CN202865126U - Dual-layer kiln crown sealing device of lime shaft kiln - Google Patents

Dual-layer kiln crown sealing device of lime shaft kiln Download PDF

Info

Publication number
CN202865126U
CN202865126U CN201220417882.8U CN201220417882U CN202865126U CN 202865126 U CN202865126 U CN 202865126U CN 201220417882 U CN201220417882 U CN 201220417882U CN 202865126 U CN202865126 U CN 202865126U
Authority
CN
China
Prior art keywords
kiln
bell
lime shaft
double
gate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201220417882.8U
Other languages
Chinese (zh)
Inventor
朱波
万敦祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Metallurgical Planning And Design Institute Co ltd
Original Assignee
HUNAN METALLURGY PLANNING AND DESIGNING INST
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN METALLURGY PLANNING AND DESIGNING INST filed Critical HUNAN METALLURGY PLANNING AND DESIGNING INST
Priority to CN201220417882.8U priority Critical patent/CN202865126U/en
Application granted granted Critical
Publication of CN202865126U publication Critical patent/CN202865126U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/40Production or processing of lime, e.g. limestone regeneration of lime in pulp and sugar mills

Landscapes

  • Muffle Furnaces And Rotary Kilns (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The utility model discloses a dual-layer kiln crown sealing device of a lime shaft kiln, belongs to the technical field of kiln equipment and is used for solving the problem of raise dust in a charging process. The dual-layer kiln crown sealing device comprises a charging bell, a charging bucket, a feeding hopper, a slide chute, a charging bell drive device, a dedusting cover, a rope wheel system, a charging bell counterweight system and the like; the dedusting cover covers the slide chute; the slide chute is abutted with the feeding hopper; the feeding hopper is abutted with the charging bucket; the device is arranged at the kiln crown of the lime shaft kiln; a hopper gate is arranged on the feeding hopper; the charging bell is arranged inside the charging bucket; the dedusting cover is connected with a dust removal pipeline; and aggregated rock contained in the kiln and dust in the furnace can be subjected to dual-layer sealing. The dual-layer kiln crown sealing device plays a positive role in improvement of surrounding environment of the lime shaft kiln.

Description

石灰竖窑双层密封窑顶设备Lime shaft kiln double-layer sealed kiln roof equipment

技术领域 technical field

本实用新型涉及一种炉窑设备,特别是气烧石灰竖窑的窑顶装料装置,属炉窑设备技术领域。  The utility model relates to furnace equipment, in particular to a kiln top charging device for a gas-fired lime vertical kiln, belonging to the technical field of furnace equipment. the

背景技术 Background technique

石灰竖窑是生产冶金用石灰的主要窑型,它具有投资少、建设周期短、运行费用低、操作简便等优点而被许多钢铁生产企业采用。石灰竖窑在窑顶设有装料装置,主要由下料溜槽(1)、进料闸门(2)、卷扬系统(3)组成, 其结构如图1所示。装满石料的小车经提升,将石料倒入下料溜槽(1),卷扬系统(3)将进料闸门(2)打开,石料装入窑内。由于气烧石灰竖窑窑内正压较高,这种结构存在着进料闸门(2)打开石料进入窑内时,窑内的粉尘会外逸,扬尘很大,它是石灰竖窑污染周围环境的一个主要污染源。  Lime shaft kiln is the main type of kiln for the production of metallurgical lime. It has the advantages of less investment, short construction period, low operating cost and easy operation, so it is adopted by many iron and steel production enterprises. The lime shaft kiln is equipped with a charging device on the top of the kiln, which is mainly composed of a feeding chute (1), a feeding gate (2), and a hoisting system (3). Its structure is shown in Figure 1. The trolley full of stones is lifted, and the stones are poured into the discharge chute (1), and the winch system (3) opens the feed gate (2), and the stones are loaded into the kiln. Due to the high positive pressure in the gas-fired lime shaft kiln, this structure has a material feed gate (2). When the stone material enters the kiln, the dust in the kiln will escape, and the dust is very large. It is the lime shaft kiln that pollutes the surrounding area. A major source of pollution to the environment. the

发明内容 Contents of the invention

本实用新型提供一种实现粉尘控制的石灰竖窑窑顶装料装置。  The utility model provides a kiln top charging device for a lime shaft kiln which realizes dust control. the

一种石灰竖窑窑顶装料设备, 其结构如图2所示:它是由料钟(4)、料罐(5)、下料斗(6)、溜槽(7)、料钟驱动装置(8) 、除尘罩(9)、绳轮系统(10)、料钟配重系统(11)构成。除尘罩(6)将溜槽(4)罩住,溜槽(4)与下料斗(3)对接,下料斗(3)与料罐(2)对接,其特征是:除尘罩(9)接有抽风除尘管抽走卸料扬尘;料斗闸门(13)与料钟(1)对于进入窑内的石料形成双层密封,从而避免窑内粉尘外逸。  A lime shaft kiln kiln roof charging equipment, its structure is shown in Figure 2: it is composed of material bell (4), material tank (5), lower hopper (6), chute (7), material bell driving device ( 8), dust removal cover (9), sheave system (10), material clock counterweight system (11) constitute. The dust removal cover (6) covers the chute (4), the chute (4) is docked with the lower hopper (3), and the lower hopper (3) is connected with the material tank (2). It is characterized in that the dust removal cover (9) is connected with a draft The dust removal pipe removes the dust from the discharge; the hopper gate (13) and the material bell (1) form a double-layer seal for the stone entering the kiln, thereby preventing the dust in the kiln from escaping. the

附图说明 Description of drawings

图1是改进前原石灰窑窑顶装料装置结构示意图;  Figure 1 is a schematic diagram of the structure of the original lime kiln roof charging device before the improvement;

图2是本实用新型结构示意图;  Fig. 2 is a structural representation of the utility model;

图3是料斗闸门结构示意图;  Figure 3 is a schematic diagram of the structure of the hopper gate;

图4是料钟驱动装置结构示意图。  Fig. 4 is a structural schematic diagram of the clock driving device. the

图中标号表示如下:1、下料溜槽;2、进料闸门;3、卷扬系统;4、料钟;5、料罐;6、下料斗;7、溜槽;8、料钟驱动装置;9、除尘罩;10、绳轮系统;11、料钟配重系统;12、均压管;13、窑顶;14、料斗闸门;15、闸门液压缸;16、闸门限位开关; 17、料钟液压缸;18、料钟限位开关; 19、反射板;20、料车接近开关。  The symbols in the figure are as follows: 1. Unloading chute; 2. Feed gate; 3. Hoisting system; 4. Material bell; 5. Material tank; 6. Unloading hopper; 7. Chute; 9. Dust removal cover; 10. Rope wheel system; 11. Material bell counterweight system; 12. Pressure equalizing pipe; 13. Kiln roof; 14. Hopper gate; 15. Gate hydraulic cylinder; 16. Gate limit switch; 17. Material bell hydraulic cylinder; 18. Material bell limit switch; 19. Reflector plate; 20. Material car proximity switch. the

具体实施方式 Detailed ways

结合实施例对本实用新型的具体实施方式作进一步的说明:  The specific embodiment of the present utility model is described further in conjunction with embodiment:

石灰竖窑装料时,石料经料车提升经过接近开关(20)时,此时料斗闸门(14)打开,料钟(4)处于关闭位置,石料经溜槽(7)进入料罐(5)内。料钟(4)位于料罐内(5),其由料钟液压缸(17)和料钟配重系统(11)共同驱动,料钟液压缸(17)工作行程由料钟限位开关(18)控制并给出信号。因为此时料钟(4)处于关闭位置,窑内的粉尘不能通过进料口外逸。料车卸完一车料后返回去装料,经过接近开关(20)时, 料斗闸门(14)关闭。料斗闸门(14)的启闭位置均由闸门限位开关(16)控制,以保证启 闭准确无误。料罐(5)内设有反射板(19),可以使料罐内物料分布更合理。当料罐(5)接受数批石料,罐内的石料达到设定值时,料钟(4)打开,石料经反射板(19)装入窑内,以获得较均匀的料层分布。料钟(4)的启闭位置由料钟限位开关(18)控制。此时料斗闸门(14)是关闭的。窑内的粉尘被密封在料罐内,不会外逸。这样料斗闸门(14)与料钟(4)对于窑内的石料形成了双层密封,有效的保护了环境。下料斗(6)设有料斗闸门(14),料斗闸门由闸门液压缸(15)驱动,由闸门限位开关(16)控制并给出信号。料车卸料时,会有扬尘冒出,加之此时料斗闸门(14)处于打开位置,密封在料罐(5)中的粉尘也会逸出,设在此处的除尘罩(9)上接有抽风除尘管,能将这些粉尘抽走。除尘罩(9)接有均压管(12)与料罐(5)连接,可防止料钟(4)处于打开状态时料罐(5)内压力上升对设备造成的不良影响。为保证料钟(4)在任何情况下都能关牢,设有料钟配重系统(11)。料钟(4)通过绳轮系统(10)与料钟配重系统(11)相连,料钟(4)通过液压缸(17)和配重系统(11)共同作用,将炉罐(5)底部密封。在事故状态下,也能保证设备安全。  When the lime shaft kiln is charged, when the stone material is lifted by the material truck and passes the proximity switch (20), the hopper gate (14) is opened, the material bell (4) is in the closed position, and the material enters the material tank (5) through the chute (7) Inside. The material bell (4) is located in the material tank (5), and it is jointly driven by the material bell hydraulic cylinder (17) and the material bell counterweight system (11). The working stroke of the material bell hydraulic cylinder (17) is controlled by the material bell limit switch ( 18) Control and give signals. Because the charging clock (4) is in the closed position at this time, the dust in the kiln cannot escape through the feeding port. After the feed truck has unloaded a car of material, it returns to charge, and when passing through the proximity switch (20), the hopper gate (14) is closed. The opening and closing positions of the hopper gate (14) are all controlled by the gate limit switch (16) to ensure that the opening and closing are accurate. The material tank (5) is provided with a reflector (19), which can make the material distribution in the material tank more reasonable. When the material tank (5) receives several batches of stone materials and the stone materials in the tank reach the set value, the material bell (4) is opened, and the stone materials are loaded into the kiln through the reflection plate (19) to obtain a more uniform material layer distribution. The opening and closing position of material bell (4) is controlled by material bell limit switch (18). Hopper gate (14) is closed this moment. The dust in the kiln is sealed in the material tank and will not escape. In this way, the hopper gate (14) and the material bell (4) form a double-layer seal for the stone in the kiln, effectively protecting the environment. Lower hopper (6) is provided with hopper gate (14), and hopper gate is driven by gate hydraulic cylinder (15), is controlled by gate limit switch (16) and gives signal. When the material truck is unloading, there will be dust coming out, and at this time the hopper gate (14) is in the open position, the dust sealed in the material tank (5) will also escape, and the dust removal cover (9) installed here Connected with a ventilation and dust removal pipe, the dust can be sucked away. The dust removal cover (9) is connected with a pressure equalizing pipe (12) to be connected with the material tank (5), which can prevent the adverse effect on the equipment caused by the pressure rise in the material tank (5) when the material bell (4) is in an open state. In order to ensure that the material bell (4) can be closed firmly under any circumstances, a material bell counterweight system (11) is provided. The material bell (4) is connected with the material bell counterweight system (11) through the rope wheel system (10), and the material bell (4) works together through the hydraulic cylinder (17) and the counterweight system (11), and the furnace tank (5) The bottom is sealed. In the case of an accident, it can also ensure the safety of the equipment. the

Claims (6)

1.一种石灰竖窑双层密封窑顶设备,构成包括料钟(4)、料罐(5)、下料斗(6)、溜槽(7)、料钟驱动装置(8) 、除尘罩(9)、绳轮系统(10)、料钟配重系统(11),其特征在于所述石灰竖窑双层密封窑顶设备位于窑顶,由料斗闸门(14)和料钟(4)构成双层密封,所述除尘罩(9)将溜槽(7)罩住,溜槽(7)与下料斗(6)对接,下料斗(6)与料罐(5)对接,除尘罩(9)接有抽风除尘管。 1. A lime shaft kiln double-layer sealed kiln roof equipment, consisting of a material bell (4), a material tank (5), a lower hopper (6), a chute (7), a material bell driving device (8), and a dust cover ( 9), rope wheel system (10), material bell counterweight system (11), characterized in that the double-layer sealed kiln roof equipment of the lime shaft kiln is located on the kiln roof, and consists of a hopper gate (14) and a material bell (4) Double-layer sealing, the dust removal cover (9) covers the chute (7), the chute (7) is docked with the lower hopper (6), the lower hopper (6) is connected with the material tank (5), and the dust removal cover (9) is connected There is a ventilation and dust removal pipe. 2.根据权利要求1所述的石灰竖窑双层密封窑顶设备,其特征在于:所述除尘罩(9)接有均压管(12)与料罐(5)连接。 2. The double-layer sealed kiln roof equipment for lime shaft kiln according to claim 1, characterized in that: the dust removal cover (9) is connected with a pressure equalizing pipe (12) to connect with the material tank (5). 3.根据权利要求1所述的石灰竖窑双层密封窑顶设备,其特征在于:所述下料斗(6)设有料斗闸门(14),料斗闸门由闸门液压缸(15)驱动,由闸门限位开关(16)控制并给出信号。 3. The double-layer sealed kiln roof equipment for lime shaft kiln according to claim 1, characterized in that: the lower hopper (6) is provided with a hopper gate (14), the hopper gate is driven by a gate hydraulic cylinder (15), and is driven by a gate hydraulic cylinder (15). Gate limit switch (16) controls and gives signal. 4.根据权利要求1所述的石灰竖窑双层密封窑顶设备,其特征在于:所述料钟(4)位于料罐(5)内,其由料钟液压缸(17)和料钟配重系统(11)共同驱动,料钟液压缸(17)工作行程由料钟限位开关(18)控制并给出信号。 4. The lime shaft kiln double-layer sealed kiln roof equipment according to claim 1, characterized in that: the material bell (4) is located in the material tank (5), and it is composed of a material bell hydraulic cylinder (17) and a material bell The counterweight system (11) is jointly driven, and the working stroke of the material bell hydraulic cylinder (17) is controlled by the material bell limit switch (18) and a signal is given. 5.根据权利要求1所述的石灰竖窑双层密封窑顶设备,其特征在于:其料罐(5)内设有反射板(19)。 5. The double-layer sealed kiln roof equipment for lime shaft kiln according to claim 1, characterized in that: the material tank (5) is provided with a reflection plate (19). 6.根据权利要求1所述的石灰竖窑双层密封窑顶设备,其特征在于:料钟配重系统经绳轮系统(10)与料钟(4)相连。  6. The double-layer sealed kiln roof equipment for lime shaft kiln according to claim 1, characterized in that: the material bell counterweight system is connected to the material bell (4) via the rope pulley system (10). the
CN201220417882.8U 2012-08-22 2012-08-22 Dual-layer kiln crown sealing device of lime shaft kiln Expired - Lifetime CN202865126U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220417882.8U CN202865126U (en) 2012-08-22 2012-08-22 Dual-layer kiln crown sealing device of lime shaft kiln

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220417882.8U CN202865126U (en) 2012-08-22 2012-08-22 Dual-layer kiln crown sealing device of lime shaft kiln

Publications (1)

Publication Number Publication Date
CN202865126U true CN202865126U (en) 2013-04-10

Family

ID=48031862

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220417882.8U Expired - Lifetime CN202865126U (en) 2012-08-22 2012-08-22 Dual-layer kiln crown sealing device of lime shaft kiln

Country Status (1)

Country Link
CN (1) CN202865126U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104163581A (en) * 2014-06-29 2014-11-26 南京梅山冶金发展有限公司 A sealing method for a lime sleeve kiln having an output of 500 t/d
CN106871646A (en) * 2017-03-15 2017-06-20 中国恩菲工程技术有限公司 High-temperature material charging apparatus
CN109534699A (en) * 2018-10-22 2019-03-29 中冶焦耐(大连)工程技术有限公司 Hanger rod device for lime double-chamber shaft kiln chamber feeding
CN109574520A (en) * 2019-01-16 2019-04-05 唐山神鹰富新环保科技有限公司 Two sections of sealing feeders and method on a kind of double-hearth lime kiln kiln top

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104163581A (en) * 2014-06-29 2014-11-26 南京梅山冶金发展有限公司 A sealing method for a lime sleeve kiln having an output of 500 t/d
CN106871646A (en) * 2017-03-15 2017-06-20 中国恩菲工程技术有限公司 High-temperature material charging apparatus
CN109534699A (en) * 2018-10-22 2019-03-29 中冶焦耐(大连)工程技术有限公司 Hanger rod device for lime double-chamber shaft kiln chamber feeding
CN109534699B (en) * 2018-10-22 2023-09-19 中冶焦耐(大连)工程技术有限公司 A boom device for charging the kiln chamber of a lime double-chamber vertical kiln
CN109574520A (en) * 2019-01-16 2019-04-05 唐山神鹰富新环保科技有限公司 Two sections of sealing feeders and method on a kind of double-hearth lime kiln kiln top

Similar Documents

Publication Publication Date Title
CN202865126U (en) Dual-layer kiln crown sealing device of lime shaft kiln
CN101486088A (en) Hot-metal bottle combined cover and method thereof for adding and lifting cover
CN202074839U (en) Environment friendly scrap preheater
CN203096090U (en) Slag-iron separating device
CN106672662A (en) Fixed earth surface feeder
CN104261153A (en) Self-sealing type sealed discharge device
CN203127794U (en) Sealing automatic para-position weighting type car loading device
CN205999402U (en) Full-automatic slag taking system for granulated slag of blast furnace
CN202063950U (en) Vacuum feeding device for refining furnace
CN202670500U (en) Novel residue-discharging funnel
CN202830063U (en) Blast furnace slag trough and sealing structure thereof
CN104074991A (en) Electric cut-off sliding-plate valve
CN206476356U (en) A kind of anticlogging concrete storage warehouse of anti-flying dust
CN204529666U (en) A kind of lime shaft kiln skew bridge top dedusting tightness system
CN215144653U (en) A device for adding and uncovering a molten iron ladle
CN111453459B (en) Feeding device of double-chamber lime shaft kiln
CN204401045U (en) AOD furnace dedusting and body of heater tiling arrangement
CN208949327U (en) A kind of Novel movable railcar pouring blast furnace slag, iron runner
CN107246799B (en) A feeding and dust removal system for RKEF nickel alloy submerged thermal electric furnace
CN108796151A (en) A kind of closed bf coal injection system
CN205526287U (en) Bucket elevator
CN206279105U (en) A kind of multi-functional firework bright bead granulates safe ingredient sector
CN112524957A (en) Double-chamber kiln top feeding device
CN207138029U (en) Tyre type energy-saving ball mill
CN204182467U (en) Coal pulverizer pebble coal equal pressure discharge device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 410007 505 Shaoshan North Road, Yuhua District, Changsha, Hunan

Patentee after: Hunan metallurgical planning and Design Institute Co.,Ltd.

Address before: 410007 505 Shaoshan North Road, Yuhua District, Changsha, Hunan

Patentee before: HUNAN METALLURGICAL PLAN AND DESIGN INSTITUTE

CP01 Change in the name or title of a patent holder
CX01 Expiry of patent term

Granted publication date: 20130410