[go: up one dir, main page]

CN115539127A - Sea area tunnel full-wrapping waterproof threshold pressure-relief water-proof and drainage-proof system and construction method - Google Patents

Sea area tunnel full-wrapping waterproof threshold pressure-relief water-proof and drainage-proof system and construction method Download PDF

Info

Publication number
CN115539127A
CN115539127A CN202211224493.8A CN202211224493A CN115539127A CN 115539127 A CN115539127 A CN 115539127A CN 202211224493 A CN202211224493 A CN 202211224493A CN 115539127 A CN115539127 A CN 115539127A
Authority
CN
China
Prior art keywords
waterproof
drainage
tunnel
blind pipe
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211224493.8A
Other languages
Chinese (zh)
Other versions
CN115539127B (en
Inventor
白鸿囯
孟庆余
吴强
夏勇
王旭
霍飞
霍永鹏
贾辉
席博阳
赵铎
赵福全
王乐明
周艺
赵云建
段忠辉
朱峰
胡世超
豆晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN202211224493.8A priority Critical patent/CN115539127B/en
Publication of CN115539127A publication Critical patent/CN115539127A/en
Application granted granted Critical
Publication of CN115539127B publication Critical patent/CN115539127B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明提供一种海域隧道全包防水阈值泄压防排水体系及施工方法,防排水体系包括防水系统和排水系统;防水系统包括土工布、防水板和防水卷材,排水系统包括沿隧道径向截面上部周向设置的环形排水板、分布于隧道两侧的边墙底部且沿隧道长度方向设置的拱脚纵向排水盲管、设置于隧道两侧边墙底部的侧沟、以及设置于隧道仰拱填充面中心位置的中心排水沟,拱脚纵向排水盲管通入侧沟,侧沟与中心排水沟通过横向排水管相连。本发明可以应用于高水压海域矿山隧道领域,通过全包防水理念实现洞内排水量的有效控制,通过阈值泄压技术实现隧道外围水压的折减,从而平衡排水量和围岩水压力。

Figure 202211224493

The invention provides an all-inclusive waterproof threshold pressure relief and waterproof drainage system and construction method for sea area tunnels. The waterproof and drainage system includes a waterproof system and a drainage system; The annular drainage boards arranged circumferentially on the upper part of the section, the vertical drainage blind pipes arranged at the bottom of the side walls on both sides of the tunnel and arranged along the length of the tunnel, the side ditches arranged at the bottom of the side walls on both sides of the tunnel, and the vertical drainage pipes arranged at the bottom of the tunnel on both sides The central drainage ditch at the center of the arch filling surface, the vertical drainage blind pipe at the foot of the arch leads to the side ditch, and the side ditch is connected to the central drainage channel through a horizontal drainage pipe. The invention can be applied to the field of mine tunnels in high water pressure sea areas. The water discharge in the tunnel can be effectively controlled through the all-inclusive waterproof concept, and the water pressure at the periphery of the tunnel can be reduced through the threshold pressure relief technology, thereby balancing the water discharge and surrounding rock water pressure.

Figure 202211224493

Description

一种海域隧道全包防水阈值泄压防排水体系及施工方法An all-inclusive waterproof threshold pressure relief waterproof and drainage system and construction method for sea tunnels

技术领域technical field

本发明涉及高水压条件海域矿山法隧道防排水措施领域,尤其涉及一种海域隧道全包防水阈值泄压防排水体系及施工方法。The invention relates to the field of water-proof and drainage measures for sea-area mining tunnels under high water pressure conditions, and in particular to an all-inclusive water-proof threshold pressure relief and water-proof drainage system for sea area tunnels and a construction method.

背景技术Background technique

既有矿山法隧道采用的多是限量排放理念(也就是水可以进入隧道),在海域富水背景下会造成隧道内抽排水量过大,运营期间成本高昂。另外部分隧道纯粹的全包防水方案会导致隧道外围水压力过大,对隧道衬砌耐久性和防水体系造成很大的挑战。因此,研发一种海域隧道全包防水阈值泄压防排水体系及施工方法是个亟待解决的问题。Most of the existing mining tunnels adopt the concept of limited discharge (that is, water can enter the tunnel). Under the background of rich water in the sea, the pumping and drainage volume in the tunnel will be too large, and the cost during operation will be high. In addition, the purely all-inclusive waterproofing scheme for some tunnels will lead to excessive water pressure on the periphery of the tunnel, posing a great challenge to the durability of the tunnel lining and the waterproofing system. Therefore, it is an urgent problem to be solved to develop an all-inclusive waterproof threshold pressure relief waterproof and drainage system and construction method for sea tunnels.

发明内容Contents of the invention

有鉴于此,本发明旨在提出一种海域隧道全包防水阈值泄压防排水体系及施工方法,既能起到全包防水效果,防止围岩水进入隧道,又能在水压达到一定阈值时,对水头进行降压,实现排水量和水压的平衡。In view of this, the present invention aims to propose an all-inclusive waterproof threshold pressure relief, waterproof and drainage system and construction method for sea area tunnels. When , reduce the pressure of the water head to achieve the balance of displacement and water pressure.

为解决上述技术问题,本发明采用的技术方案是:In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is:

一种海域隧道全包防水阈值泄压防排水体系,包括防水系统和排水系统;An all-inclusive waterproof threshold pressure relief waterproof and drainage system for sea tunnels, including a waterproof system and a drainage system;

所述防水系统包括土工布、防水板和防水卷材,所述土工布和防水板依次设置在隧道的初期支护与二次衬砌之间,所述防水卷材设置在防水板与二次衬砌之间;The waterproof system includes a geotextile, a waterproof board and a waterproof coil, the geotextile and the waterproof board are sequentially arranged between the primary support and the secondary lining of the tunnel, and the waterproof coil is arranged between the waterproof board and the secondary lining between;

所述排水系统包括沿隧道径向截面上部周向设置的环形排水板、分布于隧道两侧的边墙底部且沿隧道长度方向设置的拱脚纵向排水盲管、设置于隧道两侧边墙底部的侧沟、以及设置于隧道仰拱填充面中心位置的中心排水沟,所述拱脚纵向排水盲管通入侧沟,所述侧沟与中心排水沟通过横向排水管相连。The drainage system includes an annular drainage plate arranged along the upper circumferential direction of the radial section of the tunnel, longitudinal drainage blind pipes arranged at the bottom of the sidewalls on both sides of the tunnel and arranged along the length direction of the tunnel, and arranged at the bottom of the sidewalls on both sides of the tunnel. The side ditch, and the central drainage ditch arranged at the center of the filling surface of the tunnel invert, the vertical drainage blind pipe at the arch foot leads into the side ditch, and the side ditch is connected to the central drainage ditch through a horizontal drainage pipe.

进一步的,本防排水体系还包括设置于隧道仰拱部位的环形排水盲管,以及设置于隧道仰拱中心处的仰拱纵向排水盲管,所述环形排水盲管与仰拱纵向排水盲管通过四通管相连,所述仰拱纵向排水盲管与中心排水沟通过竖向盲管连接,在所述竖向盲管的上部端头设有可拆换式、可调阈值的泄压阀。Further, the waterproof and drainage system also includes an annular blind drainage pipe arranged at the inverted arch of the tunnel, and an inverted vertical drainage blind pipe arranged at the center of the tunnel inverted arch. Connected by a four-way pipe, the vertical blind pipe of the inverted arch is connected with the central drainage channel through a vertical dead pipe, and a detachable pressure relief valve with an adjustable threshold is provided at the upper end of the vertical dead pipe .

进一步的,所述防水卷材包括环向防水卷材和纵向防水卷材,所述环向防水卷材和纵向防水卷材交叉搭接设置,围成防水密封区。Further, the waterproof coiled material includes a hoop waterproof coiled material and a longitudinal waterproof coiled material, and the hooped waterproof coiled material and the longitudinal waterproof coiled material are intersected and overlapped to form a waterproof sealing area.

进一步的,在距隧道环向施工缝1m处拱墙范围环向设置0.5m宽的双面自粘式环向防水卷材,同时距纵向施工缝0.5m处沿隧道纵向设置0.5m宽双面自粘式纵向防水卷材,所述环向防水卷材和纵向防水卷材交叉搭接设置,且搭接长度不小于0.2m。Further, a 0.5m wide double-sided self-adhesive circumferential waterproof membrane is installed in the arch wall at a distance of 1m from the tunnel circumferential construction joint, and a 0.5m wide double-sided waterproof membrane is installed along the longitudinal direction of the tunnel at a distance of 0.5m from the longitudinal construction joint. Self-adhesive longitudinal waterproof membrane, the circumferential waterproof membrane and the longitudinal waterproof membrane are overlapped, and the overlapping length is not less than 0.2m.

进一步的,在所述隧道拱墙上由防水卷材围成的防水密封区内均设有一道环形排水板,所述拱脚纵向排水管位于所述防水密封区内,相邻两个环形排水板的纵向间距与环向施工缝的间距一致。Further, an annular drainage board is provided in the waterproof sealing area surrounded by the waterproof coiled material on the arch wall of the tunnel, and the longitudinal drainage pipe of the arch foot is located in the waterproof sealing area, and two adjacent annular drains The longitudinal spacing of the slabs is consistent with the spacing of the circumferential construction joints.

进一步的,所述拱脚纵向排水盲管为分段设置,且在其上部设置有开孔,每段长度为9m,每段所述拱脚纵向排水盲管的两端均与90°弯头相连,将拱脚纵向排水盲管通入侧沟。Further, the vertical drainage blind pipe of the arch foot is arranged in sections, and an opening is arranged on the upper part thereof, each section has a length of 9m, and the two ends of the vertical drainage blind pipe of the arch foot of each section are connected with a 90° elbow Connected, and the vertical drainage blind pipe of the arch foot is connected to the side ditch.

进一步的,当水压力达到0.5Mpa阈值时,所述泄压阀13自动打开将地下水排入隧道仰拱填充面内的中心排水沟。Further, when the water pressure reaches the threshold of 0.5Mpa, the pressure relief valve 13 is automatically opened to discharge the groundwater into the central drainage ditch in the filling surface of the tunnel invert.

进一步的,在隧道仰拱范围防水板外侧,每两道环向施工缝之间设有一道环形排水盲管和一道仰拱纵向排水盲管,所述环形排水盲管和仰拱纵向排水盲管通过四通管连接。Further, on the outside of the waterproof plate in the tunnel inversion range, an annular blind drainage pipe and an inverted vertical drainage blind pipe are arranged between every two circumferential construction joints, and the annular blind drainage pipe and the vertical drainage blind pipe in the inverted arch Connected by four-way pipe.

一种海域隧道全包防水阈值泄压防排水体系的施工方法,包括如下步骤:A construction method for an all-inclusive waterproof threshold pressure relief, waterproof and drainage system for a sea tunnel, comprising the following steps:

第一步,对地层进行注浆处理,隧道洞室开挖并进行初期支护操作,形成锚喷初期支护层;The first step is to grout the strata, excavate the tunnel chamber and carry out initial support operations to form the initial support layer of bolting and spraying;

第二步,对初支表面进行找平饰面后,先施作土工布,再在隧道拱墙及仰拱全环施作防水板,拱墙防水板和仰拱防水板在拱脚位置密封焊接;In the second step, after leveling and finishing the surface of the initial support, first apply geotextiles, and then apply waterproof boards on the tunnel arch wall and the entire ring of the inverted arch. The arch wall waterproof board and the inverted arch waterproof board are sealed and welded at the arch foot ;

第三步,在防水板内表面施作双面自粘式防水卷材,在相邻的施工缝之间形成防水密封区;The third step is to apply a double-sided self-adhesive waterproof membrane on the inner surface of the waterproof board to form a waterproof sealing area between adjacent construction joints;

第四步,在拱墙防水板密封区域范围内设置环形排水板和拱脚纵向排水盲管,防水板密封失效后地下水可通过拱脚纵向排水盲管引入洞内侧沟;The fourth step is to set the annular drainage board and the vertical drainage blind pipe of the arch foot in the sealing area of the waterproof board of the arch wall. After the sealing of the waterproof board fails, the groundwater can be introduced into the inner ditch of the cave through the vertical drainage blind pipe of the arch foot;

第五步,在隧道仰拱范围防水板外侧,每两道环向施工缝之间设置一道环形排水盲管和一道仰拱纵向排水盲管,二者通过四通管连接;仰拱纵向排水盲管通过竖向盲管与中心排水沟相通,竖向盲管端头设置泄压阀;Step 5: On the outer side of the waterproof board in the inverted arch range of the tunnel, an annular drainage blind pipe and an inverted vertical drainage blind pipe are arranged between every two circumferential construction joints, and the two are connected by a four-way pipe; the inverted arch longitudinal drainage blind pipe The pipe communicates with the central drainage ditch through a vertical blind pipe, and a pressure relief valve is installed at the end of the vertical blind pipe;

第六步,在防排水体系进行质量检查合格后,进行自密实防水混凝土结构、二衬结构浇筑施工,在仰拱填充部通过埋设横向排水管连接侧沟和中心排水沟。The sixth step is to carry out the pouring construction of the self-compacting waterproof concrete structure and the secondary lining structure after the quality inspection of the waterproof and drainage system, and connect the side ditch and the central drainage ditch by laying horizontal drainage pipes in the inverted arch filling part.

