[go: up one dir, main page]

CN116219820A - Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area - Google Patents

Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area Download PDF

Info

Publication number
CN116219820A
CN116219820A CN202310276704.0A CN202310276704A CN116219820A CN 116219820 A CN116219820 A CN 116219820A CN 202310276704 A CN202310276704 A CN 202310276704A CN 116219820 A CN116219820 A CN 116219820A
Authority
CN
China
Prior art keywords
layer
slope
road
pavement
bamboo
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310276704.0A
Other languages
Chinese (zh)
Inventor
高乾丰
石薛可
曾铃
张锐
唐佳琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN202310276704.0A priority Critical patent/CN116219820A/en
Publication of CN116219820A publication Critical patent/CN116219820A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • C04B28/04Portland cements
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/221Kerbs or like edging members, e.g. flush kerbs, shoulder retaining means ; Joint members, connecting or load-transfer means specially for kerbs
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/227Gutters; Channels ; Roof drainage discharge ducts set in sidewalks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/0075Uses not provided for elsewhere in C04B2111/00 for road construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明公开了一种南方竹林区公路路基路面根胀变形调控结构及施工方法,结构包括沥青路面结构、生态路缘石结构、路基边坡结构,沥青路面结构的厚度与竹鞭在地下生长深度相匹配;生态路缘石结构包括上窄下宽、整体呈L型的本体,本体的内部设有L型贯通空腔,本体的下体上表面设有过水道,过水道的两端沿本体长度方向贯通;本体的上体、下体均间隔开设有排水口,排水口与L型贯通空腔连通,L型贯通空腔通过沿道路纵向间隔设置的急流槽与坡底的边沟连接;路基边坡结构的边坡填土层从下至上土层中残鞭填充量逐渐递增。本发明阻止了竹鞭向公路路基路面范围内生长,克服了根胀破坏的问题,控制路基和路面的变形,提高了路面耐久性。

Figure 202310276704

The invention discloses a control structure and construction method for root swelling deformation of roadbed road surface in southern bamboo forest area. The structure includes asphalt pavement structure, ecological curb stone structure and roadbed slope structure. Matching; the ecological curb structure includes an L-shaped body that is narrow at the top and wide at the bottom. The interior of the body is provided with an L-shaped through cavity, and the upper surface of the lower body of the body is provided with a water channel. The upper body and the lower body of the main body are separated from each other with drainage outlets, and the drainage outlets are connected to the L-shaped through-cavity, and the L-shaped through-cavity is connected to the side ditch at the bottom of the slope through rapid flow troughs arranged at intervals along the longitudinal direction of the road; the subgrade slope structure The amount of remnant whip filling in the slope fill layer gradually increases from bottom to top. The invention prevents the bamboo whip from growing into the range of the roadbed and road surface, overcomes the problem of root swelling damage, controls the deformation of the roadbed and the road surface, and improves the durability of the road surface.

Figure 202310276704

Description

南方竹林区公路路基路面根胀变形调控结构及施工方法Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area

技术领域technical field

本发明属于公路建设与养护技术领域,涉及一种南方竹林区公路路基路面根胀变形调控结构及施工方法。The invention belongs to the technical field of road construction and maintenance, and relates to a structure and construction method for regulating root swelling deformation of a roadbed and pavement in a southern bamboo forest area.

背景技术Background technique

毛竹在我国长江流域及南方各省区广泛分布,是世界上生长速度最快的植物之一。毛竹竹鞭横走于地表以下40cm深度范围内的土体中,具有趋向疏松和肥沃的土壤、阳光充沛和温暖的方向生长的习性,喜温暖湿润气候、背风向阳、潮湿环境以及富含有机质和矿物元素的偏酸性土壤。Moso bamboo is widely distributed in the Yangtze River Basin and southern provinces in my country, and is one of the fastest growing plants in the world. Phyllostachys pubescens runs across the soil within a depth of 40cm below the surface. It has the habit of growing in loose and fertile soil, sunny and warm directions. It likes warm and humid climates, leeward to the sun, humid environments, and rich in organic matter and Acidic soil with mineral elements.

工程实践发现,南方竹林区的公路常见毛竹竹鞭横向生长引起的路基路面病害。在竹林区修建公路时,如果遇到地势较低的路段,常采取低路堤的形式通过。尽管修建路堤时会清除原地面毛竹及其断鞭,但由于毛竹竹鞭生命顽强力,一旦断鞭清除不完全则竹鞭会在路堤中继续蔓延;同时,路堤范围以外的竹鞭也可能向路堤方向横向生长。由于具有喜沿坡向上生长的习性,大量竹鞭侵入路堤范围后将沿边坡向上生长,最终侵入公路路肩甚至行车道范围。竹鞭在路基土中蔓延生长会对上层土体产生顶升力,由于路基土的压实度高、压缩性小,因此土层顶升力和变形将继续向上传递,引起路基土和路面结构发生鼓胀变形,继而造成路面过高隆起和开裂。而且,由于毛竹竹鞭的不断生长,路面隆起与开裂问题还会随着时间的推移持续加剧,不仅增加公路养护频率造成直接经济损失,还极大地影响行车安全和道路容貌。以上路基路面病害在南方山区普通国道与地方道路中十分常见,是南方竹林区公路提质改造中亟待解决的难点问题。Engineering practice has found that roadbed and pavement diseases caused by the lateral growth of Moso bamboo shoots are common in roads in bamboo forest areas in the south. When building roads in the bamboo forest area, if you encounter a low-lying road section, you often pass it in the form of a low embankment. Although the moso bamboo and its broken whips on the ground will be removed when the embankment is built, due to the tenacious life of the bamboo whips, once the broken whips are not completely removed, the bamboo whips will continue to spread in the embankment; at the same time, the bamboo whips outside the embankment may also spread to The direction of the embankment grows laterally. Due to the habit of growing up along the slope, a large number of bamboo whips will grow up along the slope after invading the embankment area, and finally invade the road shoulder or even the carriageway area. The spreading and growth of bamboo whips in the subgrade soil will generate jacking force on the upper soil. Due to the high degree of compaction and low compressibility of the subgrade soil, the jacking force and deformation of the soil layer will continue to be transmitted upwards, causing swelling of the subgrade soil and pavement structure Deformation, which in turn causes excessive bumps and cracks in the pavement. Moreover, due to the continuous growth of moso bamboo whips, the problems of road surface uplift and cracking will continue to intensify over time, which will not only increase the frequency of road maintenance and cause direct economic losses, but also greatly affect driving safety and road appearance. The above subgrade and pavement diseases are very common in ordinary national roads and local roads in southern mountainous areas, and they are difficult problems to be solved urgently in the improvement and reconstruction of roads in southern bamboo forest areas.

综上所述,为了预防南方竹林区公路路基路面根胀变形病害,保证公路路面正常使用寿命,研发一种南方竹林区公路路基路面根胀变形调控结构及施工方法是非常必要的。To sum up, in order to prevent the root swelling deformation disease of the highway subgrade pavement in the southern bamboo forest area and ensure the normal service life of the road pavement, it is very necessary to develop a control structure and construction method for the root swelling deformation of the road subgrade pavement in the southern bamboo forest area.

发明内容Contents of the invention

为了解决上述问题,本发明提供一种南方竹林区公路路基路面根胀变形调控结构,阻止了竹鞭向公路路基路面范围内生长,克服了根胀破坏的问题,控制路基和路面的变形,提高了路面耐久性。In order to solve the above-mentioned problems, the present invention provides a control structure for root swelling deformation of highway subgrade pavement in southern bamboo forest area, which prevents bamboo whips from growing within the range of road subgrade pavement, overcomes the problem of root swelling damage, controls the deformation of roadbed and road surface, and improves pavement durability.

本发明的另一目的是,提供一种南方竹林区公路路基路面根胀变形调控结构的施工方法。Another object of the present invention is to provide a construction method for the control structure of the root swelling deformation of the subgrade road surface of the southern bamboo forest area.

本发明所采用的技术方案是,一种南方竹林区公路路基路面根胀变形调控结构,包括:The technical solution adopted in the present invention is a control structure for controlling root swelling deformation of road subgrade pavement in southern bamboo forest area, including:

沥青路面结构,所述沥青路面结构的厚度与竹鞭在地下生长深度相匹配,路面结构表层设有排水横坡;Asphalt pavement structure, the thickness of the asphalt pavement structure matches the depth of bamboo whip growth underground, and the surface layer of the pavement structure is provided with a drainage transverse slope;

生态路缘石结构,所述生态路缘石结构包括上窄下宽、整体呈L型的本体,本体的内部设有L型贯通空腔,本体的下体上表面设有过水道,过水道的两端沿本体长度方向贯通;本体的上体、下体均间隔开设有排水口,排水口与L型贯通空腔连通,L型贯通空腔通过沿道路纵向间隔设置的急流槽与坡底的边沟连接;Ecological curb structure. The ecological curb structure includes an L-shaped body that is narrow at the top and wide at the bottom. The interior of the body is provided with an L-shaped through cavity. The upper surface of the lower body of the body is provided with a waterway. It runs along the length of the main body; the upper body and the lower body of the main body are separated by drainage outlets, and the drainage outlets communicate with the L-shaped through-cavity. ;

路基边坡结构,所述路基边坡结构的边坡填土层从下至上土层中残鞭填充量逐渐递增。The embankment side slope structure, the remnants filling amount in the side slope filling layer of the roadbed side slope structure gradually increases from the bottom to the top soil layer.

进一步的,所述生态路缘石结构的原料由以下重量份数组成:挖方石料20~70份、氢氧化钙10~20份、粉煤灰8~15份、竹木纤维2~5份、硅酸盐水泥8~16份、脂环族类环氧树脂5~15份、水1~6份;其中,竹木纤维为毛竹的颗粒状残鞭。Further, the raw materials of the ecological curb structure are composed of the following parts by weight: 20-70 parts of excavated stone, 10-20 parts of calcium hydroxide, 8-15 parts of fly ash, 2-5 parts of bamboo and wood fiber, silicon 8-16 parts of salt cement, 5-15 parts of alicyclic epoxy resin, and 1-6 parts of water; wherein, the bamboo wood fiber is the granular residual whip of moso bamboo.

进一步的,所述沥青路面结构采用骨架-密实结构,孔隙率4~6%。Further, the asphalt pavement structure adopts a skeleton-dense structure with a porosity of 4-6%.

进一步的,所述沥青路面结构从下至上依次包括下基层、上基层、下面层、上面层,下基层采用石灰粉煤灰稳定类基层,上基层采用石灰粉煤灰稳定砂砾石基层,下面层采用中粒式沥青混凝土;上面层采用细粒式改性沥青混凝土;上面层和下面层之间、下面层与上基层之间均通过改性乳化沥青粘层进行粘合。Further, the asphalt pavement structure includes a lower base layer, an upper base layer, a lower layer, and an upper layer from bottom to top, the lower base layer adopts a lime fly ash stabilized base layer, the upper base layer adopts a lime fly ash stabilized sand and gravel base layer, and the lower layer Medium-grained asphalt concrete is used; fine-grained modified asphalt concrete is used for the upper layer; between the upper layer and the lower layer, and between the lower layer and the upper base layer, the modified emulsified asphalt adhesive layer is used for bonding.

进一步的,所述过水道沿本体的高度方向由L型拐弯处向下凹陷形成,截面为弧形。Further, the water channel is formed by a downward depression of an L-shaped bend along the height direction of the body, and the cross section is arc-shaped.

进一步的,所述排水口包括高位排水口和低位排水口,高位排水口设置在本体的上部,高于过水道;低位排水口的水平高度与路面结构齐平,排水口设置间距为15~20cm。Further, the drain includes a high drain and a low drain, the high drain is set on the upper part of the body, higher than the waterway; the level of the low drain is flush with the road surface structure, and the distance between the drains is 15-20cm .

进一步的,所述排水口为拱门式,排水口设有拱门式拦污网,拦污网的孔径为5~20mm。Further, the drainage outlet is arched, and the drainage outlet is provided with an arched trash-stop, and the hole diameter of the trash-stop is 5-20mm.

进一步的,所述路基边坡结构的路基从下至上依次包括下路堤、上路堤、下路床、上路床,上路床上方的沥青路面结构的两侧边坡填筑有路侧填土层;路基两侧的边坡从下至上依次包括第四边坡填土层、第三边坡填土层、第二边坡填土层、第一边坡填土层,坡填土层中加入残鞭的质量分数为8%~14%,从下往上呈递增趋势。Further, the subgrade of the subgrade slope structure includes a lower embankment, an upper embankment, a lower road bed, and an upper road bed from bottom to top, and the side slopes on both sides of the asphalt pavement structure above the upper road bed are filled with roadside fill layers; The side slopes on both sides of the subgrade include the fourth side slope filling layer, the third side slope filling layer, the second side slope filling layer, and the first side slope filling layer from bottom to top. The mass fraction of whip is 8%-14%, and it shows an increasing trend from bottom to top.

进一步的,所述路基边坡结构的边坡表面依次设有边坡碎石层和植生层,植生层中内横向有间距的插入长度为8~10cm的残鞭,加入残鞭的质量分数为9%~11%。Further, the slope surface of the subgrade slope structure is provided with a slope crushed stone layer and a vegetation layer in turn, and in the vegetation layer, there are inserted residual whips with a length of 8 to 10 cm in the horizontal direction, and the mass fraction of the residual whips added is 9% to 11%.

一种南方竹林区公路路基路面根胀变形调控结构的施工方法,包括以下步骤:A construction method for the control structure of the root swelling deformation of the subgrade road surface of the southern bamboo forest area, comprising the following steps:

S1、铺筑路基;S1, pave the roadbed;

S2、在路基边坡外侧铺设边坡碎石层,对边坡进行挂网;S2. Lay a slope gravel layer on the outside of the roadbed slope, and hang a net on the slope;

S3、在边坡碎石层上喷播植生层;S3, spraying the vegetation layer on the slope gravel layer;

S4、在整平的路基上铺设沥青路面结构,路面结构表层表面设有排水横坡;S4. Lay the asphalt pavement structure on the leveled roadbed, and the surface layer of the pavement structure is provided with a drainage cross slope;

S5、在路面两旁设置生态路缘石结构,生态路缘石结构的埋置段埋置在路面下,位于路面以上的外露段按照与道路路面齐平的位置刨槽、找平、夯实后再安砌,每隔10~15m设置一个开口将生态路缘石结构内部的L型贯通空腔与急流槽相连接,急流槽沿道路纵向间隔设置,急流槽与坡底的边沟连接;在生态路缘石结构和路面结构之间灌缝。S5. Set up ecological curb structures on both sides of the road surface. The embedded section of the ecological curb stone structure is buried under the road surface, and the exposed section above the road surface is planed, leveled, and compacted according to the position flush with the road surface, and then installed. An opening is set every 10-15m to connect the L-shaped through cavity inside the ecological curb structure with the rapids. Fill joints between pavement structures.

本发明的有益效果是:The beneficial effects of the present invention are:

1、本发明的路基边坡结构存在两个有益效果。首先,利用该公路路堑或隧道挖方石料经破碎填筑在路基边坡外侧形成边坡碎石层,通过碎石之间的嵌挤密实达到阻碍竹鞭生长的目的;其次,在植生层中加入残鞭,起到对植生层加筋和抑制竹鞭在植生层中生长的目的。1. There are two beneficial effects in the roadbed slope structure of the present invention. Firstly, use the road cutting or tunnel excavated stones to be crushed and filled on the outside of the embankment slope to form a slope gravel layer, and the purpose of preventing the growth of bamboo whips is achieved by embedding and compacting between the gravels; secondly, adding The residual whip plays the purpose of reinforcing the vegetation layer and inhibiting the growth of the bamboo whip in the vegetation layer.

2、本发明的竹鞭骨料生态路缘石存在三个有益效果。首先,充分利用废料做成再生道路工程砌块,做到真正的废弃料资源化利用;其次,根据竹鞭浅层生长和避硬性的特性,利用埋置在地下一定深度的路缘石埋置段可以有效抵御竹鞭的延伸;最后,结构上采用L型空腔贯通结构,过流量大,可及时排除路面积水。2. There are three beneficial effects in the bamboo whip aggregate ecological curbstone of the present invention. First of all, make full use of waste materials to make recycled road engineering blocks, so as to achieve real resource utilization of waste materials; secondly, according to the characteristics of bamboo whip shallow growth and hard avoidance, use the embedding section of curbs buried at a certain depth underground It can effectively resist the extension of bamboo whips; finally, the structure adopts an L-shaped cavity through structure, which has a large flow rate and can timely remove accumulated water on the road.

3、本发明的沥青混凝土存在三个有益效果。首先,在结构上采用骨架-密实结构,孔隙率较小,能有效阻止竹鞭进入路面从而对路面结构造成破坏;其次,此沥青混凝土在面层材料中采用在面层材料中采用竹木纤维(颗粒状残鞭)作添加剂,具有较好的抗变形能力,有效地抵抗因竹鞭侵略导致的路面变形;最后,采用石灰粉煤灰稳定类基层,其中生石灰遇到潮湿的空气容易形成氢氧化钙能有效抑制竹鞭生长。3. The asphalt concrete of the present invention has three beneficial effects. First of all, the structure adopts a skeleton-dense structure with small porosity, which can effectively prevent bamboo whips from entering the road surface and causing damage to the pavement structure; secondly, this asphalt concrete uses bamboo and wood fiber in the surface material (granular residual whip) as an additive, has good anti-deformation ability, and effectively resists the deformation of the road surface caused by the invasion of bamboo whips; finally, lime fly ash is used to stabilize the base layer, and quicklime is easy to form hydrogen when it encounters humid air. Calcium oxide can effectively inhibit the growth of bamboo whip.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. Those skilled in the art can also obtain other drawings based on these drawings without creative work.

图1是本发明实施例的结构示意图。Fig. 1 is a schematic structural diagram of an embodiment of the present invention.

图2是图1的右侧局部图。Fig. 2 is a partial view on the right side of Fig. 1 .

图3是图1的左侧局部图。FIG. 3 is a partial view on the left side of FIG. 1 .

图4是本发明实施例中路缘石的结构示意图。Fig. 4 is a schematic structural view of a curb in an embodiment of the present invention.

图5是本发明实施例与对比例的路缘石力学性能试验数据。Fig. 5 is the test data of the mechanical properties of curb stones of the embodiment of the present invention and the comparative example.

图6是本发明实施例与对比例的路缘石排水性能试验数据。Fig. 6 is the test data of curb drainage performance of the embodiment of the present invention and the comparative example.

图中,1.生态路缘石结构,2.沥青路面结构,20.本体,21.高位排水口,22.过水道,23.低位排水口,24.外露段,25.埋置段,26.辅助排水通道,27.主排水通道,3.路面结构表层,4.上面层,5.下面层,6.上基层,7.下基层,8.路侧填土层,9.上路床、10.下路床、11.上路堤、12.下路堤;13.第一边坡填土层,14.第二边坡填土层,15.第三边坡填土层,16.第四边坡填土层,17.急流槽,18.边沟,19.植生层。In the figure, 1. Ecological curb structure, 2. Asphalt pavement structure, 20. Body, 21. High drain, 22. Water passage, 23. Low drain, 24. Exposed section, 25. Embedded section, 26. Auxiliary drainage channel, 27. Main drainage channel, 3. Surface layer of pavement structure, 4. Upper layer, 5. Lower layer, 6. Upper base layer, 7. Lower base layer, 8. Road side fill layer, 9. Upper road bed, 10 .Lower road bed, 11. Upper embankment, 12. Lower embankment; 13. First slope fill layer, 14. Second slope fill layer, 15. Third slope fill layer, 16. Fourth side Slope fill layer, 17. Rapid flow trough, 18. Side ditch, 19. Vegetation layer.

具体实施方式Detailed ways

下面将结合本发明实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

实施例1,Example 1,

一种南方竹林区公路路基路面根胀变形调控结构,如图1所示,包括沥青路面结构2、生态路缘石结构1以及路基边坡结构,共同组成稳定的路基路面根胀变形调控结构。A control structure for root swell deformation of highway subgrade pavement in the southern bamboo forest area, as shown in Figure 1, includes asphalt pavement structure 2, ecological curb structure 1, and subgrade slope structure, which together form a stable control structure for root swell deformation of roadbed pavement.

如图2所示,沥青路面结构2的厚度为40cm,与竹鞭在地下生长深度相对应,沥青路面结构从下至上依次由下基层7、上基层6、下面层5、上面层4组成;沥青路面结构包括面层和基层,从下至上,下基层7采用7%石灰粉煤灰稳定类基层、上基层6用5%石灰粉煤灰稳定砂砾石基层、下面层5采用8~12cm中粒式沥青混凝土;面层和基层中间用50%乳化沥青粘层油进行粘合、上面层4采用6~10cm细粒式改性沥青混凝土;下基层7厚度15~20cm、上基层6厚度25~30cm,具有足够的强度,可以起到抵御竹鞭。As shown in Figure 2, the thickness of the asphalt pavement structure 2 is 40cm, which corresponds to the depth of bamboo whip growth underground. The asphalt pavement structure is composed of the lower base layer 7, the upper base layer 6, the lower layer 5, and the upper layer 4 from bottom to top; The asphalt pavement structure includes the surface layer and the base layer. From bottom to top, the lower base layer 7 is stabilized with 7% lime fly ash; Granular asphalt concrete; 50% emulsified asphalt adhesive layer oil is used for bonding between the surface layer and the base layer, and the upper layer 4 is made of 6-10 cm fine-grained modified asphalt concrete; the thickness of the lower base layer 7 is 15-20 cm, and the thickness of the upper base layer 6 is 25 cm. ~30cm, with sufficient strength to resist bamboo whips.

上面层4和下面层5之间、下面层5与上基层6之间均用改性乳化沥青粘层进行粘合,可以加强面层之间的粘结,使相邻的面层和基层之前可以粘结成牢固的整体,以防止相邻两层之前出现滑动或者推移的现象,并且在路面结构中,由于为了保证路面结构的紧实性,其渗水性不强,通过改性乳化沥青粘层进行粘结可以起到一定的防水作用,提高了路面的强度、稳定性和防水能力。下封层采用表面均布有碎石的改性沥青制备而成,改性沥青为SBS改性沥青,可以有效改变路面结构强度,有效抵御竹鞭等植物根系对路面的破坏。Between the upper layer 4 and the lower layer 5, and between the lower layer 5 and the upper base layer 6, the modified emulsified asphalt adhesive layer is used for bonding, which can strengthen the bonding between the surface layers, so that the adjacent surface layer and the base layer It can be bonded into a firm whole to prevent sliding or pushing between adjacent two layers, and in the pavement structure, in order to ensure the compactness of the pavement structure, its water permeability is not strong, and the modified emulsified asphalt is bonded Layer bonding can play a certain role in waterproofing, improving the strength, stability and waterproofing capacity of the pavement. The lower seal layer is made of modified asphalt with gravel evenly distributed on the surface. The modified asphalt is SBS modified asphalt, which can effectively change the structural strength of the pavement and effectively resist the damage of plant roots such as bamboo whips to the pavement.

实施例中上面层4厚度为6~10cm,下面层5厚度为8~12cm,改性乳化沥青粘层采用PC-3型乳化沥青,且PC-3型乳化沥青的洒布量在0.4~0.6L/m2In the embodiment, the thickness of the upper layer 4 is 6-10 cm, and the thickness of the lower layer 5 is 8-12 cm. The modified emulsified asphalt adhesive layer adopts PC-3 emulsified asphalt, and the spraying amount of PC-3 emulsified asphalt is 0.4-0.6 L/m 2 .

如图4所示,生态路缘石结构1包括上窄下宽、整体呈L型的本体20,本体20的内部设有L型贯通空腔,加大了积水过流量;本体20的下体上表面设有过水道22,本体20的上体、下体均间隔开设有排水口,排水口与L型贯通空腔连通;L型贯通空腔通过沿道路纵向间隔设置的急流槽17与坡底的边沟18连接,加大路面结构排水强度。As shown in Figure 4, the ecological curb structure 1 includes a body 20 that is narrow at the top and wide at the bottom, and is L-shaped as a whole. The surface is provided with a water passage 22, and the upper body and the lower body of the body 20 are evenly spaced with drainage outlets, and the drainage outlets are connected with the L-shaped through-cavity; The side ditch 18 is connected to increase the drainage strength of the pavement structure.

图1中左右两侧的生态路缘石结构1分别是整体结构的不同部位的横截面,右侧是与急流槽17相贯通部分结构的截面;左侧是未与急流槽17相贯通部分结构的截面,增大排水能力。The ecological curb structure 1 on the left and right sides in Fig. 1 is the cross-section of different parts of the overall structure respectively, the right side is the cross-section of the part of the structure connected with the rapids trough 17; the left side is the part of the structure not connected with the rapids trough 17 cross-section to increase drainage capacity.

L型贯通空腔包括基部石壁空腔内的主排水通道27和路缘部石壁空腔内的辅助排水通道26,主排水通道27和辅助排水通道26的横截面均为矩形,相连通形成L型贯通空腔。The L-shaped through cavity includes the main drainage channel 27 in the stone wall cavity at the base and the auxiliary drainage channel 26 in the stone wall cavity at the curb. The cross sections of the main drainage channel 27 and the auxiliary drainage channel 26 are both rectangular, and they are connected to form a type through cavity.

过水道22沿本体20的高度方向由L型拐弯处向下凹陷形成的半圆柱体(截面为圆弧形),过水道22的两端沿本体20长度方向贯通,用以防止雨水汇集从而导致土体强度降低致使边坡失稳破坏。The water passage 22 is a semi-cylindrical body (the cross section is arc-shaped) formed by the downward depression of the L-shaped corner along the height direction of the body 20. The two ends of the water passage 22 run through the length direction of the body 20 to prevent rainwater from collecting and causing Decreased soil strength leads to slope instability and failure.

每间隔15cm有一个5cm宽、7.5cm高的排水口,排水口包括高位排水口21和低位排水口23,高位排水口21设置在路缘石的上部,高于过水道22;低位排水口23的水平高度与路面结构齐平,每个路缘石有高位排水口21、低位排水口23。高位排水口21与辅助排水通道26直接连接,低位排水口23与主排水通道27直接连接,每间隔10m连接一个急流槽17,急流槽17与边沟18连通。当路面积水较少时,水位相对较低,积水从路面流向主排水通道27;当路面积水较多时(如突发暴雨),水位相对较高,积水流量较大超过低位排水口23时,通过高位排水口21流向辅助排水通道26,积水通过急流槽17排向边沟18,对边坡防护结构降雨时的积水导出并将导出水运送到其他地方的作用,对路面结构的积水进行排除。Every interval of 15cm has a 5cm wide, 7.5cm high drain, the drain includes a high drain 21 and a low drain 23, the high drain 21 is arranged on the top of the curb, higher than the waterway 22; the low drain 23 The horizontal height is flush with the road surface structure, and each curb has a high-level drainage outlet 21 and a low-level drainage outlet 23. The high drain 21 is directly connected to the auxiliary drain 26 , the low drain 23 is directly connected to the main drain 27 , and every 10m is connected to a rapid trough 17 , and the rapid trough 17 communicates with the side ditch 18 . When there is little water on the road, the water level is relatively low, and the accumulated water flows from the road to the main drainage channel 27; At 23 o'clock, it flows to the auxiliary drainage channel 26 through the high-level drainage port 21, and the accumulated water is discharged to the side ditch 18 through the torrent trough 17. Water accumulated in the structure is removed.

排水口为拱门式,高位排水口21、低位排水口23均设有拱门式拦污网,用于拦截路面的落叶、杂物以及绿化带的泥土,防止大量路面垃圾流走污染边坡;拦污网可拆卸方便清洗,拦污网孔径为5~20mm。The drains are arched, and the high drains 21 and the low drains 23 are equipped with arched trash traps, which are used to intercept fallen leaves, debris and soil in the green belt on the road surface, preventing a large amount of road garbage from flowing away from the polluted slope; The dirt net is detachable and easy to clean, and the pore size of the trash net is 5-20mm.

每个单独L型路缘石位于路面上的外露段24上半部分长75cm、宽15cm、高10cm,下半部分长75cm、宽20cm、高15cm,其中过水道22的圆弧半径为5cm,埋置在路面下的埋置段25厚10cm。Each independent L-shaped curb stone is located on the exposed section 24 on the road surface with a length of 75cm, a width of 15cm, and a height of 10cm, and a length of the lower half of 75cm, width of 20cm, and height of 15cm. The embedding section 25 placed under the road surface is 10cm thick.

由于路面结构过于紧密,路面渗水能力不强,路面结构表层3设有2%的排水横坡,路面水通过路缘石排向急流槽17最后流入边沟18,在保证路面对竹鞭的抵抗作用下从而达到一定的排水效果。Because the pavement structure is too tight and the water seepage capacity of the pavement is not strong, the surface layer 3 of the pavement structure is provided with a 2% drainage cross slope, and the pavement water drains to the rapid flow groove 17 through the curb stone and finally flows into the side ditch 18, so as to ensure the resistance of the pavement to the bamboo whip. Under the action to achieve a certain drainage effect.

如图3所示,路基边坡结构的路基由上路床9、下路床10、上路堤11、下路堤12组成,第一边坡填土层13、第二边坡填土层14、第三边坡填土层15、第四边坡填土层16具有不同压实度,遵循路基路面压实度规范,上路床9的压实度≥94%、下路床10的压实度≥94%、上路堤11的压实度≥93%、下路堤12的压实度≥90%。从下往上边坡填土层中残鞭填充量呈递增趋势,每层递增2%填充量,即从下往上残鞭填充质量分数分别为8%、10%、12%、14%。越往上越有细小的竹鞭透过空隙向上延伸,此时就需要增加残鞭含量,通过减小土壤孔隙率以及利用竹鞭避硬性抵御竹鞭向上延伸。As shown in Figure 3, the subgrade of the subgrade slope structure is composed of an upper road bed 9, a lower road bed 10, an upper embankment 11, and a lower embankment 12. The first side slope filling layer 13, the second side slope filling layer 14, the second side slope filling layer The third side slope filling layer 15 and the fourth side slope filling layer 16 have different compaction degrees, follow the subgrade road surface compaction degree specification, the compaction degree of the upper road bed 9 is ≥94%, and the compaction degree of the lower road bed 10 is ≥ 94%, the compaction degree of the upper embankment 11≥93%, and the compaction degree of the lower embankment 12≥90%. The filling amount of remnant whip in the slope filling layer from bottom to top shows an increasing trend, and the filling amount increases by 2% for each layer, that is, the mass fraction of remnant whip filling from bottom to top is 8%, 10%, 12%, and 14%, respectively. The higher you go, the more tiny bamboo whips extend upwards through the gaps. At this time, it is necessary to increase the content of residual bamboo whips to resist the upward extension of bamboo whips by reducing the porosity of the soil and using the bamboo whips to avoid hardness.

在一些实施例中,由于边坡斜率在1:1.75,对于边坡浅层填土压实度不同土层的填充量也不一样,在路基填土过程中必须严格控制经碾压实验确定的压实度,压实合格后才可铺筑新的上层新料,机械压实不到的地方和压实面积过小的地方采用小型压实机进行压实,并且在填筑完成后要对填筑边坡进行整形。In some embodiments, since the slope slope is 1:1.75, the filling amount of the soil layer is not the same for the shallow filling soil compaction degree of the slope, and the filling amount determined by the rolling test must be strictly controlled during the filling process of the roadbed. The degree of compaction can only be paved with new materials for the upper layer after the compaction is qualified. The places that cannot be compacted by mechanical compaction and the places where the compacted area is too small should be compacted with a small compactor, and after the filling is completed, the Fill the slope for shaping.

在一些实施例中,边坡浅层采用分层包边或加筋,在路基边坡结构中利用该公路路堑或隧道挖方石料经破碎填筑在路基边坡外侧形成边坡碎石层A1,通过碎石之间的嵌挤密实达到阻碍竹鞭生长的目的;其次,在植生层19中加入残鞭,竹鞭遇到残鞭等根系会避让的避硬性特征,一方面可以增强对竹鞭的抵御能力,防止对路面结构的破坏,另一方面可以起到加筋作用,防止边坡坍塌的同时也可以减小大气干湿循环作用对填料湿度的影响,同时边坡上的急流槽17可以汇集路面上的水流使其顺利流出汇入边沟18,这样进一步提高了雨水从路面排出的排水效率,同时降低了雨水对路面基边坡的冲刷,增强了边坡稳定性。In some embodiments, layered edge wrapping or reinforcement is adopted for the shallow layer of the slope. In the subgrade slope structure, the excavated stones of the highway cutting or tunnel are crushed and filled on the outside of the subgrade slope to form the slope gravel layer A1. The purpose of hindering the growth of bamboo whips is achieved by embedding and compacting between the crushed stones; secondly, adding residual whips in the vegetation layer 19, the bamboo whips will avoid the hard characteristics that roots such as stumps will avoid, on the one hand, it can strengthen the bamboo whips on the other hand, it can play a reinforcing role, prevent the slope from collapsing, and at the same time reduce the impact of the atmospheric dry-wet cycle on the filler humidity. At the same time, the rapid flow trough 17 The water flow on the road surface can be collected to make it flow smoothly into the side ditch 18, which further improves the drainage efficiency of rainwater from the road surface, reduces the erosion of the rainwater on the road foundation slope, and enhances the stability of the slope.

在制备混凝土的同时将高强度纤维的纤维束均匀地搅拌在混凝土中,加上脂环族类环氧树脂的胶凝性与颗粒状残鞭等的填充性,得到的道路路面混凝土以及路缘石试件的制备材料无论是柔韧性还是强度方面都有较大的提升,该混凝土材料具有成本低廉、制作方便等优点,同时具有粘聚力和密实性较好的特点,该混凝土比传统的混凝土更加耐用坚固,对外界环境的适应性更强,极大的延长了路面结构的使用寿命。While preparing concrete, the fiber bundles of high-strength fibers are uniformly mixed in the concrete, and the cementation of alicyclic epoxy resin and the filling properties of granular residual whips are added to obtain road pavement concrete and curbstones. The preparation material of the specimen has been greatly improved in terms of flexibility and strength. The concrete material has the advantages of low cost, convenient production, etc., and has the characteristics of better cohesion and compactness. The concrete is better than the traditional concrete. It is more durable and firm, and has stronger adaptability to the external environment, which greatly prolongs the service life of the pavement structure.

高强度纤维选用聚丙烯腈纤维,纤维直径选择13微米,具有抗拉强度高,初始模量大,化学性能稳定,该纤维具有耐酸碱腐蚀性、耐光性、耐候性,并具有良好的分散性,能改善混凝土的粘结性、抗疲劳性,增强混凝土的抗渗、抗冻、抗冲击能力使混凝土承担更多的受荷应力,其弯曲韧性比素混凝土提高6倍以上;具有较强的耐磨性与耐化学腐蚀性,室外环境下的高强度暴晒-降雨等干湿循环情况下也能够保持较好的力学性能。The high-strength fiber is made of polyacrylonitrile fiber, and the fiber diameter is 13 microns. It has high tensile strength, large initial modulus, and stable chemical properties. The fiber has acid and alkali corrosion resistance, light resistance, weather resistance, and has good dispersion. It can improve the cohesiveness and fatigue resistance of concrete, enhance the impermeability, frost resistance and impact resistance of concrete so that concrete can bear more load stress, and its bending toughness is more than 6 times higher than that of plain concrete; it has strong Excellent wear resistance and chemical corrosion resistance, and it can also maintain good mechanical properties under high-intensity exposure-rainfall and other dry-wet cycle conditions in outdoor environments.

实施例2,Example 2,

一种南方竹林区公路路基路面根胀变形调控结构的施工方法,具体步骤如下:A construction method for the control structure of the root swelling deformation of the subgrade road surface of the southern bamboo forest area. The specific steps are as follows:

S1、铺筑路基;先进行边坡填土施工,在填土前,将场地表面进行清理干净。若在地表表面,有多个积水坑,应当将地表表面上的积水以及含水率过大的泥土进行清除替换后回填,保证路面填土的干燥,然后利用堆卸车配以挖土机、推土机联合整体进行填土,碾压的原则要秉承“薄填、慢驶、多次”,碾压方向应当从里向外。路线要注意重合搭接。在运行的过程中振动碾压机械距填方边缘应大于2.0m,防止发生溜坡倾倒,其中对于上路床9、下路床10、上路堤11、下路堤12进行分层压实,要严格控制经碾压实验确定的压实参数,每层压实合格之后才准许铺筑新的上层新料。在填筑的过程中,填筑力求全断面平行上升,分段填筑时,每层接缝处应作1:1.75斜坡面,碾压迹象重叠1m。上下分层分段错开,错缝距离不小于1m。路基两侧从在至上依次填筑第四边坡填土层16、第三边坡填土层15、第二边坡填土层14、填筑第一边坡填土层13。S1. Pave the roadbed; carry out the side slope filling construction first, and clean up the surface of the site before filling. If there are multiple puddles on the ground surface, the accumulated water on the surface and the soil with excessive moisture content should be removed and replaced, and then backfilled to ensure that the road fill is dry, and then use a dump truck with an excavator, The bulldozer is combined with the whole to fill the soil, and the principle of rolling should be "thin filling, slow driving, and multiple times", and the rolling direction should be from the inside to the outside. Pay attention to overlapping and overlapping routes. During operation, the vibratory rolling machine should be more than 2.0m away from the edge of the fill to prevent the slope from toppling over. Among them, the layered compaction of the upper road bed 9, the lower road bed 10, the upper embankment 11, and the lower embankment 12 must be strictly The compaction parameters determined by the rolling test are controlled, and the new upper layer of new materials is allowed to be paved only after each layer of compaction is qualified. During the filling process, the filling shall strive to raise the entire section in parallel. When filling in sections, the joints of each layer shall be sloped at a ratio of 1:1.75, and the signs of rolling shall overlap by 1m. The upper and lower layers are staggered in sections, and the distance between the staggered joints is not less than 1m. On both sides of the subgrade, the fourth side slope filling layer 16 , the third side slope filling layer 15 , the second side slope filling layer 14 , and the first side slope filling layer 13 are filled sequentially from top to bottom.

S2、在路基边坡外侧铺设边坡碎石层A1,利用该公路路堑或隧道挖方石料经破碎后进行填筑铺设;对边坡进行挂网,挂网采用从上向下、自左向右的放卷方式,在同一边坡层上的相邻挂网进行铁丝绑定。S2. Lay the side slope gravel layer A1 on the outside of the subgrade side slope, use the road cutting or tunnel excavated stones to be filled and paved after crushing; hang the net on the side slope from top to bottom and from left to right The unwinding method is adopted, and the adjacent hanging nets on the same slope layer are bound with iron wires.

S3、将处理好的植物种子与竹残鞭、胶凝剂、保水剂、营养肥料、泥浆搅拌均匀后,通过喷播机将混合物均匀喷洒在边坡碎石层A1形成植生层19,通过植物生态防护进一步防止水土流失。植物种子采用混合植物种子,高羊茅、百喜草、狗牙根按照4:5:1的质量比例混合,1m2坡面共配置30g植物种子,竹残鞭用量为30g/m2。胶凝剂、保水剂、营养肥料、泥浆每0.1m3混合物的用量比例为0.05kg:0.05kg:0.15kg:30kg。S3. After stirring the treated plant seeds with bamboo residue, gelling agent, water-retaining agent, nutrient fertilizer, and mud evenly, the mixture is evenly sprayed on the slope gravel layer A1 by a sprayer to form a vegetation layer 19. Ecological protection further prevents soil erosion. Mixed plant seeds are used for plant seeds. Tall fescue, bahia grass, and bermudagrass are mixed in a mass ratio of 4:5:1. A total of 30g of plant seeds are placed on a 1m 2 slope, and the amount of bamboo residue is 30g/m 2 . The dosage ratio of gelling agent, water retaining agent, nutrient fertilizer and mud per 0.1m 3 mixture is 0.05kg: 0.05kg: 0.15kg: 30kg.

喷射分两次进行,首先喷射不含种子的混合料,喷射厚度7~8cm,紧接着第二次喷射含有种子的混合料,喷射厚度2~3cm。喷射混合材料平均厚度10cm,变幅为3~15cm;尽量垂直边坡喷播,避免仰喷、俯喷或者斜喷,且喷播过程应该来回反复,不应该在某个点位中进行喷播,保证喷播厚度均匀。Spraying is carried out twice, first spraying the mixture without seeds, spraying thickness 7-8cm, followed by spraying the mixture containing seeds for the second time, spraying thickness 2-3cm. The average thickness of the sprayed mixed material is 10cm, and the amplitude is 3-15cm; try to spray vertically on the slope, avoid spraying upwards, downwards or obliquely, and the spraying process should be repeated back and forth, and should not be sprayed at a certain point , to ensure uniform spraying thickness.

植生层19内横向有间距的插入8~10cm的残鞭,间距范围为10~15cm,植生层19中残鞭的加入质量分数10%左右(9%~11%),超过对应范围会破坏植生层植物生存率,低于对应范围残鞭起不到防御措施,在起到绿色环保的前提下利用竹鞭避硬性的特性对残鞭以及碎石层进行“躲避”。In the vegetation layer 19, insert 8-10 cm residual whips with intervals in the horizontal direction. The spacing range is 10-15 cm. The mass fraction of residual whips in the vegetation layer 19 is about 10% (9%-11%). Exceeding the corresponding range will destroy the vegetation. If the survival rate of plants in the layer is lower than the corresponding range, the residual whip cannot take defensive measures. Under the premise of being green and environmentally friendly, the bamboo whip can be used to "dodge" the residual whip and the gravel layer under the premise of being green and environmentally friendly.

S4、在整平好的路堤上铺设碎石垫层,碎石基层包括下基层7和上基层6,下基层7采用7%石灰粉煤灰稳定类底基层、上基层6用5%石灰粉煤灰稳定砂砾石基层,下基层7的厚度200mm、上基层6的厚度300mm,上面层4的厚度40mm、下面层5的厚度60mm。上路床9上方的沥青路面结构2的两侧边坡填筑有路侧填土层8。S4. Lay the crushed stone cushion on the leveled embankment. The crushed stone base includes the lower base 7 and the upper base 6. The lower base 7 adopts 7% lime fly ash stabilized subbase, and the upper base 6 uses 5% lime powder. Coal ash stabilized gravel base, the thickness of the lower base 7 is 200mm, the thickness of the upper base 6 is 300mm, the thickness of the upper layer 4 is 40mm, and the thickness of the lower layer 5 is 60mm. The side slopes on both sides of the asphalt pavement structure 2 above the upper road bed 9 are filled with a roadside fill layer 8 .

竹鞭深度一般在地下500mm以上,其中路面压实采用碾压式,分层碾压,压实度>95%;在下基层7实施前先确定水泥用量,其中下基层7采用集中拌合,路单层压实,压实度≥96%,水泥稳定碎石底基层铺筑完成后,必须进行养护以及路面管制。在洒水的过程中要严格控制水量,严禁有泡水现象产生。上基层6采用集中拌和,分两层碾压,压实度≥98%。等到表面稍变干燥但是还未完全硬化时,在路下浇灌透层并及时铺设沥青下封层。上基层6的压实度大于98%,下基层7的压实度大于96%。The depth of the bamboo whip is generally more than 500mm underground, and the road surface compaction adopts rolling type, layered rolling, and the compaction degree is more than 95%. Single-layer compaction, compaction degree ≥ 96%, after the cement-stabilized gravel subbase is paved, maintenance and road surface control must be carried out. In the process of sprinkling water, the amount of water should be strictly controlled, and water soaking is strictly prohibited. The upper base layer 6 adopts concentrated mixing and is rolled in two layers, and the compaction degree is more than or equal to 98%. When the surface is slightly dry but not completely hardened, pour the permeable layer under the road and lay the asphalt lower seal in time. The degree of compaction of the upper base layer 6 is greater than 98%, and the degree of compaction of the lower base layer 7 is greater than 96%.

为使沥青路面结构2的面层与基层之间的联结更好,在基层上面喷洒高渗透性乳化沥青,透层、封层均由PC-3型乳化沥青制备而成,透层的渗透深度达到上基层6表面5mm以上的深度,透层、封层起着过渡、粘结以及固结基层表面的作用,乳化沥青的使用减少了层间破坏,对提高路面的耐久性起到了非常重要的作用。在铺筑的过程中要注意好各层之间的清洁工作,保证各层之间打扫干净防止杂土影响各层之间的粘结情况。改性乳化沥青粘层可以加强上面层4、下面层5、上基层6、下基层7彼此之间的粘结,使相邻的面层和基层之前可以粘结成牢固的整体,以防止相邻两层之前出现滑动或者推移的现象,并且在路面结构中,由于为了保证路面结构的紧实性,其渗水性不强,运用改性乳化沥青粘层进行粘结可以起到一定的防水作用。In order to make the connection between the surface layer and the base layer of the asphalt pavement structure 2 better, high-permeability emulsified asphalt is sprayed on the base layer. The permeable layer and the seal layer are made of PC-3 emulsified asphalt. Reach the depth of 5mm above the surface of the upper base layer. The penetration layer and the sealing layer play the role of transition, bonding and consolidation of the base layer surface. The use of emulsified asphalt reduces interlayer damage and plays a very important role in improving the durability of the road surface. effect. During the paving process, attention should be paid to the cleaning work between the layers to ensure that the layers are cleaned to prevent the soil from affecting the bonding between the layers. The modified emulsified asphalt adhesive layer can strengthen the bonding between the upper layer 4, the lower layer 5, the upper base layer 6, and the lower base layer 7, so that the adjacent surface layer and the base layer can be bonded into a firm whole to prevent mutual There is a phenomenon of sliding or pushing before the adjacent two layers, and in the pavement structure, in order to ensure the compactness of the pavement structure, its water permeability is not strong, and the use of modified emulsified asphalt adhesive layer for bonding can play a certain role in waterproofing .

乳化沥青是沥青和乳化剂在一定工艺作用下,生成水包油或油包水的液态沥青;从结构来看,乳化剂是由非极性的疏水基和极性的亲水基组成的两亲性分子,这种结构使乳化剂在溶液表(界)面形成定向紧密排列,改变了体系的表(界)面化学性质;较好地解决沥青高温易流淌泛油、低温硬脆开裂等不足。Emulsified asphalt is a liquid asphalt that is produced by asphalt and emulsifier under a certain process; from the structure point of view, the emulsifier is composed of a non-polar hydrophobic group and a polar hydrophilic group. Affinity molecules, this structure makes the emulsifier form a directional and dense arrangement on the surface (interface) of the solution, changing the chemical properties of the surface (interface) of the system; it better solves the problem of asphalt flowing and oiling at high temperature, hard and brittle cracking at low temperature, etc. insufficient.

路面结构表层3表面呈现一定的倾斜角度,从内到外倾斜角度为2%(即排水横坡),由于路面结构的紧密性,一定角度的倾斜角度可以增加路面的排水能力。The surface of pavement structure surface layer 3 presents a certain inclination angle, and the inclination angle from inside to outside is 2% (i.e. drainage cross slope). Due to the tightness of the pavement structure, a certain inclination angle can increase the drainage capacity of the pavement.

S5、在路面两旁设置生态路缘石结构1,生态路缘石结构1的基础与路面基层同时填挖和碾压的,生态路缘石结构1的埋置段25埋置在路面下,进一步对浅层竹鞭进行抵御;位于路面以上的外露段24按照与道路路面齐平的位置刨槽、找平、夯实后再安砌,每隔10m设置一个开口将生态路缘石结构1内部的L型贯通空腔与急流槽17相连接,急流槽17沿道路纵向间隔设置,急流槽17与坡底的边沟18连接,方便将路面上的水排除。S5. Ecological curb structure 1 is set on both sides of the road surface. If the foundation of ecological curb structure 1 is filled and excavated and rolled at the same time as the pavement base, the embedded section 25 of ecological curb structure 1 is buried under the road surface. Bamboo whips to resist; the exposed section 24 above the road surface is planed, leveled, and compacted according to the position flush with the road surface, and then installed, and an opening is set every 10m to connect the L-shaped through cavity inside the ecological curb structure 1 It is connected with the rush trough 17, and the rush trough 17 is arranged at intervals along the longitudinal direction of the road, and the rush trough 17 is connected with the side ditch 18 at the bottom of the slope, so that the water on the road surface can be easily removed.

在生态路缘石结构1和路面结构之间需要灌缝(原浆勾缝),原浆材料参照竹鞭骨料生态路缘石制备材料,路缘石安装接缝为1cm,用1:2水泥砂浆勾满、勾实接缝,饱和度≥80%,稠度14~18s。在勾缝时要注意保护路缘石不受到砂浆的污染,可以先使用塑料胶条将路缘石接缝两侧粘好再开始勾缝、路缘石要做到安砌稳固,顶面平整,缝宽均匀,勾缝密实,线条顺畅,保证外露高度为150mm左右。Between the ecological curb structure 1 and the pavement structure, it is necessary to fill joints (prototype pointing). The raw material is prepared according to the bamboo whip aggregate ecological curb. The installation joint of the curb is 1cm, and it is hooked with 1:2 cement mortar Full and solid joints, saturation ≥ 80%, consistency 14-18s. When pointing, pay attention to protecting the curb from being polluted by mortar. You can first use plastic tape to glue the two sides of the joint of the curb and then start pointing. The curb should be firmly installed, the top surface is flat, and the seam is wide Uniform, dense pointing, smooth lines, to ensure that the exposed height is about 150mm.

实施例3,Example 3,

按照以下重量份数称取该公路路堑或隧道挖方石料40份、氢氧化钙10份、粉煤灰10份、竹木纤维3份、硅酸盐水泥10份、脂环族类环氧树脂8份、水5份。竹木纤维为长度10mm的毛竹残鞭。Take by weighing 40 parts of the road cutting or tunnel excavation stone, 10 parts of calcium hydroxide, 10 parts of fly ash, 3 parts of bamboo and wood fiber, 10 parts of Portland cement, and 8 parts of alicyclic epoxy resin according to the following parts by weight. 5 parts, water 5 parts. Bamboo fiber is the remnant whip of moso bamboo with a length of 10mm.

本发明实施例的生态路缘石结构1采用当地废弃石料、氢氧化钙、粉煤灰作基层,残鞭纤维作增强抗压材料,在双向高压力的作用之下压制成路缘石。The ecological curb structure 1 of the embodiment of the present invention uses local waste stone, calcium hydroxide, and fly ash as the base layer, and remnant whip fiber as the reinforced anti-compression material, and is pressed into the curb under the action of two-way high pressure.

具体制作方法:Specific production method:

先将竹木纤维(残鞭)及该公路路堑或隧道挖方石料进行破碎,通过不同粒径筛孔筛分出粒径为0.075~2mm的细骨料、粒径为5~20mm的粗骨料,并且筛分排出杂质;First, the bamboo and wood fiber (residual whip) and the road cutting or tunnel excavation stone are crushed, and the fine aggregate with a particle size of 0.075-2mm and the coarse aggregate with a particle size of 5-20mm are screened through different particle size sieves. , and sieve out impurities;

按照对应的重量份称取挖方石料、氢氧化钙、粉煤灰、竹木纤维、硅酸盐水泥、环氧树脂、水;送入搅拌机,搅拌6min,得到混合料;Weigh the excavated stone, calcium hydroxide, fly ash, bamboo and wood fiber, Portland cement, epoxy resin, water according to the corresponding parts by weight; send it into the mixer, stir for 6 minutes, and obtain the mixture;

将搅拌好的混合料灌入路缘石模型中,35~40兆帕双向高压力下静压成型;Pour the stirred mixture into the curbstone model, and statically press it under 35-40 MPa bidirectional high pressure;

将静压成型的生态路缘石自然养护7~14天即可。Naturally maintain the ecological curb stone formed by static pressure for 7-14 days.

实施例4,Example 4,

按照以下重量份数称取该公路路堑或隧道挖方石料50份、氢氧化钙15份、粉煤灰12份、竹木纤维4份、硅酸盐水泥13份、脂环族类环氧树脂12份、水5份;按照实施例3的方法制备生态路缘石结构1,竹木纤维为长度10mm的毛竹残鞭。Take by weighing 50 parts of the road cutting or tunnel excavation stone, 15 parts of calcium hydroxide, 12 parts of fly ash, 4 parts of bamboo and wood fiber, 13 parts of Portland cement, and 12 parts of cycloaliphatic epoxy resin according to the following parts by weight. 5 parts, 5 parts of water; Ecological curb structure 1 is prepared according to the method of embodiment 3, and the bamboo wood fiber is the residual whip of moso bamboo with a length of 10mm.

实施例5,Example 5,

按照以下重量份数称取该公路路堑或隧道挖方石料70份、氢氧化钙20份、粉煤灰15份、竹木纤维5份、硅酸盐水泥16份、脂环族类环氧树脂15份、水5份;按照实施例3的方法制备生态路缘石结构1;竹木纤维为长度6mm的毛竹残鞭。Take by weighing 70 parts of the road cutting or tunnel excavation stone, 20 parts of calcium hydroxide, 15 parts of fly ash, 5 parts of bamboo fiber, 16 parts of Portland cement, and 15 parts of cycloaliphatic epoxy resin according to the following parts by weight. 5 parts, 5 parts of water; Ecological curb structure 1 is prepared according to the method of embodiment 3; Bamboo wood fiber is the residual whip of moso bamboo with a length of 6mm.

实施例6,Example 6,

按照以下重量份数称取该公路路堑或隧道挖方石料20份、氢氧化钙5份、粉煤灰8份、竹木纤维2份、硅酸盐水泥8份、脂环族类环氧树脂5份、水1份;按照实施例3的方法制备生态路缘石结构1;竹木纤维为长度8mm的毛竹残鞭。Take by weighing 20 parts of the road cutting or tunnel excavation stone, 5 parts of calcium hydroxide, 8 parts of fly ash, 2 parts of bamboo fiber, 8 parts of Portland cement, 5 parts of cycloaliphatic epoxy resin according to the following parts by weight. 1 part, 1 part of water; ecological curb structure 1 is prepared according to the method of embodiment 3; the bamboo fiber is the residual whip of moso bamboo with a length of 8mm.

对比例1,Comparative example 1,

生态路缘石在原料中不含竹木纤维、脂环族类环氧树脂、氢氧化钙,其余与实施例3相同。The ecological curb does not contain bamboo fiber, cycloaliphatic epoxy resin, and calcium hydroxide in the raw materials, and the rest are the same as in Example 3.

实施例3-6以及对比例1的抗压、抗拉强度试验数据见表1,实施例3-6以及对比例1的排水性能试验数据见表2,图5、6所示。The compressive and tensile strength test data of Examples 3-6 and Comparative Example 1 are shown in Table 1, and the drainage performance test data of Examples 3-6 and Comparative Example 1 are shown in Table 2, as shown in Figures 5 and 6.

表1路缘石的力学性能试验数据Table 1 The mechanical performance test data of curb stone

平均抗压强度/MPaAverage compressive strength/MPa 平均抗拉强度/MPaAverage tensile strength/MPa 实施例3Example 3 35.835.8 5.25.2 实施例4Example 4 36.436.4 4.94.9 实施例5Example 5 35.935.9 5.15.1 实施例6Example 6 36.236.2 5.05.0 对比例1Comparative example 1 32.132.1 4.34.3

表2路缘石的排水性能试验数据Table 2 Drainage performance test data of curbs

Figure BDA0004136490460000101
Figure BDA0004136490460000101

生态路缘石结构1的原料采用环保型材料,由以下重量份数组成:路堑或隧道挖方石料20~70份、氢氧化钙10~20份、粉煤灰8~15份、竹木纤维2~5份、硅酸盐水泥8~16份、脂环族类环氧树脂5~15份、水1~6份;其中,竹木纤维为毛竹的颗粒状残鞭,以加强路面对竹鞭的抵抗能力,加强路面结构的压实度,增强路面结构的密度。超出对应范围会破坏路缘石强度以及使用寿命;如果原料组成超出范围会导致预制路缘石的混凝土构件无法成型;比如作为粗骨料的公路路堑或隧道挖方石料占比过大,将导致路缘石易开裂、过少则强度不够;氢氧化钠掺入量超过对应范围,会腐蚀硅酸盐水泥,破坏路缘石结构;脂环族类环氧树脂掺入量超过对应范围,会降低路缘石韧性致使其容易开裂。Ecological curbstone structure 1 is made of environment-friendly materials, consisting of the following parts by weight: 20-70 parts of road cutting or tunnel excavation stone, 10-20 parts of calcium hydroxide, 8-15 parts of fly ash, 2-20 parts of bamboo and wood fiber 5 parts, 8-16 parts of Portland cement, 5-15 parts of alicyclic epoxy resin, 1-6 parts of water; among them, the bamboo wood fiber is the granular residual whip of moso bamboo to strengthen the road surface. The resistance ability, strengthen the compactness of the pavement structure, enhance the density of the pavement structure. Exceeding the corresponding range will damage the strength and service life of the curb; if the composition of raw materials exceeds the range, the concrete components of the prefabricated curb will not be formed; If the amount of sodium hydroxide added exceeds the corresponding range, it will corrode Portland cement and destroy the structure of the curb stone; if the amount of alicyclic epoxy resin added exceeds the corresponding range, the toughness of the curb stone will be reduced. It cracks easily.

实施例中路缘石细骨料选用细度模数为2.7~3.3、粒径为0.075~2mm的中砂;粗骨料选用最大粒径不大于20mm、最小粒径不小于5mm的废弃路面面板建筑废料以及该公路路堑或隧道挖方石料等,节约成本、增强路缘石强度。细骨料和粗骨料一起构成挖方石料,细骨料和粗骨料的质量比是5:1。In the embodiment, the curb fine aggregate is medium sand with a fineness modulus of 2.7 to 3.3 and a particle size of 0.075 to 2 mm; the coarse aggregate is selected from abandoned pavement panel construction waste with a maximum particle size of not more than 20 mm and a minimum particle size of not less than 5 mm As well as the road cutting or tunnel excavation stones, etc., saving costs and enhancing the strength of curbs. Fine aggregate and coarse aggregate together constitute excavation stone, and the mass ratio of fine aggregate to coarse aggregate is 5:1.

粉煤灰的比例在20%左右;其中掺和2~10mm大小的残鞭,选择合适范围内的残鞭尺寸、对自然状态下的残鞭进行研磨使其分段;水泥为强度等级为42.5的硅酸盐水泥;使用脂环族类环氧树脂可以增强混凝土之间的胶凝性和抗弯折性,不仅具有粘合力高,固化物力学性能好的特点,并且对于温度的耐用性也很强,不管是在高温环境还是超低温环境条件下,都具有较高的粘结强度,可以在改善高强度特种纤维与水泥砂浆之间的粘合性的同时提高混凝土构件对于室外温度的适应性;残鞭颗粒作为填充物可以对混凝土的粗细骨料内部孔隙进行有效填补,减少混凝土的孔隙率以及混凝土在使用过程中产生的裂纹及弯折,提升混凝土构件的柔韧性,在混凝土及砂浆中起骨架和填充作用,增加稳定性,在减少成本、节约环保的同时起到抵御根系破坏的作用;(氢氧化钠)掺入其使得路缘石干缩性能好、抗冻融性好、抗掺性能强、减小混凝土的徐变。公路路堑或隧道挖方石料作为粗骨料、竹木纤维(残鞭颗粒)作为填充物、在浇筑混凝土的情况下,掺加氢氧化钠、脂环族类环氧树脂对混凝土构件进行改善,原料相互配合一起协作,进一步增强路缘石构件强度、提升抗压强度,对温度的耐用性强,从而抵御因温度变化造成的路缘石裂纹与弯折,排水能力强。The proportion of fly ash is about 20%; it is mixed with 2-10mm remnant whip, choose the size of remnant whip within the appropriate range, grind the remnant whip in the natural state to make it segmented; the strength grade of cement is 42.5 Portland cement; the use of cycloaliphatic epoxy resin can enhance the gelation and bending resistance between concrete, not only has the characteristics of high adhesion, good mechanical properties of the cured product, and durability to temperature It is also very strong, whether it is in a high temperature environment or an ultra-low temperature environment, it has a high bond strength, which can improve the adhesion between high-strength special fibers and cement mortar and improve the adaptation of concrete components to outdoor temperature Residual whip particles as fillers can effectively fill the internal pores of concrete coarse and fine aggregates, reduce the porosity of concrete and the cracks and bending of concrete during use, and improve the flexibility of concrete components. It plays the role of skeleton and filling in the middle, increases stability, and plays a role in resisting root damage while reducing costs and saving environmental protection; (sodium hydroxide) is mixed with it to make curbs have good dry shrinkage performance, good freeze-thaw resistance, and anti-corrosion. It has strong mixing performance and reduces the creep of concrete. Road cuttings or tunnel excavation stones are used as coarse aggregates, bamboo and wood fibers (residual whip particles) are used as fillers, and in the case of pouring concrete, sodium hydroxide and cycloaliphatic epoxy resin are added to improve concrete components. Cooperate with each other to further enhance the strength of curb stone components, improve the compressive strength, and have strong durability to temperature, so as to resist cracks and bending of curb stones caused by temperature changes, and have strong drainage capacity.

本实施例在边坡填土过程中利用该公路路堑或隧道挖方石料经破碎填筑在路基边坡外侧形成边坡碎石层,通过碎石之间的嵌挤密实达到阻碍竹鞭生长的目的;其次,在植生层19中加入残鞭,起到对植生层加筋和抑制竹鞭在植生层中生长的目的,在保证加筋作用的同时,起到了防止边坡坍塌,增大边坡整体强度以及抵御根系的作用。对于边坡填土采用的碾压法与夯实法,碾压法是利用机械滚轮的压力压实土壤,使之达到所需的密实度;夯实法是利用夯锤自由下落的冲击力来夯实土壤,土体孔隙被压缩,土粒排列得更加紧密。两种方法相结合使边坡填土更加紧密在,可以抵御竹鞭横向生长。从而达到抵御根系破坏的作用。In this embodiment, during the slope filling process, the road cutting or tunnel excavated stones are crushed and filled on the outside of the roadbed slope to form a slope gravel layer, and the purpose of hindering the growth of bamboo whips is achieved by embedding and compacting between the gravels. Secondly, adding the residual whip in the vegetation layer 19 plays the purpose of reinforcing the vegetation layer and suppressing the growth of the bamboo whip in the vegetation layer. While ensuring the reinforcing effect, it prevents the slope from collapsing and increases the slope Overall strength and action against roots. The rolling method and tamping method are used for slope filling. The rolling method is to use the pressure of mechanical rollers to compact the soil to achieve the required density; the tamping method is to use the impact force of the rammer to tamp the soil. , the soil pores are compressed, and the soil particles are arranged more tightly. The combination of the two methods makes the slope fill more compact and can resist the lateral growth of bamboo whips. So as to achieve the effect of resisting root damage.

由于竹鞭横向生长的特性,生长范围大,如果利用混凝土装置进行固根,很难全方位的进行防护,涉及范围过大、成本大幅增加;本发明实施例对生态路缘石结构1、沥青路面结构2以及路基边坡结构进行改进,并且三者之间相互配合,相辅相成,构成和谐稳定的防护体系,在不破坏路面结构性能的前提下增强其强度,抵御了竹鞭根系透过缝隙生长,同时增大了积水的流通性,提升了排水性能,在能够全方位进行防护的同时也能减少造价成本。本发明实施例通过利用竹鞭“避硬下潜”的特性,通过增大路缘石埋置深度、路面结构厚度,降低路面结构层的孔隙率(4~6%),从而改变延伸方向,通过根胀变形调控,控制竹鞭向下弯曲生长。Due to the characteristics of the horizontal growth of bamboo whips, the growth range is large. If concrete devices are used to consolidate the roots, it is difficult to protect them in all directions, the scope is too large, and the cost is greatly increased; Structure 2 and the subgrade slope structure are improved, and the three cooperate with each other and complement each other to form a harmonious and stable protection system, which enhances its strength without destroying the structural performance of the pavement, and resists the growth of bamboo whip roots through the gaps. At the same time, the circulation of accumulated water is increased, the drainage performance is improved, and the cost of construction can be reduced while providing comprehensive protection. In the embodiment of the present invention, by using the characteristics of bamboo whips "avoiding hard dives", by increasing the embedding depth of curb stones and the thickness of pavement structure, and reducing the porosity (4-6%) of pavement structure layer, thereby changing the extension direction, through root The bulging deformation is regulated to control the downward bending growth of the bamboo whip.

以上所述仅为本发明的较佳实施例而已,并非用于限定本发明的保护范围。凡在本发明的精神和原则之内所作的任何修改、等同替换、改进等,均包含在本发明的保护范围内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present invention are included in the protection scope of the present invention.

Claims (10)

1.一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,包括:1. A root swelling deformation control structure of the road subgrade pavement in the South Bamboo Forest District, is characterized in that, comprising: 沥青路面结构(2),所述沥青路面结构的厚度与竹鞭在地下生长深度相匹配,路面结构表层(3)设有排水横坡;An asphalt pavement structure (2), the thickness of the asphalt pavement structure matches the depth of bamboo whips growing underground, and the surface layer (3) of the pavement structure is provided with a drainage transverse slope; 生态路缘石结构(1),所述生态路缘石结构(1)包括上窄下宽、整体呈L型的本体(20),本体(20)的内部设有L型贯通空腔,本体(20)的下体上表面设有过水道(22),过水道(22)的两端沿本体(20)长度方向贯通;本体(20)的上体、下体均间隔开设有排水口,排水口与L型贯通空腔连通,L型贯通空腔通过沿道路纵向间隔设置的急流槽(17)与坡底的边沟(18)连接;An ecological curb structure (1), the ecological curb structure (1) includes a body (20) that is narrow at the top and wide at the bottom, and is generally L-shaped. The body (20) is provided with an L-shaped through cavity inside, and the body (20) ) is provided with a water channel (22) on the upper surface of the lower body, and the two ends of the water channel (22) run through along the length direction of the body (20); The L-shaped through cavity is connected, and the L-shaped through cavity is connected with the side ditch (18) at the bottom of the slope through the rush trough (17) arranged at intervals along the longitudinal direction of the road; 路基边坡结构,所述路基边坡结构的边坡填土层从下至上土层中残鞭填充量逐渐递增。The embankment side slope structure, wherein the amount of remnant whip filling in the side slope filling layer of the roadbed side slope structure gradually increases from bottom to top. 2.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述生态路缘石结构(1)的原料由以下重量份数组成:挖方石料20~70份、氢氧化钙10~20份、粉煤灰8~15份、竹木纤维2~5份、硅酸盐水泥8~16份、脂环族类环氧树脂5~15份、水1~6份;其中,竹木纤维为毛竹的颗粒状残鞭。2. According to claim 1, a structure for regulating and controlling the root swelling deformation of roadbed and pavement in the southern bamboo forest area, is characterized in that, the raw materials of the ecological curb structure (1) are composed of the following parts by weight: 20-70 parts of excavated stone , 10~20 parts of calcium hydroxide, 8~15 parts of fly ash, 2~5 parts of bamboo and wood fiber, 8~16 parts of Portland cement, 5~15 parts of alicyclic epoxy resin, 1~6 parts of water Parts; Among them, the bamboo wood fiber is the granular residual whip of moso bamboo. 3.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述沥青路面结构(2)采用骨架-密实结构,孔隙率4~6%。3. According to claim 1, a control structure for root swelling deformation of road subgrade pavement in southern bamboo forest area, characterized in that, the asphalt pavement structure (2) adopts a skeleton-dense structure with a porosity of 4-6%. 4.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述沥青路面结构(2)从下至上依次包括下基层(7)、上基层(6)、下面层(5)、上面层(4),下基层(7)采用石灰粉煤灰稳定类基层,上基层(6)采用石灰粉煤灰稳定砂砾石基层,下面层(5)采用中粒式沥青混凝土;上面层(4)采用细粒式改性沥青混凝土;上面层(4)和下面层(5)之间、下面层(5)与上基层(6)之间均通过改性乳化沥青粘层进行粘合。4. According to claim 1, a control structure for root swelling deformation of highway subgrade pavement in southern bamboo forest area, characterized in that, the asphalt pavement structure (2) sequentially includes a lower base (7) and an upper base (6) from bottom to top , the lower layer (5), the upper layer (4), the lower base layer (7) uses lime fly ash stabilized base, the upper base (6) uses lime fly ash stabilized sand and gravel base, and the lower layer (5) adopts medium-grained modified asphalt concrete; the upper layer (4) adopts fine-grained modified asphalt concrete; between the upper layer (4) and the lower layer (5), and between the lower layer (5) and the upper base layer (6) are emulsified by modification Asphalt adhesive layer for bonding. 5.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述过水道(22)沿本体(20)的高度方向由L型拐弯处向下凹陷形成,截面为弧形。5. According to claim 1, a control structure for root bulge deformation of highway subgrade and pavement in southern bamboo forest area, characterized in that, the water passage (22) is formed by a downward depression at an L-shaped corner along the height direction of the body (20) , the section is arc-shaped. 6.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述排水口包括高位排水口(21)和低位排水口(23),高位排水口(21)设置在本体(20)的上部,高于过水道(22);低位排水口(23)的水平高度与路面结构齐平,排水口设置间距为15~20cm。6. According to claim 1, a control structure for controlling root swelling deformation of road subgrade road surface in southern bamboo forest area, characterized in that, the drainage outlets include high-level drainage outlets (21) and low-level drainage outlets (23), and the high-level drainage outlets (21 ) is arranged on the upper part of the body (20), higher than the water passage (22); the level of the low drain outlet (23) is flush with the road surface structure, and the interval between the drain outlets is 15-20cm. 7.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述排水口为拱门式,排水口设有拱门式拦污网,拦污网的孔径为5~20mm。7. according to claim 1, a kind of south bamboo forest area highway subgrade pavement root swelling control structure, it is characterized in that, described outfall is arch type, and outfall is provided with arch type trash-stop, and the aperture of trash-block is 5~20mm. 8.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述路基边坡结构的路基从下至上依次包括下路堤(12)、上路堤(11)、下路床(10)、上路床(9),上路床(9)上方的沥青路面结构(2)的两侧边坡填筑有路侧填土层(8);路基两侧的边坡从下至上依次包括第四边坡填土层(16)、第三边坡填土层(15)、第二边坡填土层(14)、第一边坡填土层(13),坡填土层中加入残鞭的质量分数为8%~14%,从下往上呈递增趋势。8. According to claim 1, a control structure for root swelling deformation of road subgrade road surface in southern bamboo forest area, characterized in that, the subgrade of the subgrade slope structure includes a lower embankment (12) and an upper embankment (11) from bottom to top. , the lower road bed (10), the upper road bed (9), the side slopes on both sides of the asphalt pavement structure (2) above the upper road bed (9) are filled with roadside fill layers (8); the side slopes on both sides of the road bed From bottom to top, it includes the fourth side slope filling layer (16), the third side slope filling layer (15), the second side slope filling layer (14), the first side slope filling layer (13), the slope The mass fraction of remnants added to the filling layer is 8%~14%, showing an increasing trend from bottom to top. 9.根据权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构,其特征在于,所述路基边坡结构的边坡表面依次设有边坡碎石层和植生层(19),植生层(19)中内横向有间距的插入长度为8~10cm的残鞭,加入残鞭的质量分数为9%~11%。9. According to claim 1, a control structure for root swelling deformation of roadbed road surface in southern bamboo forest area, characterized in that, the slope surface of the roadbed slope structure is provided with a slope gravel layer and a vegetation layer (19) in sequence , in the vegetation layer (19) there are intervals in the inner lateral direction to insert remnant whips with a length of 8-10 cm, and the mass fraction of remnant whips added is 9%-11%. 10.如权利要求1所述一种南方竹林区公路路基路面根胀变形调控结构的施工方法,其特征在于,包括以下步骤:10. the construction method of a kind of southern bamboo forest district highway subgrade pavement root swelling deformation regulation and control structure as claimed in claim 1, is characterized in that, comprises the following steps: S1、铺筑路基;S1, pave the roadbed; S2、在路基边坡外侧铺设边坡碎石层,对边坡进行挂网;S2. Lay a slope gravel layer on the outside of the roadbed slope, and hang a net on the slope; S3、在边坡碎石层上喷播植生层(19);S3, spraying the vegetation layer (19) on the slope gravel layer; S4、在整平的路基上铺设沥青路面结构(2),路面结构表层(3)表面设有排水横坡;S4. Lay the asphalt pavement structure (2) on the leveled roadbed, and the surface layer of the pavement structure (3) is provided with a drainage cross slope; S5、在路面两旁设置生态路缘石结构(1),生态路缘石结构(1)的埋置段(25)埋置在路面下,位于路面以上的外露段(24)按照与道路路面齐平的位置刨槽、找平、夯实后再安砌,每隔10~15m设置一个开口将生态路缘石结构(1)内部的L型贯通空腔与急流槽(17)相连接,急流槽(17)沿道路纵向间隔设置,急流槽(17)与坡底的边沟(18)连接;在生态路缘石结构(1)和路面结构之间灌缝。S5. Set up ecological curb structures (1) on both sides of the road surface. The embedded section (25) of the ecological curb stone structure (1) is buried under the road surface, and the exposed section (24) above the road surface is flush with the road surface. After planing, leveling, and tamping the position, install an opening every 10-15m to connect the L-shaped through cavity inside the ecological curb structure (1) with the rapids trough (17), and the rapids trough (17) along the The road is longitudinally arranged at intervals, and the rapid flow trough (17) is connected with the side ditch (18) at the bottom of the slope; joints are filled between the ecological curb structure (1) and the pavement structure.
CN202310276704.0A 2023-03-21 2023-03-21 Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area Pending CN116219820A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310276704.0A CN116219820A (en) 2023-03-21 2023-03-21 Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310276704.0A CN116219820A (en) 2023-03-21 2023-03-21 Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area

Publications (1)

Publication Number Publication Date
CN116219820A true CN116219820A (en) 2023-06-06

Family

ID=86580529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310276704.0A Pending CN116219820A (en) 2023-03-21 2023-03-21 Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area

Country Status (1)

Country Link
CN (1) CN116219820A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202830689U (en) * 2012-11-05 2013-03-27 山东高速青岛公路有限公司 Curb with drainage function
CN111472222A (en) * 2020-04-24 2020-07-31 牛诗哲 Multilayer type highway structure and construction method thereof
DE202020103108U1 (en) * 2020-05-29 2021-08-31 Godelmann Pflasterstein - GmbH & Co. KG. Curb element for bus stops
CN214992808U (en) * 2021-02-08 2021-12-03 中铁九局集团有限公司 Curb with drainage function
CN218203675U (en) * 2022-10-10 2023-01-03 国建华中建设有限公司 Quick drainage curb

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202830689U (en) * 2012-11-05 2013-03-27 山东高速青岛公路有限公司 Curb with drainage function
CN111472222A (en) * 2020-04-24 2020-07-31 牛诗哲 Multilayer type highway structure and construction method thereof
DE202020103108U1 (en) * 2020-05-29 2021-08-31 Godelmann Pflasterstein - GmbH & Co. KG. Curb element for bus stops
CN214992808U (en) * 2021-02-08 2021-12-03 中铁九局集团有限公司 Curb with drainage function
CN218203675U (en) * 2022-10-10 2023-01-03 国建华中建设有限公司 Quick drainage curb

Similar Documents

Publication Publication Date Title
CN106759825B (en) Construction method of sponge urban green land water storage system
CN110698222B (en) Composite vegetation concrete for ecological protection of stone slope and preparation method thereof
CN206928164U (en) A kind of drainage type concrete road
CN104878678A (en) Construction method for water-permeable and water-retaining water-permeable pavement structure
CN113174973B (en) Soft rock side slope ecological protection structure and construction method thereof
CN108532406A (en) Can rapid construction high-bearing capacity pervious surface and laying method
CN107034767A (en) A kind of full pervious concrete pavement structure of regeneration aggregate and its construction method
RU2492290C1 (en) Method to construct motor roads and motor road design
CN106542769A (en) A kind of composite of laying porous pavement
CN105951672B (en) A kind of construction technology of novel embankment and bank protection
CN107938480A (en) A kind of microorganism cures the desert highway embankment and its construction method of joint TGXG
CN208649826U (en) The pervious asphalt road of Collapsible Loess District
CN107032660B (en) Preparation method of composite material for paving permeable pavement
CN209338948U (en) A kind of water-permeable pavement structure
CN106702845A (en) Saline-alkaline preventing water permeable pavement structure
CN114606823B (en) Cement-based permeable concrete pavement structure and paving method thereof
CN210529400U (en) Solidified building residue soil road structure
CN113265924A (en) Construction method for using red bed mudstone blocks as high-fill dynamic compaction roadbed filling
CN209114276U (en) track pavement structure
CN208748462U (en) Can rapid construction high-bearing capacity pervious surface
CN111549603A (en) Pavement considering water load coupling and construction method thereof
CN114481735B (en) A method for filling roadbed with recycled resources for road reconstruction and expansion
CN218345835U (en) Novel town road pavement structure
CN116219820A (en) Control Structure and Construction Method of Root Expansion Deformation of Highway Subgrade Pavement in South Bamboo Forest Area
KR101185626B1 (en) Environmentally-friendly construction method for mountain reservoir using solidified material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination