CN202400723U - Lifting tool type hanger frame for prefabricated parts - Google Patents
Lifting tool type hanger frame for prefabricated parts Download PDFInfo
- Publication number
- CN202400723U CN202400723U CN2011205712748U CN201120571274U CN202400723U CN 202400723 U CN202400723 U CN 202400723U CN 2011205712748 U CN2011205712748 U CN 2011205712748U CN 201120571274 U CN201120571274 U CN 201120571274U CN 202400723 U CN202400723 U CN 202400723U
- Authority
- CN
- China
- Prior art keywords
- lifting
- prefabricated components
- girder
- prefabricated parts
- tool type
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
The utility model discloses a lifting tool type hanger frame for prefabricated parts. The lifting tool type hanger frame is characterized by comprising two main beams which are arranged in parallel and a cross beam used for connecting the main beams, wherein the upper ends of the main beams are provided with lifting lugs used for connecting with lifting equipment; the lower ends of the main beams are provided with lifting plates; lifting holes are formed in the lifting plates; and the spaces among the lifting holes are designed according to certain modules. According to the lifting tool type hanger frame for the prefabricated parts, the partial or whole plane prefabricated parts can be lifted in unit projects, the generality of the tool type hanger frame is fully embodied, and the lifting safety and the assembly efficiency of the prefabricated parts are effectively improved.
Description
Technical field
The utility model relates to the building engineering prefabricated components, relates in particular to a kind of building engineering prefabricated components lifting device formula suspension bracket.
Background technology
Prefabricated construction is the inevitable outcome of architectural industrialization, industrialization development; Members such as precast facade, balcony, stair are formed complete building through joint reinforcing through hoisted in position behind corresponding site; For ease of industrialized development; Each position, lifting point should be unified in certain modulus as far as possible in the prefabricated components design, and the lifting device of present stage can not meet this requirement.
Summary of the invention
The purpose of the utility model is in order to overcome the deficiency that above-mentioned background technology exists, and a kind of simple in structure, easy to assembly, building engineering prefabricated components lifting device formula suspension bracket of can handling meeting the multiple planar structure member of certain modulus is provided.
The utility model is achieved in that prefabricated components lifting device formula suspension bracket; It is characterized in that: it comprises two girders that are arranged in parallel, is used to connect the crossbeam of girder; Said girder upper end is provided with the hanger that is used to connect lifting appliance; Said girder lower end is provided with the lifting plate, and said lifting plate is provided with hole for hoist, and said hole for hoist is by certain modulus design pitch.
Said girder is the 120a I-beam section, and length is 2 meters to 5 meters.
Said crossbeam is the 120a I-beam section, and said crossbeam is that perpendicular spacing connects two girders with 1.5 meters.
Said hanger is the upper end that the Q235 steel plate of thick 20mm is welded in girder.
Said hanger is provided with lifting eye, and said lifting eye is the circular hole of diameter 50mm.
Said lifting plate is the steel plate of thick 20mm, long 400mm.
Said hole for hoist is the circular hole of diameter 50mm.
The utility model is simple in structure, and is easy to use, and hole for hoist can lift the some or all of plane prefabricated components of building engineering by certain modulus design pitch, has good commonality, can effectively improve prefabricated components lifting safety and packaging efficiency.
Description of drawings
Fig. 1 is the utilization structure scheme drawing of the utility model.
Among the figure: 1-girder, 2-crossbeam, 3-hanger, 4-lifting eye, 5-lifting plate, 6-hole for hoist.
The specific embodiment
Further specify the utility model below in conjunction with accompanying drawing and embodiment.
Embodiment: present embodiment relates to a kind of prefabricated components lifting device formula suspension bracket; It comprises two girders that are arranged in parallel 1; Its degree is 2 meters to 5 meters, uses the crossbeam 2 that connects girder 1 to connect two girders with 1.5 meters as perpendicular spacing, and girder 1 is the 120a I-beam section with crossbeam 2; Girder 1 upper end is welded with the hanger 3 that is used to connect lifting appliance that the Q235 steel plate of thick 20mm is processed; Hanger 3 is provided with the lifting eye 4 that diameter is 50mm, is welded with the lifting plate 5 that the steel plate of thick 20mm, long 400mm is processed in every girder 1 lower end, and lifting plate 5 is parallel with girder 1; Said lifting plate 5 is provided with the hole for hoist 6 that diameter is 50mm, and the spacing between the hole for hoist 6 is provided with according to plane prefabricated components suspension centre modulus.
