CN116006217B - Pipe curtain structure and construction method thereof - Google Patents
Pipe curtain structure and construction method thereof Download PDFInfo
- Publication number
- CN116006217B CN116006217B CN202211683652.0A CN202211683652A CN116006217B CN 116006217 B CN116006217 B CN 116006217B CN 202211683652 A CN202211683652 A CN 202211683652A CN 116006217 B CN116006217 B CN 116006217B
- Authority
- CN
- China
- Prior art keywords
- pipe
- pipe curtain
- curtain
- grouting
- main body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 30
- 238000003466 welding Methods 0.000 claims abstract description 30
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 26
- 210000001503 joint Anatomy 0.000 claims abstract description 5
- 239000002689 soil Substances 0.000 claims description 15
- 238000006243 chemical reaction Methods 0.000 claims description 7
- 238000002347 injection Methods 0.000 claims description 6
- 239000007924 injection Substances 0.000 claims description 6
- 239000002002 slurry Substances 0.000 abstract description 16
- 238000000034 method Methods 0.000 abstract description 15
- 230000008569 process Effects 0.000 abstract description 7
- 241001391944 Commicarpus scandens Species 0.000 abstract description 3
- 238000007569 slipcasting Methods 0.000 abstract 4
- 229910000831 Steel Inorganic materials 0.000 description 19
- 239000010959 steel Substances 0.000 description 19
- 238000010586 diagram Methods 0.000 description 10
- 239000011440 grout Substances 0.000 description 6
- 230000002787 reinforcement Effects 0.000 description 5
- 238000005452 bending Methods 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 239000004568 cement Substances 0.000 description 3
- 230000000903 blocking effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
Abstract
Description
技术领域Technical field
本发明涉及地下工程施工技术领域,尤其是涉及一种管幕结构及其施工方法。The invention relates to the technical field of underground engineering construction, and in particular to a pipe curtain structure and a construction method thereof.
背景技术Background technique
近年来地下空间建设迅猛发展,地下空间建设所面临的周边环境也日渐复杂,下穿、近接等工程施工已成为常态。地下空间下穿、近接敏感建筑、重要道路等工程时,必然产生对既有建(构)筑物的影响,需采用一定的加固措施控制地下空间的施工影响。管幕具有支护刚度大、抗变形能力强的优点被广泛的应用于施工影响控制中。目前常用的管幕长度约4-6m,直径150mm-600mm的钢管,全部钢管顶进完成后,灌注水泥浆,组成管幕结构。钢管搭设前需提前开挖基坑或临时导洞作为管幕施作平台,钢管在该施作平台中顶入、焊接、继续顶入直至满足设计长度。In recent years, underground space construction has developed rapidly, and the surrounding environment faced by underground space construction has become increasingly complex. The construction of underpasses and close connections has become the norm. When the underground space passes under or is close to sensitive buildings, important roads and other projects, it will inevitably have an impact on existing buildings (structures), and certain reinforcement measures need to be adopted to control the construction impact of the underground space. Pipe curtains have the advantages of high support stiffness and strong deformation resistance, and are widely used in construction impact control. At present, the commonly used pipe curtains are about 4-6m in length and 150mm-600mm in diameter steel pipes. After all the steel pipes are jacked, cement slurry is poured to form the pipe curtain structure. Before erecting steel pipes, foundation pits or temporary guide holes need to be excavated in advance as a pipe curtain construction platform. The steel pipes are jacked into the construction platform, welded, and continue to be jacked until they meet the designed length.
发明人发现,由于受成本及安全控制,管幕施作平台往往空间狭小,造成管幕焊接过程中,底部焊缝距平台底部高度小,人工施焊困难,焊缝质量难以保障,管幕顶进过程中容易沿焊缝断裂。同时在管幕承载时,底部往往作为受拉区,钢管则是主要受拉结构,一旦底部焊缝开裂,底部易出现裂缝,导致管幕承载失效等问题。另外,在管幕顶进结束后,需灌注水泥浆填充以提升抗弯刚度,而浆液扩展往往造成管幕顶部出现填充不密实,管幕顶部作为受压区域,水泥填充体为主要的受压结构,顶部填充不足时,也严重影响管幕承载。The inventor found that due to cost and safety control, the space of the pipe curtain construction platform is often small. As a result, during the pipe curtain welding process, the height of the bottom weld from the bottom of the platform is small, manual welding is difficult, and the quality of the weld is difficult to guarantee. The top of the pipe curtain It is easy to break along the welding seam during the welding process. At the same time, when the tube curtain is loaded, the bottom is often used as the tension area, and the steel pipe is the main tension structure. Once the bottom weld cracks, cracks are prone to appear at the bottom, leading to problems such as the failure of the tube curtain to bear load. In addition, after the pipe curtain is jacked, cement slurry needs to be poured to increase the bending stiffness. The expansion of the slurry often causes the top of the pipe curtain to be filled poorly. The top of the pipe curtain is the pressure area, and the cement filling body is the main pressure. Structure, if the top filling is insufficient, it will also seriously affect the bearing capacity of the tube curtain.
发明内容Contents of the invention
针对现有技术存在的不足,本发明的目的是提供一种管幕结构及其施工方法,通过相邻两管幕主体的切口对接,保证了施工管幕内部第一焊缝时的操作空间,同时切口的设置,便于安装加强板,提高管幕主体之间的连接强度;管幕主体内部设有单向逆止孔的第一注浆管,能够实现加压注浆以解决管幕结构内部浆液填充不密实,存在空腔的技术问题。In view of the shortcomings of the existing technology, the purpose of the present invention is to provide a pipe curtain structure and a construction method thereof, which ensures the operating space when constructing the first weld inside the pipe curtain through the docking of the incisions of two adjacent pipe curtain bodies. At the same time, the setting of the notch facilitates the installation of reinforcing plates and improves the connection strength between the main bodies of the pipe curtain; the first grouting pipe with a one-way check hole is provided inside the main body of the pipe curtain, which can realize pressurized grouting to solve the problem inside the pipe curtain structure. The slurry filling is not dense and there are technical problems with cavities.
为了实现上述目的,本发明是通过如下的技术方案来实现:In order to achieve the above objects, the present invention is achieved through the following technical solutions:
第一方面,一种管幕结构,包括多个依次连接的管幕主体,每个管幕主体两端设有切口以提供焊接空间,相邻两管幕主体的切口对接,相邻管幕主体对接处内壁焊接加强板,切口处焊接管幕盖板,管幕主体内部轴向设置第一注浆管,第一注浆管上设有多个单向逆止孔,用于进行加压注浆以填补空腔,管幕主体外壁固定多个第二注浆管。In the first aspect, a pipe curtain structure includes a plurality of pipe curtain main bodies connected in sequence. Each pipe curtain main body is provided with cutouts at both ends to provide welding space. The cutouts of two adjacent pipe curtain main bodies are butted together, and the adjacent pipe curtain main bodies are connected. The reinforcing plate is welded on the inner wall of the butt joint, and the pipe curtain cover is welded on the incision. A first grouting pipe is axially arranged inside the main body of the pipe curtain. There are multiple one-way check holes on the first grouting pipe for pressurized injection. Grouting is used to fill the cavity, and a plurality of second grouting pipes are fixed on the outer wall of the main body of the tube curtain.
作为进一步的实现方式,所述切口位于管幕主体的两端一侧,切口为V型切口,两管幕主体切口对接后的封闭形状与管幕盖板形状相同。As a further implementation method, the incisions are located at both ends of the main body of the tube curtain, and the incisions are V-shaped incisions. The closed shape after the incisions of the two tube curtain main bodies are butted is the same as the shape of the tube curtain cover plate.
作为进一步的实现方式,所述加强板位于管幕主体的两端另一侧,加强板的弧度与管幕主体内壁弧度适配,加强板与管幕内壁形成加强板焊缝。As a further implementation, the reinforcing plates are located on the other side of the two ends of the main body of the pipe curtain. The curvature of the reinforcing plate matches the curvature of the inner wall of the main body of the pipe curtain. The reinforcing plate and the inner wall of the pipe curtain form a reinforcing plate weld.
作为进一步的实现方式,所述管幕盖板外侧弧度与管幕主体外侧弧度相同,管幕盖板与管幕主体的切口之间形成管幕盖板焊缝。As a further implementation, the outer curvature of the pipe curtain cover plate is the same as the outer curvature of the pipe curtain main body, and a pipe curtain cover plate weld is formed between the cutout of the pipe curtain cover plate and the pipe curtain main body.
作为进一步的实现方式,每一个管幕主体内部的第一注浆管之间通过套筒固定连接,套筒位于切口处,套筒内壁两侧安装橡胶垫,橡胶垫为锥形以压紧第一注浆管。As a further implementation method, the first grouting pipes inside the main body of each pipe curtain are fixedly connected through a sleeve. The sleeve is located at the incision. Rubber pads are installed on both sides of the inner wall of the sleeve. The rubber pads are tapered to compress the first grouting pipe. A grouting pipe.
作为进一步的实现方式,相邻两管幕主体端部之间形成管幕内部第一焊缝。As a further implementation, a first weld seam inside the pipe curtain is formed between the ends of two adjacent pipe curtain bodies.
作为进一步的实现方式,所述第二注浆管沿管幕主体轴向设置,相邻两管幕主体上的第二注浆管对接,第二注浆端沿管幕主体外壁环向均匀设置。As a further implementation method, the second grouting pipe is arranged axially along the main body of the pipe curtain, the second grouting pipes on two adjacent pipe curtain bodies are butted, and the second grouting end is evenly arranged circumferentially along the outer wall of the main body of the pipe curtain. .
作为进一步的实现方式,所述第二注浆管的内径大于第一注浆管内径。As a further implementation, the inner diameter of the second grouting pipe is greater than the inner diameter of the first grouting pipe.
第二方面,一种管幕结构的施工方法,包括如下步骤:In the second aspect, a construction method of a pipe curtain structure includes the following steps:
管幕导坑开挖后安装顶管机,利用顶管机将第一个管幕主体顶进土层;After the pipe curtain guide pit is excavated, a pipe jacking machine is installed, and the pipe jacking machine is used to push the first pipe curtain main body into the soil layer;
第二个管幕主体与第一个管幕主体切口对接,施工管幕内部第一焊缝,之后焊接加强板,再利用套筒连接相邻两注浆管,焊接管幕盖板,如此循环,直到所有管幕主体顶进土层;The main body of the second pipe curtain is connected to the incision of the main body of the first pipe curtain, and the first weld seam inside the pipe curtain is constructed, and then the reinforcing plate is welded, and then the sleeve is used to connect the two adjacent grouting pipes, and the pipe curtain cover is welded, and so on. , until all the pipe curtain main bodies are pushed into the soil layer;
在管幕主体外侧进行一次注浆,一次注浆凝固后通过第一注浆管进行加压二次注浆以填补内部空腔,之后通过第二注浆管进行管幕主体外侧三次注浆,形成如上所述的一种管幕结构。One grouting is performed outside the main body of the pipe curtain. After the first grouting is solidified, a second grouting injection is carried out under pressure through the first grouting pipe to fill the internal cavity. Then, three grouting injections are carried out outside the main body of the pipe curtain through the second grouting pipe. A tube curtain structure is formed as described above.
作为进一步的实现方式,安装顶管机后,顶管机后端配合反力支架,反力支架支撑在管幕导坑侧壁;As a further implementation method, after the pipe jacking machine is installed, the rear end of the pipe jacking machine is matched with a reaction bracket, and the reaction bracket is supported on the side wall of the pipe curtain guide pit;
注浆前,利用龙门吊将顶管机移位以空出施作空间。Before grouting, use a gantry crane to move the pipe jacking machine to clear the construction space.
上述本发明的有益效果如下:The above-mentioned beneficial effects of the present invention are as follows:
1.本发明采用两端带有切口的管幕主体进行施工,切口的设置,可以实现从管幕内部对结构进行焊接,有效解决了管幕底部距离基坑底部较近,焊接空间小,在焊接时容易发生危险等问题,提高了焊接效率且安全性得到很大提高。1. The present invention uses the main body of the pipe curtain with cutouts at both ends for construction. The setting of the cutouts allows the structure to be welded from inside the pipe curtain, effectively solving the problem that the bottom of the pipe curtain is close to the bottom of the foundation pit and the welding space is small. Danger and other problems are prone to occur during welding, so the welding efficiency is improved and the safety is greatly improved.
2.本发明加强板的设置增强了管幕钢管与钢管连接处的强度,可有效解决管幕连接处因连接强度不足而发生的受压弯曲断裂的问题,提高了整体结构的安全性;同时切口的设置,也为加强板的焊接提供了施工空间。2. The arrangement of the reinforcing plate of the present invention enhances the strength of the connection between the pipe curtain steel pipe and the steel pipe, can effectively solve the problem of pressure bending and fracture at the pipe curtain connection due to insufficient connection strength, and improves the safety of the overall structure; at the same time The setting of the notch also provides construction space for the welding of the reinforced plate.
3.本发明可以实现多级注浆,以此解决管幕内两端注浆不充分问题。首先通过自然流动方式在管幕一侧向管幕内部注入夹带较粗骨料浆体,其次待一次注浆浆体凝固后通过内部第一注浆管采用加压注浆方式向管幕内部注浆,注浆管内设有逆止阀,既可避免一次注浆堵塞内部注浆管问题,又能够保证浆液加压流入管幕内部填补空腔。最后通过外部注浆管向管幕钢管间土层加压注浆,增强管幕钢管间的连接,提高所在地层的稳定性。3. The present invention can realize multi-stage grouting, thereby solving the problem of insufficient grouting at both ends of the pipe curtain. First, the coarser aggregate slurry is injected into the interior of the pipe curtain on one side of the pipe curtain through natural flow. Secondly, after the primary grouting slurry solidifies, the pressure grouting method is used to inject the inside of the pipe curtain through the first internal grouting pipe. The grouting pipe is equipped with a check valve, which can not only avoid the problem of blocking the internal grouting pipe by one grouting, but also ensure that the slurry flows into the inside of the pipe curtain to fill the cavity under pressure. Finally, the external grouting pipe is used to pressurize the soil layer between the curtain steel pipes to strengthen the connection between the curtain steel pipes and improve the stability of the stratum where they are located.
附图说明Description of the drawings
构成本发明的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。The description and drawings that constitute a part of the present invention are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention.
图1是本发明实施例中管幕主体的结构示意图。Figure 1 is a schematic structural diagram of the main body of the tube curtain in the embodiment of the present invention.
图2是本发明实施例中第一注浆管通过套筒连接的结构示意图。Figure 2 is a schematic structural diagram of the first grouting pipe connected through a sleeve in the embodiment of the present invention.
图3是本发明实施例中管幕主体端部的结构示意图。Figure 3 is a schematic structural diagram of the end of the main body of the tube curtain in the embodiment of the present invention.
图4是本发明实施例中管幕导坑的结构示意图。Figure 4 is a schematic structural diagram of the tube curtain guide pit in the embodiment of the present invention.
图5是本发明实施例中管幕主体对接处的结构示意图。Figure 5 is a schematic structural diagram of the joint of the main body of the tube curtain in the embodiment of the present invention.
图6是本发明实施例中注浆示意图。Figure 6 is a schematic diagram of grouting in an embodiment of the present invention.
图7是本发明实施例中管幕承载结构示意图。Figure 7 is a schematic diagram of the load-bearing structure of the tube curtain in the embodiment of the present invention.
图中:为显示各部位位置而夸大了互相间间距或尺寸,示意图仅作示意。In the figure: The spacing or size between each part is exaggerated to show the position of each part, and the schematic diagram is for illustration only.
其中:1.管幕主体,2.第二注浆管,3.加强板,4.第一注浆管,5.单向逆止孔,6.管幕盖板,7.套筒,8.渗浆预留孔,9.橡胶垫,10.管幕盖板焊缝,11.管幕内部第一焊缝,12.加强板焊缝,13.管幕导坑,14.导洞开挖,15.地层加固区。Among them: 1. Main body of pipe curtain, 2. Second grouting pipe, 3. Reinforcement plate, 4. First grouting pipe, 5. One-way check hole, 6. Pipe curtain cover plate, 7. Sleeve, 8 .Reserved holes for grouting, 9. Rubber pad, 10. Pipe curtain cover plate weld, 11. First weld inside the pipe curtain, 12. Reinforcement plate weld, 13. Pipe curtain guide pit, 14. Guide tunnel excavation , 15. Stratum reinforcement area.
具体实施方式Detailed ways
应该指出,以下详细说明都是例示性的,旨在对本发明提供进一步的说明。除非另有指明,本发明使用的所有技术和科学术语具有与本发明所属技术领域的普通技术人员通常理解的相同含义。It should be noted that the following detailed description is illustrative and is intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings commonly understood by one of ordinary skill in the art to which this invention belongs.
实施例一Embodiment 1
本发明的一种典型的实施方式中,参考图1-图5所示,一种管幕结构,包括多个依次焊接的的管幕主体1,每个管幕主体1两端设有相同的切口以提供焊接空间,在将两个管幕主体1对接时,相邻两管幕主体1的切口对接。相邻管幕主体1对接处内壁焊接加强板3,切口处焊接管幕盖板6。In a typical implementation of the present invention, as shown in Figures 1 to 5, a pipe curtain structure includes a plurality of pipe curtain main bodies 1 that are welded in sequence, and each pipe curtain main body 1 is provided with the same The incisions are made to provide welding space. When the two tube curtain main bodies 1 are butted, the incisions of the two adjacent tube curtain main bodies 1 are butted together. The reinforcing plate 3 is welded on the inner wall of the joint between the adjacent pipe curtain main bodies 1, and the pipe curtain cover plate 6 is welded on the incision.
在对管幕主体(钢管)进行焊接时,由于管幕主体1底部距离基坑底部较近,焊接空间小,在焊接时容易发生危险。通过切口的设置,可以从管幕主体内部对结构进行焊接,有效解决了焊接不便等问题,同时提高了焊接效率并且安全性得到很大提高。When welding the main body of the pipe curtain (steel pipe), since the bottom of the main body 1 of the pipe curtain is close to the bottom of the foundation pit, the welding space is small, and danger may easily occur during welding. Through the setting of the incisions, the structure can be welded from inside the main body of the pipe curtain, effectively solving problems such as inconvenient welding, while improving the welding efficiency and greatly improving safety.
本实施例的切口位于管幕主体1的两端一侧,切口为V型切口,加强板3位于管幕主体1两端内壁的另一侧。管幕主体1两端的切口是提前在工厂预制完成的,在实际施工时,可以直接将带有切口的两管幕主体1安装,扩大了管幕主体1焊接时的操作空间,方便可靠。In this embodiment, the incisions are located on one side of both ends of the tube curtain main body 1 and are V-shaped incisions. The reinforcing plate 3 is located on the other side of the inner wall of both ends of the tube curtain main body 1 . The cutouts at both ends of the pipe curtain main body 1 are prefabricated in the factory in advance. During actual construction, the two pipe curtain main bodies 1 with the cutouts can be directly installed, which expands the operating space during welding of the pipe curtain main body 1 and is convenient and reliable.
考虑到管幕顶进过程中容易沿焊缝断裂。同时在管幕承载时,底部往往作为受拉区,钢管作为受拉结构,一旦底部焊缝开裂,底部易出现裂缝,导致管幕承载失效等问题,本实施例相邻管幕主体1对接处内壁焊接加强板3,加强板3的弧度与管幕主体内壁弧度适配。Considering that the pipe curtain is easy to break along the weld during the jacking process. At the same time, when the tube curtain is loaded, the bottom is often used as a tension area, and the steel pipe serves as a tension structure. Once the bottom weld cracks, cracks are prone to appear at the bottom, leading to problems such as load-bearing failure of the tube curtain. In this embodiment, the joint between the adjacent tube curtain main bodies 1 The inner wall is welded with a reinforcing plate 3, and the curvature of the reinforcing plate 3 is adapted to the curvature of the inner wall of the main body of the pipe curtain.
在施工加强板3前,需要将对接的两个管幕主体1端部进行焊接,焊接后形成管幕内部第一焊缝11。施工管幕内部第一焊缝11后,安装加强板3并焊接,在管幕主体1内部对接处形成了加强板焊缝12。Before constructing the reinforcing plate 3, the ends of the two connected pipe curtain bodies 1 need to be welded. After welding, the first weld seam 11 inside the pipe curtain is formed. After constructing the first weld 11 inside the pipe curtain, the reinforcing plate 3 is installed and welded, and a reinforcing plate weld 12 is formed at the internal butt joint of the pipe curtain body 1 .
本实施例的加强板3,其底面与管幕主体内壁下侧贴合,延钢片(加强板)边线与管幕主体1内壁进行焊接;加强板3的设置增强了管幕主体之间连接处的强度,可有效解决管幕主体1连接处因连接强度不足而发生的受压弯曲断裂的问题,提高了整体结构的安全性。The bottom surface of the reinforcing plate 3 in this embodiment is attached to the lower side of the inner wall of the main body of the pipe curtain, and the edge of the steel sheet (reinforcing plate) is welded to the inner wall of the main body of the pipe curtain 1; the arrangement of the reinforcing plate 3 enhances the connection between the main bodies of the pipe curtain. The strength at the joint can effectively solve the problem of bending and fracture under pressure due to insufficient connection strength at the joint of the main body 1 of the pipe curtain, and improve the safety of the overall structure.
两管幕主体1切口对接后的封闭形状与管幕盖板6形状相同,在将两个管幕主体1对接并焊接后,通过管幕盖板6将管幕封闭,管幕盖板6与切口的沿线对齐并焊接,形成管幕盖板焊缝10,可以理解的是,所述管幕盖板6外侧弧度与管幕主体外侧弧度相同。The closed shape after the incisions of the two pipe curtain main bodies 1 are butted is the same as the shape of the pipe curtain cover plate 6. After the two pipe curtain main bodies 1 are butted and welded, the pipe curtain is closed by the pipe curtain cover plate 6, and the pipe curtain cover plate 6 is connected with the pipe curtain cover plate 6. The edges of the incisions are aligned and welded to form the pipe curtain cover plate weld 10. It can be understood that the outer curvature of the pipe curtain cover plate 6 is the same as the outer curvature of the pipe curtain main body.
如图1所示,多个管幕主体1焊接并顶进土层完成后,需要进行注浆过程。本实施例的管幕主体内部沿轴向设置第一注浆管4,第一注浆管上均布有多个单向逆止孔5,用于进行二次加压注浆以填补空腔,在管幕主体1外壁固定多个第二注浆管2,二次加压注浆时,第一注浆管4内的浆液能够通过单向逆止孔5,进而填补管幕内部一次注浆留下的空腔、空洞,保证注浆效果;此外,单向逆止孔5还可以保证一次注浆时,浆液不会进入第一注浆管4内堵塞。As shown in Figure 1, after the multiple pipe curtain main bodies 1 are welded and jacked into the soil layer, the grouting process needs to be performed. In this embodiment, a first grouting pipe 4 is arranged along the axial direction inside the main body of the pipe curtain. A plurality of one-way check holes 5 are evenly distributed on the first grouting pipe for secondary pressurized grouting to fill the cavity. , a plurality of second grouting pipes 2 are fixed on the outer wall of the main body 1 of the pipe curtain. During the second pressurized grouting, the grout in the first grouting pipe 4 can pass through the one-way check hole 5, thereby filling the primary grouting inside the pipe curtain. The cavity and cavity left by the grout ensure the grouting effect; in addition, the one-way check hole 5 can also ensure that the grout will not enter the first grouting pipe 4 and block it during one grouting.
如图2所示,每一个管幕主体内部的第一注浆管之间通过套筒7固定连接,套筒7位于切口处,切口的设置,也便于安放套筒7,套筒7内壁两侧安装橡胶垫9,橡胶垫9为锥形橡胶垫,随着管幕主体1往土层内部顶进,橡胶垫9的压力逐渐增强,有效解决了第一注浆管4漏浆问题且注浆管稳定性得到保证。As shown in Figure 2, the first grouting pipes inside the main body of each pipe curtain are fixedly connected through sleeves 7. The sleeves 7 are located at the incisions. The setting of the incisions also facilitates the placement of the sleeves 7. The two inner walls of the sleeves 7 A rubber pad 9 is installed on the side. The rubber pad 9 is a cone-shaped rubber pad. As the pipe curtain main body 1 is pushed into the soil layer, the pressure of the rubber pad 9 gradually increases, effectively solving the grout leakage problem of the first grouting pipe 4 and grouting. The stability of the slurry tube is guaranteed.
可以理解的是,在施工过程中,需要先通过套筒7连接两第一注浆管4,之后再焊接管幕盖板,封闭管幕上的切口。第一注浆管4用于二次加压注浆,填补一次注浆时管幕主体内部留下的空腔。It can be understood that during the construction process, the two first grouting pipes 4 need to be connected through the sleeve 7 first, and then the pipe curtain cover plate is welded to close the incision on the pipe curtain. The first grouting pipe 4 is used for secondary pressurized grouting to fill the cavity left inside the main body of the pipe curtain during the primary grouting.
如图1和图3所示,第二注浆管2沿管幕主体1轴向设置,相邻两管幕主体上的第二注浆管2对接并焊接,第二注浆管2沿管幕主体外壁环向均匀设置。第二注浆管2的内径大于第一注浆管4内径。As shown in Figures 1 and 3, the second grouting pipe 2 is arranged axially along the pipe curtain main body 1. The second grouting pipes 2 on the two adjacent pipe curtain bodies are butted and welded. The second grouting pipe 2 is arranged along the pipe. The outer wall of the curtain main body is evenly arranged circumferentially. The inner diameter of the second grouting pipe 2 is larger than the inner diameter of the first grouting pipe 4 .
本实施例的每一管幕主体1周侧设置两个第二注浆管2,第二注浆管2的长度与管幕主体1的长度相同,第二注浆管2上设有多个渗浆预留孔8,用于三次注浆。In this embodiment, two second grouting pipes 2 are provided around each pipe curtain main body 1. The length of the second grouting pipes 2 is the same as the length of the pipe curtain main body 1. There are multiple second grouting pipes 2 on the second grouting pipe 2. There are 8 holes reserved for grouting for three groutings.
可以理解的是,本实施例可以实现三次注浆,首先通过自然流动方式在管幕一侧向管幕内部注入夹带较粗骨料浆体,其次待一次注浆浆体凝固后通过内部注浆管采用加压注浆方式通过第一注浆管向管幕内部注浆,注浆管上设有单向逆止孔,既可避免一次注浆堵塞内部第一注浆管问题,又能够保证浆液加压流入管幕内部。最后通过外部第二注浆管向管幕钢管间土层加压注浆,增强管幕钢管间的连接,提高所在地层的稳定性。It can be understood that this embodiment can achieve three times of grouting. First, the coarser aggregate slurry is injected into the interior of the pipe curtain on one side of the pipe curtain through natural flow. Secondly, after the primary grouting slurry is solidified, grouting is performed internally. The pipe uses pressurized grouting to inject grouting into the inside of the pipe curtain through the first grouting pipe. The grouting pipe is equipped with a one-way check hole, which can not only avoid the problem of blocking the first grouting pipe inside by one grouting, but also ensure The slurry flows under pressure into the tube curtain. Finally, the external second grouting pipe is used to pressurize the soil layer between the curtain steel pipes to strengthen the connection between the curtain steel pipes and improve the stability of the stratum where they are located.
实施例二Embodiment 2
一种管幕结构的施工方法,采用该方法能够形成实施例一所述的一种管幕结构,具体包括如下步骤:A construction method of a pipe curtain structure, using this method to form a pipe curtain structure described in Embodiment 1, specifically including the following steps:
首先进行施工前的准备工作,提前在工厂预制生产两端带有V形切口的管幕主体1,第二注浆管2焊接在管幕主体两侧,本实施例中,一个管幕主体外侧设置两个第二注浆管2。第二注浆管2焊接后的状态如图2所示。First, the preparatory work before construction is carried out. The main body 1 of the pipe curtain with V-shaped cuts at both ends is prefabricated in the factory in advance. The second grouting pipe 2 is welded on both sides of the main body of the pipe curtain. In this embodiment, the outside of one pipe curtain main body Two second grouting pipes 2 are provided. The state of the second grouting pipe 2 after welding is shown in Figure 2.
顶进平台导坑开挖;Jacking platform guide pit excavation;
首先根据工程地质资料及现场实际情况,在管幕区域中部位置处开挖管幕导坑13,如图4所示。First, according to the engineering geological data and actual site conditions, the pipe curtain guide pit 13 is excavated in the middle of the pipe curtain area, as shown in Figure 4.
管幕顶进;Tube curtain jacking;
管幕导坑开挖后安装顶管机,利用顶管机将第一个管幕主体顶进土层;具体的,首先利用导坑上方龙门吊将顶管机放入指定位置,顶管机前端安装螺旋转刀,用于切割土体和及时排运土体,顶管机后端配备反力支架,反力支架支撑在管幕导坑13侧壁,用于提供反力促进管幕钢管向前顶进,由此可以实现边出土、边顶进。After the pipe curtain guide pit is excavated, a pipe jacking machine is installed, and the pipe jacking machine is used to push the first pipe curtain main body into the soil layer; specifically, the pipe jacking machine is first placed in the designated position using the gantry crane above the guide pit, and the front end of the pipe jacking machine is Install a spiral rotary cutter for cutting soil and timely transporting soil. The rear end of the pipe jacking machine is equipped with a reaction bracket. The reaction bracket is supported on the side wall of the pipe curtain guide pit 13 to provide reaction force to promote the direction of the pipe curtain steel pipe. Front jacking can realize both excavating and jacking.
管幕焊接;Pipe curtain welding;
前一节管幕主体通过顶管机顶入土层后,后一节管幕主体的前端焊接在前一节钢管末端,具体操作为,首先通过外部注浆管管口对齐,保证前后节钢管V形开口精准连接,由于V形开口存在,使得管幕内施作空间较大,能够在管幕主体内部焊接管幕内部第一焊缝11,继而避免施作时出现仰焊情况。After the main body of the previous pipe curtain enters the soil layer through the pipe jacking machine, the front end of the main body of the subsequent pipe curtain is welded to the end of the previous steel pipe. The specific operation is to first align the nozzles of the external grouting pipe to ensure that the V of the front and rear steel pipes The V-shaped opening is accurately connected. Due to the existence of the V-shaped opening, the construction space inside the pipe curtain is larger, and the first weld seam 11 inside the pipe curtain can be welded inside the main body of the pipe curtain, thus avoiding overhead welding during construction.
其次由于焊缝处承载能力较弱,管幕受力时底部易出现受压弯曲断裂,因此在管幕主体内部将加强板3围焊在管幕主体内侧底部,以此提高钢管间连接的刚度,提高管幕整体稳定性。Secondly, due to the weak load-bearing capacity of the weld, the bottom of the pipe curtain is prone to bending and fracture due to pressure. Therefore, the reinforcing plate 3 is welded to the bottom of the inner side of the pipe curtain body to increase the stiffness of the connection between the steel pipes. , improve the overall stability of the tube curtain.
然后利用套筒7将两管幕主体1内部的第一注浆管4连接在一块,套筒7内设有锥形橡胶垫,通过锤击等方式,实现两个注浆管、套筒紧密连接,同时也可保不漏浆。最后将管幕盖板6沿着V形切口焊接在管幕上,形成管幕盖板焊缝10。各焊缝示意图如图5所示,待焊接完成顶管机通过顶进后节顶管,推动前节管幕主体继续顶入土层。如此循环,直到所有管幕主体顶进土层。Then use sleeve 7 to connect the first grouting pipes 4 inside the main body 1 of the two pipe curtains together. The sleeve 7 is equipped with a tapered rubber pad. By hammering or other methods, the two grouting pipes and sleeves are tightly connected. connection, while also ensuring no leakage of slurry. Finally, the tube curtain cover plate 6 is welded to the tube curtain along the V-shaped incision to form a tube curtain cover plate weld 10. The schematic diagram of each weld is shown in Figure 5. After the welding is completed, the pipe jacking machine will jack up the pipe in the rear section and push the main body of the front section pipe curtain to continue to push into the soil layer. This cycle continues until all the pipe curtain main bodies are pushed into the soil layer.
注浆;grouting;
在管幕主体1外侧进行一次注浆,一次注浆凝固后通过第一注浆管进行加压二次注浆以填补内部空腔,之后通过第二注浆管进行管幕主体外侧三次注浆。One grouting is performed on the outside of the main body 1 of the pipe curtain. After the first grouting is solidified, a second grouting is carried out under pressure through the first grouting pipe to fill the internal cavity. Then, a third grouting is carried out on the outside of the main body of the pipe curtain through the second grouting pipe. .
具体的,由于管幕水平放置,一次注浆后管幕端部易出现空腔问题,为此需要在管幕内部进行二次注浆,特别地在套筒7内壁安装楔形的橡胶垫9,实现管幕内部注浆管在外力挤压下能够紧密连接,保证注浆过程不漏浆。Specifically, since the pipe curtain is placed horizontally, cavity problems are prone to occur at the end of the pipe curtain after primary grouting. For this reason, a second grouting is required inside the pipe curtain. In particular, a wedge-shaped rubber pad 9 is installed on the inner wall of the sleeve 7. The grouting pipes inside the pipe curtain can be tightly connected under external extrusion to ensure no grout leakage during the grouting process.
管幕主体1顶入设计位置后,首先用龙门吊将顶管机移位,为注浆空出施作空间。其次从管幕主体外部一侧向管幕主体内部进行一次注浆,注浆材料可选用带有粗骨料的混凝土。After the pipe curtain main body 1 is pushed into the designed position, the pipe jacking machine is first moved using a gantry crane to clear space for grouting. Secondly, grouting is performed from the outside side of the main body of the pipe curtain to the inside of the main body of the pipe curtain. The grouting material can be concrete with coarse aggregate.
由于管幕内部注浆管设有单向逆止孔5,其可保证一次注浆时浆体不会流入内部注浆管。待一次注浆浆体凝固后,然后通过内部第一注浆管4向管幕主体内部加压进行二次注浆,在压力作用,浆体冲破单向逆止孔5流入管幕内部空腔处,继而填补一次注浆形成的空洞。Since the grouting pipe inside the pipe curtain is provided with a one-way check hole 5, it can ensure that the slurry will not flow into the internal grouting pipe during one grouting. After the primary grouting slurry is solidified, the inside of the main body of the pipe curtain is pressurized through the first internal grouting pipe 4 for secondary grouting. Under the action of pressure, the slurry breaks through the one-way check hole 5 and flows into the internal cavity of the pipe curtain. place, and then fill the cavity formed by a grouting injection.
最后通过管幕主体1外部的第二注浆管2进行三次注浆,使得浆体通过预留孔渗透到钢管间的土层,增强管幕间连接,继而提高管幕所在地层的稳定性。管幕注浆如图6所示。Finally, grouting is performed three times through the second grouting pipe 2 outside the main body 1 of the pipe curtain, so that the grout penetrates into the soil layer between the steel pipes through the reserved holes, strengthening the connection between the pipe curtains, and thereby improving the stability of the stratum where the pipe curtain is located. The tube curtain grouting is shown in Figure 6.
顶紧平台导坑回填;Backfill the guide pit of the jacking platform;
所有管幕施工完成后,形成地层加固区15,之后进行导坑回填,在管幕承载作用下,进行导洞开挖14等地铁车站建设工作。管幕结构承载示意图如图7所示。After the construction of all pipe curtains is completed, a stratum reinforcement area 15 will be formed, and then the guide pit will be backfilled. Under the load-bearing effect of the pipe curtain, the subway station construction work such as guide tunnel excavation 14 will be carried out. The load-bearing diagram of the tube curtain structure is shown in Figure 7.
以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.
Claims (8)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211683652.0A CN116006217B (en) | 2022-12-27 | 2022-12-27 | Pipe curtain structure and construction method thereof |
PCT/CN2023/128746 WO2024139682A1 (en) | 2022-12-27 | 2023-10-31 | Pipe roofing structure and construction method therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211683652.0A CN116006217B (en) | 2022-12-27 | 2022-12-27 | Pipe curtain structure and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN116006217A CN116006217A (en) | 2023-04-25 |
CN116006217B true CN116006217B (en) | 2024-01-23 |
Family
ID=86026157
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211683652.0A Active CN116006217B (en) | 2022-12-27 | 2022-12-27 | Pipe curtain structure and construction method thereof |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN116006217B (en) |
WO (1) | WO2024139682A1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116006217B (en) * | 2022-12-27 | 2024-01-23 | 中铁十四局集团隧道工程有限公司 | Pipe curtain structure and construction method thereof |
Citations (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06568U (en) * | 1992-06-16 | 1994-01-11 | 石川島播磨重工業株式会社 | Insert ring for pipe welding |
RU2384786C1 (en) * | 2008-11-18 | 2010-03-20 | Открытое акционерное общество "Татнефть" им. В.Д. Шашина | Method of connecting pipes with internal cement-sand coating |
CN102953372A (en) * | 2012-11-14 | 2013-03-06 | 福建工程学院 | Steel pipe pile and construction method thereof |
CN104500875A (en) * | 2014-12-24 | 2015-04-08 | 重庆百齐居建材有限公司 | Convenient-to-weld fire pipeline |
CN106761768A (en) * | 2016-11-10 | 2017-05-31 | 东北大学 | A kind of novel steel tube curtain structure support system and its construction method |
CN206289664U (en) * | 2016-12-06 | 2017-06-30 | 河北健龙建筑设备有限公司 | Major diameter curve pipe curtain steel pipe |
CN206299928U (en) * | 2016-12-28 | 2017-07-04 | 王瑞莲 | A kind of gas field gathering line weld bond leakage-proof structure |
CN107081535A (en) * | 2017-07-03 | 2017-08-22 | 西京学院 | A kind of steel pipe grafting joint for improving structural strength |
CN206554102U (en) * | 2016-12-06 | 2017-10-13 | 河北健龙建筑设备有限公司 | Pipe curtain steel pipe |
KR20170114541A (en) * | 2016-04-05 | 2017-10-16 | 최찬숙 | The structure assembly for building a tunnel and building method thereof |
CN108612118A (en) * | 2016-12-12 | 2018-10-02 | 姚晓宁 | A kind of construction method of the disposable horizontal backfill of pipe curtain steel pipe inner concrete |
CN209353342U (en) * | 2018-08-20 | 2019-09-06 | 中建三局集团有限公司 | A kind of pre support system pipe curtain lock grouting and reinforcing water sealing structure |
CN209830653U (en) * | 2019-04-28 | 2019-12-24 | 中铁二院重庆勘察设计研究院有限责任公司 | Longitudinal connecting joint structure for bolt welding and pipe curtain steel pipe |
CN112427827A (en) * | 2020-11-09 | 2021-03-02 | 上海市基础工程集团有限公司 | Nondestructive welding method for large-diameter plastic-coated steel pipe |
CN112982372A (en) * | 2021-03-11 | 2021-06-18 | 中国建筑第八工程局有限公司 | Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity |
CN217421213U (en) * | 2022-04-06 | 2022-09-13 | 中建八局轨道交通建设有限公司 | Reinforced structure for subway transfer shallow-buried underground tunnel to closely pass through rainwater and sewage pipeline |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB657875A (en) * | 1948-04-21 | 1951-09-26 | Sulzer Ag | Improvements relating to rotors or the like made from at least two sections connected together by annular weld seams |
GB808469A (en) * | 1956-08-01 | 1959-02-04 | Babcock & Wilcox Ltd | Improvements in or relating to tube walls or panels |
JP3892647B2 (en) * | 2000-06-28 | 2007-03-14 | 株式会社神戸製鋼所 | Welded structure and heat exchanger provided with the same |
CN111379571A (en) * | 2018-12-30 | 2020-07-07 | 中铁十四局集团有限公司 | Pipeline, pipe shed structure and pipe shed construction method with same |
CN114856635B (en) * | 2022-05-18 | 2024-10-29 | 中铁工程装备集团有限公司 | Method and device for grouting connecting pipe curtain structure |
CN116006217B (en) * | 2022-12-27 | 2024-01-23 | 中铁十四局集团隧道工程有限公司 | Pipe curtain structure and construction method thereof |
-
2022
- 2022-12-27 CN CN202211683652.0A patent/CN116006217B/en active Active
-
2023
- 2023-10-31 WO PCT/CN2023/128746 patent/WO2024139682A1/en unknown
Patent Citations (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06568U (en) * | 1992-06-16 | 1994-01-11 | 石川島播磨重工業株式会社 | Insert ring for pipe welding |
RU2384786C1 (en) * | 2008-11-18 | 2010-03-20 | Открытое акционерное общество "Татнефть" им. В.Д. Шашина | Method of connecting pipes with internal cement-sand coating |
CN102953372A (en) * | 2012-11-14 | 2013-03-06 | 福建工程学院 | Steel pipe pile and construction method thereof |
CN104500875A (en) * | 2014-12-24 | 2015-04-08 | 重庆百齐居建材有限公司 | Convenient-to-weld fire pipeline |
KR20170114541A (en) * | 2016-04-05 | 2017-10-16 | 최찬숙 | The structure assembly for building a tunnel and building method thereof |
CN106761768A (en) * | 2016-11-10 | 2017-05-31 | 东北大学 | A kind of novel steel tube curtain structure support system and its construction method |
CN206554102U (en) * | 2016-12-06 | 2017-10-13 | 河北健龙建筑设备有限公司 | Pipe curtain steel pipe |
CN206289664U (en) * | 2016-12-06 | 2017-06-30 | 河北健龙建筑设备有限公司 | Major diameter curve pipe curtain steel pipe |
CN108612118A (en) * | 2016-12-12 | 2018-10-02 | 姚晓宁 | A kind of construction method of the disposable horizontal backfill of pipe curtain steel pipe inner concrete |
CN206299928U (en) * | 2016-12-28 | 2017-07-04 | 王瑞莲 | A kind of gas field gathering line weld bond leakage-proof structure |
CN107081535A (en) * | 2017-07-03 | 2017-08-22 | 西京学院 | A kind of steel pipe grafting joint for improving structural strength |
CN209353342U (en) * | 2018-08-20 | 2019-09-06 | 中建三局集团有限公司 | A kind of pre support system pipe curtain lock grouting and reinforcing water sealing structure |
CN209830653U (en) * | 2019-04-28 | 2019-12-24 | 中铁二院重庆勘察设计研究院有限责任公司 | Longitudinal connecting joint structure for bolt welding and pipe curtain steel pipe |
CN112427827A (en) * | 2020-11-09 | 2021-03-02 | 上海市基础工程集团有限公司 | Nondestructive welding method for large-diameter plastic-coated steel pipe |
CN112982372A (en) * | 2021-03-11 | 2021-06-18 | 中国建筑第八工程局有限公司 | Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity |
CN217421213U (en) * | 2022-04-06 | 2022-09-13 | 中建八局轨道交通建设有限公司 | Reinforced structure for subway transfer shallow-buried underground tunnel to closely pass through rainwater and sewage pipeline |
Also Published As
Publication number | Publication date |
---|---|
WO2024139682A1 (en) | 2024-07-04 |
CN116006217A (en) | 2023-04-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105822312B (en) | The construction method that soil pressure balance shielding structure pressure originates in a kind of Metro Tunnel | |
CN112012753B (en) | Shield tunneling machine starting method based on special-shaped extension steel ring | |
JP7257086B2 (en) | Comprehensive Construction Method for Low Overburden Sections of Tunnels | |
CN111677520B (en) | Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method | |
CN108915728B (en) | Construction method of primary support of tunnel arch wall based on gantry support and intrusion limit replacement | |
CN113294166B (en) | Oblique starting method for large-section rectangular jacking pipe | |
CN106014427B (en) | A kind of construction method receiving push-bench and working steel bushing | |
CN106836179A (en) | Vertical strengthening ribs enhanced bellows grouting pile and construction method | |
CN116006217B (en) | Pipe curtain structure and construction method thereof | |
CN112855225B (en) | Soft rock tunnel supporting construction method with high safety | |
CN215057406U (en) | Extension structure is originated in rectangle push pipe slant | |
CN109826634B (en) | Construction method for shield launching and shield receiving of water-rich liquefied sand layer | |
CN104389619A (en) | Shield excess hole construction method | |
CN107700490A (en) | Gunite concrete makes up constructing structure and its construction method in advance between the stratum stake of sand ovum | |
CN110410084B (en) | Prefabricated steel-UHPC composite pipe curtain device and construction method | |
CN115596479A (en) | A support method for preventing roadway surrounding rock deformation | |
CN210483733U (en) | Prefabricated steel-UHPC composite pipe curtain device | |
CN114086982A (en) | High ground stress fragmentation surrounding rock deformation construction control method | |
CN117967324B (en) | Rectangular steel sleeve passing station and receiving construction method for pipe jacking equipment | |
CN220687343U (en) | Hexagonal duct piece combining device without two liners | |
CN222275509U (en) | Advanced grouting expanded-diameter steel pipe diagonal bracing support construction structure for foundation pit | |
CN116146220B (en) | A construction method for large-section rectangular pipe jacking machine | |
CN112878350B (en) | Construction method for accurate grouting waterproof curtain of deep-buried underground excavation station | |
CN113790058B (en) | A soft soil layer small clear distance shield end reinforcement system and its design method | |
CN111379576B (en) | A connection method for initial support and large-diameter pipe shed for canopy method construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |