[go: up one dir, main page]

CN119352510A - Piling method and piling device for seabed buried piles - Google Patents

Piling method and piling device for seabed buried piles Download PDF

Info

Publication number
CN119352510A
CN119352510A CN202310908110.7A CN202310908110A CN119352510A CN 119352510 A CN119352510 A CN 119352510A CN 202310908110 A CN202310908110 A CN 202310908110A CN 119352510 A CN119352510 A CN 119352510A
Authority
CN
China
Prior art keywords
pile
main
driver
driving
piling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310908110.7A
Other languages
Chinese (zh)
Inventor
朱言顺
于静远
张晨
汪灿
甄宏昌
范国伟
段国伟
王守超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION CO LTD
China National Petroleum Corp
China Petroleum Pipeline Engineering Corp
Original Assignee
TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION CO LTD
China National Petroleum Corp
China Petroleum Pipeline Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION CO LTD, China National Petroleum Corp, China Petroleum Pipeline Engineering Corp filed Critical TIANJIN DAGANG OILFIELD GROUP ENGINEERING CONSTRUCTION CO LTD
Priority to CN202310908110.7A priority Critical patent/CN119352510A/en
Publication of CN119352510A publication Critical patent/CN119352510A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本公开的实施例提供一种海底埋入式桩的打桩方法及打桩装置,所述打桩方法包括将接桩器固定于送桩器;对主桩进行移动、翻桩,以及将主桩挂设于浮吊船舷侧的扶桩架;对固定后的接桩器和送桩器进行移动、翻桩,以及将送桩器和接桩器固定连接至主桩并进行沉桩作业,沉桩完成后将振动锤固定于送桩器;启动振动锤,通过调整振动锤的打桩频率以及吊装落钩速度,将主桩打入至海底预设深度位置;最后将振动锤、固定连接的接桩器和送桩器回收至浮吊船。本公开的实施例的打桩方法,可实现使用振动锤进行埋入式桩的打桩作业,显著提升了打桩效率,有效避免了溜桩的发生及在特殊情况下可以进行拔桩作业。

The embodiment of the present disclosure provides a pile driving method and a pile driving device for a subsea buried pile, the pile driving method comprising fixing a pile connector to a pile driver; moving and turning the main pile, and hanging the main pile on a pile support frame on the side of a floating crane; moving and turning the fixed pile connector and pile driver, and fixing the pile driver and the pile connector to the main pile and performing a pile sinking operation, after the pile sinking is completed, fixing a vibrating hammer to the pile driver; starting the vibrating hammer, and driving the main pile to a preset depth position on the seabed by adjusting the pile driving frequency of the vibrating hammer and the lifting hook speed; finally, recovering the vibrating hammer, the fixedly connected pile connector and the pile driver to the floating crane. The pile driving method of the embodiment of the present disclosure can realize the pile driving operation of the buried pile using a vibrating hammer, significantly improves the pile driving efficiency, effectively avoids the occurrence of pile slippage, and can perform pile pulling operations under special circumstances.

Description

Piling method and piling device for submarine embedded pile
Technical Field
The embodiment of the disclosure belongs to the technical field of ocean engineering, and particularly relates to a piling method and a piling device for a submarine buried pile.
Background
CALM (catenary anchor leg mooring, catenary buoy mooring system) single point mooring systems or other offshore floating structures are usually moored by anchor piles. To increase mooring forces and reduce the impact on the seabed surface, the anchor piles are of a buried pile structure. The prior technical proposal at home and abroad is to adopt a hydraulic impact hammer for piling, and to arrange a large-scale underwater pile supporting frame on the seabed for piling positioning and verticality guarantee. When piling, firstly, the underwater pile supporting frame is lifted to a piling position, the pile supporting frame is fixed after the position accuracy is determined, then, the pile inserting operation of the anchor pile is conducted under the water command by a diver, then, the pile feeder with the variable diameter is inserted into the upper end part of the anchor pile, and finally, the anchor pile is driven into the seabed by utilizing the hydraulic impact hammer. The hydraulic impact hammer is adopted for piling, so that pile slipping cannot be effectively prevented, the operation period is long and the verticality cannot be effectively monitored when the hydraulic impact hammer encounters a sea area with high ocean current velocity or turbid water quality.
The hydraulic vibration hammer has the advantages of high piling efficiency, capability of preventing pile slipping and pile pulling when needed, but the common pile driver is inserted into the anchor pile by adopting a reducing structure, has a certain gap with the inner wall of the anchor pile and cannot transmit vibration load. In the industry, no hydraulic vibratory hammer is currently used for driving a buried pile.
Disclosure of Invention
Embodiments of the present disclosure aim to solve at least one of the technical problems existing in the prior art, and provide a piling method and a piling device for a submarine buried pile.
In one aspect, embodiments of the present disclosure provide a method of driving a subsea buried pile, the method comprising:
fixing the first end of the pile driver along the length direction of the pile driver on the first end of the pile driver along the length direction of the pile driver;
The pile follower and the pile follower after being fixed are hoisted and translated to a second preset position and turned, the second end of the pile follower after being turned along the length direction is inserted into the first end of the main pile, the first end face of the pile follower is abutted with the first end face of the main pile, and the pile follower is maintained in a hoisting state;
the pile driver and the main pile are connected into a whole through the pile extension device;
Opening a limit structure of the pile supporting frame, and moving the pile driver by hoisting so that the main pile can be driven under the gravity action of the pile driver, the pile extension device and the main pile;
After pile sinking is completed, releasing the hoisting state of the pile driver, and fixing a vibrating hammer at the second end of the pile driver along the length direction;
Starting the vibrating hammer, and driving the main pile to a preset depth position on the sea floor by adjusting the piling frequency and the hoisting hook falling speed of the vibrating hammer;
And recycling the vibrating hammer, the pile extension device and the pile delivery device which are fixedly connected to the floating crane ship.
Optionally, the pile extension device comprises a pile extension device main body, a movable guide, a fixed guide and a driving unit for driving the movable guide to move, wherein a plurality of pairs of guide grooves with inclined bottoms are formed in the fixed guide and the movable guide, each pair of guide grooves is embedded with a tensioning plate, the tensioning plates are in sliding fit with the bottom of the guide grooves, and the tensioning plates are provided with ejector blocks;
the pile driver and the main pile are connected into a whole through the pile extension device, and the pile extension device comprises:
The driving unit drives the movable guide to move towards the direction close to the fixed guide, the tensioning plate is extruded to move outwards in the guide groove by the bottoms of the guide grooves with inclined sides, and the ejector block is ejected outwards to the inner wall of the main pile so as to connect the pile feeder with the main pile into a whole.
Optionally, the recovering the vibratory hammer, the pile extension device and the pile delivery device which are fixedly connected to the floating crane vessel includes:
the driving unit drives the movable guide to move in a direction away from the fixed guide, the tensioning plate moves inwards in the guide groove, and the jacking block contracts inwards in the radial direction of the pile extension device main body to be separated from the inner wall of the main pile;
and hoisting and recycling the vibrating hammer, the pile extension device and the pile delivery device which are fixedly connected to the floating crane ship.
Optionally, the pile extension device is a hydraulic pile extension device.
Optionally, the limit structure of the pile supporting frame comprises a frame body provided with a through channel and a supporting component connected with the frame body, wherein a plurality of lug plates are distributed on the outer surface of the first end of the main pile along the circumferential direction of the first end of the main pile;
The support assembly comprises a plurality of support pieces and a plurality of telescopic mechanisms corresponding to the support pieces, and the telescopic mechanisms drive the support pieces to reciprocate between a first position for supporting the ear plate and a second position far away from the ear plate.
Optionally, the hoisting and translating the main pile to the first predetermined position and turning the pile includes:
And hoisting and translating the main pile to a first preset position, connecting an anchor chain and overturning the main pile.
Optionally, central axes of the pile supporting frame, the pile extension device and the pile delivery device which are fixedly connected are coincident and perpendicular to the seabed plane.
Optionally, before the hoisting and translating the main pile to the first predetermined position and turning the pile, the piling method further includes:
and fixing the pile supporting frame on the side of the floating crane ship for hanging the main pile.
In another aspect, embodiments of the present disclosure provide a piling device for a subsea buried pile, the piling device comprising a pile follower, and a vibratory hammer, the piling device employing the piling method described above.
According to the piling method and the piling device for the submarine embedded pile, the underwater pile supporting frame can be avoided, embedded pile driving can be achieved through the vibrating hammer, the piling efficiency is remarkably improved, the occurrence of a sliding pile is effectively avoided, and pile pulling operation can be conducted under special conditions.
Drawings
FIG. 1 is a schematic block flow diagram of a method of driving a subsea buried pile according to an embodiment of the present disclosure;
FIG. 2 is a top view of a pile guide according to another embodiment of the present disclosure;
FIG. 3 is an enlarged schematic view of a limit structure of a main pile hanging on a pile frame according to another embodiment of the present disclosure;
FIG. 4 is a schematic view of a pile driver according to another embodiment of the present disclosure;
FIG. 5 is a schematic illustration of the mating of a vibratory hammer, pile driver, pile extension and main pile according to another embodiment of the present disclosure;
FIG. 6 is a schematic diagram illustrating an operation of turning a main pile according to another embodiment of the present disclosure;
FIG. 7 is a schematic illustration of an operation of hoisting a fixed pile driver and pile follower according to another embodiment of the present disclosure;
FIG. 8 is a schematic diagram of the cooperation of a pile driver, pile extension and main pile after hoisting according to another embodiment of the present disclosure;
FIG. 9 is a schematic diagram of a lifted vibratory hammer with pile driver, pile extension, and main pile in accordance with another embodiment of the present disclosure;
Fig. 10 is a schematic view of a pile-driving structure according to another embodiment of the present disclosure.
Detailed Description
In order that those skilled in the art will better understand the technical solutions of the present disclosure, the present disclosure will be described in further detail with reference to the accompanying drawings and detailed description.
As shown in FIG. 1, the piling method of the submarine buried pile comprises the following steps of S1, fixing a pile support frame on the side of a floating crane ship for hanging a main pile.
Specifically, referring to fig. 2 and 3 together, first, a pile guide 100 is fixed to the side of a floating vessel 200, and the pile guide fixed to the side of the floating vessel 200 is used for hanging a main pile 300. When the main pile 300 is hung on the pile supporting frame 100, the pile supporting frame 100 can provide fixing and guiding functions for the main pile 300, so that the subsequent pile driving operation is convenient.
It should be noted that, the pile supporting frame 100 includes a limiting structure, the limiting structure includes a frame body 110 provided with a through channel and a supporting component 120 connected to the frame body 110, and a plurality of lugs 310 are distributed on the outer surface of the first end of the main pile 300 along the circumferential direction thereof. The through channel of the frame 110 is used for penetrating the main pile 300, and the support assembly 120 is used for supporting the corresponding ear plate 310. The support assembly 120 includes a plurality of supports and a plurality of telescoping mechanisms (not shown) corresponding to the plurality of supports that drive the supports to reciprocate between a first position supporting the ear plate 310 and a second position away from the ear plate 310.
As a specific example, as shown in fig. 3, two lugs 310 are symmetrically disposed at the top end of the main pile 300 along the circumferential direction, and corresponding supporting members are respectively disposed on the frame 110 at both sides of the through channel. When the pile support 100 is required to carry out limit support on the main pile 300, the telescopic mechanism drives the supporting piece to the first position, and the supporting piece can be supported on the lug plate 310, so that the main pile 300 is erected on the pile support 100. When the pile rest 100 completes the limit support task for the main pile 300, the telescopic mechanism drives the support member to the second position, the support member is away from the lug plate 310, and the main pile 300 is no longer supported on the pile rest 100. As a specific example, the telescopic mechanism may be provided as a hydraulic jack.
S2, fixing the first end of the pile driver along the length direction of the pile driver to the first end of the pile driver along the length direction of the pile driver.
Specifically, referring to fig. 4 and 5 together, pile driver 400 and pile driver 500 are fixedly connected. As shown in fig. 4, the pile extension device 400 includes a pile extension device main body 410, a movable guide (not shown in the figure), a fixed guide (not shown in the figure), and a driving unit 420 for driving the movable guide to move, wherein a plurality of pairs of guide grooves with inclined bottoms are formed on the fixed guide and the movable guide, each pair of guide grooves is embedded with a tensioning plate 430, the tensioning plates 430 are slidably matched with the bottom of the guide grooves, and the tensioning plates 430 are provided with top blocks 431. As shown in fig. 5, the top of the pile driver 400 is connected to the bottom of the pile driver 500, it will be understood that the driving unit 420 at the top of the pile driver 400 is inserted into the bottom of the pile driver 500, and the pile driver 400 is connected to the pile driver 500 by means of the clamping heads 440 provided at the first ends along the length thereof. The collet 440 and the pile driver 500 may be connected by bolts, in particular.
S3, hoisting and translating the main pile to a first preset position, turning the pile, and hanging the turned main pile on a pile support frame on the side of the floating crane along the first end of the length direction of the main pile. And hoisting and translating the fixed pile extension device and the pile delivery device to a second preset position and turning the pile, inserting the second end of the pile extension device after turning the pile into the first end of the main pile along the length direction of the pile extension device, abutting the first end face of the pile delivery device with the first end face of the main pile, and maintaining the pile delivery device in a hoisting state.
Specifically, referring to fig. 3 and 6 together, the main pile 300 is lifted and translated to a first predetermined position by using a lifting device, and then pile turning operation is performed on the main pile 300. That is, the pile-turned main pile 300 is hung on the pile holder 100 on the side of the floating vessel 200 by a hoisting device. It should be noted that, after the main pile 300 is hoisted and translated to the first preset position, the main pile 300 and the floating vessel 200 can be connected together through the anchor chain 210, so as to perform a certain degree of fixed connection on the main pile 300, and then the main pile 300 is turned over again to perform pile turning operation, so that the later stage of launching by a diver and connecting the anchor chain under water is avoided.
As shown in fig. 5 to 8, after the hanging of the main pile 300 is completed, the hoisting operation of the pile follower 400 and the pile driver 500, which have been fixedly connected, is continued by using the hoisting device. The fixed pile extension 400 and pile driver 500 are hoisted and translated to a second preset position, and then pile turning operation is carried out on the pile extension 400 and the pile driver 500. After pile turning, the bottom of the fixed pile follower 400 is inserted into the top of the main pile 300, and the bottom end face of the fixed pile follower 500 abuts against the top end face of the main pile 300, so that no gap exists between the bottom end face of the pile follower 500 and the top end face of the main pile 300. As shown in fig. 6 and 7, the lifting hook 220 is a part of a lifting device, and the main pile 300, the pile follower 400 and the pile driver 500 which are fixedly connected are all lifted and moved by the lifting hook 220 of the lifting device.
And S4, connecting the pile driver and the main pile into a whole through the pile extension device.
Specifically, referring to fig. 4, 5 and 8 together, after the pile driver 500, the pile extension 400 and the main pile 300 are lifted, the pile extension 400 is started, and the pile driver 500 and the main pile 300 are integrally connected by the pile extension 400. The driving unit 420 in the pile extension 400 drives the movable guide to move in a direction approaching to the fixed guide, the tensioning plate 430 is pressed by the bottoms of the guide grooves with two inclined sides to move outwards in the guide grooves, and the ejector blocks 431 are ejected outwards to the inner wall of the main pile 300 to connect the pile extension 500 and the main pile 300 into a whole. It will be appreciated that when the top blocks 431 are ejected outwardly against the inner wall of the main pile 300, the radial force provided by the top blocks 431 to the main pile 300 is converted into an axial force fixedly connecting the main pile 300 and the pile follower 500. Connecting the main pile 300 and the pile driver 500 together can improve the force transmission effect during subsequent pile driving and can also effectively prevent the pile slipping. As an example, the pile driver 400 may be specifically configured as a hydraulic pile driver, and the top block 431 is moved by the driving of the hydraulic driving unit 420.
S5, opening a limit structure of the pile supporting frame, and moving the pile driver through hoisting so that the main pile can be driven under the gravity action of the pile driver, the pile extension device and the main pile.
Specifically, referring to fig. 3 to 5, 8 and 9 together, the pile driver 500 is maintained in a lifted state all the time, and after the pile driver 500 is integrally connected with the main pile 300, the limit structure of the pile supporting frame 100 is opened, and the pile driver 500, the pile extension 400 and the main pile 300 are integrally lowered by the lifting device to perform pile sinking operation. The main pile 300 can be partially submerged under the seabed mud surface by virtue of the self weights of the pile driver 500, the pile extension 400 and the main pile 300. In this process, whether the perpendicularity of the main pile 300 meets the design requirement when the pile sinking operation is obtained is measured by an angle measuring device arranged on the main pile 300, if not, pile pulling is performed again, and if yes, a vibrating hammer is placed on a pile feeder after the pile sinking operation is completed. As a specific example, the angle measuring device may be provided as a level bar, and of course, the angle measuring device may be provided as a device other than a level bar, which is not particularly limited in this embodiment.
As shown in fig. 8, the central axis of the pile supporting frame 100 is perpendicular to the seabed plane, and the central axis of the pile supporting frame 100 coincides with the central axes of the pile driver 500, the pile follower 400, and the main pile 300 after hoisting. So that the perpendicularity of the main pile 300 can be ensured in the subsequent piling process, and the main pile 300 can be driven into the seabed mud perpendicular to the seabed plane.
And S6, after pile sinking is completed, releasing the hoisting state of the pile driver, and fixing the vibrating hammer at the second end of the pile driver along the length direction of the pile driver.
Specifically, referring to fig. 5 and 9 together, the vibration hammer 600 after the hoisting is completed is positioned at the top end of the pile driver 500, the pile driver 500 is positioned at the top end of the pile extension 400, and the pile extension 400 is positioned at the top end of the main pile 300. At this time, the hoisting equipment does not have force, and the main pile 300 can continue to sink under the seabed mud surface by means of the self weights of the vibrating hammer 600, the pile driver 500, the pile extension 400 and the main pile 300 so as to perform pile sinking operation again. After the pile sinking operation is completed, whether the perpendicularity of the main pile 300 meets the design requirement after the pile sinking operation is completed is measured by an angle measuring device arranged on the main pile 300, if not, pile pulling is performed again, and if yes, vibration pile driving is performed by using a vibration hammer 600 after the pile sinking operation is completed.
The oscillating weight 600 is designed using resonance theory. When the forced vibration frequency of the main pile is consistent with the vibration frequency of the soil particles, the soil particles resonate. At this time, the soil particles have large amplitude, and enough vibration speed and acceleration can quickly destroy the adhesive force between the main pile and the soil, so that the pile body and the soil are transited from a compacting state to an instant separating state, pile sinking resistance, particularly the side resistance of the pile sinking resistance is quickly reduced, and the pile is sunk under the action of dead weight. Because the vibrating hammer achieves the aim of pile sinking by reducing the friction force between the pile and the soil, the pile can be pulled up by using a force slightly larger than the pile and the pile body under the condition that the friction force between the pile and the soil is reduced. Therefore, the vibratory hammer is suitable for pile sinking and pile pulling. Pile sinking and pile pulling efficiency are high.
S7, starting the vibrating hammer, and driving the main pile to a preset depth position of the seabed by adjusting the piling frequency and the hoisting hook falling speed of the vibrating hammer.
Specifically, referring to fig. 5, 9 and 10 together, after the pile sinking operation is completed, the vibratory hammer 600 is started, the vibratory hammer 600 performs a vibratory hammering on the pile driver 500, and the pile driver 500 transmits the force of the vibratory hammering to the main pile 300 through the pile extension 400, so that the main pile 300 can be maintained to be perpendicular to the seabed plane and move downward. During this time, the lifting hook 220 of the lifting device is adjusted to descend at the same speed as the main pile 300, so as to ensure that the vibratory hammer 600 can always transmit acting force to the main pile 300 to drive the main pile 300 to move downwards. The main pile 300 is forced to vibrate at a frequency consistent with that of the seabed soil particles by the vibratory hammer 600, and the main pile can be continuously lowered below the seabed soil surface. The specific descending depth of the main pile 300 can be controlled according to actual needs in a specific operation process, so that the main pile 300 can be driven to a preset depth position on the sea floor. As a specific example, the specific pile depth may be determined by the real-time water depth, sea wave height, and the position of the scale on the pile driver 500 at the sea surface. The embodiment of the present disclosure may set the pile driving depth to a preset depth position below the seabed mud surface by completely driving the main pile, and of course, if there are other design requirements on the pile driving depth in actual engineering, for example, a part of the main pile is exposed out of the seabed mud surface, the pile driving depth may be designed according to the design requirements, which is not limited in this embodiment.
If the main pile cannot be driven to the preset depth position of the seabed by using the vibrating hammer, the impact hammer may be replaced to continue driving until the main pile is driven to the preset depth position of the seabed. In the process of piling by using the impact hammer, whether the perpendicularity of the main pile 300 meets the design requirement is measured by an angle measuring device arranged on the main pile 300, if not, pile pulling is performed again, and if yes, pile piling is performed continuously, so that the perpendicularity of the main pile 300 meets the design requirement during pile piling is ensured. It is further noted that, because the embodiment of the disclosure adopts the hoisting device to hoist the vibratory hammer to pile, the vibratory hammer can transmit the vibratory force perpendicular to the seabed plane to the main pile at any time, and thus the perpendicularity of the main pile relative to the seabed plane during pile driving can be ensured. And the vibration hammer is hoisted by using hoisting equipment to pile, so that the situation of pile sliding can be effectively prevented. And pile pulling operation can be timely and conveniently carried out when the perpendicularity of the main pile exceeds the design requirement by adopting the vibrating hammer for pile driving.
According to the piling method of the submarine buried pile, the main pile is hung on the pile supporting frame on the side of the floating crane ship by using the hoisting equipment, so that the central axis of the main pile is perpendicular to the seabed plane. Then through hoist and mount vibratory hammer, pile follower and pile extension ware for the main pile can be under guaranteeing its straightness requirement that hangs down and the not circumstances of swift current stake, realize piling the design requirement to going into mud completely with the main pile. The pile driving operation of the embedded pile by using the vibrating hammer is realized, the pile driving efficiency is obviously improved, the pile sliding is effectively avoided, the pile pulling operation can be performed under special conditions, the pile driving device has the advantages of simplicity in operation, no need of underwater observation, underwater operation and the like, the construction efficiency is improved, and the operation risk and the construction cost are reduced.
S8, recycling the vibrating hammer, the pile extension device and the pile delivery device which are fixedly connected to the floating crane ship.
Specifically, referring to fig. 10 together, when the main pile is driven to a predetermined depth position and the vibration hammer 600, the fixedly connected pile follower 400 and the pile follower 500 are required to be recovered, the vibration hammer 600 may be recovered to the floating vessel 200 by the hoisting device, the movable guide is driven to move away from the fixed guide by the driving unit 420 of the pile follower 400, the tension plate 430 moves inward in the guide groove, the top block 431 is retracted inward in the radial direction of the pile follower body 410 to be separated from the inner wall of the main pile 300, and at this time, the pile follower 500 and the main pile 300 are disconnected to be in an integrated state, and the pile follower 500 and the pile follower 400 are recovered to the floating vessel 200 by the hoisting device.
According to the piling method of the submarine buried pile, after piling is completed, the vibrating hammer, the pile extension device and the pile delivery device which are fixedly connected can be conveniently recovered.
In another aspect, embodiments of the present disclosure provide a piling device for a subsea buried pile, the piling device comprising a pile follower, and a vibratory hammer, the piling device employing the piling method described above. The pile driving device for the submarine embedded pile can realize the design requirement of driving the pile body to completely enter mud under the conditions of ensuring that the pile body cannot slide and ensuring the perpendicularity, realizes the driving operation of the embedded pile by using a vibrating hammer, remarkably improves the driving efficiency, effectively avoids the occurrence of slide pile and can perform pile pulling operation under special conditions, has the advantages of simple operation, no need of underwater observation, underwater operation and the like, improves the construction efficiency, and reduces the operation risk and the construction cost.
It is to be understood that the above embodiments are merely exemplary embodiments employed to illustrate the principles of the present disclosure, however, the present disclosure is not limited thereto. Various modifications and improvements may be made by those skilled in the art without departing from the spirit and substance of the disclosure, and are also considered to be within the scope of the disclosure.

Claims (9)

1. A method of driving a subsea buried pile, the method comprising:
fixing the first end of the pile driver along the length direction of the pile driver on the first end of the pile driver along the length direction of the pile driver;
The pile follower and the pile follower after being fixed are hoisted and translated to a second preset position and turned, the second end of the pile follower after being turned along the length direction is inserted into the first end of the main pile, the first end face of the pile follower is abutted with the first end face of the main pile, and the pile follower is maintained in a hoisting state;
the pile driver and the main pile are connected into a whole through the pile extension device;
Opening a limit structure of the pile supporting frame, and moving the pile driver by hoisting so that the main pile can be driven under the gravity action of the pile driver, the pile extension device and the main pile;
After pile sinking is completed, releasing the hoisting state of the pile driver, and fixing a vibrating hammer at the second end of the pile driver along the length direction;
Starting the vibrating hammer, and driving the main pile to a preset depth position on the sea floor by adjusting the piling frequency and the hoisting hook falling speed of the vibrating hammer;
And recycling the vibrating hammer, the pile extension device and the pile delivery device which are fixedly connected to the floating crane ship.
2. The piling method of the submarine buried pile according to claim 1, wherein the pile extension device comprises a pile extension device main body, a movable guide, a fixed guide and a driving unit for driving the movable guide to move, a plurality of pairs of guide grooves with inclined bottoms are formed on the fixed guide and the movable guide, a tensioning plate is embedded in each pair of guide grooves, the tensioning plate is in sliding fit with the bottom of the guide groove, and a top block is arranged on the tensioning plate;
the pile driver and the main pile are connected into a whole through the pile extension device, and the pile extension device comprises:
The driving unit drives the movable guide to move towards the direction close to the fixed guide, the tensioning plate is extruded to move outwards in the guide groove by the bottoms of the guide grooves with inclined sides, and the ejector block is ejected outwards to the inner wall of the main pile so as to connect the pile feeder with the main pile into a whole.
3. A method of driving a subsea buried pile according to claim 2, wherein said retrieving said vibratory hammer, fixedly connected pile receiver and pile follower to said floating vessel comprises:
the driving unit drives the movable guide to move in a direction away from the fixed guide, the tensioning plate moves inwards in the guide groove, and the jacking block contracts inwards in the radial direction of the pile extension device main body to be separated from the inner wall of the main pile;
and hoisting and recycling the vibrating hammer, the pile extension device and the pile delivery device which are fixedly connected to the floating crane ship.
4. A method of driving a subsea buried pile according to any of claims 1 to 3, wherein the pile driver is provided as a hydraulic pile driver.
5. A piling method for a submarine buried pile according to any one of claims 1 to 3, wherein the limit structure of the pile supporting frame comprises a frame body provided with a through passage and a supporting component connected with the frame body, wherein a plurality of lugs are distributed on the outer surface of the first end of the main pile along the circumferential direction of the first end of the main pile;
The support assembly comprises a plurality of support pieces and a plurality of telescopic mechanisms corresponding to the support pieces, and the telescopic mechanisms drive the support pieces to reciprocate between a first position for supporting the ear plate and a second position far away from the ear plate.
6. A method of driving a subsea buried pile according to any of claims 1 to 3, wherein said hoisting and translating the main pile to a first predetermined position and turning the pile comprises:
And hoisting and translating the main pile to a first preset position, connecting an anchor chain and overturning the main pile.
7. A method of driving a subsea buried pile according to any of claims 1 to 3, wherein the central axes of the pile holder, the fixedly connected pile follower and the pile driver coincide and are perpendicular to the seabed plane.
8. A method of driving a subsea buried pile according to any of claims 1 to 3, wherein prior to said hoisting and translating the main pile to the first predetermined position and turning the pile, the method further comprises:
and fixing the pile supporting frame on the side of the floating crane ship for hanging the main pile.
9. A piling device for a submarine buried pile, comprising a pile receiver, a pile follower and a vibratory hammer, wherein the piling device employs the piling method of any one of claims 1 to 8.
CN202310908110.7A 2023-07-24 2023-07-24 Piling method and piling device for seabed buried piles Pending CN119352510A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310908110.7A CN119352510A (en) 2023-07-24 2023-07-24 Piling method and piling device for seabed buried piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310908110.7A CN119352510A (en) 2023-07-24 2023-07-24 Piling method and piling device for seabed buried piles

Publications (1)

Publication Number Publication Date
CN119352510A true CN119352510A (en) 2025-01-24

Family

ID=94305016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310908110.7A Pending CN119352510A (en) 2023-07-24 2023-07-24 Piling method and piling device for seabed buried piles

Country Status (1)

Country Link
CN (1) CN119352510A (en)

Similar Documents

Publication Publication Date Title
US4257721A (en) System for placement of piles into the seafloor
US4537533A (en) Installation and levelling of subsea templates
US3101798A (en) Marine drilling apparatus
GB2307708A (en) Deep water piling and methods of installing or removing
KR20080069999A (en) Installation of Underwater Anchorage
EP0972114B1 (en) Position penetrated anchor system and its use
CN110761315B (en) Method for constructing suction anchor by using drilling ship
US8784011B2 (en) Marine-equipment installation method and apparatus
JP6914411B1 (en) Pile construction method
WO2024099082A1 (en) Seabed type static cone penetration apparatus and penetration method
US3846991A (en) Pile driving method and apparatus
US20120201608A1 (en) Foundation for offshore wind turbine and method and means for its transportation and installation in deepwaters
CN110185057B (en) Tool and construction method for lifting and erecting steel pipe piles of offshore wind power single pile foundation
CN112411543A (en) Pile clamping device of vibrating pile hammer with internal support type clamping structure and using method
CN110130342B (en) Piling equipment and piling method for underwater reinforced concrete prefabricated sheet pile construction
CN119352510A (en) Piling method and piling device for seabed buried piles
CN116424487B (en) Annular anchor and torsion-resistant bearing capacity calculation method and installation and recovery assembly thereof
CN111962543A (en) Rapid connection and separation process of pile stabilizing platform and mother ship
CN117328454A (en) Method for limiting ultra-long prestressed pipe pile in complex sea-filling land area and sinking pile by hydraulic ram
EP3794183B1 (en) Method for removal of an offshore fixed platform
CN214993830U (en) Matching device of hydraulic hammer of ultra-large piling ship
CN115182341A (en) Offshore steel pipe pile sinking process
AU725166B2 (en) Position penetrated anchor system
CN214143707U (en) Amphibious low-position side-holding type steel pipe pile vibration sinking and pulling equipment
KR101859613B1 (en) Mooring apparatus

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination