CN115627675A - The structure of a kind of sports field and the construction method of its plastic runway and lawn - Google Patents
The structure of a kind of sports field and the construction method of its plastic runway and lawn Download PDFInfo
- Publication number
- CN115627675A CN115627675A CN202211309887.3A CN202211309887A CN115627675A CN 115627675 A CN115627675 A CN 115627675A CN 202211309887 A CN202211309887 A CN 202211309887A CN 115627675 A CN115627675 A CN 115627675A
- Authority
- CN
- China
- Prior art keywords
- layer
- lawn
- plastic
- soil
- runway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C11/00—Details of pavings
- E01C11/22—Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
- E01C11/224—Surface drainage of streets
- E01C11/227—Gutters; Channels ; Roof drainage discharge ducts set in sidewalks
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/02—Foundations, e.g. with drainage or heating arrangements
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/04—Pavings made of prefabricated single units
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/08—Surfaces simulating grass ; Grass-grown sports grounds
- E01C13/083—Construction of grass-grown sports grounds; Drainage, irrigation or heating arrangements therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
本发明涉及体育运动场地施工技术领域,具体为一种体育运动场地的结构及其塑胶跑道和草坪的施工方法;结构从内往外为草坪结构、排水沟和塑胶跑道结构;最下层为素土基层;从下往上:塑胶跑道结构依次为包括防水混凝土层和细粒式改性沥青混凝土层的跑道基础层、预制环保塑胶层;草坪结构依次为设有渗透排水管的草坪基础层、人造草坪层;塑胶跑道施工方法为铺设素土基层、铺设跑道基础层及其的防水混凝土层和细粒式改性沥青混凝土层、铺设预制环保塑胶层;草坪的施工方法为铺设素土基层、铺设设有渗透排水管的草坪基础层,铺设人造草坪层。可渗透施工环保胶代替沥青的使用,保护人体健康;防水混凝土层隔绝了水向下的侵蚀,避免跑道下沉影响使用。
The invention relates to the technical field of sports field construction, in particular to a structure of a sports field and a construction method for a plastic runway and a lawn; the structure is a lawn structure, a drainage ditch and a plastic runway structure from the inside to the outside; the bottom layer is a plain soil base ;From bottom to top: the structure of the plastic runway is the runway base layer including the waterproof concrete layer and the fine-grained modified asphalt concrete layer, and the prefabricated environmental protection plastic layer; the lawn structure is the lawn base layer with permeable drainage pipes, artificial turf layer; the construction method of the plastic runway is to lay the plain soil base layer, lay the runway base layer and its waterproof concrete layer and fine-grained modified asphalt concrete layer, and lay the prefabricated environmental protection plastic layer; the construction method of the lawn is to lay the plain soil base layer, lay the Lawn base layer with permeable drains, laying artificial turf layer. The use of permeable construction environmental protection glue replaces asphalt to protect human health; the waterproof concrete layer isolates the downward erosion of water and prevents the sinking of the runway from affecting the use.
Description
技术领域technical field
本发明涉及体育运动场地施工技术领域,具体为一种体育运动场地的结构及其塑胶跑道和草坪的施工方法。The invention relates to the technical field of sports field construction, in particular to a structure of a sports field and a construction method for a plastic runway and a lawn.
背景技术Background technique
像学校的操场和室外的运动场等都是比较常见的体育运动场,其主要用于训练、比赛,是学校或城市不可缺少的一部分;一般的体育运动场地主要包括外部的一圈塑胶跑道和内部的草坪。School playgrounds and outdoor playgrounds are relatively common sports fields, which are mainly used for training and competitions, and are an indispensable part of schools or cities; general sports fields mainly include an external plastic track and an internal track. lawn.
目前,运动场地的塑胶跑道的基础层一般是使用传统水泥混凝土基础层或沥青基础层,上面铺设塑胶面层。传统的混凝土基础层施工难度大、平整度难以掌握,容易起砂,会导致塑胶面层与基础层粘结不充分、粘接不牢,产生空鼓(鼓包);下雨天塑胶跑道的水会向下渗透,暴雨天气水会渗透到地下土层,导致塑胶跑道局部下沉,影响使用;塑胶跑道夏天经太阳暴晒后表面温度高达70℃以上,高温会加速塑胶面层老化,最主要的沥青基础层的沥青粘结层软化,与塑胶面层在高温下容易分解出有害气体,不利于人的健康。雨天时,草坪作为足球场由于地基表面渗透性比较差导致容易积水,在雨水和草坪的作用下运动员很容易滑倒受伤,限制了草坪作为足球场地的使用。At present, the base layer of the plastic runway in the sports field generally uses a traditional cement concrete base layer or an asphalt base layer, and a plastic surface layer is laid on it. The traditional concrete base layer is difficult to construct, the flatness is difficult to control, and it is easy to sand, which will lead to insufficient bonding between the plastic surface layer and the base layer, and the bonding will not be strong, resulting in hollowing (bulging); the water on the plastic track in rainy days will Penetrating downwards, water in rainy weather will penetrate into the underground soil layer, causing the plastic runway to partially sink and affect the use; the surface temperature of the plastic runway after being exposed to the sun in summer is as high as 70°C, and high temperature will accelerate the aging of the plastic surface layer, the most important asphalt The asphalt bonding layer of the base layer is softened, and it is easy to decompose harmful gases with the plastic surface layer at high temperature, which is not conducive to human health. In rainy days, the lawn used as a football field is prone to water accumulation due to the relatively poor permeability of the foundation surface. Under the action of rain and lawn, athletes are prone to slip and be injured, which limits the use of lawn as a football field.
发明内容Contents of the invention
本发明针对现有技术中塑胶面层容易鼓包、暴雨天气导致塑胶跑道局部下沉,草坪的地基表面渗透性较差容易积水的技术问题,提出了一种体育运动场地的结构及其塑胶跑道和草坪的施工方法。Aiming at the technical problems in the prior art that the plastic surface layer is easy to bulge, the plastic runway partially sinks due to heavy rain, and the foundation surface of the lawn has poor permeability and is prone to water accumulation, the invention proposes a structure of a sports field and its plastic runway and lawn construction methods.
为了达到上述目的,本发明采用的技术方案为:一种体育运动场地的结构,包括内部的草坪结构,以及围绕在草坪结构外部一圈的塑胶跑道结构;所述草坪结构与塑胶跑道结构之间还设有一圈排水沟;所述塑胶跑道结构与草坪结构的最下层均为素土基层;所述塑胶跑道结构在素土基层上方从下往上还依次设有跑道基础层和预制环保塑胶层;所述草坪结构在素土基层上方从下往上还依次设有草坪基础层和人造草坪层;所述跑道基础层从下往上依次为灰土层、二灰碎石层、防水混凝土层和细粒式改性沥青混凝土层;所述草坪基础层从下往上依次为级配碎石层、加强型土工布和中粗砂层;所述级配碎石层内设有渗透排水管,所述渗透排水管延伸到排水沟,且与排水沟连通。In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: a structure of a sports field, including an internal lawn structure, and a plastic runway structure around the outside of the lawn structure; the structure between the lawn structure and the plastic runway structure There is also a circle of drains; the bottom layer of the plastic runway structure and the lawn structure are plain soil bases; the plastic runway structure is also provided with a runway base layer and a prefabricated environmental protection plastic layer from bottom to top above the plain soil base ; The lawn structure is also provided with a lawn base layer and an artificial turf layer from bottom to top above the plain soil base layer; the runway base layer is successively a lime soil layer, a fly ash gravel layer, a waterproof concrete layer, and an artificial turf layer from bottom to top. A fine-grained modified asphalt concrete layer; the lawn base layer is a graded gravel layer, a reinforced geotextile and a medium-coarse sand layer from bottom to top; the graded gravel layer is provided with a permeable drainage pipe, The percolation drain extends to and communicates with the drain.
防水混凝土层隔绝水向下的侵蚀,避免跑道的下沉;减少沥青使用,降低危害气体的产生;加强型土工布隔绝了泥土、沙的同时,保证了水向下渗透,渗透排水管收集到雨水后排到排水沟。The waterproof concrete layer isolates the downward erosion of water and avoids the sinking of the runway; reduces the use of asphalt and reduces the generation of harmful gases; while the reinforced geotextile isolates the soil and sand, it ensures that the water penetrates downward and is collected by the drainage pipe Drains into gutters after rain.
优选的,所述预制环保塑胶层与细粒式改性沥青混凝土层之间涂有可渗透施工环保胶;所述人造草坪层包括种植土层及其上铺设的人造草坪;可渗透施工环保胶将跑道基础层与预制环保塑胶层紧紧粘结在一起,代替沥青的作用。Preferably, the permeable construction environmental protection adhesive is coated between the prefabricated environmental protection plastic layer and the fine-grained modified asphalt concrete layer; the artificial turf layer includes the planting soil layer and the artificial turf laid on it; the permeable construction environmental protection adhesive Tightly bond the base layer of the runway with the prefabricated environmentally friendly plastic layer to replace the role of asphalt.
优选的,所述渗透排水管沿草坪结构的中心向四周排布,且高度逐渐降低;使雨水收集更加高效,还能防止雨水出现滞留、回渗。Preferably, the permeable drainage pipes are arranged along the center of the lawn structure to the surroundings, and the height gradually decreases; the rainwater collection is more efficient, and the rainwater can also be prevented from stagnation and back seepage.
优选的,所述级配碎石层的下方设有与所述渗透排水管相同排布的集水槽,所述渗透排水管设置在集水槽内。Preferably, a sump arranged in the same arrangement as the seepage drainage pipe is provided under the graded gravel layer, and the permeation drainage pipe is arranged in the sump.
优选的,所述灰土层的石灰与土的体积比为2:8。Preferably, the lime soil layer has a volume ratio of lime to soil of 2:8.
优选的,在所述排水沟下方,沿其延长方向,均衡的设有多个与排水沟连通的集水井;所述排水沟至少在对应集水井的正上方的位置处设有井盖;雨水从草坪基础层内的渗透排水管流进排水沟,进而到集水井内,集水井的水可以二次利用,比如抽出来浇到过热的预制环保塑胶层上。Preferably, under the drainage ditch, along its extending direction, a plurality of water collection wells connected with the drainage ditch are evenly provided; the drainage ditch is provided with a manhole cover at least directly above the corresponding water collection well; The seepage drainage pipe in the lawn base layer flows into the drainage ditch, and then into the sump well, and the water in the sump well can be reused, such as being pumped out and poured on the overheated prefabricated environmental protection plastic layer.
本发明还提供了一种体育运动场地的塑胶跑道的施工方法,其特征在于,包括以下步骤:The present invention also provides a construction method for a plastic runway in a sports field, which is characterized in that it comprises the following steps:
步骤一 摊铺素土,并夯实,形成素土基层;
步骤二 摊铺并碾压石灰与土的体积比为2:8的灰土,形成灰土层;
步骤三 摊铺并碾压二灰碎石,形成二灰碎石层;
步骤四 浇筑抗渗混凝土,形成防水混凝土层;
步骤五 铺设细粒式改性沥青混凝土,形成细粒式改性沥青混凝土层;
步骤六 在细粒式改性沥青混凝土层上涂一层可渗透施工环保胶,并在其上铺设预制环保塑胶层;Step 6: Apply a layer of permeable construction environmental protection adhesive on the fine-grained modified asphalt concrete layer, and lay a prefabricated environmental protection plastic layer on it;
步骤七 在铺好的预制环保塑胶层上进行场地划线,并清理,形成塑胶跑道。
优选的,所述步骤二中将灰土分成多层,逐步摊铺并碾压每一层。Preferably, in the second step, the lime soil is divided into multiple layers, and each layer is gradually spread and rolled.
本发明还提供了一种体育运动场地的草坪的施工方法,包括以下步骤:The present invention also provides a kind of construction method of the lawn of sports field, comprises the following steps:
步骤一 摊铺素土,并夯实,形成素土基层,同时集水槽,集水槽沿草坪结构的中心向四周排布;
步骤二 在集水槽内搭设渗透排水管,渗透排水管向四周高度逐渐降低;
步骤三 摊铺并碾压级配碎石,形成级配碎石层;
步骤四 铺设一层加强型土工布;
步骤五 摊铺并碾压中粗砂,形成中粗砂层;
步骤六 摊铺一层种植土,形成种植土层,并在其上铺设人造草坪;
步骤七 填充塑胶颗粒,清理草坪。
优选的,所述素土通过平地机摊铺;所述集水槽通过平地机造型而成。Preferably, the plain soil is spread by a grader; the sump is shaped by a grader.
与现有技术相比,本发明的优点和积极效果在于:(1)可渗透施工环保胶将跑道基础层与预制环保塑胶层紧紧粘结在一起,减少沥青的使用,降低危害气体的产生,保护人体健康;(2)设置防水混凝土层,隔绝了水向下的侵蚀,避免后期跑道的部分下沉,影响使用;(3)加强型土工布隔绝泥土、砂土的同时,保证了水向下层的顺利渗透,便于排出;(4)渗透排水管收集到雨水后排到排水沟,进而到集水井内,集水井的水可以二次利用,比如抽出来浇到过热的预制环保塑胶层上进行降温;(5)渗透排水管向四周高度逐渐降低,使雨水收集更加高效,还能防止雨水出现滞留、回渗。Compared with the prior art, the advantages and positive effects of the present invention are: (1) The permeable construction environmental protection adhesive tightly bonds the runway base layer and the prefabricated environmental protection plastic layer together, reduces the use of asphalt, and reduces the generation of harmful gases , to protect human health; (2) Set up a waterproof concrete layer to isolate the downward erosion of water, avoid the partial subsidence of the runway in the later stage, and affect the use; (3) The reinforced geotextile isolates soil and sand while ensuring water Smooth infiltration to the lower layer, easy to discharge; (4) The infiltration drainage pipe collects rainwater and discharges it to the drainage ditch, and then to the water collection well. The water in the water collection well can be reused, such as pumped out and poured into the overheated prefabricated environmental protection plastic layer (5) The height of the infiltration drainage pipe gradually decreases to the surroundings, which makes rainwater collection more efficient and prevents rainwater from stagnation and back seepage.
附图说明Description of drawings
为了更清楚地说明本发明实施例的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following will briefly introduce the drawings that need to be used in the description of the embodiments.
图1为本体育运动场地的俯视图;Fig. 1 is the top view of this sports field;
图2为渗透排水管的排布示意图;Figure 2 is a schematic diagram of the arrangement of permeate drainage pipes;
图3为图1中A-A处的剖视图;Fig. 3 is the sectional view of A-A place among Fig. 1;
图4为图2中B-B处的剖视图。Fig. 4 is a cross-sectional view at B-B in Fig. 2 .
附图标记说明:Explanation of reference signs:
1-塑胶跑道结构;1-Plastic runway structure;
2-草坪结构;21-集水槽2- lawn structure; 21- sump
3-排水沟,31-集水井,32-井盖;3-drainage ditch, 31-collection well, 32-well cover;
4-渗透排水管;4 - percolation drains;
5-素土基层;5- plain soil base;
6-跑道基础层,61-灰土层,62-二灰碎石层,63-防水混凝土层,64-细粒式改性沥青混凝土层;6-runway base layer, 61-lime soil layer, 62-fly ash macadam layer, 63-waterproof concrete layer, 64-fine-grained modified asphalt concrete layer;
7-预制环保塑胶层,71-可渗透施工环保胶;7-prefabricated environmental protection plastic layer, 71-permeable construction environmental protection glue;
8-草坪基础层,81-级配碎石层,82-加强型土工布,83-中粗砂层;8-lawn base layer, 81-graded gravel layer, 82-reinforced geotextile, 83-medium coarse sand layer;
9-人造草坪层,91-种植土层,92-人造草坪。9-artificial turf layer, 91-planting soil layer, 92-artificial turf.
具体实施方式Detailed ways
为了能够更清楚地理解本发明的上述目的、特征和优点,下面结合附图和实施例对本发明做进一步说明。In order to more clearly understand the above objects, features and advantages of the present invention, the present invention will be further described below in conjunction with the accompanying drawings and embodiments.
在下面的描述中阐述了很多具体细节以便于充分理解本发明,但是,本发明还可以采用不同于在此描述的其他方式来实施,因此,本发明并不限于下面公开说明书的具体实施例的限制。In the following description, many specific details are set forth in order to fully understand the present invention. However, the present invention can also be implemented in other ways than described here. Therefore, the present invention is not limited to the specific embodiments disclosed below. limit.
实施例1Example 1
下面结合附图1-4对本发明进一步说明,一种体育运动场地的结构,包括内部的草坪结构2,以及围绕在草坪结构2外部一圈的塑胶跑道结构1;所述草坪结构2与塑胶跑道结构1之间还设有一圈排水沟3;所述塑胶跑道结构1与草坪结构2的最下层均为素土基层5;所述塑胶跑道结构1在素土基层5上方从下往上还依次设有跑道基础层6和预制环保塑胶层7;所述草坪结构2在素土基层5上方从下往上还依次设有草坪基础层8和人造草坪层9;所述跑道基础层6从下往上依次为灰土层61、二灰碎石层62、防水混凝土层63和细粒式改性沥青混凝土层64;所述草坪基础层8从下往上依次为级配碎石层81、加强型土工布82和中粗砂层83;所述级配碎石层81内设有渗透排水管4,所述渗透排水管4延伸到排水沟3,且与排水沟3连通;Below in conjunction with accompanying drawing 1-4, the present invention is further described, a kind of structure of sports field, comprises
设置防水混凝土层63,隔绝了水向下的侵蚀,避免后期跑道的部分下沉;减少沥青作为粘层的使用,降低危害气体的产生;加强型土工布82隔绝了泥土、沙的同时,保证了水向下渗透,渗透排水管4收集到雨水后排到排水沟3,将水排出。The waterproof
如图3所示,所述预制环保塑胶层7与细粒式改性沥青混凝土层64之间涂有可渗透施工环保胶71;所述人造草坪层9包括种植土层91及其上铺设的人造草坪92。As shown in Figure 3, permeable construction
如图2所示,所述渗透排水管4沿草坪结构2的中心向四周排布,且高度逐渐降低。As shown in FIG. 2 , the
如图2和3所示,所述级配碎石层81的下方设有与所述渗透排水管4相同排布的集水槽21,所述渗透排水管4设置在集水槽21内。As shown in FIGS. 2 and 3 , below the graded
所述灰土层61的石灰与土的体积比为2:8。The volume ratio of lime to soil in the lime soil layer 61 is 2:8.
如图2和4所示,在所述排水沟3下方,沿其延长方向,每隔30m均衡的设有多个与排水沟3连通的集水井31;所述排水沟3至少在对应集水井31的正上方的位置处设有井盖32;雨水从草坪基础层8内的渗透排水管4流进排水沟3,进而到集水井31内,集水井31的水可以二次利用,比如抽出来浇到过热的预制环保塑胶层7上。As shown in Figures 2 and 4, below the
实施例2Example 2
一种体育运动场地的塑胶跑道的施工方法,包括以下步骤:A construction method for a plastic runway in a sports field, comprising the following steps:
步骤一 摊铺素土,并夯实,压实度达到90%-95%,形成素土基层5;
步骤二 摊铺并碾压石灰与土的体积比为2:8的灰土,形成灰土层61,厚度达到1000mm上下;具体为:首先摊铺一层250mm上下厚度的灰土、压实,重复四次,直到完成;
步骤三 摊铺并碾压二灰碎石,形成二灰碎石层62,厚度达到250mm上下;
步骤四 浇筑抗渗混凝土,形成防水混凝土层63,厚度达到100mm上下;抗渗混凝土可以提高跑道整体刚度的同时,防止水破坏基层,有效阻绝了水的侵蚀,避免后期跑道的部分下沉;
步骤五 铺设细粒式改性沥青混凝土,形成细粒式改性沥青混凝土层64,厚度达到30mm上下;
步骤六 在细粒式改性沥青混凝土层64上涂一层可渗透施工环保胶71,并在其上铺设预制环保塑胶层7,将跑道基础层6与预制环保塑胶层7紧紧粘结在一起,减少沥青的使用,避免在热天产生有害气体;Step 6: Apply a layer of permeable construction environmental protection adhesive 71 on the fine-grained modified
步骤七 在铺好的预制环保塑胶层7上进行场地划线,并清理,形成塑胶跑道。
实施例3Example 3
一种体育运动场地的草坪的施工方法,包括以下步骤:A construction method for a lawn in a sports field, comprising the following steps:
步骤一 通过GPS平地机摊铺素土,并夯实,压实度达到90%-95%,形成素土基层5;同时,通过GPS平地机造型挖出集水槽21,集水槽21沿草坪结构2的中心向四周排布;平地机一机两用,节省了一个步骤;Step 1: Pave plain soil with a GPS grader and compact it until the compaction reaches 90%-95%, forming a
步骤二 在集水槽21内搭设型号为DN100PE的渗透排水管4,渗透排水管4向四周高度逐渐降低,使雨水收集更加高效,还能防止雨水出现滞留、回渗;
步骤三 摊铺并碾压级配碎石,形成级配碎石层81,厚度约为150mm上下,其最大粒径小于40mm;级配碎石铺在素土基层5上和集水槽21内,从上层留下的雨水在级配碎石层81内逐渐流进集水槽21的渗透排水管4,并排出;Step 3: Paving and rolling graded gravel to form a graded
步骤四 铺设一层加强型土工布82,保证一平米大小的土工布82质量在110-130克之间,用于隔绝泥土、砂土的同时,保证了水向下层的顺利渗透;
步骤五 摊铺并碾压中粗砂,形成中粗砂层83,厚度达到100mm上下;
步骤六 摊铺一层种植土,形成种植土层91,厚度达到250mm上下,并在其上铺设人造草坪92;
步骤七 填充塑胶颗粒,清理草坪。
以上所述,仅是本发明的较佳实施例而已,并非是对本发明作其他形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例应用于其他领域,但是凡是未脱离本发明技术方案内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化,仍属于本发明技术方案的保护范围。The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention to other forms. Any skilled person who is familiar with this profession may use the technical content disclosed above to change or modify the equivalent of the equivalent change. The embodiments are applied to other fields, but any simple modification or equivalent change made to the above embodiments according to the technical essence of the present invention still belongs to the protection scope of the technical solutions of the present invention, as long as they do not depart from the content of the technical solutions of the present invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211309887.3A CN115627675A (en) | 2022-10-25 | 2022-10-25 | The structure of a kind of sports field and the construction method of its plastic runway and lawn |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211309887.3A CN115627675A (en) | 2022-10-25 | 2022-10-25 | The structure of a kind of sports field and the construction method of its plastic runway and lawn |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115627675A true CN115627675A (en) | 2023-01-20 |
Family
ID=84906088
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211309887.3A Pending CN115627675A (en) | 2022-10-25 | 2022-10-25 | The structure of a kind of sports field and the construction method of its plastic runway and lawn |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115627675A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116971239A (en) * | 2023-07-26 | 2023-10-31 | 广州星卫草业股份有限公司 | Construction method for changing football field artificial lawn into mixed lawn |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014105508A (en) * | 2012-11-28 | 2014-06-09 | Takeshi Nakagawa | Structure for laying artificial lawn |
CN206692989U (en) * | 2017-04-17 | 2017-12-01 | 东莞市箭鱼体育设施有限公司 | A light PU flexible runway |
CN208685396U (en) * | 2018-07-28 | 2019-04-02 | 青岛昌洲建筑工程有限公司 | Permeable plastic cement race track |
CN111335112A (en) * | 2020-03-27 | 2020-06-26 | 闫宝生 | Environment-friendly sponge artificial lawn and construction method thereof |
CN215629144U (en) * | 2021-09-10 | 2022-01-25 | 广东盛天体育股份有限公司 | Compound plastic course |
CN216891844U (en) * | 2020-09-22 | 2022-07-05 | 深圳市凯仕澜高分子建材有限公司 | Stadium runway terrace |
-
2022
- 2022-10-25 CN CN202211309887.3A patent/CN115627675A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014105508A (en) * | 2012-11-28 | 2014-06-09 | Takeshi Nakagawa | Structure for laying artificial lawn |
CN206692989U (en) * | 2017-04-17 | 2017-12-01 | 东莞市箭鱼体育设施有限公司 | A light PU flexible runway |
CN208685396U (en) * | 2018-07-28 | 2019-04-02 | 青岛昌洲建筑工程有限公司 | Permeable plastic cement race track |
CN111335112A (en) * | 2020-03-27 | 2020-06-26 | 闫宝生 | Environment-friendly sponge artificial lawn and construction method thereof |
CN216891844U (en) * | 2020-09-22 | 2022-07-05 | 深圳市凯仕澜高分子建材有限公司 | Stadium runway terrace |
CN215629144U (en) * | 2021-09-10 | 2022-01-25 | 广东盛天体育股份有限公司 | Compound plastic course |
Non-Patent Citations (2)
Title |
---|
刘丽芬: "塑胶跑道田径场的设计与施工", 建筑技术开发, vol. 30, no. 6, 15 June 2003 (2003-06-15), pages 57 - 59 * |
姚建平: ""海绵城市"低影响开发设施改造技术在大型住宅小区中的应用", 建筑施工, no. 7, 25 July 2018 (2018-07-25), pages 1233 - 1236 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116971239A (en) * | 2023-07-26 | 2023-10-31 | 广州星卫草业股份有限公司 | Construction method for changing football field artificial lawn into mixed lawn |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106759825B (en) | Construction method of sponge urban green land water storage system | |
CN203188065U (en) | Ballastless track railway expansion soil cutting bedding and slope protection structure | |
CN106638918A (en) | Construction method for sponge city rainwater collection system | |
CN206352331U (en) | The concave herbaceous field structure of sponge the idea of the city | |
CN206752614U (en) | A kind of sponge-type road sinks formula afforests dividing strip Rainwater collection system | |
CN104831599B (en) | Composite water storage and drainage environment-friendly ground | |
CN113445396A (en) | High-fill road foundation filling construction method for high liquid limit soil road section | |
CN107989153A (en) | A kind of novel construction method for building sponge city | |
CN216712589U (en) | Water permeability cement concrete road surface | |
CN111535098A (en) | Rainwater drainage system for green belts and sidewalks of town roads and construction method | |
CN208219340U (en) | A kind of new city road permeable pavement structure | |
CN104695298A (en) | Complete permeable compound type road surface structure | |
CN202627166U (en) | Novel water-discharging ecological zone for town road | |
CN109778625A (en) | A kind of express highway roadbed structure that dregs class building castoff fills | |
CN108086459A (en) | A kind of construction method of sponge urban green space water storage system | |
CN105544341B (en) | A kind of Quick drainage pavement structure of the low-lying place's road in reply city | |
CN115627675A (en) | The structure of a kind of sports field and the construction method of its plastic runway and lawn | |
CN206581379U (en) | A kind of garden way tooth drainage system | |
CN207739092U (en) | Landscape ecology Pavement Construction | |
CN212052138U (en) | Urban road structure applied to collapsible loess mountain area | |
CN108611948A (en) | A kind of urban road permeable pavement structure | |
CN204589747U (en) | A kind of water permeability composite pavement structure completely | |
CN209924091U (en) | Rectangular side ditch structure for reducing roadbed water level and discharging road surface | |
CN209723194U (en) | highway drainage system | |
CN107829347B (en) | Sidewalk structure for urban natural turf and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20230120 |