[go: up one dir, main page]

CN1676869A - Oil-extracting well water injection method - Google Patents

Oil-extracting well water injection method Download PDF

Info

Publication number
CN1676869A
CN1676869A CN 200510043344 CN200510043344A CN1676869A CN 1676869 A CN1676869 A CN 1676869A CN 200510043344 CN200510043344 CN 200510043344 CN 200510043344 A CN200510043344 A CN 200510043344A CN 1676869 A CN1676869 A CN 1676869A
Authority
CN
China
Prior art keywords
well
water
oil
power unit
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200510043344
Other languages
Chinese (zh)
Inventor
张京三
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200510043344 priority Critical patent/CN1676869A/en
Publication of CN1676869A publication Critical patent/CN1676869A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

This invention relates to a kind of extraction method of pouring water into oil well. This invention technical plan is: installs the single tube column in the well chamber, uses in this well the stratum water upside water level, is airtight turbo-charged pours into in this well the lower part oil layer; The power unit locates upside under the water level filter and pouring layer between the above packer, underneath the power unit's pipeline connection sensor, the sensor the mine shaft pressure, the current capacity signal passes on through the far biography holding wire to the ground in on the control mechanism carries on the control, the adjustment, the demonstration. This invention adapts the common water well, which uses single tube in the flow, uses upside this well by the power unit the formation water, and is airtight turbo-charged after pours into to this well lower part oil layer, and realizes not leaving ground this well and picks the inkstone well water the goal, also it pours water the parameter definitely and may carry on the monitor and the regulation to the ground. The technical process is simple, the performance is advanced, throws transports the cost is inexpensive, but large scale enhances the small sub-area oil-field development the economic efficiency, moreover suitable to oil field common water well water-injection development.

Description

Oil-extracting well water injection method
One, technical field: the present invention relates to a kind of oil-extracting well water injection new method.
Two, background technology: for small-block oilfield and outlying wellblock, water flooding regime puts into operation routinely, needs to dig a well, builds a station and lay the line etc., certainly will cause cost of crude oil production too high, low in economic efficiency, even directly influence the whole evaluation of exploiting meaning in such block oil field.
Three, summary of the invention: the purpose of this invention is to provide a kind of oil-extracting well water injection new method, its technological process is simple, and is advanced in performance, and it is with low cost to put into operation, the economic benefit of small-block oilfield exploitation can be increased substantially, and the waterflooding extraction of oil field conventional oil well can be suitable for.
Technical scheme of the present invention is: single time tubing string is installed in pit shaft, is taked the water of the top water layer on stratum in this well, the bottom oil reservoir in this well is injected in airtight supercharging; The power unit is between the strainer and the packer on the implanted layer under the water layer of top, pipeline below the power unit connects sensor, and sensor reaches down-hole pressure, flow signal on the ground controlling organization by the remote transfer signal line and controls, regulates, shows.
The present invention adapts to the conventional oil well, adopts single tube time flow process, take this formation water of aboveground by the power unit, be injected into the bottom oil reservoir of this well after the airtight supercharging, can not realize that ground Ben Jing adopts the purpose of water water filling, and its water injection parameter can monitor in ground and regulate and control fully.Technological process is simple, and is advanced in performance, and it is with low cost to put into operation, and can increase substantially the economic benefit of small-block oilfield exploitation, and can be suitable for the waterflooding extraction of oil field conventional oil well.
Four, the specific embodiment: take the method for perforation to penetrate to drive a well in the tube corresponding top to adopt water layer and bottom oil reservoir, the water filling layer is tail pipe, packer, pressure flow sensor, electric pump unit, is in turn connected into single tube from top to bottom and injects well and hang on the simple wellhead by the socket tubing string.Servicing unit mainly comprises pressure flow display instrument, junction box, frequency converter, electric control box etc.The electric pump unit adopt on top under the water layer between the packer on sand fine filter and the water filling layer, its top is provided with cartridge, every servicing units such as sand fine filters, respectively will be from after the water desanding of this aboveground water layer, filtering, suck by the electric pump unit again, after its airtight pressurization, inject the oil reservoir of this down-hole portion.The electric pump unit is designed to inversion type.The pressure flow sensor is equipped with in electric pump unit exit, its pressure flow signal is reached on the ground pressure flow Displaying Meter by the remote transfer signal line, water injection pressure and water injection rate in order to monitoring downhole electric pump unit, and regulate near it frequency converter in view of the above, just can accurately set up water injection rate, not only satisfy the water injection technology requirement but also reached purpose of saving by the injection allocation requirement.Described sensor can be fixed on the pipeline between power unit and the packer.

Claims (1)

1, a kind of oil-extracting well water injection method is characterized in that: single time tubing string is installed in pit shaft, is taked the water of the top water layer on stratum in this well, the bottom oil reservoir in this well is injected in airtight supercharging; The power unit is between the strainer and the packer on the implanted layer under the water layer of top, pipeline below the power unit connects sensor, and sensor reaches down-hole pressure, flow signal on the ground controlling organization by the remote transfer signal line and controls, regulates, shows.
CN 200510043344 2005-04-16 2005-04-16 Oil-extracting well water injection method Pending CN1676869A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200510043344 CN1676869A (en) 2005-04-16 2005-04-16 Oil-extracting well water injection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200510043344 CN1676869A (en) 2005-04-16 2005-04-16 Oil-extracting well water injection method

Publications (1)

Publication Number Publication Date
CN1676869A true CN1676869A (en) 2005-10-05

Family

ID=35049579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200510043344 Pending CN1676869A (en) 2005-04-16 2005-04-16 Oil-extracting well water injection method

Country Status (1)

Country Link
CN (1) CN1676869A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108431367A (en) * 2015-12-21 2018-08-21 苏伊士集团 Method and system for monitoring well or drilling performance

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108431367A (en) * 2015-12-21 2018-08-21 苏伊士集团 Method and system for monitoring well or drilling performance

Similar Documents

Publication Publication Date Title
CN102493788B (en) Drainage gas recovery method for high-coal-rank coal bed gas well
US9500067B2 (en) System and method of improved fluid production from gaseous wells
CN101463718B (en) Same-well production and injection process pipe column of low-permeability horizontal well
CN101446281B (en) Drainage device for coal bed gas well electric submersible centrifugal pump
CN102953711A (en) Device and method for horizontal gas well to drain liquid and produce gas
WO2015000446A1 (en) Method and device for extracting coalbed methane by discharging water and coal fines
CN208702393U (en) With well intelligence injection-production technical tubing string
RU2334867C1 (en) Method of simultaneous-separate operation of several payout beds and installation of well for implementation of this method
CN104533356A (en) Two-layer self-control layered oil production method and layered oil production method
CN109252853A (en) Underground oil-water separation same-well injection-production system and method
CN201874543U (en) Underground boosting water injection process pipe string
CN103470233B (en) Heavy oil reservoir natural gas huff-puff oil production process system and oil production method
CN108868729A (en) A kind of pressure break process method for well completion
CN2937552Y (en) Automatic batch-type pumping device
CN201013344Y (en) Supporting equipment for bottom water oil reservoir potential balance mining
RU109792U1 (en) EQUIPMENT FOR SIMULTANEOUS-SEPARATE OIL PRODUCTION FROM TWO LAYERS
CN202132029U (en) Layer mining and testing system for petroleum
CN203412552U (en) Water and pulverized coal discharging coal-bed methane mining device
CN206419004U (en) A kind of electric pump couples lifting tubing string with gaslift
CN208294499U (en) A kind of normal pressure shale gas water drainage gas production device
CN1676869A (en) Oil-extracting well water injection method
RU2296213C2 (en) Packer pumping plant for well formations operation
CN202348240U (en) Gravel filling water control and sand prevention integrated device
CN1448614A (en) Oil extracting process and apparatus using oil field original well water
CN2538960Y (en) Oil field local well water injecting equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication