereof
CN108149866A (en) * 2017-12-26 2018-06-12 中国十七冶集团有限公司 PC stair cast-in-place node pre-cast bolt positioning devices and method

Similar Documents

Publication Publication Date Title
CN203891058U (en) Built-in foundation bolt positioning tool for fixed type tower crane foundation
CN204212175U (en) A kind of positioning auxiliary device installing pre-embedded bolt
CN203866831U (en) Telescopic splicing guide frame for large-diameter steel protecting cylinder
CN103806426B (en) Earth pressure gauge adjustable position fixed installation device
CN203795843U (en) Novel construction joint formwork
CN204199318U (en) Multi-purpose Iron Tower Foundation Anchor Bolt Positioning Formwork Device
CN205742554U (en) A kind of steel column and the Mixed Architecture of beams of concrete
CN204921558U (en) A interim connecting device that is used for component and bracket to dock
CN204152216U (en) The assembling operating platform that a kind of Construction of Steel Structure is general
CN206941823U (en) A kind of shock isolating pedestal
CN103850266A (en) Multipurpose positioning template device for foundation bolt of iron tower and positioning method
CN204876360U (en) Protection device of protective layer thickness of concrete simple beam
CN204024087U (en) The accurate preburied positioning device of a kind of steel work lattice column pedestal anchor bolt
CN203485284U (en) T-shaped beam steel formwork structure
CN204418654U (en) For the aluminum alloy pattern plate between body of wall
CN204139622U (en) Adjustable segmented column steel bar positioning fixture
CN204418705U (en) Stone bolt erecting device
CN207004016U (en) A kind of horizon adjustable binder template stationary fixture
CN202248862U (en) Pipe holder for plugging gap
CN205330152U (en) A steel form for concrete placement
CN206554526U (en) A kind of built-in fitting fixing device
CN204343154U (en) Assembled continuous rigid frame bridge steel tie beam
CN203795854U (en) Preformed hole formwork fixing device for bare concrete floor
CN204677892U (en) A kind of pipeline is shelved in advance
CN203905510U (en) High-precision embedded bolt mold

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20150318