CN117163117A - Curbstone transferring device and method - Google Patents

Curbstone transferring device and method Download PDF

Info

Publication number
CN117163117A
CN117163117A CN202311196349.2A CN202311196349A CN117163117A CN 117163117 A CN117163117 A CN 117163117A CN 202311196349 A CN202311196349 A CN 202311196349A CN 117163117 A CN117163117 A CN 117163117A
Authority
CN
China
Prior art keywords
locking
curbstone
boom
rod
jib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202311196349.2A
Other languages
Chinese (zh)
Inventor
曲洪波
李成伟
张勇
刘晓
黄力
胡欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202311196349.2A priority Critical patent/CN117163117A/en
Publication of CN117163117A publication Critical patent/CN117163117A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The application discloses a curbstone transferring device and a curbstone transferring method, and relates to the technical field of road construction. The utility model provides a curbstone transfer device, includes the horizontal pole, the both ends of horizontal pole are provided with the wheel respectively, be provided with upward extension's pole setting on the horizontal pole, be provided with around its pivoted jib in the pole setting, the jib with be provided with between the pole setting be used for with the locking mechanical system of jib locking, the both ends of jib are located respectively the both sides of pole setting, the first end of jib is provided with the lifting hook. Compared with the existing shouldering transportation mode, the method reduces the labor intensity of workers and improves the transportation efficiency.

Description

一种路沿石转运装置及方法A device and method for transporting curb stones

技术领域Technical field

本申请涉及道路施工技术领域,具体涉及一种路沿石转运装置及方法。This application relates to the field of road construction technology, and specifically to a curb stone transfer device and method.

背景技术Background technique

路沿石是用于路面边缘的界石,也称道牙石或缘石,它是在路面上区分车行道、人行道、绿地、隔离带和道路其他部分的界线,起到保障行人、车辆交通安全和保证路面边缘整齐的作用。Curb stones are boundary stones used at the edge of the road, also known as curb stones or curb stones. They are the boundaries on the road surface that distinguish the roadways, sidewalks, green spaces, isolation belts and other parts of the road. They play a role in ensuring the safety and security of pedestrians and vehicle traffic. The role of smooth road edges.

在市政、公路工程的建设过程中,路沿石的转运过程为:先利用叉车将路沿石转运至堆放位置进行堆放,然后人工再采用肩扛手抬的方式依次将路沿石转运至安装位置进行安装作业,但是人工搬运路沿石存在劳动强度大、转运效率低的问题,并且随着路沿石的安装,安装位置与堆放位置之间的距离越来越远,人工搬运路沿石时的劳动强度就越来越大,转运效率越来越低。During the construction of municipal and highway projects, the transportation process of curb stones is as follows: first, use forklifts to transport the curb stones to the stacking location for stacking, and then manually transfer the curb stones to the installation site in sequence by carrying them on the shoulders and by hand. However, manual handling of curb stones has the problems of high labor intensity and low transfer efficiency. With the installation of curb stones, the distance between the installation position and the stacking position becomes farther and farther. Manual handling of curb stones The labor intensity is getting higher and higher, and the transportation efficiency is getting lower and lower.

发明内容Contents of the invention

本申请的目的在于提供一种路沿石转运装置及方法,解决人工搬运路沿石时的劳动强度大、转运效率低的问题。The purpose of this application is to provide a curb stone transfer device and method to solve the problems of high labor intensity and low transfer efficiency when manually transporting curb stones.

本申请解决其技术问题所采用的技术方案是:一种路沿石转运装置,包括横杆,所述横杆的两端分别设置有车轮,所述横杆上设置有向上延伸的立杆,所述立杆上设置有绕其转动的吊杆,所述吊杆与所述立杆之间设置有用于将所述吊杆锁定的锁定机构,所述吊杆的两端分别位于所述立杆的两侧,所述吊杆的第一端设置有吊钩。The technical solution adopted by this application to solve the technical problem is: a roadside stone transfer device, which includes a crossbar, wheels are respectively provided at both ends of the crossbar, and a vertical pole extending upward is provided on the crossbar. The vertical pole is provided with a suspension rod that rotates around it. A locking mechanism for locking the suspension rod is provided between the suspension rod and the vertical pole. Both ends of the suspension rod are respectively located on the vertical pole. On both sides of the rod, the first end of the boom is provided with a hook.

进一步的,所述锁定机构用于将所述吊杆锁定在与所述横杆相垂直的位置。Further, the locking mechanism is used to lock the suspension rod in a position perpendicular to the crossbar.

进一步的,所述锁定机构包括固定座和锁定杆;所述固定座设置在所述吊杆的下方并与所述立杆连接,所述锁定杆从上向下依次穿过所述立杆和所述固定座;所述立杆与所述固定座上分别设置有供所述锁定杆穿过的锁定孔。Further, the locking mechanism includes a fixed seat and a locking rod; the fixed seat is provided below the suspension rod and connected to the vertical rod, and the locking rod passes through the vertical rod and the vertical rod in sequence from top to bottom. The fixed seat; the vertical rod and the fixed seat are respectively provided with locking holes for the locking rod to pass through.

进一步的,所述锁定机构包括锁定座、卡块和连接件;所述锁定座设置在所述吊杆的下方并与所述立杆连接,所述卡块的数量为两个,两个所述卡块分别设置在所述吊杆的两侧,两个所述卡块的底部与所述锁定座铰接,两个所述卡块的顶部通过所述连接件可拆卸连接,所述连接件位于所述吊杆的上方。Further, the locking mechanism includes a locking seat, a clamping block and a connecting piece; the locking seat is arranged below the suspension rod and connected to the vertical pole, and the number of the clamping blocks is two, and the two clamping blocks are The clamping blocks are respectively arranged on both sides of the suspension rod. The bottoms of the two clamping blocks are hinged with the locking seat. The tops of the two clamping blocks are detachably connected through the connecting piece. The connecting piece Located above the boom.

进一步的,所述横杆与所述立杆之间设置有斜撑杆。Further, a diagonal brace is provided between the horizontal bar and the vertical bar.

进一步的,还包括两根吊绳,所述吊绳的两端分别设置有吊环,所述吊环用于钩挂在所述吊钩上。Furthermore, it also includes two hanging ropes. Two ends of the hanging ropes are respectively provided with hanging rings, and the hanging rings are used to be hooked on the hanging hooks.

进一步的,所述吊杆的第二端设置有把手组件。Further, the second end of the boom is provided with a handle assembly.

进一步的,所述吊杆上设置有位于所述吊杆的第二端与所述立杆之间的配重。Further, the boom is provided with a counterweight located between the second end of the boom and the vertical pole.

进一步的,所述配重可在所述吊杆上移动,所述配重上设置有锁定件,所述锁定件用于将所述配重锁定在所述吊杆上。Further, the counterweight is movable on the suspension rod, and a locking piece is provided on the counterweight, and the locking piece is used to lock the counterweight on the suspension rod.

一种路沿石转运方法,采用路沿石转运装置对路沿石进行转运。A curb stone transfer method uses a curb stone transfer device to transfer the curb stone.

本申请的有益效果:Beneficial effects of this application:

本申请实施例提供的路沿石转运装置及方法,用于对路沿石进行转运,与现有肩扛手抬的转运方式相比,降低了工人的劳动强度,提高了转运效率。当路沿石转运至安装位置后,解除吊杆与立杆之间的锁定机构,在不改变车轮方向的情况下,通过转动吊杆就可使路沿石到达指定安装位置,避免人工二次调整,不受施工环境的局限,缩短了路沿石安装的时间。The curb stone transfer device and method provided by the embodiments of the present application are used to transfer curb stones. Compared with the existing shoulder-carrying and hand-carrying transfer method, the labor intensity of workers is reduced and the transfer efficiency is improved. When the curb stone is transferred to the installation position, the locking mechanism between the boom and the vertical pole is released. Without changing the direction of the wheel, the curb stone can be moved to the designated installation position by rotating the boom, avoiding manual re-installation. Adjustment is not limited by the construction environment, shortening the installation time of curb stones.

附图说明Description of drawings

为了更清楚地说明本申请实施例的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本申请的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required to be used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present application and therefore do not It should be regarded as a limitation of the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without exerting creative efforts.

图1是本申请实施例提供的路沿石转运装置的结构示意图;Figure 1 is a schematic structural diagram of a curb stone transfer device provided by an embodiment of the present application;

图2是图1的左视图;Figure 2 is a left view of Figure 1;

图3是图1的俯视图;Figure 3 is a top view of Figure 1;

图4是锁定机构的结构示意图;Figure 4 is a schematic structural diagram of the locking mechanism;

图5是锁定机构的另一结构示意图;Figure 5 is another structural schematic diagram of the locking mechanism;

图6是图5中沿A-A线的剖视图;Figure 6 is a cross-sectional view along line A-A in Figure 5;

图7是吊绳的结构示意图;Figure 7 is a schematic structural diagram of the hanging rope;

图8是配重与吊杆连接的结构示意图;Figure 8 is a schematic structural diagram of the connection between the counterweight and the boom;

图9是采用本申请实施例提供的路沿石转运装置在转运路沿石时的状态图。Figure 9 is a state diagram when the curb stone transfer device provided by the embodiment of the present application is used to transfer curb stones.

附图标记:Reference signs:

10-横杆;11-车轮;12-立杆;13-吊杆;14-锁定机构;15-吊钩;16-斜撑杆;17-吊绳;18-把手组件;19-配重;20-锁定件;21-轴承结构;30-路沿石;141-固定座;142-锁定杆;143-锁定孔;144-锁定座;145-卡块;146-连接件;147-水平转轴;171-吊环;181-连接杆;182-握把。10-cross bar; 11-wheel; 12-vertical pole; 13-suspender; 14-locking mechanism; 15-hook; 16-inclined brace; 17-sling; 18-handle assembly; 19-counterweight; 20-locking piece; 21-bearing structure; 30-kerbstone; 141-fixed seat; 142-locking rod; 143-locking hole; 144-locking seat; 145-block; 146-connector; 147-horizontal rotating shaft ; 171-suspended ring; 181-connecting rod; 182-grip.

具体实施方式Detailed ways

为使本申请实施例的目的、技术方案和优点更加清楚,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述。In order to make the purpose, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application.

应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。且在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。It should be noted that similar reference numerals and letters represent similar items in the following figures, therefore, once an item is defined in one figure, it does not need further definition and explanation in subsequent figures. And if there is no conflict, the embodiments and features in the embodiments in this application can be combined with each other.

在本申请实施例的描述中,指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该申请产品使用时惯常摆放的方位或位置关系,或者是本领域技术人员惯常理解的方位或位置关系。术语“设置”、“开有”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接、可拆卸连接和一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。In the description of the embodiments of this application, the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, or is the orientation or positional relationship that is customarily placed when the product of this application is used, or is the usual orientation or positional relationship of those skilled in the art. Understand the orientation or positional relationship. The terms "setting", "opening", "installation", "connecting" and "connecting" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection and an integral connection; it can be a mechanical connection or an electrical connection. Connection; it can be a direct connection, or an indirect connection through an intermediary, or an internal connection between two components.

参见图1至图3,本申请实施例提供的一种路沿石转运装置,包括横杆10,横杆10的两端分别设置有车轮11,横杆10上设置有向上延伸的立杆12,立杆12上设置有绕其转动的吊杆13,吊杆13与立杆12之间设置有用于将吊杆13锁定的锁定机构14,吊杆13的两端分别位于立杆12的两侧,吊杆13的第一端设置有吊钩15。Referring to Figures 1 to 3, an embodiment of the present application provides a curb stone transfer device, which includes a crossbar 10. Wheels 11 are provided at both ends of the crossbar 10, and an upwardly extending vertical pole 12 is provided on the crossbar 10. The vertical pole 12 is provided with a boom 13 that rotates around it. A locking mechanism 14 for locking the boom 13 is provided between the boom 13 and the vertical pole 12. The two ends of the boom 13 are respectively located on both sides of the vertical pole 12. On the other side, a hook 15 is provided at the first end of the boom 13 .

具体的,横杆10水平设置,横杆10的两端分别安装有对其进行支撑的车轮11,且车轮11可绕横杆10转动。立杆12竖向设置,立杆12的下端与横杆10固定连接,立杆12与两个车轮11之间的距离相等。立杆12与横杆10之间可采用扣件可拆卸连接,也可以焊接连接,还可以采用现有的其他连接方式连接。吊杆13设置在横杆10的上方,且与立杆12相垂直。吊杆13与立杆12转动连接,以使吊杆13可绕立杆12转动。例如,吊杆13通过轴承结构21与立杆12连接。轴承结构21包括轴承座和安装在轴承座内的轴承,轴承座通过轴承安装在立杆12的上端,以使轴承座可绕立杆12转动,吊杆13与轴承座固定连接。在其他实施例中,吊杆13还可与立杆12不垂直。Specifically, the crossbar 10 is arranged horizontally, and wheels 11 are respectively installed at both ends of the crossbar 10 to support the crossbar 10 , and the wheels 11 can rotate around the crossbar 10 . The vertical pole 12 is arranged vertically, the lower end of the vertical pole 12 is fixedly connected to the cross bar 10, and the distance between the vertical pole 12 and the two wheels 11 is equal. The vertical pole 12 and the horizontal pole 10 can be detachably connected by fasteners, welded, or other existing connection methods. The suspension rod 13 is arranged above the horizontal rod 10 and perpendicular to the vertical rod 12 . The boom 13 is rotatably connected to the vertical pole 12 so that the boom 13 can rotate around the vertical pole 12 . For example, the suspension rod 13 is connected to the vertical pole 12 through the bearing structure 21 . The bearing structure 21 includes a bearing seat and a bearing installed in the bearing seat. The bearing seat is installed on the upper end of the vertical pole 12 through the bearing so that the bearing seat can rotate around the vertical pole 12. The boom 13 is fixedly connected to the bearing seat. In other embodiments, the hanging rod 13 may not be perpendicular to the vertical pole 12 .

锁定机构14用于将吊杆13锁定,防止吊杆13绕立杆12转动。示例性的,锁定机构14用于将吊杆13锁定在与横杆10相垂直的位置。当然,在其他实施例中,锁定机构14还可以将吊杆13锁定在其他位置,在此不做具体的限定。The locking mechanism 14 is used to lock the boom 13 to prevent the boom 13 from rotating around the vertical pole 12 . For example, the locking mechanism 14 is used to lock the suspension rod 13 in a position perpendicular to the crossbar 10 . Of course, in other embodiments, the locking mechanism 14 can also lock the boom 13 in other positions, which is not specifically limited here.

吊杆13的两端包括第一端和第二端;其中,第一端和第二端分别位于立杆12的两侧。吊杆13的第一端为吊装端,设置有吊钩15,用于吊装路沿石。示例性的,吊钩15通过螺栓与吊杆13固定连接。吊杆13的第二端为手持端,用于供工人握持。The two ends of the suspension rod 13 include a first end and a second end; wherein the first end and the second end are respectively located on both sides of the vertical pole 12 . The first end of the boom 13 is a lifting end, and is provided with a hook 15 for lifting curb stones. Exemplarily, the hook 15 is fixedly connected to the suspension rod 13 through bolts. The second end of the boom 13 is a handheld end for workers to hold.

示例性的,横杆10、立杆12、吊杆13均采用钢管制作而成。例如,横杆10、立杆12、吊杆13均采用φ48.3×3.6mm的不锈钢管制作而成。当然,在其他实施例中,横杆10、立杆12、吊杆13还可以采用其他型材制作而成,在此不做具体的限定。For example, the horizontal bar 10, the vertical bar 12, and the hanging bar 13 are all made of steel pipes. For example, the horizontal bar 10, the vertical bar 12, and the hanging bar 13 are all made of φ48.3×3.6mm stainless steel pipes. Of course, in other embodiments, the horizontal bar 10, the vertical bar 12, and the hanging bar 13 can also be made of other profiles, which are not specifically limited here.

参见图9,本申请实施例还提供一种路沿石转运方法,采用上述实施例的路沿石转运装置对路沿石30进行转运,其转运过程为:首先,通过锁定机构14将吊杆13锁定,防止吊杆13绕立杆12转动,将路沿石转运装置移至路沿石堆放位置,利用绳索固定好路沿石30,并将绳索绑在吊钩15上;然后,利用杠杆原理,工人握住吊杆13的第二端,并下压吊杆13的第二端,吊杆13的第一端上翘并使路沿石30离地悬空;然后,工人推动该路沿石转运装置以使车轮11在地面滚动,进而将路沿石30转运至安装位置附近;然后,解除锁定机构14对吊杆13的锁定,工人控制吊杆13绕立杆12转动,使路沿石30达到指定位置,然后解开绳索卸载路沿石30。Referring to Figure 9, the embodiment of the present application also provides a curb stone transfer method. The curb stone transfer device of the above embodiment is used to transfer the curb stone 30. The transfer process is: first, the suspension rod is moved through the locking mechanism 14. 13 is locked to prevent the boom 13 from rotating around the vertical pole 12, move the curb stone transfer device to the curb stone stacking position, use the rope to fix the curb stone 30, and tie the rope to the hook 15; then, use the lever The principle is that the worker holds the second end of the boom 13 and presses down the second end of the boom 13. The first end of the boom 13 tilts up and makes the curb stone 30 hang in the air; then, the worker pushes the curb The stone transfer device is used to make the wheels 11 roll on the ground, and then the curb stones 30 are transferred to the vicinity of the installation position; then, the locking mechanism 14 unlocks the boom 13, and the worker controls the boom 13 to rotate around the vertical pole 12, so that the curb The stone 30 reaches the designated position, and then unties the rope to unload the curb stone 30.

本申请实施例提供的路沿石转运装置及方法,用于对路沿石30进行转运,与现有肩扛手抬的转运方式相比,降低了工人的劳动强度,提高了作业效率。当路沿石30转运至安装位置后,解除吊杆13与立杆12之间的锁定机构,在不改变车轮方向的情况下,通过转动吊杆13就可使路沿石30到达指定安装位置,避免人工二次调整,不受施工环境的局限,缩短了路沿石安装的时间。The curb stone transfer device and method provided by the embodiments of the present application are used to transfer the curb stone 30. Compared with the existing shoulder-carrying and hand-carrying transfer method, the labor intensity of workers is reduced and the operating efficiency is improved. After the curb stone 30 is transferred to the installation position, the locking mechanism between the boom 13 and the vertical pole 12 is released, and the curb stone 30 can be reached at the designated installation position by rotating the boom 13 without changing the wheel direction. , avoid manual secondary adjustments, are not limited by the construction environment, and shorten the installation time of curb stone.

图4中示出了锁定机构14的一种实施方式。参见图4,锁定机构14包括固定座141和锁定杆142;固定座141设置在吊杆13的下方并与立杆12连接,锁定杆142从上向下依次穿过立杆12和固定座141;立杆12与固定座141上分别设置有供锁定杆142穿过的锁定孔143。One embodiment of the locking mechanism 14 is shown in FIG. 4 . Referring to Figure 4, the locking mechanism 14 includes a fixed base 141 and a locking rod 142; the fixed base 141 is arranged below the suspension rod 13 and connected to the vertical pole 12, and the locking rod 142 passes through the vertical rod 12 and the fixed base 141 from top to bottom. ; The vertical pole 12 and the fixed base 141 are respectively provided with locking holes 143 for the locking rod 142 to pass through.

当需要将吊杆13锁定时,只需转动吊杆13,使吊杆13上的锁定孔143与固定座141上的锁定孔143正对,然后将锁定杆142从上向下依次插入立杆12上的锁定孔143和固定座141上的锁定孔143中即可,此时,吊杆13就不能绕立杆12转动。当需要解除吊杆13的锁定时,只需将锁定杆142从锁定孔143中抽出即可。为了提高锁定的可靠性,锁定机构14为两组,两组锁定机构14分别设置在立杆12的两侧。When it is necessary to lock the boom 13, just rotate the boom 13 so that the locking hole 143 on the boom 13 is directly opposite to the locking hole 143 on the fixed base 141, and then insert the locking rod 142 into the vertical pole in sequence from top to bottom. The locking hole 143 on the hanging rod 12 and the locking hole 143 on the fixed base 141 are enough. At this time, the boom 13 cannot rotate around the vertical pole 12. When it is necessary to unlock the suspension rod 13, the locking rod 142 only needs to be pulled out from the locking hole 143. In order to improve the reliability of locking, the locking mechanism 14 is divided into two groups, and the two groups of locking mechanisms 14 are respectively arranged on both sides of the vertical pole 12 .

图5、图6中示出了锁定机构14的另一种实施方式。参见图5、图6,锁定机构14包括锁定座144、卡块145和连接件146;锁定座144设置在吊杆13的下方并与立杆12连接,卡块145的数量为两个,两个卡块145分别设置在吊杆13的两侧,两个卡块145的底部与锁定座144铰接,两个卡块145的顶部通过连接件146可拆卸连接,所述连接件146位于所述吊杆13的上方。Another embodiment of the locking mechanism 14 is shown in FIGS. 5 and 6 . Referring to Figures 5 and 6, the locking mechanism 14 includes a locking seat 144, a blocking block 145 and a connecting piece 146; the locking seat 144 is provided below the suspension rod 13 and connected to the vertical pole 12. The number of the blocking blocks 145 is two, and two Two clamping blocks 145 are respectively arranged on both sides of the suspension rod 13. The bottoms of the two clamping blocks 145 are hinged with the locking seat 144. The tops of the two clamping blocks 145 are detachably connected through the connecting piece 146. The connecting piece 146 is located on the Above the boom 13.

示例性的,锁定座144为从上向下倾斜设置的杆状结构,其下端与立杆12固定连接,其上端与两个卡块145的底部铰接。例如,两个卡块145的底部通过水平转轴147与锁定座144连接,使卡块145可绕水平转轴147上下翻转,并使卡块145翻转至吊杆13的下方。连接件146可以为螺栓、插销或铁丝等。当连接件146为螺栓时,其中一个卡块145上设置有供螺栓穿过的螺栓孔,另一个卡块145上设置有与螺栓螺纹连接的螺纹孔。当连接件146为插销或铁丝时,两个卡块145上均设置有供插销或铁丝穿过的通孔。For example, the locking seat 144 is a rod-shaped structure that is inclined from top to bottom. Its lower end is fixedly connected to the vertical pole 12 , and its upper end is hinged to the bottoms of the two blocks 145 . For example, the bottoms of the two clamping blocks 145 are connected to the locking seats 144 through the horizontal rotating shaft 147 , so that the clamping blocks 145 can be flipped up and down around the horizontal rotating shaft 147 , and the clamping blocks 145 can be flipped to the bottom of the boom 13 . The connecting member 146 may be a bolt, a pin, or an iron wire. When the connecting member 146 is a bolt, one of the clamping blocks 145 is provided with a bolt hole for the bolt to pass through, and the other clamping block 145 is provided with a threaded hole for threaded connection with the bolt. When the connecting member 146 is a pin or an iron wire, both blocks 145 are provided with through holes for the pin or iron wire to pass through.

当需要将吊杆13锁定时,只需转动吊杆13,使吊杆13位于两个卡块145之间,然后将两个卡块145向上翻转,使两个卡块145与吊杆13抵接,然后通过连接件146将两个卡块145连接在一起即可,此时,吊杆13就不能绕立杆12转动。当需要解除吊杆13的锁定时,只需去除连接件146,将卡块145翻转至吊杆13的下方即可。为了提高锁定的可靠性,锁定机构14为两组,两组锁定机构14分别设置在立杆12的两侧。When it is necessary to lock the boom 13, you only need to rotate the boom 13 so that the boom 13 is located between the two blocks 145, and then flip the two blocks 145 upward so that the two blocks 145 contact the boom 13. Then connect the two clamping blocks 145 together through the connecting piece 146. At this time, the boom 13 cannot rotate around the vertical pole 12. When it is necessary to unlock the boom 13 , it is only necessary to remove the connecting piece 146 and flip the blocking block 145 to the bottom of the boom 13 . In order to improve the reliability of locking, the locking mechanism 14 is divided into two groups, and the two groups of locking mechanisms 14 are respectively arranged on both sides of the vertical pole 12 .

为了提高立杆12与横杆10连接的牢固性,参见图2,横杆10与立杆12之间设置有斜撑杆16。具体的,斜撑杆16从上向下倾斜设置,斜撑杆16的上端与立杆12固定连接,斜撑杆16的下端与横杆10固定连接。示例性的,斜撑杆16可以采用钢管制作而成,也可以采用扁钢、角钢制作而成,在此不做具体的限定。斜撑杆16与横杆10和立杆12之间可采用扣件连接,也可以焊接连接。进一步,斜撑杆16的数量为两个,两个斜撑杆16分别设置在立杆12的两侧。In order to improve the firmness of the connection between the vertical pole 12 and the horizontal pole 10 , as shown in FIG. 2 , a diagonal brace 16 is provided between the horizontal pole 10 and the vertical pole 12 . Specifically, the diagonal strut 16 is arranged inclined from top to bottom, the upper end of the diagonal strut 16 is fixedly connected to the vertical pole 12 , and the lower end of the diagonal strut 16 is fixedly connected to the horizontal bar 10 . For example, the diagonal support rod 16 can be made of steel pipes, flat steel, or angle steel, and is not specifically limited here. The diagonal support bar 16, the cross bar 10 and the vertical bar 12 can be connected by fasteners or by welding. Furthermore, the number of diagonal braces 16 is two, and the two diagonal braces 16 are respectively arranged on both sides of the vertical pole 12 .

参见图1、图7,本申请实施例提供的路沿石转运装置,还包括两根吊绳17,吊绳17的两端分别设置有吊环171,吊环171用于钩挂在吊钩15上。示例性的,吊绳17可以为钢丝绳,也可以为尼龙绳。通过设置吊绳17,用于钩挂在吊钩15上以对路沿石进行吊装。操作时,先将两根吊绳17从路沿石的下方穿过,再将四个吊环171钩挂在吊钩15上,然后利用杠杆原理使吊杆13的第一端上翘,就可使路沿石离地悬空。Referring to Figures 1 and 7, the curb stone transfer device provided by the embodiment of the present application also includes two hanging ropes 17. The two ends of the hanging rope 17 are respectively provided with lifting rings 171, and the hanging rings 171 are used to be hooked on the hanging hooks 15. . For example, the hanging rope 17 can be a steel wire rope or a nylon rope. The lifting rope 17 is provided for hanging on the hanging hook 15 to lift the curb stone. During operation, first pass the two hanging ropes 17 through the bottom of the curb stone, then hang the four hanging rings 171 on the hanging hooks 15, and then use the lever principle to tilt the first end of the hanging rod 13 upward. Make the curb stone suspended from the ground.

为了便于工人握持吊杆13,参见图1至图3,吊杆13的第二端设置有把手组件18。示例性的,把手组件18包括连接杆181和握把182,连接杆181水平设置并与吊杆13相垂直,连接杆181的中间与吊杆13固定连接,连接杆181的两端分别固定有握把182。操作时,工人双手握住握把182以推动路沿石转运装置移动。In order to facilitate workers to hold the boom 13, referring to Figures 1 to 3, a handle assembly 18 is provided at the second end of the boom 13. Exemplarily, the handle assembly 18 includes a connecting rod 181 and a grip 182. The connecting rod 181 is arranged horizontally and perpendicular to the hanging rod 13. The middle of the connecting rod 181 is fixedly connected to the hanging rod 13. Both ends of the connecting rod 181 are respectively fixed with Grip 182. During operation, the worker holds the handle 182 with both hands to push the curb stone transfer device to move.

在转运路沿石的过程中,为了使工人更省力,参见图1、图3,吊杆13上设置有位于吊杆13的第二端与立杆12之间的配重19。通过设置配重19,在转运路沿石的过程中,可利用配重19平衡路沿石的重量,进而使工人操作更省力。In order to save workers more effort during the transfer of curb stones, as shown in Figures 1 and 3, the boom 13 is provided with a counterweight 19 between the second end of the boom 13 and the vertical pole 12. By setting the counterweight 19, during the process of transporting the curb stones, the counterweight 19 can be used to balance the weight of the curb stones, thereby making the workers' operation more labor-saving.

为了便于平衡不同重量的路沿石,参见图8,配重19可在吊杆13上移动,配重19上设置有锁定件20,锁定件20用于将配重19锁定在吊杆13上。操作时,根据需要转运的路沿石的重量,调节配重19在吊杆13上的位置,当配重19的位置调整好后,通过锁定件20将配重19锁定在吊杆13上。In order to facilitate the balancing of curb stones of different weights, see Figure 8, the counterweight 19 can move on the boom 13. The counterweight 19 is provided with a locking piece 20. The locking piece 20 is used to lock the counterweight 19 on the boom 13. . During operation, adjust the position of the counterweight 19 on the boom 13 according to the weight of the curb stones that need to be transferred. When the position of the counterweight 19 is adjusted, the counterweight 19 is locked on the boom 13 through the locking piece 20 .

示例性的,配重19上设置有通孔,吊杆13从该通孔中穿过,以使配重19可在吊杆13上移动。当然,在其他实施例中,配重19还可以与套管连接,套管套设在吊杆13上,并可在吊杆13上移动,这样也可使配重19在吊杆13上移动。示例性的,锁定件20包括螺栓,配重19上设置有螺纹通孔,螺栓螺纹连接在螺纹通孔中,螺栓的端部用于与吊杆13的表面抵接。操作时,拧紧螺栓,使螺栓的端部与吊杆13的表面抵接,这样就将配重19的位置锁定。在其他实施例中,锁定件20还可以为与配重19连接的卡箍,通过将卡箍安装在吊杆13上,以对配重19的位置进行锁定。For example, the counterweight 19 is provided with a through hole, and the suspension rod 13 passes through the through hole, so that the counterweight 19 can move on the suspension rod 13 . Of course, in other embodiments, the counterweight 19 can also be connected to a casing. The casing is set on the boom 13 and can move on the boom 13 , so that the counterweight 19 can also move on the boom 13 . Exemplarily, the locking member 20 includes a bolt, the counterweight 19 is provided with a threaded through hole, the bolt is threadedly connected in the threaded through hole, and the end of the bolt is used to abut the surface of the boom 13 . During operation, tighten the bolt so that the end of the bolt contacts the surface of the boom 13, thereby locking the position of the counterweight 19. In other embodiments, the locking member 20 can also be a clamp connected to the counterweight 19 , and the position of the counterweight 19 is locked by installing the clamp on the suspension rod 13 .

以上所述,仅是本申请的较佳实施例而已,并非对本申请作任何形式上的限制,依据本申请的技术实质,在本申请的精神和原则之内,对以上实施例所作的任何简单的修改、等同替换与改进等,均仍属于本申请技术方案的保护范围之内。The above are only preferred embodiments of the present application and are not intended to limit the present application in any form. According to the technical essence of the present application and within the spirit and principles of the present application, any simple modifications to the above embodiments may be made. Modifications, equivalent substitutions and improvements, etc., all still fall within the protection scope of the technical solution of this application.

Claims (10)

1. The utility model provides a curbstone transfer device, its characterized in that, includes horizontal pole (10), the both ends of horizontal pole (10) are provided with wheel (11) respectively, be provided with pole setting (12) of upwards extending on horizontal pole (10), be provided with on pole setting (12) around its pivoted jib (13), jib (13) with be provided with between pole setting (12) be used for with locking mechanical system (14) of jib (13) locking, the both ends of jib (13) are located respectively the both sides of pole setting (12), the first end of jib (13) is provided with lifting hook (15).
2. The curbstone transport apparatus in accordance with claim 1, wherein the locking mechanism (14) is adapted to lock the boom (13) in a position perpendicular to the cross bar (10).
3. The curbstone transport apparatus in accordance with claim 1 or 2, wherein the locking mechanism (14) comprises a fixed seat (141) and a locking lever (142); the fixing seat (141) is arranged below the hanging rod (13) and is connected with the vertical rod (12), and the locking rod (142) sequentially penetrates through the vertical rod (12) and the fixing seat (141) from top to bottom; the upright rod (12) and the fixed seat (141) are respectively provided with a locking hole (143) for the locking rod (142) to pass through.
4. The curbstone transport apparatus in accordance with claim 1 or 2, wherein the locking mechanism (14) comprises a locking seat (144), a latch (145) and a connector (146); the locking seat (144) is arranged below the hanging rod (13) and is connected with the vertical rod (12), the number of the clamping blocks (145) is two, the two clamping blocks (145) are respectively arranged on two sides of the hanging rod (13), the bottoms of the two clamping blocks (145) are hinged with the locking seat (144), the tops of the two clamping blocks (145) are detachably connected through the connecting piece (146), and the connecting piece (146) is arranged above the hanging rod (13).
5. The curbstone transport apparatus in accordance with claim 1, wherein a diagonal brace (16) is provided between the cross bar (10) and the upright (12).
6. The curbstone transport apparatus in accordance with claim 1, further comprising two lifting ropes (17), wherein two ends of the lifting ropes (17) are respectively provided with a lifting ring (171), and the lifting rings (171) are used for hooking on the lifting hook (15).
7. The curbstone transport apparatus in accordance with claim 1, wherein the second end of the boom (13) is provided with a handle assembly (18).
8. The curbstone transport apparatus in accordance with claim 7, wherein the boom (13) is provided with a counterweight (19) located between the second end of the boom (13) and the upright (12).
9. The curbstone transport apparatus in accordance with claim 8, wherein the counterweight (19) is movable on the boom (13), the counterweight (19) being provided with a locking member (20), the locking member (20) being adapted to lock the counterweight (19) on the boom (13).
10. A method of transferring curbstone, characterized in that the curbstone (30) is transferred using a curbstone transfer device according to any of claims 1 to 9.
CN202311196349.2A 2023-09-15 2023-09-15 Curbstone transferring device and method Withdrawn CN117163117A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311196349.2A CN117163117A (en) 2023-09-15 2023-09-15 Curbstone transferring device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311196349.2A CN117163117A (en) 2023-09-15 2023-09-15 Curbstone transferring device and method

Publications (1)

Publication Number Publication Date
CN117163117A true CN117163117A (en) 2023-12-05

Family

ID=88946630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311196349.2A Withdrawn CN117163117A (en) 2023-09-15 2023-09-15 Curbstone transferring device and method

Country Status (1)

Country Link
CN (1) CN117163117A (en)

Similar Documents

Publication Publication Date Title
CN101337640B (en) Lifting and hoisting method of vertical equipment
US8303006B2 (en) Apparatus for gripping and lifting construction castings
US12264047B2 (en) Mobile crane having a counterweight device
US10844559B2 (en) Traffic flow barrier with corresponding production mold and hand cart
CN104555734A (en) An upper column turning device and method of a marine crane
CN106976797A (en) Three suspension centres turn round suspender
CN107022958A (en) The method in cable-stayed bridge across girder is installed using cable crane
CN108862081A (en) A kind of chain block crane boom and the application in the adjusting of beam steel protective layer thickness
CN117163117A (en) Curbstone transferring device and method
CN212270693U (en) Bridge deck boundary beam hogging moment stretch-draw operating means
CN220904985U (en) Curbstone transfer device
CN217627095U (en) Hanging bracket for rear counter weight of forklift
CN108867572A (en) Transport the trackless trolley and construction method of face-plate of rockfill dam reinforced mesh
CN206553060U (en) Multifunctional small-size car rig
CN217731554U (en) Transportation, installation and dismounting device
CN114751290A (en) Installation method of quantum electric furnace electrode lifting upright post and lifting hydraulic cylinder
CN114590727A (en) Confined space suspended pipeline device and method
CN221955101U (en) A curbstone handling tool
CN103708364B (en) Lifting mechanism with counterweight component and crane
CN216663723U (en) Curb transportation installation device for municipal works
CA2354745A1 (en) Wheel lifting device
CN216861468U (en) Roadbed strip stone conveying device
CN215249058U (en) A simple and easy gallows for prefabricated tube coupling hoist and mount
CN108583596B (en) Transport face-plate of rockfill dam reinforced mesh trackless trolley height adjusting method
KR102666100B1 (en) Clamping apparatus for carring rice field boundary block

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20231205

WW01 Invention patent application withdrawn after publication