进一步的,在第四步中,在防水层上敷设有环纵盲管导排系统,环纵盲管导排系统包括环向凹凸排水板和拱脚纵向排水盲管,环向凹凸排水板沿拱墙间隔铺设,拱脚纵向排水盲管在两个边墙底部之间敷设。Further, in the fourth step, a circular vertical blind pipe drainage system is laid on the waterproof layer. The circular longitudinal blind pipe drainage system includes a circular concave-convex drainage board and a longitudinal blind pipe with arch feet. The arch walls are laid at intervals, and the longitudinal drainage blind pipes of the arch feet are laid between the bottoms of the two side walls.

相对于现有技术,本发明所述的海域隧道全包防水阈值泄压防排水体系及施工方法具有以下优势:本发明可以应用于高水压海域矿山隧道领域,通过全包防水理念实现洞内排水量的有效控制,通过阈值泄压技术实现隧道外围水压的折减,从而平衡排水量和围岩水压力;应用“防排并重、防排结合”的理念,通过可调阈值泄压阀来控制和减小衬砌的背水压力,避免了全封堵衬砌的水压力过大问题,同时也避免了全排水衬砌的环境、资源、能耗问题。Compared with the prior art, the all-inclusive waterproof threshold pressure relief, waterproof and drainage system and construction method of the sea tunnel described in the present invention have the following advantages: the present invention can be applied to the field of mine tunnels in high water pressure sea areas, and realize the construction of the tunnel through the all-inclusive waterproof concept. Effective control of displacement, through the threshold pressure relief technology to reduce the water pressure outside the tunnel, so as to balance the displacement and surrounding rock water pressure; apply the concept of "equal attention to drainage and combination of prevention and drainage", and control through the adjustable threshold pressure relief valve And reduce the backwater pressure of the lining, avoiding the problem of excessive water pressure of the fully blocked lining, and also avoiding the environment, resources, and energy consumption of the fully drained lining.

附图说明Description of drawings

构成本发明的一部分的附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:The drawings constituting a part of the present invention are used to provide a further understanding of the present invention, and the schematic embodiments and descriptions of the present invention are used to explain the present invention, and do not constitute an improper limitation of the present invention. In the attached picture:

图1是本发明结构示意图;Fig. 1 is a structural representation of the present invention;

图2是本发明中土工布及防水板细部示意图;Fig. 2 is a detailed schematic diagram of geotextile and waterproof board in the present invention;

图3是本发明中排水板及防水板末端细部设计示意图;Fig. 3 is a schematic diagram of the detailed design of the end of the drainage board and the waterproof board in the present invention;

图4是海域段本发明防排水系统布设仰拱范围平面展开图;Fig. 4 is a plane expansion diagram of the range of the inverted arch of the waterproof and drainage system of the present invention in the sea area section;

图5是海域段本发明防排水系统布设拱墙范围平面展开图;Fig. 5 is a plane expansion diagram of the range of arch walls laid out by the waterproof and drainage system of the present invention in the sea area section;

图6是本发明拱墙环形排水板及纵向盲管设置示意图。Fig. 6 is a schematic diagram of the arrangement of the ring-shaped drainage plate and the vertical blind pipe of the arch wall of the present invention.

附图标记说明:Explanation of reference signs:

01、仰拱填充面;02、二次衬砌;03、初期支护;01. Inverted arch filling surface; 02. Secondary lining; 03. Primary support;

1、土工布;2、防水板;3、防水卷材;3-1、环向防水卷材;3-2、纵向防水卷材;4、环形排水板;5、拱脚纵向排水盲管;6、横向排水管;7、侧沟;8、中心排水沟;9、环形排水盲管;10、仰拱纵向排水盲管;11、四通管;12、竖向盲管;13、泄压阀;14、环向施工缝;15、纵向施工缝;16、防水板连接条。1. Geotextile; 2. Waterproof board; 3. Waterproof membrane; 3-1. Circular waterproof membrane; 3-2. Longitudinal waterproof membrane; 4. Ring drainage board; 6. Horizontal drainage pipe; 7. Side ditch; 8. Central drainage ditch; 9. Annular drainage blind pipe; 10. Inverted vertical drainage blind pipe; 11. Four-way pipe; 12. Vertical blind pipe; 13. Pressure relief Valve; 14. Circumferential construction joint; 15. Longitudinal construction joint; 16. Waterproof board connecting strip.

具体实施方式detailed description

需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。It should be noted that, in the case of no conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”等仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”等的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,除非另有说明,“多个”的含义是两个或两个以上。In describing the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", " The orientations or positional relationships indicated by "vertical", "horizontal", "top", "bottom", "inner" and "outer" are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and Simplified descriptions, rather than indicating or implying that the device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and thus should not be construed as limiting the invention. In addition, the terms "first", "second", etc. are used for descriptive purposes only, and should not be understood as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, a feature defined as "first", "second", etc. may expressly or implicitly include one or more of that feature. In the description of the present invention, unless otherwise specified, "plurality" means two or more.

在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以通过具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that unless otherwise specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection. Connected, or integrally connected; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediary, and it can be the internal communication of two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention based on specific situations.

下面将参考附图并结合实施例来详细说明本发明。The present invention will be described in detail below with reference to the accompanying drawings and examples.

一种海域隧道全包防水阈值泄压防排水体系,所述隧道包括由上至下依次设置的仰拱填充面01、二次衬砌02和初期支护03。An all-inclusive waterproof threshold pressure relief, waterproof and drainage system for sea area tunnels, the tunnel includes an inverted arch filling surface 01, secondary lining 02 and primary support 03 arranged in sequence from top to bottom.

如图1至图4所示,一种海域隧道全包防水阈值泄压防排水体系,包括防水系统和排水系统。所述防水系统包括土工布1、防水板2和防水卷材3,所述土工布1和防水板2依次设置在隧道的初期支护03与二次衬砌02之间,所述防水卷材3设置在防水板2与二次衬砌02之间,通过防水卷材3隔离出防水分区,所述防水卷材材料为PVC高分子材料。所述排水系统包括沿隧道径向截面上部周向设置的环形排水板4、分布于隧道两侧的边墙底部且沿隧道长度方向设置的拱脚纵向排水盲管5、设置于隧道两侧边墙底部的侧沟7、以及设置于隧道仰拱填充面01中心位置的中心排水沟8,所述拱脚纵向排水盲管5通入侧沟7,所述侧沟7与中心排水沟8通过横向排水管6相连。本防排水体系还包括设置于隧道仰拱部位的环形排水盲管9,以及设置于隧道仰拱中心处的仰拱纵向排水盲管10,在隧道仰拱范围防水板外侧,每两道环向施工缝之间设置一道环形排水盲管9和一道仰拱纵向排水盲管10,所述环形排水盲管9与仰拱纵向排水盲管10通过四通管11相连。所述仰拱纵向排水盲管10与中心排水沟8通过竖向盲管12连接,在所述竖向盲管12的上部端头设有可拆换式、可调阈值的泄压阀13。当水压力达到0.5Mpa阈值时,所述泄压阀13自动打开将地下水排入隧道仰拱填充面01内的中心排水沟。As shown in Figures 1 to 4, an all-inclusive waterproof threshold pressure relief waterproof and drainage system for sea tunnels includes a waterproof system and a drainage system. The waterproof system includes a geotextile 1, a waterproof board 2 and a waterproof coiled material 3. The geotextile 1 and the waterproof board 2 are sequentially arranged between the primary support 03 and the secondary lining 02 of the tunnel. The waterproof coiled material 3 It is arranged between the waterproof board 2 and the secondary lining 02, and the waterproof partition is isolated by the waterproof coiled material 3, and the material of the waterproof coiled material is PVC polymer material. The drainage system includes an annular drainage plate 4 arranged circumferentially along the upper part of the radial cross-section of the tunnel, a vertical drainage blind pipe 5 arranged at the bottom of the side walls on both sides of the tunnel and arranged along the length direction of the tunnel, and a vertical drainage pipe 5 arranged on both sides of the tunnel. The side ditch 7 at the bottom of the wall, and the central drainage ditch 8 arranged at the center of the tunnel inverted arch filling surface 01, the vertical drainage blind pipe 5 at the arch foot leads into the side ditch 7, and the side ditch 7 and the central drainage ditch 8 pass through Horizontal drainage pipe 6 is connected. The waterproof and drainage system also includes an annular drainage blind pipe 9 arranged at the tunnel invert, and an inverted vertical drainage blind pipe 10 arranged at the center of the tunnel invert. An annular blind drain pipe 9 and an inverted vertical blind drain pipe 10 are arranged between the construction joints, and the annular blind drain pipe 9 and the inverted vertical blind drain pipe 10 are connected through a four-way pipe 11 . The vertical dead pipe 10 of the inverted arch is connected to the central drainage ditch 8 through a vertical dead pipe 12 , and a detachable pressure relief valve 13 with an adjustable threshold is provided at the upper end of the vertical dead pipe 12 . When the water pressure reaches the threshold of 0.5Mpa, the pressure relief valve 13 is automatically opened to discharge the groundwater into the central drainage ditch in the filling surface 01 of the tunnel invert.

如图5所示,所述防水卷材3包括环向防水卷材3-1和纵向防水卷材3-2,所述环向防水卷材3-1和纵向防水卷材3-2交叉搭接设置,围成防水密封区。具体的,在距隧道环向施工缝1m处拱墙范围环向设置0.5m宽的双面自粘式环向防水卷材3-1,同时距纵向施工缝0.5m处沿隧道纵向设置0.5m宽双面自粘式纵向防水卷材3-2,所述环向防水卷材3-1和纵向防水卷材3-2交叉搭接设置,且搭接长度不小于0.2m。As shown in Figure 5, the waterproof membrane 3 includes a hoop waterproof membrane 3-1 and a longitudinal waterproof membrane 3-2, the hoop waterproof membrane 3-1 and the longitudinal waterproof membrane 3-2 overlap Set up directly to form a waterproof sealing area. Specifically, a 0.5m-wide double-sided self-adhesive circumferential waterproof membrane 3-1 is installed in the arch wall at a distance of 1m from the circumferential construction joint of the tunnel, and 0.5m is installed along the longitudinal direction of the tunnel at a distance of 0.5m from the longitudinal construction joint. Wide double-sided self-adhesive longitudinal waterproof roll material 3-2, the circumferential waterproof roll material 3-1 and the longitudinal waterproof roll material 3-2 are cross-overlapped, and the overlapping length is not less than 0.2m.

如图6所示,在所述隧道拱墙上由防水卷材围成的防水密封区内均设有一道环形排水板4,所述拱脚纵向排水盲管5位于所述防水密封区内,相邻两个环形排水板4的纵向间距与环向施工缝的间距一致。所述拱脚纵向排水盲管5为分段设置,且在其上部设置有开孔,每段长度为9m,每段所述拱脚纵向排水盲管5的两端均与90°弯头相连,将拱脚纵向排水盲管5通入侧沟。As shown in Figure 6, an annular drainage plate 4 is provided in the waterproof sealing area surrounded by waterproof coiled materials on the arch wall of the tunnel, and the vertical drainage blind pipe 5 of the arch foot is located in the waterproof sealing area. The longitudinal distance between two adjacent annular drainage boards 4 is consistent with the distance between the circumferential construction joints. The vertical drainage blind pipe 5 of the arch foot is arranged in sections, and an opening is arranged on the upper part thereof, the length of each section is 9m, and the two ends of the vertical drainage blind pipe 5 of the arch foot of each section are connected with a 90° elbow , the vertical drainage blind pipe 5 of the arch foot is passed into the side ditch.

如图3所示,在防水密封区内,与防水板2相连的防水板连接条16将拱脚纵向排水盲管5围绕。As shown in FIG. 3 , in the waterproof sealing area, the waterproof board connecting strip 16 connected with the waterproof board 2 surrounds the longitudinal blind pipe 5 of the arch foot.

一种海域隧道全包防水阈值泄压防排水体系的施工方法,包括以下步骤:A construction method for an all-inclusive waterproof threshold pressure relief waterproof and drainage system for sea tunnels, comprising the following steps:

第一步,对地层进行注浆处理,隧道洞室开挖并进行初期支护操作,形成锚喷初期支护层。The first step is to grout the strata, excavate the tunnel chamber and carry out initial support operations to form the initial support layer of bolting and spraying.

具体来说,以外径为14.68m的圆形隧道为例。开挖前先通过对地层注浆来降低围岩的渗透性,而后隧道洞室开挖,选用合理的分部开挖工序及锚杆(锚索等)支护措施,隧道洞室拱部及边墙喷射C35高性能混凝土形成锚喷初期支护层。Specifically, take a circular tunnel with an outer diameter of 14.68m as an example. Before the excavation, the permeability of the surrounding rock is reduced by grouting the ground, and then the excavation of the tunnel chamber is carried out. The side wall is sprayed with C35 high-performance concrete to form the initial support layer of anchor shotcrete.

第二步,对初支表面进行找平饰面后,先施作土工布,再在隧道拱墙及仰拱全环施作防水板2,拱墙防水板和仰拱防水板在拱脚位置密封焊接。In the second step, after leveling and finishing the surface of the initial support, first apply geotextiles, and then apply waterproof board 2 on the tunnel arch wall and the entire ring of the inverted arch. The arch wall waterproof board and the inverted arch waterproof board are sealed at the arch foot welding.

具体来说,须确保开挖面平整方可铺设防水板2。爆破及清理效果难以满足要求时,结合仰拱超挖情况,设置5cm-10cm厚水泥砂浆找平层,避免防水板被刺破。Specifically, it is necessary to ensure that the excavation surface is flat before laying the waterproof board 2 . When the blasting and cleaning effects are difficult to meet the requirements, a 5cm-10cm thick cement mortar leveling layer shall be set in combination with the over-excavation of the inverted arch to avoid the waterproof board being punctured.

第三步,在防水板2内表面施作双面自粘式防水卷材3,在相邻的施工缝之间形成防水隔离区。The third step is to apply a double-sided self-adhesive waterproof roll material 3 on the inner surface of the waterproof board 2 to form a waterproof isolation area between adjacent construction joints.

具体来说,距环向施工缝14一米处拱墙范围环向设置0.5m宽双面自粘式环向防水卷材3-1,同时距纵向施工缝0.5m处沿纵向设置0.5m宽双面自粘式纵向防水卷材3-2,上述防水卷材3一面与防水板2粘结、一面与二次衬砌02粘结。环向防水卷材3-1与纵向防水卷材3-2交叉搭接,搭接长度不小于0.2m,形成防水密封区。形成以每板台车长度为单位的拱墙范围独立分区防排水体系,后续局部位置出现渗漏水病害后便于定位、整治。Specifically, a 0.5m wide double-sided self-adhesive circumferential waterproof membrane 3-1 is installed in the arch wall at a distance of one meter from the circumferential construction joint 14, and a 0.5m wide Double-sided self-adhesive longitudinal waterproof roll material 3-2, the above waterproof roll material 3 is bonded to the waterproof board 2 on one side and bonded to the secondary lining 02 on the other side. The circumferential waterproof membrane 3-1 is overlapped with the longitudinal waterproof membrane 3-2, and the overlapping length is not less than 0.2m to form a waterproof sealing area. Form an independent partition waterproof and drainage system for the arch wall range based on the length of each pallet trolley, so that it is easy to locate and rectify after water leakage occurs in subsequent local locations.

第四步,拱墙防水板密封区域范围内设置一道环形排水板4和两道拱脚纵向排水盲管5,防水板密封失效后地下水可通过拱脚纵向排水盲管5引入洞内侧沟。In the fourth step, an annular drainage board 4 and two longitudinal drainage blind pipes 5 at the arch feet are arranged within the sealing area of the waterproof board of the arch wall. After the sealing of the waterproof board fails, groundwater can be introduced into the inner ditch of the cave through the longitudinal blind pipes 5 at the arch feet.

具体来说,防水层上敷设有环纵盲管导排系统,环纵盲管导排系统包括环向凹凸排水板和80mmDG防结晶拱脚纵向排水盲管5,环向凹凸排水板沿拱墙间隔铺设,拱脚纵向排水盲管5在两个边墙底部之间敷设。Specifically, a circular vertical blind pipe drainage system is laid on the waterproof layer. The circular vertical blind pipe drainage system includes a circular concave-convex drainage board and an 80mmDG anti-crystallization arch foot vertical drainage blind pipe 5. The circular concave-convex drainage board runs along the arch wall It is laid at intervals, and the vertical drainage blind pipe 5 of the arch foot is laid between the bottoms of the two side walls.

其中,相邻的0.5m宽凸壳型排水板的纵向间距为12m,与环向施工缝的间距一致。拱脚纵向排水盲管5为分段设置,且上部设置有开孔,每段长度为9m,两端设90°弯头通入侧沟。Among them, the longitudinal spacing of adjacent 0.5m wide convex shell drainage boards is 12m, which is consistent with the spacing of circumferential construction joints. The vertical drainage blind pipe 5 of the arch foot is arranged in sections, and the upper part is provided with openings. The length of each section is 9m, and 90° elbows are provided at both ends to lead into the side ditch.

第五步,在隧道仰拱范围防水板外侧,每两道环向施工缝之间设置一道环形排水盲管9和一道仰拱纵向排水盲管10,二者通过四通管11连接。仰拱纵向排水盲管10通过竖向盲管12与中心排水沟8相通,竖向盲管12端头设置可拆换式可调阈值泄压阀13,所述泄压阀13产品型号为A41H弹簧式泄压阀。In the fifth step, on the outside of the waterproof board in the inverted arch range of the tunnel, an annular blind drainage pipe 9 and an inverted vertical drainage blind pipe 10 are arranged between every two circumferential construction joints, and the two are connected by a four-way pipe 11 . The vertical blind pipe 10 of the inverted arch communicates with the central drainage ditch 8 through the vertical dead pipe 12, and the end of the vertical dead pipe 12 is provided with a detachable adjustable threshold pressure relief valve 13, and the product model of the pressure relief valve 13 is A41H Spring loaded pressure relief valve.

具体来说,在每板台车中部的防水板与仰拱衬砌间设置内径80mmDG防结晶仰拱纵向排水盲管10及环形排水盲管9,并在每板仰拱中心沟(低端)内设置可调节阈值泄压阀13,通过内径80mmDG防结晶竖向排水盲管12与仰拱纵向排水盲管10相连。当水压力达到0.5Mpa阈值时,泄压阀13自动打开将地下水排入洞内中心排水沟8,在控制地下水排放的同时起到降低围岩水压力作用。Specifically, an inner diameter of 80mm DG anti-crystallization vertical drainage blind pipe 10 and a ring-shaped drainage blind pipe 9 are set between the waterproof board in the middle of each pallet and the inverted arch lining, and in the center ditch (lower end) of each board inverted arch An adjustable threshold pressure relief valve 13 is provided, and is connected to the vertical vertical drainage blind pipe 10 of the inverted arch through an anti-crystallization vertical dead pipe 12 with an inner diameter of 80mmDG. When the water pressure reaches the threshold of 0.5Mpa, the pressure relief valve 13 is automatically opened to discharge groundwater into the central drainage ditch 8 in the cave, thereby reducing the surrounding rock water pressure while controlling groundwater discharge.

第六步,在防排水体系进行质量检查合格后,进行自密实防水混凝土结构、二衬结构浇筑施工,在仰拱填充部通过埋设横向排水管6连接侧沟7和中心排水沟8。In the sixth step, after the quality inspection of the waterproof and drainage system is qualified, the self-compacting waterproof concrete structure and the secondary lining structure are poured, and the lateral drainage pipe 6 is buried in the inverted arch filling part to connect the side ditch 7 and the central drainage ditch 8 .

具体来说,侧沟7通过间距10m内径100mm的横向PVC排水管与中心水沟相连。具体来说,防水系统中的二衬结构为自密实高性能防水混凝土,相比较常规的普通防水混凝土,具有高流动性与密实性、高耐久性,高抗渗性能,防水性能更优,能进一步提高海域隧道的防排水质量。Specifically, the side ditch 7 is connected to the central gutter through transverse PVC drainage pipes with an inner diameter of 100 mm at a distance of 10 m. Specifically, the secondary lining structure in the waterproof system is self-compacting high-performance waterproof concrete. Compared with conventional ordinary waterproof concrete, it has high fluidity and compactness, high durability, high impermeability, and better waterproof performance. Further improve the waterproof and drainage quality of sea tunnels.

本发明可以应用于高水压海域矿山隧道领域,在隧道全环设置多道防水,即采用“注浆圈+抗渗初支+全包防水板+C50高标号抗渗混凝土模筑二衬”实现全包防水,通过全包防水理念实现洞内排水量的有效控制;同时,在仰拱部位设置泄压阀,通过阈值泄压技术实现隧道外围水压的折减,从而平衡排水量和围岩水压力。The present invention can be applied to the field of mine tunnels in high-water-pressure sea areas, and multiple waterproofing channels are installed in the entire ring of the tunnel, that is, "grouting ring + impermeable primary support + all-inclusive waterproof board + C50 high-grade impermeable concrete molded second lining" Realize all-inclusive waterproofing, and realize effective control of the drainage in the tunnel through the concept of all-inclusive waterproofing; at the same time, set a pressure relief valve at the inverted arch, and realize the reduction of the peripheral water pressure of the tunnel through the threshold pressure relief technology, so as to balance the drainage and surrounding rock water pressure.

应用“防排并重、防排结合”的理念,通过可调阈值泄压阀来控制和减小衬砌的背水压力,避免了全封堵衬砌的水压力过大问题,同时也避免了全排水衬砌的环境、资源、能耗问题。Applying the concept of "equal emphasis on anti-drainage and combination of anti-drainage", the adjustable threshold pressure relief valve is used to control and reduce the backwater pressure of the lining, which avoids the problem of excessive water pressure in the fully blocked lining and also avoids the problem of full drainage lining environment, resources, and energy consumption.

开挖前先通过对地层注浆来降低围岩的渗透性,使得围岩内部得以胶结和密实,增强围岩抗渗能力,所形成的围岩保护圈层起到封堵地下水渗流通路的作用,减少地下水向隧道区域汇集、渗出,可显著减轻隧道外水压力。Before excavation, the permeability of the surrounding rock is reduced by grouting the ground, so that the interior of the surrounding rock can be cemented and compacted, and the anti-seepage ability of the surrounding rock can be enhanced. The formed surrounding rock protection circle can block the groundwater seepage passage. , reducing the collection and seepage of groundwater to the tunnel area, which can significantly reduce the water pressure outside the tunnel.

以防水板为主体的防水层设置在初期支护和二次衬砌之间,起到隔离润滑的作用,避免了二衬混凝土在硬化过程中由于温度应力、收缩应力等附加应力引起的混凝土表面拉裂,保证了混凝土本身的防水作用。The waterproof layer with the waterproof board as the main body is set between the primary support and the secondary lining, which plays the role of isolation and lubrication, and avoids the concrete surface tension caused by the additional stress such as temperature stress and shrinkage stress during the hardening process of the secondary lining concrete. Cracks ensure the waterproofing effect of the concrete itself.

防水板和二次衬砌之间设置的双面自粘式防水卷材将隧道分割成一个个防水分区,穿过防水层的渗水被环向排水板及时排出,避免渗水在二次衬砌背后沿隧道纵向流窜并从施工缝等薄弱环节渗漏至隧道净空。The double-sided self-adhesive waterproof membrane installed between the waterproof board and the secondary lining divides the tunnel into waterproof partitions. The seepage water passing through the waterproof layer is discharged in time by the circular drainage board to prevent water seepage along the tunnel behind the secondary lining. Longitudinal flow and leakage from weak links such as construction joints to the tunnel clearance.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (10)

1. The utility model provides a waterproof threshold pressure release drainage system is prevented in sea area tunnel complete package which characterized in that: comprises a waterproof system and a drainage system;
the waterproof system comprises geotextile, a waterproof board and a waterproof coiled material, wherein the geotextile and the waterproof board are sequentially arranged between a primary support and a secondary lining of the tunnel, and the waterproof coiled material is arranged between the waterproof board and the secondary lining;
drainage system includes the annular drain bar that sets up along tunnel radial cross section upper portion circumference, distributes in the vertical drainage blind pipe of hunch foot that the side wall bottom of tunnel both sides just set up along tunnel length direction, sets up in the side ditch of tunnel both sides side wall bottom and set up in the central escape canal that tunnel invert filling surface central point put, the vertical drainage blind pipe of hunch foot lets in the side ditch, the side ditch links to each other through horizontal drain pipe with the central escape canal.
2. The all-covered waterproof threshold pressure-relief water-proof and drainage system for the sea area tunnel according to claim 1, which is characterized in that: this drainage system still including setting up in the annular drainage blind pipe of tunnel invert to and set up in the vertical drainage blind pipe of invert at tunnel invert center department, the annular drainage blind pipe passes through the four-way pipe with the vertical drainage blind pipe of invert and links to each other, the vertical drainage blind pipe of invert passes through vertical blind union coupling with central escape canal the upper portion end of vertical blind pipe is equipped with the relief valve.
3. The all-covered waterproof threshold pressure-relief water-proof and drainage system for the sea area tunnel according to claim 1 or 2, which is characterized in that: the waterproof roll comprises a circumferential waterproof roll and a longitudinal waterproof roll, wherein the circumferential waterproof roll and the longitudinal waterproof roll are in cross lap joint to form a waterproof sealing area.
4. The all-covered waterproof threshold pressure-relief water-proof and drainage system for the sea area tunnel according to claim 3, characterized in that: set up the hoop waterproofing membrane of 0.5m width in the arch wall hoop direction apart from tunnel hoop construction joint 1m, set up the wide vertical waterproofing membrane of 0.5m along tunnel longitudinal direction apart from vertical construction joint 0.5m department, hoop waterproofing membrane and vertical waterproofing membrane alternately overlap joint set up, and overlap joint length is not less than 0.2m.
5. The all-covered waterproof threshold pressure-relief water-proof and drainage system for the sea area tunnel according to claim 3, characterized in that: the tunnel encircles all to be equipped with one annular drain bar in the waterproof sealing district that encloses by waterproofing membrane on the wall, the longitudinal drain pipe of hunch foot is located in the waterproof sealing district, the longitudinal separation of two adjacent annular drain bars is unanimous with the interval of hoop construction joint.
6. The all-covered waterproof threshold pressure-relief water-proof and drainage system for the sea area tunnel according to claim 5, characterized in that: the arch foot longitudinal drainage blind pipe is arranged in a subsection mode, an opening is formed in the upper portion of the arch foot longitudinal drainage blind pipe, two ends of each arch foot longitudinal drainage blind pipe are connected with 90-degree elbows, and the arch foot longitudinal drainage blind pipe is led into the side ditch.
7. The all-covered waterproof threshold pressure-relief water-proof and drainage system for the sea area tunnel according to claim 1, which is characterized in that: and when the water pressure reaches a threshold value of 0.5Mpa, the pressure release valve automatically opens to discharge the underground water into a central drainage ditch in the filling surface of the inverted arch of the tunnel.
8. The all-covered waterproof threshold pressure-relief water-proof and drainage system for the sea area tunnel according to claim 1, which is characterized in that: and an annular drainage blind pipe and an inverted arch longitudinal drainage blind pipe are arranged between every two annular construction joints outside the tunnel inverted arch range waterproof plate, and the annular drainage blind pipes and the inverted arch longitudinal drainage blind pipes are connected through a four-way pipe.
9. A construction method of a sea tunnel full-wrap waterproof threshold pressure-relief waterproof and drainage system is characterized by comprising the following steps:
firstly, grouting a stratum, excavating a tunnel cavern and carrying out primary support operation to form an anchor-shotcreting primary support layer;
secondly, after the leveling and facing of the primary support surface is carried out, geotextile is firstly applied, waterproof boards are applied to the tunnel arch wall and the inverted arch in a full-circle manner, and the waterproof boards of the arch wall and the inverted arch waterproof boards are hermetically welded at arch foot positions;
thirdly, applying double-sided self-adhesive waterproof coiled materials on the inner surface of the waterproof board to form a waterproof sealing area between adjacent construction joints;
fourthly, arranging an annular drainage plate and an arch foot longitudinal drainage blind pipe in the sealing area range of the waterproof plate of the arch wall, and introducing underground water into an inner side ditch of the tunnel through the arch foot longitudinal drainage blind pipe after the waterproof plate fails in sealing;
fifthly, arranging an annular drainage blind pipe and an inverted arch longitudinal drainage blind pipe between every two annular construction joints on the outer side of the tunnel inverted arch range waterproof plate, wherein the two annular drainage blind pipes are connected through a four-way pipe; the inverted arch longitudinal drainage blind pipe is communicated with the central drainage ditch through a vertical blind pipe, and the end of the vertical blind pipe is provided with a pressure release valve;
and sixthly, after the quality of the waterproof and drainage system is checked to be qualified, pouring construction of a self-compaction waterproof concrete structure and a secondary lining structure is carried out, and the inverted arch filling part is connected with the side ditch and the central drainage ditch by embedding the transverse drainage pipe.
10. The construction method of the sea area tunnel full-enclosed waterproof threshold pressure-relief water-proof and drainage system according to claim 9, characterized by comprising the following steps: in the fourth step, lay the vertical blind pipe drainage guide system of ring on the waterproof layer, the vertical blind pipe drainage guide system of ring is indulged including the unsmooth drain bar of hoop and the vertical drainage blind pipe of hunch foot, and the unsmooth drain bar of hoop is laid along the hunch wall interval, and the vertical drainage blind pipe of hunch foot lays between two side wall bottoms.
CN202211224493.8A 2022-09-29 2022-09-29 Sea area tunnel full-package waterproof threshold pressure relief waterproof and drainage system and construction method Active CN115539127B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211224493.8A CN115539127B (en) 2022-09-29 2022-09-29 Sea area tunnel full-package waterproof threshold pressure relief waterproof and drainage system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211224493.8A CN115539127B (en) 2022-09-29 2022-09-29 Sea area tunnel full-package waterproof threshold pressure relief waterproof and drainage system and construction method

Publications (2)

Publication Number Publication Date
CN115539127A true CN115539127A (en) 2022-12-30
CN115539127B CN115539127B (en) 2025-11-21

Family

ID=84730689

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211224493.8A Active CN115539127B (en) 2022-09-29 2022-09-29 Sea area tunnel full-package waterproof threshold pressure relief waterproof and drainage system and construction method

Country Status (1)

Country Link
CN (1) CN115539127B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116753025A (en) * 2023-07-07 2023-09-15 中铁二院昆明勘察设计研究院有限责任公司 An intelligent waterproof and drainage system for water-rich tunnels and its construction method
CN118390578A (en) * 2024-06-28 2024-07-26 中铁第六勘察设计院集团有限公司 Waterproof and drainage system for underwater tunnel connection position

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103939142A (en) * 2014-03-31 2014-07-23 中铁工程设计咨询集团有限公司 Tunnel drainage system with controllable water pressure and water pressure controlling device thereof
JP2015155626A (en) * 2014-02-21 2015-08-27 大成建設株式会社 Tunnel structure and lining back water pressure adjustment method
CN107355242A (en) * 2017-09-08 2017-11-17 中国铁道科学研究院铁道建筑研究所 Tunnel waterproof and water drainage system
CN206874310U (en) * 2017-04-14 2018-01-12 长沙理工大学 Be applicable to high-pressure rich water district tunnel decompression drainage device
CN107816361A (en) * 2017-12-08 2018-03-20 四川省交通运输厅公路规划勘察设计研究院 Tunnel rich water section partitioning waterproofing system
CN108533316A (en) * 2018-05-07 2018-09-14 中铁工程设计咨询集团有限公司 A kind of full packet pressure release waterproof/drainage structure in tunnel
CN212337306U (en) * 2020-05-07 2021-01-12 中铁上海工程局集团华海工程有限公司 Automatic device that overflows of pressure-bearing water at bottom of tunnel
CN218522694U (en) * 2022-09-29 2023-02-24 中国铁路设计集团有限公司 An all-inclusive waterproof threshold pressure relief waterproof and drainage system for sea tunnels

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015155626A (en) * 2014-02-21 2015-08-27 大成建設株式会社 Tunnel structure and lining back water pressure adjustment method
CN103939142A (en) * 2014-03-31 2014-07-23 中铁工程设计咨询集团有限公司 Tunnel drainage system with controllable water pressure and water pressure controlling device thereof
CN206874310U (en) * 2017-04-14 2018-01-12 长沙理工大学 Be applicable to high-pressure rich water district tunnel decompression drainage device
CN107355242A (en) * 2017-09-08 2017-11-17 中国铁道科学研究院铁道建筑研究所 Tunnel waterproof and water drainage system
CN107816361A (en) * 2017-12-08 2018-03-20 四川省交通运输厅公路规划勘察设计研究院 Tunnel rich water section partitioning waterproofing system
CN108533316A (en) * 2018-05-07 2018-09-14 中铁工程设计咨询集团有限公司 A kind of full packet pressure release waterproof/drainage structure in tunnel
CN212337306U (en) * 2020-05-07 2021-01-12 中铁上海工程局集团华海工程有限公司 Automatic device that overflows of pressure-bearing water at bottom of tunnel
CN218522694U (en) * 2022-09-29 2023-02-24 中国铁路设计集团有限公司 An all-inclusive waterproof threshold pressure relief waterproof and drainage system for sea tunnels

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116753025A (en) * 2023-07-07 2023-09-15 中铁二院昆明勘察设计研究院有限责任公司 An intelligent waterproof and drainage system for water-rich tunnels and its construction method
CN118390578A (en) * 2024-06-28 2024-07-26 中铁第六勘察设计院集团有限公司 Waterproof and drainage system for underwater tunnel connection position

Also Published As

Publication number Publication date
CN115539127B (en) 2025-11-21

Similar Documents

Publication Publication Date Title
CN101748755B (en) Flexible connecting and sealing bitumastic impervious structure of tunnel deformation joint and constructing method
CN103256052B (en) Construction method for integral straight middle wall type double-arch tunnel
CN108222979B (en) Waterproof and Drainage Construction Method of Karst Water-rich Tunnel
CN105019919B (en) Tunnel and its construction method for transmitting fluid
CN107191197A (en) A kind of shield duct piece and its pushed away in shield sky by the application in Tunneling by mining method
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN101324073A (en) Construction method and anti-seepage structure of deformation joint anti-seepage structure of ground fissure formation tunnel
CN112610233B (en) A "golden cicada shelling" type rectangular pipe jacking construction method
CA3217077C (en) Single-layer shaft lining with joint sealing structure and grouting system and its construction method
CN115539127A (en) Sea area tunnel full-wrapping waterproof threshold pressure-relief water-proof and drainage-proof system and construction method
CN109440951A (en) New-old concrete works intersection stitches waterproof construction and construction technology
WO2024139800A1 (en) Construction method for gas partition system of gas outburst tunnel
CN115949437A (en) Shallow cold-proof heat preservation, drainage structure that buries bias voltage tunnel
CN111472813A (en) A super-span bolt and shotcrete support rock tunnel waterproof and drainage system and construction method
CN204827469U (en) A tunnel for transmission fluid
CN105421497A (en) Water-proof construction method for connected nodes of foundation slab and ground wall in composite surround system
CN112081607B (en) Tunnel primary support and waterproof and drainage combined system and construction method
CN218522694U (en) An all-inclusive waterproof threshold pressure relief waterproof and drainage system for sea tunnels
WO2024139801A1 (en) Isolation protection system for safe operation of gas tunnel
CN108361049A (en) A kind of tunnel waterproofing construction construction method
CN111472803B (en) Tunnel structure suitable for upper soft and lower hard composite stratum and construction method
CN209397743U (en) New-old concrete works intersection stitches waterproof construction
CN110761815A (en) Tunnel negative-pressure laying waterproof plate and construction method thereof
CN212202065U (en) A tunnel structure suitable for upper soft and lower hard composite strata
CN212563251U (en) Triple baffling type partition waterproof structure of underground excavation tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant