CN202731940U - Longitudinal connection device for tunnel steel arch - Google Patents

Longitudinal connection device for tunnel steel arch Download PDF

Info

Publication number
CN202731940U
CN202731940U CN201220389612.0U CN201220389612U CN202731940U CN 202731940 U CN202731940 U CN 202731940U CN 201220389612 U CN201220389612 U CN 201220389612U CN 202731940 U CN202731940 U CN 202731940U
Authority
CN
China
Prior art keywords
steel arch
utility
connecting rods
model
connection device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201220389612.0U
Other languages
Chinese (zh)
Inventor
张立波
黄相锋
张心灵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201220389612.0U priority Critical patent/CN202731940U/en
Application granted granted Critical
Publication of CN202731940U publication Critical patent/CN202731940U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/25Greenhouse technology, e.g. cooling systems therefor

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本实用新型公开了一种隧道钢拱架纵向连接装置,其特征在于在所述钢拱架上等间距的布设有复数个连接杆,所述连接杆两端沿所述钢拱架轴线方向延伸出所述钢拱架,所述连接杆的两端设有方向相反的螺纹,相邻两所述钢拱架的所述连接杆通过一套筒相连接,进而将相邻两所述钢拱架连为一体。本实用新型钢拱架之间采用螺纹连接的方法,工艺较传统焊接在操作难易程度、工作效率、安全文明施工、质量控制等方面均有较大的优势。特别是满足了地铁隧道暗挖十八字方针中“短进尺、快封闭”的要求,在保证现场施工质量、消除安全隐患中发挥了很大作用。

Figure 201220389612

The utility model discloses a tunnel steel arch longitudinal connection device, which is characterized in that a plurality of connecting rods are arranged at equal intervals on the steel arch, and the two ends of the connecting rods extend along the axial direction of the steel arch. Out of the steel arch frame, the two ends of the connecting rod are provided with threads in opposite directions, and the connecting rods of two adjacent steel arch frames are connected by a sleeve, and then the two adjacent steel arch frames The frame is connected as one. The utility model adopts the method of screw connection between the steel arch frames, and the process has greater advantages than traditional welding in terms of operation difficulty, work efficiency, safe and civilized construction, and quality control. In particular, it meets the requirements of "short footage and fast closure" in the 18-character guideline for underground excavation of subway tunnels, and has played a great role in ensuring the quality of on-site construction and eliminating potential safety hazards.

Figure 201220389612

Description

隧道钢拱架纵向连接装置Longitudinal connection device for tunnel steel arch

技术领域 technical field

本实用新型关于一种隧道施工装置,尤其是指一种隧道钢拱架纵向连接装置。The utility model relates to a tunnel construction device, in particular to a tunnel steel arch vertical connection device.

背景技术 Background technique

隧道浅埋暗挖法初期支护采用钢拱架+喷射混凝土,其中钢拱架间距一般为50cm,各榀拱架之间采用纵向连接筋进行连接,保证其整体稳定性,每榀纵向连接筋采用单面搭接焊相连接。The initial support of tunnel shallow buried excavation method adopts steel arch frame + sprayed concrete, in which the distance between steel arch frames is generally 50cm, and the longitudinal connecting bars are used to connect each arch frame to ensure its overall stability. It is connected by single-sided lap welding.

现有技术存在的缺点:The shortcoming that prior art exists:

1、速度慢,通常一榀格栅焊接2个焊工需90分钟。1. The speed is slow, usually it takes 90 minutes for 2 welders to weld a grid.

2、污染重,焊接产生大量有毒气体,且隧道内封闭作业,污染气体难以排除。2. The pollution is heavy, welding produces a large amount of poisonous gas, and the operation is closed in the tunnel, so it is difficult to get rid of the polluted gas.

3、施工质量差,由于现场焊接有仰焊、且需要从格栅缝隙内进行作业,焊接质量难以保证。3. The construction quality is poor. Since the on-site welding requires overhead welding and the work needs to be carried out from the grille gap, the welding quality is difficult to guarantee.

实用新型内容 Utility model content

有鉴于上述问题,本实用新型提供了一种隧道钢拱架纵向连接装置,在所述钢拱架上等间距的布设有复数个连接杆,所述连接杆两端沿所述钢拱架轴线方向延伸出所述钢拱架,所述连接杆的两端设有方向相反的螺纹,相邻两所述钢拱架的所述连接杆通过一套筒相连接,进而将相邻两所述钢拱架连为一体。In view of the above problems, the utility model provides a longitudinal connection device for tunnel steel arches, in which a plurality of connecting rods are arranged at equal intervals on the steel arch, and the two ends of the connecting rods are along the axis of the steel arch The two ends of the connecting rods are provided with threads in opposite directions, and the connecting rods of the two adjacent steel arches are connected by a sleeve, and then the two adjacent The steel arch frame is connected as a whole.

本实用新型钢拱架之间采用螺纹连接的方法,工艺较传统焊接在操作难易程度、工作效率、安全文明施工、质量控制等方面均有较大的优势。特别是满足了地铁隧道暗挖十八字方针中“短进尺、快封闭”的要求,在保证现场施工质量、消除安全隐患中发挥了很大作用。The utility model adopts the method of screw connection between the steel arch frames, and the process has greater advantages than traditional welding in terms of operation difficulty, work efficiency, safe and civilized construction, and quality control. In particular, it meets the requirements of "short footage and fast closure" in the 18-character guideline for underground excavation of subway tunnels, and has played a great role in ensuring the quality of on-site construction and eliminating potential safety hazards.

附图说明 Description of drawings

图1是本实用新型隧道钢拱架纵向连接装置的结构示意图。Fig. 1 is a structural schematic diagram of the utility model tunnel steel arch longitudinal connection device.

图2是本实用新型隧道钢拱架纵向连接装置的局部放大连接示意图。Fig. 2 is a partially enlarged connection schematic diagram of the utility model tunnel steel arch longitudinal connection device.

具体实施方式 Detailed ways

配合参阅图1所示,本实用新型隧道钢拱架纵向连接装置1,在所述钢拱架10上等间距的布设有复数个连接杆20,所述连接杆20与所述钢拱架10之间采用点焊连接,所述连接杆20两端沿所述钢拱架10轴线方向延伸出所述钢拱架10,结合图2所示,所述连接杆20的两端设有方向相反的螺纹21,相邻两所述钢拱架10的所述连接杆20通过一套筒30采用直螺纹连接方式连接,进而将相邻两所述钢拱架10连为一体。Referring to Fig. 1, the tunnel steel arch longitudinal connection device 1 of the present utility model is equipped with a plurality of connecting rods 20 equally spaced on the steel arch 10, and the connecting rods 20 and the steel arch 10 The two ends of the connecting rod 20 extend out of the steel arch 10 along the axial direction of the steel arch 10. As shown in FIG. 2, the two ends of the connecting rod 20 are provided with opposite directions. The connecting rods 20 of the two adjacent steel arches 10 are connected by a straight thread connection through a sleeve 30, and then the two adjacent steel arches 10 are connected as a whole.

应用本实用新型隧道钢拱架纵向连接装置1时:When applying the utility model tunnel steel arch vertical connection device 1:

1、首先按设计钢拱架10间距的长度对连接杆20下料、套丝,在平地上对位。1. Firstly, according to the length of the designed steel arch 10 spacing, the connecting rod 20 is blanked and threaded, and aligned on the flat ground.

2、隧道开挖后,安装钢拱架10,并在相邻钢拱架10之间通过套筒30采用直螺纹连接方式将相邻两钢拱架10连成整体。2. After the excavation of the tunnel, the steel arches 10 are installed, and the two adjacent steel arches 10 are connected as a whole through the sleeve 30 through the straight thread connection between the adjacent steel arches 10 .

以上所述仅是本实用新型的较佳实施例而已,并非对本实用新型做任何形式上的限制,虽然本实用新型已以较佳实施例揭露如上,然而并非用以限定本实用新型,任何熟悉本专业的技术人员,在不脱离本实用新型技术方案的范围内,当可利用上述揭示的技术内容作出些许更动或修饰为等同变化的等效实施例,但凡是未脱离本实用新型技术方案的内容,依据本实用新型的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本实用新型技术方案的范围内。The above descriptions are only preferred embodiments of the utility model, and do not limit the utility model in any form. Although the utility model has been disclosed as above with preferred embodiments, it is not used to limit the utility model. Those skilled in the art, without departing from the scope of the technical solution of the utility model, can use the technical content disclosed above to make some changes or modify equivalent embodiments with equivalent changes, but all the technical solutions of the utility model do not depart from Any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the utility model still belong to the scope of the technical solution of the utility model.

Claims (1)

1. tunnel steel arch frame one-above-the-other layout, it is characterized in that a plurality of connecting rods that are laid with in described steel arch frame equal intervals, described steel arch frame is extended along described steel arch frame axis direction in described connecting rod two ends, the two ends of described connecting rod are provided with the screw thread of opposite direction, the described connecting rod of adjacent two described steel arch framves is connected by a sleeve, and then adjacent two described steel arch framves are connected as a single entity.
CN201220389612.0U 2012-08-07 2012-08-07 Longitudinal connection device for tunnel steel arch Expired - Fee Related CN202731940U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220389612.0U CN202731940U (en) 2012-08-07 2012-08-07 Longitudinal connection device for tunnel steel arch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220389612.0U CN202731940U (en) 2012-08-07 2012-08-07 Longitudinal connection device for tunnel steel arch

Publications (1)

Publication Number Publication Date
CN202731940U true CN202731940U (en) 2013-02-13

Family

ID=47657652

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220389612.0U Expired - Fee Related CN202731940U (en) 2012-08-07 2012-08-07 Longitudinal connection device for tunnel steel arch

Country Status (1)

Country Link
CN (1) CN202731940U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103696786A (en) * 2013-11-14 2014-04-02 中铁隧道集团有限公司 Arch support connecting method for enhancing longitudinal stability between steel arch supports
CN105971641A (en) * 2016-07-08 2016-09-28 山东大学 Mechanical construction and fast location longitudinal connecting device for tunnel confined concrete arch supports
CN106574499A (en) * 2014-06-04 2017-04-19 奥菲奇内·马卡费里意大利有限责任公司 Rib for supporting and consolidating an excavation and method for installing a structure to support and consolidate an excavation
CN110645025A (en) * 2019-10-18 2020-01-03 樊建昆 Double-layer arch frame support construction system for highway soft rock tunnel and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103696786A (en) * 2013-11-14 2014-04-02 中铁隧道集团有限公司 Arch support connecting method for enhancing longitudinal stability between steel arch supports
CN106574499A (en) * 2014-06-04 2017-04-19 奥菲奇内·马卡费里意大利有限责任公司 Rib for supporting and consolidating an excavation and method for installing a structure to support and consolidate an excavation
CN105971641A (en) * 2016-07-08 2016-09-28 山东大学 Mechanical construction and fast location longitudinal connecting device for tunnel confined concrete arch supports
CN105971641B (en) * 2016-07-08 2018-06-22 山东大学 A kind of tunnel confined concrete arch mechanized construction quickly positions one-above-the-other layout
CN110645025A (en) * 2019-10-18 2020-01-03 樊建昆 Double-layer arch frame support construction system for highway soft rock tunnel and construction method thereof

Similar Documents

Publication Publication Date Title
CN202731940U (en) Longitudinal connection device for tunnel steel arch
CN204098918U (en) Dimensional parameters multiple degrees of freedom is adjustable uses shield launching bracket repeatedly
CN207194917U (en) A kind of shape steel tube curtain structure for tunnel advanced support
CN206986644U (en) A kind of tunnel track simply removes device
CN202560241U (en) Forming shield tunnel top segment removing device
CN103696786A (en) Arch support connecting method for enhancing longitudinal stability between steel arch supports
CN203320952U (en) Constructional column template drawing device
CN206616765U (en) Large span is without depending on huge bandy truss pull bar
CN204418658U (en) Integrated hydraulic creeping formwork periphery protection unit
CN205778933U (en) A kind of Tunnel shaped steel arch attachment means
CN204783057U (en) Vertical connecting device of U -shaped of tunnel steel bow member
CN206513387U (en) The exempting from of a kind of tunnel steel arch frame welds adjustable one-above-the-other layout
CN204143790U (en) A kind of outer LED display structure hung on crane span structure
CN207420211U (en) A kind of checking depositing dust wall
CN202707076U (en) Double-line railway tunnel trolley
CN204139577U (en) Embedment means formula wall-connecting piece after a kind of
CN203795824U (en) Suspension type fastener scaffold erecting device
CN204282850U (en) Steel work-concrete combined floor reserved opening protective net frame
CN203278108U (en) power cable laying device
CN202851007U (en) Movable type work platform used for laneway drilling and supporting
CN206233246U (en) For the saw component of box formula equalizer bar foundation ditch support
CN204370807U (en) Exterior wall typified form secondary joist fixture
CN205957134U (en) A novel suspended structure for boiler cigarette wind channel
CN204552757U (en) A kind of energy-saving tunnel and Double pilot tunnel
CN205387945U (en) Steel portal that subway shield zone hard rock changeover portion was used

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130213

Termination date: 20210807