CN202451983U - Multi-pipe support laid along bottom of piping trench - Google Patents
Multi-pipe support laid along bottom of piping trench Download PDFInfo
- Publication number
- CN202451983U CN202451983U CN2011204751266U CN201120475126U CN202451983U CN 202451983 U CN202451983 U CN 202451983U CN 2011204751266 U CN2011204751266 U CN 2011204751266U CN 201120475126 U CN201120475126 U CN 201120475126U CN 202451983 U CN202451983 U CN 202451983U
- Authority
- CN
- China
- Prior art keywords
- trench
- steel
- angle steel
- pipe
- vertical angle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 64
- 239000010959 steel Substances 0.000 claims abstract description 64
- 238000003466 welding Methods 0.000 claims description 7
- 238000009434 installation Methods 0.000 abstract description 4
- 239000000463 material Substances 0.000 abstract description 4
- 229910000838 Al alloy Inorganic materials 0.000 description 2
- 230000007797 corrosion Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 239000003755 preservative agent Substances 0.000 description 1
- 230000002335 preservative effect Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
Images
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model discloses a multi-pipe support laid along the bottom of a piping trench. The multi-pipe support comprises an angle steel (1), the angle steel comprises a horizontal angle steel (2) and vertical angle steels (3), two vertical angle steels (3) are welded at two ends of the horizontal angle steel respectively, bottoms of the two vertical angle steels (3) are welded with a steel plate (5) which is pre-embedded in a trench bottom board, and a pipe strap (7) capable of fixing a pipeline is arranged on the horizontal angle steel (2). The multi-pipe support laid along the bottom of the piping trench has the advantages that the structure is simple, the installation is convenient, besides, the design is ingenious, the multi-pipe support is safe, reliable and practical, the materials are convenient to obtain and the like.
Description
Technical field
The utility model relates to a kind of multitube support, particularly a kind of multitube support that lays along the pipe trench bottom of trench.
Background technique
At present, because a lot of enterprise customer has nothing in common with each other to water supply requirement, the waterpipe kind of laying when quality classification water supply is adopted in feedwater is more than 2 kinds; Consider that from practicing thrift the engineering cost angle other are used for heating, steam line also is arranged in the pipe trench, so pipe trench interior conduit kind is usually greater than 5 kinds; If pipeline is laid immediately in the pipe trench, pipe leakage can produce corrosion to pipeline, so pipeline is provided with support in the pipe trench domestic demand; Existing technology is the support of in pipe trench, installing in advance by the aluminum alloy welding, because the welding aluminum alloy support is complicated, and expense is higher; Brought inconvenience to the workmen when laying, so existing technology is still perfect inadequately.
The model utility content
The purpose of the utility model is: provide a kind of simple in structure, practical, draw materials conveniently, a kind of multitube support that lays along the pipe trench bottom of trench easy for installation, to overcome the deficiency of existing technology.
The utility model is to be constructed as follows: a kind of multitube support that lays along the pipe trench bottom of trench; Comprise angle steel; Angle steel comprises horizontal corner steel and vertical angle steel; Weld two vertical angle steel respectively at the two ends of horizontal corner steel, the steel plate of burying underground in advance in the bottom of two vertical angle steel and the trench floor welds mutually, horizontal corner steel be provided with can fixing tube pipe clamp.
The horizontal corner steel two ends constitute " П " type framework with vertical angle steel welding.
2-10 pipeline can be set on horizontal corner steel.
Owing to adopted technique scheme; At first two vertical angle steel are welded at the two ends of horizontal corner steel respectively; Then the bottom of vertical angle steel is welded with the steel plate of burying underground in advance in the trench floor mutually, fix at the upper surface track of an overturned cart pipeline of horizontal corner steel and with pipe clamp after fixing, accomplish and install; Compared with prior art, the utility model not only has simple in structure, convenient installation, and design ingenious, safe and reliable, practical, the advantage such as convenient of drawing materials.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the plan view of Fig. 1;
Description of reference numerals: 1-angle steel, 2-horizontal corner steel, the vertical angle steel of 3-, 4-trench floor, 5-steel plate, 6-pipeline, 7-pipe clamp.
Embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is done further to specify.
The enforcement of the utility model: a kind of multitube support that lays along the pipe trench bottom of trench; Comprise angle steel 1; Shown in Fig. 1~2, angle steel 1 comprises horizontal corner steel 2 and vertical angle steel 3, welds two vertical angle steel 3 respectively at the two ends of horizontal corner steel 2; The steel plates of burying underground in advance 5 in the bottom of two vertical angle steel 3 and the trench floor 4 weld mutually, horizontal corner steel 2 be provided with can fixing tube 6 pipe clamp 7; Horizontal corner steel 2 two ends constitute " П " type framework with vertical angle steel 3 welding; 2-10 pipeline 6 can be set on horizontal corner steel 2.
When making the utility model; Can select the angle steel of respective length to weld according to actual conditions, piping erection highly also can be adjusted according to actual needs, at first welds two vertical angle steel 3 respectively at the two ends of horizontal corner steel 2; Make the support after the welding form " П " type framework; Two vertical angle steel 3 with " П " type base of frame weld with being embedded in trench floor 4 interior steel plates 5 in advance mutually then, accomplish installing and fixing of support like this, and support and each welding portion must be done preservative treatment; In order to avoid the generation corrosion, angle steel 1 model needs to calculate according to each pipe load definite.
Channelling 6 on the upper surface of the horizontal corner steel that has welded 2, and the pipeline 6 usefulness pipe clamps 7 after laying are fixing, to avoid rolling, and the pipe clamp of selecting for use 7 is the existing pipe fitting that is used for fixing pipeline.
The utility model efficiently solves in the pipe trench multitube road along the problem that the pipe trench bottom of trench lays, and has simple and easy, practical, the convenience of drawing materials, advantage such as easy for installation, is worthy to be popularized.
Claims (5)
1. multitube support that lays along the pipe trench bottom of trench; Comprise angle steel (1); It is characterized in that: angle steel (1) comprises horizontal corner steel (2) and vertical angle steel (3); Weld two vertical angle steel (3) respectively at the two ends of horizontal corner steel (2), the steel plate of burying underground in advance (5) in the bottom of two vertical angle steel (3) and the trench floor (4) welds mutually, horizontal corner steel (2) be provided with can fixing tube (6) pipe clamp (7).
2. the multitube support that lays along the pipe trench bottom of trench according to claim 1 is characterized in that: horizontal corner steel (2) two ends constitute " П " type framework with vertical angle steel (3) welding.
3. the multitube support that lays along the pipe trench bottom of trench according to claim 1 is characterized in that: weld with the interior steel plate of burying underground in advance (5) of trench floor (4) mutually the bottom of two vertical angle steel (3).
4. the multitube support that lays along the pipe trench bottom of trench according to claim 1 is characterized in that: horizontal corner steel (2) be provided with can fixing tube (6) pipe clamp (7).
5. the multitube support that lays along the pipe trench bottom of trench according to claim 1 is characterized in that: on horizontal corner steel (2), 2-10 pipeline (6) can be set.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204751266U CN202451983U (en) | 2011-11-25 | 2011-11-25 | Multi-pipe support laid along bottom of piping trench |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204751266U CN202451983U (en) | 2011-11-25 | 2011-11-25 | Multi-pipe support laid along bottom of piping trench |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202451983U true CN202451983U (en) | 2012-09-26 |
Family
ID=46867848
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011204751266U Expired - Fee Related CN202451983U (en) | 2011-11-25 | 2011-11-25 | Multi-pipe support laid along bottom of piping trench |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202451983U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107763317A (en) * | 2016-08-17 | 2018-03-06 | 五冶集团上海有限公司 | A kind of support locating slot button and its manufacturing process and application method |
CN108177756A (en) * | 2018-02-08 | 2018-06-19 | 亚达管道系统股份有限公司 | Easy cleaning pipe holder |
-
2011
- 2011-11-25 CN CN2011204751266U patent/CN202451983U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107763317A (en) * | 2016-08-17 | 2018-03-06 | 五冶集团上海有限公司 | A kind of support locating slot button and its manufacturing process and application method |
CN108177756A (en) * | 2018-02-08 | 2018-06-19 | 亚达管道系统股份有限公司 | Easy cleaning pipe holder |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205271305U (en) | Group of ocean module drilling machine high pressure line is to using special fixture | |
CN102518300B (en) | Embedded conical bearing joint type steel structure support and construction method thereof | |
CN202451983U (en) | Multi-pipe support laid along bottom of piping trench | |
CN204042190U (en) | A kind of cable bearer be arranged in cable channel | |
CN201419307Y (en) | Pipeline combined line-up clamp | |
CN208034022U (en) | A kind of nozzle for Large Diameter Pipeline steel pipe and nozzle docking facilities | |
CN202047367U (en) | Integral cable clamp for stayed cables | |
CN201764119U (en) | Lining plastic steel pipe fixing device | |
CN206530771U (en) | Detachable large-scale upstanding tube support meanss | |
CN205781389U (en) | Turn floor conjoined support | |
CN209163819U (en) | A kind of working top iron of soil pressing balance pipe jacking machine | |
CN202913423U (en) | Pre-buried connecting device of facility base | |
CN203292747U (en) | Multi-station welding test board locating device | |
CN204922220U (en) | A quick docking pipe support | |
CN201954105U (en) | Pulley support adopting non-digging technology to lay heat network pipeline | |
CN203526868U (en) | Pipe welded junction prefabrication grouping device | |
CN204075618U (en) | A kind of steel-pipe welding device | |
CN203292746U (en) | Welded test plate positioning device having pipe welding positioning function | |
CN201493644U (en) | Tool equipment for welding transformer fuel tank pipe joint | |
CN103255773B (en) | Combined type template support and application method thereof | |
CN208535316U (en) | Assembled piping lane bracket | |
CN206245487U (en) | A kind of steel pipe carries bearing | |
CN206608617U (en) | The heat-insulated fixed support of heat-net-pipeline | |
CN204704489U (en) | Pipeline staggered floor supporting structure | |
CN214946857U (en) | Pipeline pressurized supporting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120926 Termination date: 20141125 |
|
EXPY | Termination of patent right or utility model |