CN204199157U
CN204199157U CN201420611606.4U CN201420611606U CN204199157U CN 204199157 U CN204199157 U CN 204199157U CN 201420611606 U CN201420611606 U CN 201420611606U CN 204199157 U CN204199157 U CN 204199157U
Authority
CN
China
Prior art keywords
walking mechanism
cantilever
post
crane
assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420611606.4U
Other languages
Chinese (zh)
Inventor
李仲海
宋刚
郭高
李依伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dunhua Jiusheng Environmental Protection Building Material Co ltd
Jilin Jiusheng Ecological Environmental Technologies Co ltd
Jilin Jiusheng Machining Co ltd
Jilin Xusheng Environmental Building Materials Co ltd
Original Assignee
JILIN JIUSHENG BUILDING MATERIALS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JILIN JIUSHENG BUILDING MATERIALS CO Ltd filed Critical JILIN JIUSHENG BUILDING MATERIALS CO Ltd
Priority to CN201420611606.4U priority Critical patent/CN204199157U/en
Application granted granted Critical
Publication of CN204199157U publication Critical patent/CN204199157U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model relates to a kind of construction equipment of urban road construction, specifically the efficient assembled all-in-one machine special of a kind of prefabricated assembled roadbase construction.This all-in-one comprises truss, main crane, crawler type walking mechanism, cantilever crane assembly and electric control box, described truss is by main beam and to be arranged on main beam two ends be that two vertical beams of herringbone structure are formed, described main crane is arranged on the main beam of truss, described crawler type walking mechanism is arranged on below the vertical beam of everyone character form structure, described two cantilever crane assemblies are arranged on the side of the vertical beam of everyone character form structure, described cantilever crane assembly is by only post, only post electric rotating machine, be arranged on the cantilever above only post and be arranged on the cantilever crane formation on cantilever, described crawler type walking mechanism is made up of walking mechanism support body and two the triangle track rail assemblies be arranged on below walking mechanism support body.The utility model adopts gantry type frame structure, connection and reasonable arrangement, safe and reliable, easy to loading and unloading, efficiency of mating formation is high, simple to operate; This all-in-one can be widely used in mat formation precast concrete segment, precast concrete manhole and mating formation of various buried pipeline of municipal construction and execute.

Description

The assembled all-in-one of road construction
Technical field
The utility model relates to a kind of construction equipment of urban road construction, specifically the efficient assembled all-in-one machine special of a kind of prefabricated assembled roadbase construction.
Background technology
In existing urban road construction, roadbase sequence of construction is mainly: excavation foundation → surveying and locating → installation form → concrete mixing → concrete transportation → pave and vibrate → whole and form removal → maintenance.Build townie interference for reducing in road construction and maintenance engineering, resume traffic as early as possible, construction operation is completed within comparatively short period, early development is for the concrete precast block of the concrete base layer of alternative conventional concrete cast-in-place construction, carry out mating formation in Practical Project in process of the test and find, owing to there is no special-purpose machinery, carry out in the process of mating formation at use autocrane, find the problems such as efficiency and expense, be in particular in: 1., the concrete precast block construction apparatus plane such as (mobile crane plant equipment), vertical occupation of land space is large, the large place of assembled needs arranged side by side, comparatively cannot construct in narrow road face, the operation of half range road can not be realized, the requirement that half range road is current, the backlash distance of the assembled suspension arm of crane of file, efficiency is low.2., enough obstruction clearance criterias are needed, substantially there is the various pipe network infrastructure such as many energising cables and communication due to urban road overhead, easily touch cable during construction and cause power-off and even Danger Electric shock risk occur and affect the similar incidents such as the electricity consumption such as nearby residents, business.3., batch (-type) operation, limit by crane brachium during consolidation service, lay one section and will move a crane: receive arm, receive leg, movement, to move back, boom, mobilely need more than 10 minutes time, no matter parallel operation or file operation when unloading at every turn, often unload a car prefabricated section and all want jenny, assembled efficiency is low, and prefabricated section assembled (only) time average is 2 minutes, and every 4 row move a train, 96 points+15 minutes, assembled 27 pieces per hour.4., comprehensively cause costly assembled, raise road construction overall cost.
Summary of the invention
The purpose of this utility model be to provide a kind of simple and reasonable, adopt gantry type frame structure, connection and reasonable arrangement, the efficient assembled all-in-one machine special of prefabricated assembled roadbase construction that safe and reliable, easy to loading and unloading, efficiency of mating formation is high, simple to operate; This all-in-one can be widely used in municipal construction and to mat formation the pavement construction of precast concrete segment, precast concrete manhole and various buried pipeline.
The purpose of this utility model is achieved in that this all-in-one comprises truss, main crane, crawler type walking mechanism, cantilever crane assembly and electric control box, described truss is by main beam and to be arranged on main beam two ends be that two vertical beams of herringbone structure are formed, described main crane is arranged on the main beam of truss, described crawler type walking mechanism is arranged on below the vertical beam of everyone character form structure, described two cantilever crane assemblies are arranged on the side of the vertical beam of everyone character form structure, described cantilever crane assembly is by only post, only post electric rotating machine, be arranged on the cantilever above only post and be arranged on the cantilever crane formation on cantilever, described crawler type walking mechanism is made up of walking mechanism support body and two the triangle track rail assemblies be arranged on below walking mechanism support body.
Described triangle track rail assembly is by structural frame, the regulating wheel that is arranged on driving wheel above structural frame, is arranged on two ends below structural frame by two tensioning frames, and four support wheels between the regulating wheel being arranged on two ends below structural frame and the crawler belt be sleeved on outside driving wheel, tensioning frame and support wheel are formed.
Advantage of the present utility model and good effect are:
1, the speed of travel of the present utility model is 20-30 m/min; Hoisting velocity is 8 ms/min; Suspending arm rotary speed is 220o/ minute.
2, the crawler type walking mechanism of the utility model employing, adds stability and the skid resistance of equipment, and road pavement requires low simultaneously.
3, the utility model have employed gantry type frame structure, makes compact equipment, connection and reasonable arrangement; More safe and reliable, easy to loading and unloading in use.
4, the utility model is cheap, handling ease, operation and maintenance are with low cost.
5, the utility model efficiency of mating formation is high, simple to operate easy to learn, can be widely used in municipal construction and to mat formation the pavement construction of precast concrete segment, precast concrete manhole and various buried pipeline.
Accompanying drawing explanation
Fig. 1 is the utility model overall structure schematic diagram.
Fig. 2 is the elevation of the utility model Fig. 1.
Fig. 3 is the utility model cantilever crane assembly structure schematic diagram.
Fig. 4 is the utility model triangle track rail assembly forward projection structure chart.
Detailed description of the invention
By accompanying drawing 1, shown in 2: this all-in-one comprises truss 1, main crane 2, crawler type walking mechanism 3, cantilever crane assembly 4 and electric control box 5, described truss 1 is by main beam 6 and to be arranged on main beam 6 two ends be that two vertical beams 7 of herringbone structure are formed, described main crane 2 is arranged on the main beam 6 of truss 1, described crawler type walking mechanism 3 is arranged on below the vertical beam 7 of everyone character form structure, described two cantilever crane assemblies 4 are arranged on the side of the vertical beam 7 of everyone character form structure, described cantilever crane assembly 4 is by only post 8, only post electric rotating machine 9, the cantilever 10 be arranged on above only post 8 is formed with the cantilever crane 11 be arranged on cantilever 10, described crawler type walking mechanism 3 is made up of walking mechanism support body 12 and two the triangle track rail assemblies 13 be arranged on below walking mechanism support body 12.
Described electric control box 5 to be arranged on walking mechanism support body 12 and control main crane 2, crawler type walking mechanism 3, cantilever crane assembly 4 work, two the cantilever crane assemblies 4 in described left and right high and low position different.
Shown in accompanying drawing 3: be provided with a support 20 between described only post 8 and support 20, described only post electric rotating machine 9 is arranged on support 20, and one end of described support 20 is provided with spacing blob of viscose 21.
Shown in accompanying drawing 4: described triangle track rail assembly 13 by structural frame 14, the regulating wheel 17 that is arranged on driving wheel 15 above structural frame 14, is arranged on structural frame 14 two ends below by two tensioning frames 16, four support wheels 18 between the regulating wheel 17 being arranged on structural frame 14 two ends below and the crawler belt 19 be sleeved on outside driving wheel 15, tensioning frame 16 and support wheel 18 are formed.
operating principle:
Entrucking with unload: operating personnel control crawler type walking mechanism 3 by relevant apparatus (Digiplex) subsidiary on electric control box 5 and drive assembled all-in-one to arrive assigned address, by main crane 2 sling prefabricated section and carry out left and right, move up and down put in transport vehicle or by prefabricated section from unloading in transport vehicle to scene, construction site.
Construction: carry out alternately construction operation simultaneously by two cantilevers being in height diverse location of cantilever crane assembly 4.Be specially, while only post electric rotating machine 9 drives cantilever 10 movement, prefabricated section is sling and slowly descends while outwards rotating to an angle general who has surrendered's prefabricated section to put to appointment job location by cantilever crane 11, operate cantilever crane 11 zero load rise while only post electric rotating machine 9 drives cantilever 10 afterwards and inwardly rotate to an angle and carry out the operation of slinging of next prefabricated section, two, the left and right cantilever of cantilever crane assembly 4 hockets the assembling construction work of prefabricated section in same operation unit simultaneously, after having constructed in the first operation unit, manipulation crawler type walking mechanism 3 drives assembled all-in-one to march to next operation unit, alternately operating is carried out by cantilever crane assembly 4, so repeatedly construct, until engineering terminates.

Claims (4)

1. the assembled all-in-one of road construction, it is characterized in that: this all-in-one comprises truss (1), main crane (2), crawler type walking mechanism (3), cantilever crane assembly (4) and electric control box (5), described truss (1) is by main beam (6) and to be arranged on main beam (6) two ends be that two vertical beams (7) of herringbone structure are formed, described main crane (2) is arranged on the main beam (6) of truss (1), described crawler type walking mechanism (3) is arranged on below the vertical beam (7) of everyone character form structure, described two cantilever crane assemblies (4) are arranged on the side of the vertical beam (7) of everyone character form structure, described cantilever crane assembly (4) is by only post (8), only post electric rotating machine (9), be arranged on the cantilever (10) above only post (8) and be arranged on cantilever crane (11) formation on cantilever (10), described crawler type walking mechanism (3) is made up of walking mechanism support body (12) and two the triangle track rail assemblies (13) be arranged on below walking mechanism support body (12).
2. the assembled all-in-one of a kind of road construction according to claim 1, it is characterized in that: described triangle track rail assembly (13) by structural frame (14), the regulating wheel (17) that is arranged on driving wheel (15) above structural frame (14), is arranged on structural frame (14) two ends below by two tensioning frames (16), four support wheels (18) between the regulating wheel (17) being arranged on structural frame (14) two ends below and be sleeved on crawler belt (19) formation of driving wheel (15), tensioning frame (16) and support wheel (18) outside.
3. the assembled all-in-one of a kind of road construction according to claim 1, it is characterized in that: between described only post (8) and support (20), be provided with a support (20), described only post electric rotating machine (9) is arranged on support (20), and one end of described support (20) is provided with spacing blob of viscose (21).
4. the assembled all-in-one of a kind of road construction according to claim 1, is characterized in that: two the cantilever crane assemblies (4) in described left and right high and low position different.
CN201420611606.4U 2014-10-22 2014-10-22 The assembled all-in-one of road construction Expired - Fee Related CN204199157U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420611606.4U CN204199157U (en) 2014-10-22 2014-10-22 The assembled all-in-one of road construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420611606.4U CN204199157U (en) 2014-10-22 2014-10-22 The assembled all-in-one of road construction

Publications (1)

Publication Number Publication Date
CN204199157U true CN204199157U (en) 2015-03-11

Family

ID=52657132

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420611606.4U Expired - Fee Related CN204199157U (en) 2014-10-22 2014-10-22 The assembled all-in-one of road construction

Country Status (1)

Country Link
CN (1) CN204199157U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105274929A (en) * 2014-10-22 2016-01-27 吉林省久盛绿色建材股份有限公司 All-in-one assembling machine for road construction
CN111188247A (en) * 2020-01-07 2020-05-22 中源宏宇建设集团有限公司 Road curb erection and laying equipment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105274929A (en) * 2014-10-22 2016-01-27 吉林省久盛绿色建材股份有限公司 All-in-one assembling machine for road construction
CN105274929B (en) * 2014-10-22 2017-07-28 吉林久盛生态环境科技股份有限公司 Road construction assembly all-in-one
CN111188247A (en) * 2020-01-07 2020-05-22 中源宏宇建设集团有限公司 Road curb erection and laying equipment

Similar Documents

Publication Publication Date Title
CN108343087B (en) Prefabricated part transportation and assembly equipment system and construction method thereof
CN105274929A (en) All-in-one assembling machine for road construction
JP2022169347A (en) Floor slab erection machine
CN205024717U (en) Construction equipment of city utility tunnel immersed tube section
CN103726421A (en) Height and span adjustable track paver for metro construction
CN103640862B (en) The transportation system of electrical equipment spare part
CN103938509A (en) Track panel laying equipment for medium-low-speed magnetic levitation tracks
CN102587284B (en) Independent derrick mast and beam plate mounting method
CN204199157U (en) The assembled all-in-one of road construction
CN110645004A (en) Method for turning over shield tunneling machine trolley in negative two-layer of operated station
CN210768900U (en) Translation device in shield machine station
CN202449737U (en) Main girder of electric single-girder crane
CN202465067U (en) Crane cart traveling mechanism with travel switch
CN114162735A (en) Floor hoisting method
CN102776840B (en) Mal-position assembly in-position method of truss bridge
CN203684019U (en) Height and span adjustable track laying machine for subway construction
CN206245344U (en) An installation vehicle used for assembling prefabricated and assembled comprehensive pipe gallery
CN202264775U (en) Pipeline transporting trolley
CN206092012U (en) Operation car is demolishd to subway deep tunnel reinforced concrete pipe piece
CN205171288U (en) Magnetism floats section of track and moves gantry crane
JP2006336392A (en) Bridge batch removal method
CN103410100B (en) The construction method of city intersection pedestrian overcrossing and integration of transporting and building machine
CN106368718A (en) Metro deep-buried tunnel reinforced concrete duct piece dismounting operation vehicle
CN201849911U (en) Conveying device for heavy equipment
CN204701627U (en) A kind of railway locomotive tune special purpose device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 136000, No. 5658, South First Street, Tiedong District, Siping City, Jilin

Patentee after: JILIN JIUSHENG ECOLOGICAL ENVIRONMENTAL TECHNOLOGIES Co.,Ltd.

Address before: 136000, No. 5658, South First Street, Tiedong District, Siping City, Jilin

Patentee before: JILIN JIUSHENG ECOLOGICAL ENVIRONMENTAL TECHNOLOGIES CO.,LTD.

TR01 Transfer of patent right

Effective date of registration: 20160219

Address after: 136000, No. 5658, South First Street, Tiedong District, Siping City, Jilin

Patentee after: JILIN JIUSHENG ECOLOGICAL ENVIRONMENTAL TECHNOLOGIES Co.,Ltd.

Patentee after: JILIN XUSHENG ENVIRONMENTAL BUILDING MATERIALS CO.,LTD.

Patentee after: DUNHUA JIUSHENG ENVIRONMENTAL PROTECTION BUILDING MATERIAL Co.,Ltd.

Patentee after: JILIN JIUSHENG MACHINING Co.,Ltd.

Address before: 136000, No. 5658, South First Street, Tiedong District, Siping City, Jilin

Patentee before: JILIN JIUSHENG ECOLOGICAL ENVIRONMENTAL TECHNOLOGIES Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150311

Termination date: 20181022