CN115872255A - Installation method of fast loading shaft for sundries freight elevator - Google Patents

Installation method of fast loading shaft for sundries freight elevator Download PDF

Info

Publication number
CN115872255A
CN115872255A CN202211565573.XA CN202211565573A CN115872255A CN 115872255 A CN115872255 A CN 115872255A CN 202211565573 A CN202211565573 A CN 202211565573A CN 115872255 A CN115872255 A CN 115872255A
Authority
CN
China
Prior art keywords
vertical
transverse
door
door body
installing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211565573.XA
Other languages
Chinese (zh)
Inventor
毛先金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Schmidt Elevator Co ltd
Original Assignee
Schmidt Elevator Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Schmidt Elevator Co ltd filed Critical Schmidt Elevator Co ltd
Priority to CN202211565573.XA priority Critical patent/CN115872255A/en
Publication of CN115872255A publication Critical patent/CN115872255A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B50/00Energy efficient technologies in elevators, escalators and moving walkways, e.g. energy saving or recuperation technologies

Landscapes

  • Elevator Door Apparatuses (AREA)

Abstract

The invention discloses a method for installing a rapid hoistway of a goods elevator, which comprises the following steps: vertical roof beam, direction track and horizontal roof beam, vertical roof beam has four, the horizontal cross-section of vertical roof beam is L shape structure, each horizontal roof beam is square frame shape structure, four vertical roof beams all encircle four corners departments at each horizontal roof beam, the direction track has immediately at the inboard of each horizontal roof beam, the direction track is used for leading elevator car to go up and down, the inner wall that the horizontal roof beam corresponds layer gate one side is the layer door inner wall, three side inner walls are basic inner wall in addition, the three basic inner wall middle parts of horizontal roof beam all are provided with a direction track, the direction track passes through the screw and is connected with horizontal roof beam middle part. The method for installing the sundry goods elevator fast-assembly shaft solves the problem that in the prior art, the production efficiency is low because the vertical beam and the transverse beam need to be welded before leaving a factory.

Description

杂物货梯快装井道安装方法Installation method of fast loading shaft for sundries freight elevator

技术领域technical field

本发明涉及电梯井道,具体涉及一种杂物货梯快装井道安装方法。The invention relates to an elevator shaft, in particular to a method for installing the quick-installed shaft of a miscellaneous cargo elevator.

背景技术Background technique

在电梯系统中,为了实现为轿厢的升降提供一个升降空间,因此设置了电梯井道。在一般居民楼中,电梯井道都是混凝土围成的电梯井道,这个需要在修建房屋的时候,就需要预设电梯井道。而有一些老楼需要加装电梯井道在楼房旁边,为了提高安装效率,因此设计了快装式电梯井道。In the elevator system, in order to provide a lifting space for the lifting of the car, an elevator shaft is provided. In general residential buildings, the elevator shafts are all elevator shafts surrounded by concrete. When building a house, it is necessary to preset the elevator shaft. However, some old buildings need to install an elevator shaft next to the building. In order to improve the installation efficiency, a quick-installed elevator shaft is designed.

现有技术中,快装式电梯井道包括:若干节骨架,骨架包括:导向锥头、竖直梁以及横向梁,竖直梁有四根,四根竖直梁中部被横向梁连接,每根竖直梁底端均延伸有导向锥头,竖直梁为钢管结构,下一节的骨架中竖直梁供上一节的骨架中导向锥头插入,从而方便自傲吊装的时候,上一节骨架与下一节骨架对准。虽然能够提高电梯井道现场的安装效率,但是该快装式电梯井道仍然存在的缺点为:In the prior art, the quick-installed elevator shaft includes: several section skeletons, and the skeleton includes: guide cone heads, vertical beams and transverse beams, there are four vertical beams, and the middle parts of the four vertical beams are connected by transverse beams, each There are guide cones extending from the bottom of the vertical beams. The vertical beams are steel pipe structures. The vertical beams in the skeleton of the next section are inserted into the guide cones in the skeleton of the previous section, so that it is convenient for self-prosperous hoisting. The skeleton is aligned with the skeleton of the next section. Although the on-site installation efficiency of the elevator shaft can be improved, the disadvantages that still exist in the quick-installed elevator shaft are:

但是生产过程中,需要在出厂之前将竖直梁和横向梁焊接在一起,同时也需要在竖直梁底端生产导向锥头,导致生产效率低,导致需要足够长的时间才能出厂,对于货梯这种安全性要求不高,又需要快速安装的场景来说,时间等不起。However, in the production process, the vertical beam and the horizontal beam need to be welded together before leaving the factory. At the same time, the guide cone needs to be produced at the bottom of the vertical beam, resulting in low production efficiency and a long enough time to leave the factory. For freight elevators For a scenario where the security requirements are not high and quick installation is required, time cannot afford to wait.

发明内容Contents of the invention

本发明要提供一种杂物货梯快装井道安装方法,解决现有技术中因在出厂之前需要将竖直梁和横向梁焊接而导致生产效率低的问题。The present invention provides a quick-loading hoistway installation method for sundry cargo elevators, which solves the problem of low production efficiency in the prior art due to the need to weld the vertical beams and transverse beams before leaving the factory.

为实现上述目的,本发明采用了如下的技术方案:To achieve the above object, the present invention adopts the following technical solutions:

本发明公开了一种杂物货梯快装井道安装方法,包括如下步骤:The invention discloses a method for installing a fast-loading hoistway of a miscellaneous cargo elevator, which comprises the following steps:

S1、备好如下部件:竖直梁、导向轨道以及横向梁,竖直梁有四根,竖直梁的水平截面均为L形结构,每一横向梁均为方框形结构,导向轨道用于导向电梯轿厢升降,横向梁对应层门口一侧的内壁为层门内壁,另外三侧内壁为基本内壁;S1. Prepare the following components: vertical beams, guide rails and transverse beams. There are four vertical beams. The horizontal sections of the vertical beams are all L-shaped structures. For the elevator car to go up and down, the inner wall of the horizontal beam corresponding to the landing door is the inner wall of the landing door, and the inner walls of the other three sides are the basic inner walls;

S2、安装竖直梁:在地面上浇筑混凝土层,混凝土层内插入竖直梁;S2. Install vertical beams: pour a concrete layer on the ground, and insert vertical beams into the concrete layer;

S3、安装横向梁:将横向梁置入四根竖直梁之间,四根竖直梁均环绕在每一横向梁的四个角落处;S3, install the transverse beam: place the transverse beam between the four vertical beams, and the four vertical beams surround the four corners of each transverse beam;

S4、安装导向轨道:横向梁的基本内壁中部均设置有一导向轨道,导向轨道通过螺钉与横向梁中部连接。S4. Installing the guide rail: the middle part of the basic inner wall of the transverse beam is provided with a guide track, and the guide track is connected with the middle part of the transverse beam through screws.

优选的是,步骤S3中,使用卡接机构将竖直梁与横向梁连接。Preferably, in step S3, the vertical beams are connected to the horizontal beams using a snap-fit mechanism.

优选的是,卡接机构包括:压紧螺栓以及卡爪,卡爪被压紧螺栓压紧在竖直梁上,压紧螺栓安装在横向梁上。Preferably, the clamping mechanism includes: a clamping bolt and a clamping claw, the clamping claw is clamped on the vertical beam by the clamping bolt, and the clamping bolt is installed on the transverse beam.

优选的是,卡爪包括:盘体以及爪部,盘体一端面凸出形成有至少三爪部,盘体与压紧螺栓大端紧贴,爪部被压紧在竖直梁和横向梁上。Preferably, the jaws include: a disc body and claws, at least three claws protrude from one end of the disc body, the disc body is in close contact with the big end of the compression bolt, and the claws are pressed against the vertical beam and the transverse beam superior.

优选的是,步骤S1中同时还备好如下部件:门导轨以及层门装置,步骤S3完成后还执行以下步骤:Preferably, the following components are also prepared in step S1: door guide rail and landing door device, and the following steps are performed after step S3 is completed:

S5、安装门导轨:在横向梁与竖直梁的连接处安装门导轨;S5, install the door guide rail: install the door guide rail at the junction of the horizontal beam and the vertical beam;

S6、安装层门装置:门导轨上安装层门装置,且层门装置对应相邻两横向梁安装。S6. Install the landing door device: install the landing door device on the door guide rail, and install the landing door device corresponding to two adjacent transverse beams.

优选的是,步骤S1中备好的层门装置包括如下部件:上门体、下门体以及竖直驱动机构;Preferably, the landing door device prepared in step S1 includes the following components: an upper door body, a lower door body and a vertical driving mechanism;

步骤S3包括如下步骤:Step S3 comprises the following steps:

S31、将上门体和下门体安装在电梯井中安装的门导轨上,上门体和下门体能在门导轨导向下在竖直方向上运动;S31, installing the upper door body and the lower door body on the door guide rail installed in the elevator shaft, the upper door body and the lower door body can move in the vertical direction under the guidance of the door guide rail;

S32、将在门导轨旁安装竖直驱动机构,竖直驱动机构有两个,一个竖直驱动机构的输出端连接至上门体,另一个竖直驱动机构的输出端连接至下门体。S32. A vertical drive mechanism will be installed next to the door guide rail. There are two vertical drive mechanisms. The output end of one vertical drive mechanism is connected to the upper door body, and the output end of the other vertical drive mechanism is connected to the lower door body.

优选的是,对应每一层门装置中两横向梁中一横向梁为第一横筋,另一横向梁为第二横筋;Preferably, one of the two transverse beams corresponding to each floor door device is the first transverse rib, and the other transverse beam is the second transverse rib;

步骤S1中备好上门体和下门体的步骤为:The steps for preparing the upper door body and the lower door body in step S1 are:

S11、备好上门体和下门体包括的部件:上门体和下门体均包括:门板、阻挡板以及导向板:门板包括:板体以及边框,边框有两个,每一边框均由两边块构成;S11. Prepare the parts included in the upper door body and the lower door body: both the upper door body and the lower door body include: door panel, blocking plate and guide plate; the door panel includes: panel body and frame. block composition;

S12、安装边框:将两边块夹紧在板体一侧形成一边框,将两边块夹紧在板体另一侧形成另一边框;S12. Install the frame: clamp the two side blocks on one side of the board body to form a frame, and clamp the two side blocks on the other side of the board body to form another frame;

S13、安装导向板:通过第一安装螺栓和第一螺帽将导向板安装在两边框上,第一安装螺栓大端和第一螺帽夹紧边框的两边块以及导向板,板体上端和下端均安装导向板;S13. Install the guide plate: install the guide plate on the two frames through the first installation bolt and the first nut, the large end of the first installation bolt and the first nut clamp the two side blocks of the frame and the guide plate, the upper end of the plate body and the guide plate Guide plates are installed at the lower end;

S14、安装阻挡板:在边框端部上安装阻挡板,阻挡板勾住第一横筋或第二横筋。S14. Install the blocking plate: Install the blocking plate on the end of the frame, and the blocking plate hooks the first transverse rib or the second transverse rib.

优选的是,阻挡板呈现为“ㄣ”形结构,阻挡板一侧开设有两第一定位孔,阻挡板另一侧开设有两第二定位孔,第一定位孔和第二定位孔均供第二安装螺栓穿过,第二安装螺栓穿过边框,第二安装螺栓与第二螺帽配合夹紧阻挡板以及边框。Preferably, the blocking plate has a "ㄣ"-shaped structure, two first positioning holes are opened on one side of the blocking plate, and two second positioning holes are opened on the other side of the blocking plate, and both the first positioning hole and the second positioning hole are used for The second installation bolt passes through, the second installation bolt passes through the frame, and the second installation bolt cooperates with the second nut to clamp the blocking plate and the frame.

相比于现有技术,本发明具有如下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

实现了电梯井道的骨架仅仅由竖直梁和横向梁制成,且在出厂之前不需要焊接竖直梁和横向梁,且不需要在竖直梁上形成导向锥头,减少了骨架在工厂生产的时间,且在现场组装的时候,仅仅需要将横向梁焊接在竖直梁上,不需要耗费大量的人力和物力来吊装现有技术的骨架节,提高了生产效率。当然本申请中是因为杂物货梯要求不高,仅仅将电梯井道安装牢靠即可,同时整个杂物货梯快装井道安装方法高度也不高,因此仅仅设置整根竖直梁来形成杂物货梯快装井道安装方法,应用方向的特殊性。Realized that the skeleton of the elevator shaft is only made of vertical beams and transverse beams, and does not need to weld the vertical beams and transverse beams before leaving the factory, and does not need to form a guide cone on the vertical beams, which reduces the production time of the skeleton in the factory , and during on-site assembly, only the transverse beams need to be welded to the vertical beams, without spending a lot of manpower and material resources to hoist the skeleton joints of the prior art, which improves the production efficiency. Of course, in this application, because the requirements for the sundry goods elevator are not high, it is only necessary to install the elevator shaft firmly, and at the same time, the installation method of the quick-installation shaft of the sundry goods elevator is not high, so only the entire vertical beam is set to form the sundries goods elevator The installation method of the quick-loading shaft and the particularity of the application direction.

本发明的其它优点、目标和特征将部分通过下面的说明体现,部分还将通过对本发明的研究和实践而为本领域的技术人员所理解。Other advantages, objectives and features of the present invention will partly be embodied through the following descriptions, and partly will be understood by those skilled in the art through the study and practice of the present invention.

附图说明Description of drawings

图1为杂物货梯快装井道安装方法的结构示意图;Fig. 1 is the structural representation of the fast loading hoistway installation method of sundry cargo elevator;

图2为图1中I处的放大图。Fig. 2 is an enlarged view of position I in Fig. 1 .

图3为层门装置处的结构示意图。Fig. 3 is a schematic diagram of the structure of the landing door device.

附图标记:竖直梁1、导向轨道2、横向梁3、卡接机构4、压紧螺栓41、卡爪42、盘体421、爪部422、层门装置5、上门体51、下门体52、门板511、阻挡板512、导向板513、板体514、边框515、第一定位孔516、第二定位孔517、第二安装螺栓518、门导轨6。Reference signs: vertical beam 1, guide rail 2, transverse beam 3, clamping mechanism 4, compression bolt 41, claw 42, plate body 421, claw part 422, landing door device 5, upper door body 51, lower door Body 52, door panel 511, blocking plate 512, guide plate 513, plate body 514, frame 515, first positioning hole 516, second positioning hole 517, second mounting bolt 518, door guide rail 6.

具体实施方式Detailed ways

为了使本发明实现的技术手段、创作特征、达成目的与作用更加清楚及易于了解,下面结合附图和具体实施方式对本发明作进一步阐述:In order to make the technical means, creative features, goals and functions achieved by the present invention clearer and easier to understand, the present invention will be further elaborated below in conjunction with the accompanying drawings and specific embodiments:

实施例1:Example 1:

如图1以及图2所示,本实施例公开了一种杂物货梯快装井道安装方法,包括:竖直梁1、导向轨道2以及横向梁3,竖直梁1有四根,竖直梁1的水平截面均为L形结构,每一横向梁3均为方框形结构,四根竖直梁1均环绕在每一横向梁3的四个角落处,在每一横向梁3的内侧立有导向轨道2,导向轨道2用于导向电梯轿厢升降,横向梁3对应层门口一侧的内壁为层门内壁,另外三侧内壁为基本内壁,横向梁3的三个基本内壁中部均设置有一导向轨道2,导向轨道2通过螺钉与横向梁3中部连接。As shown in Fig. 1 and Fig. 2, the present embodiment discloses a method for installing a quick-installation hoistway of a miscellaneous cargo elevator, including: vertical beams 1, guide rails 2 and transverse beams 3, there are four vertical beams 1, vertical The horizontal section of the beam 1 is an L-shaped structure, and each transverse beam 3 is a square frame structure, and four vertical beams 1 surround the four corners of each transverse beam 3, and each transverse beam 3 There is a guide rail 2 on the inner side, and the guide rail 2 is used to guide the elevator car to go up and down. The inner wall of the side of the horizontal beam 3 corresponding to the landing door is the inner wall of the landing door, and the inner walls of the other three sides are the basic inner walls. The middle part of the three basic inner walls of the transverse beam 3 All are provided with a guide rail 2, and the guide rail 2 is connected with the middle part of the transverse beam 3 by screws.

竖直梁1通过卡接机构4与横向梁3连接。以竖直梁1为基础,竖直梁1的设置为横向梁3提供了安装基础,横向梁3起到的是抱起四根竖直梁1的作用,同时也为层门的设置提供了安装基础。The vertical beam 1 is connected to the transverse beam 3 through a clamping mechanism 4 . Based on the vertical beam 1, the setting of the vertical beam 1 provides the installation foundation for the horizontal beam 3, and the horizontal beam 3 plays the role of holding up the four vertical beams 1, and also provides a basis for the setting of the landing door. Install base.

卡接机构4包括:压紧螺栓41以及卡爪42,卡爪42被压紧螺栓41压紧在竖直梁1上,压紧螺栓41安装在横向梁3上。实现了压紧螺栓41安装在横向梁3上,卡爪42被压紧螺栓41压紧在竖直梁1上,从而限制横向梁3在竖直梁1上运动。The clamping mechanism 4 includes: a pressing bolt 41 and a claw 42 , the claw 42 is pressed on the vertical beam 1 by the pressing bolt 41 , and the pressing bolt 41 is installed on the transverse beam 3 . It realizes that the pressing bolt 41 is installed on the transverse beam 3 , and the claw 42 is pressed on the vertical beam 1 by the pressing bolt 41 , thereby restricting the movement of the transverse beam 3 on the vertical beam 1 .

卡爪42包括:盘体421以及爪部422,盘体421一端面凸出形成有至少三爪部422,盘体421与压紧螺栓41大端紧贴,爪部422被压紧在竖直梁1和横向梁3上。盘体421与压紧螺栓41配合提供了基础,爪部422则是抓紧在竖直梁1上。The claw 42 includes: a disc body 421 and a claw portion 422. At least three claw portions 422 protrude from one end of the disc body 421. The disc body 421 is in close contact with the large end of the compression bolt 41, and the claw portion 422 is compressed in a vertical position. Beam 1 and Transverse Beam 3. The plate body 421 cooperates with the pressing bolt 41 to provide a foundation, and the claw portion 422 is then grasped on the vertical beam 1 .

在电梯井道底部安装有支撑电梯轿厢的缓冲支撑装置(图中未示)。避免了轿厢冲击电梯井道底部而导致轿厢损坏。A buffer support device (not shown) for supporting the elevator car is installed at the bottom of the elevator shaft. The car is prevented from being damaged by impacting the bottom of the elevator shaft.

缓冲支撑装置包括:缓冲头以及支撑柱,支撑柱安装在底坑,支撑柱顶部安装有缓冲头,缓冲头采用弹性材料制成,缓冲头向着电梯轿厢延伸。缓冲头用于与电梯轿厢接触,缓冲头连接支撑柱,从而为缓冲头提供安装基础。The buffer support device includes: a buffer head and a support column, the support column is installed in the bottom pit, the buffer head is installed on the top of the support column, the buffer head is made of elastic material, and the buffer head extends toward the elevator car. The buffer head is used to contact the elevator car, and the buffer head is connected to the support column, thus providing the installation base for the buffer head.

横向梁3的层门内壁上安装层门装置5。横向梁3为层门装置5的开闭提供了基础,也就是对应两相邻横向梁3之间,层门装置5对应安装。A landing door device 5 is installed on the inner wall of the landing door of the transverse beam 3 . The transverse beam 3 provides a basis for the opening and closing of the landing door device 5 , that is, the landing door device 5 is correspondingly installed between two adjacent transverse beams 3 .

层门装置5包括:上门体51、下门体52以及竖直驱动机构,上门体51和下门体52安装在电梯井中安装的门导轨6上(图中,门导轨6和竖直梁1长短不一致,由于图只是示意图,门导轨6和竖直梁1在实际中长短一致),上门体51和下门体52能在门导轨6导向下在竖直方向上运动;对应每一楼层均设置有两相互间隔的横向梁3,对应每一楼层的横向梁3中一横向梁3为第一横筋,另一横向梁3为第二横筋,第一横筋和第二横筋位于门导轨6旁,对应每一楼层均设置有一组第一横筋和第二横筋,每组中第一横筋和第二横筋之间有间隙;上门体51和下门体52均包括:门板511、阻挡板512以及导向板513,门板511上安装有阻挡板512,阻挡板512用于通过与第一横筋和第二横筋配合限制上门体51和下门体52的运行范围,门板511上安装有导向板513,导向板513在能滑动地伸入至门导轨6,门导轨6位于竖直方向上;在电梯井中安装有竖直驱动机构(图中未示),竖直驱动机构地输出端连接至上门体51和下门体52,竖直驱动机构用于驱动上门体51和下门体52开闭。横向梁3不但将竖直梁1连接在了一起,同时横向梁3与阻挡板512配合,限制了层门的运行范围。在竖直梁1处安装门导轨6,门导轨6通过导向板513导向上门体51和下门体52的运行,使得上门体51和下门体52按照指定范围运行。The landing door device 5 includes: an upper door body 51, a lower door body 52 and a vertical drive mechanism, and the upper door body 51 and the lower door body 52 are installed on the door guide rail 6 installed in the elevator shaft (in the figure, the door guide rail 6 and the vertical beam 1 Inconsistent in length, because the figure is only a schematic diagram, the door guide rail 6 and the vertical beam 1 are consistent in length in reality), the upper door body 51 and the lower door body 52 can move in the vertical direction under the guidance of the door guide rail 6; corresponding to each floor There are two transverse beams 3 spaced apart from each other, one of the transverse beams 3 corresponding to each floor is the first transverse bar, and the other transverse beam 3 is the second transverse bar, and the first transverse bar and the second transverse bar are located beside the door guide rail 6 , each floor is provided with a group of first and second cross bars, and there is a gap between the first and second bars in each group; the upper door body 51 and the lower door body 52 include: a door panel 511, a blocking plate 512 and Guide plate 513, a blocking plate 512 is installed on the door plate 511, and the blocking plate 512 is used to limit the operating range of the upper door body 51 and the lower door body 52 by cooperating with the first transverse rib and the second transverse rib, and the door plate 511 is equipped with a guide plate 513, The guide plate 513 is slidably stretched into the door guide rail 6, and the door guide rail 6 is positioned in the vertical direction; a vertical drive mechanism (not shown) is installed in the elevator shaft, and the output end of the vertical drive mechanism is connected to the upper door body 51 and the lower door body 52, the vertical drive mechanism is used to drive the upper door body 51 and the lower door body 52 to open and close. The transverse beam 3 not only connects the vertical beams 1 together, but also cooperates with the blocking plate 512 to limit the operating range of the landing door. Door guide rail 6 is installed at vertical beam 1 place, and door guide rail 6 guides the operation of upper door body 51 and lower door body 52 by guide plate 513, makes upper door body 51 and lower door body 52 run according to specified range.

装整个杂货电梯快装井道的时候,首先,将竖直梁1通过混凝土结构预埋在地面上,混凝土结构保证整个竖直梁1处于竖直状态,也保证竖直梁1处于站立状态;然后,将横向梁3放置于四根竖直梁1之间,保持所有横向梁3相互间隔地设置在竖直梁1上,横向梁3通过卡接机构4安装在竖直梁1上,卡接机构4仅能需要旋转压紧螺栓41到位即可,压紧螺栓41与穿过盘体421,从而通过盘体421将爪部422压紧在竖直梁1上,爪部422将每根竖直梁1向着四根竖直梁1的中心拉,从而使得四根竖直梁1能够被抱紧在一起,避免竖直梁1向着四根竖直梁1外偏倒,从而保证竖直梁1位于竖直方向上,同时竖直梁1通过与爪部422的摩擦而限制横向梁3在竖直梁1上滑动;再后,安装门导轨6,门导轨6焊接在横向梁3和竖直梁1上;最后,安装上门体51和下门体52。When installing the entire cargo elevator for fast-loading the hoistway, firstly, the vertical beam 1 is pre-embedded on the ground through a concrete structure, and the concrete structure ensures that the entire vertical beam 1 is in a vertical state, and also ensures that the vertical beam 1 is in a standing state; then , placing the transverse beams 3 between the four vertical beams 1, keeping all the transverse beams 3 spaced apart from each other on the vertical beams 1, the transverse beams 3 are installed on the vertical beams 1 through the clamping mechanism 4, and the clamping The mechanism 4 only needs to rotate the compression bolt 41 to put it in place, and the compression bolt 41 passes through the disc body 421, so that the claw part 422 is pressed on the vertical beam 1 by the disc body 421, and the claw part 422 pushes each vertical beam The straight beam 1 is pulled toward the center of the four vertical beams 1, so that the four vertical beams 1 can be tightly held together, and the vertical beam 1 is prevented from tilting toward the outside of the four vertical beams 1, thereby ensuring that the vertical beams 1 is located in the vertical direction, while the vertical beam 1 limits the sliding of the horizontal beam 3 on the vertical beam 1 by friction with the claw part 422; then, install the door guide rail 6, and the door guide rail 6 is welded on the horizontal beam 3 and the vertical beam 1 On the straight beam 1; finally, install the upper door body 51 and the lower door body 52.

实施例2:Example 2:

如图1至图3所示,基于实施例1,本实施例公开了一种杂物货梯快装井道安装方法,包括如下步骤:As shown in Figures 1 to 3, based on Embodiment 1, this embodiment discloses a method for installing a fast-loading hoistway for a sundry cargo elevator, including the following steps:

S1、备好如下部件:竖直梁1、导向轨道2以及横向梁3,竖直梁1有四根,竖直梁1的水平截面均为L形结构,每一横向梁3均为方框形结构,导向轨道2用于导向电梯轿厢升降,横向梁3对应层门口一侧的内壁为层门内壁,另外三侧内壁为基本内壁;S1. Prepare the following components: vertical beam 1, guide rail 2 and horizontal beam 3, there are four vertical beams 1, the horizontal section of vertical beam 1 is L-shaped structure, and each horizontal beam 3 is a square frame Shaped structure, the guide track 2 is used to guide the elevator car up and down, the inner wall of the transverse beam 3 corresponding to the landing door side is the inner wall of the landing door, and the inner walls of the other three sides are the basic inner walls;

S2、安装竖直梁1:在地面上浇筑混凝土层,混凝土层内插入竖直梁1;S2. Installing the vertical beam 1: pouring a concrete layer on the ground, inserting the vertical beam 1 in the concrete layer;

S3、安装横向梁3:将横向梁3置入四根竖直梁1之间,四根竖直梁1均环绕在每一横向梁3的四个角落处;S3, install the transverse beam 3: place the transverse beam 3 between the four vertical beams 1, and the four vertical beams 1 surround the four corners of each transverse beam 3;

S4、安装导向轨道2:横向梁3的基本内壁中部均设置有一导向轨道2,导向轨道2通过螺钉与横向梁3中部连接。S4. Install the guide rail 2: the middle part of the basic inner wall of the transverse beam 3 is provided with a guide track 2, and the guide track 2 is connected with the middle part of the transverse beam 3 by screws.

步骤S3中,使用卡接机构4将竖直梁1与横向梁3连接。In step S3 , the vertical beam 1 is connected to the transverse beam 3 using the clamping mechanism 4 .

卡接机构4包括:压紧螺栓41以及卡爪42,卡爪42被压紧螺栓41压紧在竖直梁1上,压紧螺栓41安装在横向梁3上。The clamping mechanism 4 includes: a pressing bolt 41 and a claw 42 , the claw 42 is pressed on the vertical beam 1 by the pressing bolt 41 , and the pressing bolt 41 is installed on the transverse beam 3 .

卡爪42包括:盘体421以及爪部422,盘体421一端面凸出形成有至少三爪部422,盘体421与压紧螺栓41大端紧贴,爪部422被压紧在竖直梁1和横向梁3上。The claw 42 includes: a disc body 421 and a claw portion 422. At least three claw portions 422 protrude from one end of the disc body 421. The disc body 421 is in close contact with the large end of the compression bolt 41, and the claw portion 422 is compressed in a vertical position. Beam 1 and Transverse Beam 3.

优选的是,步骤S1中同时还备好如下部件:门导轨6以及层门装置5,步骤S3完成后还执行以下步骤:Preferably, the following components are also prepared in step S1: door guide rail 6 and landing door device 5, and the following steps are performed after step S3 is completed:

S5、安装门导轨6:在横向梁3与竖直梁1的连接处安装门导轨6;S5, install the door guide rail 6: install the door guide rail 6 at the junction of the transverse beam 3 and the vertical beam 1;

S6、安装层门装置5:门导轨6上安装层门装置5,且层门装置5对应相邻两横向梁3安装。S6. Installing the landing door device 5: the landing door device 5 is installed on the door guide rail 6, and the landing door device 5 is installed corresponding to two adjacent transverse beams 3.

步骤S1中备好的层门装置5包括如下部件:上门体51、下门体52以及竖直驱动机构;The landing door device 5 prepared in step S1 includes the following components: an upper door body 51, a lower door body 52 and a vertical drive mechanism;

步骤S3包括如下步骤:Step S3 comprises the following steps:

S31、将上门体51和下门体52安装在电梯井中安装的门导轨6上,上门体51和下门体52能在门导轨6导向下在竖直方向上运动;S31, the upper door body 51 and the lower door body 52 are installed on the door guide rail 6 installed in the elevator shaft, the upper door body 51 and the lower door body 52 can move in the vertical direction under the guidance of the door guide rail 6;

S32、将在门导轨6旁安装竖直驱动机构,竖直驱动机构有两个,一个竖直驱动机构的输出端连接至上门体51,另一个竖直驱动机构的输出端连接至下门体52。S32. A vertical drive mechanism will be installed next to the door guide rail 6. There are two vertical drive mechanisms. The output end of one vertical drive mechanism is connected to the upper door body 51, and the output end of the other vertical drive mechanism is connected to the lower door body. 52.

优选的是,对应每一层门装置5中两横向梁3中一横向梁3为第一横筋,另一横向梁3为第二横筋;Preferably, one of the two transverse beams 3 corresponding to each floor door device 5 is the first transverse rib, and the other transverse beam 3 is the second transverse rib;

步骤S1中备好上门体51和下门体52的步骤为:The steps of getting the upper door body 51 and the lower door body 52 ready in step S1 are:

S11、备好上门体51和下门体52包括的部件:上门体51和下门体52均包括:门板511、阻挡板512以及导向板513:门板511包括:板体514以及边框515,边框515有两个,每一边框515均由两边块构成;S11. Prepare the parts included in the upper door body 51 and the lower door body 52: the upper door body 51 and the lower door body 52 include: a door panel 511, a blocking plate 512 and a guide plate 513; the door panel 511 includes: a panel body 514 and a frame 515, the frame 515 has two, and each frame 515 is all made of two side blocks;

S12、安装边框515:将两边块夹紧在板体514一侧形成一边框515,将两边块夹紧在板体514另一侧形成另一边框515;S12, install the frame 515: clamp the two side blocks on one side of the plate body 514 to form a frame 515, and clamp the two side blocks on the other side of the plate body 514 to form another frame 515;

S13、安装导向板513:通过第一安装螺栓和第一螺帽将导向板513安装在两边框515上,第一安装螺栓大端和第一螺帽夹紧边框515的两边块以及导向板513,板体514上端和下端均安装导向板513;S13. Install the guide plate 513: install the guide plate 513 on the two frames 515 through the first installation bolt and the first nut, and clamp the two side blocks of the frame 515 and the guide plate 513 by the big end of the first installation bolt and the first nut , the upper end and the lower end of the plate body 514 are equipped with a guide plate 513;

S14、安装阻挡板512:在边框515端部上安装阻挡板512,阻挡板512勾住第一横筋或第二横筋。S14. Install the blocking plate 512: install the blocking plate 512 on the end of the frame 515, and the blocking plate 512 hooks the first transverse rib or the second transverse rib.

阻挡板512呈现为“ㄣ”形结构,阻挡板512一侧开设有两第一定位孔516,阻挡板512另一侧开设有两第二定位孔517,第一定位孔516和第二定位孔517均供第二安装螺栓518穿过,第二安装螺栓518穿过边框515,第二安装螺栓518与第二螺帽配合夹紧阻挡板512以及边框515。The blocking plate 512 presents a "ㄣ"-shaped structure. One side of the blocking plate 512 is provided with two first positioning holes 516, and the other side of the blocking plate 512 is provided with two second positioning holes 517. The first positioning hole 516 and the second positioning hole 517 are for the second mounting bolts 518 to pass through, the second mounting bolts 518 pass through the frame 515 , and the second mounting bolts 518 cooperate with the second nuts to clamp the blocking plate 512 and the frame 515 .

本申请中,首先,为了整个井道能够站立,因此设置了混凝土层,混凝土层将竖直梁1树立在地面上,避免了竖直梁1偏倒,整个竖直梁1后续承担所有部件的重量,因此混凝土层为基础处,要牢靠;然后,设置了横向梁3,横向梁3上安装卡接机构4,卡接机构4使得四根竖直梁1向中间拉,从而避免了竖直梁1有偏倒的倾向,同时将横向梁3定位在竖直梁1上,横向梁3的设置为后续层门装置5的设置提供了基础,特别是与层门装置5中阻挡板512配合,限制了上门体51和下门体52的运行范围;再后,为了方便安装成上门体51和下门体52,因此设置了边块将板体514两侧夹紧,避免了因此板体514较薄而导致人被割伤,同时边框515安装导向板513,可以将两边块配合定位在板体514上;再后,为了设置上门体51和下门体52的运行范围,因此设置了阻挡板512,阻挡板512与横向梁3形成的第一横筋和第二横筋,从而限定了阻挡板512的运行范围;最后,通过设置阻挡板512呈现为“ㄣ”形结构,同时阻挡板512一侧设置第一定位孔516,阻挡板512另一侧设置第二定位孔517,实现了安装阻挡板512的时候,不需要注意阻挡板512的方向,从而使得阻挡板512能够勾住第一横筋和第二横筋,安装的时候不需要注意阻挡板512第一定位孔516处与边框515紧贴,还是阻挡板512第二定位孔517处与边框515紧贴;当阻挡板512第一定位孔516处与边框515紧贴的时候,第二安装螺栓518穿过第一定位孔516,第二安装螺栓518大端与第二螺帽配合阻挡板512以及边框515即可;当阻挡板512第二定位孔517处与边框515紧贴的时候,第二安装螺栓518穿过第二定位孔517,第二安装螺栓518大端与第二螺帽配合阻挡板512以及边框515即可,使得阻挡板512在边框515上的安装更加方便。In this application, first of all, in order that the entire hoistway can stand, a concrete layer is set up, and the concrete layer erects the vertical beam 1 on the ground, avoiding the vertical beam 1 from tilting, and the entire vertical beam 1 subsequently bears the weight of all components , so the concrete layer is the foundation, and it must be firm; then, a horizontal beam 3 is installed, and a clamping mechanism 4 is installed on the horizontal beam 3. The clamping mechanism 4 makes the four vertical beams 1 pull toward the middle, thereby avoiding the vertical beam 1 has a tendency to be tilted, and at the same time, the transverse beam 3 is positioned on the vertical beam 1. The setting of the transverse beam 3 provides a basis for the setting of the subsequent landing door device 5, especially in cooperation with the blocking plate 512 in the landing door device 5, The operating range of the upper door body 51 and the lower door body 52 is limited; then, in order to facilitate the installation of the upper door body 51 and the lower door body 52, side blocks are provided to clamp both sides of the board body 514, so that the board body 514 is avoided. It is thinner and causes people to be cut. At the same time, the frame 515 is equipped with a guide plate 513, and the two side blocks can be matched and positioned on the plate body 514; Plate 512, the first transverse rib and the second transverse rib formed by blocking plate 512 and transverse beam 3, thereby limiting the operating range of blocking plate 512; finally, by setting blocking plate 512, it is presented as a "ㄣ" shaped structure, while blocking plate 512 The first positioning hole 516 is set on one side, and the second positioning hole 517 is set on the other side of the blocking plate 512, so that when the blocking plate 512 is installed, no need to pay attention to the direction of the blocking plate 512, so that the blocking plate 512 can hook the first transverse rib And the second transverse rib, when installing, it is not necessary to pay attention to whether the first positioning hole 516 of the blocking plate 512 is close to the frame 515, or the second positioning hole 517 of the blocking plate 512 is close to the frame 515; when the first positioning hole of the blocking plate 512 When the 516 place is close to the frame 515, the second mounting bolt 518 passes through the first positioning hole 516, and the large end of the second mounting bolt 518 and the second nut cooperate with the blocking plate 512 and the frame 515; When the second positioning hole 517 is close to the frame 515, the second mounting bolt 518 passes through the second positioning hole 517, and the large end of the second mounting bolt 518 cooperates with the second nut to block the plate 512 and the frame 515, so that the blocking plate 512 and the frame 515 can be blocked. The installation of the plate 512 on the frame 515 is more convenient.

最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的宗旨和范围,其均应涵盖在本发明的权利要求范围当中。Finally, it is noted that the above embodiments are only used to illustrate the technical solutions of the present invention without limitation. Although the present invention has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical solutions of the present invention can be carried out Modifications or equivalent replacements without departing from the spirit and scope of the technical solution of the present invention shall be covered by the claims of the present invention.

Claims (8)

1. The installation method of the rapid hoistway of the cargo lift is characterized by comprising the following steps:
s1, preparing the following components: the elevator car lifting guide device comprises four vertical beams, four guide rails and four transverse beams, wherein the horizontal sections of the vertical beams are L-shaped structures, each transverse beam is of a square frame structure, the guide rails are used for guiding the elevator car to lift, the inner wall of one side, corresponding to a landing door, of each transverse beam is a landing door inner wall, and the inner walls of the other three sides are basic inner walls;
s2, mounting a vertical beam: pouring a concrete layer on the ground, and inserting a vertical beam into the concrete layer;
s3, mounting a transverse beam: placing the transverse beams among four vertical beams, wherein the four vertical beams surround four corners of each transverse beam;
s4, installing a guide rail: the middle parts of the basic inner walls of the transverse beams are provided with guide rails, and the guide rails are connected with the middle parts of the transverse beams through screws.
2. The method for installing the package well of the glove cargo lift according to claim 1, wherein in step S3, the vertical beam and the transverse beam are connected by a clamping mechanism.
3. The method for installing the rapid loading shaft of the cargo lift according to claim 2, characterized in that the clamping mechanism comprises: the clamping jaw is pressed on the vertical beam by the pressing bolt, and the pressing bolt is installed on the transverse beam.
4. The method of installing the glove cargo lift quick-install hoistway of claim 3, wherein the claw comprises: the clamping device comprises a disc body and claw parts, wherein at least three claw parts are formed on one end face of the disc body in a protruding mode, the disc body is tightly attached to the large end of the pressing bolt, and the claw parts are pressed on the vertical beam and the transverse beam.
5. The method for installing the glove cargo lift quick-installation hoistway according to any one of claims 1 to 4, wherein the following components are prepared in step S1: and the door guide rail and the landing door device, after the step S3 is finished, the following steps are executed:
s5, mounting a door guide rail: a door guide rail is arranged at the joint of the transverse beam and the vertical beam;
s6, installing a landing door device: and a landing door device is arranged on the door guide rail and is arranged corresponding to the two adjacent transverse beams.
6. The method for installing the rapid package hoistway of the cargo lift according to claim 5, wherein the landing door device prepared in the step S1 comprises the following components: the door comprises an upper door body, a lower door body and a vertical driving mechanism;
the step S3 comprises the following steps:
s31, mounting an upper door body and a lower door body on a door guide rail mounted in the elevator shaft, wherein the upper door body and the lower door body can move in the vertical direction under the guidance of the door guide rail;
and S32, installing two vertical driving mechanisms beside the door guide rail, wherein the output end of one vertical driving mechanism is connected to the upper door body, and the output end of the other vertical driving mechanism is connected to the lower door body.
7. The method as claimed in claim 6, wherein one of the two transverse beams of each landing door assembly is a first transverse rib, and the other transverse beam is a second transverse rib;
the step of preparing the upper door body and the lower door body in the step S1 comprises the following steps:
s11, preparing parts of the upper door body and the lower door body: the upper door body and the lower door body both comprise: door plant, barrier plate and deflector: the door panel includes: the plate comprises a plate body and two frames, wherein each frame is composed of two side blocks;
s12, installing a frame: clamping the two side blocks on one side of the plate body to form a frame, and clamping the two side blocks on the other side of the plate body to form another frame;
s13, installing a guide plate: the guide plates are arranged on the two frames through a first mounting bolt and a first nut, the large end of the first mounting bolt and the first nut clamp the two side blocks of the frames and the guide plates, and the guide plates are arranged at the upper end and the lower end of the plate body;
s14, mounting a blocking plate: and a blocking plate is arranged at the end part of the frame and hooks the first transverse rib or the second transverse rib.
8. The method for installing the rapid loading hoistway of the cargo lift of the sundries according to claim 7, wherein the blocking plate is of a structure like a '12579', one side of the blocking plate is provided with two first positioning holes, the other side of the blocking plate is provided with two second positioning holes, the first positioning holes and the second positioning holes are used for the second installation bolts to pass through, the second installation bolts pass through the frame, and the second installation bolts are matched with second nuts to clamp the blocking plate and the frame tightly.
CN202211565573.XA 2022-12-07 2022-12-07 Installation method of fast loading shaft for sundries freight elevator Pending CN115872255A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211565573.XA CN115872255A (en) 2022-12-07 2022-12-07 Installation method of fast loading shaft for sundries freight elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211565573.XA CN115872255A (en) 2022-12-07 2022-12-07 Installation method of fast loading shaft for sundries freight elevator

Publications (1)

Publication Number Publication Date
CN115872255A true CN115872255A (en) 2023-03-31

Family

ID=85766329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211565573.XA Pending CN115872255A (en) 2022-12-07 2022-12-07 Installation method of fast loading shaft for sundries freight elevator

Country Status (1)

Country Link
CN (1) CN115872255A (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001097650A (en) * 1999-10-01 2001-04-10 Otis Elevator Co Construction method for installing elevator without machine room
CN201751354U (en) * 2010-05-19 2011-02-23 陈显森 Sundry elevator door structure
CN102583131A (en) * 2011-01-04 2012-07-18 张向阳 Elevator shaft wall assembled by combined shaft frames
CN206069177U (en) * 2016-08-29 2017-04-05 四川科莱电梯股份有限公司 A kind of dumb waiter safety landing door system
CN107352358A (en) * 2017-07-19 2017-11-17 苏州天梭电梯有限公司 Elevator frame
CN107447952A (en) * 2017-08-18 2017-12-08 江苏天奥电梯有限公司 A kind of dismountable steel structure lift shaft
CN108217387A (en) * 2016-12-21 2018-06-29 齐茂山 A kind of novel biography dish elevator
CN207597605U (en) * 2017-11-27 2018-07-10 海芙德建筑产品(上海)有限公司 The connection structure of aluminium alloy elevator shaft column and crossbeam
CN109279480A (en) * 2018-11-02 2019-01-29 广州广日电梯工业有限公司 A kind of steel structure lift shaft splicing apparatus and method
CN209835337U (en) * 2019-04-19 2019-12-24 西继迅达(许昌)电梯有限公司 Household elevator shaft with glass outer seal and simple and convenient to install
CN210025480U (en) * 2018-10-11 2020-02-07 安徽源和堂药业股份有限公司 Herbal pieces-slicer
CN211225943U (en) * 2019-08-27 2020-08-11 江苏菱智电梯制造有限公司 Elevator steel constructs well
CN214456075U (en) * 2021-02-24 2021-10-22 中国新兴建设开发有限责任公司 Construction stage indoor elevator baffle protector
CN113602937A (en) * 2021-08-12 2021-11-05 广东奥菱电梯有限公司 Installation process of elevator hoistway

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001097650A (en) * 1999-10-01 2001-04-10 Otis Elevator Co Construction method for installing elevator without machine room
CN201751354U (en) * 2010-05-19 2011-02-23 陈显森 Sundry elevator door structure
CN102583131A (en) * 2011-01-04 2012-07-18 张向阳 Elevator shaft wall assembled by combined shaft frames
CN206069177U (en) * 2016-08-29 2017-04-05 四川科莱电梯股份有限公司 A kind of dumb waiter safety landing door system
CN108217387A (en) * 2016-12-21 2018-06-29 齐茂山 A kind of novel biography dish elevator
CN107352358A (en) * 2017-07-19 2017-11-17 苏州天梭电梯有限公司 Elevator frame
CN107447952A (en) * 2017-08-18 2017-12-08 江苏天奥电梯有限公司 A kind of dismountable steel structure lift shaft
CN207597605U (en) * 2017-11-27 2018-07-10 海芙德建筑产品(上海)有限公司 The connection structure of aluminium alloy elevator shaft column and crossbeam
CN210025480U (en) * 2018-10-11 2020-02-07 安徽源和堂药业股份有限公司 Herbal pieces-slicer
CN109279480A (en) * 2018-11-02 2019-01-29 广州广日电梯工业有限公司 A kind of steel structure lift shaft splicing apparatus and method
CN209835337U (en) * 2019-04-19 2019-12-24 西继迅达(许昌)电梯有限公司 Household elevator shaft with glass outer seal and simple and convenient to install
CN211225943U (en) * 2019-08-27 2020-08-11 江苏菱智电梯制造有限公司 Elevator steel constructs well
CN214456075U (en) * 2021-02-24 2021-10-22 中国新兴建设开发有限责任公司 Construction stage indoor elevator baffle protector
CN113602937A (en) * 2021-08-12 2021-11-05 广东奥菱电梯有限公司 Installation process of elevator hoistway

Similar Documents

Publication Publication Date Title
US20200217087A1 (en) Elevator system
WO2023240813A1 (en) Steel platform deformation construction structure and method for construction of sloping wall of core tube
CN106698208A (en) Hoisting equipment and hoisting method for external transportation of super high-rise building
WO2019015243A1 (en) Shaft module splicing system and splicing method therefor
CN106121253B (en) Installation component adjustable auxiliary installation device and method
CN115872255A (en) Installation method of fast loading shaft for sundries freight elevator
CN218809757U (en) Sundry goods elevator fast-assembling well
CN104806001A (en) Safety operation platform for sliding and lifting of elevator shaft guide rail and construction method
CN109138492A (en) A kind of curtain wall removes device and method for dismounting
CN115676559A (en) Steel construction elevator well
CN114933238A (en) Self-unloading type hoisting device for steel beam and construction method thereof
CN113216593A (en) Anti-falling hoisting device for elevator shaft of high-rise building
CN209244309U (en) A kind of curtain wall dismounting device
JPH0842153A (en) Construction method of long steel members and joint structure of steel beams
JPH05319729A (en) Attaching work device of guide rail of elevator and attaching work method of guide rail using that device
CN118581967A (en) A green building construction method for assembled wall
CN211895621U (en) A return rope pulley frame assembly for a construction hoist
JPH0826622A (en) Construction method of guide rail of elevator
WO2019138545A1 (en) Elevator and refurbishing method therefor
JP3237999B2 (en) Elevator device and method of forming elevator device
CN222976444U (en) Auxiliary device for butt-jointing installation of I-beams in prefabricated building steel structures
CN220058756U (en) Externally hung operating platform
JP3253441B2 (en) Elevator installation method
JPH07286368A (en) Method and device for lifting up the top floor frame for structure construction
JP2002060158A (en) Installation method for elevator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20230331