[go: up one dir, main page]

CN203097921U - System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area - Google Patents

System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area Download PDF

Info

Publication number
CN203097921U
CN203097921U CN 201320082985 CN201320082985U CN203097921U CN 203097921 U CN203097921 U CN 203097921U CN 201320082985 CN201320082985 CN 201320082985 CN 201320082985 U CN201320082985 U CN 201320082985U CN 203097921 U CN203097921 U CN 203097921U
Authority
CN
China
Prior art keywords
station
heat extraction
public area
heat dissipation
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201320082985
Other languages
Chinese (zh)
Inventor
梅宁
熊朝辉
邱少辉
付维纲
刘俊
李香凡
林昶隆
蔡崇庆
赵建伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN 201320082985 priority Critical patent/CN203097921U/en
Application granted granted Critical
Publication of CN203097921U publication Critical patent/CN203097921U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Ventilation (AREA)

Abstract

The utility model relates to a smoke exhaust system of a public area of a platform layer in a subway station, in particular to a system integrating a function of heat dissipation of shielded-gate-type subway station tunnels with a function of smoke exhaust of the public area of a platform. The system comprises the station tunnels on two sides of the platform of the station and heat dissipation air ducts arranged at two ends of the public area of the platform layer. Two ends of each station tunnel are both connected with heat dissipation fans. The top of each station tunnel is provided with a rail top heat dissipation air duct. The heat dissipation fans are connected with the rail top heat dissipation air ducts through the heat dissipation air ducts, the bottoms of the rail top heat dissipation air ducts are provided with first electrical air valves communicated with the station tunnels, and side walls, close to the public area of the platform, of the rail top heat dissipation air ducts are provided with second electrical air valves communicated with the public area of the platform. According to the system, by means of the rail top heat dissipation air ducts of the station, the smoke exhaust of the public area of the platform layer of the shielded-gate-type subway station is achieved through the heat dissipation fans of the station, influences of air pipes on building headroom are reduced, engineering cost is saved, and the system has the advantages of being simple in structure, low in cost, convenient to carry out and easy to control and adjust.

Description

The shield door standard metro station tunnel heat extraction platform public area smoke evacuation system of holding concurrently
Technical field
The utility model relates to the smoke evacuation system of station layer public area in the subway station, is specifically related to a kind of shield door standard metro station tunnel heat extraction platform public area smoke evacuation system of holding concurrently.
Background technology
The smoke evacuation scheme that extensively adopt the station layer public area in the at present domestic subway station that is provided with shield door is: utilize the smoke extractor exhaust fan that is arranged at the station station hall layer to discharge fume by time exhaust duct of station layer public area air-conditioning system, the smoke evacuation system that is the station layer public area is provided with separately, and separates between the smoke evacuation system in the station tunnel.Because the smoke evacuation air quantity of station layer public area is bigger, in order to satisfy the smoke evacuation requirement of station layer, need to increase back the size of exhaust duct, the headroom to building has considerable influence like this; Because need to increase the air quantity and the total head of smoke extractor exhaust fan, cause construction costs to increase to some extent again; And the setting separately respectively of the smoke evacuation system in the smoke evacuation system of station layer public area and the station tunnel, increased manufacturing cost and operation.
Summary of the invention
The purpose of this utility model is exactly in order to solve the deficiency that the above-mentioned background technology exists, to provide a kind of simple in structure, and cost is low, implements the platform public area smoke evacuation system of holding concurrently of shield door standard metro station tunnel heat extraction easily.
The technical solution adopted in the utility model is: a kind of shield door standard metro station tunnel heat extraction platform public area smoke evacuation system of holding concurrently, the station tunnel and the heat extraction air channel that is arranged on two ends, station layer public area that comprise the station platform both sides, the station tunnel two ends all are connected with the heat extraction blower fan, the station tunnel top is provided with tread heat extraction air channel, described heat extraction blower fan links to each other with tread heat extraction air channel by the heat extraction air channel, the bottom in tread heat extraction air channel is provided with first Electric air valve that is communicated with station tunnel, and tread heat extraction air channel is provided with second Electric air valve that is communicated with the platform public area near the sidewall of platform public area.
Further, the entrance point of described heat extraction blower fan and the port of export are provided with sound absorber.
Further, the entrance point of described heat extraction blower fan also is provided with the 3rd Electric air valve.
The utility model is by opening or close the Electric air valve that bottom, tread heat extraction air channel or sidewall are installed, and realizes heat extraction or smoke evacuation to capable district of rail, shield door standard subway station or station layer public area through the heat extraction blower fan of station station hall layer.Compared with prior art, the utility model combines the station layer public area with smoke evacuation system in the station tunnel, designs a kind of station tunnel heat extraction platform smoke evacuation system of holding concurrently, and effectively reduces the influence of airduct to the building headroom, has saved construction costs; And the air quantity of energy capable district of flexible modulation rail or platform public area, help the energy-saving run and the control and regulation of system.Have simple in structurely, cost is low, and it is convenient to implement, and control and regulation are simple, the advantage that operating cost is low.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Fig. 2 be among Fig. 1 A-A to generalized section.
Wherein, 1-heat extraction air channel; 2-heat extraction blower fan; 3.1-the first Electric air valve; 3.2-the second Electric air valve; 3.3-the three Electric air valve; 4-sound absorber; 5-air draft booth; 6-tread heat extraction air channel; 7-shield door; 8-platform public area; 9-station tunnel.
The specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments, is convenient to be well understood to the utility model, but they do not constitute qualification to the utility model.
As shown in Figure 1 and Figure 2, the utility model comprises the station tunnel 9 of station platform both sides, be arranged on the heat extraction air channel 1 at 8 two ends, platform public area, be arranged on heat extraction blower fan 2, tread heat extraction air channel 6 and the Electric air valve of station station hall layer, separate by shield door 7 between station tunnel 9 and the platform public area 8.The two ends in each tunnel, sidecar station 9 all are connected with a heat extraction blower fan 2, and each 9 top, tunnel, sidecar station is provided with tread heat extraction air channel 6, and heat extraction blower fan 2 links to each other with tread heat extraction air channel 6 by heat extraction air channel 1.The bottom in each heat extraction air channel, siding track top 6 is equipped with first Electric air valve 3.1, and tread heat extraction air channel 6 is provided with second Electric air valve 3.2 at the sidewall near platform public area 8.Tread heat extraction air channel 6 is communicated with station tunnel 9 by first Electric air valve 3.1, is communicated with platform public area 8 by second Electric air valve 3.2.The entrance point of heat extraction blower fan 2 and the port of export are provided with sound absorber 4, and the entrance point of heat extraction blower fan 2 also is provided with the 3rd Electric air valve 3.3.
The utility model independently is provided with 1 heat extraction blower fan 2 on the heat extraction air channel 1 at every, heat extraction blower fan 2 independent operatings in every heat extraction air channel 1.Second Electric air valve 3.2 of tread heat extraction air channel 6 sidewalls keeps closed condition under the normal condition; During platform public area 8 breaking out of fires, second Electric air valve 3.2 of tread heat extraction air channel 6 sidewalls is all opened, first Electric air valve, 3.1 parts of 6 bottoms, tread heat extraction air channel are opened, to regulate the cigarette amount ratio of discharging platform public area 8 and station tunnel 9, under the requirement of satisfying platform public area 8 exhaust smoke levels, discharge fume, flue gas is drained into air draft booth 5 by heat extraction blower fan 2.Because of utilizing the flue gas of heat extraction blower fan 2 by 6 eliminating platform public areas 8, tread heat extraction air channel, reduced of the influence of air-conditioning system airduct to the building headroom, saved construction costs.

Claims (3)

1. the shield door standard metro station tunnel heat extraction platform public area smoke evacuation system of holding concurrently, it is characterized in that: the station tunnel and the heat extraction air channel that is arranged on two ends, station layer public area that comprise the station platform both sides, the station tunnel two ends all are connected with the heat extraction blower fan, the station tunnel top is provided with tread heat extraction air channel, described heat extraction blower fan links to each other with tread heat extraction air channel by the heat extraction air channel, the bottom in tread heat extraction air channel is provided with first Electric air valve that is communicated with station tunnel, and tread heat extraction air channel is provided with second Electric air valve that is communicated with the platform public area near the sidewall of platform public area.
2. the shield door standard metro station tunnel according to claim 1 heat extraction platform public area smoke evacuation system of holding concurrently, it is characterized in that: the entrance point and the port of export of described heat extraction blower fan are provided with sound absorber.
3. the shield door standard metro station tunnel according to claim 1 heat extraction platform public area smoke evacuation system of holding concurrently, it is characterized in that: the entrance point of described heat extraction blower fan also is provided with the 3rd Electric air valve.
CN 201320082985 2013-02-22 2013-02-22 System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area Expired - Lifetime CN203097921U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320082985 CN203097921U (en) 2013-02-22 2013-02-22 System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320082985 CN203097921U (en) 2013-02-22 2013-02-22 System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area

Publications (1)

Publication Number Publication Date
CN203097921U true CN203097921U (en) 2013-07-31

Family

ID=48849329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320082985 Expired - Lifetime CN203097921U (en) 2013-02-22 2013-02-22 System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area

Country Status (1)

Country Link
CN (1) CN203097921U (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060865A (en) * 2017-04-28 2017-08-18 长江勘测规划设计研究有限责任公司 The totally-enclosed gate auxiliary smoke exhaust system of track traffic
CN107387146A (en) * 2017-08-17 2017-11-24 中铁第四勘察设计院集团有限公司 Rail traveling region of subway station natural draught system, heat extraction and Tunnel Ventilation System and method
CN107420123A (en) * 2017-05-26 2017-12-01 山东交通学院 A kind of open and close type system station subway platform fume exhaust layout structure
CN108049905A (en) * 2017-11-03 2018-05-18 中国安全生产科学研究院 A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway
CN109404029A (en) * 2018-11-21 2019-03-01 重庆大学 Tunnel wind field regulates and controls method by the island subway platform of underground
CN110094824A (en) * 2019-05-22 2019-08-06 上海市政工程设计研究总院(集团)有限公司 A kind of air cleaning system suitable for subway platform layer
CN110295939A (en) * 2019-07-08 2019-10-01 中铁第四勘察设计院集团有限公司 Road cooperates with platform smoke exhaust system to a kind of overall height gate standard subway station rail against the wind
CN110617078A (en) * 2019-09-27 2019-12-27 广州地铁设计研究院股份有限公司 Embedded air duct type rail passing structure
CN111231990A (en) * 2020-03-24 2020-06-05 中铁第四勘察设计院集团有限公司 Switching device for subway train platform and air duct
CN111255502A (en) * 2020-03-17 2020-06-09 中铁第四勘察设计院集团有限公司 Subway train platform and smoke exhaust method thereof
CN111255727A (en) * 2020-03-17 2020-06-09 中铁第四勘察设计院集团有限公司 Subway train platform and smoke exhaust method thereof
CN112253207A (en) * 2020-11-06 2021-01-22 天津大学 Intensive subway ventilation and smoke exhaust system
CN112523792A (en) * 2020-12-09 2021-03-19 林同棪国际工程咨询(中国)有限公司 Subway station platform smoke discharge control system and control method thereof
CN112983527A (en) * 2021-03-30 2021-06-18 中国安全生产科学研究院 Integrated station tunnel ventilation system and smoke exhaust method thereof
CN114183867A (en) * 2021-11-24 2022-03-15 中铁第五勘察设计院集团有限公司 Air-conditioning ventilation system of subway underground station platform

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060865A (en) * 2017-04-28 2017-08-18 长江勘测规划设计研究有限责任公司 The totally-enclosed gate auxiliary smoke exhaust system of track traffic
CN107420123A (en) * 2017-05-26 2017-12-01 山东交通学院 A kind of open and close type system station subway platform fume exhaust layout structure
CN107420123B (en) * 2017-05-26 2019-03-29 山东交通学院 A kind of open and close type system station subway platform fume exhaust layout structure
CN107387146A (en) * 2017-08-17 2017-11-24 中铁第四勘察设计院集团有限公司 Rail traveling region of subway station natural draught system, heat extraction and Tunnel Ventilation System and method
CN108049905A (en) * 2017-11-03 2018-05-18 中国安全生产科学研究院 A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway
CN108049905B (en) * 2017-11-03 2019-04-16 中国安全生产科学研究院 A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway
CN109404029B (en) * 2018-11-21 2020-06-02 重庆大学 Control method of wind field in tunnel beside underground island subway platform
CN109404029A (en) * 2018-11-21 2019-03-01 重庆大学 Tunnel wind field regulates and controls method by the island subway platform of underground
CN110094824A (en) * 2019-05-22 2019-08-06 上海市政工程设计研究总院(集团)有限公司 A kind of air cleaning system suitable for subway platform layer
CN110295939A (en) * 2019-07-08 2019-10-01 中铁第四勘察设计院集团有限公司 Road cooperates with platform smoke exhaust system to a kind of overall height gate standard subway station rail against the wind
CN110617078A (en) * 2019-09-27 2019-12-27 广州地铁设计研究院股份有限公司 Embedded air duct type rail passing structure
CN110617078B (en) * 2019-09-27 2021-05-18 广州地铁设计研究院股份有限公司 Embedded air duct type rail passing structure
CN111255502A (en) * 2020-03-17 2020-06-09 中铁第四勘察设计院集团有限公司 Subway train platform and smoke exhaust method thereof
CN111255727A (en) * 2020-03-17 2020-06-09 中铁第四勘察设计院集团有限公司 Subway train platform and smoke exhaust method thereof
CN111231990A (en) * 2020-03-24 2020-06-05 中铁第四勘察设计院集团有限公司 Switching device for subway train platform and air duct
CN112253207A (en) * 2020-11-06 2021-01-22 天津大学 Intensive subway ventilation and smoke exhaust system
CN112523792A (en) * 2020-12-09 2021-03-19 林同棪国际工程咨询(中国)有限公司 Subway station platform smoke discharge control system and control method thereof
CN112983527A (en) * 2021-03-30 2021-06-18 中国安全生产科学研究院 Integrated station tunnel ventilation system and smoke exhaust method thereof
CN114183867A (en) * 2021-11-24 2022-03-15 中铁第五勘察设计院集团有限公司 Air-conditioning ventilation system of subway underground station platform

Similar Documents

Publication Publication Date Title
CN203097921U (en) System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area
CN202370563U (en) Heat removal system for tunnel of subway station
CN202946180U (en) Tunnel ventilation system suitable for underground public transit system
CN203925558U (en) The short interval ventilation smoke exhaust structure of subway
CN102519110B (en) Subway platform ventilation and smoke removal distribution structure in station with opened-closed system
CN204002896U (en) One-tunnel one-track subway tunnel natural ventilating structure
CN203452824U (en) Ventilating system for city dual-layer mountain tunnel
CN108035759A (en) A kind of underground railway tunnel fire ventilation smoke extraction system and method
CN105525935A (en) Combined and closed subway station ventilation and air conditioning system and application thereof
CN106356735B (en) A kind of device automatically controlled for hyperbaric chamber exhaust fan
CN107420123A (en) A kind of open and close type system station subway platform fume exhaust layout structure
CN204757258U (en) Bury power equipment's self -ventilation structure energy -savingly
CN102513323A (en) Fume exhaust layout structure for subway platform and screen door system
CN102519120B (en) Open-closed system station subway platform ventilation and smoke exhaust method
CN107387146B (en) Natural smoke exhausting, heat exhausting and tunnel ventilation system and method for subway station track area
CN207218020U (en) One kind dehumidifying switch cubicle
CN203063661U (en) Cooling air flue structure of wheel traction motor and brake of electric wheel mining dumper
CN204754964U (en) Highway tunnel's waste gas discharge structure
CN205731472U (en) A kind of Novel positive pressure Strategy of Ball Mill Coal Pulverizing System add steel ball device
CN206099104U (en) A device for automatic control of exhaust fan in high pressure chamber
CN116378738A (en) Method for ventilating by using ultra-long distance of wind storage bin
CN205930721U (en) Locomotive power battery organizes cooling system
CN204591329U (en) A kind of wind storehouse ventilation installation for tunnel
CN203570335U (en) Ventilation structure of longitudinal air passages of subway long section
CN209339993U (en) A Monsoon-based Ventilation and Smoke Exhaust Device for Tunnel Shaft

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130731