Before the lifting, calculate earlier and hung the prefabricated components center-of-gravity position, will be hung again prefabricated components be articulated to the corresponding hole for hoist 6 of present embodiment on, its center of gravity line is overlapped with playing a messenger wire, be that available lifting appliance lifts by crane then.
Claims (7)
1. prefabricated components lifting device formula suspension bracket; It is characterized in that: it comprises two girders that are arranged in parallel (1), is used to connect the crossbeam (2) of girder (1); Said girder (1) upper end is provided with the hanger (3) that is used to connect lifting appliance; Said girder (1) lower end is provided with lifting plate (5), and said lifting plate (5) is provided with hole for hoist (6), and said hole for hoist (6) is by certain modulus design pitch.
2. prefabricated components lifting device formula suspension bracket according to claim 1, it is characterized in that: said girder (1) is the 120a I-beam section, and length is 2 meters to 5 meters.
3. prefabricated components lifting device formula suspension bracket according to claim 1 is characterized in that: said crossbeam (2) is the 120a I-beam section, and said crossbeam (2) is that perpendicular spacing connects two girders (1) with 1.5 meters.
4. prefabricated components lifting device formula suspension bracket according to claim 3, it is characterized in that: said hanger (3) is welded in the upper end of girder (1) for the Q235 steel plate of thick 20mm.
5. prefabricated components lifting device formula suspension bracket according to claim 4, it is characterized in that: said hanger (3) is provided with lifting eye (4), and said lifting eye (4) is the circular hole of diameter 50mm.
6. prefabricated components lifting device formula suspension bracket according to claim 5 is characterized in that: said lifting plate (5) is the steel plate of thick 20mm, long 400mm.
7. prefabricated components lifting device formula suspension bracket according to claim 6, it is characterized in that: said hole for hoist (6) is the circular hole of diameter 50mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011205712748U CN202400723U (en) | 2011-12-30 | 2011-12-30 | Lifting tool type hanger frame for prefabricated parts |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011205712748U CN202400723U (en) | 2011-12-30 | 2011-12-30 | Lifting tool type hanger frame for prefabricated parts |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202400723U true CN202400723U (en) | 2012-08-29 |
Family
ID=46698386
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011205712748U Expired - Fee Related CN202400723U (en) | 2011-12-30 | 2011-12-30 | Lifting tool type hanger frame for prefabricated parts |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202400723U (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103601121A (en) * | 2013-11-25 | 2014-02-26 | 广西玉柴机器股份有限公司 | Hanging device for forklift |
CN105314524A (en) * | 2014-06-26 | 2016-02-10 | 中天建设集团有限公司 | Skylight truss hanger |
CN105329767A (en) * | 2015-11-26 | 2016-02-17 | 中国航空工业集团公司沈阳飞机设计研究所 | Aircraft hoisting appliance |
CN105923533A (en) * | 2016-05-24 | 2016-09-07 | 中交航局第四工程有限公司 | Special lifting appliance for shield segment three-ring horizontal assembling |
CN106185597A (en) * | 2016-08-29 | 2016-12-07 | 上海二十冶建设有限公司 | A kind of large-scale Analytic Tower merogenesis special hanger for hoisting and hanging method |
CN107089586A (en) * | 2017-05-03 | 2017-08-25 | 中建科技有限公司深圳分公司 | The suspender of liftable regulation and the tower crane frock with the suspender |
CN107298371A (en) * | 2017-06-23 | 2017-10-27 | 中冶天工集团有限公司 | A kind of steel structure modularization house universal hanger and on-site hoisting installation method |
CN109132839A (en) * | 2018-10-31 | 2019-01-04 | 科能源科技(天津)有限公司 | The boom hoisting of building block unit |
CN110040621A (en) * | 2019-04-24 | 2019-07-23 | 上海外高桥造船有限公司 | Hanging row and the hoisting method for utilizing it |
CN110963437A (en) * | 2019-12-18 | 2020-04-07 | 林华 | Transfer device for flat prefabricated parts |
CN113071984A (en) * | 2021-04-27 | 2021-07-06 | 中国铁建重工集团股份有限公司 | Hoisting device and hoisting method |
-
2011
- 2011-12-30 CN CN2011205712748U patent/CN202400723U/en not_active Expired - Fee Related
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103601121A (en) * | 2013-11-25 | 2014-02-26 | 广西玉柴机器股份有限公司 | Hanging device for forklift |
CN105314524A (en) * | 2014-06-26 | 2016-02-10 | 中天建设集团有限公司 | Skylight truss hanger |
CN105329767A (en) * | 2015-11-26 | 2016-02-17 | 中国航空工业集团公司沈阳飞机设计研究所 | Aircraft hoisting appliance |
CN105923533A (en) * | 2016-05-24 | 2016-09-07 | 中交航局第四工程有限公司 | Special lifting appliance for shield segment three-ring horizontal assembling |
CN106185597A (en) * | 2016-08-29 | 2016-12-07 | 上海二十冶建设有限公司 | A kind of large-scale Analytic Tower merogenesis special hanger for hoisting and hanging method |
CN106185597B (en) * | 2016-08-29 | 2018-06-12 | 上海二十冶建设有限公司 | A kind of large size Analytic Tower merogenesis special hanger for hoisting and hanging method |
CN107089586B (en) * | 2017-05-03 | 2018-09-07 | 中建科技有限公司深圳分公司 | The suspender that liftable is adjusted and the tower crane tooling with the suspender |
CN107089586A (en) * | 2017-05-03 | 2017-08-25 | 中建科技有限公司深圳分公司 | The suspender of liftable regulation and the tower crane frock with the suspender |
CN107298371A (en) * | 2017-06-23 | 2017-10-27 | 中冶天工集团有限公司 | A kind of steel structure modularization house universal hanger and on-site hoisting installation method |
CN109132839A (en) * | 2018-10-31 | 2019-01-04 | 科能源科技(天津)有限公司 | The boom hoisting of building block unit |
CN110040621A (en) * | 2019-04-24 | 2019-07-23 | 上海外高桥造船有限公司 | Hanging row and the hoisting method for utilizing it |
CN110963437A (en) * | 2019-12-18 | 2020-04-07 | 林华 | Transfer device for flat prefabricated parts |
CN110963437B (en) * | 2019-12-18 | 2021-04-02 | 林华 | Transfer device for flat prefabricated parts |
CN113071984A (en) * | 2021-04-27 | 2021-07-06 | 中国铁建重工集团股份有限公司 | Hoisting device and hoisting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202400723U (en) | Lifting tool type hanger frame for prefabricated parts | |
CN202080812U (en) | Dedicated sling system for large-scaled reinforcing cage | |
CN202575670U (en) | Prefabricated member hoisting tool type lifting beam | |
CN204385883U (en) | A kind of Fabricated balcony | |
CN111847218A (en) | A kind of balance hanger for precast concrete composite slab bottom plate and its making method | |
CN203006792U (en) | Single-attachment-point tower crane wall attaching device | |
CN201195661Y (en) | Permanent deflection-proof sheet metal sling | |
CN205296844U (en) | Precast box girder steel strand wires hoisting point | |
CN102434001B (en) | Construction method of steel beam-steel pipe concrete column and reinforced concrete beam through connection node structure | |
CN205527291U (en) | A frame type frame for hoisting two superimposed sheets | |
CN204455858U (en) | A kind of hanger of large sections steel box-girder | |
CN102383613B (en) | Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device | |
CN106276630A (en) | A kind of internal-climbing tower crane supporting construction of band shearing frame | |
CN104499565A (en) | Assembled balcony | |
CN201746222U (en) | Installation lifting device of cooling wall of furnace shell | |
CN209778062U (en) | An extension spreader for hoisting steel pipe arch bridge lattice girders | |
CN203639016U (en) | Balance beam for hoisting reinforcing steel bars by tower crane | |
CN209367649U (en) | A kind of superimposed sheet hanger | |
CN202467221U (en) | Power plant main workshop steel roof truss hoisting lifting device | |
CN209177844U (en) | A plate type quick lifting device | |
CN206457187U (en) | A kind of pole of mounting steel chimney | |
CN201649667U (en) | Steel cage sinking guide frame | |
CN221720275U (en) | A cap beam lifting auxiliary device | |
CN207244453U (en) | A kind of suspension bridge light anchorage mast apparatus | |
CN202936088U (en) | T-shaped beam steel lifting bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |