CN204199657U - The construction operation platform of irregular ceiling - Google Patents
The construction operation platform of irregular ceiling Download PDFInfo
- Publication number
- CN204199657U CN204199657U CN201420526880.1U CN201420526880U CN204199657U CN 204199657 U CN204199657 U CN 204199657U CN 201420526880 U CN201420526880 U CN 201420526880U CN 204199657 U CN204199657 U CN 204199657U
- Authority
- CN
- China
- Prior art keywords
- ceiling
- construction
- operation platform
- platform
- irregular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 71
- 230000001788 irregular Effects 0.000 title claims abstract description 49
- 230000003044 adaptive effect Effects 0.000 claims abstract description 4
- 241000282326 Felis catus Species 0.000 claims description 5
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 238000005034 decoration Methods 0.000 abstract description 9
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 239000011521 glass Substances 0.000 description 3
- 238000007493 shaping process Methods 0.000 description 3
- 239000004567 concrete Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000000465 moulding Methods 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model relates to a kind of construction operation platform of irregular ceiling, comprising: be located at the brace table in ceiling agent structure; The stepped operation platform of adaptive irregular ceiling, props up and is located on described brace table, be provided with the pulley along described brace table slippage bottom described operating platform.Adopt on brace table and stepped operation platform is set, meet the constructing operation of irregular ceiling, eliminate the operation of setting up and removing full hall handling frame, improve efficiency of construction, do not take ground decoration engineering construction work plane simultaneously, the ground decoration engineering that can make launches construction simultaneously, has not only saved construction cost, but also highly shortened the integral construction duration.Arrange pulley in the bottom of operating platform, operating personnel are after place construction terminates, and can promote the construction that operating platform carries out next place, operating platform has the feature of conveniently moving.
Description
Technical field
The utility model relates to the realm of building construction, espespecially a kind of construction operation platform of irregular ceiling.
Background technology
Along with more and more higher to the pursuit of architectural appearance moulding, the light shaft ceiling frequency of occurrences that is special-shaped, irregular structure is also more and more higher, this brings more difficulty also to the construction of ceiling, adopt the Normal practice setting up full hall handling frame bottom light shaft ceiling, not only need the setting up of at substantial, remove the scaffold time, construction efficiency is low, and takies the work plane of ground decoration engineering, has a strong impact on integrated engineering progress.
Utility model content
The purpose of this utility model is the defect overcoming prior art, a kind of construction operation platform of irregular ceiling is provided, the consumptive material adopting full hall handling frame to bring when solving the construction of irregular ceiling is consuming time, construction efficiency is low, take the work plane of ground decoration engineering and affect the problems such as programming.
The technical scheme realizing above-mentioned purpose is:
The construction operation platform of a kind of irregular ceiling of the utility model, comprising:
Be located at the brace table in ceiling agent structure;
Be located on described brace table, the stepped operation platform of adaptive irregular ceiling, be provided with the pulley along described brace table slippage bottom described operating platform.
Adopt on brace table and stepped operation platform is set, meet the constructing operation of irregular ceiling, eliminate the operation of setting up and removing full hall handling frame, improve efficiency of construction, do not take ground decoration engineering construction work plane simultaneously, the ground decoration engineering that can make launches construction simultaneously, has not only saved construction cost, but also highly shortened the integral construction duration.Arrange pulley in the bottom of operating platform, operating personnel are after place construction terminates, and can promote the construction that operating platform carries out next place, operating platform has the feature of conveniently moving.
The further improvement of the construction operation platform of the irregular ceiling of the utility model is, described brace table is for together to build formation with described ceiling agent structure; Described ceiling agent structure comprises two strutbeams be oppositely arranged, and described brace table is two plates that waft of building the inner side being formed at two described strutbeams respectively, and described stepped operation platform is located at described in two and wafts on plate.
The further improvement of the construction operation platform of the irregular ceiling of the utility model is, described operating platform comprises base, column, crossbeam and scaffold floor, Length discrepancy between described column and straggly are located on described base, described crossbeam is located on described column, described scaffold floor is layed on described crossbeam, and the bottom of described base is located at by described pulley.
The further improvement of the construction operation platform of the irregular ceiling of the utility model is, described scaffold floor be provided with guard rail all around.
The further improvement of the construction operation platform of the irregular ceiling of the utility model is, described operating platform also includes raker beam, is located between described column for oblique.
The further improvement of the construction operation platform of the irregular ceiling of the utility model is, described operating platform also comprises cat ladder, is located at the both sides of described operating platform.
The further improvement of the construction operation platform of the irregular ceiling of the utility model is, described brace table is fixed with safety guard net, and described safety guard net is located at the below of described operating platform.
The further improvement of the construction operation platform of the irregular ceiling of the utility model is, described pulley is provided with locking part.
Accompanying drawing explanation
Fig. 1 is the structural representation of the construction operation platform of the irregular ceiling of the utility model;
Fig. 2 is the top view of the construction operation platform of the irregular ceiling of the utility model;
Fig. 3 is the lateral view of the construction operation platform of the irregular ceiling of the utility model; And
Fig. 4 is the construction operation platform of the irregular ceiling of the utility model and the structural representation of irregular ceiling.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
Consult Fig. 1, show the structural representation of the construction operation platform of the irregular ceiling of the utility model.The construction operation platform of the irregular ceiling of the utility model comprises the stepped operation platform of adaptive irregular ceiling, this operating platform props up on the brace table be located in ceiling agent structure, such structure can eliminate the operation of setting up and removing full hall handling frame, improves efficiency of construction.And do not take ground decoration engineering construction work plane simultaneously, greatly can shorten the construction period.Be provided with pulley in the bottom of operating platform, by pulley, operating platform moved on brace table, for construction offers convenience.Be described below in conjunction with the structure of accompanying drawing to the construction operation platform of the irregular ceiling of the utility model.
Consult Fig. 1, show the structural representation of the construction operation platform of the irregular ceiling of the utility model, below in conjunction with Fig. 1, the construction operation platform of the irregular ceiling of the utility model is described.
As shown in Figure 1, the construction operation platform of the irregular ceiling of the utility model comprises brace table 20 and operating platform 30, and wherein brace table 20 is located in the ceiling agent structure 10 of irregular ceiling, with ceiling agent structure 10 be integrated build shaping.Brace table 20 is that the reinforced concrete radial that both sides, light shaft top are arranged wafts plate, together build shaping with ceiling agent structure 20, ceiling agent structure 10 comprises two strutbeams be oppositely arranged, and the plate that wafts is formed at the inner side of strutbeam respectively, and operating platform 30 is located at two and wafts on plate.Be fixed with safety guard net 201 between brace table 20, safety guard net 201 is located at the below of operating platform 30, and preventing has object to fall during work high above the ground, avoids the danger that placement in height produce are raw.Operating platform 30 is located on brace table 20, and this operating platform 30 adapts to irregular ceiling, and be stepped operation platform, operating personnel carry out the constructing operation of ceiling on operating platform 30.The bottom of operating platform 30 is provided with pulley 301, by the setting of pulley 301, operating platform 30 can be moved on brace table 20, the direction extended along brace table 20 is moved, after place ceiling construction, operating personnel can promote operating platform 30 to next place, carry out the ceiling construction at next place.Shown in composition graphs 2 and Fig. 3, operating platform 30 comprises base 302, column 303, crossbeam 304, scaffold floor 305, guard rail 306, raker beam 307, and cat ladder 308, length between column 303 is not etc., achieve the structure of stepped operating platform, 303, column is located on base 302, crossbeam 304 is located on column 303, scaffold floor 305 is layed on crossbeam 304, define the operating platform of standing for constructor, the bottom of base 302 is located at by pulley 301, pulley 301 is provided with locking part, when constructing on the operational platform, by locking part by temporary fixed for pulley 301, when Mobile operating platform 30, by the lock releasing of locking part.Guard rail 306 is located in the surrounding of scaffold floor 305, constructor is played to the effect of protection.Oblique of raker beam 307 is located between column 303, improves the stability of operating platform 30.Cat ladder 308 is located at the both sides of operating platform 30, and handled easily personnel climb up the operation scaffold floor 305 in operating platform 30 carrying out ceiling.
Consult shown in Fig. 4, show the construction operation platform of the irregular ceiling of the utility model and the structural representation of irregular ceiling, below in conjunction with Fig. 4, the structure of the construction operation platform of the irregular ceiling of the utility model is described in detail.
As shown in Figure 4, the construction operation platform of the irregular ceiling of the utility model increases concrete and to waft plate in both sides, light shaft top, form brace table 20, both as moulding, be used as again the operating platform of supporting removable stairstepping.This steel concrete plate that wafts is that arc wafts plate, and together build shaping with ceiling agent structure 10, the arrangement of reinforcement of the plate that wafts is checked by design and determined, guarantees to meet safety requirements.According to the change in shape of light shaft glass ceiling, design the construction stepped operation platform 30 meeting glass ceiling 40, by force analysis, calculate the specification of material therefor, guarantee safe and reliable.The base 302 of operating platform 30 adopts 200mm*150mm*6mm steel square tube, staged platform column 303 and crossbeam 304 all adopt 50mm*50mm*3mm equal leg angle, and raker beam 307 is set with identical angle steel reinforces, tool-type scaffold floor 305 is set between top cross-bar 304 as operating platform, the surrounding of scaffold floor 305 arranges guard rail 306, left and right sides angle steel welding arranges upper and lower cat ladder, and the corner of steel square tube base 302 arranges pulley 301.Adopt between all parts of operating platform 30 and be welded and fixed, when the construction operation platform of the irregular ceiling of the utility model uses, the safety guard net 201 be positioned at below operating platform 30 is set on brace table, prevents high-altitude junk.Adopt tower crane by operating platform 30 Integral lifting on brace table 20, after operating platform 30 is in place, operating personnel carry out keel welding and glass installation, after completing place's ceiling from the cat ladder of both sides to scaffold floor 305, operating personnel walk lower platform, promote platform and carry out next place's ceiling construction.Bottom light shaft, ground surface works also can launch construction simultaneously, improves efficiency of construction.
The beneficial effect of the construction operation platform of the irregular ceiling of the utility model is:
Adopt on brace table and stepped operation platform is set, meet the constructing operation of irregular ceiling, eliminate the operation of setting up and removing full hall handling frame, improve efficiency of construction, do not take ground decoration engineering construction work plane simultaneously, the ground decoration engineering that can make launches construction simultaneously, has not only saved construction cost, but also highly shortened the integral construction duration.Arrange pulley in the bottom of operating platform, operating personnel are after place construction terminates, and can promote the construction that operating platform carries out next place, operating platform has the feature of conveniently moving.
Below embodiment has been described in detail the utility model by reference to the accompanying drawings, and those skilled in the art can make many variations example to the utility model according to the above description.Thus, some details in embodiment should not formed restriction of the present utility model, the utility model by the scope that defines using appended claims as protection domain of the present utility model.
Claims (8)
1. a construction operation platform for irregular ceiling, is characterized in that, comprising:
Be located at the brace table in ceiling agent structure;
Be located on described brace table, the stepped operation platform of adaptive irregular ceiling, the bottom of described stepped operation platform is provided with the pulley along described brace table slippage.
2. the construction operation platform of irregular ceiling as claimed in claim 1, is characterized in that, described brace table and described ceiling agent structure together build formation; Described ceiling agent structure comprises two strutbeams be oppositely arranged, and described brace table is two plates that waft of building the inner side being formed at two described strutbeams respectively, and described stepped operation platform is located at described in two and wafts on plate.
3. the construction operation platform of irregular ceiling as claimed in claim 1, it is characterized in that, described operating platform comprises base, column, crossbeam and scaffold floor, Length discrepancy between described column and straggly are located on described base, described crossbeam is located on described column, described scaffold floor is layed in form stepped operation platform on described crossbeam, and the bottom of described base is located at by described pulley.
4. the construction operation platform of irregular ceiling as claimed in claim 3, is characterized in that, described scaffold floor be provided with guard rail all around.
5. the construction operation platform of irregular ceiling as claimed in claim 3, is characterized in that, described operating platform also includes raker beam, is located between described column for oblique.
6. the construction operation platform of irregular ceiling as claimed in claim 3, is characterized in that, described operating platform also comprises cat ladder, is located at the both sides of described operating platform.
7. the construction operation platform of irregular ceiling as claimed in claim 1, is characterized in that, described brace table is fixed with safety guard net, and described safety guard net is located at the below of described operating platform.
8. the construction operation platform of irregular ceiling as claimed in claim 1, is characterized in that, described pulley is provided with locking part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420526880.1U CN204199657U (en) | 2014-09-15 | 2014-09-15 | The construction operation platform of irregular ceiling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420526880.1U CN204199657U (en) | 2014-09-15 | 2014-09-15 | The construction operation platform of irregular ceiling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204199657U true CN204199657U (en) | 2015-03-11 |
Family
ID=52657629
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420526880.1U Expired - Fee Related CN204199657U (en) | 2014-09-15 | 2014-09-15 | The construction operation platform of irregular ceiling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204199657U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106193476A (en) * | 2015-05-05 | 2016-12-07 | 五冶集团上海有限公司 | A kind of concealed roofing tile mounting platform |
CN107816223A (en) * | 2017-12-01 | 2018-03-20 | 江苏沪宁钢机股份有限公司 | A kind of safety and stability type platform canopy station and its installation method |
-
2014
- 2014-09-15 CN CN201420526880.1U patent/CN204199657U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106193476A (en) * | 2015-05-05 | 2016-12-07 | 五冶集团上海有限公司 | A kind of concealed roofing tile mounting platform |
CN107816223A (en) * | 2017-12-01 | 2018-03-20 | 江苏沪宁钢机股份有限公司 | A kind of safety and stability type platform canopy station and its installation method |
CN107816223B (en) * | 2017-12-01 | 2023-07-28 | 江苏沪宁钢机股份有限公司 | Safe and stable type station canopy station house and installation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201506699U (en) | Electric lifting bridge rack for construction | |
CN101824910B (en) | Quick template supporting construction method of elevator shaft | |
CN206088920U (en) | Construction scaffold | |
CN207144449U (en) | A kind of hoistway operation platform | |
CN106013776A (en) | Hydraulic climbing type elevator shaft finalization operation platform and construction method | |
CN206513052U (en) | A kind of spring layer support and hydraulic pressure spring layer climbing system | |
CN105908960B (en) | Scaffold for large space construction | |
CN106012824A (en) | Movable bridge anti-collision guardrail construction operation trolley | |
CN206986744U (en) | Steel box-girder flange area slidably construction operation platform | |
CN103485574B (en) | A kind of granulation tower tower top structure of reinforced concrete method | |
CN204199657U (en) | The construction operation platform of irregular ceiling | |
KR101339284B1 (en) | Safety ladder for concrete mold | |
CN104989111A (en) | Construction method for steel structure high-rise hoisting | |
CN206053393U (en) | One kind can have enough to meet the need steel stair operating platform | |
JP2015055062A (en) | Lift type work scaffold device of tower crane | |
CN203175016U (en) | Movable type overhanging operation platform car | |
CN204238537U (en) | A kind of elevated hoistway operation platform | |
CN104131635A (en) | Method and platform for constructing peripheral shear wall of prefabricated staircase | |
CN205206274U (en) | Scaffold for building construction | |
CN207003970U (en) | A kind of building scaffold being easily installed | |
CN216947940U (en) | Box culvert external mold lifting device | |
CN205617770U (en) | Overhanging movable type edge construction operation platform | |
CN203924652U (en) | The operation platform of periphery shear wall between a kind of precast stair | |
CN204126237U (en) | A kind of elevator hoistway construction platform | |
CN204059908U (en) | Hydraulic climbing device for discharging |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150311 |