CN204098964U - A kind of waste heat recovery heat-insulation system of turbogenerator - Google Patents

A kind of waste heat recovery heat-insulation system of turbogenerator Download PDF

Info

Publication number
CN204098964U
CN204098964U CN201420473945.0U CN201420473945U CN204098964U CN 204098964 U CN204098964 U CN 204098964U CN 201420473945 U CN201420473945 U CN 201420473945U CN 204098964 U CN204098964 U CN 204098964U
Authority
CN
China
Prior art keywords
turbogenerator
waste heat
steam boiler
heat
insulation system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420473945.0U
Other languages
Chinese (zh)
Inventor
王庆楠
黄红华
曲玉强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SJS Ltd
Original Assignee
SJS Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SJS Ltd filed Critical SJS Ltd
Priority to CN201420473945.0U priority Critical patent/CN204098964U/en
Application granted granted Critical
Publication of CN204098964U publication Critical patent/CN204098964U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Engine Equipment That Uses Special Cycles (AREA)

Abstract

The utility model relates to oil drilling and extracting equipment field, in particular to a kind of waste heat recovery heat-insulation system of turbogenerator, comprise the turbogenerator driving well cementation fracturing pump, between the tail gas end of described turbogenerator and the outlet pipe with silencing apparatus, waste heat steam boiler is set, the feed-water end of this waste heat steam boiler is communicated with water storage cabinet, is communicated with after the hot output terminal connection gas holder of waste heat steam boiler with heat exchanger again.The utility model under extremely cold environment, effectively can reclaim the turbogenerator used heat of high-power well cementation fracturing unit, realizes the insulation in equipment and other regions, heat insulation work high-efficiency and economic, safe and reliable.

Description

A kind of waste heat recovery heat-insulation system of turbogenerator
Technical field
The utility model relates to oil drilling and extracting equipment field, particularly a kind of waste heat recovery heat-insulation system of turbogenerator.
Background technique
Along with the expansion in petroleum production region, a large amount of oil drilling and extracting equipments puts into (subzero 40 degrees Celsius) under extremely cold environment, needs a kind of reliable, economic heat-insulation system to maintain the normal work of equipment.At present, the heat insulation work in petroleum production process mainly adopts two kinds of methods.One is under general environment, is furnished with the equipment of diesel engine, carries out thermal cycle to maintain the insulation of himself by pipeline, but the insulation needs in the outer supporting region of the equipment that cannot realize.And because its calorific value produced is low, pipeline is complicated, and the insulation of general low temperature (subzero 20 degrees Celsius) only can be supplied to need, under extremely cold environment, be difficult to work, reliability is low.Two is increase independently steam boiler car or steam generation sled, and consume fuel oil extra in a large number, carry out heating and thermal insulation to other equipment, Economy is low, heat utilization ratio is low, and strengthens difficulty and the danger of site operation.
High-power well cementation fracturing unit configuration turbogenerator, as power source, all wants high several times compared with the diesel engine acc power of conventional equipment and efficiency, drive cement the well fracturing pump operation time, also produce a large amount of high-octane used heat.Turbogenerator used heat directly enters air primarily of its high-temp waste gas produced and takes away, and its calorific value is sustainable is stabilized in high temperature 550 degrees Celsius, more than 12 kilograms per second of mass flow rate.Reclaim the turbogenerator used heat of high-power well cementation fracturing unit, by the thermal requirement needed for equipment under enough satisfied extremely cold environment and the insulation of supporting region thereof.
Summary of the invention
The purpose of this utility model is to overcome above-mentioned deficiency, a kind of waste heat recovery heat-insulation system of turbogenerator is provided, this heat-insulation system can under extremely cold environment, the turbogenerator used heat of the high-power well cementation fracturing unit of effective recovery, realize the insulation in equipment and other regions, heat insulation work high-efficiency and economic, safe and reliable.
For realizing above-mentioned technical purpose, the scheme that the utility model provides is: a kind of waste heat recovery heat-insulation system of turbogenerator, comprise the turbogenerator driving well cementation fracturing pump, between the tail gas end of described turbogenerator and the outlet pipe with silencing apparatus, waste heat steam boiler is set, the feed-water end of this waste heat steam boiler is communicated with water storage cabinet, is communicated with after the hot output terminal connection gas holder of waste heat steam boiler with heat exchanger again.
And arrange between described turbogenerator and outlet pipe with waste heat steam boiler and the bypass line connected, this bypass line has control valve.
And, between described waste heat steam boiler and described water storage cabinet, small pump is set.
The utility model also provides a kind of turbogenerator used heat that reclaims to carry out heating heat preserving method to oil drilling and extracting equipment, comprises the steps.
Step one, by turbogenerator for the operation of well cementation fracturing pump provides the high-temp waste gas produced during power to lead to steam boiler.
Step 2, passes into steam boiler by water source, and after water is heated, gasification forms high-temperature steam; High-temp waste gas cools after heat exchange, by having the emission by exhaust pipe of silencing apparatus.
Step 3, after high-temperature steam being passed into the voltage stabilizing of gas holder buffering, is transported to heat exchanger, carries out heating and thermal insulation by heat exchanger to whole equipment and supporting region.
And described water source is the water in water storage cabinet.
The beneficial effects of the utility model are, the high-temp waste gas produced when utilizing turbogenerator to work, for waste heat steam boiler provides energy to prepare a large amount of high-temperature steam, heat needed for insulation of equipment under extremely cold environment is provided, can be used for the heat preservation and heat supply in equipment and supporting region, also can be used for other operation needs that scene needs steam; This programme is simple and reasonable, can be incorporated in high-power well cementation fracturing unit, be conducive to the lightweight of equipment, and without the need to newly-increased thermal source, waste heat energy regenerating utilization ratio is high, improves safety reliability, the Economy of site operation.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Wherein, 1. turbogenerator, 2. cement the well fracturing pump, 3. waste heat steam boiler, 4. control valve, 5. have the outlet pipe of baffler, 6. gas holder, 7. heat exchanger, 8. small pump, 9. water storage cabinet.
Embodiment
Below in conjunction with drawings and Examples, the utility model is described in further detail.
The present embodiment provides a kind of waste heat recovery heat-insulation system of turbogenerator, as shown in Figure 1, comprise the turbogenerator 1 driving well cementation fracturing pump 2, the waste gas outlet of turbogenerator 1 is connected with the smoke inlet of waste heat steam boiler 3, to connect after the smoke outlet of waste heat steam boiler 3 baffler and outlet pipe 5, form energy input drain passageway prepared by steam.The waste gas outlet of turbogenerator 1 is connected with the entrance of control valve 4, the outlet joint noise reduction device of control valve 4 and outlet pipe 5, bypass circulation when formation Waste Heat Recovery System (WHRS) is out of service.
The steam (vapor) outlet of waste heat steam boiler 3 is connected with the entrance of gas holder 6, and the outlet of gas holder 6 connects the entrance of heat exchanger 7, forms the thermal source supply passage of heating and thermal insulation system.Gas holder 6 leaves air outlet, on-the-spot other operations needing steam of supply.The water inlet of waste heat steam boiler 3 is connected with the water outlet of water storage cabinet 9, form prepared by steam for water passage, can the steam preparation amount of control system by the adjustment for water passage.What be connected to form at waste heat steam boiler 3 and water storage cabinet 9 arranges small pump 8 on water passage, can ensure persistency, stability prepared by steam.
The utility model also provides a kind of turbogenerator used heat that reclaims to carry out heating heat preserving method to oil drilling and extracting equipment, comprises the steps.
Step one, by turbogenerator for the operation of well cementation fracturing pump provides the high-temp waste gas produced during power to lead to steam boiler.
Step 2, passes into steam boiler by water source, and after water is heated, gasification forms high-temperature steam; High-temp waste gas cools after heat exchange, by having the emission by exhaust pipe of silencing apparatus.
Step 3, after high-temperature steam being passed into the voltage stabilizing of gas holder buffering, is transported to heat exchanger, carries out heating and thermal insulation by heat exchanger to whole equipment and supporting region.
The implementation process of the Waste Heat Recovery System (WHRS) of this turbogenerator of the utility model is: when high-power well cementation fracturing unit runs, and turbogenerator 1 drives well cementation fracturing pump 2 to carry out field operation.Meanwhile, turbogenerator 1 produces a large amount of high-temp waste gas, collects the smoke inlet entering waste heat steam boiler 3 through fume pipe; In waste heat steam boiler 3, heat exchange is fully carried out in high-temp waste gas and boiler feed water, and high-temp waste gas releases energy after cooling, discharges through baffler and outlet pipe 5, and after boiler feed water absorption heat, vaporization forms high-temperature steam; High-temperature steam input gas holder 6, gas holder 6 plays the effect of buffering voltage stabilizing, then is transported to heat exchanger 7 through gas holder 6, carries out heating and thermal insulation by heat exchanger 7 to whole equipment and supporting region; The boiler feed water that waste heat steam boiler 3 vaporization consumes, constantly supply supplementary from water storage cabinet 9 by small pump 8, and the turbogenerator 1 of fracturing work of cementing the well continuously also constantly will produce high-temp waste gas, for waste heat steam boiler 3 provides energy, thus ensure the continual and steady of heat-insulation system heat energy.Gas holder 6 also leaves air supply opening, on-the-spot other operations needing steam of supply.Regulate the supply channel of waste heat steam boiler 3 and water storage cabinet 9 can the steam preparation amount of control system.
Run under conventional environment, do not need heating and thermal insulation measure, then use control valve 4 to open exhaust gas bypass loop, the waste gas that turbogenerator 1 produces directly discharges through baffler and outlet pipe 5, and waste heat recovery heat-insulation system quits work.
The above is only preferred implementation of the present utility model; it should be pointed out that for those skilled in the art, under the prerequisite not departing from the utility model principle; can also make some improvement or distortion, these improve or distortion also should be considered as protection domain of the present utility model.

Claims (3)

1. the waste heat recovery heat-insulation system of a turbogenerator, comprise the turbogenerator driving well cementation fracturing pump, it is characterized in that: between the tail gas end of described turbogenerator and the outlet pipe with silencing apparatus, waste heat steam boiler is set, the feed-water end of this waste heat steam boiler is communicated with water storage cabinet, is communicated with after the hot output terminal connection gas holder of waste heat steam boiler with heat exchanger again.
2. the waste heat recovery heat-insulation system of a kind of turbogenerator according to claim 1, is characterized in that: arrange between described turbogenerator and outlet pipe with waste heat steam boiler and the bypass line connected, this bypass line has control valve.
3. the waste heat recovery heat-insulation system of a kind of turbogenerator according to claim 1 and 2, is characterized in that: arrange small pump between described waste heat steam boiler and described water storage cabinet.
CN201420473945.0U 2014-08-21 2014-08-21 A kind of waste heat recovery heat-insulation system of turbogenerator Expired - Fee Related CN204098964U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420473945.0U CN204098964U (en) 2014-08-21 2014-08-21 A kind of waste heat recovery heat-insulation system of turbogenerator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420473945.0U CN204098964U (en) 2014-08-21 2014-08-21 A kind of waste heat recovery heat-insulation system of turbogenerator

Publications (1)

Publication Number Publication Date
CN204098964U true CN204098964U (en) 2015-01-14

Family

ID=52267400

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420473945.0U Expired - Fee Related CN204098964U (en) 2014-08-21 2014-08-21 A kind of waste heat recovery heat-insulation system of turbogenerator

Country Status (1)

Country Link
CN (1) CN204098964U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104179535A (en) * 2014-08-21 2014-12-03 四机赛瓦石油钻采设备有限公司 Waste heat recycling and heat-insulation system of turbine engine
CN104688032A (en) * 2015-03-26 2015-06-10 刘甄 hot water pot
US12078093B2 (en) 2021-04-25 2024-09-03 Yantai Jereh Petroleum Equipment & Technologies Co., Ltd. Turbine fracturing equipment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104179535A (en) * 2014-08-21 2014-12-03 四机赛瓦石油钻采设备有限公司 Waste heat recycling and heat-insulation system of turbine engine
CN104688032A (en) * 2015-03-26 2015-06-10 刘甄 hot water pot
US12078093B2 (en) 2021-04-25 2024-09-03 Yantai Jereh Petroleum Equipment & Technologies Co., Ltd. Turbine fracturing equipment

Similar Documents

Publication Publication Date Title
CN201321918Y (en) Heat power and cold cogeneration device for waste heat utilization of large-scale marine diesel engine
CN205101052U (en) Novel heating system of thermal power plant
CN104819054A (en) Distributed energy resource waste heat utilization system
CN204098964U (en) A kind of waste heat recovery heat-insulation system of turbogenerator
CN205779061U (en) Coal mine gas gradient thermoelectric cold supply system
TR201901543T4 (en) Gas turbine exhaust gas cooling system.
CN103343734A (en) Single-screw expander medium and low temperature geothermal power generating system with added lubricating oil cycle loop
CN104100313A (en) Thermal power plant heat supply extraction steam residual pressure utilization system adopting back pressure extraction turbine
CN204082093U (en) A kind of natural gas well head based on pressure energy generating and heat pump heats throttle system
CN208040541U (en) Gas turbine cycle flue gas waste heat recovery and inlet gas cooling association system
CN103452670A (en) Micro gas turbine combined circulating system based on renewable energy sources
CN204704010U (en) A kind of bootstrap system of distributed energy
CN208900080U (en) A kind of throttle system of natural gas wellhead pressure energy power generation
CN203704428U (en) Flue gas hot water single-effect or dual-effect composite-type lithium bromide absorption-type cold water and cold hot water unit
CN107489468A (en) A kind of low-concentration gas power generation system based on intermittent combustion
CN103759459B (en) Fume hot-water single-double effect compound type lithium bromide absorption type refrigeration unit
CN103759458A (en) Flue gas waste heat recovery system based on absorption-type heat pump technology
CN204041244U (en) One utilizes balance of power plant cooling water backwater waste heat natural gas system
CN104179535A (en) Waste heat recycling and heat-insulation system of turbine engine
CN105508055A (en) System and method for cooling circulation water in distributed energy station
CN109162672A (en) A kind of throttle system of natural gas wellhead pressure energy power generation
RU2605878C1 (en) Turbo-expansion system of heat utilization of circulating water on condensation units of steam turbines of thermal power station
CN108625915A (en) It is a kind of using boiler blowdown water and flue gas as the organic rankine cycle system of heat source
RU2561777C2 (en) Fuel gas heating system with cogeneration unit
CN204063684U (en) A kind of fume afterheat segmented utilizes device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150114

CF01 Termination of patent right due to non-payment of annual fee