[go: up one dir, main page]

CN116290064A - Bridge ultra-deep foundation reinforcement structure and construction method thereof - Google Patents

Bridge ultra-deep foundation reinforcement structure and construction method thereof Download PDF

Info

Publication number
CN116290064A
CN116290064A CN202310149333.XA CN202310149333A CN116290064A CN 116290064 A CN116290064 A CN 116290064A CN 202310149333 A CN202310149333 A CN 202310149333A CN 116290064 A CN116290064 A CN 116290064A
Authority
CN
China
Prior art keywords
reinforcement
nozzle
area
pressure
diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310149333.XA
Other languages
Chinese (zh)
Other versions
CN116290064B (en
Inventor
南进江
刘钊
朱晓亮
李志忠
何思元
唐政
方升
张京海
马千里
陈�峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202310149333.XA priority Critical patent/CN116290064B/en
Priority claimed from CN202310149333.XA external-priority patent/CN116290064B/en
Publication of CN116290064A publication Critical patent/CN116290064A/en
Application granted granted Critical
Publication of CN116290064B publication Critical patent/CN116290064B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本申请公开了一种桥梁超深地基加固结构及其施工方法,包括墙壁加固区以及设置在墙壁加固区内部的中心加固区,中心加固区包括第一加固区和/或第二加固区,第一加固区包括阵列设置的多个第一加固体,相邻两第一加固体相切设置;第二加固区包括阵列设置的多个第二加固体,相邻两第二加固体存在部分交叠;每一第一加固体为一次加固成型,每一第二加固体均为一次加固成型;在中心加固区包括第一加固区和第二加固区时,第一加固区和第二加固区层叠设置,第一加固区设置在第二加固区的上层,第一加固体和对应位置处的第二加固体的轴线重合,且第一加固体和第二加固体同轴施工且一次加固成型。

Figure 202310149333

The application discloses a bridge ultra-deep foundation reinforcement structure and its construction method, including a wall reinforcement area and a central reinforcement area arranged inside the wall reinforcement area, the central reinforcement area includes the first reinforcement area and/or the second reinforcement area, No. A reinforcement area includes a plurality of first reinforcements arranged in an array, and two adjacent first reinforcements are arranged tangentially; a second reinforcement area includes a plurality of second reinforcements arranged in an array, and there is a partial intersection between two adjacent second reinforcements. stack; each first reinforcement body is a reinforcement molding, and each second reinforcement body is a reinforcement molding; when the central reinforcement area includes the first reinforcement area and the second reinforcement area, the first reinforcement area and the second reinforcement area Layered arrangement, the first reinforcement area is set on the upper layer of the second reinforcement area, the axis of the first reinforcement body and the second reinforcement body at the corresponding position coincide, and the first reinforcement body and the second reinforcement body are coaxially constructed and reinforced at one time .

Figure 202310149333

Description

一种桥梁超深地基加固结构及其施工方法A bridge ultra-deep foundation reinforcement structure and its construction method

技术领域technical field

本申请一般涉及建设工程技术领域,具体涉及一种桥梁超深地基加固结构及其施工方法。The application generally relates to the technical field of construction engineering, and specifically relates to a super-deep foundation reinforcement structure of a bridge and a construction method thereof.

背景技术Background technique

锚碇位于冲积江心岛,工程场区基岩埋深超过100m,软弱覆盖层厚度超过50m,主要以粉质黏土为主,强度和地基摩擦系数低,塑性差,压缩性高,不存在满足传统地连墙要求的持力层。靠近基坑底部的砂层均为强透水性和承压含水层,承压水的水头高,基底不存在天然隔水层,基坑开始施工期间,锚碇基础作为基坑主要的锚固作用,其底部的抗滑移要求高,然而现有技术中的施工期基坑底部不仅仅是风险高,基本上是无法施工,如何解决基坑施工过程坑底的隔水、承载力和抗滑移等问题是关键。The anchorage is located on the alluvial river center island. The bedrock in the project site is buried deeper than 100m, and the soft covering layer is more than 50m thick. Bearing layer traditionally required for connecting walls. The sand layer near the bottom of the foundation pit is a highly permeable and confined aquifer. The water head of the confined water is high, and there is no natural water-resisting layer at the base. The anti-slip requirements at the bottom are high. However, the bottom of the foundation pit in the prior art is not only risky during the construction period, it is basically impossible to construct. How to solve the water resistance, bearing capacity and anti-slip of the bottom of the foundation pit during the construction process And so on is the key.

发明内容Contents of the invention

鉴于现有技术中的上述缺陷或不足,期望提供一种桥梁超深地基加固结构及其施工方法,可以提高桥梁地基加固结构的强度、摩擦性、抗渗性。In view of the above-mentioned defects or deficiencies in the prior art, it is desired to provide a bridge ultra-deep foundation reinforcement structure and its construction method, which can improve the strength, friction, and impermeability of the bridge foundation reinforcement structure.

第一方面,本申请提供了一种桥梁地基加固结构,包括墙壁加固区以及设置在墙壁加固区内部的中心加固区,所述中心加固区包括第一加固区和/或第二加固区,所述第一加固区包括阵列设置的多个第一加固体,相邻两第一加固体相切设置;所述第二加固区包括阵列设置的多个第二加固体,相邻两第二加固体存在部分交叠;每一所述第一加固体为一次加固成型,每一所述第二加固体均为一次加固成型;In a first aspect, the present application provides a bridge foundation reinforcement structure, including a wall reinforcement area and a central reinforcement area arranged inside the wall reinforcement area, the central reinforcement area includes a first reinforcement area and/or a second reinforcement area, so The first reinforcement area includes a plurality of first reinforcements arranged in an array, and two adjacent first reinforcements are arranged tangentially; the second reinforcement area includes a plurality of second reinforcements arranged in an array, and two adjacent second reinforcements Partial overlap of solids exists; each of the first reinforcements is formed by one reinforcement, and each of the second reinforcements is formed by one reinforcement;

在所述中心加固区包括所述第一加固区和所述第二加固区时,所述第一加固区和所述第二加固区层叠设置,所述第一加固区设置在所述第二加固区的上层,所述第一加固体和对应位置处的所述第二加固体的轴线重合,且所述第一加固体和所述第二加固体同轴施工且一次加固成型。When the central reinforced area includes the first reinforced area and the second reinforced area, the first reinforced area and the second reinforced area are stacked, and the first reinforced area is arranged on the second reinforced area. In the upper layer of the reinforcement area, the axis of the first reinforcement body and the second reinforcement body at the corresponding position are coincident, and the first reinforcement body and the second reinforcement body are coaxially constructed and reinforced at one time.

可选地,所述墙壁加固区包括与所述第一加固体同层设置的第一边缘加固体以及与所述第二加固体同层设置的第二边缘加固体,相邻两第二边缘加固体存在部分交叠;所述第一边缘加固体和对应位置处的所述第二边缘加固体的轴线重合。Optionally, the wall reinforcement area includes a first edge reinforcement disposed on the same layer as the first reinforcement and a second edge reinforcement disposed on the same layer as the second reinforcement, and two adjacent second edges There is a partial overlap of the reinforcements; the axes of the first edge reinforcement and the second edge reinforcement at the corresponding positions are coincident.

可选地,所述第一加固体的高度大于所述第二加固体的高度,所述第一加固体的直径小于所述第二加固体的直径,所述第一边缘加固体和所述第一加固体的直径相同,所述第二边缘加固体和所述第二加固体的直径相同;相邻两所述第一边缘加固体的中心距小于所述相邻两所述第一加固体的中心距,相邻两所述第二边缘加固体的中心距小于所述相邻两所述第二加固体的中心距。Optionally, the height of the first reinforcement is greater than the height of the second reinforcement, the diameter of the first reinforcement is smaller than the diameter of the second reinforcement, and the first edge reinforcement and the The diameter of the first reinforcement is the same, the diameter of the second edge reinforcement is the same as that of the second reinforcement; the center distance between two adjacent first edge reinforcements is smaller than that of the adjacent two first reinforcements The center-to-center distance of the solids is smaller than the center-to-center distance between two adjacent second edge reinforcements.

可选地,所述第一加固体的高度为20m~27m、直径为1.5m~2m;Optionally, the first reinforcing body has a height of 20m-27m and a diameter of 1.5m-2m;

所述第二加固体的高度为4m~8m、直径为2.4m~3m;The second reinforcing body has a height of 4m-8m and a diameter of 2.4m-3m;

所述第一加固体的底面深度为40m~51m;The depth of the bottom surface of the first reinforcement is 40m-51m;

所述第二加固体的底面深度为48m~55m。The depth of the bottom surface of the second reinforcement is 48m-55m.

第二方面,本申请提供了一种桥梁地基加固结构的施工方法,用于成型如以上任一所述的桥梁地基加固结构,采用旋喷钻杆进行施工,所述旋喷钻杆包括上下设置的第一喷嘴和第二喷嘴,所述第一喷嘴用于喷射高压水与高压空气,所述第二喷嘴用于喷射高压硬化材料;所述方法包括:In the second aspect, the present application provides a construction method for a bridge foundation reinforcement structure, which is used to form a bridge foundation reinforcement structure as described above, and is constructed by using rotary jet drilling rods, and the rotary jet drilling rods include vertically arranged A first nozzle and a second nozzle, the first nozzle is used to spray high-pressure water and high-pressure air, and the second nozzle is used to spray high-pressure hardening material; the method includes:

在第一加固体和/或第二加固体的轴线位置处形成引孔;forming guide holes at the axial positions of the first reinforcement and/or the second reinforcement;

通过旋喷钻杆伸入所述引孔内通过旋喷硬化形成阵列设置的多个第一加固体和/或多个第二加固体;forming a plurality of first reinforcements and/or a plurality of second reinforcements arranged in an array through rotary spraying drill rods inserted into the guide hole and hardened by rotary spraying;

在所述中心加固区包括所述第一加固区和所述第二加固区时,通过同一所述旋喷钻杆伸入同一所述引孔内进行同轴施工,通过旋喷硬化的方式一次加固成型所述第一加固体和所述第二加固体;When the central reinforcement area includes the first reinforcement area and the second reinforcement area, the same rotary spraying drill pipe is inserted into the same guide hole for coaxial construction, and the rotary spraying hardening is performed once Reinforcing the first reinforcement body and the second reinforcement body;

其中,所述旋喷硬化的方式具体包括:Wherein, the manner of said rotary spray hardening specifically includes:

通过第一喷嘴旋转喷射高压水与高压空气对土体进行预切削,以扩大桩体并形成水与原生土的水泥浆;Pre-cutting the soil body by spraying high-pressure water and high-pressure air through the first nozzle to expand the pile body and form a cement slurry of water and native soil;

通过第二喷嘴旋转喷射高压硬化材料对土体二次切削,以再次扩大桩体并形成硬化材料与水泥浆的加固体浆料。The second nozzle rotates and sprays the high-pressure hardening material to cut the soil twice, so as to expand the pile body again and form a solid slurry of hardening material and cement slurry.

可选地,在形成所述引孔之前,所述方法还包括:Optionally, before forming the introduction hole, the method further includes:

在对应每一所述引孔位置的场地上埋设一定深度的钢护筒,并对应每一引孔位置处开设用于收集所述水泥浆和所述加固体浆料的收集坑。A steel casing of a certain depth is buried on the site corresponding to each of the introduction holes, and a collection pit for collecting the cement slurry and the reinforcement slurry is opened at each of the introduction hole locations.

可选地,所述引孔的直径为40cm~65cm;所述旋喷钻杆的直径为10cm~20cm;所述引孔与所述旋喷钻杆之间形成返浆通道的间距为15cm~20cm;Optionally, the diameter of the introduction hole is 40cm-65cm; the diameter of the jet-jet drill pipe is 10cm-20cm; 20cm;

所述形成引孔的方法包括:The method for forming a hole includes:

通过钻头辅以泥浆护壁进行钻孔;Drilling through the drill bit supplemented by mud retaining walls;

每间隔固定高度进行一次垂直度测量,保证所述引孔的垂直度偏差≤1/300。Perpendicularity measurement is performed at intervals of fixed heights to ensure that the verticality deviation of the pilot hole is ≤1/300.

可选地,所述第一喷嘴靠近地基上表面,所述第二喷嘴远离地基上表面,所述第一喷嘴和所述第二喷嘴设置在所述旋喷钻杆的相对侧,第一喷嘴预切削形成桩体的直径小于所述第二喷嘴二次切削形成桩体的直径;Optionally, the first nozzle is close to the upper surface of the foundation, the second nozzle is away from the upper surface of the foundation, the first nozzle and the second nozzle are arranged on opposite sides of the rotary jet drill pipe, and the first nozzle The diameter of the pile body formed by pre-cutting is smaller than the diameter of the pile body formed by secondary cutting of the second nozzle;

所述旋喷硬化的操作方式包括:所述旋喷钻杆采用边旋转喷射边提升的方式,自所述引孔的底部向上,在所述第一喷嘴旋转喷射一定高度后再开启第二喷嘴进行选择喷射。The operation mode of the rotary spray hardening includes: the rotary spray drill rod adopts the method of lifting while rotating and spraying, from the bottom of the guide hole upwards, and then opens the second nozzle after the first nozzle rotates and sprays to a certain height Perform selective injection.

可选地,所述旋喷钻杆上所述第一喷嘴与所述第二喷嘴的间距为1.2m~1.4m;Optionally, the distance between the first nozzle and the second nozzle on the jet-jet drill pipe is 1.2m-1.4m;

在形成所述第二加固体时,所述第一喷嘴的高压水的压力为35MPa~45MPa、流量为180L/min~220L/min;高压空气的压力为1.05MPa~1.75MPa、流量为5.0Nm3/min~6.5Nm3/min;所述第二喷嘴的高压硬化材料的压力为40MPa~45MPa,流量为120L/min~155L/min;所述第一喷嘴的喷射半径为第二加固体半径的85%~90%;所述第二喷嘴的喷射半径为所述第二加固体半径的10%~15%;When forming the second reinforced body, the pressure of the high-pressure water in the first nozzle is 35MPa-45MPa, and the flow rate is 180L/min-220L/min; the pressure of the high-pressure air is 1.05MPa-1.75MPa, and the flow rate is 5.0Nm 3 /min~6.5Nm 3 /min; the pressure of the high pressure hardening material of the second nozzle is 40MPa~45MPa, the flow rate is 120L/min~155L/min; the spray radius of the first nozzle is the radius of the second reinforced body 85%-90% of that; the spray radius of the second nozzle is 10%-15% of the radius of the second reinforcement;

在形成所述第一加固体时,所述第一喷嘴的高压水的压力为25MPa~37MPa、流量为150L/min~200L/min;高压空气的压力为0.75MPa~1.25MPa、流量为4.5Nm3/min~5.5Nm3/min;所述第二喷嘴的高压硬化材料的压力为37MPa~42MPa;所述第一喷嘴的喷射半径为第一加固体半径的85%~90%;所述第二喷嘴的喷射半径为所述第一加固体半径的10%~15%。When forming the first reinforced body, the pressure of the high-pressure water in the first nozzle is 25MPa-37MPa, and the flow rate is 150L/min-200L/min; the pressure of the high-pressure air is 0.75MPa-1.25MPa, and the flow rate is 4.5Nm 3 /min~5.5Nm 3 /min; the pressure of the high-pressure hardening material of the second nozzle is 37MPa~42MPa; the spray radius of the first nozzle is 85%~90% of the radius of the first reinforcement; The spraying radius of the second nozzle is 10%-15% of the radius of the first reinforcing body.

可选地,对应位置处的所述第一加固体和所述第二加固体通过同一旋喷钻杆通过两次旋喷硬化的方式形成;Optionally, the first reinforcement body and the second reinforcement body at the corresponding positions are formed by two times of jet-spray hardening through the same jet-jet drill pipe;

所述方法还包括:The method also includes:

除所述旋喷杆旋喷钻杆,待所述加固浆料初凝后,在所述引孔内再次注浆形成二次填充。In addition to the jet-jet drill pipe, after the initial setting of the reinforcement slurry, grouting is performed again in the guide hole to form secondary filling.

本申请的实施例提供的技术方案可以包括以下有益效果:The technical solutions provided by the embodiments of the present application may include the following beneficial effects:

本申请实施例提供的桥梁超深地基加固结构,适用于桥梁超深地基,通过双层加固体的设置可以形成达到地基加固目的,形成具有超高加固强度、摩擦系数满足要求且渗透系数小的“人工隔水层”,从而满足锚碇地连墙基础对持力层、摩擦层和封水层的需要。The bridge ultra-deep foundation reinforcement structure provided by the embodiment of the present application is suitable for bridge ultra-deep foundations. The purpose of foundation reinforcement can be achieved through the setting of double-layer reinforcements, forming a structure with ultra-high reinforcement strength, friction coefficient that meets the requirements, and low permeability coefficient. "Artificial water-resisting layer", so as to meet the needs of the anchorage ground and wall foundation for the bearing layer, friction layer and water sealing layer.

附图说明Description of drawings

通过阅读参照以下附图所作的对非限制性实施例所作的详细描述,本申请的其它特征、目的和优点将会变得更明显:Other characteristics, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

图1为本申请的实施例提供的一种加固结构的结构示意图;Fig. 1 is a structural schematic diagram of a reinforcement structure provided by an embodiment of the present application;

图2为本申请的实施例提供的一种加固结构的截面示意图;Fig. 2 is a schematic cross-sectional view of a reinforcement structure provided by an embodiment of the present application;

图3为本申请的实施例提供的一种加固结构的布置示意图;Fig. 3 is a schematic layout diagram of a reinforcing structure provided by the embodiment of the present application;

图4为本申请的实施例提供的一种第一加固区的布置示意图;Fig. 4 is a schematic layout diagram of a first reinforcement zone provided by the embodiment of the present application;

图5为本申请的实施例提供的一种第二加固区的布置示意图;Fig. 5 is a schematic layout diagram of a second reinforcement area provided by the embodiment of the present application;

图6为本申请的实施例提供的一种加固结构施工位置的结构示意图;Fig. 6 is a structural schematic diagram of a reinforcement structure construction position provided by an embodiment of the present application;

图7-10为本申请的实施例提供的一种旋喷硬化的施工示意图;Figure 7-10 is a construction schematic diagram of a rotary spray hardening provided by the embodiment of the present application;

图11为本申请的实施例提供的一种引孔位置桩间土的示意图;Fig. 11 is a schematic diagram of the soil between the piles at the position of the pilot hole provided by the embodiment of the present application;

图12为本申请的实施例提供的一种旋喷钻杆的排浆示意图;Fig. 12 is a schematic diagram of a slurry discharge of a rotary jet drill pipe provided by an embodiment of the present application;

图13为本申请的实施例提供的一种旋喷钻杆的排浆示意图。Fig. 13 is a schematic diagram of a slurry discharge of a rotary jet drill pipe provided in an embodiment of the present application.

图中,In the figure,

100、墙壁加固区;200、中心加固区;300、地连墙底;400、外壁;100, wall reinforcement area; 200, central reinforcement area; 300, ground connection wall bottom; 400, outer wall;

110、第一加固体;120、第二加固体;130、第一边缘加固体;140、第二边缘加固体;110. First reinforcement; 120. Second reinforcement; 130. First edge reinforcement; 140. Second edge reinforcement;

D1、第一加固区;D2、第二加固区;I、第一深区;II、第二深区;III、第三深区;D1, the first reinforcement zone; D2, the second reinforcement zone; I, the first deep zone; II, the second deep zone; III, the third deep zone;

10、旋喷钻杆;11、第一喷嘴;12、第二喷嘴;10. Rotary spray drill pipe; 11. The first nozzle; 12. The second nozzle;

20、引孔;21、无效引孔;30、预成孔;20. Lead hole; 21. Invalid lead hole; 30. Preformed hole;

40、收集坑;50、排泥设备;40. Collection pit; 50. Sludge discharge equipment;

1、高压水;2、高压空气;3、硬化材料;4、水泥浆;5、加固体浆料。1. High pressure water; 2. High pressure air; 3. Hardened material; 4. Cement slurry; 5. Reinforced solid slurry.

具体实施方式Detailed ways

下面结合附图和实施例对本申请作进一步的详细说明。可以理解的是,此处所描述的具体实施例仅仅用于解释相关发明,而非对该发明的限定。另外还需要说明的是,为了便于描述,附图中仅示出了与发明相关的部分。The application will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain related inventions, rather than to limit the invention. It should also be noted that, for ease of description, only parts related to the invention are shown in the drawings.

需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。下面将参考附图并结合实施例来详细说明本申请。It should be noted that, in the case of no conflict, the embodiments in the present application and the features in the embodiments can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and embodiments.

请详见图1-2,本申请提供了一种桥梁地基加固结构,包括墙壁加固区100以及设置在墙壁加固区100内部的中心加固区200,所述中心加固区200包括层叠设置的第一加固区D1和/或第二加固区D2,所述第一加固区D1包括阵列设置的多个第一加固体110,相邻两第一加固体110相切设置;所述第二加固区D2包括阵列设置的多个第二加固体120,相邻两第二加固体120存在部分交叠;Please refer to Figures 1-2 for details. The present application provides a bridge foundation reinforcement structure, which includes a wall reinforcement area 100 and a central reinforcement area 200 disposed inside the wall reinforcement area 100. The central reinforcement area 200 includes a stacked first The reinforced area D1 and/or the second reinforced area D2, the first reinforced area D1 includes a plurality of first reinforced bodies 110 arranged in an array, and two adjacent first reinforced bodies 110 are arranged tangentially; the second reinforced area D2 It includes a plurality of second reinforcements 120 arranged in an array, and two adjacent second reinforcements 120 partially overlap;

每一所述第一加固体110为一次加固成型,每一所述第二加固体120均为一次加固成型;在所述中心加固区200包括所述第一加固区D1和所述第二加固区D2时,所述第一加固区D1和所述第二加固区D2层叠设置,所述第一加固区D1设置在所述第二加固区D2的上层,所述第一加固体110和对应位置处的所述第二加固体120的轴线重合,且所述第一加固体110和所述第二加固体120同轴施工且一次加固成型。Each of the first reinforcements 110 is formed by one reinforcement, and each of the second reinforcements 120 is formed by one reinforcement; the central reinforcement area 200 includes the first reinforcement area D1 and the second reinforcement area. In the area D2, the first reinforcement area D1 and the second reinforcement area D2 are arranged in layers, the first reinforcement area D1 is arranged on the upper layer of the second reinforcement area D2, and the first reinforcement body 110 and the corresponding The axes of the second reinforcing body 120 at the position are coincident, and the first reinforcing body 110 and the second reinforcing body 120 are coaxially constructed and reinforced at one time.

本申请实施例中提供的桥梁超深地基加固结构,适用于桥梁超深地基,通过双层加固体的设置可以形成达到地基加固目的,形成具有超高加固强度、摩擦系数满足要求且渗透系数小的“人工隔水层”,从而满足锚碇地连墙基础对持力层、摩擦层和封水层的需要。The bridge ultra-deep foundation reinforcement structure provided in the embodiment of this application is suitable for bridge ultra-deep foundations. The purpose of foundation reinforcement can be achieved through the setting of double-layer reinforcements, and the formation has ultra-high reinforcement strength, friction coefficient meets requirements, and permeability coefficient is small. The "artificial water-resisting layer" can meet the needs of the anchorage ground and wall foundation for the bearing layer, friction layer and water sealing layer.

可以理解的是,图1中示出了加固结构中的部分中心加固区的结构示意图,其中第一加固体层D1中去除了部分第一加固体110,图2中未示出第一加固体110和第二加固体120的单独结构。图3中示出了一种加固结构中各个加固体的布置方式,其中上半圆为第一加固层D1上的第一加固体110和与第一加固层D1同层的墙壁加固区100上第一边缘加固体130的布置示意图;下半圆为第二加固层D2上的第二加固体120和与第二加固层D2同层的墙壁加固区100上第二边缘加固体140的布置示意图。It can be understood that, FIG. 1 shows a schematic structural diagram of a part of the central reinforcement area in the reinforcement structure, wherein part of the first reinforcement 110 is removed from the first reinforcement layer D1, and the first reinforcement is not shown in FIG. 2 110 and a separate structure of the second reinforcing body 120. Figure 3 shows the arrangement of each reinforcing body in a reinforcing structure, wherein the upper semicircle is the first reinforcing body 110 on the first reinforcing layer D1 and the first reinforcing body 110 on the wall reinforcement area 100 on the same floor as the first reinforcing layer D1. A schematic layout of an edge reinforcement 130; the lower semicircle is a schematic layout of the second reinforcement 120 on the second reinforcement layer D2 and the second edge reinforcement 140 on the wall reinforcement area 100 on the same floor as the second reinforcement layer D2.

在本实施例中所述墙壁加固区100包括与所述第一加固体110同层设置的第一边缘加固体130以及与所述第二加固体120同层设置的第二边缘加固体140,相邻两第二边缘加固体140存在部分交叠;所述第一边缘加固体130和对应位置处的所述第二边缘加固体140的轴线重合。In this embodiment, the wall reinforcement area 100 includes a first edge reinforcement 130 disposed on the same layer as the first reinforcement 110 and a second edge reinforcement 140 disposed on the same layer as the second reinforcement 120 , Two adjacent second edge reinforcements 140 partially overlap; axes of the first edge reinforcement 130 and the second edge reinforcement 140 at the corresponding position coincide.

本申请实施例中在所述加固结构的外围可以设置外壁400,所述外壁400为连续性结构,所述中心加固区200设置在所述外壁400的中心区域,所述墙壁加强区设置在所述中心加固区200的外围靠近所述墙壁加强区的区域,通过墙壁加强区可以形成外层致密防水和加固作用,在本申请中墙壁加固区100上的第一边缘加固体130与第一加固体110存在部分交叠,第二边缘加固体140与第二加固体120也存在部分交叠,同时,第一边缘加固体130、第二边缘加固体140均与外壁400存在部分交叠,可以提高加固结构的连接强度,提高边缘渗透系数。In the embodiment of the present application, an outer wall 400 can be set on the periphery of the reinforcement structure, the outer wall 400 is a continuous structure, the central reinforcement area 200 is set at the central area of the outer wall 400, and the wall reinforcement area is set at the In the area near the wall reinforcement area on the periphery of the central reinforcement area 200, the outer layer of dense waterproof and reinforcement can be formed through the wall reinforcement area. In this application, the first edge reinforcement 130 on the wall reinforcement area 100 is connected with the first reinforcement The solid 110 partially overlaps, the second edge reinforcement 140 and the second reinforcement 120 also partially overlap, and at the same time, both the first edge reinforcement 130 and the second edge reinforcement 140 partially overlap the outer wall 400, which can Improve the connection strength of the reinforced structure and increase the edge permeability coefficient.

在布置时,所述第一加固体110的高度大于所述第二加固体120的高度,所述第一加固体110的直径小于所述第二加固体120的直径,所述第一边缘加固体130和所述第一加固体110的直径相同,所述第二边缘加固体140和所述第二加固体120的直径相同;相邻两所述第一边缘加固体130的中心距小于所述相邻两所述第一加固体110的中心距,相邻两所述第二边缘加固体140的中心距小于所述相邻两所述第二加固体120的中心距。When arranged, the height of the first reinforcement 110 is greater than the height of the second reinforcement 120, the diameter of the first reinforcement 110 is smaller than the diameter of the second reinforcement 120, and the first edge reinforcement The solid 130 has the same diameter as the first reinforcement 110, the second edge reinforcement 140 has the same diameter as the second reinforcement 120; the center-to-center distance between two adjacent first edge reinforcements 130 is smaller than the The center-to-center distance between two adjacent first reinforcements 110 , the center-to-center distance between two adjacent second edge reinforcements 140 is smaller than the center-to-center distance between two adjacent second reinforcements 120 .

在本申请的一个实施例中,如图3所示,所述中心加固区200包括连续设置的第一深区I、第二深区II、第三深区III,所述第一深区I的高度小于所述第三深区III的高度,所述第一深区I内的第一加固体110的高度小于所述第三深区III的第一加固体110的高度,所述第一深区I内的所述第二加固体120的高度等于所述第二加固体120的高度;所述第二深区II内的所述第一加固体110的高度等于所述第一深区I内的所述第一加固体110的高度,所述第二深区II内的第二加固体120的高度等于所述第三深区III的第二加固体120的高度。In one embodiment of the present application, as shown in FIG. 3 , the central reinforcement zone 200 includes a first deep zone I, a second deep zone II, and a third deep zone III arranged continuously, and the first deep zone I The height of the first reinforcement 110 in the first deep region I is less than the height of the third deep region III, the height of the first reinforcement 110 in the first deep region I is smaller than the height of the first reinforcement 110 in the third deep region III, the first The height of the second reinforcement 120 in the deep zone I is equal to the height of the second reinforcement 120; the height of the first reinforcement 110 in the second deep zone II is equal to the height of the first deep zone II The height of the first reinforcement 110 in I, the height of the second reinforcement 120 in the second deep region II is equal to the height of the second reinforcement 120 in the third deep region III.

可以理解的是,本申请提供的加固结构在应用于桥梁结构时,根据应用位置不同,可以存在同一加固结构不同位置上受力情况不同,本申请中示例了第一深区I的承载力小于第三深区III的承载力,本申请中可以采用增加第一加固体110的高度方式,增加第三深区III范围内的加固结构的承载能力,节省成本。另外,为了提高在第一深区I和第三深区III之间过渡能力,防止出现应力集中等问题,本申请中在第一深区I和第三深区III之间设置了过渡的第二深区II,通过第二深区II范围内增加第二加固体120的高度,提高过渡区的承载力以及平衡第一深区I和第二深区II的应力,提高加固结构的寿命。It can be understood that when the reinforcement structure provided by the application is applied to bridge structures, depending on the application location, there may be different stress conditions at different positions of the same reinforcement structure. For the bearing capacity of the third deep zone III, in this application, the method of increasing the height of the first reinforcement body 110 can be adopted to increase the bearing capacity of the reinforced structure within the range of the third deep zone III and save costs. In addition, in order to improve the transition ability between the first deep zone I and the third deep zone III and prevent problems such as stress concentration, a transitional third zone is set between the first deep zone I and the third deep zone III in this application. In the second deep zone II, by increasing the height of the second reinforcing body 120 within the scope of the second deep zone II, the bearing capacity of the transition zone is increased and the stress of the first deep zone I and the second deep zone II is balanced to increase the life of the reinforced structure.

本申请实施例中所述第一加固体110的高度为20m~27m、直径为1.5m~2m;The height of the first reinforcing body 110 described in the embodiment of the present application is 20m-27m, and the diameter is 1.5m-2m;

所述第二加固体120的高度为4m~8m、直径为2.4m~3m;The second reinforcing body 120 has a height of 4m-8m and a diameter of 2.4m-3m;

所述第一加固体110的底面深度为40m~51m;The depth of the bottom surface of the first reinforcing body 110 is 40m-51m;

所述第二加固体120的底面深度为48m~55m。The depth of the bottom surface of the second reinforcing body 120 is 48m-55m.

可以理解的是,本申请实施例中并不限制所述多个加固体形成后的加固结构的截面形状,可以圆形、方形、三角形、无边形等规则形状或者其他不规则形状,在具体应用时根据场景等进行设置。本申请实施例中以圆形截面进行实施例性描述。It can be understood that the embodiment of the present application does not limit the cross-sectional shape of the reinforcement structure formed by the plurality of reinforcement bodies, and may be regular shapes such as circles, squares, triangles, and borderless shapes or other irregular shapes, depending on specific applications. set according to the scene, etc. In the embodiments of the present application, circular cross sections are used for exemplary description.

如图4和图5中示出了部分加固体的布置方式,图中实线为第一加固体110或第二加固体120,虚线为第一边缘加固体130或第二边缘加固体140,在每层中所述墙壁加固区100包括沿距离地连墙内缘线均匀布置162根桩,桩中心距1.673m;中心加固区200为除墙壁加固区100以外的区域,桩中心距1.7m。第一边缘加固体130与第一加固体110的中心距为2.1m。Figure 4 and Figure 5 show the arrangement of part of the reinforcing body, the solid line in the figure is the first reinforcing body 110 or the second reinforcing body 120, the dotted line is the first edge reinforcing body 130 or the second edge reinforcing body 140, In each layer, the wall reinforcement zone 100 includes 162 piles evenly arranged along the inner edge line of the ground connection wall, and the pile center distance is 1.673m; the central reinforcement zone 200 is an area other than the wall reinforcement zone 100, and the pile center distance is 1.7m . The center distance between the first edge reinforcement 130 and the first reinforcement 110 is 2.1 m.

在本申请中上层的第一加固区D1内,第一加固体110的桩径为1.7m;下层的第二加固区D2内,第二加固体120的桩径为2.4m,搭接(交叠尺寸)为0.7m其中,第一加固区D1和第二加固区D2的布置方式如下表1所示。In the first reinforcement area D1 of the upper layer in the present application, the pile diameter of the first reinforcement body 110 is 1.7m; in the second reinforcement area D2 of the lower layer, the pile diameter of the second reinforcement body 120 is 2.4m, and the overlap (intersection) Stack size) is 0.7m where the arrangement of the first reinforcement area D1 and the second reinforcement area D2 is shown in Table 1 below.

表1Table 1

Figure BDA0004091913240000081
Figure BDA0004091913240000081

由上表可以看出,本申请中加固结构适用于超深地基,地基深度超过50m,然而,目前现有的方法无法实现50m的超深高度下形成直径超过2.4m的第二加固体120的形成,一般地,若加固太深,地内压力过大,在采用旋转硬化的方式,会抵消一部超高压硬化材与空气喷流体或超高压水1与空气喷流体的能量,使得成桩直径变小,同时由于加固太深,气举的效果不是很好,导致返浆不太通畅,使得地内压力进一步增加,加固同时容易发生塌孔,将钻杆抱死,从而增加施工风险和难度。现有技术中的加固结构的形成方式,其理论成桩直径为20m以内为3m,其后每深10m,桩径减少20cm,根据实际试验,50m深很难达到桩径2.4m。It can be seen from the above table that the reinforcement structure in this application is suitable for ultra-deep foundations, and the depth of the foundation exceeds 50m. However, the current existing methods cannot realize the formation of the second reinforcement body 120 with a diameter exceeding 2.4m at an ultra-deep height of 50m. Formation, generally, if the reinforcement is too deep and the pressure in the ground is too large, the rotational hardening method will offset the energy of a part of ultra-high pressure hardened material and air jet fluid or ultra-high pressure water 1 and air jet fluid, making the pile diameter At the same time, because the reinforcement is too deep, the effect of gas lift is not very good, resulting in the unsmooth return of slurry, which further increases the pressure in the ground, and it is easy to collapse holes during reinforcement, which will lock the drill pipe, thereby increasing the risk and difficulty of construction. In the formation method of the reinforcement structure in the prior art, the theoretical pile diameter is 3m within 20m, and the pile diameter is reduced by 20cm for every 10m thereafter. According to actual tests, it is difficult to reach a pile diameter of 2.4m at a depth of 50m.

基于此超深高度地基,本申请还提供了一种桥梁地基加固结构的施工方法,用于成型如以上任一所述的桥梁地基加固结构,采用如图6所示的旋喷钻杆10进行施工,所述旋喷钻杆10包括上下设置的第一喷嘴11和第二喷嘴12,所述第一喷嘴11用于喷射高压水1与高压空气2,所述第二喷嘴12用于喷射高压硬化材料3;所述方法包括:Based on this ultra-deep foundation, the application also provides a construction method for a bridge foundation reinforcement structure, which is used to form a bridge foundation reinforcement structure as described above, using a rotary grouting drill pipe 10 as shown in Figure 6. construction, the rotary grouting drill pipe 10 includes a first nozzle 11 and a second nozzle 12 arranged up and down, the first nozzle 11 is used to spray high-pressure water 1 and high-pressure air 2, and the second nozzle 12 is used to spray high-pressure hardened material 3; the method comprising:

S100、在第一加固体110和/或第二加固体120的轴线位置处形成引孔20;S100, forming the guide hole 20 at the axial position of the first reinforcement body 110 and/or the second reinforcement body 120;

在所述中心加固区200包括第二加固体120时,所述方法包括:S200、通过旋喷钻杆10伸入所述引孔20内通过旋喷硬化形成阵列设置的多个第二加固体120;When the central reinforcement area 200 includes the second reinforcement 120, the method includes: S200, inserting the rotary grouting drill pipe 10 into the introduction hole 20 and hardening by rotary spraying to form a plurality of second reinforcements arranged in an array 120;

在所述中心加固区200包括第二加固体120时,所述方法包括:S300、通过旋喷钻杆10伸入所述引孔20内通过旋喷硬化形成阵列设置的多个第一加固体110;When the central reinforcement area 200 includes the second reinforcement 120, the method includes: S300, inserting the rotary grouting drill pipe 10 into the introduction hole 20 and hardening by rotary spraying to form a plurality of first reinforcements arranged in an array 110;

在所述中心加固区200包括所述第一加固区D1和所述第二加固区D2时,通过同一所述旋喷钻杆10伸入同一所述引孔20内进行同轴施工,通过旋喷硬化的方式一次加固成型所述第一加固体110和所述第二加固体120。When the central reinforcement zone 200 includes the first reinforcement zone D1 and the second reinforcement zone D2, the same rotary grouting drill pipe 10 is inserted into the same guide hole 20 for coaxial construction, The first reinforcement body 110 and the second reinforcement body 120 are reinforced and formed in one shot by spray hardening.

其中,如图7-10所示,所述旋喷硬化的方式具体包括:Wherein, as shown in Figure 7-10, the method of rotary spray hardening specifically includes:

ST02、通过第一喷嘴11旋转喷射高压水与高压空气对土体进行预切削,以扩大桩体并形成水与原生土的水泥浆4;ST02, pre-cutting the soil by spraying high-pressure water and high-pressure air through the first nozzle 11, so as to expand the pile body and form the cement slurry 4 of water and native soil;

ST04、通过第二喷嘴12旋转喷射高压硬化材料3对土体二次切削,以再次扩大桩体并形成硬化材料3与水泥浆4的加固体浆料5。ST04. The second nozzle 12 rotates and sprays the high-pressure hardening material 3 to cut the soil twice, so as to expand the pile body again and form the reinforcement slurry 5 of the hardening material 3 and the cement slurry 4 .

本申请提供的施工方法,上段第一喷嘴11喷射的超高压空气2和超高压水1切削形成的原生土混凝土在高压空气2和注入的水作用下,通过返浆通道排除,同时下段第二喷嘴12喷射的超高压硬化材料3形成二次切削并形成加固体浆料5,同样有利于原生土水泥浆排除,从而降低地内压力,有效的保留下段二次切削能量,形成更大直径桩体。In the construction method provided by this application, the original soil concrete formed by cutting the ultra-high-pressure air 2 and ultra-high-pressure water 1 sprayed by the first nozzle 11 in the upper section is discharged through the slurry return channel under the action of the high-pressure air 2 and the injected water, and at the same time, the second The ultra-high pressure hardening material 3 sprayed by the nozzle 12 forms a secondary cutting and forms a reinforced solid slurry 5, which is also conducive to the removal of the original soil cement slurry, thereby reducing the internal pressure, effectively retaining the secondary cutting energy of the lower section, and forming a larger diameter pile .

本申请提供的施工方法,本申请中上段喷射超高压水1和超高压空气2下段喷射高压硬化材料3,在压力作用下内部浆料相向受力,下段第二喷嘴12提供的喷射力向上将带着废弃水泥浆4排除,上段第一喷嘴11提供的喷射力向下将下段的超高压硬化材料3浆料紧密的按压在的引孔20下侧进行填填充,使得极少部分的超高压硬化材料3浆料被带出。In the construction method provided by this application, in this application, the upper section sprays ultra-high pressure water 1 and ultra-high pressure air 2 and the lower section sprays high-pressure hardening material 3. Under the action of pressure, the internal slurry is forced against each other, and the injection force provided by the second nozzle 12 of the lower section will move upward. With the waste cement slurry 4 discharged, the injection force provided by the first nozzle 11 in the upper section presses the slurry of the ultra-high pressure hardening material 3 in the lower section tightly on the lower side of the introduction hole 20 for filling, so that a very small part of the ultra-high pressure The hardened material 3 slurry is brought out.

可以理解的是,本申请实施例中的第二喷嘴12喷射的高压硬化材料3中不包含高压空气2,防止在气举的作用下将超高压硬化材料3浆料向上引导带出一大部分的加固浆料。若第二喷嘴12中喷射过程中含有高压空气2,则在喷射过程中,通过返浆带出加固硬化材料3约为加固体的20%,即浪费20%的硬化材料3,本申请中采用第二喷嘴12喷射高压硬化材料3的方式,可以提高超高压硬化材的置换率。It can be understood that the high-pressure hardening material 3 sprayed by the second nozzle 12 in the embodiment of the present application does not contain high-pressure air 2, so as to prevent the slurry of the ultra-high-pressure hardening material 3 from being guided upward by a large part under the action of gas lift. reinforcement slurry. If the injection process in the second nozzle 12 contains high-pressure air 2, then in the injection process, the reinforcement and hardening material 3 is brought out by returning slurry to about 20% of the reinforcement, that is, 20% of the hardening material 3 is wasted. The method of spraying the high pressure hardening material 3 from the second nozzle 12 can improve the replacement rate of the ultra high pressure hardening material.

本申请提供的施工方法,在保证上下复合加固土体强度、摩擦系数、渗透系数的前提下,合理提高加固硬化材料3置换率,减少加固硬化原材消耗量,节省硬化原材投入,降低项目成本的投入。在注入更少的原材下,可以达到相同的加固效果,同时利用大直径引孔20,可以提高加固体的垂直度,确保咬合效果,同时可建立可靠的返浆通道,减少地内压力,为超高压硬化材与空气喷流体创造好的条件,从而确保加固体的直径和质量。The construction method provided by this application, under the premise of ensuring the strength, friction coefficient and permeability coefficient of the upper and lower composite reinforced soil, reasonably increases the replacement rate of reinforcement and hardening materials 3, reduces the consumption of reinforcement and hardening raw materials, saves the investment of hardening raw materials, and reduces the project cost. cost input. The same reinforcement effect can be achieved by injecting fewer raw materials. At the same time, the use of large-diameter guide holes 20 can improve the verticality of the reinforcement body and ensure the occlusal effect. At the same time, a reliable slurry return channel can be established to reduce the internal pressure. The ultra-high pressure hardening material and the air jet fluid create good conditions to ensure the diameter and quality of the reinforcement.

需要说明的是,本申请实施例中并不限制第一加固体110和对应位置处的第二加固体120的形成顺序,在一些实施例中,可以基于相同的引孔20同时形成第一加固体110和第二加固体120,例如,在对应第二加固层上采用第二旋喷工艺,提升到一定高度后采用第一旋喷工艺继续形成第一加固体110。在另一些实施例中还可以先在第二加固区D2上形成各个第二加固体120,待第二加固体120硬化成型后,再在第一加固体110区上形成各个第一加固体110,本申请中由于提供的加固结构可以通过多种方式形成,在具体应用时根据场景或者成本等进行选择,本申请并不限制。It should be noted that the embodiment of the present application does not limit the formation sequence of the first reinforcement 110 and the second reinforcement 120 at the corresponding position. In some embodiments, the first reinforcement can be formed simultaneously based on the same guide hole 20 The solid 110 and the second reinforced body 120, for example, adopt the second rotary spraying process on the corresponding second reinforced layer, and then use the first rotary spraying process to continue to form the first reinforced body 110 after being raised to a certain height. In some other embodiments, each second reinforcement body 120 can be formed on the second reinforcement area D2 first, and then each first reinforcement body 110 can be formed on the first reinforcement body 110 area after the second reinforcement body 120 is hardened and formed. , because the reinforcement structure provided in this application can be formed in various ways, which can be selected according to scenarios or costs in specific applications, and this application is not limited.

在本申请实施例中,所述引孔20的直径为40cm~65cm;所述旋喷钻杆10的直径为10cm~20cm;所述引孔20与所述旋喷钻杆10之间形成返浆通道的间距为15cm~20cm。示例性地,旋喷钻杆10直径是11cm,引孔20的直径在40~65cm之间,两侧的半径差在15~20cm,即返浆通道的空间为15~20cm的圆环。In the embodiment of the present application, the diameter of the introduction hole 20 is 40 cm to 65 cm; the diameter of the rotary jet drill pipe 10 is 10 cm to 20 cm; The distance between the slurry channels is 15cm-20cm. Exemplarily, the diameter of the jet-jet drill pipe 10 is 11 cm, the diameter of the guide hole 20 is between 40-65 cm, and the radius difference on both sides is 15-20 cm, that is, the space of the slurry return channel is a ring of 15-20 cm.

本申请中提供的施工方式,一项重要改进点在于引孔20的设置以及引孔20直径的设置,本申请通过引孔20的设置有利于建立可靠的返浆通道,降低加固区地内压力,减少喷射切削能量损失。In the construction method provided in this application, an important point of improvement lies in the setting of the introduction hole 20 and the setting of the diameter of the introduction hole 20. The setting of the introduction hole 20 in this application is conducive to establishing a reliable grout return channel and reducing the internal pressure of the reinforcement area. Reduce jet cutting energy loss.

引孔20直径越大,意味着上部高压空气2和高压水1进行桩体的切割时,越远才能碰到土体,然后发生切削土体,但是也会因为悬浮液损失一部分喷射出去能量。引孔20达到一定直径后,能量损失完毕,就不能切削周围土体了。引孔20越大,塌孔风险越大;引孔20越大,施工时间越长,意味着投入的引孔20设备规格也会越大,引孔20设备的价格会成倍的增加。The larger the diameter of the guide hole 20 means that when the upper high-pressure air 2 and the high-pressure water 1 are cutting the pile, the farther they can touch the soil, and then the soil will be cut, but a part of the ejected energy will also be lost due to the suspension. After the lead hole 20 reached a certain diameter, the energy loss was completed, and the surrounding soil could not be cut. The larger the lead hole 20, the greater the risk of hole collapse; the larger the lead hole 20, the longer the construction time, which means that the input hole 20 equipment specifications will be larger, and the price of the lead hole 20 equipment will increase exponentially.

最主要的是,如图11所示,由于第二加固体120都是一根一根交叠(咬合),如果引孔20(A区)过大,会破坏周围已经成桩的加固体。同时,引孔20越大,意味着桩间土(B区)的面积会越小,可能会发生桩间土坍塌,导致塌孔、抱死钻杆的情况,发生安全事故。另外,如果引孔20和加固桩一样大,其实就可以直接灌注混凝土,形成混凝土结构,造价会成几何倍数增加;更为重要的是,本申请实施例中第二加固层中第二加固体120采用的是交叠方式设置,若引孔20过大,则无法形成交叠设置的第二加固体120,从而不能形成全断面密封的要求。如果引孔20的直径过小,导致地下内压力过大,造成上部切削土体的喷射能量一部分去对抗地内压力,剩余的部分才会进行切削土体,导致上部预成孔30的直径过小。从而在相同施工参数下,成桩直径小。Most importantly, as shown in FIG. 11 , since the second reinforcing bodies 120 overlap (occlude) one by one, if the guide hole 20 (area A) is too large, the surrounding reinforcing bodies that have been piled will be destroyed. Simultaneously, the larger the lead hole 20 means that the area of the soil between the piles (B district) will be smaller, and the soil between the piles may collapse, resulting in the collapse of the hole and the locking of the drill pipe, resulting in a safety accident. In addition, if the guide hole 20 is as large as the reinforcement pile, concrete can be poured directly to form a concrete structure, and the cost will increase geometrically; more importantly, the second reinforcement in the second reinforcement layer in the embodiment of the present application 120 is arranged in an overlapping manner. If the guide hole 20 is too large, the overlapping second reinforcement 120 cannot be formed, thus failing to meet the requirement of full-section sealing. If the diameter of the pilot hole 20 is too small, the underground internal pressure is too large, causing part of the injection energy of the upper cutting soil to resist the internal pressure, and the remaining part will cut the soil, causing the diameter of the upper preformed hole 30 to be too small. . Therefore, under the same construction parameters, the pile diameter is small.

本申请实施例中,第一加固体110和第二加固体120的轴线重合,采用同一引孔20实现第二加固体120和上层的第一加固体110的旋转硬化。在步骤S100中,所述形成引孔20的方法包括:In the embodiment of the present application, the axes of the first reinforcement body 110 and the second reinforcement body 120 are coincident, and the same guide hole 20 is used to realize the rotation hardening of the second reinforcement body 120 and the upper layer of the first reinforcement body 110 . In step S100, the method for forming the lead hole 20 includes:

通过钻头辅以泥浆护壁进行钻孔;Drilling through the drill bit supplemented by mud retaining walls;

每间隔固定高度进行一次垂直度测量,保证所述引孔20的垂直度偏差≤1/300。The verticality measurement is carried out at intervals of fixed heights to ensure that the verticality deviation of the guide hole 20 is ≤ 1/300.

示例性地,为满足第二加固体120的桩径2.4m,桩间距1.7m,咬合70cm,允许偏差仅22cm,为了提高止水能力和提高承载力,要求垂直度偏差应小于1/220。Exemplarily, in order to satisfy the pile diameter of the second reinforcing body 120 of 2.4m, the pile spacing of 1.7m, the bite of 70cm, and the allowable deviation of only 22cm, in order to improve the water-stopping ability and bearing capacity, the verticality deviation should be less than 1/220.

在施工时,采用60cm钻头进行预成孔30钻进,每间隔10m进行一次垂直度测量,若有偏斜,及时纠偏和调整,直至引孔20比加固体设计桩身深1.4m。可以理解的是,1.4m为引孔20的深度需要预留第一喷嘴11和第二喷嘴12的间距,以使得旋喷钻杆10的第一喷嘴11可以在预设位置进行旋喷,以下描述第二加固体120以下位置的引孔20为无效引孔21。During construction, use a 60cm drill bit to drill the pre-formed hole 30, and measure the verticality every 10m. If there is any deviation, correct and adjust it in time until the pilot hole 20 is 1.4m deeper than the designed pile body of the reinforced body. It can be understood that 1.4m is the depth of the guide hole 20, and the distance between the first nozzle 11 and the second nozzle 12 needs to be reserved, so that the first nozzle 11 of the rotary jet drill pipe 10 can perform rotary spraying at a preset position, as follows The introduction hole 20 describing the position below the second reinforcing body 120 is an invalid introduction hole 21 .

所述引孔20的垂直度直接关系到加固的桩的准确位置,本方法采用40cm~65cm的大直径引孔20,为超高压旋喷钻机下方过程中调整位置预留了空间,让钻杆在重力的作用下自然下垂,使得后期超高压旋喷钻杆10垂直度不在受预成孔30的影响。可以理解的是,引孔20的直径可以根据加固体的高度进行调整和优化,具体调整的尺寸以利于建立可靠的返浆通道和预留调整空间为主。The verticality of the guide hole 20 is directly related to the exact position of the reinforced pile. This method adopts a large diameter guide hole 20 of 40 cm to 65 cm, which reserves space for adjusting the position in the process of the ultra-high pressure rotary grouting drilling machine, so that the drill pipe Under the action of gravity, it sags naturally, so that the verticality of the ultra-high pressure rotary grouting drill pipe 10 is no longer affected by the pre-formed hole 30 . It can be understood that the diameter of the guide hole 20 can be adjusted and optimized according to the height of the reinforcing body, and the specific adjusted size is mainly conducive to the establishment of a reliable slurry return channel and reserved adjustment space.

本申请在步骤S200和S300中采用旋喷硬化的方式,以高压设备使高压水与高压空气成为高压射流,从喷嘴中喷射出来冲击破坏土体,起到切削土体的作用,另外,旋转喷射的方式还可以实现搅拌功能,形成水泥浆,其中部分细小的土料随着水泥浆冒出水面,其余土粒在喷射流的冲击力,离心力和重力等作用下,与浆料搅拌混合,并按一定的浆土比例有规律地重新排列。This application adopts the method of rotary jet hardening in steps S200 and S300, using high-pressure equipment to make high-pressure water and high-pressure air into high-pressure jets, which are ejected from the nozzles to impact and destroy the soil, and play the role of cutting the soil. In addition, the rotary spray The method can also realize the stirring function to form cement slurry, in which part of the fine soil material emerges from the water surface with the cement slurry, and the rest of the soil particles are stirred and mixed with the slurry under the impact force of the jet flow, centrifugal force and gravity, etc. Regularly rearrange according to a certain slurry-to-soil ratio.

其中,所述第一喷嘴11靠近地基上表面,所述第二喷嘴12远离地基上表面,所述第一喷嘴11和所述第二喷嘴12设置在所述旋喷钻杆10的相对侧,所述第一喷嘴11切削形成桩体的直径小于所述第二喷嘴12二次切削形成桩体的直径,即,所述第一喷嘴11形成预成孔30的直径小于所述第一加固体110的直径。Wherein, the first nozzle 11 is close to the upper surface of the foundation, the second nozzle 12 is away from the upper surface of the foundation, and the first nozzle 11 and the second nozzle 12 are arranged on opposite sides of the rotary jet drill pipe 10, The diameter of the pile body formed by cutting the first nozzle 11 is smaller than the diameter of the pile body formed by the secondary cutting of the second nozzle 12, that is, the diameter of the pre-formed hole 30 formed by the first nozzle 11 is smaller than that of the first reinforcement body 110 diameter.

其中,所述旋喷硬化的操作方式包括:如图7-10所示,所述旋喷钻杆10采用边旋转喷射边提升的方式,自所述引孔20的底部向上,在所述第一喷嘴11旋转喷射一定高度后再开启第二喷嘴12进行选择喷射。Wherein, the operation mode of the rotary spraying hardening includes: as shown in Fig. 7-10, the rotary spraying drill pipe 10 adopts the method of lifting while rotating and spraying, from the bottom of the guide hole 20 upwards, at the first One nozzle 11 rotates and sprays to a certain height, and then opens the second nozzle 12 for selective spraying.

需要说明的是,本申请实施例中,第一喷嘴11中的高压空气2和高压水1采用的是高压空气2包高压水1的设置方式,即高压空气2位于喷射范围的外围高压水1位于高压空气2喷射范围的中心,形成类似“气包水”的高压水与高压空气,通过气包水的方式可以切割、搅拌的作用。It should be noted that, in the embodiment of the present application, the high-pressure air 2 and the high-pressure water 1 in the first nozzle 11 are set in the way that the high-pressure air 2 packs the high-pressure water 1, that is, the high-pressure air 2 is located at the periphery of the spray range of the high-pressure water 1 Located in the center of the spray range of high-pressure air 2, it forms high-pressure water and high-pressure air similar to "water-in-air", which can cut and stir through the water-in-air method.

上段的第一喷嘴11喷出超高压水1与空气喷流体对土体进行引导预切削,形成一定的预成孔30,下段的第二喷嘴12喷出超高压硬化材料3对预成孔30继续扩大切削土体,同时在气举的作用下可顺利地将产生的淀渣和浆料向上排除;超高压硬化材料3喷射压力更大,使得可以加固更快,但也要避免超高压硬化材料3喷射压力过大影响相邻交叠的第二加固体120的结构。The first nozzle 11 in the upper section sprays ultra-high pressure water 1 and air jet fluid to guide and pre-cut the soil to form certain pre-formed holes 30, and the second nozzle 12 in the lower section sprays ultra-high pressure hardening material 3 to pre-form holes 30 Continue to expand the cutting soil, and at the same time, under the action of air lift, the generated sediment and slurry can be smoothly removed upward; the injection pressure of ultra-high pressure hardening material 3 is higher, so that it can be reinforced faster, but ultra-high pressure hardening should also be avoided Excessive injection pressure of the material 3 affects the structure of the adjacent overlapping second reinforcing body 120 .

另外,所述预成孔30超过超高压旋喷桩一定的高度,该高度由上下段喷嘴的间距决定;所述的钻杆上、下喷嘴间距,该间距可以根据需要进行调整。In addition, the pre-formed hole 30 exceeds a certain height of the ultra-high pressure jet grouting pile, and the height is determined by the distance between the upper and lower nozzles; the distance between the upper and lower nozzles of the drill pipe can be adjusted as required.

可以理解的是,本申请实施例中引孔20直径和第一喷嘴11、第二喷嘴12的参数具有一定的匹配关系,第一喷嘴11和第二喷嘴12的参数直接关系到与加固体的桩径和加固体的高度。It can be understood that in the embodiment of the present application, the diameter of the guide hole 20 has a certain matching relationship with the parameters of the first nozzle 11 and the second nozzle 12, and the parameters of the first nozzle 11 and the second nozzle 12 are directly related to the reinforcement. The diameter of the pile and the height of the reinforcement.

可选地,所述旋喷钻杆10上所述第一喷嘴11与所述第二喷嘴12的间距为1.2m~1.4m;需要说明的是,第一喷嘴11和第二喷嘴12的间距越大,如图12所示,意味着第一喷嘴11切掉土体的水和气对第二喷嘴12喷出的高压硬化材料3与水泥浆4混合的加固体浆料5的扰动越小。如果第一喷嘴11和第二喷嘴12很近,如图13所示,产生的扰动以及压力将会带走大部分的加固体浆料5。第一喷嘴11和第二喷嘴12的间距的设置还可以避免无效引孔21的深度太长,浪费引孔20的费用、时间;最主要的是,无效引孔21的太长,加固体浆液也不利于填充无效引孔21,从而无效引孔21内可能还是土和水的混合物,造成加固结构的危险。经过本申请中的研究,设置1.2m~1.4m可以综合以上各方面的因素,实现优化效果。Optionally, the distance between the first nozzle 11 and the second nozzle 12 on the rotary jet drill pipe 10 is 1.2m-1.4m; it should be noted that the distance between the first nozzle 11 and the second nozzle 12 The larger it is, as shown in FIG. 12 , it means that the water and air that the first nozzle 11 cuts off the soil have less disturbance to the reinforcement slurry 5 mixed with the high-pressure hardening material 3 and the cement slurry 4 sprayed out by the second nozzle 12 . If the first nozzle 11 and the second nozzle 12 are very close, as shown in FIG. 13 , the generated turbulence and pressure will take away most of the reinforcement slurry 5 . The setting of the distance between the first nozzle 11 and the second nozzle 12 can also avoid the too long depth of the ineffective introduction hole 21, which wastes the cost and time of the introduction hole 20; It is also not conducive to filling the invalid lead hole 21, so the mixture of soil and water may still be in the invalid lead hole 21, causing the danger of reinforcing the structure. After the research in this application, the setting of 1.2m to 1.4m can combine the factors of the above aspects to achieve the optimization effect.

可选地,在形成所述第一加固体110时,所述第一喷嘴11的高压水1的压力为25MPa~37MPa、流量为150L/min~200L/min;高压空气2的压力为0.75MPa~1.25MPa、流量为4.5Nm3/min~5.5N m3/min;所述第二喷嘴12的高压硬化材料3的压力为37MPa~42MPa,流量为115L/min~135L/min;所述第一喷嘴11的喷射半径为第一加固体110半径的85%~90%;所述第二喷嘴12的喷射半径为所述第一加固体110半径的10%~15%。Optionally, when the first reinforcement 110 is formed, the pressure of the high-pressure water 1 of the first nozzle 11 is 25MPa-37MPa, the flow rate is 150L/min-200L/min; the pressure of the high-pressure air 2 is 0.75MPa ~1.25MPa, the flow rate is 4.5Nm 3 /min~5.5N m 3 /min; the pressure of the high pressure hardening material 3 of the second nozzle 12 is 37MPa~42MPa, the flow rate is 115L/min~135L/min; The spraying radius of the first nozzle 11 is 85%-90% of the radius of the first reinforcing body 110; the spraying radius of the second nozzle 12 is 10%-15% of the radius of the first reinforcing body 110.

在形成所述第二加固体120时,所述第一喷嘴11的高压水1的压力为35MPa~45MPa、流量为180L/min~220L/min;高压空气2的压力为1.05MPa~1.75MPa、流量为5.0Nm3/min~6.5Nm3/min;所述第二喷嘴12的高压硬化材料3的压力为40MPa~45MPa,流量为120L/min~155L/min;所述第一喷嘴11的喷射半径为第二加固体120半径的85%~90%;所述第二喷嘴12的喷射半径为所述第二加固体120半径的10%~15%。When forming the second reinforcement 120, the pressure of the high-pressure water 1 of the first nozzle 11 is 35MPa-45MPa, the flow rate is 180L/min-220L/min; the pressure of the high-pressure air 2 is 1.05MPa-1.75MPa, The flow rate is 5.0Nm 3 /min~6.5Nm 3 /min; the pressure of the high-pressure hardening material 3 of the second nozzle 12 is 40MPa~45MPa, and the flow rate is 120L/min~155L/min; the injection of the first nozzle 11 The radius is 85%-90% of the radius of the second reinforcement 120 ; the spray radius of the second nozzle 12 is 10%-15% of the radius of the second reinforcement 120 .

具体参数的设置如下表2所示。The specific parameter settings are shown in Table 2 below.

表2Table 2

Figure BDA0004091913240000141
Figure BDA0004091913240000141

本申请实施例中通过控制引孔20与旋喷钻杆10的返浆通道,可以预留足够的空间,在超高压加固旋喷的过程中,能够有效避免槽壁塌孔而抱死旋喷钻杆10的情况,节约处理故障时间,提高加固效率。In the embodiment of the present application, by controlling the return passage of the guide hole 20 and the rotary grouting drill pipe 10, enough space can be reserved, and during the process of ultra-high pressure reinforced rotary grouting, the groove wall can be effectively prevented from collapsing and blocking the rotary grouting In the case of the drill pipe 10, the time for dealing with failures is saved and the reinforcement efficiency is improved.

本申请实施例中通过控制引孔20的尺寸,有利于第一次超高压空气2和超高压水1切削形成更大的圆柱,减少了钻杆附近的土体,减少了能量损失,使得超高压空气2和超高压水1能量得到有效利用,喷射更远,切削范围更大,为第二次超高压硬化材料3的再切削创造有利条条件。In the embodiment of the present application, by controlling the size of the pilot hole 20, it is beneficial for the first ultra-high pressure air 2 and ultra-high pressure water 1 to cut to form a larger cylinder, reducing the soil near the drill pipe, reducing energy loss, and making the super The energy of high-pressure air 2 and ultra-high-pressure water 1 is effectively utilized, the spraying is farther, and the cutting range is larger, which creates favorable conditions for the second re-cutting of ultra-high-pressure hardened material 3 .

本申请中的另一方面的重要改进点在于预切削和二次切削范围的匹配。第一,由于上部的高压空气2包高压水1进行桩体的切割,高压空气2包高压水1切割的加固体需要桩径的85-90%,加固体桩径剩下10-15%由下部喷嘴的高压浆进行切割。第二,下部喷嘴的高压浆在整个加固过程中,扮演者扩大桩体和进一步喷射浆液,搅拌均匀下部混合液的作用,从而使得加固体强度更加的均匀,也能留下更多的硬化材料3的浆液提高置换率。在施用相同硬化材料3的条件下,能够得到桩径更大,加固质量更好,渗透系数越小,加固强度越大的加固体。Another important improvement point in this application lies in the matching of pre-cutting and secondary cutting ranges. First, because the upper part of the high-pressure air with 2 packs of high-pressure water 1 carries out the cutting of the pile body, the reinforced body cut by 2 packs of high-pressure air with 1 high-pressure water needs 85-90% of the pile diameter, and the remaining 10-15% of the pile diameter of the reinforced body is determined by The high-pressure slurry of the lower nozzle performs the cutting. Second, during the entire reinforcement process, the high-pressure grout of the lower nozzle plays the role of expanding the pile body and further spraying the grout, stirring the lower mixed liquid evenly, so that the strength of the reinforcement is more uniform, and more hardened materials can be left A slurry of 3 increases the displacement rate. Under the condition of applying the same hardening material 3, a reinforced body with larger pile diameter, better reinforcement quality, smaller permeability coefficient and greater reinforcement strength can be obtained.

可以理解的是,本申请实施例中所述第一加固体110和第二加固体120均为圆柱形,所述第一喷嘴11和第二喷嘴12的旋喷角度可以为360°,在不同实施例中也可根据设计的需要,旋喷任意角度;所述的超高压空气2、超高压水1、超高压硬化材料3浆料旋喷注浆所采用的压力可根据需要进行调整。另外,以上工艺参数仅是试验参考,和土的性质、加固深度等共同作用。同时加固桩的直径还和土的特性有关,砂性土成桩直径大,粘性土成桩直径小。It can be understood that, in the embodiment of the present application, the first reinforcement 110 and the second reinforcement 120 are both cylindrical, and the swirling angle of the first nozzle 11 and the second nozzle 12 can be 360°, in different In the embodiment, according to the requirements of the design, any angle can be sprayed; the pressures of the ultra-high pressure air 2, ultra-high pressure water 1, and ultra-high pressure hardening material 3 slurry rotary jet grouting can be adjusted according to needs. In addition, the above process parameters are only for experimental reference, and work together with the properties of the soil and the depth of reinforcement. At the same time, the diameter of the reinforcement pile is also related to the characteristics of the soil. The diameter of the pile is large in sandy soil, and the diameter of the pile in cohesive soil is small.

实施例Example

S1:场地整平,在对应每一所述引孔位置的场地上埋设一定深度的钢护筒,例如埋设3-4m深钢护筒,为防止引孔20预成孔30水泥浆4和加固土体返回浆料四处排放,在加固体顶处开挖返浆临时收集坑40。S1: The site is leveled, and steel casings of a certain depth are buried on the site corresponding to each of the above-mentioned introduction holes, for example, 3-4m deep steel casings are buried, in order to prevent the introduction holes 20 pre-formed holes 30 cement slurry 4 and reinforcement The returned slurry of the soil body is discharged everywhere, and a temporary collection pit 40 for the returned slurry is excavated at the top of the reinforced body.

在临时收集坑40的位置处设置有排泥设备50吸水泥浆4,可以控制地内压力,若压力过大,可主动泵吸排除水泥浆4,减小地内压力,从而使得超高压硬化材与空气喷流体在相同的喷浆压力下,可以使得加固体更加均匀,加固质量更好At the position of the temporary collection pit 40, a mud discharge device 50 is provided to absorb the cement slurry 4, which can control the internal pressure. If the pressure is too high, the cement slurry 4 can be actively pumped to reduce the internal pressure, so that the ultra-high pressure hardened material and air Under the same spraying pressure, the spray fluid can make the reinforcement more uniform and the reinforcement quality better

S2:大直径引孔20钻机就位,辅以优质的泥浆护壁,采用60cm钻头进行预成孔30钻进,每间隔10m进行一次垂直度测量,若有偏斜,及时纠偏和调整,直至引孔20比第二加固体120深1.4m。S2: 20 drilling rigs for large-diameter lead holes are in place, supplemented by high-quality mud protection walls, and 30 pre-formed holes are drilled with 60cm drill bits, and the verticality is measured every 10m. The hole 20 is 1.4 m deeper than the second reinforcement 120 .

S3:超高压旋喷设备就位,精确调整设备水平,并对准设计桩中心位置,其后采用汽车吊辅助进行旋喷钻杆10下放。S3: The ultra-high pressure rotary grouting equipment is in place, the level of the equipment is precisely adjusted, and it is aligned with the center of the designed pile, and then the rotary grouting drill pipe 10 is lowered with the assistance of a truck crane.

S4:待旋喷钻杆10下放到位后,启动后台空压机输送高压空气2,高压水1泵输送高压水1,开启旋喷钻杆10上段第一喷嘴11,超高压旋喷设备转动钻杆,第一喷嘴11随钻杆360°转动并喷射超高压水1和高压空气2混合流进行上段原状土体预切削,同时旋喷钻杆10根据设定缓慢提升,从而不断线向上预切削土体,在圆柱空间内形成水泥浆4,达到第一次扩大桩体和切削土体目的;S4: After the rotary jet drill pipe 10 is put in place, start the background air compressor to deliver high-pressure air 2, high-pressure water pump 1 to deliver high-pressure water 1, turn on the first nozzle 11 in the upper section of the rotary jet drill pipe 10, and the ultra-high pressure rotary jet equipment rotates the drill Rod, the first nozzle 11 rotates 360° with the drill pipe and sprays the mixed flow of ultra-high pressure water 1 and high-pressure air 2 to pre-cut the original soil body in the upper section, and at the same time, the rotary jet drill pipe 10 is slowly lifted according to the setting, so as to continuously pre-cut upward Soil, form cement slurry 4 in the cylindrical space, to achieve the purpose of expanding the pile body and cutting the soil for the first time;

S5:同时部分水泥浆4在气举和不断注入的高压水1共同作用下,通过返浆通道向上排除多余的水泥浆4,由排泥设备50将其抽走。S5: At the same time, part of the cement slurry 4 is discharged upward through the slurry return channel under the combined action of the gas lift and the continuously injected high-pressure water 1 , and is sucked away by the mud discharge device 50 .

S6:后台高压浆液设备自动拌制超高压硬化材料3的浆液,其配合比根据设计配置。S6: The background high-pressure slurry equipment automatically mixes the slurry of the ultra-high pressure hardening material 3, and its mixing ratio is configured according to the design.

S7:待提升旋喷钻杆10通过第一喷嘴11切削1.4m上段原状土体预后,立即开启下段第二喷嘴12,第二喷嘴12随钻杆360°转动并喷射超高压硬化材料3液体,在超高压的作用下超高压硬化材料3浆液再次切削原状土,形成满足桩径要求的空间圆柱,同时在喷射的作用下超高压硬化材料3浆液和水泥浆4充分搅拌混合,从而形成超高压硬化材料3与水泥浆4的加固体浆料5。S7: After the rotary grouting drill pipe 10 is lifted to cut 1.4m of the undisturbed soil in the upper section through the first nozzle 11, the second nozzle 12 in the lower section is opened immediately, and the second nozzle 12 rotates with the drill pipe 360° and sprays the ultra-high pressure hardening material 3 liquid, Under the action of ultra-high pressure, the ultra-high pressure hardening material 3 slurry cuts the undisturbed soil again to form a space cylinder that meets the pile diameter requirements. At the same time, under the action of jetting, the ultra-high pressure hardening material 3 slurry and cement slurry 4 are fully stirred and mixed to form ultra-high pressure. Hardening material 3 and cement slurry 4 reinforcement slurry 5 .

S8:在第二喷嘴12旋转喷射同时,上层部分水泥浆4在气举和不断注入的高压水1、高压空气2、超高压硬化材料3液体共同作用下,利用可靠的返浆通道,将排除多余的水泥浆4由排泥设备50将其抽走。S8: While the second nozzle 12 is rotating and spraying, the upper part of the cement slurry 4 will be discharged under the combined action of air lift and continuous injection of high-pressure water 1, high-pressure air 2, and ultra-high-pressure hardening material 3, using a reliable slurry return channel. Surplus cement slurry 4 is sucked away by mud discharge equipment 50 .

S9:根据设定,按设定好的步距缓慢提升旋喷钻杆10并360°转动喷射,直至加固到设计桩顶,停止第一喷嘴11和第二喷嘴12喷射注浆,并拆除第二加固体120,进行下一施工。S9: According to the setting, slowly lift the rotary grouting drill pipe 10 according to the set step distance and rotate and spray 360° until it is reinforced to the top of the designed pile, stop the first nozzle 11 and the second nozzle 12 from spraying grouting, and remove the first nozzle 11 and the second nozzle 12. The second reinforced body 120 is used for the next construction.

在本申请实施例中,对应位置处的所述第一加固体110和所述第二加固体120通过同一旋喷钻杆10通过一次旋喷硬化的方式形成;第一加固体110和第二加固体120的旋喷硬化的工艺参数不同,在完成第一加固体110和第二加固体120的旋喷硬化后,一并拆除旋喷钻杆10,进行下一施工。In the embodiment of the present application, the first reinforcement body 110 and the second reinforcement body 120 at the corresponding positions are formed by the same rotary spraying drill pipe 10 through one-time rotary spray hardening; the first reinforcement body 110 and the second reinforcement body 110 The technical parameters of the jet hardening of the reinforcing body 120 are different. After the jet hardening of the first reinforcing body 110 and the second reinforcing body 120 is completed, the jet drilling drill pipe 10 is removed together for the next construction.

所述方法还包括:The method also includes:

拆除所述旋喷钻杆10,待所述加固浆料初凝后,在所述引孔20内再次注浆形成二次填充。The rotary grouting drill pipe 10 is disassembled, and after the initial setting of the reinforcement slurry, grouting is performed again in the introduction hole 20 to form secondary filling.

S10:待1天后,在引孔20通道浆液硬化前,和超高压硬化材料3液体+土颗粒混合物化学反应初凝后,为保证深层加固桩设计桩顶处的质量,对桩顶进行二次普通注浆,用以二次填从桩头,确保桩头质量。可以理解的是,对于同时旋喷硬化的第一加固体110和第二加固体120可以采用一次或者两次普通注浆的方式,本申请对此并不限制。S10: After 1 day, before the grout hardening in the 20 channels of the pilot hole, after the chemical reaction with the ultra-high pressure hardening material 3 liquid + soil particle mixture for initial setting, in order to ensure the quality of the deep reinforcement pile at the top of the pile, the pile top shall be subjected to secondary Ordinary grouting is used for secondary filling from the pile head to ensure the quality of the pile head. It can be understood that one or two ordinary grouting methods can be used for the first reinforcement body 110 and the second reinforcement body 120 that are simultaneously jet-hardened, and the present application is not limited thereto.

需要理解的是,术语“长度”、“宽度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It is to be understood that the terms "length", "width", "top", "bottom", "front", "rear", "left", "right", "vertical", "horizontal", "top" , "bottom", "inner", "outer" and other indicated orientations or positional relationships are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the referred device Or elements must have a certain orientation, be constructed and operate in a certain orientation, and thus should not be construed as limiting the invention.

此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features. In the description of the present invention, "plurality" means two or more, unless otherwise specifically defined.

除非另有定义,本文中所使用的技术和科学术语与本发明的技术领域的技术人员通常理解的含义相同。本文中使用的术语只是为了描述具体的实施目的,不是旨在限制本发明。本文中出现的诸如“设置”等术语既可以表示一个部件直接附接至另一个部件,也可以表示一个部件通过中间件附接至另一个部件。本文中在一个实施方式中描述的特征可以单独地或与其它特征结合地应用于另一个实施方式,除非该特征在该另一个实施方式中不适用或是另有说明。Unless defined otherwise, technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the technical field of the invention. The terminology used herein is only for the purpose of describing a specific implementation, and is not intended to limit the present invention. Terms such as "disposed" appearing herein may mean that one component is directly attached to another component or that one component is attached to another component through an intermediary. Features described herein in one embodiment may be applied to another embodiment alone or in combination with other features, unless the feature is not applicable in that other embodiment or stated otherwise.

本发明已经通过上述实施方式进行了说明,但应当理解的是,上述实施方式只是用于举例和说明的目的,而非意在将本发明限制于所描述的实施方式范围内。本领域技术人员可以理解的是,根据本发明的教导还可以做出更多种的变型和修改,这些变型和修改均落在本发明所要求保护的范围以内。The present invention has been described through the above-mentioned embodiments, but it should be understood that the above-mentioned embodiments are only for the purpose of illustration and description, and are not intended to limit the present invention within the scope of the described embodiments. Those skilled in the art can understand that more variations and modifications can be made according to the teaching of the present invention, and these variations and modifications all fall within the scope of protection claimed by the present invention.

Claims (10)

1.一种桥梁地基加固结构,其特征在于,包括墙壁加固区以及设置在墙壁加固区内部的中心加固区,所述中心加固区包括第一加固区和/或第二加固区,所述第一加固区包括阵列设置的多个第一加固体,相邻两第一加固体相切设置;所述第二加固区包括阵列设置的多个第二加固体,相邻两第二加固体存在部分交叠;每一所述第一加固体为一次加固成型,每一所述第二加固体均为一次加固成型;1. A bridge foundation reinforcement structure, characterized in that it includes a wall reinforcement area and a central reinforcement area arranged inside the wall reinforcement area, the central reinforcement area includes a first reinforcement area and/or a second reinforcement area, the first reinforcement area A reinforcement area includes a plurality of first reinforcements arranged in an array, and two adjacent first reinforcements are arranged tangentially; the second reinforcement area includes a plurality of second reinforcements arranged in an array, and two adjacent second reinforcements exist Partially overlapping; each of the first reinforcements is formed by one reinforcement, and each of the second reinforcements is formed by one reinforcement; 在所述中心加固区包括所述第一加固区和所述第二加固区时,所述第一加固区和所述第二加固区层叠设置,所述第一加固区设置在所述第二加固区的上层,所述第一加固体和对应位置处的所述第二加固体的轴线重合,且所述第一加固体和所述第二加固体同轴施工且一次加固成型。When the central reinforced area includes the first reinforced area and the second reinforced area, the first reinforced area and the second reinforced area are stacked, and the first reinforced area is arranged on the second reinforced area. In the upper layer of the reinforcement area, the axis of the first reinforcement body and the second reinforcement body at the corresponding position are coincident, and the first reinforcement body and the second reinforcement body are coaxially constructed and reinforced at one time. 2.根据权利要求1所述的桥梁地基加固结构,其特征在于,所述墙壁加固区包括与所述第一加固体同层设置的第一边缘加固体以及与所述第二加固体同层设置的第二边缘加固体,相邻两第二边缘加固体存在部分交叠;所述第一边缘加固体和对应位置处的所述第二边缘加固体的轴线重合。2. The bridge foundation reinforcement structure according to claim 1, wherein the wall reinforcement area includes a first edge reinforcement set on the same layer as the first reinforcement body and a first edge reinforcement body on the same layer as the second reinforcement body For the second edge reinforcement provided, two adjacent second edge reinforcements partially overlap; the axis of the first edge reinforcement coincides with the axis of the second edge reinforcement at the corresponding position. 3.根据权利要求2所述的桥梁地基加固结构,其特征在于,所述第一加固体的高度大于所述第二加固体的高度,所述第一加固体的直径小于所述第二加固体的直径,所述第一边缘加固体和所述第一加固体的直径相同,所述第二边缘加固体和所述第二加固体的直径相同;相邻两所述第一边缘加固体的中心距小于所述相邻两所述第一加固体的中心距,相邻两所述第二边缘加固体的中心距小于所述相邻两所述第二加固体的中心距。3. The bridge foundation reinforcement structure according to claim 2, wherein the height of the first reinforcement body is greater than the height of the second reinforcement body, and the diameter of the first reinforcement body is smaller than that of the second reinforcement body The diameter of the solid, the diameter of the first edge reinforcement is the same as that of the first reinforcement, the diameter of the second edge reinforcement is the same as that of the second reinforcement; two adjacent first edge reinforcements The center-to-center distance of the two adjacent first reinforcement bodies is smaller than the center-to-center distance of the two adjacent second reinforcement bodies, and the center-to-center distance between the two adjacent second edge reinforcement bodies is smaller than the center-to-center distance of the two adjacent second reinforcement bodies. 4.根据权利要求1所述的桥梁地基加固结构,其特征在于,4. The bridge foundation reinforcement structure according to claim 1, characterized in that, 所述第一加固体的高度为20m~27m、直径为1.5m~2m;The height of the first reinforcement is 20m-27m, and the diameter is 1.5m-2m; 所述第二加固体的高度为4m~8m、直径为2.4m~3m;The second reinforcing body has a height of 4m-8m and a diameter of 2.4m-3m; 所述第一加固体的底面深度为40m~51m;The depth of the bottom surface of the first reinforcement is 40m-51m; 所述第二加固体的底面深度为48m~55m。The depth of the bottom surface of the second reinforcement is 48m-55m. 5.一种桥梁地基加固结构的施工方法,其特征在于,用于成型如权利要求1-4任一所述的桥梁地基加固结构,采用旋喷钻杆进行施工,所述旋喷钻杆包括上下设置的第一喷嘴和第二喷嘴,所述第一喷嘴用于喷射高压水与高压空气,所述第二喷嘴用于喷射高压硬化材料;所述方法包括:5. A construction method for a bridge foundation reinforcement structure, characterized in that, for forming the bridge foundation reinforcement structure as claimed in any one of claims 1-4, the construction is carried out using a jet-jet drill pipe, and the jet-jet drill pipe comprises A first nozzle and a second nozzle arranged up and down, the first nozzle is used to spray high-pressure water and high-pressure air, and the second nozzle is used to spray high-pressure hardening material; the method includes: 在第一加固体和/或第二加固体的轴线位置处形成引孔;forming guide holes at the axial positions of the first reinforcement and/or the second reinforcement; 通过旋喷钻杆伸入所述引孔内通过旋喷硬化形成阵列设置的多个第一加固体和/或多个第二加固体;forming a plurality of first reinforcements and/or a plurality of second reinforcements arranged in an array through rotary spraying drill rods inserted into the guide hole and hardened by rotary spraying; 在所述中心加固区包括所述第一加固区和所述第二加固区时,通过同一所述旋喷钻杆伸入同一所述引孔内进行同轴施工,通过旋喷硬化的方式一次加固成型所述第一加固体和所述第二加固体;When the central reinforcement area includes the first reinforcement area and the second reinforcement area, the same rotary spraying drill pipe is inserted into the same guide hole for coaxial construction, and the rotary spraying hardening is performed once Reinforcing the first reinforcement body and the second reinforcement body; 其中,所述旋喷硬化的方式具体包括:Wherein, the manner of said rotary spray hardening specifically includes: 通过第一喷嘴旋转喷射高压水与高压空气对土体进行预切削,以扩大桩体并形成水与原生土的水泥浆;Pre-cutting the soil body by spraying high-pressure water and high-pressure air through the first nozzle to expand the pile body and form a cement slurry of water and native soil; 通过第二喷嘴旋转喷射高压硬化材料对土体二次切削,以再次扩大桩体并形成硬化材料与水泥浆的加固体浆料。The second nozzle rotates and sprays the high-pressure hardening material to cut the soil twice, so as to expand the pile body again and form a solid slurry of hardening material and cement slurry. 6.根据权利要求5所述的桥梁地基加固结构的施工方法,其特征在于,在形成所述引孔之前,所述方法还包括:6. The construction method of bridge foundation reinforcement structure according to claim 5, is characterized in that, before forming described lead hole, described method also comprises: 在对应每一所述引孔位置的场地上埋设一定深度的钢护筒,并对应每一引孔位置处开设用于收集所述水泥浆和所述加固体浆料的收集坑。A steel casing of a certain depth is buried on the site corresponding to each of the introduction holes, and a collection pit for collecting the cement slurry and the reinforcement slurry is opened at each of the introduction hole locations. 7.根据权利要求5所述的桥梁地基加固结构的施工方法,其特征在于,所述引孔的直径为40cm~65cm;所述旋喷钻杆的直径为10cm~20cm;所述引孔与所述旋喷钻杆之间形成返浆通道的间距为15cm~20cm;7. the construction method of bridge foundation reinforcement structure according to claim 5, is characterized in that, the diameter of described guide hole is 40cm~65cm; The diameter of described rotary grouting drill rod is 10cm~20cm; Described guide hole and The distance between the jet grouting drill pipes to form the return slurry channel is 15cm-20cm; 所述形成引孔的方法包括:The method for forming a hole includes: 通过钻头辅以泥浆护壁进行钻孔;Drilling through the drill bit supplemented by mud retaining walls; 每间隔固定高度进行一次垂直度测量,保证所述引孔的垂直度偏差≤1/300。Perpendicularity measurement is performed at intervals of fixed heights to ensure that the verticality deviation of the pilot hole is ≤1/300. 8.根据权利要求5所述的桥梁地基加固结构的施工方法,其特征在于,所述第一喷嘴靠近地基上表面,所述第二喷嘴远离地基上表面,所述第一喷嘴和所述第二喷嘴设置在所述旋喷钻杆的相对侧,第一喷嘴预切削形成桩体的直径小于所述第二喷嘴二次切削形成桩体的直径;8. The construction method of the bridge foundation reinforcement structure according to claim 5, wherein the first nozzle is close to the upper surface of the foundation, the second nozzle is far away from the upper surface of the foundation, and the first nozzle and the second nozzle are The two nozzles are arranged on opposite sides of the jet-jet drill pipe, and the diameter of the pile body formed by the pre-cutting of the first nozzle is smaller than the diameter of the pile body formed by the secondary cutting of the second nozzle; 所述旋喷硬化的操作方式包括:所述旋喷钻杆采用边旋转喷射边提升的方式,自所述引孔的底部向上,在所述第一喷嘴旋转喷射一定高度后再开启第二喷嘴进行选择喷射。The operation mode of the rotary spray hardening includes: the rotary spray drill rod adopts the method of lifting while rotating and spraying, from the bottom of the guide hole upwards, and then opens the second nozzle after the first nozzle rotates and sprays to a certain height Perform selective injection. 9.根据权利要求5所述的桥梁地基加固结构的施工方法,其特征在于,所述旋喷钻杆上所述第一喷嘴与所述第二喷嘴的间距为1.2m~1.4m;9. The construction method of bridge foundation reinforcement structure according to claim 5, characterized in that, the distance between the first nozzle and the second nozzle on the jet-jet drill pipe is 1.2m-1.4m; 在形成所述第二加固体时,所述第一喷嘴的高压水的压力为35MPa~45MPa、流量为180L/min~220L/min;高压空气的压力为1.05MPa~1.75MPa、流量为5.0Nm3/min~6.5Nm3/min;所述第二喷嘴的高压硬化材料的压力为40MPa~45MPa,流量为120L/min~155L/min;所述第一喷嘴的喷射半径为第二加固体半径的85%~90%;所述第二喷嘴的喷射半径为所述第二加固体半径的10%~15%;When forming the second reinforced body, the pressure of the high-pressure water in the first nozzle is 35MPa-45MPa, and the flow rate is 180L/min-220L/min; the pressure of the high-pressure air is 1.05MPa-1.75MPa, and the flow rate is 5.0Nm 3 /min~6.5Nm 3 /min; the pressure of the high pressure hardening material of the second nozzle is 40MPa~45MPa, the flow rate is 120L/min~155L/min; the spray radius of the first nozzle is the radius of the second reinforced body 85%-90% of that; the spray radius of the second nozzle is 10%-15% of the radius of the second reinforcement; 在形成所述第一加固体时,所述第一喷嘴的高压水的压力为25MPa~37MPa、流量为150L/min~200L/min;高压空气的压力为0.75MPa~1.25MPa、流量为4.5Nm3/min~5.5Nm3/min;所述第二喷嘴的高压硬化材料的压力为37MPa~42MPa;所述第一喷嘴的喷射半径为第一加固体半径的85%~90%;所述第二喷嘴的喷射半径为所述第一加固体半径的10%~15%。When forming the first reinforced body, the pressure of the high-pressure water in the first nozzle is 25MPa-37MPa, and the flow rate is 150L/min-200L/min; the pressure of the high-pressure air is 0.75MPa-1.25MPa, and the flow rate is 4.5Nm 3 /min~5.5Nm 3 /min; the pressure of the high-pressure hardening material of the second nozzle is 37MPa~42MPa; the spray radius of the first nozzle is 85%~90% of the radius of the first reinforcement; The spraying radius of the second nozzle is 10%-15% of the radius of the first reinforcing body. 10.根据权利要求5所述的桥梁地基加固结构的施工方法,其特征在于,所述方法还包括:10. The construction method of bridge foundation reinforcement structure according to claim 5, is characterized in that, described method also comprises: 拆除所述旋喷钻杆,待所述加固浆料初凝后,在所述引孔内再次注浆形成二次填充。The rotary grouting drill pipe is removed, and after the initial setting of the reinforcement slurry, grouting is performed again in the introduction hole to form secondary filling.
CN202310149333.XA 2023-02-22 A bridge ultra-deep foundation reinforcement structure and construction method thereof Active CN116290064B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310149333.XA CN116290064B (en) 2023-02-22 A bridge ultra-deep foundation reinforcement structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310149333.XA CN116290064B (en) 2023-02-22 A bridge ultra-deep foundation reinforcement structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN116290064A true CN116290064A (en) 2023-06-23
CN116290064B CN116290064B (en) 2025-04-18

Family

ID=

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060879A (en) * 1996-08-19 1998-03-03 Nippon Concrete Ind Co Ltd Building foundation and construction method thereof
CN1944809A (en) * 2006-10-26 2007-04-11 上海隧道工程股份有限公司 Three pipe double high pressure rotary jet sprouting reinforced construction method and its equipment
JP2013167144A (en) * 2012-01-16 2013-08-29 Grape Co Ltd Foundation structure and construction method for foundation
CN111254922A (en) * 2018-11-30 2020-06-09 周兆弟 Soft soil foundation strengthening method and composite pile foundation construction method thereof
RU198240U1 (en) * 2020-03-12 2020-06-25 Федеральное государственное бюджетное образовательное учреждение высшего образования "Вологодский государственный университет" Pile stand with multi-layer sleeve at the lower end
CN215562677U (en) * 2021-08-23 2022-01-18 中冶集团武汉勘察研究院有限公司 Deep soft soil area foundation ditch passive zone reinforced structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060879A (en) * 1996-08-19 1998-03-03 Nippon Concrete Ind Co Ltd Building foundation and construction method thereof
CN1944809A (en) * 2006-10-26 2007-04-11 上海隧道工程股份有限公司 Three pipe double high pressure rotary jet sprouting reinforced construction method and its equipment
JP2013167144A (en) * 2012-01-16 2013-08-29 Grape Co Ltd Foundation structure and construction method for foundation
CN111254922A (en) * 2018-11-30 2020-06-09 周兆弟 Soft soil foundation strengthening method and composite pile foundation construction method thereof
RU198240U1 (en) * 2020-03-12 2020-06-25 Федеральное государственное бюджетное образовательное учреждение высшего образования "Вологодский государственный университет" Pile stand with multi-layer sleeve at the lower end
CN215562677U (en) * 2021-08-23 2022-01-18 中冶集团武汉勘察研究院有限公司 Deep soft soil area foundation ditch passive zone reinforced structure

Similar Documents

Publication Publication Date Title
AU2020103672A4 (en) Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
CN106836204A (en) The device and method of pouring pile bearing capacity under a kind of lifting Soft Soil
CN105256795B (en) Hold type thread core built pile and its construction equipment and construction method in a kind of end
CN107246267A (en) Mine Shaft Lining, constructing device and method in a kind of poor strata
CN110616709A (en) Triple-pipe three-high-pressure jet grouting pile construction method
CN111608210A (en) Construction method of pressure bearing type anti-floating anchor rod in water-saturated silt stratum
CN102966110A (en) Vertically-combined type impermeable waterproof curtain structure and construction method thereof
CN108729440A (en) Wing stirring base expanding and base expanding stiff composite pile, its construction method and drilling machine are expanded in the spray of spiral height
CN107366282A (en) A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique
CN207377562U (en) Mine Shaft Lining and constructing device in a kind of poor strata
CN202954371U (en) Vertical combined type seepage-proofing waterproof curtain structure
CN110777775A (en) Foundation pit structure and construction method thereof
CN207862925U (en) A kind of slip casting casing device
CN101793024B (en) Construction method for multi-head small-diameter deep mixing and high-pressure jet combined anti-seepage wall of foundation pit
CN210507500U (en) Drilling, spraying and stirring integrated seepage-proof curtain wall forming device
CN116290064A (en) Bridge ultra-deep foundation reinforcement structure and construction method thereof
CN107700508A (en) A kind of shaped steel stirs the construction method of water spray soil curtain support pile
CN116290064B (en) A bridge ultra-deep foundation reinforcement structure and construction method thereof
CN208917856U (en) For the constructing structure on aerial leakage stratum in deep hole impervious wall construction
CN103774645B (en) The construction method of a kind of soil cement and the stake of Combined concrete material
CN114352189B (en) Construction method of jet grouting pile
CN112227356A (en) Gravel grouting steel pipe pile and preparation method thereof
CN111254939A (en) Foundation pit enclosure strengthening method for soft soil foundation
CN111379283A (en) Foundation reinforcement method
CN208201858U (en) Wing stirring base expanding and base expanding stiff composite pile and drilling machine are expanded in the spray of spiral height

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant