[go: up one dir, main page]

CN202678841U - Fast rush repair tower of high-voltage transmission lines - Google Patents

Fast rush repair tower of high-voltage transmission lines Download PDF

Info

Publication number
CN202678841U
CN202678841U CN 201220345695 CN201220345695U CN202678841U CN 202678841 U CN202678841 U CN 202678841U CN 201220345695 CN201220345695 CN 201220345695 CN 201220345695 U CN201220345695 U CN 201220345695U CN 202678841 U CN202678841 U CN 202678841U
Authority
CN
China
Prior art keywords
tower
wire
insulators
transmission line
synthetic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220345695
Other languages
Chinese (zh)
Inventor
邓渝生
余长国
景文柄
唐娟
周双勇
刘清
杨雪松
孟颖
蒋荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING ELECTRIC POWER Corp MAINTENANCE BRANCH
State Grid Corp of China SGCC
Original Assignee
CHONGQING ELECTRIC POWER Corp MAINTENANCE BRANCH
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING ELECTRIC POWER Corp MAINTENANCE BRANCH, State Grid Corp of China SGCC filed Critical CHONGQING ELECTRIC POWER Corp MAINTENANCE BRANCH
Priority to CN 201220345695 priority Critical patent/CN202678841U/en
Application granted granted Critical
Publication of CN202678841U publication Critical patent/CN202678841U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Insulators (AREA)

Abstract

一种高压输电线路快速抢修塔,包括塔身(10),其左侧依次串接有三个借助钢绞拉线(20)固定在地面上的合成绝缘子(30),合成绝缘子连接处的下方悬挂导线滑车(40);塔身(10)的右侧依次串接有二个借助钢绞拉线(20)固定在地面上的合成绝缘子(30),这二个合成绝缘子连接处的下方悬挂一个导线滑车,所述各合成绝缘子(30)与高压顺线路方向相垂直;所述塔身(10)左侧近顶部处设有架空地线滑车(50);塔身(10)的前后两侧也分别设有钢绞拉线(20)。该抢修塔用钢绞拉线代替了横担,从而使绝缘子变成了固定式,这样避免了悬式绝缘子造成的风偏效应,同时,本实用新型抢修塔还允许高压线路有不大于30°的平面转角。

A rapid repair tower for high-voltage transmission lines, comprising a tower body (10), three synthetic insulators (30) fixed on the ground by means of steel strand stay wires (20) are connected in series on the left side of the tower, and the wires are suspended below the joints of the synthetic insulators Pulley (40); the right side of the tower body (10) is connected in series with two composite insulators (30) fixed on the ground by means of steel strand stay wires (20), and a wire pulley is suspended below the connection of the two composite insulators , the composite insulators (30) are perpendicular to the direction of the high voltage line; the overhead ground wire pulley (50) is provided near the top of the left side of the tower body (10); the front and rear sides of the tower body (10) are also respectively Steel strand stay wire (20) is provided. The emergency repair tower uses steel strands instead of cross arms, so that the insulators become fixed, which avoids the windage effect caused by the suspension insulators. Flat corner.

Description

高压输电线路快速抢修塔High-voltage transmission line rapid repair tower

技术领域 technical field

本实用新型涉及高压架空输电线路事故状态下,能进行快速抢修并临时恢复供电的抢修塔,尤其涉及适用220kV及以下输电线路、取消横担的单柱式铝合金抢修塔。 The utility model relates to a repair tower capable of quick repair and temporary restoration of power supply under the accident state of a high-voltage overhead transmission line, in particular to a single-column aluminum alloy repair tower suitable for 220kV and below transmission lines and canceling the cross arm.

背景技术 Background technique

现有技术高压线路抢险铁塔分为单柱式塔和双柱式塔两大类,称为传统抢险铁塔,其包括避雷线支架、导线横担、绝缘子、塔身及基础。传统抢险铁塔均使用了横担,横担是一个悬臂梁,悬挂在横担下方的绝缘子会产生风偏效应。抢险施工中,应先将横担组装好,再将绝缘子安装完毕后,才能进行导地线施放工作。因而增加了工作量和难度,延长了抢修时间,此其一。 The existing high-voltage line rescue towers are divided into two categories: single-column towers and double-column towers, which are called traditional rescue towers, which include lightning protection wire supports, conductor crossarms, insulators, tower bodies and foundations. Traditional emergency towers use cross-arms, which are cantilever beams, and insulators suspended below the cross-arms will produce windage effects. In the emergency construction, the cross arm should be assembled first, and then the insulators should be installed before the ground wire can be released. Thereby increased workload and difficulty, extended repair time, this one.

其二、传统抢险铁塔对线路平面转角要求较高,线路平面转角一般限制在5°以内。但实际上线路发生断线倒塔事故后,都是在原有的走廊利用原有基础进行铁塔组立和施放导地线工作,或者靠近原有走廊重新选线。在山区,如果要靠近原走廊组立抢险塔时,考虑到线路平面转角的限制以及带电线路对地距离、杆塔受力情况等因素,需要受力更大的塔型才能满足现场施工要求。 Second, the traditional emergency tower has higher requirements on the plane angle of the line, and the plane angle of the line is generally limited to within 5°. But in fact, after the accident of line breakage and tower collapse, the original foundation is used to set up the iron tower and release the ground wire in the original corridor, or re-select the line near the original corridor. In mountainous areas, if emergency towers are to be erected close to the original corridor, taking into account factors such as the limitation of line plane corners, the distance of live lines to the ground, and the force of the tower, towers with greater force are required to meet the construction requirements on site.

实用新型内容 Utility model content

本实用新型要解决的技术问题在于避免上述现有技术的不足之处,而提供一种高压输电线路快速抢修塔,该抢修塔取消了横担,将位于原抢修塔横担下方的绝缘子的一端直接悬挂在塔顶部的拉线板上,而绝缘子的另一端通过钢绞拉线与地面固定,即,用拉线代替了横担,从而使绝缘子变成了固定式,这样避免了悬式绝缘子造成的风偏效应,同时,本实用新型抢修塔还允许高压线路有不大于30°的平面转角。 The technical problem to be solved by the utility model is to avoid the deficiencies of the above-mentioned prior art, and provide a high-voltage transmission line rapid repair tower. It is directly suspended on the guyed board at the top of the tower, and the other end of the insulator is fixed to the ground through the steel strand guyed wire, that is, the guyed wire is used instead of the cross arm, so that the insulator becomes a fixed type, which avoids the wind caused by the suspended insulator. At the same time, the emergency repair tower of the utility model also allows the high-voltage line to have a plane angle not greater than 30°.

本实用新型抢修塔不使用横担,可根据不同电压等级,使用不同长度的合成绝缘子,调整钢绞拉线的角度,以满足电气距离的要求。同时根据不同的导线型号,选择相应规格的拉线、地锚、绝缘子及立柱,以满足机械强度的要求。 The emergency repair tower of the utility model does not use a cross arm, and can use synthetic insulators of different lengths according to different voltage levels to adjust the angle of the steel strand stay wires to meet the requirements of the electrical distance. At the same time, according to different types of wires, choose corresponding specifications of guy wires, ground anchors, insulators and columns to meet the requirements of mechanical strength.

本实用新型解决所述技术问题采用的技术方案是: The technical solution adopted by the utility model to solve the technical problem is:

一种高压输电线路快速抢修塔,用于高压输电线路事故状态下的临时恢复供电,包括由各个基本段组成的柱式塔身,尤其是: A high-voltage transmission line rapid repair tower is used for temporary restoration of power supply under the high-voltage transmission line accident state, including a column-type tower body composed of various basic sections, especially:

所述塔身的左侧沿其塔顶向地面依次串接有三个合成绝缘子,这三个串接在一起的合成绝缘子借助钢绞拉线相对地面倾斜固定,每相邻二个合成绝缘子连接处的下方悬挂一个导线滑车,即,三个合成绝缘子的下方共悬挂两个导线滑车,所述塔身的右侧沿其塔顶向地面依次串接有二个合成绝缘子,这二个串接在一起的合成绝缘子同样借助钢绞拉线相对地面倾斜固定,这二个合成绝缘子连接处的下方同样悬挂一个导线滑车,所述各合成绝缘子与高压顺线路方向相垂直;所述塔身左侧近顶部处设有架空地线滑车; On the left side of the tower body, there are three composite insulators connected in series along the top of the tower to the ground. The three composite insulators connected in series are fixed obliquely relative to the ground by means of steel strand stay wires. A wire block is suspended below, that is, two wire blocks are suspended below the three composite insulators, and the right side of the tower body is connected in series with two composite insulators along the top of the tower to the ground. The composite insulators of the composite insulators are also obliquely fixed relative to the ground by means of steel strand stay wires, and a wire block is suspended below the connection of the two composite insulators. The composite insulators are perpendicular to the direction of the high voltage line; Equipped with overhead ground wire block;

所述塔身的前后两侧分别设有用于平衡所述塔身左右两侧荷载的钢绞拉线。 The front and rear sides of the tower body are respectively provided with steel strand stay wires for balancing the loads on the left and right sides of the tower body.

该抢修塔适用于220kV及以下输电线路,整体为单柱铝合金桁架式构造,所述基本段长6m,横截面为0.6*0.6m的正方形,各基本段借助法兰盘通过螺栓联结,所述塔身顶部安装有一块四方形的拉线板,用于安装所述塔身左右两侧的所述合成绝缘子,及所述塔身前后两侧的所述钢绞拉线,所述塔身腰部也安装有一块四方形的拉线板,用于安装四根钢绞拉线。 The emergency repair tower is suitable for transmission lines of 220kV and below. The whole is a single-column aluminum alloy truss structure. The basic section is 6m long and the cross-section is a square of 0.6*0.6m. A square guy plate is installed on the top of the tower body for installing the synthetic insulators on the left and right sides of the tower body, and the steel strand guy wires on the front and rear sides of the tower body. A square guy plate is installed for installing four steel strand guy wires.

该抢修塔允许不大于30°的高压线路平面转角。 The emergency repair tower allows a plane corner of the high-voltage line not greater than 30°.

所述每相邻的两个合成绝缘子之间连接有金具,其包括两个U型环和连接在这两个U型环之间的牵引板,所述牵引板通过滑车吊环悬挂所述导线滑车。 Fittings are connected between each adjacent two composite insulators, which include two U-shaped rings and a traction plate connected between the two U-shaped rings, and the traction plate suspends the wire block through the pulley ring .

所述导线滑车的直径大于导线截面直径的15倍,同时,所述架空地线滑车的直径也大于架空地线截面直径的15倍;所述导线滑车采用铝合金制成,而所述地线滑车为钢制滑车。 The diameter of the wire pulley is greater than 15 times the cross-sectional diameter of the wire, and at the same time, the diameter of the overhead ground wire pulley is also greater than 15 times the cross-sectional diameter of the overhead ground wire; the wire pulley is made of aluminum alloy, and the ground wire The tackle is a steel tackle.

所述塔身顶部与腰部拉线板的火曲倾角分别为45°和30°。 The curved inclination angles of the top of the tower body and the backguy boards at the waist are 45° and 30° respectively.

该抢修塔最佳高度为24m,导线对地面高度至少达13m。 The optimal height of the emergency repair tower is 24m, and the height of the wire to the ground is at least 13m.

所述合成绝缘子用于支撑和固定导线位置并保证导线的绝缘强度,每个合成绝缘子由两个长 2.5m或3.0m的绝缘子组成。 The composite insulator is used to support and fix the wire position and ensure the insulation strength of the wire. Each composite insulator is composed of two insulators with a length of 2.5m or 3.0m.

同现有技术相比,本实用新型高压输电线路快速抢修塔的有益效果在于: Compared with the prior art, the utility model has the beneficial effects of quickly repairing the tower of the high-voltage transmission line as follows:

首先,本实用新型抢修塔解决了导线风偏问题。由于无横担,导线是靠两个或三个合成绝缘子固定的,那么,只要解决导线带电部分离塔身电气距离到达到安规要求即可,即, 110千伏电气距离为1.0米,220千伏电气距离为1.9米,当然此处还有留有一定裕度,因此,这种塔型较单柱或双柱式抢险塔适应性更强。由于减少了横担,组立本实用新型抢修塔的时间比组立单柱式抢险塔少三之一,如果与双柱式抢险塔相比,至少省时省料一半以上。 First of all, the utility model rush repair tower solves the wind deflection problem of the conductor. Since there is no cross-arm, the wire is fixed by two or three synthetic insulators, then, as long as the electrical distance between the live part of the wire and the tower body meets the requirements of safety regulations, that is, the electrical distance of 110 kV is 1.0 meters, 220 The kilovolt electrical distance is 1.9 meters. Of course, there is a certain margin here. Therefore, this tower type is more adaptable than single-column or double-column emergency towers. Due to the reduction of the cross arm, the time of setting up the emergency repair tower of the utility model is less than one-third than that of the single-column emergency tower, and if compared with the double-column emergency tower, it saves time and materials by at least half.

其次,本实用新型抢修塔还允许高压线路有不大于30°的平面转角,当线路平面转角为30°时,绝缘子串对铅垂线夹角实际为15°。这样,抢修塔就可以避开恢复供电线路走廊,任意选择抢险塔组立位置,只要两基抢险塔之间距离小于300米,导线规格小于LGJ-500/35时就可满足要求。 Secondly, the emergency repair tower of the utility model also allows the high-voltage line to have a plane angle not greater than 30°. When the line plane angle is 30°, the angle between the insulator string and the plumb line is actually 15°. In this way, the emergency repair tower can avoid the corridor of the restoration power supply line, and the location of the emergency tower can be selected arbitrarily, as long as the distance between the two emergency towers is less than 300 meters, and the wire specification is less than LGJ-500/35, the requirements can be met.

附图说明 Description of drawings

图1是本实用新型高压输电线路快速抢修塔的轴测投影结构示意图; Fig. 1 is the schematic diagram of the axonometric projection structure of the utility model high-voltage transmission line quick repair tower;

图2是图1的俯视结构示意图; Fig. 2 is a top view structural schematic diagram of Fig. 1;

图3是图2的局部放大图; Fig. 3 is a partial enlarged view of Fig. 2;

图4是导线滑车40、导线70、牵引板90、U型环100相互连接的结构示意图; Fig. 4 is the structure schematic diagram that wire block 40, wire 70, traction plate 90, U-shaped ring 100 are interconnected;

图5是架空地线滑车50、地线80、牵引板90、U型环100相互连接的的结构示意图。 Fig. 5 is a structural diagram of the interconnection of the overhead ground wire block 50, the ground wire 80, the traction plate 90, and the U-shaped ring 100.

具体实施方式 Detailed ways

下面结合附图对本实用新型的内容进一步详述。 Below in conjunction with accompanying drawing, the content of the present utility model is described in further detail.

参照图1至图5所示,一种高压输电线路快速抢修塔,用于高压输电线路事故状态下的临时恢复供电,包括由各个基本段组成的柱式塔身10,所述塔身10的左侧沿其塔顶向地面依次串接有三个合成绝缘子30,这三个串接在一起的合成绝缘子30借助钢绞拉线20相对地面倾斜固定,每相邻合成绝缘子连接处的下方悬挂一个导线滑车40,即,三个合成绝缘子的下方共悬挂两个导线滑车40,所述塔身10的右侧沿其塔顶向地面依次串接有二个合成绝缘子30,这二个串接在一起的合成绝缘子30同样借助钢绞拉线20相对地面倾斜固定,这二个合成绝缘子连接处的下方同样悬挂一个导线滑车,所述各合成绝缘子30与高压顺线路方向相垂直;所述塔身10左侧近顶部处设有架空地线滑车50;所述导线滑车40上架设导线70,而所述地线滑车50上架设地线80。 Referring to Figures 1 to 5, a high-voltage transmission line rapid repair tower is used for temporary restoration of power supply under the high-voltage transmission line accident state, including a column-type tower body 10 composed of various basic sections, the tower body 10 On the left side, there are three composite insulators 30 connected in series along the top of the tower to the ground. The three composite insulators 30 connected in series are fixed obliquely relative to the ground by means of steel strand stay wires 20, and a wire is suspended below the joint of each adjacent composite insulator. Pulley 40, that is, two wire pulleys 40 are suspended below the three composite insulators. The right side of the tower body 10 is connected in series with two composite insulators 30 along its tower top to the ground, and these two are connected in series. The composite insulators 30 of the composite insulators 30 are also obliquely fixed relative to the ground by means of the steel strand stay wires 20, and a wire block is also suspended below the connection of the two composite insulators, and the composite insulators 30 are perpendicular to the high voltage line direction; An overhead ground wire trolley 50 is arranged near the top; the wire 70 is erected on the wire trolley 40 , and the ground wire 80 is erected on the ground wire trolley 50 .

所述塔身10的前后两侧分别设有用于平衡所述塔身10左右两侧荷载的钢绞拉线20。 The front and rear sides of the tower body 10 are respectively provided with steel strand stay wires 20 for balancing the loads on the left and right sides of the tower body 10 .

该抢修塔适用于220kV及以下输电线路,整体为单柱铝合金桁架式构造,所述基本段长6m,横截面为0.6*0.6m的正方形,各基本段借助法兰盘通过螺栓联结,所述塔身10顶部安装有一块四方形的拉线板60,用于安装所述塔身10左右两侧的所述合成绝缘子30,及所述塔身10前后两侧的所述钢绞拉线20,所述塔身10腰部也安装有一块四方形的拉线板60,用于安装四根钢绞拉线20。 The emergency repair tower is suitable for transmission lines of 220kV and below. The whole is a single-column aluminum alloy truss structure. The basic section is 6m long and the cross-section is a square of 0.6*0.6m. A square guy plate 60 is installed on the top of the tower body 10 for installing the composite insulators 30 on the left and right sides of the tower body 10, and the steel strand guy wires 20 on the front and rear sides of the tower body 10, A square guy plate 60 is also installed at the waist of the tower body 10 for installing four steel strand guy wires 20 .

该抢修塔允许不大于30°的高压线路平面转角,减少了直线抢险塔对线路转角的苛刻要求,传统的直线抢险塔要求线路转角不得大于5°,而本实用新型抢险塔布置只要满足塔与塔之间距离在要求的范围内,其线路转角不大于30°即可,所以该抢险塔适应性较强。 The emergency repair tower allows a high-voltage line plane angle of not more than 30°, which reduces the stringent requirements of the straight line emergency tower on the line angle. The traditional straight line emergency tower requires the line angle not to exceed 5°. The distance between the towers is within the required range, and the line angle is not more than 30°, so the emergency tower has strong adaptability.

所述每相邻的两个合成绝缘子30之间连接有金具,其包括两个U型环100和连接在这两个U型环100之间的牵引板90,所述牵引板90通过滑车吊环悬挂所述导线滑车40。 Fittings are connected between each adjacent two composite insulators 30, which include two U-shaped rings 100 and a traction plate 90 connected between the two U-shaped rings 100, and the traction plate 90 passes through the pulley ring The wire tackle 40 is suspended.

所述导线滑车40的直径大于导线截面直径的15倍,同时,所述架空地线滑车50的直径也大于架空地线截面直径的15倍;所述导线滑车40采用铝合金制成,而所述地线滑车50为钢制滑车。 The diameter of the wire block 40 is greater than 15 times the cross-sectional diameter of the wire, and at the same time, the diameter of the overhead ground wire block 50 is also greater than 15 times the cross-sectional diameter of the overhead ground wire; the wire block 40 is made of aluminum alloy, and the The ground wire block 50 is a steel block.

所述塔身顶部与腰部拉线板60的火曲倾角分别为45°和30°,也就是说,所述塔身顶部和腰部各安装有一块拉线板,顶部拉线板拉线火曲倾角为45°,腰部拉线板拉线火曲倾角为30°,以满足拉线和绝缘子串的拉线倾角,所述的合成绝缘子和拉线均装在塔身顶部的拉线板上,抢险塔的底部插入其中的塔腿上,该塔腿由0.5 m钢底板和十字型支撑板电焊而成,其中支撑板中间开有塔身插入的槽口和穿入螺栓的螺孔,塔腿与抢险塔通过螺栓连接固定,所述槽口的钢板由三块钢板组成,其中,中间的钢板较之两边钢板低,以方便塔身插入,如果抢修塔基础松软时,可考虑采用枕木扩大基础底板面积,以减少其基础应力。 The fire curve inclination angles of the top of the tower body and the waist guy board 60 are 45° and 30° respectively, that is to say, a guy board is respectively installed on the top of the tower body and the waist, and the fire curve inclination angle of the top guy board is 45°. , the inclination angle of the guy wire on the waist guy board is 30° to meet the guy wire inclination angle of the guy wire and the insulator string, the composite insulators and guy wires are installed on the guy board on the top of the tower, and the bottom of the emergency tower is inserted into the tower leg , the tower leg is welded by a 0.5 m steel bottom plate and a cross-shaped support plate, wherein there is a notch in the middle of the support plate for inserting the tower body and a screw hole for the bolt to pass through, and the tower leg and the emergency tower are fixed by bolts. The steel plate of the notch is composed of three steel plates. Among them, the steel plate in the middle is lower than the steel plates on both sides to facilitate the insertion of the tower body. If the foundation of the emergency repair tower is soft, it can be considered to use sleepers to expand the area of the foundation floor to reduce its foundation stress.

该抢修塔塔身最佳高度为四段24m,除合成绝缘子对地面有个几何垂直对地距离,导线对地面高度实际至少达13m以上,而现有抢险铁塔设计的呼称高为9m左右,呼称高指的是位于抢险塔最下方的横担对地面的相对高度,对于110kV和220KV线路来说,现有抢险塔的呼称高一般为9米以上。 The optimal height of the tower body for emergency repair is 24m in four sections. Except that the composite insulator has a geometric vertical distance to the ground, the actual height of the wire to the ground is at least 13m. The height refers to the relative height of the cross arm located at the bottom of the emergency tower to the ground. For 110kV and 220KV lines, the height of the existing emergency tower is generally more than 9 meters.

所述合成绝缘子30用于支撑和固定导线位置并保证导线的绝缘强度,每个合成绝缘子30由两个长 2.5m或3.0m的绝缘子组成。 Described composite insulator 30 is used for supporting and fixing wire position and guarantees the insulation strength of wire, and each composite insulator 30 is made up of two long 2.5m or 3.0m insulators.

本抢修塔塔身采用铝合金制成,相对于钢材塔身,其重量可减轻近三分之一。所述塔身主要由一根下段、若干中段及一根上段组成,下段朝地面部分呈锥形,朝天部分的横截面长宽均为600mm。塔身中、上段宽度均为600mm,各段组成24m、30m或36m不同高度,由于该塔稳定必须靠拉线支撑。所以从塔顶必须有四根临时拉线固定。同时塔身中间部分还需多加四根临时拉线固定。 The tower body of this emergency repair tower is made of aluminum alloy, and its weight can be reduced by nearly one-third compared with the steel tower body. The tower body is mainly composed of a lower section, several middle sections and an upper section. The lower section is tapered toward the ground, and the cross-section length and width of the skyward section are 600 mm. The width of the middle and upper sections of the tower body is 600mm, and each section has a different height of 24m, 30m or 36m. Because the tower is stable, it must be supported by guy wires. So there must be four temporary guy wires fixed from the top of the tower. At the same time, the middle part of the tower needs to add four more temporary stay wires to fix it.

参照图1所示,A、B、C、D为拉线盘或临时地锚,主要起固定塔身不发生偏移,避免抢塔身失去平衡。 Referring to Fig. 1, A, B, C, and D are cable reels or temporary ground anchors, which are mainly used to fix the tower body so that it does not shift and avoid losing balance by grabbing the tower body.

为避免三根导线对塔身电气距离过近造成短路放电,关键是靠近塔身的两根导线必须满足与塔身距离110kV在1.0米以上,220kV在2.1米以上。塔顶因为是架空地线,可以直接接地。 In order to avoid the short-circuit discharge caused by the three wires being too close to the tower body, the key is that the two wires close to the tower body must meet the distance from the tower body of 110kV above 1.0 meters and 220kV above 2.1 meters. Because the top of the tower is an overhead ground wire, it can be directly grounded.

抢险塔塔身平衡必须靠拉线解决,所以左右侧合成绝缘子固定也是靠拉线解决。前后侧拉线因顺线路方向,纯粹是固定作用。 The balance of the emergency tower body must be solved by guy wires, so the fixing of the composite insulators on the left and right sides is also solved by guy wires. The front and rear side pull wires are purely fixed because they follow the direction of the line.

合成绝缘子可任意加工其长度,通过合成绝缘子加工长度和地面拉线的调整,可满足带电导线对塔身距离达到各等级电压对塔身的安全距离。临时拉线可以合盘,即上下拉线合用一块拉线盘,也可以分别用各自拉线盘与地面固定。 The length of the composite insulator can be processed at will. Through the adjustment of the processing length of the composite insulator and the adjustment of the ground cable, the distance between the live wire and the tower body can be satisfied to reach the safe distance of each level of voltage to the tower body. Temporary guy wires can be combined, that is, the upper and lower pull wires share a guy wire drum, or they can be fixed to the ground with their respective guy wire drums.

合成绝缘子通过线路金具与地面拉线固定,架空输电线路三相导线必须满足带电导线对杆塔塔身接地部分的最小距离,而合成绝缘子有着重量轻,加工方便,绝缘性能优良的特点,从图2可知,抢险塔的左侧有两相导线,那么合成绝缘子应有三组,而抢险塔右侧只有一相导线,那么合成绝缘子只有两组,这样能确保证导线与抢险塔、拉线均保持绝缘性能。架空地线通过线路金具与抢险塔身直接接地。 Composite insulators are fixed to the ground by line fittings. The three-phase conductors of overhead transmission lines must meet the minimum distance between live conductors and the grounding part of the tower body. Composite insulators have the characteristics of light weight, convenient processing and excellent insulation performance. It can be seen from Figure 2 If there are two-phase wires on the left side of the emergency tower, then there should be three sets of composite insulators, and there are only one phase wires on the right side of the emergency tower, so there are only two sets of composite insulators, so as to ensure that the insulation performance of the wires, the emergency tower, and the pull wires is maintained. The overhead ground wire is directly grounded to the emergency tower body through line fittings.

绝缘子方向与高压顺线路方向相互垂直,是线路必须满足的条件之一,从另一方面说,三相导线和架空地线应安装在抢修塔横线路方向的两侧。 The direction of the insulator and the direction of the high voltage line are perpendicular to each other, which is one of the conditions that the line must meet. On the other hand, the three-phase conductor and the overhead ground wire should be installed on both sides of the line direction of the emergency repair tower.

     用于塔身平衡的拉线就是用拉线金具UT型线夹和钢绞线与地面拉线固定,同样,合成绝缘子末端有个挂孔,也可用UT型线夹和钢绞线与地面拉线固定。 The guy wires used for tower body balance are fixed to the ground guy wires with guy wire fittings UT-shaped clamps and steel strands. Similarly, there is a hanging hole at the end of the synthetic insulator, which can also be fixed with UT-shaped wire clamps and steel strands to the ground guy wires.

带电的导线由两个合成绝缘子之间的金具与铝质滑车固定,由于合成绝缘子与地面由钢绞线固定,其绝缘子串避免了现有技术抢险塔因风偏造成塔型尺寸偏大、结构复杂的缺点。 The charged wire is fixed by the metal fittings and the aluminum pulley between the two composite insulators. Since the composite insulator and the ground are fixed by steel strands, the insulator string avoids the large size of the tower due to wind deflection in the prior art. Complicated shortcomings.

所谓火曲倾角就是将拉线板弯角朝下弯曲45°或30°,由于绝缘子拉线或塔身顶部顺线路侧拉线对地面夹角为45°,而腰部拉线对地夹角约在30°左右,考虑到拉线对地夹角,所以拉线板火曲倾角要尽量满足实际情况,顶部拉线板和腰部拉线板倾角分别为45度和30度。 The so-called inclination angle of the fire curve is to bend the cable board downward by 45° or 30°, because the angle between the cable of the insulator or the top of the tower along the side of the line is 45° to the ground, and the angle of the cable at the waist to the ground is about 30° , considering the angle between the guy wire and the ground, the inclination angle of the guy board should meet the actual situation as much as possible. The inclination angles of the top guy board and the waist guy board are 45 degrees and 30 degrees respectively.

经计算,上述抢修塔实施例适用于导线规格为LGJ-500/35,单重为1642kg/km;架空地线规格为1 19结构镀锌钢绞线,规格为φ9.0mm,其单重为41.11kg/km,截面积为48.32mm2,或与之重量相匹配的OPGW光纤电缆,按六段36m塔高时,确定该塔使用条件为垂直荷重下的档距不大于500m,水平风荷载档距为330m,若是冬季施工可不考虑架空地线保护角,若夏季施工,可考虑架空地线保护角在30°左右,因为冬季施工雷暴日发生的概率很少,而夏季施工要考虑雷击线路的可能性,所以要考虑架空地线的保护角,必要时抢险塔顶部还要加一根短横担,以加大架空地线保护角,为防止抢险塔遭受雷击,还可敷设完善的接地系统。 According to calculations, the above-mentioned embodiment of the emergency repair tower is applicable to the wire specification of LGJ-500/35, and the unit weight is 1642kg/km; 41.11kg/km, with a cross-sectional area of 48.32mm2, or an OPGW optical fiber cable that matches its weight. When the tower height is 36m in six sections, the use condition of the tower is determined to be that the span under vertical load is not more than 500m, and the horizontal wind load The distance is 330m. If the construction is in winter, the protection angle of the overhead ground wire may not be considered. If the construction is in summer, the protection angle of the overhead ground wire may be considered to be about 30°, because the probability of thunderstorms in winter construction is very small, and the lightning strike line should be considered in summer construction. Possibility, so the protection angle of the overhead ground wire should be considered. If necessary, a short cross arm should be added to the top of the emergency tower to increase the protection angle of the overhead ground wire. In order to prevent the emergency tower from being struck by lightning, a complete grounding system can also be laid .

所述塔身采用铝合金型材分段组成,每段6m,每段之间通过法兰盘连接,所述法兰盘由四块角钢焊接而成,其角钢上还焊有筋板,以加强支撑,筋板之间钻有连接螺栓的连接孔,法兰盘之间用M16螺栓连接。 The tower body is composed of aluminum alloy sections, each section is 6m, and each section is connected by a flange. The flange is welded by four pieces of angle steel, and the angle steel is also welded with ribs to strengthen the structure. For support, connecting holes for connecting bolts are drilled between ribs, and M16 bolts are used for connecting flanges.

合成绝缘子是支持和固定导线在杆塔中位置并保证导线有相当的绝缘强度,为方便运输和储存,其长度为2.5m和3.0m左右。考虑到其电气距离,合成绝缘子可以两个组合成一串斜距为5m至6m的合成绝缘子,从而保证导线垂直距离与水平几何投影距离满足线路线间距离和垂直距离的要求。合成绝缘子是近十来年发展起来的绝缘子,它替代了目前送电线路普遍使用的瓷质和玻璃绝缘子,其特点是绝缘性能好,重量轻,并可根据输电线路电压等级的高低来决定其绝缘长度,例如,低电压绝缘子长度可选择短一些的合成绝缘子,高电压的绝缘子长度可选择长一些的合成绝缘子。 Composite insulators are used to support and fix the position of the wire in the tower and ensure that the wire has a considerable insulation strength. For the convenience of transportation and storage, its length is about 2.5m and 3.0m. Considering its electrical distance, two composite insulators can be combined into a string of composite insulators with a slant distance of 5m to 6m, so as to ensure that the vertical distance of the conductor and the horizontal geometric projection distance meet the requirements of the distance between lines and the vertical distance. Composite insulator is an insulator developed in the past ten years. It replaces the porcelain and glass insulators commonly used in power transmission lines. It is characterized by good insulation performance and light weight, and its insulation can be determined according to the voltage level of the transmission line. Length, for example, the length of low-voltage insulators can choose shorter composite insulators, and the length of high-voltage insulators can choose longer composite insulators.

临时钢绞拉线在地面入土部分可能是土壤或岩石,为抢时间,若是泥土部分,可快速将拉线入土部分挖成长1m、宽0.4m,高2m的土坑,然后埋入带拉线棒的组合式拉线盘,若拉线入土部分为岩石,可浇灌一个上口直径0.2m,下口直径0.4m,深度0.5的带拉线棒的混凝土地锚。 The part of the temporary steel strand stay wire buried in the ground may be soil or rock. To save time, if it is the soil part, the part of the stay wire buried in the soil can be quickly dug into a pit with a length of 1m, a width of 0.4m, and a height of 2m, and then bury it in a combination with a wire rod. Type cable reel, if the part of the cable that enters the soil is rock, you can pour a concrete ground anchor with a cable rod with a diameter of 0.2m at the top, a diameter of 0.4m at the bottom, and a depth of 0.5.

本实用新型抢修塔左侧承载一根架空地线,两根导线的垂直荷载,右侧承载一根导线的垂直荷载。由于两侧垂直荷载不同,该塔的稳定全靠整个塔身上层和中层拉线固定。从图1中可以看出,该塔允许一定的线路平面转角。 The left side of the emergency repair tower of the utility model carries an overhead ground wire, the vertical load of two wires, and the right side carries the vertical load of a wire. Due to the different vertical loads on both sides, the stability of the tower depends entirely on the upper and middle stay wires on the entire tower body. As can be seen from Figure 1, the tower allows a certain line plane angle.

该塔的最大特点是替代了现有通用的带横担抢险塔,借助拉线将合成绝缘子斜拉至地面固定,从图1可看出,拉线固定点分别为A、B、C、D处。本实用新型抢修塔解决导线带电部分与塔身的距离的问题,一是控制地面临时拉线的松紧,二是加大合成绝缘子的长度。当拉线对地夹角为45°时,那么合成绝缘子与塔身夹角可考虑30°,从而给合成绝缘子调整打下基础。 The biggest feature of this tower is that it replaces the existing general-purpose emergency tower with cross arms, and the composite insulator is obliquely pulled to the ground with the help of guy wires. As can be seen from Figure 1, the guy wire fixing points are A, B, C, and D respectively. The utility model rush repair tower solves the problem of the distance between the charged part of the wire and the tower body, one is to control the tightness of the temporary stay wire on the ground, and the other is to increase the length of the composite insulator. When the angle between the guy line and the ground is 45°, the angle between the composite insulator and the tower body can be considered to be 30°, thus laying the foundation for the adjustment of the composite insulator.

Claims (8)

1. a high voltage transmission line pipeline quick-speed first-aid repair tower is used for temporarily restoring electricity under the ultra-high-tension power transmission line accident condition, comprises the pillar body of the tower (10) that is comprised of each basic segment, it is characterized in that:
The left side of described body of the tower (10) is serially connected with three synthetic insulators (30) earthward successively along its cat head, these three synthetic insulators that are serially connected (30) by steel strand backguy (20) relatively face tilt fix, the below of every adjacent synthetic insulator junction hangs a wire coaster (40), namely, the below of three synthetic insulators hangs two wire coasters (40) altogether, the right side of described body of the tower (10) is serially connected with two synthetic insulators (30) earthward successively along its cat head, these two synthetic insulators that are serially connected (30) equally by steel strand backguy (20) relatively face tilt fix, wire coaster of the same suspension in the below of these two synthetic insulator junctions, described each synthetic insulator (30) is perpendicular with high pressure fair line road direction; Place, nearly top, described body of the tower (10) left side is provided with overhead ground wire coaster (50);
The both sides, front and back of described body of the tower (10) are respectively equipped with the steel strand backguy (20) for the described body of the tower of balance (10) left and right sides load.
2. high voltage transmission line pipeline quick-speed first-aid repair tower according to claim 1, it is characterized in that: this emergent repairing tower is applicable to 220kV and following transmission line, integral body is single-column aluminium alloy truss formula structure, described basic segment length 6m, cross section is the square of 0.6*0.6m, each basic segment is passed through bolted on connection by ring flange, described body of the tower (10) top is equipped with a tetragonal strain plate (60), be used for installing the described synthetic insulator (30) of described body of the tower (10) left and right sides, and the described steel of both sides twists backguy (20) before and after the described body of the tower (10), described body of the tower (10) waist also is equipped with a tetragonal strain plate (60), is used for installing the backguy (20) of four steel strands.
3. high voltage transmission line pipeline quick-speed first-aid repair tower according to claim 1, it is characterized in that: this emergent repairing tower allows to be not more than 30 ° high-tension line plane corner, and the insulator string inclination angle is high-tension line plane corner half.
4. high voltage transmission line pipeline quick-speed first-aid repair tower according to claim 1, it is characterized in that: be connected with gold utensil between described every adjacent two synthetic insulators (30), it comprises two U-shaped rings (100) and is connected to towing plate (90) between these two U-shaped rings (100) that described towing plate (90) hangs described wire coaster (40) by the coaster suspension ring.
5. high voltage transmission line pipeline quick-speed first-aid repair tower according to claim 1, it is characterized in that: the diameter of described wire coaster (40) is greater than 15 times of the conductor cross-section diameter, simultaneously, the diameter of described overhead ground wire coaster (50) is also greater than 15 times of overhead ground wire diameter of section; Described wire coaster (40) adopts aluminium alloy to make, and described ground wire coaster (50) is the steel coaster.
6. high voltage transmission line pipeline quick-speed first-aid repair tower according to claim 2, it is characterized in that: the fiery bent inclination angle of described body of the tower top and waist strain plate (60) is respectively 45 ° and 30 °.
7. high voltage transmission line pipeline quick-speed first-aid repair tower according to claim 2 is characterized in that, this emergent repairing tower height is 24m, and wire reaches 13m at least to ground level.
8. high voltage transmission line pipeline quick-speed first-aid repair tower according to claim 1, it is characterized in that: described synthetic insulator (30) is used for support and fixing cord position and guarantees the dielectric strength of wire, and each synthetic insulator (30) is comprised of the insulator of two long 2.5m or 3.0m.
CN 201220345695 2012-07-17 2012-07-17 Fast rush repair tower of high-voltage transmission lines Expired - Lifetime CN202678841U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220345695 CN202678841U (en) 2012-07-17 2012-07-17 Fast rush repair tower of high-voltage transmission lines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220345695 CN202678841U (en) 2012-07-17 2012-07-17 Fast rush repair tower of high-voltage transmission lines

Publications (1)

Publication Number Publication Date
CN202678841U true CN202678841U (en) 2013-01-16

Family

ID=47499717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220345695 Expired - Lifetime CN202678841U (en) 2012-07-17 2012-07-17 Fast rush repair tower of high-voltage transmission lines

Country Status (1)

Country Link
CN (1) CN202678841U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103066523A (en) * 2012-07-17 2013-04-24 重庆市电力公司检修分公司 High-tension transmission line quick repair tower
CN109559584A (en) * 2018-11-28 2019-04-02 国网辽宁省电力有限公司丹东供电公司 Multifunctional mobile distribution training platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103066523A (en) * 2012-07-17 2013-04-24 重庆市电力公司检修分公司 High-tension transmission line quick repair tower
CN103066523B (en) * 2012-07-17 2015-07-01 重庆市电力公司检修分公司 High-tension transmission line quick repair tower
CN109559584A (en) * 2018-11-28 2019-04-02 国网辽宁省电力有限公司丹东供电公司 Multifunctional mobile distribution training platform

Similar Documents

Publication Publication Date Title
CN203377546U (en) High speed railway spanning construction apparatus
CN204316006U (en) A kind of electric transmission line hot-line crosses over block device
CN202401815U (en) Novel composite insulator cross arm repairing tower of 220 kV electric transmission line
CN204386221U (en) A kind of three layers of association type outlet framework for the outdoor GIS transformer station of 220kV
CN111478261B (en) Overhead transmission line galloping suppression device
CN103362343B (en) A six-circuit pole tower with the same tower
CN204326669U (en) A kind of direct current transportation steel tower
CN202678841U (en) Fast rush repair tower of high-voltage transmission lines
CN205646634U (en) Device is strideed across with highway to electric wire netting construction
CN103066523B (en) High-tension transmission line quick repair tower
CN205617888U (en) Power transmission line shaft tower and wire cross arm structure thereof
CN216109881U (en) High-voltage line protection device
CN103956683A (en) Crossing frame system used for 220-KV outgoing line engineering wire erection of 500-KV transformer substation
CN201406865Y (en) 66KV overhead transmission line double-circuit horizontal crossing tower
CN207260730U (en) A kind of double loop cable termination tower
CN114808794A (en) High-voltage line protection support system
CN206554591U (en) A kind of tree-shaped power transmission line column
CN107346873A (en) A kind of New insulated crossing frame
CN213980169U (en) Composite material cross arm tower
CN210517669U (en) Assembled strong and weak current channel
CN211313561U (en) Connecting device for double-loop cable line and overhead line
CN204609420U (en) A kind of voltage levels rapid rush-repair tower
CN204030412U (en) There is engineering stringing crossing frame system in a kind of 500 kv substation 220 kilovolts
CN216240034U (en) A multistage formula wire pole for construction of 10 kilovolts of distribution network
CN112012553A (en) Two-phase composite cross arm tangent tower

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130116