[go: up one dir, main page]

CN203944677U - The cold stewing producing device of a kind of wafer type band steel pipe clamp - Google Patents

The cold stewing producing device of a kind of wafer type band steel pipe clamp Download PDF

Info

Publication number
CN203944677U
CN203944677U CN201420338837.2U CN201420338837U CN203944677U CN 203944677 U CN203944677 U CN 203944677U CN 201420338837 U CN201420338837 U CN 201420338837U CN 203944677 U CN203944677 U CN 203944677U
Authority
CN
China
Prior art keywords
steel
force
application
band steel
axle sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420338837.2U
Other languages
Chinese (zh)
Inventor
高玉新
王云峰
杨翊
郭小红
李刚
翟战强
李亚
郑岑岭
杨东峰
吴豪强
洪宾院
王辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum First Construction Corp
Original Assignee
China Petroleum First Construction Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum First Construction Corp filed Critical China Petroleum First Construction Corp
Priority to CN201420338837.2U priority Critical patent/CN203944677U/en
Application granted granted Critical
Publication of CN203944677U publication Critical patent/CN203944677U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Clamps And Clips (AREA)

Abstract

The utility model has been introduced the cold stewing producing device of a kind of wafer type band steel pipe clamp, comprises the cold stewing device of semi arch part and the cold stewing device of straight portion flanging; The cold stewing device of semi arch part comprises the first shaped steel bearing, positioning support fagging, locating hole, supporting mould, application of force mould, axle sleeve gripper shoe, fixed hub, the first movable axle sleeve, the first force application rod, movable axis and reinforcement gusset; The cold stewing device of straight portion flanging comprises Second-Type bridle iron, two blocks of spacing angle steel, position stopping arch plate, two blocks of flanging chopping blocks, fixed axis, the second movable axle sleeve, application of force angle steel, strengthens angle steel and the second force application rods.Utilize this patent by the band steel cold semi arch band steel of simmering into two straight flanges once; Be placed on again on the cold stewing device of straight portion flanging, at twice cold two straight flanges simmering in one plane; Thereby significantly improved efficiency of construction, save material, improve pipe clamp appearance forming quality, avoid scalding risk.

Description

The cold stewing producing device of a kind of wafer type band steel pipe clamp
Technical field
The utility model patent relates to a kind of pipe clamp producing device, particularly the cold stewing producing device of a kind of wafer type band steel pipe clamp.
Background technology
Pipe clamp is that piping load is delivered to the element on pipe frame structure, to reducing pipe stress, guarantees that the even running of pipeline long period plays vital effect.Two two ends that wafer type band steel pipe clamp is simmered into by band steel form with the semicircular arc structure of straight flange with through the bolt of straight flange upper bolt hole.
Because material therefor is common and simple in structure, for reducing costs, wafer type band steel pipe clamp mostly is field fabrication but not entrusts machinery plant's processing.Traditional wafer type Flat steel pipe card manufacturing method and step are as follows:
1, select to meet the band steel material of drawing requirement, cutting stock after the clean material that accounting making pipe clamp is required rule of thumb amplification reserve.
2, make as required the specification of pipe clamp, one section of steel pipe matching with pipe clamp specification is vertically welded on steel platform as the mould of simmering tubulation card.
3, one end of band steel is weldingly fixed on steel platform to the length of pipe clamp straight flange the length of assurance band steel from pad to mould steel pipe point of contact is greater than and completes.
4, from the position, point of contact (being the starting the arc position of semi arch) of band steel and mould steel pipe, utilize oxygen acetylene flame to heat band steel, when heating-up temperature reaches 700 degree when above, with iron hammer, knock band steel, make its along mould steel pipe gradually fire bending become half-circle-arc shape.
5, utilize oxygen acetylene flame cut the pad of band steel on steel platform open and polish flat.
6, utilize oxygen acetylene flame to heat the flanging position of band steel straight flange (being the starting the arc position of semi arch), when heating-up temperature reaches more than 700 ℃, be placed on chopping block and knock with iron hammer, complete flanging.
7, utilize the surplus of two straight flanges of oxygen acetylene flame cutting.
8, auger shell keyhole on straight flange.
9, the semicircular arc structure with straight flange by two two ends, utilizes the bolt through straight flange upper bolt hole to link together.Complete the making of wafer type band steel pipe clamp.
Above-mentioned oxygen acetylene flame is heated to uniform temperature by band steel, the method for utilizing fire bending that iron hammer knocks on mould steel pipe and chopping block to make pipe clamp, and the wafer type band steel pipe clamp of making can meet instructions for use, but has following shortcoming:
1, because the larger scale error of wafer type band steel pipe clamp existence is made in fire bending, clean material can not be descended before with the semicircular arc structure fabrication of straight flange in each two ends, but will adjust, make the required clean material of pipe clamp and rule of thumb after amplification reserve, descend woollen, after fire bending completes, excising again clout.
2, because fire bending making wafer type Flat steel pipe calorie requirement is by a plurality of operations such as clout that band steel is welded on steel platform, oxygen acetylene flame heats, iron hammer knocks band steel fire bending, cutting pad is also polished, cut two straight flanges, and craftsmanship is had relatively high expectations, so efficiency of construction is lower.
3, owing to being that iron hammer knocks and forms after oxygen acetylene flame heating, the wafer type band steel pipe clamp appearance forming that fire bending is made is poor.
4, because fire bending making wafer type Flat steel pipe calorie requirement is heated to band steel more than 700 ℃, in manufacturing process, be manual operation, so exist, scald risk.
In sum, traditional oxygen acetylene flame is heated to uniform temperature by band steel, the method of utilizing fire bending that iron hammer knocks on mould steel pipe and chopping block to make pipe clamp, the wafer type band steel pipe clamp of making can meet instructions for use, but material is wasted in existence, efficiency of construction is low, pipe clamp appearance forming is poor, have the shortcomings such as the risk of scald.
Summary of the invention
Technical problem to be solved in the utility model is to provide the cold stewing producing device of a kind of wafer type band steel pipe clamp, avoid making wafer type band steel pipe clamp waste of material, improve efficiency of construction and pipe clamp appearance forming quality, avoid scalding risk.
In order to realize the object solving the problems of the technologies described above, the utility model has adopted following technical scheme:
The cold stewing producing device of a kind of wafer type band steel pipe clamp of the present utility model, coordinates steel platform to use, and comprises the cold stewing device of semi arch part, the cold stewing device of straight portion flanging, and the two is used in conjunction with; Wherein:
The cold stewing device of semi arch part comprises the first shaped steel bearing, positioning support fagging, locating hole, supporting mould, application of force mould, axle sleeve gripper shoe, fixed hub, the first movable axle sleeve, the first force application rod, movable axis and reinforcement gusset, wherein:
The first shaped steel bearing is one section of H shaped steel, and the lower wing plate of H shaped steel is weldingly fixed on steel platform, is the assembling carrier of the cold stewing device of semi arch part miscellaneous part;
Positioning support fagging is the rectangle steel plate being welded on the first shaped steel bearing web, in the cold stewing process of pipe clamp semi arch part, band steel is played to location and supporting role; During use, band steel one end is placed on positioning support fagging, and the point of contact of band steel and supporting mould cylindrical equals the length of pipe clamp straight flange to the vertical range of positioning support fagging upper surface; The point of contact of supporting mould cylindrical is the starting the arc position of semi arch;
Locating hole is the slot cutting on the upper flange of the first shaped steel bearing, and the size of locating hole to be just can meet band steel through being as the criterion, and band steel is passed be vertically placed on after locating hole on positioning support fagging and tangent with supporting mould cylindrical;
Supporting mould is that external diameter equals 270 ° of circular arcs that pipe clamp internal diameter, width are greater than the steel pipe of band steel width, is the mould of the cold stewing of pipe clamp semi arch part, and supporting mould both sides are welded on the upper flange of the first shaped steel bearing, wherein concordant with shaped steel wing plate edge on one side;
Application of force mould is that internal diameter equals 180 ° of circular arcs that pipe clamp external diameter, width are greater than the steel pipe of band steel width, is the mould of the cold stewing of pipe clamp semi arch part; Application of force mould front center has size just can meet the rectangle draw-in groove that band steel is put into, draw-in groove directly to the band steel application of force and and locating hole co-controlling band steel on supporting mould along circular motion; Application of force mould and the first movable axle sleeve, the first force application rod, to strengthen gusset integrally welded, can rotate to the band steel application of force around movable axis;
Axle sleeve gripper shoe is the rectangle steel plate being welded on the first shaped steel bearing upper flange, is the support of fixed hub; The height of controlling axle sleeve gripper shoe makes to penetrate movable axis in fixed hub and movable axle sleeve and contour being as the criterion in point of contact of band steel and supporting mould cylindrical; Distance between axle sleeve gripper shoe and supporting mould should make the minimum range between fixed hub outer wall and supporting mould outer wall equal the thickness of band steel;
Fixed hub is the steel pipe that is welded on axle sleeve gripper shoe top, is the support set of movable axis, has the function of movable support axle; Distance between fixed hub outer wall and supporting mould outer wall can be so that band steel passes;
The first movable axle sleeve is and the steel pipe of fixed hub same specification that the first movable axle sleeve is welded on one end of the first force application rod and application of force mould; When the first force application rod is subject to artificial External Force Acting, application of force mould, along with the rotation of the first movable axle sleeve around movable axis, is given the band steel application of force;
One end of the first force application rod and the first movable axle sleeve, application of force mould and reinforcement gusset weld together; When the first force application rod is subject to artificial External Force Acting, application of force mould, along with the rotation of the first movable axle sleeve around movable axis, is given the band steel application of force;
Movable axis is the round steel being through in two fixed hubs and movable axle sleeve, and the first force application rod and application of force mould can rotate around movable axis, gives the band steel application of force; The point of contact of movable axis and band steel and supporting mould cylindrical is that the starting the arc position of semi arch is contour;
Strengthening gusset is the steel plate being welded between the first force application rod and application of force mould, and application of force mould is played to booster action;
The cold stewing device of straight portion flanging comprises Second-Type bridle iron, two blocks of spacing angle steel, position stopping arch plate, two blocks of flanging chopping blocks, fixed axis, the second movable axle sleeve, application of force angle steel, strengthens angle steel and the second force application rods, wherein:
Second-Type bridle iron is one section of H shaped steel, and the lower wing plate of H shaped steel is weldingly fixed on steel platform, is the assembling carrier of the cold stewing device of straight portion flanging miscellaneous part;
Two spacing angle steel fillet welding in the vertical positions are connected on the upper flange of Second-Type bridle iron, and the four edges place diameter of a circle of two blocks of spacing angle steel equals pipe clamp external diameter, and pipe clamp semi arch is partly stuck in four edges and two flanging chopping block inner sides of two blocks of spacing angle steel; More specifically, the height of spacing angle steel should be greater than the width of band steel;
Position stopping arch plate is 180 ° of arc plates that are highly greater than the steel pipe of band steel width; Position stopping arch plate is welded on the upper flange of Second-Type bridle iron, and the external diameter of position stopping arch plate equals pipe clamp internal diameter, and pipe clamp semi arch is partly stuck in position stopping arch plate outside;
Two flanging chopping blocks are the rectangle steel plates that are highly greater than band steel width; Flanging chopping block is welded on the upper flange of Second-Type bridle iron, and the distance between two flanging chopping blocks equals pipe clamp external diameter, and the stress surface of two flanging chopping blocks is concordant with the end of position stopping arch plate, after the cold stewing of two straight flanges that guarantees pipe clamp is shaped in one plane;
Fixed axis is the round steel being welded on Second-Type bridle iron upper flange, the center of circle that is centered close to position stopping arch plate of fixed axis;
The second movable axle sleeve is the steel pipe welding together with the second force application rod and application of force angle steel, and wherein, the top of the second force application rod is welded on the side of the second movable axle sleeve, two application of force angle steel sides that are welded on the second movable axle sleeve in 90 °;
The second force application rod is the steel pipe that intensity meets force request; Strengthening angle steel for two is welded between the second force application rod and two application of force angle steel; Two application of force angle steel and two reinforcement angle steel form a square, and the second force application rod is on this foursquare diagonal; When the second force application rod is subject to artificial External Force Acting, application of force angle steel, along with the rotation of the second movable axle sleeve around fixed axis, is given the band steel application of force under the cooperation of flanging chopping block.
The cold stewing producing device of above-mentioned wafer type band steel pipe clamp is comprised of the cold stewing device of semi arch part and the cold stewing device of straight portion flanging two parts.Utilize the cold stewing producing device of wafer type band steel pipe clamp, the mode of traditional fire bending being made to pipe clamp is optimized for the mode that pipe clamp is made in cold stewing.Make the cold stewing producing device of wafer type band steel pipe clamp of different size, can realizing cold stewing, to make conventional nominal diameter be that 100 millimeters to 600 millimeters, width are that 50 millimeters to 100 millimeters, thickness are the wafer type band steel pipe clamp of 6 millimeters to 12 millimeters.And can save material, improve efficiency of construction and pipe clamp appearance forming quality, avoid scalding risk.
The cold stewing producing device of wafer type band steel pipe clamp of the utility model patent, concrete implementation step is:
1, make the cold stewing device of semi arch part.
The lower wing plate of the first shaped steel bearing is weldingly fixed on steel platform, as the assembling carrier of the cold stewing device of semi arch part miscellaneous part.
External diameter is equaled to the both sides of supporting mould of 270 ° of circular arcs that pipe clamp internal diameter, width be greater than the steel pipe of band steel width and be welded on the upper flange of the first shaped steel bearing, wherein concordant with shaped steel wing plate edge on one side.
On the upper flange of the first shaped steel bearing, cut lengths just can meet the rectangle locating hole that band steel passes, and guarantee that band steel is through being vertically placed on after locating hole on positioning support fagging and tangent with supporting mould cylindrical.
Rectangular positioning support fagging is welded on the web of the first shaped steel bearing, guarantee that band steel is through after locating hole, the point of contact of band steel and supporting mould cylindrical (being the starting the arc position of semi arch) equals the length of pipe clamp straight flange to the vertical range of positioning support fagging upper surface.
By application of force mould, the first movable axle sleeve, the first force application rod, reinforcement gusset, integrally welded according to connected mode.And in application of force mould front center, open size and just can meet the rectangle draw-in groove that band steel is put into.
The side of fixed hub is welded on to the top of axle sleeve gripper shoe, the other end of axle sleeve gripper shoe is welded on the upper flange of the first shaped steel bearing.It is contour that assurance penetrates the point of contact (being the starting the arc position of semi arch) of movable axis in fixed hub and movable axle sleeve and band steel and supporting mould cylindrical, guarantees that minimum range between fixed hub outer wall and supporting mould outer wall just can meet band steel and pass simultaneously;
Movable axis is through in two fixed hubs and the first movable axle sleeve.Complete the making of the cold stewing device of semi arch part.
2, make the cold stewing device of straight portion flanging.
The lower wing plate of Second-Type bridle iron is weldingly fixed on steel platform, as the assembling carrier of the cold stewing device of straight portion flanging miscellaneous part.
Two spacing angle steel fillet welding in the vertical positions are connected on the upper flange of Second-Type bridle iron.The four edges place diameter of a circle that guarantees two blocks of spacing angle steel equals pipe clamp external diameter, and pipe clamp semi arch is partly stuck in four edges and two flanging chopping block inner sides of two blocks of spacing angle steel.
External diameter is equaled to pipe clamp internal diameter, and the position stopping arch plate of 180 ° of circular arcs that is highly greater than the steel pipe of band steel width is welded on the upper flange of Second-Type bridle iron, and pipe clamp semi arch is partly stuck in position stopping arch plate outside.
The square flanging chopping block of two block lengths that is highly greater than band steel width is welded on the upper flange of Second-Type bridle iron, guarantees that the distance between two flanging chopping blocks equals pipe clamp external diameter, the stress surface of two flanging chopping blocks is concordant with the end of position stopping arch plate.
The top of the second force application rod is welded on to the side of the second movable axle sleeve, by two application of force angle steel sides that are welded on the second movable axle sleeve in 90 °; By two, strengthen angle steel and be welded between the second force application rod and two application of force angle steel, make two application of force angle steel and two reinforcement angle steel form a square, the second force application rod is on this foursquare diagonal.
Round steel fixed axis is welded on the upper flange of Second-Type bridle iron to the center of circle that is centered close to position stopping arch plate of fixed axis; The second movable axle sleeve is enclosed within on fixed axis, completes the making of the cold stewing device of straight portion flanging.
3, wafer type band steel pipe clamp is made in cold stewing.
Selection meets the band steel material of drawing requirement, and after adjusting, the required clean material of pipe clamp is made in cutting.
Band steel is penetrated to the locating hole of the cold stewing device of semi arch part, be vertically placed on positioning support fagging and tangent with supporting mould cylindrical.
Adjust the first force application rod position, band steel is put into the draw-in groove of application of force mould front center.Manually afterburning to the first force application rod, make band steel under the effect of application of force mould draw-in groove, along with the rotation of the first movable axle sleeve around movable axis, the cold semi arch band steel of simmering into two straight flanges gradually on supporting mould.
Semi arch band steel symmetry with two straight flanges is placed on the cold stewing device of straight portion flanging, and pipe clamp semi arch is partly stuck between the four edges of two blocks of spacing angle steel, two flanging chopping blocks and position stopping arch plate.
Manually afterburning to the second force application rod, make a straight portion of band steel pipe clamp under the effect of application of force angle steel, along with the rotation of the second movable axle sleeve around fixed axis, 90 ° of cold stewings gradually on flanging chopping block.Change the second force application rod and add force direction, complete 90 ° of the cold stewings of another straight portion of band steel pipe clamp.
In like manner completing second two ends makes with the cold stewing of the semicircular arc band steel pipe clamp of straight flange.
Auger shell keyhole on band steel pipe clamp straight flange.Semicircular arc band steel pipe clamp by two two ends with straight flange, utilizes the bolt through straight flange upper bolt hole to link together.Complete the making of wafer type band steel pipe clamp.
By adopting technique scheme, the cold stewing producing device of wafer type band steel pipe clamp of the utility model patent, has following beneficial effect:
1, utilize the cold stewing producing device of wafer type band steel pipe clamp, cold stewing is made wafer type band steel pipe clamp and is not had scale error, can adjust rear cutting and make the required clean material of pipe clamp.Make wafer type Flat steel pipe cacaine with fire bending and have large-size error and need rule of thumb after amplification reserve, to descend woollen to compare, saved material.
2, utilize the cold stewing producing device of wafer type band steel pipe clamp, cold stewing is made wafer type band steel pipe clamp and is only needed first band steel to be placed on the cold stewing device of semi arch part, once the cold semi arch band steel of simmering into two straight flanges; Then the semi arch band steel symmetry with two straight flanges is placed on the cold stewing device of straight portion flanging, at twice cold two straight flanges simmering in one plane.Make wafer type Flat steel pipe calorie requirement with fire bending a plurality of operations such as clout that band steel is welded on steel platform, band steel fire bending, cutting pad polishing, two straight flanges of cutting are knocked in oxygen acetylene flame heating, iron hammer are compared, significantly improved efficiency of construction.
3, utilize the cold stewing producing device of wafer type band steel pipe clamp, cold stewing is made wafer type band steel pipe clamp and need to after oxygen acetylene flame heating, with iron hammer, do not knocked, and the wafer type band steel pipe clamp appearance forming quality of making than fire bending is good.
4, utilize the cold stewing producing device of wafer type band steel pipe clamp, wafer type band steel pipe clamp is made in cold stewing not to be needed to utilize oxygen acetylene flame to heat band steel, has avoided scald risk, has also saved oxygen-acetylene.
Accompanying drawing explanation
Fig. 1 is the cold stewing device of semi arch part.
Fig. 2 is the cold stewing device of straight portion flanging.
In figure, 1-the first shaped steel bearing, 2-positioning support fagging, 3-locating hole, 4-supporting mould, 5-application of force mould, 6-axle sleeve gripper shoe, 7-fixed hub, the movable axle sleeve of 8-first, 9-the first force application rod, 10-movable axis, 11-strengthens gusset, 12-band steel, 13-Second-Type bridle iron, the spacing angle steel of 14-, 15-position stopping arch plate, 16-flanging chopping block, 17-fixed axis, the movable axle sleeve of 18-second, 19-application of force angle steel, 20-strengthens angle steel, 21-the second force application rod, 22-band steel pipe clamp.
The specific embodiment
Embodiment 1
The cold stewing producing device of wafer type band steel pipe clamp is comprised of the cold stewing device of semi arch part and the cold stewing device of straight portion flanging two parts.
(actual inner diameter is 330 millimeters as 300 millimeters to take nominal diameter, external diameter is 350 millimeters), width is that 80 millimeters, thickness are that the cold stewing of the wafer type band steel pipe clamp of 10 millimeters is made as example, and the cold stewing device of semi arch part of this specification and manufacturing process and the using method of the cold stewing device of straight portion flanging are described.
1, make the cold stewing device of semi arch part.
The cold stewing device of semi arch part comprises the first shaped steel bearing 1, positioning support fagging 2, locating hole 3, supporting mould 4, application of force mould 5, axle sleeve gripper shoe 6, the movable axle sleeve 8 of fixed hub 7, first, the first force application rod 9, movable axis 10 and reinforcement gusset 11, and the cold stewing device of semi arch part manufacturing process is as follows:
Select be highly 400 millimeters, width be 500 millimeters, length be one section of H shaped steel of 500 millimeters as the first shaped steel bearing 1, its lower wing plate is weldingly fixed on steel platform, as the assembling carrier of the cold stewing device of semi arch part miscellaneous part.
Select external diameter be 330 millimeters of (equaling pipe clamp internal diameter), width be 270 ° of circular arcs of steel pipe of 150 millimeters as supporting mould 4, the both sides of supporting mould 4 are welded on the upper flange of the first shaped steel bearing 1, wherein concordant with shaped steel wing plate edge on one side.
On the upper flange of the first shaped steel bearing 1, Cutting Length is that 82 millimeters, width are the rectangle locating hole 3 of 12 millimeters, making width is that 80 millimeters, thickness are that the band steel of 10 millimeters just can pass locating hole 3, and guarantees that band steel passes that locating hole 3 is rear to be vertically placed on positioning support fagging 2 and tangent with supporting mould 4 cylindricals.
Selecting thickness is that 10 millimeters, length are that 200 millimeters, width are that the rectangle steel plate of 150 millimeters is as positioning support fagging 2, positioning support fagging 2 is welded on the web of the first shaped steel bearing 1, guarantee that band steel is through after locating hole 3, the point of contact of band steel and supporting mould 4 cylindricals (being the starting the arc position of semi arch) equals 168 millimeters of the length of pipe clamp straight flange to the vertical range of positioning support fagging 2 upper surfaces.
Selecting internal diameter is that 350 millimeters of (equaling pipe clamp external diameter), width are that 180 ° of circular arcs of steel pipe of 120 millimeters are as application of force mould 5; Selecting internal diameter is that 37 millimeters, wall thickness are that 4 millimeters, length are that the steel pipe of 150 millimeters is as the first movable axle sleeve 8; Selecting internal diameter is that 37 millimeters, wall thickness are that 4 millimeters, length are that the steel pipe of 1500 millimeters is as the first force application rod 9; Selecting thickness is that the steel plate of 12 millimeters is as strengthening gusset 11; By the movable axle sleeve 8 of application of force mould 5, first, the first force application rod 9, reinforcement gusset 11, integrally welded according to connected mode.And to open width in application of force mould 5 front center be that 82 millimeters, the degree of depth are the rectangle draw-in groove of 12 millimeters, making width is that 80 millimeters, thickness are that the band steel of 10 millimeters just can be put into draw-in groove.
Selecting two internal diameters is that 37 millimeters, wall thickness are that 4 millimeters, length are that the steel pipe of 100 millimeters is as two fixed hubs 7; Selecting two thickness is that 16 millimeters, length are that 100 millimeters, width are that the rectangle steel plate of 94 millimeters is as two axle sleeve gripper shoes 6; The side of fixed hub 7 is welded on to the top, long limit of axle sleeve gripper shoe 6, another long side weld of axle sleeve gripper shoe 6 is connected on the upper flange of the first shaped steel bearing 1; Make to penetrate movable axis 10 and the point of contact (being the starting the arc position of semi arch) of band steel and supporting mould 4 cylindricals contour (all exceeding 117 millimeters, the first shaped steel bearing 1 upper flange surface) in fixed hub 7 and the first movable axle sleeve 8, the minimum range of simultaneously controlling between fixed hub 7 outer walls and supporting mould 4 outer walls is 12 millimeters, and making thickness is that the band steel of 10 millimeters just can pass.
Selecting diameter is that 35 millimeters, length are that the round steel of 400 millimeters is as movable axis 10; Movable axis 10 is through in two fixed hubs 7 and the first movable axle sleeve 8.Complete the making of the cold stewing device of semi arch part.
2, make the cold stewing device of straight portion flanging.
The cold stewing device of straight portion flanging comprises Second-Type bridle iron 13, two blocks of spacing angle steel 14, position stopping arch plate 15, two blocks of flanging chopping blocks 16, the movable axle sleeve 18 of fixed axis 17, second, application of force angle steel 19, strengthens angle steel 20 and the second force application rod 21, and the cold stewing device of straight portion flanging manufacturing process is as follows:
Select be highly 400 millimeters, width be 500 millimeters, length be one section of H shaped steel of 500 millimeters as Second-Type bridle iron 13, its lower wing plate is weldingly fixed on steel platform, as the assembling carrier of the cold stewing device of straight portion flanging miscellaneous part.
Selecting external diameter is that 330 millimeters of (equaling pipe clamp internal diameter), thickness are that 180 ° of circular arcs of steel pipe of 10 millimeters are as position stopping arch plate 15, position stopping arch plate 15 is welded on the upper flange of Second-Type bridle iron 1, makes pipe clamp semi arch partly be stuck in position stopping arch plate 15 outsides.
Select two thickness be 10 millimeters, be highly 100 millimeters, the length of side be the equal leg angle of 90 millimeters as two blocks of spacing angle steel 14, selecting two thickness is 20 millimeters, is highly 100 millimeters, width is that the rectangle steel plate of 60 millimeters is as two flanging chopping blocks 16; Two blocks of spacing angle steel 14 and two flanging chopping block 16 fillet welding in the vertical positions are connected on the upper flange of Second-Type bridle iron 13, the four edges place diameter of a circle that makes two blocks of spacing angle steel 14 is 350 millimeters (equaling pipe clamp external diameter), distance between two flanging chopping blocks 16 is 350 millimeters (equaling pipe clamp external diameter), and the stress surface of two flanging chopping blocks 16 is concordant with the end of position stopping arch plate 15, make pipe clamp semi arch partly be stuck in four edges and two flanging chopping block 16 inner sides of two blocks of spacing angle steel 14.
Selecting internal diameter is that 37 millimeters, wall thickness are that 4 millimeters, length are that the steel pipe of 1800 millimeters is as the second force application rod 21; Selecting internal diameter is that 37 millimeters, wall thickness are that 4 millimeters, length are that the steel pipe of 100 millimeters is as the second movable axle sleeve 18; Selecting two thickness is that 10 millimeters, length are that 200 millimeters, the length of side are that the equal leg angle of 90 millimeters is as two application of force angle steel 19; Selecting two thickness is that 10 millimeters, length are that 200 millimeters, the length of side are that the equal leg angle of 90 millimeters is strengthened angle steel 20 as two; The top of the second force application rod 21 is welded on to the side of the second movable axle sleeve 18, by two application of force angle steel 19 sides that are welded on the second movable axle sleeve 18 in 90 °; By two, strengthen angle steel 20 and be welded between the second force application rod 21 and two application of force angle steel 19, make two application of force angle steel 19 and two reinforcement angle steel 20 form a square, the second force application rod 21 is on this foursquare diagonal.
Select diameter be 35 millimeters, be highly the round steel of 110 millimeters as fixed axis 17, fixed axis is welded on the upper flange of Second-Type bridle iron 13 to the center of circle that is centered close to position stopping arch plate 15 of fixed axis 17.
The second movable axle sleeve 18 is enclosed within on fixed axis 17, completes the making of the cold stewing device of straight portion flanging.
3, wafer type band steel pipe clamp is made in cold stewing.
Selecting width is that 80 millimeters, thickness are the band steel material of 10 millimeters, accounting nominal diameter is 300 millimeters, and (actual inner diameter is 330 millimeters, external diameter is 350 millimeters) the required clean material length of band steel pipe clamp be 886 millimeters, cut two length and be the band steel of 886 millimeters and only expect.
The length that band steel is penetrated to the cold stewing device of semi arch part is that 82 millimeters, width are the locating hole 3 of 12 millimeters, is vertically placed on positioning support fagging 2 and tangent with supporting mould 4 cylindricals.
Adjust the position of the first force application rod 9, it is that 82 millimeters, the degree of depth are the draw-in groove of 12 millimeters that band steel is put into application of force mould 5 front center width.Manually, to the first force application rod 9 reinforcings, make band steel under the effect of application of force mould 5 draw-in grooves, along with the rotation of the first movable axle sleeve 8 around movable axis 10, the cold semi arch band steel of simmering into two straight flanges gradually on supporting mould 4.
Semi arch band steel symmetry with two straight flanges is placed on the cold stewing device of straight portion flanging, and pipe clamp semi arch is partly stuck between the four edges of two blocks of spacing angle steel 14, two flanging chopping blocks 16 and position stopping arch plate 15.
Manually, to the second force application rod 21 reinforcings, make a straight portion of band steel pipe clamp under the effect of application of force angle steel 19, along with the rotation of the second movable axle sleeve 18 around fixed axis 17,90 ° of cold stewings gradually on flanging chopping block 16.Change the second force application rod 21 and add force direction, complete 90 ° of the cold stewings of another straight portion of band steel pipe clamp.
In like manner completing second two ends makes with the cold stewing of the semicircular arc band steel pipe clamp of straight flange.
On band steel pipe clamp straight flange, drill diameter is the bolt hole of 33 millimeters.Semicircular arc band steel pipe clamp by two two ends with straight flange, utilizing diameter through straight flange upper bolt hole is that the bolt of 30 millimeters links together.Complete the making of wafer type band steel pipe clamp.
Embodiment 2
In the construction of Mou petro-chemical corporation hydrogenation plant, 100 millimeters of the diameters wafer type band steel pipe clamp to 600 millimeters of diameters has 386, makes 25 wafer type Flat steel pipe calorimeters average every day calculate according to traditional fire bending method Yi Ge teams and groups, and the 15 day time of needs just can complete.Use the cold stewing producing device of wafer type band steel pipe clamp of the present utility model, utilize cold roasting method Yi Ge teams and groups can make 70 wafer type band steel pipe clamps average every day, 6 day time has just completed construction task, significantly improved efficiency of construction, and improved the appearance forming quality of wafer type band steel pipe clamp, also saved the materials such as band steel and oxygen-acetylene simultaneously.

Claims (2)

1. the cold stewing producing device of wafer type band steel pipe clamp, coordinates steel platform to use, and it is characterized in that: comprise the cold stewing device of semi arch part, the cold stewing device of straight portion flanging, the two is used in conjunction with; Wherein:
The cold stewing device of semi arch part comprises the first shaped steel bearing, positioning support fagging, locating hole, supporting mould, application of force mould, axle sleeve gripper shoe, fixed hub, the first movable axle sleeve, the first force application rod, movable axis and reinforcement gusset, wherein:
The first shaped steel bearing is one section of H shaped steel, and the lower wing plate of H shaped steel is weldingly fixed on steel platform, is the assembling carrier of the cold stewing device of semi arch part miscellaneous part;
Positioning support fagging is the rectangle steel plate being welded on the first shaped steel bearing web, in the cold stewing process of pipe clamp semi arch part, band steel is played to location and supporting role; During use, band steel one end is placed on positioning support fagging, and the point of contact of band steel and supporting mould cylindrical equals the length of pipe clamp straight flange to the vertical range of positioning support fagging upper surface; The point of contact of supporting mould cylindrical is the starting the arc position of semi arch;
Locating hole is the slot cutting on the upper flange of the first shaped steel bearing, and the size of locating hole to be just can meet band steel through being as the criterion, and band steel is passed be vertically placed on after locating hole on positioning support fagging and tangent with supporting mould cylindrical;
Supporting mould is that external diameter equals 270 ° of circular arcs that pipe clamp internal diameter, width are greater than the steel pipe of band steel width, is the mould of the cold stewing of pipe clamp semi arch part, and supporting mould both sides are welded on the upper flange of the first shaped steel bearing, wherein concordant with shaped steel wing plate edge on one side;
Application of force mould is that internal diameter equals 180 ° of circular arcs that pipe clamp external diameter, width are greater than the steel pipe of band steel width, is the mould of the cold stewing of pipe clamp semi arch part; Application of force mould front center has size just can meet the rectangle draw-in groove that band steel is put into, draw-in groove directly to the band steel application of force and and locating hole co-controlling band steel on supporting mould along circular motion; Application of force mould and the first movable axle sleeve, the first force application rod, to strengthen gusset integrally welded, can rotate to the band steel application of force around movable axis;
Axle sleeve gripper shoe is the rectangle steel plate being welded on the first shaped steel bearing upper flange, is the support of fixed hub; The height of controlling axle sleeve gripper shoe makes to penetrate movable axis in fixed hub and movable axle sleeve and contour being as the criterion in point of contact of band steel and supporting mould cylindrical; Distance between axle sleeve gripper shoe and supporting mould should make the minimum range between fixed hub outer wall and supporting mould outer wall equal the thickness of band steel;
Fixed hub is the steel pipe that is welded on axle sleeve gripper shoe top, is the support set of movable axis, has the function of movable support axle; Distance between fixed hub outer wall and supporting mould outer wall can be so that band steel passes;
The first movable axle sleeve is and the steel pipe of fixed hub same specification that the first movable axle sleeve is welded on one end of the first force application rod and application of force mould; When the first force application rod is subject to artificial External Force Acting, application of force mould, along with the rotation of the first movable axle sleeve around movable axis, is given the band steel application of force;
One end of the first force application rod and the first movable axle sleeve, application of force mould and reinforcement gusset weld together; When the first force application rod is subject to artificial External Force Acting, application of force mould, along with the rotation of the first movable axle sleeve around movable axis, is given the band steel application of force;
Movable axis is the round steel being through in two fixed hubs and movable axle sleeve, and the first force application rod and application of force mould can rotate around movable axis, gives the band steel application of force; The point of contact of movable axis and band steel and supporting mould cylindrical is that the starting the arc position of semi arch is contour;
Strengthening gusset is the steel plate being welded between the first force application rod and application of force mould, and application of force mould is played to booster action;
The cold stewing device of straight portion flanging comprises Second-Type bridle iron, two blocks of spacing angle steel, position stopping arch plate, two blocks of flanging chopping blocks, fixed axis, the second movable axle sleeve, application of force angle steel, strengthens angle steel and the second force application rods, wherein:
Second-Type bridle iron is one section of H shaped steel, and the lower wing plate of H shaped steel is weldingly fixed on steel platform, is the assembling carrier of the cold stewing device of straight portion flanging miscellaneous part;
Two spacing angle steel fillet welding in the vertical positions are connected on the upper flange of Second-Type bridle iron, and the four edges place diameter of a circle of two blocks of spacing angle steel equals pipe clamp external diameter, and pipe clamp semi arch is partly stuck in four edges and two flanging chopping block inner sides of two blocks of spacing angle steel;
Position stopping arch plate is 180 ° of arc plates that are highly greater than the steel pipe of band steel width; Position stopping arch plate is welded on the upper flange of Second-Type bridle iron, and the external diameter of position stopping arch plate equals pipe clamp internal diameter, and pipe clamp semi arch is partly stuck in position stopping arch plate outside;
Two flanging chopping blocks are the rectangle steel plates that are highly greater than band steel width; Flanging chopping block is welded on the upper flange of Second-Type bridle iron, and the distance between two flanging chopping blocks equals pipe clamp external diameter, and the stress surface of two flanging chopping blocks is concordant with the end of position stopping arch plate, after the cold stewing of two straight flanges that guarantees pipe clamp is shaped in one plane;
Fixed axis is the round steel being welded on Second-Type bridle iron upper flange, the center of circle that is centered close to position stopping arch plate of fixed axis;
The second movable axle sleeve is the steel pipe welding together with the second force application rod and application of force angle steel, and wherein, the top of the second force application rod is welded on the side of the second movable axle sleeve, two application of force angle steel sides that are welded on the second movable axle sleeve in 90 °;
The second force application rod is the steel pipe that intensity meets force request; Strengthening angle steel for two is welded between the second force application rod and two application of force angle steel; Two application of force angle steel and two reinforcement angle steel form a square, and the second force application rod is on this foursquare diagonal; When the second force application rod is subject to artificial External Force Acting, application of force angle steel, along with the rotation of the second movable axle sleeve around fixed axis, is given the band steel application of force under the cooperation of flanging chopping block.
2. the cold stewing producing device of a kind of wafer type band steel pipe clamp according to claim 1, is characterized in that: the height of described spacing angle steel is greater than the width of band steel.
CN201420338837.2U 2014-06-24 2014-06-24 The cold stewing producing device of a kind of wafer type band steel pipe clamp Expired - Lifetime CN203944677U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420338837.2U CN203944677U (en) 2014-06-24 2014-06-24 The cold stewing producing device of a kind of wafer type band steel pipe clamp

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420338837.2U CN203944677U (en) 2014-06-24 2014-06-24 The cold stewing producing device of a kind of wafer type band steel pipe clamp

Publications (1)

Publication Number Publication Date
CN203944677U true CN203944677U (en) 2014-11-19

Family

ID=51886737

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420338837.2U Expired - Lifetime CN203944677U (en) 2014-06-24 2014-06-24 The cold stewing producing device of a kind of wafer type band steel pipe clamp

Country Status (1)

Country Link
CN (1) CN203944677U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108160771A (en) * 2018-02-07 2018-06-15 中天建设集团有限公司 A kind of band steel founds curved device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108160771A (en) * 2018-02-07 2018-06-15 中天建设集团有限公司 A kind of band steel founds curved device

Similar Documents

Publication Publication Date Title
CN204545055U (en) The manual bending device of a kind of pipe with small pipe diameter steel pipe
CN104532829B (en) A method for manufacturing a pile foundation reinforcement cage
WO2012083638A1 (en) Fixture supporting plate, forward assembly welding fixture and method for welding arc sectional material
CN104942051B (en) A kind of earthing pole anchor ear making apparatus and preparation method thereof
CN202207851U (en) Trackless bevel cutting guide
CN203944677U (en) The cold stewing producing device of a kind of wafer type band steel pipe clamp
CN207857586U (en) A kind of simple self-made band iron bending machine
CN108857241A (en) A kind of attached molten built-up welding cutter ring fixture for processing of plasma
CN207138579U (en) A kind of dustbin arc plate pressure setting
CN203764698U (en) Simple manual plate bending device
CN203999730U (en) Tube panel weld seam thermal treatment rigidity fixture
CN206393091U (en) Adjustable cylinder heater
CN206357648U (en) A kind of implementation for PPR pipe road hot-melt adhesive paste
CN204584569U (en) A kind of for hull flat-bulb steel joint without code assembling device
CN205096294U (en) Roll formula bending machine
CN207138587U (en) A kind of steel bar bending machine
CN205764636U (en) A kind of straw pulverizer tool rest welding tooling
CN207629514U (en) A kind of positioning device
CN206936709U (en) A kind of power shovel bucket spindle seat positions instrument
CN205684520U (en) Automatically steel band press
CN206109949U (en) Concrete road surface crackle producing implement
CN107486642A (en) Header reversible deformation welding procedure
CN222247223U (en) A quartz crucible transfer vehicle
CN208628199U (en) Bending device
CN202450633U (en) Connection structure for large-sized cast steel joint and steel member

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20141119