[go: up one dir, main page]

CN116770876A - Rock foundation local shallow layer advanced precipitation construction method - Google Patents

Rock foundation local shallow layer advanced precipitation construction method Download PDF

Info

Publication number
CN116770876A
CN116770876A CN202310823541.3A CN202310823541A CN116770876A CN 116770876 A CN116770876 A CN 116770876A CN 202310823541 A CN202310823541 A CN 202310823541A CN 116770876 A CN116770876 A CN 116770876A
Authority
CN
China
Prior art keywords
water
layer
pipe
ppr
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310823541.3A
Other languages
Chinese (zh)
Other versions
CN116770876B (en
Inventor
李长宁
郁勇
时景彬
刘志猛
樊怀亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202310823541.3A priority Critical patent/CN116770876B/en
Publication of CN116770876A publication Critical patent/CN116770876A/en
Application granted granted Critical
Publication of CN116770876B publication Critical patent/CN116770876B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)
  • Sewage (AREA)

Abstract

本发明公开了一种岩石地基局部浅层超前降水施工方法,包括以下步骤:确定裂隙水区域、制作PPR真空支管、布置PPR真空管、回填黄砂铺土工布、接水泵抽水、浇筑垫层混凝土、做防水、施工保护层及底板以及拆卸真空支管并封堵,其中,确定裂隙水区域的方法如下:垫层施工前,观察岩石地基裂隙水情况,确定裂隙水存在的区域,白石灰洒出区域范围,制作PPR真空支管方法如下:由于裂隙水量通常较小,所以选用直径20mm的小直径PPR管,在PPR管的四周纵向每隔10cm开1mm的小孔。本发明中通过在浇筑垫层前预埋真空降水管,所有的降水管均在垫层以下,对垫层和防水层没有交叉影响,确保了垫层和防水层的连续性和整体性。

The invention discloses a local shallow advanced dewatering construction method for rock foundations, which includes the following steps: determining the fissure water area, making PPR vacuum branch pipes, arranging PPR vacuum pipes, backfilling yellow sand and laying geotextile, collecting water with a water pump, pouring cushion concrete, and making Waterproofing, construction of protective layers and bottom plates, and removal of vacuum branch pipes and sealing. Among them, the method of determining the fissure water area is as follows: before cushion construction, observe the fissure water situation in the rock foundation to determine the area where fissure water exists and the area where white lime spills. The method for making a PPR vacuum branch pipe is as follows: Since the amount of water in the fissure is usually small, a small diameter PPR pipe with a diameter of 20mm is used, and small holes of 1mm are opened every 10cm longitudinally around the PPR pipe. In the present invention, vacuum dewatering pipes are pre-embedded before pouring the cushion layer, so that all the dewatering pipes are below the cushion layer and have no cross-effect on the cushion layer and waterproof layer, thus ensuring the continuity and integrity of the cushion layer and waterproof layer.

Description

一种岩石地基局部浅层超前降水施工方法A construction method for local shallow advance dewatering of rock foundations

技术领域Technical field

本发明涉及建筑施工技术领域,尤其涉及一种岩石地基局部浅层超前降水施工方法。The invention relates to the technical field of building construction, and in particular to a local shallow advance dewatering construction method for rock foundations.

背景技术Background technique

岩石地基地下水多以基岩裂隙水的形式存在,主要以层状、带状赋存于基岩裂隙密集发育带中,富水性差,水位不连续、不均匀,此类地基基坑降水通常采用在基坑四周设置排水沟和集水井的集水明排方式,但是遇到局部岩石节理发育产生局部地下水较多时,基坑四周的排水沟不能将局部的地下水排除,影响垫层及防水的施工。Groundwater in rock foundations mostly exists in the form of bedrock fissure water. It mainly exists in layers and strips in densely developed zones of bedrock fissures. It has poor water richness and discontinuous and uneven water levels. The precipitation of such foundation pits is usually carried out by Drainage ditches and water collection wells are set up around the foundation pit to collect and drain water. However, when local rock joints develop and produce local groundwater, the drainage ditches around the foundation pit cannot drain local groundwater, which affects the construction of cushion and waterproofing. .

现有的在浇筑混凝土垫层时,局部挖集水坑抽水,边抽水边浇筑混凝土垫层,垫层混凝土在硬化前,已经混入了大量地下水,导致垫层混凝土强度不足,并且在有渗水的垫层上开槽导流,但是开槽部位会一直存在明水,基层潮湿,防水卷材无法与垫层贴合,导致防水施工质量无法保证,为地下室底板渗漏埋下了隐患,另外,在防水层鼓包和有上浮风险的部位,将防水卷材开孔埋管,用自吸泵抽水,在浇筑混凝土底板时,用密封高封堵埋管,埋管处形成防水薄弱点,存在渗水风险。When pouring a concrete cushion, a local water pit is dug to pump water, and the concrete cushion is poured while pumping water. Before the cushion concrete hardens, a large amount of groundwater has been mixed, resulting in insufficient strength of the cushion concrete, and when there is water seepage. There are grooves on the cushion to guide water, but there will always be open water in the grooves. The base layer is moist, and the waterproofing membrane cannot fit well with the cushion. As a result, the quality of waterproofing construction cannot be guaranteed, which creates hidden dangers for basement floor leakage. In addition, In areas where the waterproofing layer bulges and is at risk of floating, open holes in the waterproofing membrane and bury the pipes, and use a self-priming pump to pump water. When pouring the concrete floor, seal the buried pipes with high seals. A waterproof weak point will form at the buried pipe and there will be water seepage. risk.

基于此,我们提出一种岩石地基局部浅层超前降水施工方法。Based on this, we propose a local shallow advanced precipitation construction method for rock foundations.

发明内容Contents of the invention

本发明的目的是为了解决现有技术中存在的缺点,而提出的一种岩石地基局部浅层超前降水施工方法。The purpose of the present invention is to propose a local shallow advanced dewatering construction method for rock foundations in order to solve the shortcomings existing in the prior art.

为了实现上述目的,本发明采用了如下技术方案:In order to achieve the above objects, the present invention adopts the following technical solutions:

一种岩石地基局部浅层超前降水施工方法,包括以下步骤:确定裂隙水区域、制作PPR真空支管、布置PPR真空管、回填黄砂铺土工布、接水泵抽水、浇筑垫层混凝土、做防水、施工保护层及底板以及拆卸真空支管并封堵;A local shallow advanced dewatering construction method for rock foundations, including the following steps: determining the fissure water area, making PPR vacuum branch pipes, arranging PPR vacuum pipes, backfilling yellow sand and laying geotextile, connecting water pumps to pump water, pouring cushion concrete, waterproofing, and construction protection layer and bottom plate as well as dismantling and sealing the vacuum branch pipe;

其中,确定裂隙水区域的方法如下:垫层施工前,观察岩石地基裂隙水情况,确定裂隙水存在的区域,白石灰洒出区域范围;Among them, the method of determining the fissure water area is as follows: before cushion construction, observe the fissure water situation in the rock foundation, determine the area where fissure water exists, and the area where white lime spills;

制作PPR真空支管方法如下:由于裂隙水量通常较小,所以选用直径20mm的小直径PPR管,在PPR管的四周纵向每隔10cm开1mm的小孔,同一截面开4个小孔,用双层密目网将PPR管缠绕紧密,一端用专用堵头将PPR管封堵严密,另一端不封堵作为出水端;The method of making a PPR vacuum branch pipe is as follows: Since the amount of water in the fissure is usually small, a small diameter PPR pipe with a diameter of 20mm is used. Small holes of 1mm are opened every 10cm longitudinally around the PPR pipe. Four small holes are opened in the same section. Double-layer Wrap the PPR pipe tightly with dense mesh, use a special plug to seal the PPR pipe tightly at one end, and leave the other end unblocked as the water outlet;

布置PPR真空管方法如下:在确定好的裂隙水区域间隔1m布置PPR真空支管,出水端超出裂隙水区域边界至少50cm,将所有的真空支管出水端用变径接头与50mmPPR主管连接,主管一端用专用堵头封堵,另一端接水泵。The method of arranging PPR vacuum pipes is as follows: arrange PPR vacuum branch pipes at intervals of 1m in the determined fissure water area. The outlet end exceeds the boundary of the fracture water area by at least 50cm. Connect the outlet ends of all vacuum branch pipes to the 50mm PPR main pipe with a reducing joint. One end of the main pipe shall be connected with a special The plug is sealed and the other end is connected to the water pump.

优选地,回填黄砂铺土工布方法如下:在裂隙水区域内回填50mm厚含泥量不超3%的中粗黄砂,整平后在黄砂表面覆盖一层土工布。Preferably, the method of backfilling yellow sand and paving geotextile is as follows: backfill 50mm thick medium-coarse yellow sand with a mud content of no more than 3% in the fissure water area, and after leveling, cover the surface of the yellow sand with a layer of geotextile.

优选地,接水泵抽水方法如下:将主管出水端与水泵连接,开启水泵抽水。Preferably, the method of connecting the water pump to pump water is as follows: connect the water outlet end of the main pipe to the water pump, and start the water pump to pump water.

优选地,浇筑垫层混凝土方法如下:在铺好的土工布上浇筑垫层混凝土,垫层混凝土四周需要超出划定的裂隙水区域至少10cm,确保在开启自吸泵后在黄沙层中形成负压区域。Preferably, the method of pouring cushion concrete is as follows: pour cushion concrete on the paved geotextile. The surrounding area of the cushion concrete needs to be at least 10cm beyond the designated fissure water area to ensure that it is formed in the yellow sand layer after the self-priming pump is turned on. Negative pressure area.

优选地,做防水方法如下:垫层混凝土强度强度满足要求后,观察垫层上是否有渗水、潮湿现象,无潮湿后施工防水层。Preferably, the waterproofing method is as follows: after the strength of the cushion concrete meets the requirements, observe whether there is water seepage or moisture on the cushion, and construct the waterproof layer after there is no moisture.

优选地,施工保护层及底板方法如下:防水施工完成后,开始施工防水保护层和底板。Preferably, the construction method of the protective layer and the base plate is as follows: after the waterproof construction is completed, the construction of the waterproof protective layer and the base plate begins.

优选地,拆卸真空支管并封堵方法如下:混凝土底板强度达到设计要求后,停止降水,然后将真空支管抽出,并使用混凝土浇注真空支管留下的孔洞,保证强度。Preferably, the method for disassembling and sealing the vacuum branch pipes is as follows: after the strength of the concrete floor reaches the design requirements, stop precipitation, then extract the vacuum branch pipes, and use concrete to pour the holes left by the vacuum branch pipes to ensure strength.

一种岩石地基局部浅层超前降水施工装置,包括:岩石层,所述岩石层上端覆盖有粗黄砂层,所述粗黄砂层上端覆盖有土工布层,所述土工布层上端表面浇注有混凝土层;A local shallow advanced dewatering construction device for rock foundations, including: a rock layer, the upper end of the rock layer is covered with a coarse yellow sand layer, the upper end of the coarse yellow sand layer is covered with a geotextile layer, and the upper end surface of the geotextile layer is poured with concrete layer;

施工机构,所述施工机构包括排水管、连接管、滑杆、弧形滑板、弧形支撑板、弹簧和固定组件,所述排水管埋设于粗黄砂层内,所述排水管另一端贯穿混凝土层侧壁并固定连接有连接管,所述排水管与连接管连通,所述排水管上端贯穿滑动连接有多个滑杆,多个所述滑杆下端共同固定连接有弧形滑板,多个所述滑杆上端共同固定连接有弧形支撑板,所述排水管内顶部与弧形滑板上端之间共同固定连接有多个弹簧,所述弧形支撑板侧壁设置有固定组件Construction mechanism, the construction mechanism includes drainage pipes, connecting pipes, sliding rods, arc-shaped slide plates, arc-shaped support plates, springs and fixed components. The drainage pipe is buried in the coarse yellow sand layer, and the other end of the drainage pipe runs through the concrete. The side wall of the layer is fixedly connected with a connecting pipe. The drainage pipe is connected with the connecting pipe. The upper end of the drainage pipe is slidably connected with a plurality of sliding rods. The lower ends of the plurality of sliding rods are jointly fixedly connected with an arc-shaped sliding plate. An arc-shaped support plate is fixedly connected to the upper end of the sliding rod, a plurality of springs are fixedly connected to the inner top of the drainage pipe and the upper end of the arc-shaped slide plate, and a fixing assembly is provided on the side wall of the arc-shaped support plate.

优选地,所述固定组件包括固定连接在弧形支撑板侧壁的连接座,所述连接座侧壁螺纹连接有螺纹杆,所述排水管上端开设有与螺纹杆配合的螺纹槽。Preferably, the fixing assembly includes a connection seat fixedly connected to the side wall of the arc-shaped support plate, a threaded rod is threadedly connected to the side wall of the connection seat, and a threaded groove is provided in the upper end of the drainage pipe to cooperate with the threaded rod.

优选地,所述排水管采用直径为20mm的PPR管制成,所述连接管采用双层密目网缠绕PPR管制成。Preferably, the drainage pipe is made of a PPR pipe with a diameter of 20 mm, and the connecting pipe is made of a double-layer dense mesh wound PPR pipe.

本发明具有以下有益效果:The invention has the following beneficial effects:

1、本方案通过在浇筑垫层前预埋真空降水管,所有的降水管均在垫层以下,对垫层和防水层没有交叉影响,确保了垫层和防水层的连续性和整体性;1. This plan embeds vacuum dewatering pipes before pouring the cushion. All downpipes are below the cushion and have no cross-effect on the cushion and waterproof layer, ensuring the continuity and integrity of the cushion and waterproof layer;

2、超前降水,将局部裂隙水位降至垫层以下,避免了地下水对垫层和防水层施工的影响,确保了垫层及防水层的施工质量,避免了底板施工前防水层的鼓包和上浮;2. Advance precipitation reduces the water level in local fissures below the cushion layer, avoiding the impact of groundwater on the construction of the cushion layer and waterproof layer, ensuring the construction quality of the cushion layer and waterproof layer, and avoiding the bulging and floating of the waterproof layer before floor construction. ;

3、通过设置施工机构,在结束降水后,可以通过向下按动弧形支撑板,使得弧形支撑板与粗黄砂层形成一定的间隙,进而可以将整个排水管抽出,再浇注混凝土封堵,可以有效的避免排水管留存于粗黄砂层内,增加建筑的强度;3. By setting up a construction mechanism, after the precipitation is over, the arc-shaped support plate can be pressed downward to form a certain gap between the arc-shaped support plate and the coarse yellow sand layer, and then the entire drainage pipe can be extracted and concrete can be poured to seal it. , which can effectively prevent drainage pipes from remaining in the coarse yellow sand layer and increase the strength of the building;

4、本方案采用的材料简单易得,施工现场均能够找到,使用起来方便,并且组装简单,一般的工人进行简单组装即可,拆卸简单,结构简单;4. The materials used in this plan are simple and easy to obtain and can be found at the construction site. They are easy to use and simple to assemble. It can be easily assembled by ordinary workers. It is easy to disassemble and has a simple structure;

5、实用性强,所有岩石地基均可以使用,通过自吸泵在支管中和黄砂层中形成负压,大大提升了降水效率,降水效果显著。5. It is highly practical and can be used on all rock foundations. The self-priming pump creates negative pressure in the branch pipes and the yellow sand layer, which greatly improves the precipitation efficiency and the precipitation effect is significant.

附图说明Description of drawings

图1为本发明提出的一种岩石地基局部浅层超前降水施工装置的结构示意图;Figure 1 is a schematic structural diagram of a local shallow advanced dewatering construction device for rock foundation proposed by the present invention;

图2为图1中的A处结构放大示意图;Figure 2 is an enlarged schematic diagram of the structure at point A in Figure 1;

图3为图1中的B处结构放大示意图;Figure 3 is an enlarged schematic diagram of the structure at B in Figure 1;

图4为图1中排水管的结构示意图;Figure 4 is a schematic structural diagram of the drainage pipe in Figure 1;

图5为图1中连接管的立体结构示意图。Figure 5 is a schematic three-dimensional structural diagram of the connecting pipe in Figure 1.

图中:1岩石层、2粗黄砂层、3土工布层、4混凝土层、5排水管、6连接管、7滑杆、8弧形滑板、9弧形支撑板、10弹簧、11连接座、12螺纹杆、13螺纹槽。In the picture: 1 rock layer, 2 coarse yellow sand layer, 3 geotextile layer, 4 concrete layer, 5 drainage pipes, 6 connecting pipes, 7 sliding rods, 8 curved skateboards, 9 curved support plates, 10 springs, 11 connecting seats , 12 threaded rod, 13 threaded groove.

具体实施方式Detailed ways

为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图对本发明的具体实施方式做详细的说明。在下面的描述中阐述了很多具体细节以便于充分理解本发明。但是本发明能够以很多不同于在此描述的其它方式来实施,本领域技术人员可以在不违背本发明内涵的情况下做类似改进,因此本发明不受下面公开的具体实施的限制。In order to make the above objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the invention. However, the present invention can be implemented in many other ways different from those described here. Those skilled in the art can make similar improvements without departing from the connotation of the present invention. Therefore, the present invention is not limited to the specific implementation disclosed below.

需要说明的是,当元件被称为“固定于”另一个元件,它可以直接在另一个元件上或者也可以存在居中的元件。当一个元件被认为是“连接”另一个元件,它可以是直接连接到另一个元件或者可能同时存在居中元件。本文所使用的术语“垂直的”、“水平的”、“左”、“右”以及类似的表述只是为了说明的目的,并不表示是唯一的实施方式。It should be noted that when an element is referred to as being "fixed" to another element, it can be directly on the other element or intervening elements may also be present. When an element is said to be "connected" to another element, it can be directly connected to the other element or there may also be intervening elements present. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and do not represent the only implementation manner.

除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施例的目的,不是旨在于限制本发明。本文所使用的术语“及/或”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the technical field to which the invention belongs. The terminology used herein in the description of the invention is for the purpose of describing specific embodiments only and is not intended to limit the invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.

参照图1-图5,一种岩石地基局部浅层超前降水施工方法,包括以下步骤:确定裂隙水区域、制作PPR真空支管、布置PPR真空管、回填黄砂铺土工布、接水泵抽水、浇筑垫层混凝土、做防水、施工保护层及底板以及拆卸真空支管并封堵;Referring to Figures 1 to 5, a local shallow advance dewatering construction method for rock foundations includes the following steps: determining the fissure water area, making PPR vacuum branch pipes, arranging PPR vacuum pipes, backfilling yellow sand and spreading geotextiles, pumping water, and pouring cushions Concrete, waterproofing, construction of protective layer and floor, and removal and sealing of vacuum branch pipes;

其中,确定裂隙水区域的方法如下:垫层施工前,观察岩石地基裂隙水情况,确定裂隙水存在的区域,白石灰洒出区域范围;Among them, the method of determining the fissure water area is as follows: before cushion construction, observe the fissure water situation in the rock foundation, determine the area where fissure water exists, and the area where white lime spills;

制作PPR真空支管方法如下:由于裂隙水量通常较小,所以选用直径20mm的小直径PPR管,在PPR管的四周纵向每隔10cm开1mm的小孔,同一截面开4个小孔,用双层密目网将PPR管缠绕紧密,一端用专用堵头将PPR管封堵严密,另一端不封堵作为出水端;The method of making a PPR vacuum branch pipe is as follows: Since the amount of water in the fissure is usually small, a small diameter PPR pipe with a diameter of 20mm is used. Small holes of 1mm are opened every 10cm longitudinally around the PPR pipe. Four small holes are opened in the same section. Double-layer Wrap the PPR pipe tightly with dense mesh, use a special plug to seal the PPR pipe tightly at one end, and leave the other end unblocked as the water outlet;

布置PPR真空管方法如下:在确定好的裂隙水区域间隔1m布置PPR真空支管,出水端超出裂隙水区域边界至少50cm,将所有的真空支管出水端用变径接头与50mmPPR主管连接,主管一端用专用堵头封堵,另一端接水泵。The method of arranging PPR vacuum pipes is as follows: arrange PPR vacuum branch pipes at intervals of 1m in the determined fissure water area. The outlet end exceeds the boundary of the fracture water area by at least 50cm. Connect the outlet ends of all vacuum branch pipes to the 50mm PPR main pipe with a reducing joint. One end of the main pipe shall be connected with a special The plug is sealed and the other end is connected to the water pump.

回填黄砂铺土工布方法如下:在裂隙水区域内回填50mm厚含泥量不超3%的中粗黄砂,整平后在黄砂表面覆盖一层土工布。The method of backfilling yellow sand and spreading geotextile is as follows: backfill 50mm thick medium-coarse yellow sand with a mud content of no more than 3% in the fissure water area. After leveling, cover the surface of the yellow sand with a layer of geotextile.

接水泵抽水方法如下:将主管出水端与水泵连接,开启水泵抽水。The method of connecting the water pump to pump water is as follows: Connect the water outlet end of the main pipe to the water pump, and start the water pump to pump water.

浇筑垫层混凝土方法如下:在铺好的土工布上浇筑垫层混凝土,垫层混凝土四周需要超出划定的裂隙水区域至少10cm,确保在开启自吸泵后在黄沙层中形成负压区域。The method of pouring cushion concrete is as follows: pour cushion concrete on the paved geotextile. The surrounding area of the cushion concrete needs to be at least 10cm beyond the designated fissure water area to ensure that a negative pressure area is formed in the yellow sand layer after the self-priming pump is turned on. .

做防水方法如下:垫层混凝土强度强度满足要求后,观察垫层上是否有渗水、潮湿现象,无潮湿后施工防水层。The waterproofing method is as follows: After the strength of the cushion concrete meets the requirements, observe whether there is water seepage or moisture on the cushion. If there is no moisture, construct the waterproof layer.

施工保护层及底板方法如下:防水施工完成后,开始施工防水保护层和底板。The method of constructing the protective layer and base plate is as follows: After the waterproofing construction is completed, start the construction of the waterproof protective layer and base plate.

拆卸真空支管并封堵方法如下:混凝土底板强度达到设计要求后,停止降水,然后将真空支管抽出,并使用混凝土浇注真空支管留下的孔洞,保证强度。The method for dismantling and sealing the vacuum branch pipe is as follows: After the strength of the concrete floor reaches the design requirements, stop precipitation, then extract the vacuum branch pipe, and use concrete to pour the holes left by the vacuum branch pipe to ensure the strength.

一种岩石地基局部浅层超前降水施工装置,包括:岩石层1,岩石层1上端覆盖有粗黄砂层2,粗黄砂层2上端覆盖有土工布层3,土工布层3上端表面浇注有混凝土层4;A local shallow advanced dewatering construction device for rock foundations, including: rock layer 1, the upper end of the rock layer 1 is covered with a coarse yellow sand layer 2, the upper end of the coarse yellow sand layer 2 is covered with a geotextile layer 3, and the upper end surface of the geotextile layer 3 is poured with concrete layer 4;

施工机构,施工机构包括排水管5、连接管6、滑杆7、弧形滑板8、弧形支撑板9、弹簧10和固定组件,排水管5埋设于粗黄砂层2内,排水管5另一端贯穿混凝土层4侧壁并固定连接有连接管6,排水管5与连接管6连通,排水管5上端贯穿滑动连接有多个滑杆7,多个滑杆7下端共同固定连接有弧形滑板8,多个滑杆7上端共同固定连接有弧形支撑板9,排水管5内顶部与弧形滑板8上端之间共同固定连接有多个弹簧10,弧形支撑板9侧壁设置有固定组件。The construction mechanism includes drainage pipe 5, connecting pipe 6, sliding rod 7, arc sliding plate 8, arc support plate 9, spring 10 and fixed components. The drainage pipe 5 is buried in the coarse yellow sand layer 2, and the drainage pipe 5 is another One end penetrates the side wall of the concrete layer 4 and is fixedly connected with a connecting pipe 6. The drainage pipe 5 is connected with the connecting pipe 6. The upper end of the drainage pipe 5 is slidably connected with a plurality of sliding rods 7, and the lower ends of the plurality of sliding rods 7 are jointly fixedly connected with an arc. The upper ends of the sliding plate 8 and the plurality of sliding rods 7 are jointly fixedly connected with an arc-shaped support plate 9. The inner top of the drainage pipe 5 and the upper end of the arc-shaped sliding plate 8 are jointly fixedly connected with a plurality of springs 10. The side walls of the arc-shaped support plate 9 are provided with Fixed components.

固定组件包括固定连接在弧形支撑板9侧壁的连接座11,连接座11侧壁螺纹连接有螺纹杆12,排水管5上端开设有与螺纹杆12配合的螺纹槽13。The fixed assembly includes a connecting seat 11 fixedly connected to the side wall of the arc-shaped support plate 9. The side wall of the connecting seat 11 is threadedly connected with a threaded rod 12. The upper end of the drainage pipe 5 is provided with a threaded groove 13 that matches the threaded rod 12.

排水管5采用直径为20mm的PPR管制成,连接管6采用双层密目网缠绕PPR管制成。The drainage pipe 5 is made of a PPR pipe with a diameter of 20 mm, and the connecting pipe 6 is made of a double-layer dense mesh wound PPR pipe.

本发明中,首先确定裂隙水区域,垫层施工前,观察岩石地基裂隙水情况,确定裂隙水存在的区域,白石灰洒出区域范围,接着制作排水管5和连接管6,由于裂隙水量通常较小,所以排水管5选用直径20mm的小直径PPR管,在PPR管的四周纵向每隔10cm开1mm的小孔,同一截面开4个小孔,连接管6则用双层密目网将PPR管缠绕紧密,一端用专用堵头将PPR管封堵严密,另一端不封堵作为出水端。In the present invention, the fissure water area is first determined. Before cushion construction, the fissure water situation in the rock foundation is observed to determine the area where fissure water exists and the white lime spilled area. Then the drainage pipe 5 and the connecting pipe 6 are made. Since the amount of fissure water is usually Small, so the drainage pipe 5 uses a small diameter PPR pipe with a diameter of 20mm. Small holes of 1mm are opened longitudinally every 10cm around the PPR pipe. Four small holes are opened in the same section. The connecting pipe 6 is connected with a double-layer dense mesh. The PPR pipe is tightly wound. One end of the PPR pipe is tightly sealed with a special plug, and the other end is left unblocked as the water outlet.

布置排水管5和连接管6,在确定好的裂隙水区域间隔1m布置排水管5,出水端超出裂隙水区域边界至少50cm,将所有的排水管5出水端用变径接头与50mm连接管6连接,连接管6一端用专用堵头封堵,另一端接水泵。Arrange drainage pipes 5 and connecting pipes 6. Arrange drainage pipes 5 at intervals of 1m in the determined fissure water area. The outlet end exceeds the boundary of the fissure water area by at least 50cm. Connect the outlet ends of all drainage pipes 5 with reducing joints and 50mm connecting pipes 6. Connect, one end of the connecting pipe 6 is blocked with a special plug, and the other end is connected to the water pump.

接着回填粗黄砂层2,在裂隙水区域内回填50mm厚含泥量不超3%的中粗黄砂,整平后在粗黄砂层2表面覆盖一层土工布,形成土工布层3,然后将连接管6出水端与水泵连接,开启水泵抽水。Then backfill the coarse yellow sand layer 2, and backfill 50mm thick medium-coarse yellow sand with a mud content of no more than 3% in the fissure water area. After leveling, cover the surface of the coarse yellow sand layer 2 with a layer of geotextile to form a geotextile layer 3. The water outlet end of the connecting pipe 6 is connected to the water pump, and the water pump is turned on to pump water.

浇筑混凝土层4,在铺好的土工布层3上浇筑垫层混凝土,混凝土层4四周需要超出划定的裂隙水区域至少10cm,确保在开启自吸泵后在粗黄砂层2中形成负压区域,混凝土层4强度满足要求后,观察垫层上是否有渗水、潮湿现象,无潮湿后施工防水层,防水施工完成后,开始施工防水保护层和底板。Pour concrete layer 4 and pour cushion concrete on the paved geotextile layer 3. The surrounding area of concrete layer 4 needs to be at least 10cm beyond the designated fissure water area to ensure that a negative pressure is formed in the coarse yellow sand layer 2 after the self-priming pump is turned on. Area, after the strength of concrete layer 4 meets the requirements, observe whether there is water seepage or moisture on the cushion layer. If there is no moisture, construct the waterproof layer. After the waterproof construction is completed, start the construction of the waterproof protective layer and bottom plate.

混凝土底板强度达到设计要求后,停止降水,然后将向下按动弧形支撑板9,使得弧形支撑板9与粗黄砂层2之间形成空隙,然后将螺纹杆12转入到螺纹槽13中,对弧形支撑板9的位置进行固定,然后便可以将排水管5从粗黄砂层2中抽出,并使用混凝土浇注排水管5留下的孔洞,保证垫层的强度。After the strength of the concrete floor reaches the design requirements, stop dewatering, then press the arc-shaped support plate 9 downward to form a gap between the arc-shaped support plate 9 and the coarse yellow sand layer 2, and then turn the threaded rod 12 into the threaded groove 13 , the position of the arc-shaped support plate 9 is fixed, and then the drainage pipe 5 can be extracted from the coarse yellow sand layer 2, and the holes left by the drainage pipe 5 can be poured with concrete to ensure the strength of the cushion.

以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。The above are only preferred specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any person familiar with the technical field can, within the technical scope disclosed in the present invention, implement the technical solutions of the present invention. Equivalent substitutions or changes of the inventive concept thereof shall be included in the protection scope of the present invention.

Claims (10)

1.一种岩石地基局部浅层超前降水施工方法,其特征在于,包括以下步骤:确定裂隙水区域、制作PPR真空支管、布置PPR真空管、回填黄砂铺土工布、接水泵抽水、浇筑垫层混凝土、做防水、施工保护层及底板以及拆卸真空支管并封堵;1. A local shallow advanced dewatering construction method for rock foundations, which is characterized by including the following steps: determining the fissure water area, making PPR vacuum branch pipes, arranging PPR vacuum pipes, backfilling yellow sand and laying geotextiles, pumping water with water pumps, and pouring cushion concrete , make waterproofing, construct protective layer and base plate, and disassemble and seal the vacuum branch pipe; 其中,确定裂隙水区域的方法如下:垫层施工前,观察岩石地基裂隙水情况,确定裂隙水存在的区域,白石灰洒出区域范围;Among them, the method of determining the fissure water area is as follows: before cushion construction, observe the fissure water situation in the rock foundation, determine the area where fissure water exists, and the area where white lime spills; 制作PPR真空支管方法如下:由于裂隙水量通常较小,所以选用直径20mm的小直径PPR管,在PPR管的四周纵向每隔10cm开1mm的小孔,同一截面开4个小孔,用双层密目网将PPR管缠绕紧密,一端用专用堵头将PPR管封堵严密,另一端不封堵作为出水端;The method of making a PPR vacuum branch pipe is as follows: Since the amount of water in the fissure is usually small, a small diameter PPR pipe with a diameter of 20mm is used. Small holes of 1mm are opened every 10cm longitudinally around the PPR pipe. Four small holes are opened in the same section. Double-layer Wrap the PPR pipe tightly with dense mesh, use a special plug to seal the PPR pipe tightly at one end, and leave the other end unblocked as the water outlet; 布置PPR真空管方法如下:在确定好的裂隙水区域间隔1m布置PPR真空支管,出水端超出裂隙水区域边界至少50cm,将所有的真空支管出水端用变径接头与50mmPPR主管连接,主管一端用专用堵头封堵,另一端接水泵。The method of arranging PPR vacuum pipes is as follows: arrange PPR vacuum branch pipes at intervals of 1m in the determined fissure water area. The outlet end exceeds the boundary of the fracture water area by at least 50cm. Connect the outlet ends of all vacuum branch pipes to the 50mm PPR main pipe with a reducing joint. One end of the main pipe shall be connected with a special The plug is sealed and the other end is connected to the water pump. 2.根据权利要求1所述的一种岩石地基局部浅层超前降水施工方法,其特征在于,回填黄砂铺土工布方法如下:2. A construction method for advanced dewatering of local shallow layers of rock foundation according to claim 1, characterized in that the method of backfilling yellow sand and paving geotextile is as follows: 在裂隙水区域内回填50mm厚含泥量不超3%的中粗黄砂,整平后在黄砂表面覆盖一层土工布。Backfill the fissure water area with 50mm thick medium-coarse yellow sand with a mud content of no more than 3%. After leveling, cover the surface of the yellow sand with a layer of geotextile. 3.根据权利要求2所述的一种岩石地基局部浅层超前降水施工方法,其特征在于,接水泵抽水方法如下:3. A construction method for advanced dewatering of local shallow layers of rock foundations according to claim 2, characterized in that the water pumping method is as follows: 将主管出水端与水泵连接,开启水泵抽水。Connect the water outlet end of the main pipe to the water pump and start the water pump to pump water. 4.根据权利要求3所述的一种岩石地基局部浅层超前降水施工方法,其特征在于,浇筑垫层混凝土方法如下:4. A construction method for local shallow advanced dewatering of rock foundations according to claim 3, characterized in that the method for pouring cushion concrete is as follows: 在铺好的土工布上浇筑垫层混凝土,垫层混凝土四周需要超出划定的裂隙水区域至少10cm,确保在开启自吸泵后在黄沙层中形成负压区域。Pour cushion concrete on the paved geotextile. The surrounding areas of the cushion concrete need to be at least 10cm beyond the designated fissure water area to ensure that a negative pressure area is formed in the yellow sand layer after the self-priming pump is turned on. 5.根据权利要求4所述的一种岩石地基局部浅层超前降水施工方法,其特征在于,做防水方法如下:5. A construction method for advance dewatering of local shallow layers of rock foundation according to claim 4, characterized in that the waterproofing method is as follows: 垫层混凝土强度强度满足要求后,观察垫层上是否有渗水、潮湿现象,无潮湿后施工防水层。After the strength of the cushion concrete meets the requirements, observe whether there is water seepage or moisture on the cushion. If there is no moisture, construct a waterproof layer. 6.根据权利要求5所述的一种岩石地基局部浅层超前降水施工方法,其特征在于,施工保护层及底板方法如下:6. A construction method for advance dewatering of local shallow layers of rock foundation according to claim 5, characterized in that the method of constructing the protective layer and bottom plate is as follows: 防水施工完成后,开始施工防水保护层和底板。After the waterproofing construction is completed, the construction of the waterproof protective layer and base plate begins. 7.根据权利要求6所述的一种岩石地基局部浅层超前降水施工方法,其特征在于,拆卸真空支管并封堵方法如下:7. A construction method for local shallow advanced dewatering of rock foundations according to claim 6, characterized in that the method of disassembling and blocking the vacuum branch pipes is as follows: 混凝土底板强度达到设计要求后,停止降水,然后将真空支管抽出,并使用混凝土浇注真空支管留下的孔洞,保证强度。After the strength of the concrete base plate reaches the design requirements, the precipitation is stopped, the vacuum branch pipe is then extracted, and the holes left by the vacuum branch pipe are poured with concrete to ensure the strength. 8.根据权利要求1-7任意一项所述的一种岩石地基局部浅层超前降水施工装置,其特征在于,包括:8. A local shallow advance dewatering construction device for rock foundations according to any one of claims 1 to 7, characterized in that it includes: 岩石层(1),所述岩石层(1)上端覆盖有粗黄砂层(2),所述粗黄砂层(2)上端覆盖有土工布层(3),所述土工布层(3)上端表面浇注有混凝土层(4);Rock layer (1), the upper end of the rock layer (1) is covered with a coarse yellow sand layer (2), the upper end of the coarse yellow sand layer (2) is covered with a geotextile layer (3), the upper end of the geotextile layer (3) A concrete layer (4) is poured on the surface; 施工机构,所述施工机构包括排水管(5)、连接管(6)、滑杆(7)、弧形滑板(8)、弧形支撑板(9)、弹簧(10)和固定组件,所述排水管(5)埋设于粗黄砂层(2)内,所述排水管(5)另一端贯穿混凝土层(4)侧壁并固定连接有连接管(6),所述排水管(5)与连接管(6)连通,所述排水管(5)上端贯穿滑动连接有多个滑杆(7),多个所述滑杆(7)下端共同固定连接有弧形滑板(8),多个所述滑杆(7)上端共同固定连接有弧形支撑板(9),所述排水管(5)内顶部与弧形滑板(8)上端之间共同固定连接有多个弹簧(10),所述弧形支撑板(9)侧壁设置有固定组件。Construction mechanism, the construction mechanism includes a drainage pipe (5), a connecting pipe (6), a sliding rod (7), an arc-shaped sliding plate (8), an arc-shaped support plate (9), a spring (10) and a fixed component. The drainage pipe (5) is buried in the coarse yellow sand layer (2). The other end of the drainage pipe (5) penetrates the side wall of the concrete layer (4) and is fixedly connected with a connecting pipe (6). The drainage pipe (5) Communicated with the connecting pipe (6), the upper end of the drainage pipe (5) is slidably connected with a plurality of sliding rods (7), and the lower ends of the plurality of sliding rods (7) are jointly fixedly connected with an arc-shaped sliding plate (8). The upper ends of each of the sliding rods (7) are jointly fixedly connected with an arc-shaped support plate (9), and the inner top of the drainage pipe (5) and the upper end of the arc-shaped sliding plate (8) are jointly fixedly connected with a plurality of springs (10). , the side wall of the arc-shaped support plate (9) is provided with a fixing component. 9.根据权利要求8所述的一种岩石地基局部浅层超前降水施工装置,其特征在于,其中:9. A construction device for advanced dewatering of local shallow layers of rock foundation according to claim 8, characterized in that: 所述固定组件包括固定连接在弧形支撑板(9)侧壁的连接座(11),所述连接座(11)侧壁螺纹连接有螺纹杆(12),所述排水管(5)上端开设有与螺纹杆(12)配合的螺纹槽(13)。The fixed component includes a connection seat (11) fixedly connected to the side wall of the arc-shaped support plate (9). The side wall of the connection seat (11) is threaded with a threaded rod (12). The upper end of the drainage pipe (5) A threaded groove (13) matching the threaded rod (12) is provided. 10.根据权利要求9所述的一种岩石地基局部浅层超前降水施工装置,其特征在于,其中:10. A construction device for advanced dewatering of local shallow layers of rock foundation according to claim 9, characterized in that: 所述排水管(5)采用直径为20mm的PPR管制成,所述连接管(6)采用双层密目网缠绕PPR管制成。The drainage pipe (5) is made of a PPR pipe with a diameter of 20 mm, and the connecting pipe (6) is made of a PPR pipe wound with double-layer dense mesh.
CN202310823541.3A 2023-07-06 2023-07-06 A construction method for local shallow advance precipitation of rock foundation Active CN116770876B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310823541.3A CN116770876B (en) 2023-07-06 2023-07-06 A construction method for local shallow advance precipitation of rock foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310823541.3A CN116770876B (en) 2023-07-06 2023-07-06 A construction method for local shallow advance precipitation of rock foundation

Publications (2)

Publication Number Publication Date
CN116770876A true CN116770876A (en) 2023-09-19
CN116770876B CN116770876B (en) 2025-04-15

Family

ID=87989470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310823541.3A Active CN116770876B (en) 2023-07-06 2023-07-06 A construction method for local shallow advance precipitation of rock foundation

Country Status (1)

Country Link
CN (1) CN116770876B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104314090A (en) * 2014-08-29 2015-01-28 中铁八局集团建筑工程有限公司 Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof
CN105484288A (en) * 2015-06-12 2016-04-13 中铁隧道勘测设计院有限公司 Bottom plate structure with rock foundation, of underground structure
CN113089681A (en) * 2021-04-23 2021-07-09 中建八局第一建设有限公司 Waterproof invasion structure of deep foundation pit base concrete cushion layer and construction method
CN214038920U (en) * 2020-12-16 2021-08-24 杭州虹华环保科技有限公司 Fixing structure for energy-saving drain pipe of air conditioner
CN217204180U (en) * 2022-05-12 2022-08-16 中铁隧道集团三处有限公司 Weathered rock stratum fracture water blind ditch drainage system
CN115419094A (en) * 2022-10-13 2022-12-02 中建八局发展建设有限公司 Dewatering construction method for deep foundation pit without dewatering well

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104314090A (en) * 2014-08-29 2015-01-28 中铁八局集团建筑工程有限公司 Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof
CN105484288A (en) * 2015-06-12 2016-04-13 中铁隧道勘测设计院有限公司 Bottom plate structure with rock foundation, of underground structure
CN214038920U (en) * 2020-12-16 2021-08-24 杭州虹华环保科技有限公司 Fixing structure for energy-saving drain pipe of air conditioner
CN113089681A (en) * 2021-04-23 2021-07-09 中建八局第一建设有限公司 Waterproof invasion structure of deep foundation pit base concrete cushion layer and construction method
CN217204180U (en) * 2022-05-12 2022-08-16 中铁隧道集团三处有限公司 Weathered rock stratum fracture water blind ditch drainage system
CN115419094A (en) * 2022-10-13 2022-12-02 中建八局发展建设有限公司 Dewatering construction method for deep foundation pit without dewatering well

Also Published As

Publication number Publication date
CN116770876B (en) 2025-04-15

Similar Documents

Publication Publication Date Title
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN108457249B (en) Structural design and construction method of a composite face sand-gravel dam
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN204530732U (en) A kind of structure of the precipitation based on basement elevator shaft plash
CN102995599A (en) Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal
CN103147614B (en) Pool with multi-layer structure and building method thereof
CN112281882A (en) Method for treating water and sand gushing from substrate
CN111236284A (en) A method and structure for groundwater drainage at the bottom of a basement and surrounding areas
CN103741715A (en) Novel waterproof hydrophobic construction method for basement
CN108487331B (en) An underground structure anti-floating system integrating corridor drainage and fertilizer tank anti-seepage
CN103967015B (en) A kind of water seal for deep foundation pit excavation method and structure thereof
CN115012452A (en) Post-casting belt construction technology and basement drainage and pressure relief structure
CN204059380U (en) Deep-well precipitation well head well-sealing device in underground garage foundation ditch
CN114439027A (en) Construction method of concrete building foundation on deep and strong permeable foundation of hydropower project
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN206289732U (en) A kind of active antiseepage basement shear wall
CN205907658U (en) Be used for anti - structure that seeps water of concrete -faced rockfill dam construction time dam body
CN209816896U (en) Collapsible loess area utility tunnel foundation structure
CN202755438U (en) Integrative structure with functions of anchoring, drainage and flood interception in refuse landfill
CN117107792A (en) Combined drainage slope protection system for deep-excavation square expansion soil canal slope and integrated construction method
CN206477347U (en) The water storage structure of basement
CN116770876A (en) Rock foundation local shallow layer advanced precipitation construction method
CN113463673B (en) High vacuum system combined densification method foundation treatment method and device
CN211312560U (en) Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant