[go: up one dir, main page]

CN115748841A - Karst region impact hole-forming cast-in-place pile deviation monitoring method - Google Patents

Karst region impact hole-forming cast-in-place pile deviation monitoring method Download PDF

Info

Publication number
CN115748841A
CN115748841A CN202211477607.XA CN202211477607A CN115748841A CN 115748841 A CN115748841 A CN 115748841A CN 202211477607 A CN202211477607 A CN 202211477607A CN 115748841 A CN115748841 A CN 115748841A
Authority
CN
China
Prior art keywords
model
pile
perforated
steel casing
karst
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211477607.XA
Other languages
Chinese (zh)
Inventor
张瑞富
梁松林
安永昌
黄海权
李双福
刘均利
谭波
陈开恒
黄遵明
韦日锋
黄智冠
赵航
代勇
李昌锋
丁铭
潘旭晨
戴宗松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Guitong Engineering Management Group Co ltd
Guilin University of Technology
Guangxi Road Construction Engineering Group Co Ltd
Original Assignee
Guangxi Guitong Engineering Management Group Co ltd
Guilin University of Technology
Guangxi Road Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Guitong Engineering Management Group Co ltd, Guilin University of Technology, Guangxi Road Construction Engineering Group Co Ltd filed Critical Guangxi Guitong Engineering Management Group Co ltd
Priority to CN202211477607.XA priority Critical patent/CN115748841A/en
Publication of CN115748841A publication Critical patent/CN115748841A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the field of civil engineering construction monitoring, in particular to a karst region impact hole-forming cast-in-place pile deviation monitoring method, which comprises the following steps of constructing a BIM model of an impact hole-forming cast-in-place pile based on the diameter of a steel casing in a karst region construction site by utilizing a BIM modeling method; constructing a three-dimensional live-action model of a karst area construction site through unmanned aerial vehicle oblique photography; based on the same coordinate system, fusing the BIM model and the three-dimensional live-action model to obtain a fusion model, and measuring the horizontal distance between the impact cast-in-situ pile model and the steel casing model in the fusion model; and monitoring the deviation distance of the cast-in-situ bored pile in the karst area through the horizontal distance between the cast-in-situ bored pile model and the steel casing model. By adopting the scheme of the invention, the deviation degree of the position of the impact hole-forming cast-in-place pile in the karst area can be monitored at any time, the monitoring process is convenient, and the normal construction of the impact hole-forming cast-in-place pile is not influenced.

Description

一种岩溶区冲击成孔灌注桩偏位监测方法A method for monitoring the displacement of perforated piles in karst areas

技术领域technical field

本发明涉及土木工程施工监测领域,具体涉及一种岩溶区冲击成孔灌注桩偏位监测方法。The invention relates to the field of civil engineering construction monitoring, in particular to a method for monitoring the displacement of perforated piles in karst areas.

背景技术Background technique

钢筋混凝土灌注桩是桥梁工程中最常用的基础。规范对桩位有着严格的规定,要求排架桩偏位不大于50mm,极限偏位不大于100mm;承台桩的偏位不大于100mm。在岩溶地区,钢筋混凝土灌注桩基础施工方法最常用的是冲击成孔法。该方法设备简单,造价低廉,适用于各种覆盖层,结合回填片石和黏土能方便有效地处治溶洞、裂隙、半边岩和岩面不平等岩溶现象,在技术和经济方面具有明显的优越性。但在岩溶发育区桩基础施工时,经常遇到洪水、暴雨等极端天气,工作环境恶劣。岩层上面往往有覆盖层,冲击成孔灌注桩在入岩和到达溶洞底时,由于桩孔底面软硬不一导致钻机偏向较软的一边,需要反复回填片石,予以纠正,此时吊着钻机的钢丝绳也偏向一侧,钢丝绳的拉力给钻机机架一个水平力,当支撑钻机机架的覆盖层软弱时,机架和护筒容易发生水平偏位,从而导致冲孔灌注桩偏位。冲孔灌注桩的偏位超出规范允许值虽不常发生,但一旦出现,处治麻烦,增加工期和成本。Reinforced concrete cast-in-place piles are the most commonly used foundations in bridge engineering. The code has strict regulations on the pile position, requiring that the offset of the bent pile is not greater than 50mm, and the limit offset is not greater than 100mm; the offset of the cap pile is not greater than 100mm. In karst areas, the most commonly used construction method for reinforced concrete pouring pile foundations is the percussion drilling method. The method is simple in equipment and low in cost, and is suitable for various covering layers. Combined with backfilling flakes and clay, it can conveniently and effectively treat karst caves, fissures, hemirocks and uneven karst phenomena, and has obvious advantages in terms of technology and economy. However, during pile foundation construction in karst development areas, extreme weather such as floods and heavy rains are often encountered, and the working environment is harsh. There is often an overburden layer on the rock layer. When the percussion hole-forming pile enters the rock and reaches the bottom of the cave, the drilling rig tends to the softer side due to the different hardness of the bottom surface of the pile hole. It needs to be repeatedly backfilled with rubble to correct it. At this time, the drilling rig is suspended. The steel wire rope is also biased to one side, and the pulling force of the steel wire rope gives a horizontal force to the drilling rig frame. When the covering layer supporting the drilling rig frame is weak, the horizontal deviation of the frame and the casing is prone to occur, resulting in the displacement of the punched cast-in-place pile. Although the deviation of the perforated cast-in-situ pile exceeds the allowable value of the specification, it does not often happen, but once it occurs, the treatment will be troublesome, and the construction period and cost will be increased.

例如某高速公路桥梁采用排架墩,每一个排架墩下设有一个冲击成孔灌注桩基础,其中有一个冲击成孔灌注桩基础在成桩后的检测过程中,发现横桥向偏出15cm,顺桥向偏出18cm,而规范允许值是5cm,偏移值远远超出规范允许值,最终重新冲击成孔,影响工期2.5个月。再例如某市桥梁的桥墩采用承台桩基础,每个承台下面顺桥向设置3排冲击成孔灌注桩基础,横桥向设置4排冲击成孔灌注桩基础,该桥基岩面起伏剧烈,岩溶发育强烈,基岩上覆盖红黏土。开挖基坑检测桩基时,多数冲击成孔灌注桩基础偏位超出规范允许值,其中最大偏位55cm,远超规范允许值10cm,最终将承台尺寸向外扩大60cm,增加了工程造价。For example, a highway bridge adopts bent piers, and there is an impact-holed cast-in-place pile foundation under each bent pier, and one of the impact-holed cast-in-place pile foundations was found to be deflected in the direction of the transverse bridge during the inspection process after the pile was completed. 15cm, 18cm deviation along the bridge direction, while the allowable value of the specification is 5cm, the deviation value is far beyond the allowable value of the specification, and finally the hole is re-impacted, affecting the construction period of 2.5 months. Another example is that the piers of a bridge in a certain city adopt cap pile foundations. Under each cap, 3 rows of perforated pile foundations are arranged in the direction of the bridge, and 4 rows of perforated pile foundations are arranged in the direction of the bridge. The rock surface of the bridge foundation is undulating. Vigorous, with strong karst development and bedrock covered with red clay. When excavating the foundation pit to test the pile foundation, most of the perforated pile foundation deflection exceeded the allowable value of the code, and the maximum deflection was 55 cm, far exceeding the allowable value of the code by 10 cm. Finally, the size of the cap was enlarged by 60 cm, which increased the project cost .

综上,在冲击成孔灌注桩成孔施工过程中难以检测和发现桩基的偏位,在冲击成孔灌注桩施工完成后桩基检测过程中发现后往往处治复杂,影响工期,尤其影响整座桥的工期,增加造价。In summary, it is difficult to detect and discover the deviation of the pile foundation during the construction of the perforated piles. After the construction of the perforated piles is completed, the pile foundation detection process is often complicated to deal with, which affects the construction period, especially the overall impact. The construction period of the bridge increases the cost.

岩溶发育区冲击成孔灌注桩偏位最方便的处治方法是在施工过程中,监测冲击成孔灌注桩成孔位置的偏位,当发现冲击成孔灌注桩成孔位置偏位超出规范允许值时,立即重新回填片石和混凝土,重新埋设钢护筒,重新成孔。但桥梁冲击成孔灌注桩施工环境恶劣,采用人工在冲击成孔灌注桩成孔过程中测量桩基偏位量,只能检测钢护筒的直径,监测工作量大,误差大,影响施工,操作难度大。鉴于此,有必要提供一种新的岩溶区冲击成孔灌注桩偏位监测方法,以克服现有技术的不足。The most convenient way to deal with the deviation of the perforated piles in the karst development area is to monitor the displacement of the perforated piles during the construction process. , immediately backfill the rubble and concrete, re-bury the steel casing, and re-form the hole. However, the construction environment of bridge perforated piles is harsh. Manually measuring the displacement of the pile foundation during the process of perforating piles can only detect the diameter of the steel casing. The monitoring workload is large and the error is large, which affects the construction. Operation is difficult. In view of this, it is necessary to provide a new method for monitoring the displacement of percussive perforated piles in karst areas, so as to overcome the shortcomings of the existing technology.

发明内容Contents of the invention

本发明所要解决的技术问题是提供岩溶区冲击成孔灌注桩偏位监测方法,可以随时监测岩溶区冲击成孔灌注桩位置的偏移程度,且监测过程方便,不影响冲击成孔灌注桩的正常施工。The technical problem to be solved by the present invention is to provide a method for monitoring the deviation of the impact hole-forming pile in the karst area, which can monitor the deviation degree of the impact hole-forming pile position in the karst area at any time, and the monitoring process is convenient, and does not affect the impact of the hole-forming pile. Normal construction.

本发明解决上述技术问题的技术方案如下:一种岩溶区冲击成孔灌注桩偏位监测方法,包括以下步骤,The technical solution of the present invention to solve the above-mentioned technical problems is as follows: a method for monitoring the displacement of perforated piles in karst areas, comprising the following steps,

步骤1,利用BIM建模方法,基于岩溶区施工现场中钢护筒的直径构建冲击成孔灌注桩的BIM模型;Step 1, using the BIM modeling method to construct the BIM model of the perforated pile based on the diameter of the steel casing in the construction site in the karst area;

步骤2,通过无人机倾斜摄影构建岩溶区施工现场的三维实景模型;Step 2, constructing a 3D real scene model of the construction site in the karst area through oblique photography of the UAV;

步骤3,基于同一坐标系,将所述BIM模型与所述三维实景模型融合,得到融合模型,并在所述融合模型中量取冲击成孔灌注桩模型与钢护筒模型之间的水平距离;Step 3. Based on the same coordinate system, the BIM model is fused with the 3D real scene model to obtain a fused model, and the horizontal distance between the perforated pile model and the steel casing model is measured in the fused model ;

步骤4,通过所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离监测岩溶区冲击成孔灌注桩偏位距离。Step 4, monitoring the offset distance of the percussion perforation piles in the karst area through the horizontal distance between the perforation perforation pile model and the steel casing model.

本发明的原理是:建一个冲击成孔灌注桩的BIM模型,无人机倾斜摄影构建施工现场的三维实景模型,将两个模型在同一坐标系下融合,在融合模型中量取冲击成孔灌注桩模型与钢护筒模型的水平距离,即为岩溶区冲击成孔灌注桩偏位程度。The principle of the present invention is: build a BIM model of the impact hole-forming pile, use UAV oblique photography to build a three-dimensional real scene model of the construction site, fuse the two models in the same coordinate system, and measure the impact hole in the fusion model The horizontal distance between the cast-in-place pile model and the steel casing model is the displacement degree of the perforated pile in the karst area.

具体的:specific:

步骤1,利用BIM建模方法,基于岩溶区施工现场中钢护筒的直径构建冲击成孔灌注桩的BIM模型,冲击成孔灌注桩的BIM模型的位置是设计要求的位置。冲击成孔灌注桩属于隐蔽工程,为保证质量,钢护筒直径比冲击成孔灌注桩大20cm,故冲击成孔灌注桩成桩后实际直径也比其设计直径大20cm。冲击成孔灌注桩的BIM模型的直径取钢护筒直径,故冲击成孔灌注桩的BIM模型的直径等于冲击成孔灌注桩实际直径。Step 1. Using the BIM modeling method, the BIM model of the perforated pile is constructed based on the diameter of the steel casing in the construction site in the karst area. The position of the BIM model of the perforated pile is the position required by the design. The impact-holed cast-in-place pile is a concealed project. In order to ensure the quality, the diameter of the steel casing is 20cm larger than the impact-holed cast-in-place pile, so the actual diameter of the impact-holed cast-in-place pile is also 20cm larger than its design diameter. The diameter of the BIM model of the perforated pile is taken as the diameter of the steel casing, so the diameter of the BIM model of the perforated pile is equal to the actual diameter of the perforated pile.

步骤2,通过无人机倾斜摄影构建岩溶区施工现场的三维实景模型。从三维实景模型中,可以测量冲击成孔灌注桩施工过程中钢护筒的位置,终孔时钢护筒的位置就是冲击成孔灌注桩的实际位置。Step 2: Construct a 3D real scene model of the construction site in the karst area through oblique photography of the UAV. From the three-dimensional real-scene model, the position of the steel casing during the construction of the perforated pile can be measured, and the position of the steel casing at the end of the hole is the actual position of the perforated pile.

步骤3,基于同一坐标系,将所述BIM模型与所述三维实景模型融合,得到融合模型,并在所述融合模型中量取冲击成孔灌注桩模型与钢护筒模型之间的水平距离;其中,融合模型中的冲击成孔灌注桩模型来自于BIM模型,融合模型中的钢护筒模型来自于三维实景模型;Step 3. Based on the same coordinate system, the BIM model is fused with the 3D real scene model to obtain a fused model, and the horizontal distance between the perforated pile model and the steel casing model is measured in the fused model ; Among them, the impact hole-forming cast-in-place pile model in the fusion model comes from the BIM model, and the steel casing model in the fusion model comes from the 3D real scene model;

步骤4,通过所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离监测岩溶区冲击成孔灌注桩偏位距离。Step 4, monitoring the offset distance of the percussion perforation piles in the karst area through the horizontal distance between the perforation perforation pile model and the steel casing model.

综上,本发明可以监测冲击成孔灌注桩施工过程中实际成孔位置与设计位置的偏位大小。To sum up, the present invention can monitor the deviation between the actual hole-forming position and the designed position during the construction of the impact-hole-forming cast-in-situ pile.

本发明的有益效果是:采用本发明一种岩溶区冲击成孔灌注桩偏位监测方法,可以监测岩溶区冲击成孔灌注桩位置的偏移程度,采用无人机倾斜摄影,监测过程方便,不影响冲击成孔灌注桩的正常施工。The beneficial effects of the present invention are: adopting the displacement monitoring method of perforated piles in karst areas according to the present invention can monitor the deviation degree of the perforated piles in karst areas, and adopting oblique photography of unmanned aerial vehicle, the monitoring process is convenient, It does not affect the normal construction of perforated piles.

在上述技术方案的基础上,本发明还可以做如下改进。On the basis of the above technical solutions, the present invention can also be improved as follows.

进一步,构建冲击成孔灌注桩的BIM模型的具体过程为,Further, the specific process of constructing the BIM model of the percussive bored pile is as follows:

利用Openroads designer软件中的交点法对桥梁平面线进行绘制,得到桥梁平面线;Use the intersection method in the Openroads designer software to draw the bridge plane line to get the bridge plane line;

通过输入坡度、桩号和竖曲线半径在桥梁平面线上绘制纵断面;Draw a profile on the bridge plane by entering the slope, station number, and vertical curve radius;

将绘制有纵断面的桥梁平面线导入OpenBridges Modeler软件中,根据桥梁跨数与距离放置布跨线;Import the plane line of the bridge with longitudinal section into OpenBridges Modeler software, and place the spanning line according to the number of bridge spans and distance;

将OpenBridges Modeler软件安装目录下的自定义模版库文件提取到Miscrostation中,且在Miscrostation中根据钢护筒的直径进行冲击成孔灌注桩的绘制;在原点命令中通过自定义原点的方式定义冲击成孔灌注桩在布跨线中放置的位置,形成冲击成孔灌注桩三维BIM模板;Extract the custom template library file under the installation directory of the OpenBridges Modeler software into Miscrostation, and draw the impact hole-forming cast-in-place pile according to the diameter of the steel casing in Miscrostation; define the impact size by customizing the origin in the origin command The position where the bored pile is placed in the spanning line forms a three-dimensional BIM template for the impacted bored pile;

将冲击成孔灌注桩三维BIM模板放置在OpenBridges Modeler中,得到冲击成孔灌注桩的BIM模型。Place the 3D BIM template of the perforated pile in OpenBridges Modeler to obtain the BIM model of the perforated pile.

采用上述进一步方案的有益效果是:对常规桥梁,Openroads designer和Miscrostation有现成的模板,可以快速建模。对特殊桥梁,可以把模型保存为模板,方便快速编辑、重复使用。The beneficial effect of adopting the above-mentioned further solution is: for conventional bridges, Openroads designer and Miscrostation have ready-made templates, which can be modeled quickly. For special bridges, the model can be saved as a template for quick editing and repeated use.

进一步,所述BIM模型中冲击成孔灌注桩的直径取施工现场中钢护筒的直径,且所述BIM模型中冲击成孔灌注桩的桩顶标高取钢护筒顶面标高。Further, the diameter of the impact-forming cast-in-place pile in the BIM model is the diameter of the steel casing in the construction site, and the pile top elevation of the impact-forming cast-in-place pile in the BIM model is taken as the top surface elevation of the steel casing.

采用上述进一步方案的有益效果是:实际施工中,钢护筒直径比冲击成孔灌注桩的设计直径大20cm左右,护筒顶部的标高也大于冲击成孔灌注桩的桩顶标高。为方便量取冲击成孔灌注桩模型与钢护筒模型之间的水平距离,故在BIM模型中,冲击成孔灌注桩的直径取钢护筒的直径,冲击成孔灌注桩的顶标高采用钢护筒顶部的标高。冲击成孔灌注桩的BIM模型和钢护筒直径、顶部标高相同,方便在BIM模型和三维实景模型融合,量取冲击成孔灌注桩的偏位。The beneficial effect of adopting the above-mentioned further scheme is that in actual construction, the diameter of the steel casing is about 20 cm larger than the design diameter of the perforated pile, and the elevation of the top of the casing is also greater than that of the perforated pile. In order to conveniently measure the horizontal distance between the perforated pile model and the steel casing model, in the BIM model, the diameter of the perforated pile is taken as the diameter of the steel casing, and the top elevation of the perforated pile is taken as The elevation of the top of the steel casing. The BIM model of the perforated pile is the same as the diameter and top elevation of the steel casing, which facilitates the integration of the BIM model and the 3D real-scene model to measure the deviation of the perforated pile.

进一步,构建岩溶区施工现场的三维实景模型的具体过程为,Further, the specific process of constructing the 3D real scene model of the construction site in the karst area is as follows:

在岩溶区施工现场周边布设半永久性像控点;Arrange semi-permanent image control points around the construction site in the karst area;

根据施工现场的区域地势、范围以及无人机的续航能力,规划飞行航线并设置飞行参数;According to the regional terrain and scope of the construction site and the endurance of the drone, plan the flight route and set the flight parameters;

控制搭载有五镜头倾斜摄影测量相机的无人机根据飞行航线以及飞行参数进行外业航测,得到带有像控点影像的航测数据;Control the UAV equipped with a five-lens oblique photogrammetry camera to conduct field aerial surveys according to the flight route and flight parameters, and obtain aerial survey data with image control point images;

基于空中三角测量,根据航测数据进行三维场景建模,生成岩溶区施工现场的三维实景模型。Based on aerial triangulation, 3D scene modeling is carried out according to aerial survey data, and a 3D real scene model of the construction site in the karst area is generated.

采用上述进一步方案的有益效果是:设置半永久性像控点,可以在施工阶段一直采用;采用五镜头倾斜摄影测量相机的无人机根据飞行航线以及飞行参数进行外业航测,得到带有像控点影像的航测数据,航测效率高,一个桥梁工地,10分钟即可航测完毕;空中三角测量,计算效率高,几个小时即可完成建模。The beneficial effects of adopting the above-mentioned further scheme are: setting semi-permanent image control points, which can be used all the time in the construction stage; UAVs using five-lens oblique photogrammetry cameras conduct field aerial surveys according to flight routes and flight parameters, and obtain images with image control points. The aerial survey data of point image has high aerial survey efficiency, and the aerial survey of a bridge construction site can be completed in 10 minutes; the aerial triangulation survey has high calculation efficiency, and the modeling can be completed in a few hours.

进一步,基于空中三角测量,根据航测数据进行三维场景建模的具体步骤为,Further, based on aerial triangulation, the specific steps for 3D scene modeling based on aerial survey data are as follows:

根据航测数据获取相邻影像之间的同名点并进行影像匹配,得到相邻影像之间的视差和深度信息;Obtain the same-named points between adjacent images according to the aerial survey data and perform image matching to obtain the parallax and depth information between adjacent images;

基于相邻影像之间的视差和深度信息,结合影像的位置和姿态信息,利用摄影测量方法结算出相邻影像之间的空中关系;Based on the disparity and depth information between adjacent images, combined with the position and attitude information of the images, the aerial relationship between adjacent images is calculated using photogrammetry;

基于相邻影像之间的空中关系,通过影像密集匹配将影像中的所有像素在三维空间中离散化,得到多个离散的且带有彩色信息的点;三维空间中多个离散的且带有彩色的点形成彩色点云;Based on the aerial relationship between adjacent images, all pixels in the image are discretized in three-dimensional space through dense image matching, and multiple discrete points with color information are obtained; multiple discrete points with color information in three-dimensional space Colored points form a colored point cloud;

通过TIN三角构网方法将彩色点云中多个离散的点进行连接,形成多个三角形面片;Connect multiple discrete points in the color point cloud through the TIN triangular network method to form multiple triangular patches;

将多个三角形面片构成三角网,并将三角网作为基础模型;A triangular network is composed of multiple triangular patches, and the triangular network is used as the basic model;

根据彩色点云点的空间位置,将点的彩色信息映射到基础模型表面,得到初始三维实景模型;According to the spatial position of the color point cloud point, the color information of the point is mapped to the surface of the basic model to obtain the initial 3D real scene model;

对初始三维实景模型进行精细化及修正处理,得到岩溶区施工现场的三维实景模型。The initial 3D real scene model is refined and corrected to obtain a 3D real scene model of the construction site in the karst area.

采用上述进一步方案的有益效果是:由于航摄盲区、地物反光和不同航摄时间等问题,导致三维实景模型出现空洞区域、纹理变形、模型悬浮等,这是基于倾斜摄影技术进行实景三维建模不可避免的,采用上述方法,方便对初始三维实景模型进行修复。The beneficial effects of adopting the above-mentioned further scheme are: due to problems such as aerial photography blind spots, ground object reflections and different aerial photography time, etc., resulting in hollow areas, texture deformation, model suspension, etc. It is inevitable to use the above method to repair the initial 3D real scene model.

进一步,在飞行参数中,航向重叠度不低于75%,旁向重叠度不低于60%,无人机采用贴近摄影测量,且飞行高度范围为15~40m。Further, in the flight parameters, the degree of heading overlap is not less than 75%, and the degree of lateral overlap is not less than 60%. The UAV adopts close-in photogrammetry, and the flight height range is 15-40m.

采用上述进一步方案的有益效果是:桩基础的偏位限值为5cm或10cm,因此对无人机倾斜摄影的精度要求较高,要求无人机倾斜摄影的平面精度在2cm左右,故无人机采用贴近摄影,无人机距地面的距离采用15m~40m,无人机距地面的距离小于40m是为了拍摄高清晰度的照片,保证精度;无人机距地面的距离大于15m,是为了现场拍摄的安全。The beneficial effect of adopting the above-mentioned further scheme is: the displacement limit of the pile foundation is 5cm or 10cm, so the accuracy of the oblique photography of the UAV is required to be high, and the plane accuracy of the oblique photography of the UAV is required to be about 2cm, so no one The drone adopts close-up photography, and the distance between the drone and the ground is 15m to 40m. The distance between the drone and the ground is less than 40m to take high-definition photos to ensure accuracy; On-site shooting security.

进一步,基于同一坐标系,将所述BIM模型与所述三维实景模型融合,得到融合模型,并在所述融合模型中量取冲击成孔灌注桩模型与钢护筒模型之间的水平距离的具体步骤为,Further, based on the same coordinate system, the BIM model is fused with the 3D real scene model to obtain a fused model, and the horizontal distance between the perforated pile model and the steel casing model is measured in the fused model. The specific steps are,

将岩溶区施工现场的三维实景模型以FBX格式导入到MicroStation中,并将岩溶区施工现场的三维实景模型与冲击成孔灌注桩的BIM模型放到MicroStation的同一坐标空间中,得到融合模型;Import the 3D real scene model of the construction site in the karst area into MicroStation in FBX format, and put the 3D real scene model of the construction site in the karst area and the BIM model of the perforated pile into the same coordinate space of MicroStation to obtain the fusion model;

利用MicroStation中的测量功能,选取融合模型中的冲击成孔灌注桩模型与钢护筒模型进行距离测量,得到所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离。Using the measurement function in MicroStation, the impact hole-forming pile model and the steel casing model in the fusion model are selected to measure the distance, and the horizontal distance between the impact hole-forming pile model and the steel casing model is obtained.

采用上述进一步方案的有益效果是:在BIM模型和钢护筒三维实景模型均能查询其各自的水平位置坐标,但冲击成孔灌注桩尺寸大,而其偏位限值小,钢护筒的制作误差和变形均能影响直接从三维实景模型中查询的水平位置坐标。采用上述进一步方案可以确保冲击成孔灌注桩模型与钢护筒模型的水平距离的精度,也可以直观地反映冲击成孔灌注桩成孔位置和设计位置的相对距离。The beneficial effect of adopting the above-mentioned further scheme is that: both the BIM model and the 3D real-scene model of the steel casing can be queried for their respective horizontal position coordinates, but the size of the perforated pile is large, and its deviation limit is small, so the steel casing can Both fabrication errors and deformations can affect the horizontal position coordinates queried directly from the 3D reality model. Adopting the above-mentioned further scheme can ensure the accuracy of the horizontal distance between the perforated pile model and the steel casing model, and can also intuitively reflect the relative distance between the hole-forming position and the design position of the perforated pile.

进一步,在监测完岩溶区冲击成孔灌注桩偏位距离后,根据冲击成孔灌注桩与钢护筒的偏移距离在施工现场选择对应的处治方法;具体的,Further, after monitoring the offset distance of the perforated piles in the karst area, select the corresponding treatment method at the construction site according to the offset distance between the perforated piles and the steel casing; specifically,

若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离小于或等于X1,则安装冲击成孔灌注桩钢筋笼时,将冲击成孔灌注桩钢筋笼中心与冲击成孔灌注桩设计中心对齐;If the horizontal distance between the impact-forming cast-in-place pile model and the steel casing model is less than or equal to X1, when installing the impact-forming cast-in-place pile reinforcement cage, the center of the impact-forming cast-in-place pile reinforcement cage and the impact-forming hole Center alignment of cast-in-situ pile design;

若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离在(X1,X2]范围内,则安装冲击成孔灌注桩钢筋笼时,将冲击成孔灌注桩钢筋笼中心偏向钢护筒偏移方向,冲击成孔灌注桩钢筋笼中心与钢护筒中心的距离取钢护筒的偏移距离与X1之差;If the horizontal distance between the perforated pile model and the steel casing model is in the range of (X1, X2], when installing the perforated pile reinforcement cage, the center of the perforated pile reinforcement cage will be impacted Deviated to the offset direction of the steel casing, the difference between the offset distance of the steel casing and X1 is taken as the distance between the center of the reinforced cage of the perforated pile and the center of the steel casing;

若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离大于X2,则安装钢筋混凝土桩的基础钢筋笼之前回填片石和黏土并重新开孔;If the horizontal distance between the impact hole-forming cast-in-place pile model and the steel casing model is greater than X2, backfill rubble and clay and re-drill holes before installing the foundation reinforcement cage of the reinforced concrete pile;

其中,X1、X2均为预设值,X1取钢护筒直径与冲击成孔灌注桩设计直径之差的一半,X2取X1与桩基础偏位允许值之和。Among them, X1 and X2 are preset values, X1 is half of the difference between the diameter of the steel casing and the design diameter of the perforated pile, and X2 is the sum of X1 and the allowable value of the pile foundation deviation.

采用上述进一步方案的有益效果是:在冲击成孔灌注桩成孔过程中监测钢护筒的偏位,可以及时确定桩孔的偏位。而且可以根据所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离选择不同的处治方法,经济有效。The beneficial effect of adopting the above further scheme is that the deviation of the steel casing can be monitored in the process of forming the hole of the percussion hole-forming cast-in-place pile, and the deviation of the pile hole can be determined in time. Moreover, different treatment methods can be selected according to the horizontal distance between the impact hole-forming cast-in-place pile model and the steel casing model, which is economical and effective.

进一步,当桩基础偏位允许值为5cm时,X1和X2分别取10cm和15cm;当桩基础偏位允许值为10cm时,X1和X2分别取10cm和20cm。Further, when the allowable value of pile foundation deviation is 5cm, X1 and X2 are taken as 10cm and 15cm respectively; when the allowable value of pile foundation deviation is 10cm, X1 and X2 are taken as 10cm and 20cm respectively.

采用上述进一步方案的有益效果是:排架桩,承台群桩基础桩基础偏位允许值不同,根据桩基础偏位允许值,X2采取不同的预设值,允许桩基出现一定的小于桩基础偏位允许值的位移,符合经济性原则。The beneficial effect of adopting the above-mentioned further scheme is: the permissible value of pile foundation displacement of bent pile and cap group pile foundation is different, and according to the permissible value of pile foundation displacement, X2 adopts different preset values, allowing the pile foundation to have a certain value smaller than that of the pile foundation. The displacement of the allowable value of the foundation deviation is in line with the principle of economy.

附图说明Description of drawings

图1为本发明一种岩溶区冲击成孔灌注桩偏位监测方法的流程图;Fig. 1 is the flow chart of a kind of karst area percussion perforation pile deflection monitoring method of the present invention;

图2为冲击成孔灌注桩的BIM模型与岩溶区施工现场的三维实景模型的俯视图;Fig. 2 is a top view of the BIM model of the perforated pile and the three-dimensional real scene model of the construction site in the karst area;

图3为冲击成孔灌注桩与钢护筒的偏位示意图。Figure 3 is a schematic diagram of the displacement of the perforated pile and the steel casing.

具体实施方式Detailed ways

以下结合附图对本发明的原理和特征进行描述,所举实例只用于解释本发明,并非用于限定本发明的范围。The principles and features of the present invention are described below in conjunction with the accompanying drawings, and the examples given are only used to explain the present invention, and are not intended to limit the scope of the present invention.

如图1所示,本实施例的岩溶区冲击成孔灌注桩偏位监测方法,包括以下步骤,As shown in Figure 1, the method for monitoring the displacement of percussive perforated piles in the karst area of the present embodiment includes the following steps,

步骤1,利用BIM建模方法,基于岩溶区施工现场中钢护筒的直径构建冲击成孔灌注桩的BIM模型;Step 1, using the BIM modeling method to construct the BIM model of the perforated pile based on the diameter of the steel casing in the construction site in the karst area;

步骤2,通过无人机倾斜摄影构建岩溶区施工现场的三维实景模型;Step 2, constructing a 3D real scene model of the construction site in the karst area through oblique photography of the UAV;

步骤3,基于同一坐标系,将所述BIM模型与所述三维实景模型融合,得到融合模型,并在所述融合模型中量取冲击成孔灌注桩模型与钢护筒模型之间的水平距离;Step 3. Based on the same coordinate system, the BIM model is fused with the 3D real scene model to obtain a fused model, and the horizontal distance between the perforated pile model and the steel casing model is measured in the fused model ;

步骤4,通过所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离监测岩溶区冲击成孔灌注桩偏位距离。Step 4, monitoring the offset distance of the percussion perforation piles in the karst area through the horizontal distance between the perforation perforation pile model and the steel casing model.

下面对各步骤进行详细说明。Each step is described in detail below.

冲击成孔灌注桩的BIM模型的构建:Construction of the BIM model of the perforated pile:

根据设计,首先通过在MicroStation中绘制多个不规则多边形及路径曲线,然后利用拉伸构造和放置路径等命令可实现冲击成孔灌注桩的BIM模型的构建。本实施例采用Bentley系列软件进行冲击成孔灌注桩的BIM模型的构建。According to the design, first draw multiple irregular polygons and path curves in MicroStation, and then use commands such as stretching construction and placing paths to realize the construction of the BIM model of the perforated pile. In this embodiment, the Bentley series software is used to construct the BIM model of the perforated pile.

在本具体实施例中,构建冲击成孔灌注桩的BIM模型的具体过程为,In this specific embodiment, the specific process of constructing the BIM model of the impact hole-forming cast-in-place pile is as follows:

(1)利用OpenRoads Designer软件中的交点法对桥梁平面线进行绘制,得到桥梁平面线;具体是通过输入三点坐标及曲线元素实现桥梁平面线的绘制。(1) Use the intersection method in OpenRoads Designer software to draw the plane line of the bridge to obtain the plane line of the bridge; specifically, the drawing of the plane line of the bridge is realized by inputting three-point coordinates and curve elements.

(2)在平面线的上绘制纵断面,通过输入坡度、桩号和竖曲线半径完成。(2) Draw the vertical section on the plane line, and complete it by inputting the slope, chainage and vertical curve radius.

(3)桥梁平面线绘制完成后将绘制有纵断面的桥梁平面线导入OpenBridgesModeler软件中,根据桥梁跨数与距离放置布跨线,从而精确定位冲击成孔灌注桩放置的位置。(3) After the bridge plane line is drawn, import the bridge plane line with the vertical section into the OpenBridgesModeler software, and place the span line according to the number and distance of the bridge, so as to accurately locate the position of the impact-holed cast-in-place pile.

(4)在OpenBridges Modeler软件安装目录下找到cel格式文件,也就是自定义模版库文件,并将自定义模版库文件提取到Miscrostation中进行冲击成孔灌注桩三维BIM模版的建立。方法为首先获取钢护筒的直径,绘制出冲击成孔灌注桩的二维断面,接着利用拉伸结构的方式将断面拉伸成冲击成孔灌注桩的三维形状;对于简单的规则形状,可直接通过在智能实体中找到对应规则体进行绘制,例如圆柱体,可直接通过输入直径及高的方式实现绘制;放置的规则体可以是一个或多个,如果是多个,最后只需要利用布尔求和命令将各种规则体组合成一个体,即可实现冲击成孔灌注桩整体的绘制;接着在原点命令中通过自定义原点的方式定义放置路径,也就是冲击成孔灌注桩模版在布跨线中放置的位置,完成模版绘制并回到Open bridges modeler中放置冲击成孔灌注桩模版,得到冲击成孔灌注桩的BIM模型。(4) Find the cel format file in the installation directory of the OpenBridges Modeler software, that is, the custom template library file, and extract the custom template library file into Miscrostation to establish a 3D BIM template for impact-holed cast-in-place piles. The method is to first obtain the diameter of the steel casing, draw the two-dimensional section of the perforated pile, and then stretch the section into a three-dimensional shape of the perforated pile by means of tensile structure; for simple regular shapes, it can be Draw directly by finding the corresponding regular body in the smart entity, such as a cylinder, which can be drawn directly by entering the diameter and height; the placed regular body can be one or more, if there are more than one, you only need to use Boolean The summation command combines various regular bodies into one body to realize the overall drawing of the perforated pile; then define the placement path by customizing the origin in the origin command, that is, the perforated pile template is placed on the layout Cross the position placed in the line, complete the template drawing and return to the Open bridges modeler to place the template of the perforated pile, and obtain the BIM model of the perforated pile.

在本具体实施例中,所述BIM模型中冲击成孔灌注桩的直径为施工现场中钢护筒的直径,且所述BIM模型中冲击成孔灌注桩的桩顶标高取钢护筒顶面标高。In this specific embodiment, the diameter of the impact-forming cast-in-place pile in the BIM model is the diameter of the steel casing in the construction site, and the pile top elevation of the impact-forming cast-in-place pile in the BIM model is taken from the top surface of the steel casing elevation.

冲击成孔灌注桩在冲击成孔前,需要埋设一个钢护筒,起到定位、护壁和保护孔口的作用。钢护筒的直径比冲击成孔灌注桩设计直径大一些,大20cm左右。因此冲击成孔灌注桩的成孔直径也比冲击成孔灌注桩设计直径大20cm。本实施例的在建立冲击成孔灌注桩的BIM模型时,冲击成孔灌注桩的直径取钢护筒的直径,这是为了方便监测桩基础成孔的偏位。另外,桥梁工程桩基础施工过程中,需要采用人工筑岛,搭设钢结构平台等作为施工平台,钢护筒的顶部标高一般高于桩顶的设计标高,BIM模型中冲击成孔灌注桩的桩顶设计标高取钢护筒顶部的标高,这样做,也是为了方便监测桩基础成孔的偏位。Before impacting the hole-forming cast-in-place pile, a steel casing needs to be buried to play the role of positioning, retaining wall and protecting the hole. The diameter of the steel casing is larger than the design diameter of the perforated pile, about 20cm larger. Therefore, the hole-forming diameter of the impact-forming cast-in-place pile is also 20 cm larger than the design diameter of the impact-forming cast-in-place pile. In this embodiment, when establishing the BIM model of the perforated perforated pile, the diameter of the perforated perforated pile is taken as the diameter of the steel casing, which is for the convenience of monitoring the deviation of the perforated pile foundation. In addition, during the construction of bridge engineering pile foundations, it is necessary to use artificial islands and build steel structure platforms as construction platforms. The top elevation of the steel casing is generally higher than the design elevation of the pile top. The design elevation of the top is taken as the elevation of the top of the steel casing, which is also for the convenience of monitoring the deviation of the hole formed by the pile foundation.

三维实景模型的构建:Construction of 3D reality model:

在本具体实施例中,构建施工现场的三维实景模型的具体过程为,In this specific embodiment, the specific process of constructing the 3D real scene model of the construction site is as follows:

(1)在施工现场周边布设半永久性像控点;像控点就是在进行无人机航测时,通过使用rtk或者全站仪(大多数情况都是使用rtk),在所拍摄的测区内建立的具有标志性的真实坐标点,通过所做的像控点,可以对后期无人机航测出的坐标点进行矫正,从而完成无人机的测量。通过在施工现场均匀布设像控点实现模型与真实的大地坐标相匹配,并实现对模型精度的控制。(1) Arrange semi-permanent image control points around the construction site; the image control points are in the survey area captured by using rtk or total station (rtk is used in most cases) during aerial survey of UAV The established iconic real coordinate points, through the image control points, can correct the coordinate points measured by the drone in the later stage, so as to complete the measurement of the drone. By uniformly arranging image control points on the construction site, the model can be matched with the real geodetic coordinates, and the accuracy of the model can be controlled.

(2)根据施工现场的区域地势、范围以及无人机的续航能力,规划飞行航线并设置飞行参数,如飞行高度、航向重叠度和侧向重叠度等;无人机航测的精度需要小于2cm,为此,采取如下措施:无人机航测过程中保证航向重叠度不低于75%,旁向重叠度不低于60%;无人机采用贴近摄影测量,高度15m~40m。(2) According to the regional topography and scope of the construction site and the endurance of the UAV, plan the flight route and set the flight parameters, such as flight height, course overlap and lateral overlap, etc.; the accuracy of UAV aerial survey needs to be less than 2cm , To this end, the following measures are taken: during the UAV aerial survey process, ensure that the heading overlap is not less than 75%, and the lateral overlap is not less than 60%; the UAV adopts close-in photogrammetry, and the height is 15m ~ 40m.

(3)控制搭载有五镜头倾斜摄影测量相机的无人机根据飞行航线进行外业航测,得到带有像控点影像的航测数据;其中,航测数据包括无人机获取的航片、GPS数据、像控点数据等。(3) Control the UAV equipped with a five-lens oblique photogrammetry camera to conduct field aerial surveys according to the flight route, and obtain aerial survey data with image control point images; among them, the aerial survey data includes aerial photos and GPS data obtained by the UAV , like control point data, etc.

(4)基于空中三角测量,根据航测数据进行三维场景建模,生成三维实景模型。(4) Based on aerial triangulation, 3D scene modeling is carried out according to aerial survey data, and a 3D real scene model is generated.

空中三角测量也称解析空中三角测量,指的是用摄影测量解析法确定区域内所有影像的外方位元素。在传统摄影测量中,这是通过对点位进行测定来实现的,即根据影像上量测的像点坐标及少量控制点的大地坐标,求出未知点的大地坐标,使得已知点增加到每个模型中不少于4个,然后利用这些已知点求解影像的外方位元素,因而解析空中三角测量也称摄影测量加密或者空三加密。Aerial triangulation, also known as analytical aerial triangulation, refers to the use of photogrammetric analysis to determine the outer orientation elements of all images in an area. In traditional photogrammetry, this is achieved by measuring the point position, that is, according to the image point coordinates measured on the image and the geodetic coordinates of a small number of control points, the geodetic coordinates of the unknown points are obtained, so that the known points increase to There are no less than 4 in each model, and then use these known points to solve the outer orientation elements of the image, so analytical aerial triangulation is also called photogrammetric encryption or spatial three encryption.

基于空中三角测量生成三维实景模型的原理为:首先对图像(无人机获取的航片)中颜色或纹理变化剧烈的点进行提取,把这些点称之为特征点;其次利用图像中由于重叠度而存在的相同特征点,来实现不同照片的特征信息关联;接着通过调整相机内参、成像时位置和姿态,让特征点在三维空间中相交的误差最小;以空三调整过相机位置和姿态的图像作为输出,进行逐像素匹配,生成稠密化的三维点云;以三维点云为基础构建三角网;最后,找到拍摄到三角面片的照片,通过一定的规则选出最佳拍摄角度,给三角面片赋色,以此生成三维实景模型。在本具体实施例中:基于空中三角测量,根据航测数据进行三维场景建模的具体步骤为,The principle of generating a 3D real-scene model based on aerial triangulation is as follows: firstly, extract points with drastic changes in color or texture in the image (acquired by UAV), and call these points feature points; The same feature points that exist at different degrees to realize the feature information association of different photos; then adjust the camera internal parameters, position and attitude during imaging to minimize the error of feature points intersecting in three-dimensional space; adjust the camera position and attitude with aerotriangulation As the output, the image is matched pixel by pixel to generate a dense 3D point cloud; the triangulation network is constructed based on the 3D point cloud; finally, the photos taken with the triangular surface are found, and the best shooting angle is selected through certain rules. Color the triangles to generate a 3D reality model. In this specific embodiment: based on aerial triangulation, the specific steps of performing three-dimensional scene modeling according to aerial survey data are as follows:

根据航测数据获取相邻影像之间的同名点并进行影像匹配,得到相邻影像之间的视差和深度信息;Obtain the same-named points between adjacent images according to the aerial survey data and perform image matching to obtain the parallax and depth information between adjacent images;

基于相邻影像之间的视差和深度信息,结合影像的位置和姿态信息,利用摄影测量方法结算出相邻影像之间的空中关系;Based on the disparity and depth information between adjacent images, combined with the position and attitude information of the images, the aerial relationship between adjacent images is calculated using photogrammetry;

基于相邻影像之间的空中关系,通过影像密集匹配将影像中的所有像素在三维空间中离散化,得到多个离散的且带有彩色信息的点;三维空间中多个离散的且带有彩色的点形成彩色点云;彩色点云既有作为点云的几何特性,每个点又带有彩色信息;Based on the aerial relationship between adjacent images, all pixels in the image are discretized in three-dimensional space through dense image matching, and multiple discrete points with color information are obtained; multiple discrete points with color information in three-dimensional space The colored points form a colored point cloud; the colored point cloud not only has the geometric characteristics of a point cloud, but also has color information for each point;

通过TIN三角构网方将彩色点云中多个离散的点进行连接,形成多个三角形面片;Connect multiple discrete points in the color point cloud through the TIN triangulation network to form multiple triangular patches;

将多个三角形面片构成三角网,并将三角网作为基础模型,该基础模型即为白模;根据彩色点云点的空间位置,将点的彩色信息映射到基础模型表面,得到初始三维实景模型;将点的彩色信息映射到基础模型表面是发挥了彩色点云的彩色属性,这样,既有几何外观、又有真实彩色纹理的初始三维实景模型。A triangular network is composed of multiple triangular patches, and the triangular network is used as the basic model, which is the white model; according to the spatial position of the colored point cloud points, the color information of the points is mapped to the surface of the basic model to obtain the initial 3D real scene Model; mapping the color information of points to the surface of the basic model is to play the color attribute of the color point cloud, so that the initial 3D real scene model has both geometric appearance and real color texture.

由于航摄盲区、地物反光和不同航摄时间等问题,导致三维实景模型出现空洞区域、纹理变形、模型悬浮等,这是基于倾斜摄影技术进行实景三维建模不可避免的;因此联系现场实际,采用DP-Model修模软件对初始三维实景模型中存在的缺陷进行精细化及修正处理,同时,也删除桩工机械,挖掘机等施工机械,即可得到最终的三维实景模型,最终的三维实景模型只包括地面和钢护筒。Due to problems such as aerial photography blind spots, ground object reflections, and different aerial photography times, hollow areas, texture deformation, and model suspension appear in the 3D real-scene model. This is inevitable for real-scene 3D modeling based on oblique photography technology; , using DP-Model modeling software to refine and correct the defects existing in the initial 3D real-scene model, and delete pile machinery, excavators and other construction machinery to obtain the final 3D real-scene model, and the final 3D real-scene model The realistic model only includes the ground and steel casings.

模型融合并测距:Model fusion and ranging:

在本具体实施例中,图2为冲击成孔灌注桩的BIM模型与岩溶区施工现场的三维实景模型的俯视图;所示以无人机倾斜摄影数据获取的三维实景模型和采用MicroStation建立的冲击成孔灌注桩的BIM模型都是wgs84坐标系为基础来实现的;因此,将BIM模型与三维实景模型融合,得到融合模型;在融合模型中量取所述冲击成孔灌注桩模型与钢护筒模型之间的水平距离的具体步骤为,In this specific embodiment, Fig. 2 is a top view of the BIM model of the perforated pile and the three-dimensional real-scene model of the construction site in the karst area; The BIM models of bored piles are realized based on the wgs84 coordinate system; therefore, the fusion model is obtained by combining the BIM model with the 3D real scene model; The specific steps to determine the horizontal distance between cylinder models are:

将三维实景模型导入以FBX格式导入到MicroStation中,并将三维实景模型与BIM模型放到MicroStation中的同一坐标空间中,得到融合模型;Import the 3D real scene model into MicroStation in FBX format, and put the 3D real scene model and BIM model in the same coordinate space in MicroStation to obtain the fusion model;

利用MicroStation中的测量功能,选取融合模型中的冲击成孔灌注桩模型与钢护筒模型进行距离测量,得到所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离,冲击成孔灌注桩与钢护筒的偏位如图3所示。Utilize the measurement function in MicroStation, select the model of perforated perforated pile in the fusion model and the steel casing model to measure the distance, obtain the horizontal distance between the model of perforated perforated pile and the model of steel casing, impact The deviation between the hole-forming cast-in-place pile and the steel casing is shown in Figure 3.

偏位监测:Offset monitoring:

在本具体实施例中,在监测完岩溶区冲击成孔灌注桩偏位距离后,根据所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离在施工现场选择对应的处治方法;具体的,In this specific embodiment, after monitoring the offset distance of the perforated pile in the karst area, the corresponding treatment is selected at the construction site according to the horizontal distance between the perforated pile model and the steel casing model. method; specifically,

若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离小于或等于X1,则安装冲击成孔灌注桩钢筋笼时,将冲击成孔灌注桩钢筋笼中心与冲击成孔灌注桩设计中心对齐;If the horizontal distance between the impact-forming cast-in-place pile model and the steel casing model is less than or equal to X1, when installing the impact-forming cast-in-place pile reinforcement cage, the center of the impact-forming cast-in-place pile reinforcement cage and the impact-forming hole Center alignment of cast-in-situ pile design;

若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离在(X1,X2]范围内,则安装冲击成孔灌注桩钢筋笼时,将冲击成孔灌注桩钢筋笼中心偏向钢护筒偏移方向,冲击成孔灌注桩钢筋笼中心与钢护筒中心的距离取钢护筒的偏移距离与X1之差;If the horizontal distance between the perforated pile model and the steel casing model is in the range of (X1, X2], when installing the perforated pile reinforcement cage, the center of the perforated pile reinforcement cage will be impacted Deviated to the offset direction of the steel casing, the difference between the offset distance of the steel casing and X1 is taken as the distance between the center of the reinforced cage of the perforated pile and the center of the steel casing;

若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离大于X2,则安装钢筋混凝土桩的基础钢筋笼之前回填片石和黏土并重新开孔;If the horizontal distance between the impact hole-forming cast-in-place pile model and the steel casing model is greater than X2, backfill rubble and clay and re-drill holes before installing the foundation reinforcement cage of the reinforced concrete pile;

其中,X1、X2均为预设值,X1取钢护筒直径与冲击成孔灌注桩设计直径之差的一半,X2取X1与桩基础偏位允许值之和。Among them, X1 and X2 are preset values, X1 is half of the difference between the diameter of the steel casing and the design diameter of the perforated pile, and X2 is the sum of X1 and the allowable value of the pile foundation deviation.

在本具体实施例中,当桩基础偏位允许值为5cm时,X1和X2分别取10cm和15cm;当桩基础偏位允许值为10cm时,X1和X2分别取10cm和20cm。In this specific embodiment, when the allowable value of the pile foundation deviation is 5cm, X1 and X2 are respectively 10cm and 15cm; when the allowable value of the pile foundation deviation is 10cm, X1 and X2 are respectively 10cm and 20cm.

下面以具体应用实例来说明本实施例:The present embodiment is described below with specific application examples:

以平南高速公路K114+600旧圩大桥为例。该桥跨径布置为5×20m+4×20m+4×20m+5×20m。下部结构中的覆盖层为10m-20m厚的中等膨胀土,下伏基岩为强风化灰岩和中风化灰岩,岩溶发育强烈。旧圩大桥的桥墩采用排架墩,每一个排架墩墩下设置一个钢筋混凝土桩基础,钢筋混凝土桩基础采用冲击成孔方法施工。冲击成孔灌注桩的直径150cm。Take the K114+600 Jiuxu Bridge of Pingnan Expressway as an example. The bridge span layout is 5×20m+4×20m+4×20m+5×20m. The covering layer in the substructure is medium expansive soil with a thickness of 10m-20m, and the underlying bedrock is strongly weathered limestone and moderately weathered limestone, with strong karst development. The piers of the Jiuwei Bridge are bent piers, and a reinforced concrete pile foundation is set under each bent pier, and the reinforced concrete pile foundation is constructed by impact hole forming. The diameter of the impact hole-forming cast-in-situ pile is 150cm.

首先采用Bentley平台下OpenBridge Modeler和Microstation软件建立桥梁的冲击成孔灌注桩的BIM模型。冲击成孔灌注桩的BIM模型的直径取170cm,冲击成孔灌注桩的BIM模型的顶部标高取钢护筒的顶部标高。Firstly, the BIM model of the percussive perforated piles of the bridge is established by using OpenBridge Modeler and Microstation software under the Bentley platform. The diameter of the BIM model of the perforated pile is taken as 170cm, and the top elevation of the BIM model of the perforated pile is taken as the top elevation of the steel casing.

然后,在冲击成孔灌注桩施工过程中,周期性地采用型号为Phantom 4RTK多旋翼无人机搭载型号为RIY-D2M五镜头相机进行现场信息数据采集,沿公路两侧每间隔80m布置一个相控点,无人机飞行高度20m,航向重叠度85%,旁向重叠度85%,一次获得2000张照片。采用Bentley平台下Context Capture软件重建三维实景模型,每次计算时间在6小时左右,采用DP-Model修模软件对初始三维实景模型中存在的缺陷进行精细化及修正处理,同时,也删除桩工机械,挖掘机等施工机械,即可得到最终的三维实景模型,如图2所示。从图2可以看出,将模型平面误差控制在2cm内。Then, during the construction of perforated piles, the Phantom 4RTK multi-rotor UAV equipped with the RIY-D2M five-lens camera is used periodically to collect on-site information and data. The control point, the UAV flying height is 20m, the course overlap is 85%, the side overlap is 85%, and 2000 photos are obtained at a time. Context Capture software under Bentley platform is used to reconstruct the 3D real scene model, and the calculation time is about 6 hours each time. DP-Model software is used to refine and correct the defects existing in the initial 3D real scene model. At the same time, the pile work is also deleted. Machinery, excavators and other construction machinery can get the final 3D real scene model, as shown in Figure 2. It can be seen from Figure 2 that the model plane error is controlled within 2cm.

接着将冲击成孔灌注桩的BIM模型与三维实景模型融合,量取冲击成孔灌注桩模型与钢护筒模型的偏移距离。具体:先将BIM模型以DNG格式导入Microstation平台中,再从Context Capture软件建立的三维实景模型中导出FBX格式的块状网格,然后以网格的形式依次导入Microstation平台中,从而完成BIM模型与三维实景模型的整合。Then, the BIM model of the perforated pile is integrated with the 3D real scene model, and the offset distance between the perforated pile model and the steel casing model is measured. Specifically: first import the BIM model into the Microstation platform in DNG format, then export block grids in FBX format from the 3D real scene model established by Context Capture software, and then import them into the Microstation platform in the form of grids to complete the BIM model Integration with 3D reality models.

在Microstation平台中,量取冲击成孔灌注桩模型与钢护筒模型的距离,即冲击成孔灌注桩设计平面位置与钢护筒之间的水平距离,也就是冲击成孔灌注桩成孔的偏位位置,如图3所示。In the Microstation platform, measure the distance between the perforated pile model and the steel casing model, that is, the horizontal distance between the design plane position of the perforated pile and the steel casing, that is, the hole-forming distance of the perforated pile. Offset position, as shown in Figure 3.

当所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离小于或等于5cm时为合格,安装钢筋混凝土冲击成孔灌注桩钢筋笼时,为施工方便,钢筋笼中心可与钢护筒中心对齐;It is qualified when the horizontal distance between the impact-forming cast-in-place pile model and the steel casing model is less than or equal to 5cm. When installing the reinforced concrete impact-forming cast-in-place pile reinforcement cage, for the convenience of construction, the center of the reinforcement cage can be connected with the Center alignment of steel casing;

当所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离大于5cm且小于或等于10cm时,由于冲击成孔灌注桩实际直径大于设计直径20cm,当钢护筒偏位10cm以内时,下放安装钢筋笼时钢筋笼中心与桩基设计中心对齐,仍能保证冲击成孔灌注桩最小保护层厚度大于5cm;When the horizontal distance between the impact hole-forming cast-in-place pile model and the steel casing model is greater than 5cm and less than or equal to 10cm, since the actual diameter of the impact-hole-forming cast-in-place pile is greater than the design diameter of 20cm, when the steel casing deviates by 10cm When the reinforcement cage is lowered and installed, the center of the reinforcement cage is aligned with the design center of the pile foundation, which can still ensure that the minimum protective layer thickness of the perforated pile is greater than 5cm;

将冲击成孔灌注桩钢筋笼中心偏向钢护筒偏移方向,冲击成孔灌注桩钢筋笼中心与钢护筒中心的距离取钢护筒的偏移距离与X1之差,此时冲击成孔灌注桩钢筋笼中心与冲击成孔灌注桩设计中心距离人能满足桩基础偏位容许值;The center of the reinforcement cage of the perforated pile is biased towards the offset direction of the steel casing, and the distance between the center of the reinforcement cage of the perforated pile and the center of the steel casing is taken as the difference between the offset distance of the steel casing and X1. The distance between the steel cage center of the cast-in-place pile and the design center of the impact-holed cast-in-place pile can meet the allowable value of pile foundation deviation;

当所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离大于15cm时,尽管实际直径大于设计直径20cm,冲击成孔灌注桩实际直径大于设计直径20cm,但已经不能保证冲击成孔灌注桩实际直径大于设计直径20cm钢筋笼的中心位于冲击成孔灌注桩设计中心了。因此需要回填片石和黏土,重新开孔。When the horizontal distance between the impact-forming cast-in-place pile model and the steel casing model is greater than 15cm, although the actual diameter is greater than the design diameter of 20cm, the actual diameter of the impact-forming cast-in-place pile is greater than the design diameter of 20cm, but the impact cannot be guaranteed. The actual diameter of the bored pile is greater than the design diameter of 20cm. The center of the steel cage is located at the design center of the perforated pile. Therefore, it is necessary to backfill the flakes and clay and re-drill the holes.

对比例:Comparative example:

岩溶发育区地质情况复杂,溶洞、溶槽、裂隙等在宏观上有一定规律,微观上千变万化,毫无规律可循,基岩以上覆盖层也有多种地质条件。有时即使同一桥梁相邻桩基的地质情况也差异较大,桩基础一次成孔,不能做重复试验。The geological conditions in the karst development area are complex. There are certain laws in the macroscopic view of karst caves, karst troughs, and fissures, but they are ever-changing in the microscopic view and have no rules to follow. The overburden above the bedrock also has a variety of geological conditions. Sometimes even the geological conditions of adjacent pile foundations of the same bridge are quite different, and the pile foundation is drilled once, so repeated tests cannot be done.

为验证本实施例效果,以水口-崇左-爱店公路(崇左至爱店段,全长58.67km)为例。水口-崇左-爱店公路(崇左至爱店段)有8座桥位于岩溶地质地段,分别为:K1+343会皮大桥(48根桩基)、K4+180下其逢分离式立交桥(20根桩基)、K4+605渠逢1号大桥(48根桩基)、K6+215渠扬高架大桥(48根桩基)、天西枢纽互通FK0+982.5匝道桥(112根桩基)、天西枢纽互通GK0+551.5匝道桥(104根桩基)、天西枢纽互通HK0+641.000匝道桥(44根桩基)、IK4+992亭亮互通IK4+992匝道桥(16根桩基),总共有372根桩基,全部采用冲击成孔灌注桩。上述8座桥梁的桩基础于2020年12月19日开工,2022年10月全部完工。2021年6月在检测早期完成的100根桩基时,发现2根桩基偏位,其中1根顺桥向偏移15cm,横桥向偏移20cm,另一根顺桥向偏移10cm。为防止后续桩基础继续出现偏位事故,2021年7月份开始采用本实施例的方法,至2022年10月份全部桩基完工,没有再发生桩基偏移超过5cm的情况。To verify the effect of this embodiment, take the Shuikou-Chongzuo-Aidian highway (the section from Chongzuo to Aidian, with a total length of 58.67 km) as an example. Shuikou-Chongzuo-Aidian Highway (Chongzuo-Aidian Section) has 8 bridges located in karst geological areas, namely: K1+343 Huipi Bridge (48 pile foundations), K4+180 Xiaqifeng Separation Overpass (20 pile foundations), K4+605 Qufeng No. 1 Bridge (48 pile foundations), K6+215 Quyang Viaduct Bridge (48 pile foundations), FK0+982.5 Ramp Bridge of Tianxi Hub Interchange (112 pile foundations ), Tianxi hub interchange GK0+551.5 ramp bridge (104 pile foundations), Tianxi hub interchange HK0+641.000 ramp bridge (44 pile foundations), IK4+992 Tingliang interchange IK4+992 ramp bridge (16 pile foundations ), there are a total of 372 pile foundations, all of which are perforated piles. The pile foundations of the above eight bridges started on December 19, 2020 and will be completed in October 2022. In June 2021, when inspecting the 100 pile foundations completed in the early stage, it was found that 2 pile foundations were displaced, one of which was offset by 15cm along the bridge, 20cm across the bridge, and the other 10cm along the bridge. In order to prevent subsequent pile foundation deviation accidents, the method of this embodiment will be adopted in July 2021, and all pile foundations will be completed by October 2022, and there will be no pile foundation displacement exceeding 5cm.

因此,本实施例成功解决了岩溶区桩基础冲孔过程中偏位监测问题。现在无人机已经用于高速公路建设中,本实施例不会增加硬件支出,成本不高,满足精度要求。Therefore, this embodiment successfully solves the problem of displacement monitoring during the punching process of the pile foundation in the karst area. Now that the UAV has been used in highway construction, this embodiment will not increase the hardware expenditure, the cost is not high, and the accuracy requirement is met.

在本实施例的岩溶区冲击成孔灌注桩偏位监测方法中,首先利用BIM建模方法构建冲击成孔灌注桩的BIM模型;然后通过无人机倾斜摄影构建施工现场的三维实景模型;接着将冲击成孔灌注桩的BIM模型与三维实景模型融合得到融合模型,并在融合模型中量取冲击成孔灌注桩与钢护筒的偏移距离;最后通过冲击成孔灌注桩与钢护筒的偏移距离即可监测岩溶区冲击成孔灌注桩偏位程度;采用本实施例的方案,可以随时监测岩溶区冲击成孔灌注桩位置的偏移程度,且监测过程方便,不影响冲击成孔灌注桩的正常施工。In the method for monitoring the displacement of perforated piles in karst areas in this embodiment, the BIM model of perforated piles is first constructed using the BIM modeling method; then the three-dimensional real scene model of the construction site is constructed through oblique photography of UAVs; and then The BIM model of the perforated pile and the three-dimensional real scene model are fused to obtain a fusion model, and the offset distance between the perforated pile and the steel casing is measured in the fusion model; finally, the perforated pile and the steel casing are measured The offset distance of the impact hole-forming pile in the karst area can be monitored for the deviation degree; the scheme of this embodiment can monitor the offset degree of the impact hole-forming pile position in the karst area at any time, and the monitoring process is convenient without affecting the impact cost. Normal construction of bored piles.

以上所述仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection of the present invention. within range.

Claims (9)

1.一种岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:包括以下步骤,1. A method for monitoring the displacement of perforated piles in karst areas, characterized in that: comprising the following steps, 步骤1,利用BIM建模方法,基于岩溶区施工现场中钢护筒的直径构建冲击成孔灌注桩的BIM模型;Step 1, using the BIM modeling method to construct the BIM model of the perforated pile based on the diameter of the steel casing in the construction site in the karst area; 步骤2,通过无人机倾斜摄影构建岩溶区施工现场的三维实景模型;Step 2, constructing a 3D real scene model of the construction site in the karst area through oblique photography of the UAV; 步骤3,基于同一坐标系,将所述BIM模型与所述三维实景模型融合,得到融合模型,并在所述融合模型中量取冲击成孔灌注桩模型与钢护筒模型之间的水平距离;Step 3. Based on the same coordinate system, the BIM model is fused with the 3D real scene model to obtain a fused model, and the horizontal distance between the perforated pile model and the steel casing model is measured in the fused model ; 步骤4,通过所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离监测岩溶区冲击成孔灌注桩偏位距离。Step 4, monitoring the offset distance of the percussion perforation piles in the karst area through the horizontal distance between the perforation perforation pile model and the steel casing model. 2.根据权利要求1所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:构建冲击成孔灌注桩的BIM模型的具体过程为,2. The displacement monitoring method of perforated piles in karst area according to claim 1, characterized in that: the specific process of constructing the BIM model of perforated piles with percussion is as follows: 利用Openroads designer软件中的交点法对桥梁平面线进行绘制,得到桥梁平面线;Use the intersection method in the Openroads designer software to draw the bridge plane line to get the bridge plane line; 通过输入坡度、桩号和竖曲线半径在桥梁平面线上绘制纵断面;Draw a profile on the bridge plane by entering the slope, station number, and vertical curve radius; 将绘制有纵断面的桥梁平面线导入OpenBridges Modeler软件中,根据桥梁跨数与距离放置布跨线;Import the plane line of the bridge with longitudinal section into OpenBridges Modeler software, and place the spanning line according to the number of bridge spans and distance; 将OpenBridges Modeler软件安装目录下的自定义模版库文件提取到Miscrostation中,并在Miscrostation中根据钢护筒的直径进行冲击成孔灌注桩横断面的绘制;在原点命令中通过自定义原点的方式定义冲击成孔灌注桩在布跨线中放置的位置,形成冲击成孔灌注桩三维BIM模板;Extract the custom template library file in the installation directory of the OpenBridges Modeler software into Miscrostation, and draw the cross-section of the perforated pile in Miscrostation according to the diameter of the steel casing; define it by customizing the origin in the origin command Impact the position of the hole-forming cast-in-place pile in the spanning line to form a three-dimensional BIM template for the impact-hole-forming cast-in-place pile; 将冲击成孔灌注桩三维BIM模板放置在OpenBridges Modeler中,得到冲击成孔灌注桩的BIM模型。Place the 3D BIM template of the perforated pile in OpenBridges Modeler to obtain the BIM model of the perforated pile. 3.根据权利要求1所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:所述BIM模型中冲击成孔灌注桩的直径为施工现场中钢护筒的直径,且所述BIM模型中冲击成孔灌注桩的桩顶标高取钢护筒顶面标高。3. The method for monitoring the displacement of perforated piles in karst areas according to claim 1, characterized in that: the diameter of perforated piles impacted in the BIM model is the diameter of the steel casing in the construction site, and the In the BIM model, the elevation of the top surface of the steel casing is taken as the pile top elevation of the perforated pile. 4.根据权利要求1所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:构建岩溶区施工现场的三维实景模型的具体过程为,4. the displacement monitoring method of perforated pile in karst area according to claim 1, characterized in that: the specific process of constructing the three-dimensional real scene model of the construction site in karst area is as follows: 在岩溶区施工现场周边布设半永久性像控点;Arrange semi-permanent image control points around the construction site in the karst area; 根据施工现场的区域地势、范围以及无人机的续航能力,规划飞行航线并设置飞行参数;According to the regional terrain and scope of the construction site and the endurance of the drone, plan the flight route and set the flight parameters; 控制搭载有五镜头倾斜摄影测量相机的无人机,根据飞行航线以及飞行参数进行外业航测,得到带有像控点影像的航测数据;Control the UAV equipped with a five-lens tilt photogrammetry camera, conduct field aerial surveys according to the flight route and flight parameters, and obtain aerial survey data with image control point images; 基于空中三角测量,根据航测数据进行三维场景建模,生成岩溶区施工现场的三维实景模型。Based on aerial triangulation, 3D scene modeling is carried out according to aerial survey data, and a 3D real scene model of the construction site in the karst area is generated. 5.根据权利要求4所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:基于空中三角测量,根据航测数据进行三维场景建模的具体步骤为,5. The method for monitoring the displacement of perforated piles in karst areas according to claim 4, characterized in that: based on aerial triangulation, the specific steps of performing three-dimensional scene modeling according to aerial survey data are as follows: 根据航测数据获取相邻影像之间的同名点并进行影像匹配,得到相邻影像之间的视差和深度信息;Obtain the same-named points between adjacent images according to the aerial survey data and perform image matching to obtain the parallax and depth information between adjacent images; 基于相邻影像之间的视差和深度信息,结合影像的位置和姿态信息,利用摄影测量方法结算出相邻影像之间的空中关系;Based on the disparity and depth information between adjacent images, combined with the position and attitude information of the images, the aerial relationship between adjacent images is calculated using photogrammetry; 基于相邻影像之间的空中关系,通过影像密集匹配将影像中的所有像素在三维空间中离散化,得到多个离散的且带有彩色信息的点;三维空间中多个离散的且带有彩色的点形成彩色点云;Based on the aerial relationship between adjacent images, all pixels in the image are discretized in three-dimensional space through dense image matching, and multiple discrete points with color information are obtained; multiple discrete points with color information in three-dimensional space Colored points form a colored point cloud; 通过TIN三角构网法将彩色点云中多个离散的点进行连接,形成多个三角形面片;Connect multiple discrete points in the color point cloud through the TIN triangulation network method to form multiple triangular patches; 将多个三角形面片构成三角网,并将三角网作为基础模型;A triangular network is composed of multiple triangular patches, and the triangular network is used as the basic model; 根据彩色点云点的空间位置,将点的彩色信息映射到基础模型表面,得到初始三维实景模型;According to the spatial position of the color point cloud point, the color information of the point is mapped to the surface of the basic model to obtain the initial 3D real scene model; 对初始三维实景模型进行精细化及修正处理,得到岩溶区施工现场的三维实景模型。The initial 3D real scene model is refined and corrected to obtain a 3D real scene model of the construction site in the karst area. 6.根据权利要求4所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:在飞行参数中,航向重叠度不低于75%,旁向重叠度不低于60%,无人机采用贴近摄影测量,且飞行高度为15m~40m。6. The method for monitoring the displacement of perforated piles in karst areas according to claim 4, characterized in that: in the flight parameters, the heading overlap is not less than 75%, the lateral overlap is not less than 60%, and no The man-machine adopts close-in photogrammetry, and the flying height is 15m~40m. 7.根据权利要求2所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:基于同一坐标系,将冲所述BIM模型与所述三维实景模型融合,得到融合模型,并在所述融合模型中量取冲击成孔灌注桩模型与钢护筒模型之间的水平距离的具体步骤为,7. The method for monitoring the displacement of perforated piles in karst areas according to claim 2, characterized in that: based on the same coordinate system, the BIM model is fused with the three-dimensional real-scene model to obtain a fusion model, and in the The specific steps for measuring the horizontal distance between the impact hole-forming cast-in-place pile model and the steel casing model in the fusion model are as follows: 将岩溶区施工现场的三维实景模型以FBX格式导入到MicroStation中,并将岩溶区施工现场的三维实景模型与冲击成孔灌注桩的BIM模型放到MicroStation的同一坐标空间中,得到融合模型;Import the 3D real scene model of the construction site in the karst area into MicroStation in FBX format, and put the 3D real scene model of the construction site in the karst area and the BIM model of the perforated pile into the same coordinate space of MicroStation to obtain the fusion model; 利用MicroStation中的测量功能,选取融合模型中的冲击成孔灌注桩模型与钢护筒模型进行距离测量,得到所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离。Using the measurement function in MicroStation, the impact hole-forming pile model and the steel casing model in the fusion model are selected to measure the distance, and the horizontal distance between the impact hole-forming pile model and the steel casing model is obtained. 8.根据权利要求1所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:在监测完岩溶区冲击成孔灌注桩偏位距离后,根据所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离在施工现场选择对应的处治方法;具体的,8. The method for monitoring the displacement of perforated piles in karst areas according to claim 1, characterized in that: after monitoring the displacement distance of perforated piles in karst regions, according to the model of perforated piles with impact and The horizontal distance between the steel casing models selects the corresponding treatment method at the construction site; specifically, 若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离小于或等于X1,则安装冲击成孔灌注桩钢筋笼时,将冲击成孔灌注桩钢筋笼中心与冲击成孔灌注桩设计中心对齐;If the horizontal distance between the impact-forming cast-in-place pile model and the steel casing model is less than or equal to X1, when installing the impact-forming cast-in-place pile reinforcement cage, the center of the impact-forming cast-in-place pile reinforcement cage and the impact-forming hole Center alignment of cast-in-situ pile design; 若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离在(X1,X2]范围内,则安装冲击成孔灌注桩钢筋笼时,将冲击成孔灌注桩钢筋笼中心偏向钢护筒偏移方向,冲击成孔灌注桩钢筋笼中心与钢护筒中心的距离取钢护筒的偏移距离与X1之差;If the horizontal distance between the perforated pile model and the steel casing model is in the range of (X1, X2], when installing the perforated pile reinforcement cage, the center of the perforated pile reinforcement cage will be impacted Deviated to the offset direction of the steel casing, the difference between the offset distance of the steel casing and X1 is taken as the distance between the center of the reinforced cage of the perforated pile and the center of the steel casing; 若所述冲击成孔灌注桩模型与所述钢护筒模型之间的水平距离大于X2,则安装钢筋混凝土桩的基础钢筋笼之前回填片石和黏土并重新开孔;If the horizontal distance between the impact hole-forming cast-in-place pile model and the steel casing model is greater than X2, backfill rubble and clay and re-drill holes before installing the foundation reinforcement cage of the reinforced concrete pile; 其中,X1、X2均为预设值,X1取钢护筒直径与冲击成孔灌注桩设计直径之差的一半,X2取X1与桩基础偏位允许值之和。Among them, X1 and X2 are preset values, X1 is half of the difference between the diameter of the steel casing and the design diameter of the perforated pile, and X2 is the sum of X1 and the allowable value of the pile foundation deviation. 9.根据权利要求8所述的岩溶区冲击成孔灌注桩偏位监测方法,其特征在于:当桩基础偏位允许值为5cm时,X1和X2分别取10cm和15cm;当桩基础偏位允许值为10cm时,X1和X2分别取10cm和20cm。9. The method for monitoring the displacement of perforated piles in karst areas according to claim 8, characterized in that: when the allowable value of the displacement of the pile foundation is 5cm, X1 and X2 are respectively 10cm and 15cm; When the allowable value is 10cm, X1 and X2 are taken as 10cm and 20cm respectively.
CN202211477607.XA 2022-11-23 2022-11-23 Karst region impact hole-forming cast-in-place pile deviation monitoring method Pending CN115748841A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211477607.XA CN115748841A (en) 2022-11-23 2022-11-23 Karst region impact hole-forming cast-in-place pile deviation monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211477607.XA CN115748841A (en) 2022-11-23 2022-11-23 Karst region impact hole-forming cast-in-place pile deviation monitoring method

Publications (1)

Publication Number Publication Date
CN115748841A true CN115748841A (en) 2023-03-07

Family

ID=85336353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211477607.XA Pending CN115748841A (en) 2022-11-23 2022-11-23 Karst region impact hole-forming cast-in-place pile deviation monitoring method

Country Status (1)

Country Link
CN (1) CN115748841A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117687426A (en) * 2024-01-31 2024-03-12 成都航空职业技术学院 Unmanned aerial vehicle flight control method and system in low-altitude environment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117687426A (en) * 2024-01-31 2024-03-12 成都航空职业技术学院 Unmanned aerial vehicle flight control method and system in low-altitude environment

Similar Documents

Publication Publication Date Title
US11783248B2 (en) United states construction management system and method
CN110288268B (en) Construction safety risk and hidden danger integrated monitoring system and monitoring method
CN114659492B (en) Monitoring platform and monitoring method for tunneling
CN102635059B (en) Bridge investigation method
CN105912798A (en) Ultra-deep foundation pit pumping based ground subsidence intelligent early-warning method and monitoring system
CN111125820B (en) BIM+GIS-based construction site space virtual construction method
CN113468637B (en) Airport pavement modeling method based on BIM technology
CN113532509A (en) A large-scale monitoring method for high and steep slopes based on space-to-ground three-dimensional technology
CN113362469A (en) Shield tunnel construction early warning method integrating city building information and stratum structure
CN109409827A (en) The monitoring method of construction speed in a kind of engineering construction based on virtual-real comparison
CN115116198A (en) Air-ground integrated road collapse monitoring method and system
CN116448080A (en) Unmanned aerial vehicle-based oblique photography-assisted earth excavation construction method
CN110672073A (en) Method and device for assisting tunnel site area construction based on three-dimensional remote sensing technology
CN115748841A (en) Karst region impact hole-forming cast-in-place pile deviation monitoring method
Alicandro et al. UAV photogrammetry for resilience management in reconstruction plan of urban historical centres after seismic events. A case study
CN114519775A (en) Oil-gas pipeline engineering pipe ditch construction management method and system
CN115510607A (en) Three-electricity migration and transformation design method based on three-dimensional live-action modeling technology
CN119004620A (en) Mine construction planning method and system based on BIM three-dimensional modeling
CN117876612B (en) Route fitting design method based on unmanned aerial vehicle oblique photography
CN110106825A (en) Construction process for intelligent filling and digging of artificial lake
CN115758552A (en) Building construction monitoring method and monitoring and early warning system based on FEA and BIM
CN116776449A (en) Sketchup software-based nuclear power plant area total plane layout method and system
CN115652960A (en) BIM and oblique photography-based slope support construction method
CN115726403A (en) Open caisson construction visual monitoring system and monitoring method based on Beidou and 5G
CN114581601A (en) Method and system for monitoring mound in pipeline engineering construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination