CN1867483A - A method of constructing a semi-submersible vessel using dry dock mating - Google Patents
A method of constructing a semi-submersible vessel using dry dock mating Download PDFInfo
- Publication number
- CN1867483A CN1867483A CNA2004800303901A CN200480030390A CN1867483A CN 1867483 A CN1867483 A CN 1867483A CN A2004800303901 A CNA2004800303901 A CN A2004800303901A CN 200480030390 A CN200480030390 A CN 200480030390A CN 1867483 A CN1867483 A CN 1867483A
- Authority
- CN
- China
- Prior art keywords
- upper body
- truss
- dry dock
- support structure
- auxiliary support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 84
- 230000013011 mating Effects 0.000 title claims description 6
- 238000003466 welding Methods 0.000 claims description 12
- 239000000463 material Substances 0.000 claims description 6
- 230000000452 restraining effect Effects 0.000 claims description 5
- 230000008569 process Effects 0.000 claims description 3
- 230000001052 transient effect Effects 0.000 claims 1
- 238000005553 drilling Methods 0.000 abstract description 31
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 11
- 238000010276 construction Methods 0.000 description 15
- 238000009434 installation Methods 0.000 description 5
- 230000032258 transport Effects 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000002401 inhibitory effect Effects 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000007246 mechanism Effects 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 230000008030 elimination Effects 0.000 description 1
- 238000003379 elimination reaction Methods 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B75/00—Building or assembling floating offshore structures, e.g. semi-submersible platforms, SPAR platforms or wind turbine platforms
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/44—Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B77/00—Transporting or installing offshore structures on site using buoyancy forces, e.g. using semi-submersible barges, ballasting the structure or transporting of oil-and-gas platforms
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B1/00—Hydrodynamic or hydrostatic features of hulls or of hydrofoils
- B63B1/02—Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement
- B63B1/10—Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with multiple hulls
- B63B1/107—Semi-submersibles; Small waterline area multiple hull vessels and the like, e.g. SWATH
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63C—LAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
- B63C5/00—Equipment usable both on slipways and in dry docks
- B63C5/02—Stagings; Scaffolding; Shores or struts
- B63C2005/022—Shores or struts, e.g. individual oblique support elements for stabilizing hulls in dry-docks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63C—LAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
- B63C5/00—Equipment usable both on slipways and in dry docks
- B63C5/02—Stagings; Scaffolding; Shores or struts
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Transportation (AREA)
- Civil Engineering (AREA)
- Fluid Mechanics (AREA)
- Physics & Mathematics (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Filling Or Discharging Of Gas Storage Vessels (AREA)
- Earth Drilling (AREA)
- Structures Of Non-Positive Displacement Pumps (AREA)
- Control Of Non-Positive-Displacement Pumps (AREA)
Abstract
一种在造船厂中构建半潜式钻探设备并在船坞中完成全部装配的方法。上部壳体(1)在邻近干船坞的陆地上构建,下部壳体(2)在所述干船坞中构建,并最终在干船坞中完成上下壳体的接合。上部壳体滑动到下部壳体上方的位置,通过往干船坞中注水使下部壳体浮起上升,通过下部壳体中的压舱箱来调整下部壳体的位置。一旦上部壳体和下部壳体接触对准时,便将它们永久的焊接在一起,从而在干船坞中完成了钻探设备的装配。
A method of constructing a semi-submersible drilling rig in a shipyard and fully assembling it in a shipyard. The upper hull (1) is constructed on land adjacent to the dry dock in which the lower hull (2) is constructed and the joining of the upper and lower hulls is finally done in the dry dock. The upper shell slides to a position above the lower shell, and the lower shell is floated up by injecting water into the dry dock, and the position of the lower shell is adjusted through the ballast tank in the lower shell. Once the upper and lower hulls are in contact alignment, they are permanently welded together, completing the rig assembly in dry dock.
Description
技术领域technical field
本发明一般地涉及一种建造近海岸结构的方法,特别的涉及一种在船坞中建造半潜式钻机、船只或结构(称为“钻探设备”)的方法。The present invention relates generally to a method of building an off-shore structure, and in particular to a method of building a semi-submersible drilling rig, vessel or structure (referred to as a "drilling rig") in a dock.
背景技术Background technique
市场上对能在超过150米深的海底进行石油和天然气探测的半潜式钻探设备的需求在不断增加。There is an increasing demand in the market for semi-submersible drilling equipment capable of oil and gas exploration at depths of more than 150 meters.
目前有两种常规的建造半潜式钻探设备的方法。第一种所谓的“连续块堆积”的方法,提供一种“从底部到顶部”顺序构建半潜式钻探设备的方法。根据这种方法,这种平台的下部壳体是浮动的,首先使用海岸起重机或者水上浮式起重机把支柱和连接支撑物一块一块的架设起来。其后立在下部壳体上的上部壳体以相同的方式装配。这种方法一个主要缺点是需要广泛地使用海岸起重机和水上浮式起重机。时常的,建造的进度依赖于水上浮式起重机的能力。此外,大量的连接块的焊接工作将导致长的建造周期。另一方面,配套设备(outfitting)和主要装备的安装和试运行必须在全部钻探设备的架设完成后,才能在钻探设备上进行。这将接下来导致总建造周期较长和装备的试运行被推迟,特别是影响在上部壳体中心部分的钻探装置。There are currently two conventional methods of constructing semi-submersible drilling rigs. The first, the so-called "sequential block build-up" method, provides a method of sequentially building semi-submersible rigs "from bottom to top". According to this method, the lower shell of the platform is floating, and the pillars and connecting supports are first erected piece by piece using a shore crane or a floating crane on water. The upper housing which then stands on the lower housing is assembled in the same way. A major disadvantage of this approach is the extensive use of shore and floating cranes. Frequently, the progress of the construction depends on the capacity of the floating cranes on the water. Furthermore, the welding work of a large number of connecting blocks will result in a long construction period. On the other hand, the installation and trial operation of ancillary equipment (outfitting) and main equipment can only be carried out on the drilling equipment after the erection of all the drilling equipment is completed. This will in turn lead to a longer overall construction period and a delay in the commissioning of the equipment, especially affecting the drilling rig in the central part of the upper casing.
第二种现有的建造半潜式钻探设备的方法是同时建造平台的上部壳体和下部壳体,接着再将这两半连接在一起。根据这种方法,上部壳体装载在驳船上,上部壳体和下部壳体都被牵引到水深能够容纳下部壳体的海面位置。随后下部壳体伴随压舱物和平衡装置沉入需要的深度,只有支柱的顶部暴露在海面之上暂时的停泊,电源系统和复杂的输给系统也需要这种类型的操作。驳船运送上部壳体并将其定位于下部壳体顶部。在接合(mating)之前,驳船必须紧固在与下部壳体相对的位置。随后浮动的驳船在压舱物地作用下,逐渐地在水中下沉直到上部壳体的底部接触到下部壳体支柱。在上部壳体和下部壳体之间连接处进行焊接是最后的操作。这种方法的主要缺点是连接操作通常存在很高的风险,海面环境很恶劣而且无法控制。而且,这种操作可能会面临大量的不确定因素。这种连接操作的安全性和质量将成为主要的关注点。A second existing method of building a semi-submersible rig is to build the upper and lower hulls of the platform simultaneously and then join the two halves together. According to this method, the upper hull is loaded on a barge and both the upper and lower hulls are towed to a position on the sea surface where the water depth is sufficient to accommodate the lower hull. The lower hull is then sunk to the required depth with ballast and balancing devices, only the tops of the struts are exposed above the sea surface for temporary berthing, the power supply system and complex input systems also require this type of operation. A barge transports the upper shell and positions it on top of the lower shell. Before mating, the barge must be secured in position against the lower hull. The floating barge then gradually sinks in the water under the action of the ballast until the bottom of the upper hull touches the lower hull struts. Welding at the junction between the upper and lower shells is the final operation. The main disadvantage of this method is that the connection operation is usually very risky, and the sea environment is harsh and uncontrollable. Moreover, this operation may face a large number of uncertainties. The security and quality of this connection operation will be the main concern.
在许多已出版的或已公开的专利文献中也揭示其他建造海面钻探设备的方法。比如,在2002年2月19日发布的美国专利US6347909中揭示了一种建造钻探设备的方法,其把甲板运送到海面并把该甲板安装在海面的下部结构上。整个甲板制造在用来支撑托顶(jacking)单元的一组多层(deep)钢架上。紧固在一起的甲板和多层钢架滑动到两个浮船(pontoon)上。全部的装配件被拖到安装地点,在那钢架被顶起,同时浮船配被压下去直到装配件被浮船支撑起。随后甲板降低到下部结构上,浮船被撤去。Other methods of constructing offshore drilling rigs are also disclosed in numerous published or disclosed patent documents. For example, in US Pat. No. 6,347,909 issued on February 19, 2002, a method of constructing a drilling rig is disclosed, which transports a deck to the sea surface and installs the deck on the substructure of the sea surface. The entire deck is fabricated on a set of deep steel frames used to support the jacking units. Fastened together decks and multi-level steel frames slide onto two pontoons. The entire assembly is towed to the installation site where the steel frame is jacked up while the pontoon is pushed down until the assembly is supported by the pontoon. The deck was then lowered onto the substructure and the pontoons were removed.
另一个取得专利权的方法在2002年1月22日发布的美国专利US6340272中揭示的,通过接合自身能浮动在海面的甲板结构与自身浮动在海面的下部结构建造海面平台。自身能浮动的甲板结构可以是漂浮的码头(pier)或者是驳船,在其上已经安装有需要的装备。使下部结构部分浸没在水中,码头或者是驳船定位于其上方,随后卸掉基础中的压舱物以在下部结构与码头或驳船之间产生垂直方向的支承力,从而实现接合。Another patented method disclosed in US Pat. No. 6,340,272 issued on January 22, 2002, is to construct an offshore platform by joining a self-floating deck structure with a self-floating substructure. The self-floating deck structure may be a floating pier or barge on which the required equipment is already installed. The joint is achieved by partially submerging the substructure in water, over which a quay or barge is positioned, and subsequently deballasting the foundation to create a vertically oriented bearing force between the substructure and the quay or barge.
另一个取得专利权的方法,在1999年7月10日发布的美国专利US5924822中揭示了一种在海面下部结构上安装甲板的设备和方法。两个独立的浮船每个含有两个彼此空间分离且从浮船向上延伸的支柱。每个浮船都设置有压舱箱,并且在运送的过程中压满压舱物。浮船允许甲板直接放置在海面下部结构的上方。在浮动的下部结构卸掉压舱物的同时对浮船压舱,以将甲板移送到浮动的下部结构。Another patented method, US Pat. No. 5,924,822 issued on July 10, 1999, discloses a device and method for installing a deck on a marine substructure. Two separate pontoons each contain two struts spaced apart from each other and extending upwardly from the pontoons. Each pontoon is provided with ballast tanks and is filled with ballast during transport. The pontoon allows the deck to be placed directly above the sea surface substructure. The pontoon is ballasted while the floating substructure is deballasted to move the deck to the floating substructure.
在1993年8月24日发布的美国专利US5237949揭示了一种建造和装配海面平台的方法,其中海面平台的普通吃水超过建造地点与平台使用位置之间水路的深度。平台的壳体和甲板在很浅的干船坞中分别制造。干船坞中部分注水,壳体上浮到与甲板相接合的位置,平台随后被升起。US Patent No. 5,237,949 issued on August 24, 1993 discloses a method of constructing and assembling an offshore platform, wherein the ordinary draft of the offshore platform exceeds the depth of the waterway between the construction site and the platform service location. The hull and deck of the platform are fabricated separately in a shallow dry dock. The dry dock is partially filled with water, the hull floats up to engage the deck and the platform is then raised.
在1981年11月28日公布的专利号为56-154381的日本专利揭示了一种半潜式钻探设备,它由一对浮船,上甲板和支柱组成。支柱的连接构件的末端部分和甲板末端部分被固定在一起。随后,甲板、浮船和支柱被压舱以使连接构件的中心部分和甲板的中心部分对准,同时调整支柱的倾斜度。Japanese Patent No. 56-154381 published on November 28, 1981 discloses a semi-submersible drilling rig consisting of a pair of pontoons, an upper deck and pillars. The end portions of the connecting members of the struts and the deck end portions are fastened together. Subsequently, the deck, pontoon and struts are ballasted to align the central portion of the connecting member with the central portion of the deck while adjusting the inclination of the struts.
尽管这些已取得专利权的方法可以在一定的条件下建造半潜式钻探设备,但是仍然需要一个更简单、更安全、更有经济效益的方法能够在靠近船坞的地方,最好是在船坞里实现的装配方案。Although these patented methods allow the construction of semi-submersible rigs under certain conditions, there is still a need for a simpler, safer and more cost-effective method that can be built close to the dock, preferably in the dock Implemented assembly scheme.
发明内容Contents of the invention
因此,本发明的目的是提供一种相比于其他方法以安全、可靠且相对低的成本建造半潜式钻探设备的方法。It is therefore an object of the present invention to provide a method of building a semi-submersible drilling rig which is safe, reliable and relatively low cost compared to other methods.
本发明的另一个目的是提供一种在岸边和常规船坞的干船坞中建造半潜式钻探设备的方法。Another object of the present invention is to provide a method of constructing a semi-submersible drilling rig both on shore and in dry dock of conventional docks.
本发明的这些与其他目的通过方法的规定而达到,该方法允许在船坞中同时建造上部壳体和下部壳体,且从而缩短总建造进度。在岸边,上部壳体完全地架设在滑动桁架和支撑塔上,与此同时下部壳体在靠近滑动桁架的干船坞里建造。在干船坞中安装支撑桁架,用来支撑一直从在岸边的上部壳体建造地点延伸到干船坞中的下部壳体上方接合位置的多个滑动梁。These and other objects of the invention are achieved by the provision of a method which allows simultaneous construction of the upper and lower hulls in the dock and thus shortens the overall construction schedule. On shore, the upper hull is erected entirely on the sliding trusses and support towers, while the lower hull is built in dry dock next to the sliding trusses. A support truss is installed in the dry dock to support a plurality of sliding beams extending all the way from the upper hull construction site on shore to the engagement location above the lower hull in the dry dock.
一旦上部壳体和下部壳体建造完成,运用水压托顶系统使上部壳体在滑动梁上滑动到接合位置。接着进行接合操作,使干船坞中的下部壳体上浮直到接触并支撑上部壳体。上部壳体和下部壳体的连接处的焊接最后执行。通过这样的方法,整个接合操作可以在可控制的情况下进行,这保证了操作的安全性和质量。Once the upper and lower shells are constructed, the upper shell is slid into joint position on sliding beams using a hydraulic jacking system. This is followed by a mating operation in which the lower hull in dry dock is floated up until it contacts and supports the upper hull. Welding at the junction of the upper and lower shells is performed last. By such a method, the entire joining operation can be carried out under control, which guarantees the safety and quality of the operation.
附图说明Description of drawings
为了进一步理解本发明的特性和目的,接下来的描述将与附图相结合,其中相应的部分在附图中给出了相应的标号,其中:In order to further understand the nature and purpose of the present invention, the following description will be combined with the accompanying drawings, wherein corresponding parts have provided corresponding symbols in the accompanying drawings, wherein:
图1和图2分别是运载和接合操作装置的外部轮廓视图和俯视图。1 and 2 are an external outline view and a top view of the carrying and engaging handling devices, respectively.
图3是被滑动桁架和建筑塔支撑的上部壳体的横截面图。Figure 3 is a cross-sectional view of the upper shell supported by sliding trusses and building towers.
图4说明了在干船坞里安装支撑桁架的步骤。Figure 4 illustrates the steps involved in installing a support truss in a dry dock.
图5说明了本发明的方法中楔形构件的位置。Figure 5 illustrates the position of the wedge member in the method of the present invention.
图6是说明在干船坞中上部壳体处于下部壳体上方接合位置的横截面图。Figure 6 is a cross-sectional view illustrating the upper shell in the engaged position above the lower shell in dry dock.
图7说明了当上部壳体完全由下部壳体支撑且在接合操作后移除滑动桁架过程的步骤。Figure 7 illustrates the steps of the sliding truss procedure when the upper shell is fully supported by the lower shell and after the joining operation.
图8是显示在钻探设备浮出水面前分离滑动梁的示意图。Figure 8 is a schematic diagram showing the separation of the sliding beam before the drilling rig is surfaced.
图9是说明接合操作完成的示意图。Fig. 9 is a schematic diagram illustrating the completion of the joining operation.
具体实施方式Detailed ways
现在结合附图作更详细的描述,图1和图2显示了包括干船坞的船坞一般设置,其中本发明所述的半潜式钻探设备已建造并接合完毕。如图1和图2所示,半潜式钻探设备包含上部壳体1和一个下部壳体2。在建造的过程中,上部壳体1由位于岸边并邻近干船坞4的滑动桁架3支撑。桁架3还被设计为能够在卸载操作中使用滑动靴8在滑动梁6上滑动整个上部壳体。辅助支撑结构5或者是支撑桁架5架设在干船坞4中。Now described in more detail with reference to the accompanying drawings, Figures 1 and 2 show a general arrangement of a dock, including a dry dock, in which a semi-submersible drilling rig according to the present invention has been built and engaged. As shown in FIGS. 1 and 2 , the semi-submersible drilling equipment includes an upper shell 1 and a
滑动梁或连接构件6在支撑桁架5和滑动桁架3的底部之间延伸。连接构件6在接合操作完成后从支撑桁架上移走,这将在下文中更详细的描述。Sliding beams or connecting
圆柱形的水压式托顶系统7安装在第一个滑动靴8上,锚块9附着在滑动梁6的远端。多股线(strand wire)14连接锚块9与水压式托顶系统7上。在干船坞上的支撑桁架5后面设置了两艘驳船10。驳船10的舱内装满了压舱物。驳船10由拉杆11(tie bar)连接到梁6的远端。驳船10作为平衡物阻止滑动梁6的上升运动。A cylindrical hydraulic jacking system 7 is mounted on the first sliding
在建造上部壳体1之前,在滑动桁架3周围架设了临时支撑塔16以支撑上部壳体1(如图3所示)。在上部壳体1下面设有工作平台19。垂直楼梯17和水平走道18提供了从地面穿过工作平台19到达上部壳体1的通道。这些构件提供了一个安全、友好的工作环境。Before the upper shell 1 is built, a temporary support tower 16 is erected around the sliding
图4说明了干船坞中中支撑桁架5的安装。从图中可以看到,支撑桁架5由上部5A和下部5B组成。下部5B具有连接构件5C,该连接构件5C具有外凸表面,上部5A具有连接构件5D,该连接构件5D具有与凸部5C的半径相吻合的半径的内凹表面。下部5B安装在干船坞底板上,其后用驳船10安装上部5A。桁架5的上部5A简单的下降以停留在下部5B上,使凸面5C和凹面5D相配接合。无需焊接,实现了支撑桁架5的快速安装与拆卸,缩短了干船坞的占用时间。Figure 4 illustrates the installation of the
图5说明了本发明涉及通过在建造过程中在邻近构件之间定位摩擦力增强装置的特征。多个楔形构件,如木楔13,被用了降低对焊接的需求。在图5的局部放大图1中,可以看见两个楔形构件13安装在上部壳体1的底部和滑动桁架3的顶部之间。类似地,如图5的视图A和局部放大图2所示,支撑桁架5和滑动梁6分别安装于船坞底板和支撑桁架之间的楔形构件13上。高耐压强度的木材转移垂直载荷,且邻近构件表面之间的摩擦力约束了侧向转移。Figure 5 illustrates the features of the present invention related to friction enhancing means by positioning them between adjacent components during construction. Multiple wedge members, such as wooden wedges 13, are used to reduce the need for welding. In the partially enlarged view 1 of FIG. 5 , it can be seen that two wedge members 13 are mounted between the bottom of the upper shell 1 and the top of the sliding
一旦上部壳体1和下部壳体2建造完成,上部壳体1被顶起且沿着滑动梁6滑动到下部壳体2上方的位置,并和下部壳体2的支柱大致对准。图6说明了上部壳体1的位置和在前者到达接合位置后下部壳体2的位置。上部壳体底部与下部壳体支柱顶部之间保留大约500毫米的间隙就足够了。Once the upper shell 1 and
本过程的下一步骤是上浮下部壳体。在这个阶段,往干船坞里注水。通过排出各个水舱中的压舱水或者在几个舱内移送压舱水,使下部壳体2处于需要的浮动状态,与此同时,通过浮动的方法调整对准上部壳体和下部壳体。下部壳体2的支柱顶部与下部壳体1的底部最终相接触。在该阶段执行在上部壳体和下部壳体的连接处焊接临时引导块。The next step in the process is to float the lower shell. At this stage, the dry dock is filled with water. By discharging the ballast water in each water tank or transferring the ballast water in several tanks, the
下部壳体2不断地上浮直到其支撑上部壳体1的重量,上部壳体1和下部壳2体之间的缝隙被关闭。随后上部壳体1完全地从滑动梁3移除。在上部壳体和下部壳体的连接处进行充分的焊接,使下部壳体2永久的附接到上部壳体1上。The
在此接合步骤后,半潜式钻探设备已经从辅助支撑结构5上移除。滑动桁架3使用安装在滑动桁架3上的水压式托顶系统7从接合位置回到岸边。在干船坞4上方的滑动梁6使用安装在滑动梁6上的水压式托顶系统7,9被切断、拉出并卸到驳船10上。随后使用一辆或多辆运输装置或浅湾拖车12从干船坞4移除连接梁6。After this joining step, the semi-submersible drilling rig has been removed from the
图8显示了具有壳体1和2的整个钻探设备在干船坞4中的接合位置从支撑桁架5浮出水面。FIG. 8 shows the joint position of the entire drilling rig with
图9是说明在干船坞4中的支撑桁架5移除钻探设备的俯视图。FIG. 9 is a top view illustrating the removal of the drilling rig from the
本发明所提供的搭建平台的方法与现有的常规钻探设备建造方法相比有以下几个优点。通过同时建造上部壳体和下部壳体,使得总建造周期被缩短。避免了在恶劣海面环境的高风险和不确定的接合过程,因此,确保了高安全性和质量。因此,上部壳体和下部壳体良好对准和设备的提早试运行成为了可能。Compared with the existing conventional drilling equipment construction method, the platform construction method provided by the present invention has the following advantages. By building the upper shell and the lower shell simultaneously, the total construction period is shortened. Risky and uncertain joining processes in harsh sea environments are avoided, thus ensuring high safety and quality. Thus, good alignment of the upper and lower housings and early commissioning of the device are possible.
本方法提供了一种在上部壳体的整个安装过程中考虑到载荷模式的变化支撑上部壳体的适当结构。在上部壳体的下面架设了安全的工作平台,其增强了本发明的安全性,并使工作环境变得很友好。塔提供了竖直的和水平的从地面到上部壳体的下方的工作平台的安全通道。另外,能够无阻碍的将上部壳体滑动到接合位置。The present method provides a suitable structure to support the upper shell taking into account changes in the load pattern throughout the installation of the upper shell. A safe working platform is set up under the upper shell, which enhances the safety of the present invention and makes the working environment very friendly. The tower provides vertical and horizontal safe access from the ground to the working platform below the upper shell. In addition, the upper housing can be slid into the engaged position without hindrance.
支撑桁架构件很容易安装,很容易排列,并且很容易移除。不需要在干船坞底板上进行任何额外的打桩工程。滑动过程中将由微小的地表下沉导致的潜在问题完全消除了,且下部壳体的交叉撑条和支撑桁架之间的干涉被降到最低,甚至被消除。Supporting truss members are easy to install, easy to line up, and easy to remove. There is no need for any additional piling work on the dry dock floor. Potential problems caused by minor ground subsidence during sliding are completely eliminated, and interference between the cross braces of the lower shell and the supporting trusses is minimized or even eliminated.
本发明方法的额外优点是取消了昂贵的地面锚点,以经受滑动工程中高强度的拉力;使用这种方法可回收滑动梁和支撑桁架,并保护了滑动表面。木楔允许更好的调整机构的水平,并通过表面间的摩擦力限制了机构的横向移动。An additional advantage of the method of the invention is the elimination of expensive ground anchor points to withstand the high tension forces involved in sliding engineering; using this method the sliding beams and support trusses are recovered and the sliding surfaces are protected. Wooden wedges allow better leveling of the mechanism and limit the lateral movement of the mechanism through friction between the surfaces.
尽管本发明如上参考特殊实施例进行了描述,但本说明书并意味着认识的局限。所揭示的实施例的不同变化,如同本发明的其他实施例一样,对本领域的技术人员通过参考说明书是很明显的。本领域的技术人员显然能在本发明基础上,进行各种各样的变化。但这些变化显然应该包含在本发明的权利要求中。While the invention has been described above with reference to particular embodiments, this description is not to be construed as limiting. Various variations of the disclosed embodiments, as with other embodiments of the invention, will become apparent to those skilled in the art upon reference to the description. Those skilled in the art can obviously make various changes on the basis of the present invention. But these changes should obviously be included in the claims of the present invention.
权利要求书claims
(按照条约第19条的修改)(Amended in accordance with Article 19 of the Treaty)
1.一种建造半潜式钻探设备的方法,包含以下几个步骤1. A method for building semi-submersible drilling equipment, comprising the following steps
设置上部壳体和在陆地上支撑该壳体的滑动桁架装置;providing an upper hull and a sliding truss arrangement supporting the hull on land;
在干船坞中设置靠近该滑动桁架装置的下部壳体;providing a lower hull adjacent to the sliding truss arrangement in dry dock;
提供一种装置,该装置安装在所述的滑动桁架装置上,用来将上部壳体移动到下部壳体上方的位置;providing a device mounted on the sliding truss device for moving the upper shell to a position above the lower shell;
移送上部壳体到下部壳体上方的位置;Move the upper shell to a position above the lower shell;
调整下部壳体中的压舱物,使下部壳体与上部壳体对准;Adjust the ballast in the lower shell so that the lower shell is aligned with the upper shell;
将上部壳体接合到下部壳体,从而装配半潜式钻探设备;以及从上部壳体支撑装置移除半潜式钻探设备。joining the upper shell to the lower shell, thereby assembling the semi-submersible drilling rig; and removing the semi-submersible drilling rig from the upper shell support means.
2.如权利要求1所述的方法,进一步包含以下步骤:当上部壳体定位于下部壳体上方时,设置辅助桁架支撑结构以暂时支撑上部壳体,且其中所述从滑动桁架装置移除半潜式钻探设备的步骤进一步包括步骤:钻探设备从辅助桁架支撑结构上移除半潜式钻探设备。2. The method of claim 1, further comprising the step of providing an auxiliary truss support structure to temporarily support the upper shell while the upper shell is positioned above the lower shell, and wherein said removal from the sliding truss means The step of semi-submersible drilling rig further includes the step of removing the semi-submersible drilling rig from the auxiliary truss support structure.
3.如权利要求1所述的方法,其中所述设置滑动桁架装置的步骤进一步包括如下步骤:在所述滑动桁架与塔式上层结构上构造上部壳体之前架设滑动桁架和多个塔式上层结构以将上部壳体保持在陆地上抬高的位置,用于提供通向上部壳体的水平和垂直通道。3. The method of claim 1, wherein said step of providing a sliding truss arrangement further comprises the step of erecting a sliding truss and a plurality of tower superstructures prior to constructing an upper shell on said sliding truss and tower superstructure Structure to hold the upper hull in an elevated position on land for providing horizontal and vertical access to the upper hull.
4.如权利要求3所述的方法,进一步包含在上部壳体和滑动桁架之间没有焊接的情况下,设置抑制上部壳体相对于滑动桁架的水平移动的装置的步骤。4. The method of
5.如权利要求4所述的方法,其中所述的抑制装置包含多个楔形构件,该楔形构件至少在表面由增加摩擦力的材料形成,所述的楔形构件安装在上部壳体的底部表面与滑动桁架的接触表面之间。5. The method of
6.如权利要求2所述的方法,其中设置所述辅助桁架支撑结构的步骤包含在干船坞设置支撑桁架并设置在辅助桁架支撑结构和滑动桁架装置之间延伸的连接梁的步骤。6. The method of
7.如权利要求6所述的方法,进一步包含在上部壳体和滑动桁架之间没有焊接或锚接的情况下,设置抑制辅助桁架支撑结构相对于干船坞的水平移动的装置的步骤。7. A method as claimed in
8.如权利要求7所述的方法,其中所述抑制装置包含多个楔形构件,该楔形构件至少在表面由增加摩擦力的材料形成,所述楔形构件安装在辅助支撑结构底表面和干船坞底板之间。8. The method of claim 7, wherein said restraint means comprises a plurality of wedge-shaped members formed at least on the surface of a friction-increasing material, said wedge-shaped members mounted on the bottom surface of the auxiliary support structure and the dry dock between the bottom plates.
9.如权利要求6所述的方法,进一步包含在辅助桁架支撑结构和连接梁之间不进行焊接的情况下,设置用于抑制连接梁和辅助桁架支撑结构的水平移动的装置。9. The method of
10.如权利要求9所述的方法,其中所述的抑制装置包含多个楔形构件,该楔形构件至少表面由增加摩擦力的材料形成,所述楔形构件安装在连接梁底表面和辅助桁架支撑结构的接触表面之间。10. The method of claim 9, wherein said restraining means comprises a plurality of wedge-shaped members, at least one surface of which is formed of a friction-increasing material, said wedge-shaped members are mounted on the bottom surface of the connecting beam and the auxiliary truss support between the contacting surfaces of the structure.
11.如权利要求6所述的方法,其中所述的移送上部壳体的装置包含安装在滑动桁架装置和连接梁上的托顶系统。11. The method of
12.如权利要求6所述的方法,其中所述的连接梁具有近端,且所述近端紧固到滑动桁架装置。12. The method of
13.如权利要求12所述的方法,进一步包含将连接梁的远端可拆卸地紧固到位于辅助桁架支撑结构后部的平衡装置的步骤。13. The method of claim 12, further comprising the step of releasably securing the distal ends of the connecting beams to a balancing device located at the rear of the auxiliary truss support structure.
14.如权利要求1所述的方法,进一步包含在干船坞底板上安装辅助桁架支撑结构的步骤。14. The method of claim 1, further comprising the step of installing an auxiliary truss support structure on the dry dock floor.
15.如权利要求14所述的方法,所述的辅助桁架支撑结构包含具有外凸连接构件的下部和具有对应的内凹连接构件的上部,且所述在干船坞底板上安装辅助桁架支撑结构的步骤包含使辅助桁架支撑结构的上部和下部配对接合的步骤。15. The method of claim 14, wherein said auxiliary truss support structure comprises a lower portion having male connecting members and an upper portion having corresponding female connecting members, and said installing the auxiliary truss supporting structure on the dry dock floor The step comprises the step of matingly engaging the upper and lower portions of the auxiliary truss support structure.
16.如权利要求2所述的方法,其中所述的从辅助桁架支撑结构上移除半潜式钻探设备的步骤包含回收滑动桁架装置和连接梁的步骤。16. The method of
17.如权利要求16所述的方法,进一步包含使用安装在滑动桁架上的托顶系统拉滑动桁架的步骤。17. The method of claim 16, further comprising the step of pulling the sliding truss using a jacking system mounted on the sliding truss.
18.如权利要求16所述的方法,进一步包含使用安装在连接梁上的托顶系统拉动连接梁并将所述连接梁卸到多个运输装置上的步骤。18. The method of claim 16, further comprising the step of pulling the connecting beam and unloading the connecting beam onto a plurality of transport devices using a jacking system mounted on the connecting beam.
19.在船坞里建造半潜式钻探设备的方法,包含以下步骤:19. A method for constructing a semi-submersible drilling rig in a shipyard, comprising the following steps:
在陆地上设置滑动桁架和多个支撑塔;Setting sliding trusses and multiple support towers on land;
在滑动桁架和支撑塔上建造半潜式钻探设备的上部壳体;Construction of the upper hull of the semi-submersible drilling rig on sliding trusses and support towers;
在干船坞中设置邻近于滑动桁架的支撑桁架;provision of support trusses adjacent to the sliding trusses in the dry dock;
建造上部壳体的同时,在干船坞中建造半潜式钻探设备的下部壳体;Simultaneously with the construction of the upper hull, the lower hull of the semi-submersible drilling rig is constructed in dry dock;
在滑动桁架下紧固托顶系统;Fasten the jacking system under the sliding truss;
设置多个紧固在支撑桁架和滑动桁架下部之间的滑动梁;providing a plurality of sliding beams fastened between the support truss and the lower part of the sliding truss;
托顶上部壳体并沿着滑动梁将建造好的上部壳体移送到建造好的下部壳体上方的位置;Lift the upper shell and move the built upper shell along the sliding beam to a position above the built lower shell;
让下部壳体在干船坞中浮动;floating the lower hull in dry dock;
调整下部壳体的压舱物以使下部壳体与上部壳体对准;Adjust the ballast of the lower hull to align the lower hull with the upper hull;
将上部壳体接合到下部壳体上,从而在干船坞中装配半潜式钻探设备;Joining the upper hull to the lower hull to assemble the semi-submersible drilling rig in dry dock;
从滑动桁架和支撑桁架移除半潜式钻探设备。Removal of the semi-submersible rig from the slide truss and support truss.
20.如权利要求19所述的方法,其中所述的滑动梁具有远端,所述远端可拆卸地连接到用于在上部壳体移送的过程中抵抗滑动梁上升的平衡装置。20. The method of claim 19, wherein the sliding beam has a distal end removably connected to a counterweight for resisting rising of the sliding beam during transfer of the upper housing.
21.如权利要求20所述的方法,进一步包含在干船坞底板上安装支撑桁架的步骤。21. The method of claim 20, further comprising the step of installing support trusses on the dry dock floor.
22.如权利要求21所述的方法,其中所述的支撑桁架包含具有外凸连接构件的下部和具有相应内凹连接构件的上部,其中所述的在干船坞底板上安装支撑桁架的步骤包含配对结合支撑桁架上部和下部的步骤。22. The method of claim 21, wherein said support trusses comprise a lower portion having male connecting members and an upper portion having corresponding female connecting members, wherein said step of installing the supporting trusses on the dry dock floor comprises Pair the steps that join the upper and lower sections of the support truss.
23.如权利要求20所述的方法,进一步包含至少在上部壳体和滑动桁架之间安装提高摩擦力的楔形构件的步骤,所述楔形构件在上部壳体和滑动梁之间不进行焊接的情况下,抑制上部壳体的横向移动。23. The method of claim 20, further comprising the step of installing a friction-enhancing wedge member between at least the upper shell and the sliding truss, said wedge member being non-welded between the upper shell and the sliding beam case, restrain the lateral movement of the upper housing.
24.如权利要求19所述的方法,其中所述的从滑动桁架和支撑桁架上移除半潜式钻探设备的步骤包含回收滑动桁架和滑动梁的步骤。24. The method of claim 19, wherein the step of removing the semi-submersible drilling rig from the sliding truss and the support truss includes the step of recovering the sliding truss and the sliding beam.
25.如权利要求24所述的方法,进一步包含使用安装在滑动桁架上的托顶系统拉滑动桁架的步骤。25. The method of claim 24, further comprising the step of pulling the sliding truss using a jacking system mounted on the sliding truss.
26.如权利要求24所述的方法,进一步包含使用安装在滑动梁上的托顶系统拉滑动梁并将滑动梁卸到多个驳船上的步骤。26. The method of claim 24, further comprising the step of pulling the sliding beam and unloading the sliding beam onto a plurality of barges using a jacking system mounted on the sliding beam.
Claims (26)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SG2003060860 | 2003-10-17 | ||
SG200306086-0A SG135929A1 (en) | 2003-10-17 | 2003-10-17 | A method of constructing a semi-submersible vessel using dry dock mating |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1867483A true CN1867483A (en) | 2006-11-22 |
CN100515858C CN100515858C (en) | 2009-07-22 |
Family
ID=34432638
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2004800303901A Expired - Lifetime CN100515858C (en) | 2003-10-17 | 2004-10-15 | A method of constructing a semi-submersible vehicle using a dry-dock mating connection |
Country Status (7)
Country | Link |
---|---|
KR (1) | KR101153607B1 (en) |
CN (1) | CN100515858C (en) |
MY (1) | MY138006A (en) |
NO (1) | NO339281B1 (en) |
SG (1) | SG135929A1 (en) |
TW (1) | TWI342852B (en) |
WO (1) | WO2005035354A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI380932B (en) * | 2006-09-25 | 2013-01-01 | Jurong Shipyard Pte Ltd | A method of contemporaneously constructing more than one semi-submersible rig using transverse skidding |
WO2018214334A1 (en) * | 2017-05-25 | 2018-11-29 | 广船国际有限公司 | Method for over-water hoisting and positioning semi-submersible ship ballast tank |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102044969B1 (en) * | 2013-05-21 | 2019-11-14 | 대우조선해양 주식회사 | Move jig and move method for fpb |
GB2538275B (en) | 2015-05-13 | 2018-01-31 | Crondall Energy Consultants Ltd | Floating production unit and method of installing a floating production unit |
CN105151236B (en) * | 2015-09-28 | 2017-07-21 | 大连理工大学 | Floating pier and tower snorkeling movement carrying platform device and its method of work |
CN108454798B (en) * | 2017-09-11 | 2022-04-26 | 青岛武船麦克德莫特海洋工程有限公司 | Integrated construction and installation method of upper process module of floating production facility |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1527759A (en) * | 1975-12-11 | 1978-10-11 | Mitsui Shipbuilding Eng | Semi-submersible structures and method of manufacture thereof |
IL66064A (en) * | 1981-06-22 | 1985-08-30 | Adragem Ltd | Semi-submersible marine platform |
JPS58207413A (en) * | 1982-05-26 | 1983-12-02 | Mitsui Eng & Shipbuild Co Ltd | Construction of semisub type platform |
US5237949A (en) * | 1992-05-29 | 1993-08-24 | Shell Offshore Inc. | Floating platform shallow draft hull/deck mating |
GB2330854B (en) * | 1997-10-31 | 2002-04-17 | Ove Arup Partnership | Method of transporting and installing an offshore structure |
-
2003
- 2003-10-17 SG SG200306086-0A patent/SG135929A1/en unknown
-
2004
- 2004-10-15 CN CNB2004800303901A patent/CN100515858C/en not_active Expired - Lifetime
- 2004-10-15 WO PCT/SG2004/000337 patent/WO2005035354A1/en active Application Filing
- 2004-10-15 MY MYPI20044266A patent/MY138006A/en unknown
- 2004-10-15 KR KR1020067009437A patent/KR101153607B1/en active IP Right Grant
- 2004-10-15 TW TW093131386A patent/TWI342852B/en not_active IP Right Cessation
-
2006
- 2006-05-12 NO NO20062140A patent/NO339281B1/en unknown
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI380932B (en) * | 2006-09-25 | 2013-01-01 | Jurong Shipyard Pte Ltd | A method of contemporaneously constructing more than one semi-submersible rig using transverse skidding |
WO2018214334A1 (en) * | 2017-05-25 | 2018-11-29 | 广船国际有限公司 | Method for over-water hoisting and positioning semi-submersible ship ballast tank |
Also Published As
Publication number | Publication date |
---|---|
KR20060098385A (en) | 2006-09-18 |
SG135929A1 (en) | 2007-10-29 |
MY138006A (en) | 2009-04-30 |
WO2005035354A1 (en) | 2005-04-21 |
TW200521024A (en) | 2005-07-01 |
NO339281B1 (en) | 2016-11-21 |
WO2005035354B1 (en) | 2005-06-02 |
CN100515858C (en) | 2009-07-22 |
KR101153607B1 (en) | 2012-06-11 |
NO20062140L (en) | 2006-05-12 |
TWI342852B (en) | 2011-06-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA3011226C (en) | A seabed supported unit and method to provide a shallow water drilling terminal | |
EP1189804B1 (en) | Device for positioning and lifting a marine structure, particularly a platform deck | |
US4648751A (en) | Method and apparatus for erecting offshore platforms | |
EP1189803B1 (en) | Lifting vessel and method for positioning, lifting and handling a platform deck and a jacket | |
KR20100087094A (en) | Method for installing a drilling apparatus on a rig and for preparing drilling operations | |
US6736571B2 (en) | Removal of decks from offshore structures | |
US8534213B2 (en) | Skid shoe assembly for loading and transporting large structures | |
AU2010216206B2 (en) | Skid beam assembly for loading and transporting large structures | |
NO339281B1 (en) | Method of constructing a semi-submersible rig | |
US20060204340A1 (en) | Floating construction, a platform construction, a method for placing a floating platform construction at sea, and a method for removing a platform construction at sea | |
WO2002004287A1 (en) | Installation and removal of decks on and from offshore structures | |
AU2080000A (en) | Offshore deck installation | |
AU2010216203B2 (en) | Skid shoe assembly for loading and transporting large structures | |
JPH1096212A (en) | Method for removing bridge | |
KR20240013167A (en) | Floating fabrication device and method of constructing a floating structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20090722 |