[go: up one dir, main page]

CN116122491A - A lightweight prefabricated concrete composite wall panel and its preparation method and construction technology - Google Patents

A lightweight prefabricated concrete composite wall panel and its preparation method and construction technology Download PDF

Info

Publication number
CN116122491A
CN116122491A CN202211607742.1A CN202211607742A CN116122491A CN 116122491 A CN116122491 A CN 116122491A CN 202211607742 A CN202211607742 A CN 202211607742A CN 116122491 A CN116122491 A CN 116122491A
Authority
CN
China
Prior art keywords
layer
wallboard
composite
concrete slab
composite wallboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211607742.1A
Other languages
Chinese (zh)
Inventor
熊峰
娄广亚
冉明明
吕洋
沈焱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tibet Zangjian Technology Co ltd
Sichuan University
Original Assignee
Tibet Zangjian Technology Co ltd
Sichuan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tibet Zangjian Technology Co ltd, Sichuan University filed Critical Tibet Zangjian Technology Co ltd
Priority to CN202211607742.1A priority Critical patent/CN116122491A/en
Publication of CN116122491A publication Critical patent/CN116122491A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Panels For Use In Building Construction (AREA)

Abstract

The invention discloses a lightweight precast concrete composite wallboard, a preparation method and a construction process thereof, wherein the composite wallboard comprises an inner reinforced concrete slab layer and an outer heat preservation concrete slab layer; the reinforced concrete slab layer is used as a wallboard bearing part, and a double-layer bidirectional reinforcing mesh is arranged in the reinforced concrete slab layer; the inside space wire net that adopts vertically and horizontally staggered steel wire truss to constitute of thermal insulation concrete slab layer, and space wire net and the outer reinforcing bar ligature of double-deck two-way reinforcing bar net are in the same place. The invention improves the strength of the composite wall body through the steel structure skeleton constructed by the double-layer bidirectional reinforcing steel bar net and the space steel wire net, and has good combination property between the reinforced concrete slab layer and the heat preservation concrete slab layer. The reinforced concrete plate is wrapped in the heat-insulating concrete plate, the reinforced concrete plate is little affected by external temperature change, the problem that sandwich wall boards crack under the action of temperature difference does not exist, and the preparation method is simpler and more convenient than sandwich wall boards.

Description

一种轻量化预制混凝土复合墙板及其制备方法和施工工艺A lightweight prefabricated concrete composite wall panel and its preparation method and construction technology

技术领域technical field

本发明涉及装配式剪力墙结构体系技术领域,尤其涉及一种轻量化预制混凝土复合墙板及其制备方法和施工工艺。The invention relates to the technical field of prefabricated shear wall structure systems, in particular to a lightweight prefabricated concrete composite wall panel and its preparation method and construction process.

背景技术Background technique

作为外围护结构的重要组成部分,外墙在建筑节能中起着十分重要的作用。关于外墙保温,传统的做法有内保温、外保温和夹心保温。内保温将保温板集成在墙体内表面,不仅减小室内有效使用面积,而且在装修时易被损坏。采用有机保温材料(如模塑聚苯板、挤塑聚苯板、聚氨酯泡沫板等)做为保温板集成在墙体外表面的外保温形式非常常见,但该种保温形式存在建筑外表皮易脱落、防火性能差、火灾发生时外保温易形成火灾通道等问题。夹心保温墙板是近几年使用较多的新型保温墙板类型,其将保温板集成在墙板内部,实现了结构保温一体化。但由于夹心保温墙板采用分层浇筑工艺,并且为了固定保温板,需要采用拉结件使内叶板和外叶板连接在一起,施工工艺复杂,造价高,不宜推广。同时,拉结件会形成天然的热桥,降低墙板的保温效果。此外,由于保温板位于墙体内部,内外叶墙板所处温度条件不同,夹心墙板还存在温差作用下墙板开裂的问题。因而,亟需一种新型结构保温一体化复合墙板。As an important part of the outer envelope structure, the outer wall plays a very important role in building energy saving. Regarding external wall insulation, traditional methods include internal insulation, external insulation and sandwich insulation. Inner insulation integrates the insulation board on the inner surface of the wall, which not only reduces the effective use area of the room, but is also easily damaged during decoration. It is very common to use organic thermal insulation materials (such as molded polystyrene board, extruded polystyrene board, polyurethane foam board, etc.) Problems such as shedding, poor fire performance, and easy formation of fire channels by external insulation in case of fire. Sandwich insulation wallboard is a new type of insulation wallboard that has been used more in recent years. It integrates the insulation board inside the wallboard to realize the integration of structural insulation. However, since the sandwich insulation wallboard adopts a layered pouring process, and in order to fix the insulation board, tie pieces are needed to connect the inner leaf board and the outer leaf board together, the construction process is complicated and the cost is high, so it is not suitable for promotion. At the same time, the anchors will form a natural thermal bridge, reducing the insulation effect of the wall panels. In addition, because the insulation board is located inside the wall, the temperature conditions of the inner and outer leaf wall boards are different, and the sandwich wall board also has the problem of cracking of the wall board under the action of temperature difference. Thereby, there is an urgent need for a novel structure-insulation-integrated composite wallboard.

发明内容Contents of the invention

本发明提供了一种轻量化预制混凝土复合墙板及其制备方法和施工工艺,以解决上述背景技术中保温墙板存在的问题。The present invention provides a lightweight prefabricated concrete composite wallboard and its preparation method and construction technology to solve the problems existing in the thermal insulation wallboard in the above-mentioned background technology.

本发明采用的技术方案是:提供一种轻量化预制混凝土复合墙板,包括内侧的钢筋混凝土板层和外侧的保温混凝土板层;所述钢筋混凝土板层作为墙板承重部分,内部配置有双层双向钢筋网;所述保温混凝土板层内部采用纵横交错的钢丝桁架组成的空间钢丝网,且空间钢丝网与双层双向钢筋网的外层钢筋绑扎在一起。The technical solution adopted by the present invention is to provide a lightweight prefabricated concrete composite wall panel, which includes an inner reinforced concrete slab and an outer thermal insulation concrete slab; Two-layer two-way steel mesh; the interior of the thermal insulation concrete slab is a space steel mesh composed of criss-cross steel wire trusses, and the space steel mesh is bound together with the outer steel bars of the double-layer two-way steel mesh.

进一步的,所述双层双向钢筋网包括水平分布钢筋和竖向受力钢筋,所述水平分布钢筋和竖向受力钢筋通过焊接成为一个整体。Further, the double-layer two-way steel mesh includes horizontally distributed steel bars and vertically stressed steel bars, and the horizontally distributed steel bars and vertically stressed steel bars are integrated into a whole through welding.

进一步的,所述钢筋混凝土板层的两侧设置有边缘暗柱,所述边缘暗柱中的四根竖向受力钢筋替换为一对边缘加强钢筋,并用拉筋将一对边缘加强钢筋拉结,所述边缘加强钢筋直径不小于12mm,拉筋直径不小于6mm,且间距不大于150mm。Further, the two sides of the reinforced concrete slab are provided with edge concealed columns, and the four vertical stressed steel bars in the edge concealed columns are replaced by a pair of edge reinforced steel bars, and the pair of edge reinforced steel bars are pulled The diameter of the edge reinforcing steel bar is not less than 12mm, the diameter of the tie bar is not less than 6mm, and the spacing is not greater than 150mm.

进一步的,所述边缘暗柱沿竖直方向设置有凹槽以及若干水平钢丝绳套,相邻复合墙板中的水平钢丝绳套叠放之后,穿入竖缝连接钢筋,然后灌浆,以实现复合墙板与复合墙板竖缝间的可靠连接。Further, the edge concealed column is provided with grooves and several horizontal steel wire rope sleeves along the vertical direction. After the horizontal steel wire rope sleeves in adjacent composite wall panels are stacked, they are inserted into vertical joints to connect steel bars, and then grouted to realize composite wall Reliable connection between the panel and the vertical joint of the composite wall panel.

进一步的,所述复合墙板包括底层复合墙板、中间层复合墙板、顶层复合墙板,所述底层复合墙板和中间层复合墙板下侧预留有用于浆锚搭接连接的金属波纹管,上侧预埋有水平缝连接钢筋,以实现上下相邻层复合墙板之间或者底层复合墙板与基础之间的水平缝浆锚搭接连接。Further, the composite wallboard includes a bottom composite wallboard, a middle layer composite wallboard, and a top layer composite wallboard, and the bottom side of the bottom layer composite wallboard and the middle layer composite wallboard are reserved with metal anchors for lap joint connection. The corrugated pipe is pre-embedded with horizontal seam connection reinforcement on the upper side to realize the horizontal seam grout anchor lap connection between the upper and lower adjacent layers of composite wallboards or between the bottom layer of composite wallboards and the foundation.

进一步的,所述顶层复合墙板的钢筋混凝土板层下侧预留有用于浆锚搭接连接的金属波纹管,而钢筋混凝土板层上侧中的竖向受力钢筋和窗洞连梁箍筋伸出,以便和现浇圈梁和现浇楼盖连接在一起。Further, the lower side of the reinforced concrete slab of the top composite wallboard is reserved with a metal bellows for the lap connection of the grout anchor, while the vertical stressed steel bar and the window hole connecting beam stirrup in the upper side of the reinforced concrete slab are Stretch out to connect with cast-in-place ring beams and cast-in-place slabs.

进一步的,所述钢筋混凝土板层板层厚度不低于140mm,混凝土强度等级不小于C30。Further, the thickness of the reinforced concrete slab is not less than 140mm, and the concrete strength grade is not less than C30.

进一步的,所述保温混凝土板层采用泡沫混凝土、加气混凝土或气凝胶混凝土。Further, the thermal insulation concrete slab layer adopts foam concrete, aerated concrete or airgel concrete.

本发明还提供一种轻量化预制混凝土复合墙板制备方法,所述复合墙板在工厂预制,采用固定模台或流水模台施工,具体包括如下步骤:The present invention also provides a method for preparing a lightweight prefabricated concrete composite wallboard. The composite wallboard is prefabricated in a factory and constructed by using a fixed mold table or a flowing water mold table, which specifically includes the following steps:

S1.绑扎钢筋混凝土板层的双层双向钢筋网,并在其上绑扎保温混凝土板层的空间钢丝网;S1. Bind the double-layer two-way steel mesh of the reinforced concrete slab, and bind the space steel wire mesh of the thermal insulation concrete slab on it;

S2.将墙板所需模具在模台上进行组装,模具内部涂抹脱模剂;S2. Assemble the mold required for the wallboard on the mold table, and apply a release agent inside the mold;

S3.在墙板底模上面放置已经绑扎好的双层双向钢筋网和空间钢丝网,并在双层双向钢筋网下均匀设置垫块;S3. Place the bound double-layer two-way steel mesh and space steel wire mesh on the bottom mold of the wallboard, and evenly set pads under the double-layer two-way steel mesh;

S4.在吊点位置绑扎吊点钢筋或螺纹套筒,预埋金属波纹管、水平缝连接钢筋、水平钢丝绳套和水电管线;S4. Bind the lifting point steel bar or threaded sleeve at the lifting point position, pre-embed metal bellows, horizontal seam connecting steel bars, horizontal steel wire rope sleeves and water and electricity pipelines;

S5.浇筑钢筋混凝土板层的混凝土,浇筑至指定厚度,采用振捣设备振捣密实平整;S5. Pour the concrete of the reinforced concrete slab, pour it to the specified thickness, and use vibrating equipment to vibrate and compact it;

S6.浇筑保温混凝土板层的混凝土,浇筑至指定厚度,采用振捣设备振捣密实平整;S6. Pouring the concrete for the thermal insulation concrete slab, pouring it to the specified thickness, and using vibrating equipment to vibrate and compact it;

S7.将墙板置于标准条件或蒸养条件下养护,达到脱模条件后脱模,之后继续养护至设计强度。S7. Put the wallboard under standard conditions or steam curing conditions for curing, demould after reaching the demoulding conditions, and then continue curing to the design strength.

本发明还提供一种轻量化预制混凝土复合墙板施工工艺,包括:The present invention also provides a lightweight prefabricated concrete composite wall panel construction process, including:

S1.完成基础的施工,其中,在基础钢筋绑扎时预埋水平缝连接钢筋,浇筑基础混凝土后对基础表面拉毛处理,凹凸差不小于4mm;S1. Complete the construction of the foundation, where the horizontal joints are pre-embedded to connect the steel bars when the foundation steel bars are bound, and the surface of the foundation is roughened after pouring the foundation concrete, and the unevenness is not less than 4mm;

S2.在基础表面铺设20mm厚砂浆找平层;S2. Lay a 20mm thick mortar leveling layer on the foundation surface;

S3.将根据上述制备方法得到的复合墙板吊装到指定高度,缓慢放下预制复合墙板的同时,将基础预埋水平缝连接钢筋插入钢筋混凝土板层的预埋金属波纹管内,最后将预制复合墙板放置于尚未凝结的砂浆找平层上,调整复合墙板位置及垂直度后,设置复合墙板面外支撑对复合墙板进行固定;S3. Hoist the composite wall panel obtained according to the above preparation method to the specified height, and while slowly lowering the prefabricated composite wall panel, insert the foundation pre-embedded horizontal joint connection reinforcement into the pre-embedded metal bellows of the reinforced concrete slab, and finally place the prefabricated composite wall panel The wallboard is placed on the leveling layer of mortar that has not yet condensed, and after adjusting the position and verticality of the composite wallboard, set the outer support of the composite wallboard to fix the composite wallboard;

S4.从金属波纹管的入浆口灌入高强灌浆料;S4. Pour high-strength grouting material from the grouting port of the metal bellows;

S5.将同一层的复合墙板按照步骤S3和S4的方法安装就位,灌入高强灌浆料;S5. The composite wallboard of the same layer is installed in place according to the method of steps S3 and S4, and poured into high-strength grouting material;

S6.将相邻复合墙板之间的水平钢丝绳套叠放,插入竖缝连接钢筋,竖缝凹槽外钉紧木板,然后采用高强灌浆料从凹槽上部灌注,直至高强灌浆料充满相邻墙板凹槽形成的空腔;S6. Stack the horizontal steel wire rope sleeves between adjacent composite wall panels, insert the vertical joints to connect the steel bars, nail the wooden boards outside the grooves of the vertical joints, and then use high-strength grouting material to pour from the upper part of the groove until the high-strength grouting material fills the adjacent cavities formed by wall panel grooves;

S7.将同一层的复合墙板之间的竖缝按照步骤S5的方法灌入高强灌浆料;S7. pour the vertical joint between the composite wallboards of the same layer into the high-strength grouting material according to the method of step S5;

S8.完成楼盖的施工;S8. Complete the construction of the floor;

S9.按照步骤S2-S8的方法完成其他楼层的施工。S9. Complete the construction of other floors according to the method of steps S2-S8.

本发明的有益效果是:The beneficial effects of the present invention are:

1、本发明通过双层双向钢筋网和空间钢丝网构建的钢结构骨架使得复合墙体的强度得到提高,钢筋混凝土板层和保温混凝土板层之间结合性好。1. In the present invention, the steel structure framework constructed by double-layer bidirectional steel mesh and space steel wire mesh improves the strength of the composite wall, and the combination between the reinforced concrete slab and the thermal insulation concrete slab is good.

2、本发明采用钢筋混凝土板层受力,保温混凝土板层实现保温作用,实现结构保温一体化复合功能。以泡沫混凝土、加气混凝土或气凝胶混凝土等轻质保温混凝土材料作为保温层,降低墙板自重的同时还具有良好的防水、防火和耐久性能,具有良好的经济效益,尤其适合在村镇住宅和低、多层建筑中使用。2. The present invention adopts the reinforced concrete slab to be stressed, and the heat-preserving concrete slab realizes the heat preservation effect, and realizes the composite function of structural heat preservation integration. Lightweight thermal insulation concrete materials such as foam concrete, aerated concrete or airgel concrete are used as the insulation layer to reduce the weight of the wall panel and also have good waterproof, fireproof and durable performance, which has good economic benefits and is especially suitable for residential buildings in villages and towns. And low, multi-storey buildings used.

3、本发明中钢筋混凝土板层包裹在保温混凝土板层内,钢筋混凝土板层受外界温度变化影响小,不存在夹心墙板在温差作用下开裂问题,且制备方法较夹心墙板更加简单方便。3. In the present invention, the reinforced concrete slab is wrapped in the thermal insulation concrete slab. The reinforced concrete slab is less affected by the external temperature change, and there is no cracking problem of the sandwich wallboard under the action of temperature difference, and the preparation method is simpler and more convenient than the sandwich wallboard. .

4、本发明墙板与墙板之间的竖缝采用水平钢丝绳套灌浆连接,水平缝采用预埋金属波纹管浆锚搭接连接,可以达到等同现浇的连接效果。同时,竖缝连接避免了传统的后浇带施工工艺,整个施工过程工艺简单,现场湿作业较少,大大提升了建造速率。4. The vertical joints between the wall panels of the present invention are connected by grouting with horizontal steel wire rope sleeves, and the horizontal joints are connected by pre-embedded metal bellows grout anchor lap joints, which can achieve the same connection effect as cast-in-place. At the same time, the vertical joint connection avoids the traditional post-casting construction technology, the whole construction process is simple, and there are fewer wet operations on site, which greatly improves the construction speed.

附图说明Description of drawings

图1a为本发明公开的轻量化预制混凝土复合墙板结构层次示意图;Figure 1a is a schematic diagram of the structural hierarchy of the lightweight precast concrete composite wall panel disclosed by the present invention;

图1b为本发明公开的轻量化预制混凝土复合墙板在底部预埋金属波纹管区域的剖面图;Figure 1b is a cross-sectional view of the lightweight prefabricated concrete composite wall panel at the bottom of the pre-embedded metal bellows area disclosed by the present invention;

图1c为本发明公开的轻量化预制混凝土复合墙板在中部区域的剖面图;Fig. 1c is a sectional view of the lightweight prefabricated concrete composite wall panel disclosed in the present invention in the middle region;

图1d为本发明公开的轻量化预制混凝土复合墙板在顶部预埋水平缝连接钢筋区域的剖面图Figure 1d is a cross-sectional view of the lightweight prefabricated concrete composite wall panel at the top pre-embedded horizontal seam connecting reinforcement area disclosed by the present invention

图2a为本发明公开的底层复合墙板及中间层复合墙板的结构示意立体图;Figure 2a is a schematic perspective view of the structure of the bottom composite wallboard and the middle layer composite wallboard disclosed by the present invention;

图2b为本发明公开的顶层复合墙板的结构示意立体图;Fig. 2b is a schematic perspective view of the structure of the top composite wallboard disclosed by the present invention;

图3为本发明公开的内部的双层双向钢筋网和空间钢丝网的结构示意图;Fig. 3 is the structural representation of the internal double-layer two-way steel mesh and space steel wire mesh disclosed by the present invention;

图4为本发明公开的轻量化预制混凝土复合墙板的竖缝连接方式示意图;Fig. 4 is a schematic diagram of the vertical joint connection method of the lightweight precast concrete composite wallboard disclosed by the present invention;

图5为本发明公开的轻量化预制混凝土复合墙板水平缝连接方式示意图。Fig. 5 is a schematic diagram of the horizontal joint connection mode of the lightweight precast concrete composite wall panel disclosed by the present invention.

附图标记:1-钢筋混凝土板层,2-保温混凝土板层,3-双层双向钢筋网,4-边缘暗柱,5-边缘加强钢筋,6-拉筋,7-水平分布钢筋,8-竖向受力钢筋,9-空间钢丝网,10-纵向钢丝桁架,11-横向钢丝桁架,12-凹槽,13-水平钢丝绳套,14-竖缝连接钢筋,15-金属波纹管,16-水平缝连接钢筋,17-浆锚搭接连接,18-吊点钢筋,19-基础,20-基础顶面,21-砂浆找平层,22-入浆口,23-高强灌浆料,24-木板,25-窗洞连梁箍筋。Reference signs: 1-reinforced concrete slab, 2-insulated concrete slab, 3-double-layer two-way steel mesh, 4-edge concealed column, 5-edge reinforcing steel bar, 6-tension bar, 7-horizontal distribution steel bar, 8 -Vertical stress reinforcement, 9-space steel wire mesh, 10-longitudinal steel wire truss, 11-horizontal steel wire truss, 12-groove, 13-horizontal wire rope sleeve, 14-vertical seam connection reinforcement, 15-metal bellows, 16 -Horizontal seam connection reinforcement, 17-grout anchor lap connection, 18-hanging point reinforcement, 19-foundation, 20-top surface of foundation, 21-mortar leveling layer, 22-grout inlet, 23-high-strength grouting material, 24- Planks, 25-window holes with beam stirrups.

具体实施方式Detailed ways

为了使本发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明作进一步详细描述,但本发明的实施方式不限于此。In order to make the purpose, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings, but the embodiments of the present invention are not limited thereto.

实施例1:Example 1:

参见图1a-1d,本实施例公开一种轻量化预制混凝土复合墙板,包括内侧的钢筋混凝土板层1和外侧的保温混凝土板层2;所述钢筋混凝土板层1作为墙板承重部分,内部配置有双层双向钢筋网3;所述保温混凝土板层2内部采用纵横交错的钢丝桁架组成的空间钢丝网9,且空间钢丝网9与双层双向钢筋网3的外层钢筋绑扎在一起。Referring to Figures 1a-1d, this embodiment discloses a lightweight prefabricated concrete composite wall panel, including an inner reinforced concrete slab 1 and an outer thermal insulation concrete slab 2; the reinforced concrete slab 1 is used as a load-bearing part of the wall panel, The interior is equipped with a double-layer two-way steel mesh 3; the interior of the thermal insulation concrete slab 2 adopts a space steel mesh 9 composed of criss-cross steel wire trusses, and the space steel mesh 9 is bound together with the outer steel bars of the double-layer two-way steel mesh 3 .

所述钢筋混凝土板层1板层厚度不低于140mm,混凝土强度等级不小于C30。双层双向钢筋网3中受力钢筋的具体配置由内力设计值计算和规范规定中的构造要求确定。The thickness of the reinforced concrete slab 1 is not less than 140mm, and the concrete strength grade is not less than C30. The specific configuration of the stressed steel bars in the double-layer two-way steel mesh 3 is determined by the calculation of the internal force design value and the construction requirements in the specification.

所述的保温混凝土板层2采用泡沫混凝土、加气混凝土或气凝胶混凝土等保温混凝土材料,其厚度按照满足不同地区对墙板热工性能的要求灵活设置。The thermal insulation concrete slab 2 is made of thermal insulation concrete materials such as foam concrete, aerated concrete or airgel concrete, and its thickness is flexibly set to meet the thermal performance requirements of the wall panels in different regions.

所述双层双向钢筋网3包括水平分布钢筋7和竖向受力钢筋8,所述水平分布钢筋7和竖向受力钢筋8通过焊接成为一个整体。The double-layer two-way reinforcement mesh 3 includes horizontal distribution reinforcement bars 7 and vertical stress reinforcement bars 8, and the horizontal distribution reinforcement bars 7 and vertical stress reinforcement bars 8 are welded into a whole.

所述钢筋混凝土板层1的两侧设置有边缘暗柱4,所述边缘暗柱4中的四根竖向受力钢筋8替换为一对边缘加强钢筋5,不同于现有的边缘暗柱4中采用箍筋,本发明采用拉筋6将一对边缘加强钢筋5拉结,所述边缘加强钢筋5直径不小于12mm,拉筋6直径不小于6mm,且间距不大于150mm。The two sides of the reinforced concrete slab 1 are provided with edge concealed columns 4, and the four vertical stressed steel bars 8 in the edge concealed columns 4 are replaced by a pair of edge reinforcing steel bars 5, which is different from the existing edge concealed columns In 4, stirrups are used. The present invention adopts tie bars 6 to tie a pair of edge reinforcement bars 5. The diameter of the edge reinforcement bars 5 is not less than 12mm, and the diameter of the tie bars 6 is not less than 6mm, and the spacing is not greater than 150mm.

参见图2a-2b,所述边缘暗柱4的中部沿竖直方向设置有凹槽12以及若干水平钢丝绳套13,参见图4,相邻复合墙板中的水平钢丝绳套13叠放之后,穿入竖缝连接钢筋14,在墙缝两侧安装木板24,然后灌浆,以实现复合墙板与复合墙板竖缝间的半干式连接。Referring to Figures 2a-2b, the middle part of the edge concealed column 4 is provided with grooves 12 and several horizontal steel wire rope sleeves 13 along the vertical direction. Insert vertical joints to connect steel bars 14, install planks 24 on both sides of the wall joints, and then grout to realize the semi-dry connection between the composite wall panels and the vertical joints of the composite wall panels.

参见图2a-2b,所述复合墙板包括底层复合墙板、中间层复合墙板、顶层复合墙板,所述底层复合墙板和中间层复合墙板下侧预留有用于浆锚搭接连接17的金属波纹管15,上侧预埋有水平缝连接钢筋16,以实现上下相邻中间层复合墙板之间或者底层复合墙板与基础19之间的水平缝浆锚搭接连接17。所述顶层预制复合墙板的钢筋混凝土板层1下侧预留有用于浆锚搭接连接17的金属波纹管15,而钢筋混凝土板层1上侧中的竖向受力钢筋8和窗洞连梁箍筋25伸出,以便和现浇圈梁和现浇楼盖连接在一起。Referring to Figures 2a-2b, the composite wall panels include a bottom composite wall panel, a middle layer composite wall panel, and a top layer composite wall panel. The metal bellows 15 connecting 17 has a horizontal seam connection steel bar 16 pre-embedded on the upper side, so as to realize the horizontal joint grout anchor lap connection 17 between the upper and lower adjacent middle layer composite wallboards or between the bottom composite wallboard and the foundation 19 . The lower side of the reinforced concrete slab 1 of the prefabricated composite wallboard on the top floor is reserved with a metal bellows 15 for the slurry anchor lap connection 17, and the vertical stressed steel bar 8 in the upper side of the reinforced concrete slab 1 is connected to the window hole. The beam stirrup 25 stretches out so as to be connected together with the cast-in-place ring beam and the cast-in-place floor.

实施例2Example 2

本实施例公开一种轻量化预制混凝土复合墙板制备方法,所述复合墙板在工厂预制,采用固定模台或流水模台施工,具体包括如下步骤:This embodiment discloses a method for preparing a lightweight prefabricated concrete composite wallboard. The composite wallboard is prefabricated in a factory and constructed by using a fixed formwork or a flowing water formwork, which specifically includes the following steps:

S1.绑扎位于内侧的钢筋混凝土板层1的双层双向钢筋网3,并在其上绑扎位于外侧的保温混凝土板层2的空间钢丝网9。其中双层双向钢筋网3采用预压电焊技术,可以使得双层双向钢筋网3直接成型,同时,使用边缘加强钢筋5和拉筋6代替边缘暗柱4中的纵筋和箍筋,减少钢筋绑扎的工作量,便于工业化生产。S1. Binding the double-layer bidirectional steel mesh 3 of the reinforced concrete slab 1 on the inner side, and binding the space steel wire mesh 9 of the thermal insulation concrete slab 2 on the outer side thereon. Among them, the double-layer two-way steel mesh 3 adopts pre-pressing electric welding technology, which can make the double-layer two-way steel mesh 3 be directly formed. At the same time, the edge reinforcement bars 5 and tie bars 6 are used to replace the longitudinal bars and stirrups in the edge concealed columns 4, reducing the number of bars. The workload of binding is convenient for industrialized production.

S2.将复合墙板所需模具清理过表面残渣后进行组装,将模板摆放位置处模台清理干净后进行模板位置固定和涂抹脱模剂。S2. After cleaning the surface residues of the mold required for the composite wallboard, assemble it. After cleaning the mold table at the position where the formwork is placed, fix the formwork position and apply a release agent.

S3.在复合墙板底模上面放置已经绑扎好的钢筋混凝土板层1的双层双向钢筋网3和保温混凝土板层2的空间钢筋网9,并在钢筋混凝土板层1的双层双向钢筋网3下均匀设置垫块,以确保钢筋混凝土板层1钢筋的保护层厚度。S3. Place the double-layer two-way steel mesh 3 of the reinforced concrete slab 1 and the space steel mesh 9 of the thermal insulation concrete slab 2 on the bottom formwork of the composite wallboard, and place the double-layer two-way steel bars on the reinforced concrete slab 1 Pad blocks are evenly arranged under the net 3 to ensure the thickness of the protective layer of the reinforcement of the reinforced concrete slab layer 1.

S4.在吊点位置绑扎吊点钢筋18或设置螺纹套筒,并预埋金属波纹管15、水平钢丝绳套13、水平缝连接钢筋16和墙体内的管线、线槽。金属波纹管15、水平钢丝绳套13、水平缝连接钢筋16和墙体内的管线、线槽一定要定位准确,定位误差满足验收规范要求,以便于施工现场的快捷施工。此外,水平钢丝绳套13的直径和间距布置满足规范要求,且需将金属波纹管15、水电管道和线槽进行填塞,避免在浇筑钢筋混凝土板层1混凝土时,混凝土进入到金属波纹管15、水电管道和线槽内。S4. Bind the steel bars 18 at the hanging points or set threaded sleeves, and pre-embed metal bellows 15, horizontal steel wire rope sleeves 13, horizontal seams connecting the steel bars 16 and the pipelines and wire slots in the wall. The metal bellows 15, the horizontal steel wire rope cover 13, the horizontal seam connecting steel bars 16 and the pipelines and trunking in the wall must be positioned accurately, and the positioning error meets the acceptance specification requirements, so as to facilitate quick construction on the construction site. In addition, the diameter and spacing of the horizontal wire rope sleeves 13 meet the requirements of the specification, and the metal bellows 15, water and electricity pipes, and wire slots need to be filled to prevent concrete from entering the metal bellows 15, In water and electricity pipes and trunking.

S5.浇筑钢筋混凝土板层1的混凝土,浇筑至指定厚度,采用振捣设备振捣密实,之后将混凝土表面找平。在此过程中一定要严格控制好混凝土的浇筑量,混凝土多了要及时铲出,从而严格控制内侧混凝土板1厚度,振捣要均匀并且充分,避免墙板出现蜂窝麻面等问题。振捣完成后,将混凝土表面找平。S5. Pour the concrete of the reinforced concrete slab layer 1 to a specified thickness, vibrate and compact it with vibrating equipment, and then level the concrete surface. During this process, the amount of concrete pouring must be strictly controlled. If there is too much concrete, it must be shoveled out in time, so as to strictly control the thickness of the inner concrete slab 1, and the vibration must be uniform and sufficient to avoid problems such as honeycomb pockmarks on the wall panels. After vibrating, level the concrete surface.

S6.浇筑保温混凝土板层2的保温混凝土材料,浇筑至指定厚度,采用振捣设备振捣密实,振捣要均匀并且充分,从而保证浇筑质量,避免墙板出现蜂窝麻面等问题。之后将混凝土表面找平后抹平抛光。此外,还可以在其表面贴瓷砖和其他立面装饰构造,以满足墙板立面造型的需要。S6. Pouring the thermal insulation concrete material for the thermal insulation concrete slab layer 2, pouring it to the specified thickness, using vibrating equipment to vibrate and compact it, and the vibration should be uniform and sufficient, so as to ensure the pouring quality and avoid problems such as honeycomb pockmarks on the wall panels. After that, the concrete surface is leveled and polished. In addition, tiles and other facade decoration structures can also be pasted on its surface to meet the needs of the facade shape of the wall panel.

S7.将墙板置于标准条件或蒸养条件下进行养护,达到脱模条件后脱模。脱侧模时,要及时将两侧预埋水平钢丝绳套13从钢筋混凝土板层1侧边凹槽12中拉出,避免水平钢丝绳套13埋在混凝土内部。脱模之后继续养护至设计强度。S7. Put the wallboard under standard conditions or steam curing conditions for curing, and demould after reaching the demoulding conditions. When taking off the side formwork, both sides pre-embedded horizontal wire rope sleeves 13 will be pulled out from the side groove 12 of the reinforced concrete slab 1 in time to prevent the horizontal wire rope sleeves 13 from being embedded in the concrete. Continue curing to design strength after demoulding.

实施例3Example 3

本实施例公开一种轻量化预制混凝土复合墙板施工工艺,包括:This embodiment discloses a lightweight prefabricated concrete composite wall panel construction process, including:

S1.完成基础19的施工,其中基础钢筋绑扎时预埋水平缝连接钢筋16并进行固定,确保水平缝连接钢筋16在基础19混凝土浇筑过程中保持竖直和位置准确,以实现预制复合墙板与基础19之间可靠且准确的连接。基础19混凝土浇筑完成后,要在其混凝土初凝之前,对基础表面20进行拉毛处理,凹凸差不小于4mm,以加强墙板底面与基础顶面20的连接效果。S1. Complete the construction of the foundation 19, wherein the horizontal seam connecting steel bars 16 are pre-embedded and fixed when the foundation steel bars are bound, to ensure that the horizontal joint connecting steel bars 16 remain vertical and in an accurate position during the concrete pouring process of the foundation 19, so as to realize the prefabricated composite wall panel Reliable and accurate connection to base 19. After foundation 19 concrete pouring is completed, the foundation surface 20 should be roughened before the initial setting of the concrete, and the unevenness difference is not less than 4mm, so as to strengthen the connection effect between the bottom surface of the wallboard and the top surface 20 of the foundation.

S2.在预制复合墙板吊装施工前,要在基础表面铺设20mm厚砂浆找平层21,填充基础顶面20与预制复合墙板底面之间的缝隙和实现两个表面之间的粘结。S2. Before the hoisting construction of the prefabricated composite wallboard, lay a 20mm thick mortar leveling layer 21 on the surface of the foundation, fill the gap between the top surface of the foundation 20 and the bottom surface of the prefabricated composite wallboard and realize the bonding between the two surfaces.

S3.将实施例1所述的复合墙板吊装到指定高度,缓慢放下预制复合墙板的同时,将基础19预埋水平缝连接钢筋16插入墙板的预埋金属波纹管15内,最后将预制复合墙板放置于尚未凝结的砂浆找平层21上,调整墙板位置及垂直度后,设置墙板面外支撑对墙板进行固定。墙板的位置和垂直度要调整准确,误差控制在规范允许的范围之内。S3. Hoist the composite wallboard described in Example 1 to a designated height, and while slowly lowering the prefabricated composite wallboard, insert the foundation 19 pre-embedded horizontal seam connecting steel bars 16 into the pre-embedded metal bellows 15 of the wallboard, and finally place the The prefabricated composite wallboard is placed on the uncondensed mortar leveling layer 21, and after adjusting the position and verticality of the wallboard, set the external support of the wallboard to fix the wallboard. The position and verticality of the wall panel should be adjusted accurately, and the error should be controlled within the range allowed by the specification.

S4.从金属波纹管15的入浆口22灌入高强灌浆料23,直至高强灌浆料23从金属波纹管15入浆口22溢出。灌浆时一定要保证灌浆质量,使得金属波纹管15内高强灌浆料23均匀致密,不存在空腔和气泡,以保证水平缝连接的可靠度。S4. Pour the high-strength grouting material 23 from the grouting port 22 of the metal bellows 15 until the high-strength grouting material 23 overflows from the grouting port 22 of the metal bellows 15 . When grouting, the grouting quality must be ensured so that the high-strength grouting material 23 in the metal bellows 15 is uniform and dense without cavities and air bubbles, so as to ensure the reliability of the horizontal seam connection.

S5.将同一层的预制复合墙板按照步骤S3和S4的方法安装就位,灌入高强灌浆料23。S5. Install the prefabricated composite wall panels of the same layer in place according to the method of steps S3 and S4, and pour high-strength grouting material 23 into them.

S6.将相邻预制复合墙板之间的水平钢丝绳套13叠放,插入竖缝连接钢筋14,竖缝凹槽12外钉紧木板24,然后采用高强灌浆料23从凹槽12上部灌注,直至高强灌浆料23充满相邻墙板凹槽12组成的空腔。要保证灌浆质量,使得高强灌浆料23均匀填满由相邻预制复合墙板侧面凹槽12组成的空腔,必要时可以采用较细的混凝土振捣棒进行振捣,避免高强灌浆料23内部存在空腔和气泡,从而保证竖缝连接质量。S6. Stack the horizontal wire rope sleeves 13 between the adjacent prefabricated composite wall panels, insert the vertical joints to connect the steel bars 14, nail the wooden boards 24 outside the vertical joint grooves 12, and then use high-strength grouting material 23 to pour from the upper part of the grooves 12, Until the high-strength grouting material 23 fills the cavity formed by the adjacent wallboard grooves 12 . To ensure the grouting quality, the high-strength grouting material 23 evenly fills the cavity formed by the side grooves 12 of adjacent prefabricated composite wall panels. The presence of cavities and air bubbles ensures the quality of the vertical seam connection.

S7.将同一层的预制复合墙板之间的竖缝按照步骤S5的方法灌入高强灌浆料23。S7. Fill the vertical joints between the prefabricated composite wallboards of the same layer into the high-strength grouting material 23 according to the method of step S5.

S8.完成楼盖的施工。S8. Complete the construction of the floor.

S9.按照步骤S2-S8的方法完成其他楼层的施工。S9. Complete the construction of other floors according to the method of steps S2-S8.

本发明墙板采用钢筋混凝土板层受力、保温混凝土板层保温,并采用水平钢丝绳套-竖缝连接钢筋灌浆连接和浆锚搭接连接等等同现浇的半干式连接方式,具有良好的力学和抗震性能,在实际工程中可以作为保温剪力墙使用。采用泡沫混凝土、加气混凝土、气凝胶混凝土等保温混凝土材料作为外侧保温层,具有良好的防水、防火和耐久性能。使用半干式连接方式,施工现场湿作业较少,施工效率高,能很好满足农村住宅和城镇低、多层建筑的功能要求,有利于进一步推广使用。The wall panel of the present invention adopts reinforced concrete slabs for stress and thermal insulation for heat preservation, and adopts semi-dry connection methods that are the same as cast-in-place, such as horizontal steel wire rope sleeves-vertical joints, steel grouting connections, grout anchor lap connections, etc. Mechanical and seismic performance, it can be used as thermal insulation shear wall in actual engineering. Foam concrete, aerated concrete, airgel concrete and other insulating concrete materials are used as the outer insulation layer, which has good waterproof, fireproof and durable performance. Using the semi-dry connection method, there is less wet work on the construction site, and the construction efficiency is high. It can well meet the functional requirements of rural residences and urban low-rise and multi-storey buildings, and is conducive to further popularization and use.

以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的精神和范围。The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them; although the invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: it can still be described in the foregoing embodiments Modifications are made to the recorded technical solutions, or equivalent replacements are made to some of the technical features; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims (10)

1. The lightweight precast concrete composite wallboard is characterized by comprising an inner reinforced concrete slab layer and an outer heat preservation concrete slab layer; the reinforced concrete slab layer is used as a wallboard bearing part, and a double-layer bidirectional reinforcing mesh is arranged in the reinforced concrete slab layer; the inside space wire net that adopts vertically and horizontally staggered steel wire truss to constitute of thermal insulation concrete slab layer, and space wire net and the outer reinforcing bar ligature of double-deck two-way reinforcing bar net are in the same place.
2. The lightweight precast concrete composite wallboard of claim 1, wherein the double-layer bidirectional reinforcing mesh comprises horizontally distributed reinforcing bars and vertically stressed reinforcing bars, and the horizontally distributed reinforcing bars and the vertically stressed reinforcing bars are integrated by welding.
3. The lightweight precast concrete composite wallboard of claim 2, wherein edge hidden columns are arranged on two sides of the reinforced concrete slab layer, four vertical stress steel bars in the edge hidden columns are replaced by a pair of edge reinforcing steel bars, the pair of edge reinforcing steel bars are tied by tie bars, the diameter of the edge reinforcing steel bars is not less than 12mm, the diameter of the tie bars is not less than 6mm, and the distance is not more than 150mm.
4. A lightweight precast concrete composite wall panel as recited in claim 3, wherein the edge hidden posts are provided with grooves and a plurality of horizontal wire rope bushings in a vertical direction, and after the horizontal wire rope bushings in adjacent composite wall panels are stacked, vertical joint connection reinforcing bars are penetrated and then grouting is performed to realize reliable connection between the composite wall panels and the vertical joints of the composite wall panels.
5. The lightweight precast concrete composite wallboard of claim 4, wherein the composite wallboard comprises a bottom composite wallboard, a middle composite wallboard and a top composite wallboard, metal bellows used for slurry anchor lap joint are reserved on the lower sides of the bottom composite wallboard and the middle composite wallboard, and horizontal seam connecting steel bars are pre-buried on the upper sides of the bottom composite wallboard and the middle composite wallboard so as to realize horizontal seam slurry anchor lap joint between the upper and lower adjacent layers of composite wallboards or between the bottom composite wallboard and a foundation.
6. The lightweight precast concrete composite wallboard of claim 5, wherein a metal corrugated pipe for slurry anchor lap joint connection is reserved on the lower side of the reinforced concrete slab layer of the top-layer composite wallboard, and vertical stress steel bars and window hole beam connecting stirrups in the upper side of the reinforced concrete slab layer extend so as to be connected with the cast-in-situ girt and the cast-in-situ floor.
7. The lightweight precast concrete composite wallboard of any one of claims 1 to 6, wherein the reinforced concrete panel layer thickness is not less than 140mm, and the concrete strength grade is not less than C30.
8. The lightweight precast concrete composite wallboard of any one of claims 1 to 6, wherein the insulated concrete slab is foam concrete, aerated concrete, or aerogel concrete.
9. The preparation method of the lightweight precast concrete composite wallboard is characterized by comprising the following steps of:
s1, binding a double-layer bidirectional reinforcing steel bar net of a reinforced concrete slab layer, and binding a space steel wire net of a heat-insulating concrete slab layer on the double-layer bidirectional reinforcing steel bar net;
s2, assembling a mould required by the wallboard on a mould table, and coating a release agent in the mould;
s3, placing a bound double-layer bidirectional steel bar mesh and a space steel wire mesh on the bottom die of the wallboard, and uniformly arranging cushion blocks under the double-layer bidirectional steel bar mesh;
s4, binding a lifting point steel bar or a threaded sleeve at the position of the lifting point, and embedding a metal corrugated pipe, a horizontal seam connecting steel bar, a horizontal steel wire rope sleeve and a hydropower pipeline;
s5, pouring concrete of the reinforced concrete slab layer to a specified thickness, and compacting and flattening by vibrating equipment;
s6, pouring concrete of the heat-insulating concrete slab layer to a specified thickness, and compacting and flattening by vibrating equipment;
s7, curing the wallboard under standard conditions or steam curing conditions, demolding after the demolding conditions are reached, and continuing to cure until the design strength is reached.
10. The construction process of the lightweight precast concrete composite wallboard is characterized by comprising the following steps of:
s1, completing construction of a foundation, wherein horizontal seam connecting steel bars are pre-buried when foundation steel bars are bound, and after foundation concrete is poured, the surface of the foundation is napped, wherein the concave-convex difference is not smaller than 4mm;
s2, paving a mortar leveling layer with the thickness of 20mm on the surface of the foundation;
s3, hoisting the composite wallboard prepared according to the method 9 to a specified height, slowly putting down the prefabricated composite wallboard, inserting a foundation embedded horizontal seam connecting steel bar into an embedded metal corrugated pipe of a reinforced concrete slab layer, finally placing the prefabricated composite wallboard on a mortar leveling layer which is not coagulated, and setting an external support of the composite wallboard to fix the composite wallboard after adjusting the position and the verticality of the composite wallboard;
s4, pouring high-strength grouting material from a grouting opening of the metal corrugated pipe;
s5, installing the composite wallboard of the same layer in place according to the method of the steps S3 and S4, and pouring high-strength grouting material;
s6, stacking horizontal steel wire ropes between adjacent composite wallboards, inserting vertical joint connecting steel bars, nailing the wood boards outside the vertical joint grooves, and then pouring high-strength grouting materials from the upper parts of the grooves until the high-strength grouting materials fill cavities formed by the grooves of the adjacent wallboards;
s7, filling high-strength grouting material into the vertical joints between the composite wallboards of the same layer according to the method of the step S5;
s8, finishing construction of the floor system;
s9, completing construction of other floors according to the method of the steps S2-S8.
CN202211607742.1A 2022-12-14 2022-12-14 A lightweight prefabricated concrete composite wall panel and its preparation method and construction technology Pending CN116122491A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211607742.1A CN116122491A (en) 2022-12-14 2022-12-14 A lightweight prefabricated concrete composite wall panel and its preparation method and construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211607742.1A CN116122491A (en) 2022-12-14 2022-12-14 A lightweight prefabricated concrete composite wall panel and its preparation method and construction technology

Publications (1)

Publication Number Publication Date
CN116122491A true CN116122491A (en) 2023-05-16

Family

ID=86303590

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211607742.1A Pending CN116122491A (en) 2022-12-14 2022-12-14 A lightweight prefabricated concrete composite wall panel and its preparation method and construction technology

Country Status (1)

Country Link
CN (1) CN116122491A (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010036318A (en) * 1999-10-07 2001-05-07 하진규 Precast concrete slab including thermal insulating layer and the method for the same
CN203393895U (en) * 2013-07-19 2014-01-15 四川大学 Novel prefabricated composite reinforced concrete wall board member
CN203499098U (en) * 2013-08-30 2014-03-26 湖北弘毅钢结构工程有限公司 Compound external wallboard with reinforced concrete external layer
CN103790266A (en) * 2014-01-28 2014-05-14 江苏建筑职业技术学院 Concrete filled steel tube core column reinforced prefabricated assembly type shear wall unit
CN205444555U (en) * 2016-03-11 2016-08-10 中民筑友有限公司 Wallboard connected node
CN108035485A (en) * 2018-01-10 2018-05-15 济南市城乡建设发展服务中心 Assembled CF steam pressures porcelain powder air entrained concrete shear wall Side fascia and production method
CN207419839U (en) * 2017-08-30 2018-05-29 西安建构实业有限责任公司 A kind of prefabricated combined wall board
WO2018121632A1 (en) * 2016-12-28 2018-07-05 河北卉原建材有限公司 Steel mesh frame-perlite composite external thermal insulation board
CN208309983U (en) * 2018-04-27 2019-01-01 南通联泷建筑材料有限公司 A kind of assembling thermal-insulating wall board
CN209339444U (en) * 2018-02-11 2019-09-03 北京泽昌盛建筑科技有限公司 A kind of assembled heat insulation load-bearing integration combined wall board
CN211690939U (en) * 2019-12-11 2020-10-16 上海紫宝住宅工业有限公司 Double-sided superposed sandwich heat-insulation shear wall using heat-insulation concrete
CN115126148A (en) * 2022-07-19 2022-09-30 四川大学 A kind of bolt-connected precast concrete composite sandwich thermal insulation wall panel and preparation method thereof
CN115262811A (en) * 2022-09-09 2022-11-01 华北水利水电大学 Construction method of transverse section steel concrete combined shear wall
CN115354793A (en) * 2022-05-05 2022-11-18 北京工业大学 Prefabricated ceramsite and foam concrete composite shear wall provided with triangular-cone truss ribs and preparation method of prefabricated ceramsite and foam concrete composite shear wall

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010036318A (en) * 1999-10-07 2001-05-07 하진규 Precast concrete slab including thermal insulating layer and the method for the same
CN203393895U (en) * 2013-07-19 2014-01-15 四川大学 Novel prefabricated composite reinforced concrete wall board member
CN203499098U (en) * 2013-08-30 2014-03-26 湖北弘毅钢结构工程有限公司 Compound external wallboard with reinforced concrete external layer
CN103790266A (en) * 2014-01-28 2014-05-14 江苏建筑职业技术学院 Concrete filled steel tube core column reinforced prefabricated assembly type shear wall unit
CN205444555U (en) * 2016-03-11 2016-08-10 中民筑友有限公司 Wallboard connected node
WO2018121632A1 (en) * 2016-12-28 2018-07-05 河北卉原建材有限公司 Steel mesh frame-perlite composite external thermal insulation board
CN207419839U (en) * 2017-08-30 2018-05-29 西安建构实业有限责任公司 A kind of prefabricated combined wall board
CN108035485A (en) * 2018-01-10 2018-05-15 济南市城乡建设发展服务中心 Assembled CF steam pressures porcelain powder air entrained concrete shear wall Side fascia and production method
CN209339444U (en) * 2018-02-11 2019-09-03 北京泽昌盛建筑科技有限公司 A kind of assembled heat insulation load-bearing integration combined wall board
CN208309983U (en) * 2018-04-27 2019-01-01 南通联泷建筑材料有限公司 A kind of assembling thermal-insulating wall board
CN211690939U (en) * 2019-12-11 2020-10-16 上海紫宝住宅工业有限公司 Double-sided superposed sandwich heat-insulation shear wall using heat-insulation concrete
CN115354793A (en) * 2022-05-05 2022-11-18 北京工业大学 Prefabricated ceramsite and foam concrete composite shear wall provided with triangular-cone truss ribs and preparation method of prefabricated ceramsite and foam concrete composite shear wall
CN115126148A (en) * 2022-07-19 2022-09-30 四川大学 A kind of bolt-connected precast concrete composite sandwich thermal insulation wall panel and preparation method thereof
CN115262811A (en) * 2022-09-09 2022-11-01 华北水利水电大学 Construction method of transverse section steel concrete combined shear wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王威;熊峰;徐锦祥;徐咏;: "预制装配式混凝土墙板螺栓连接抗剪性能试验研究", 四川大学学报(工程科学版), no. 2, 30 June 2016 (2016-06-30) *

Similar Documents

Publication Publication Date Title
CN107165272B (en) Prestressed assembled concrete frame node connecting structure and construction method thereof
CN110439137B (en) Prefabricated wall board, wall body, prefabricated wall board production method and prefabricated wall body construction method
CN103397696B (en) Shatter-proof, prefabricated steel bar girder shear wall Temperature Variation In Buildings of Mixed Structures thing
CN103388357B (en) Shatter-proof, prefabricated steel tube shear Temperature Variation In Buildings of Mixed Structures thing
CN202012136U (en) U-shaped closed rib connection structure for horizontal seam of assembling shear wall structure
CN203475598U (en) Shock-proof prefabricated building of steel bar truss shearing wall composite structure
CN205046685U (en) External heated board of prefabricated masonry wall
CN110670770A (en) Combined structure and construction method of solid shear wall and laminated plate edge member
CN115492230B (en) A kind of assembled integral building and construction method connected by keyway and centralized reinforcement
CN108842944A (en) A kind of assembled light composite thermo-insulating wall board and preparation method thereof and installation method
CN207538322U (en) A Prefabricated Prestressed Concrete Frame System
CN110219366B (en) Assembled building heat preservation formwork integrated structure and construction method
CN104878836A (en) Prefabricated house and construction method thereof
CN216475803U (en) A Novel Prefabricated Floor Structure Applied to Shear Wall System
CN113585578B (en) Prefabricated assembly type prestress combined floor system and construction method
CN201826392U (en) Reinforced concrete construction adopting precast reinforced building blocks, as well as vibration isolation and absorption system thereof
CN204959963U (en) Compound lightweight wall housing construction of assembled steel frame
CN110359612A (en) A kind of novel two-way ribs profiled steel sheet combination floor of assembled
CN102242551B (en) Reinforcing bars building block reinforced concrete structure and shock insulation, shock absorption system
CN110820983B (en) A longitudinal connection method of prefabricated prefabricated wall panels
WO2016086948A1 (en) The modified hollow core slabs
CN210369292U (en) Cast-in-place coincide mould shell integral structure of assembled building
CN112982692A (en) One-way superimposed sheet joint connecting structure and construction method
CN218758102U (en) Energy-conserving integration assembled shear force wall
CN217811906U (en) A bolt-connected prefabricated concrete composite sandwich insulation wall panel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination