CN115478552A - A kind of caisson sinking construction method under hard rock geological conditions - Google Patents
A kind of caisson sinking construction method under hard rock geological conditions Download PDFInfo
- Publication number
- CN115478552A CN115478552A CN202211149849.6A CN202211149849A CN115478552A CN 115478552 A CN115478552 A CN 115478552A CN 202211149849 A CN202211149849 A CN 202211149849A CN 115478552 A CN115478552 A CN 115478552A
- Authority
- CN
- China
- Prior art keywords
- caisson
- construction
- hole
- drilling
- sinking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Earth Drilling (AREA)
Abstract
本发明公开了一种硬岩地质情况下沉井下沉施工方法,S1:地场地进行平整,使场地满足旋挖钻机施工要求,S2:按照设计图纸,定位沉井内、外壁位置,采用梅花形设计引孔布置,并进行标注,步骤S3:运用旋挖钻采用跳孔法进行孔,钻孔顺序按照先外圈后内圈,步骤S4:每完成一个钻孔后立即采用碎石渣土进行回填,防止塌孔或穿孔,并减少对后续钻孔施工的影响。S5:所有钻孔回填完成之后按照在按照掘进下沉的方式进行后续沉井制作与施工。本发明通过在沉井施工之前采用旋挖钻机破碎硬岩结构,减小后续沉井掘进下沉难度,加快沉井下沉速度,并且方便了刃角下方掘土量控制,减少沉井发生倾斜的几率,很大程度的缩短硬岩地层沉井施工工期。
The invention discloses a caisson sinking construction method under the condition of hard rock geological conditions. S1: Level the ground site so that the site meets the construction requirements of a rotary drilling rig. S2: Position the inner and outer walls of the caisson according to the design drawings, and adopt a plum-shaped design Layout and mark the lead holes, step S3: use the rotary drilling drill to drill holes using the jump hole method, the drilling sequence follows the outer circle first and then the inner circle, step S4: immediately backfill with gravel and slag after each hole is completed , Prevent hole collapse or perforation, and reduce the impact on subsequent drilling construction. S5: Subsequent caisson fabrication and construction shall be carried out in the way of excavation and sinking after all boreholes are backfilled. The invention uses a rotary drilling rig to break the hard rock structure before the construction of the caisson, reduces the difficulty of subsequent caisson excavation and sinking, accelerates the sinking speed of the caisson, facilitates the control of the amount of excavated soil under the edge angle, and reduces the risk of inclination of the caisson probability, greatly shortening the construction period of caissons in hard rock formations.
Description
技术领域technical field
本发明属于市政工程施工技术领域,具体涉及一种硬岩地质情况下沉井下沉施工方法。The invention belongs to the technical field of municipal engineering construction, and in particular relates to a caisson sinking construction method under hard rock geological conditions.
背景技术Background technique
沉井下沉施工主要是通过从沉井内用机械或人工方法均匀除土,削弱基底土对刃脚的正面阻力和沉井壁与土之间的摩阻力,使沉井依靠自重力克服上述阻力而下沉。The sinking construction of the caisson is mainly to remove the soil uniformly from the caisson by mechanical or manual methods, weaken the frontal resistance of the base soil to the blade foot and the frictional resistance between the caisson wall and the soil, so that the caisson relies on its own gravity to overcome the above-mentioned resistance. sink.
当沉井施工区域为硬岩地层时,以往采用炮机碎岩的方式进行沉井施工,但由于岩层硬度较大,炮机碎岩效率低,且较难均匀的破除井底及边缘的岩土,导致沉井井壁与下侧易被坚硬的岩石卡住,或发生侧倾现象,严重影响沉井施工工期,对后续顶管施工的推进造成较大阻碍。When the caisson construction area is a hard rock formation, in the past, the method of crushing rock by gun machine was used for caisson construction. However, due to the hardness of the rock formation, the efficiency of rock crushing by gun machine is low, and it is difficult to evenly remove the rock at the bottom and edge of the well. As a result, the caisson well wall and lower side are easily stuck by hard rocks, or sideways phenomenon occurs, seriously affecting the construction period of the caisson and causing great obstacles to the advancement of subsequent pipe jacking construction.
发明内容Contents of the invention
为了克服现有技术中岩石地层沉井掘进下沉难的问题,本发明提供一种硬岩地质区域沉井助沉施工方法,减小了后续沉井施工掘进下沉施工难度以及沉井发生倾斜的概率,便于后续进行沉井施工时能均匀挖掘井孔内的岩石,有利于沉井的快速均匀下沉,解决了上述技术问题。In order to overcome the problem of difficult sinking of caissons in rock formations in the prior art, the present invention provides a construction method for subsidence of caissons in hard rock geological regions, which reduces the difficulty of subsequent caisson construction and the difficulty of caisson inclination. probability, it is convenient for the subsequent caisson construction to evenly excavate the rock in the well hole, which is conducive to the rapid and uniform subsidence of the caisson, and solves the above technical problems.
一种硬岩地质情况下沉井下沉施工方法,该施工方法包括以下施工步骤:A caisson sinking construction method under hard rock geological conditions, the construction method includes the following construction steps:
S1:引孔准备,在施工前对现场进行打围,利用测量设备定位出沉井位置并标识,采用破碎锤对原地面的混凝土进行凿除,托运设备进场,引孔设备采用旋挖钻机,其钻头为直径1m的破岩钻头;S1: Lead hole preparation, encircling the site before construction, using measuring equipment to locate and mark the location of the caisson, using a breaking hammer to chisel out the concrete on the original ground, consigning the equipment into the site, and using a rotary drilling rig for the leading hole equipment, The drill bit is a rock-breaking drill bit with a diameter of 1m;
S2:设计与测量,根据沉井平面设计图确定具体位置,参照沉井具体位置规划多个引孔,根据设计图进行测量放线,其中引孔分布呈梅花形且完全覆盖后期沉井的引孔施工范围;S2: Design and measurement, determine the specific location according to the plane design drawing of the caisson, plan multiple guide holes referring to the specific location of the caisson, and carry out measurement and setting out according to the design drawing. Hole construction scope;
S3:旋挖钻施工,运用旋挖钻机进行引孔,引孔方式采用跳孔法施工。施工顺序为外圈后内圈,为防止破岩深度不够,钻孔设计深度一般比沉井底部设计标高深0.5m;S3: Rotary drilling construction, use the rotary drilling rig to lead the hole, and the method of leading the hole is to use the jump hole method for construction. The construction sequence is the outer ring and then the inner ring. In order to prevent insufficient rock breaking depth, the design depth of drilling is generally 0.5m deeper than the design elevation of the bottom of the caisson;
S4:钻孔回填,每处完成引孔的钻孔均需用碎石块回填,然后再启动下一处钻孔施工,用逐个施工逐个回填的方式;S4: Drilling and backfilling, every drilled hole that has completed the lead hole needs to be backfilled with gravel, and then start the construction of the next drilling hole, and use the method of backfilling one by one;
S5:沉井制作及掘进下沉。引孔及回填完成后,按照常规的沉井施工方案进行后续施工。S5: Fabrication of caisson and excavation and sinking. After the introduction hole and backfilling are completed, the follow-up construction will be carried out according to the conventional caisson construction plan.
上述的一种硬岩地质情况下沉井下沉施工方法,所述步骤S2中的沉井中心与中心引孔重合,中心孔周围间隔0.4m-0.5m设置六个钻孔均匀环绕,外圈18个钻孔均匀分布,其两圈钻孔之间间距约为0.4m-0.5m,设计沉井外壁与最外圈钻孔中心连成的圆相重合。In the above-mentioned construction method of caisson sinking under hard rock geological conditions, the center of the caisson in the step S2 coincides with the central leading hole, and six boreholes are arranged around the central hole at intervals of 0.4m-0.5m to surround them evenly, and the outer ring is 18 The boreholes are evenly distributed, and the distance between the two circles of boreholes is about 0.4m-0.5m. The outer wall of the caisson is designed to coincide with the circle formed by the center of the outermost circle of boreholes.
上述的一种硬岩地质情况下沉井下沉施工方法,所述步骤S3中的钻孔采用旋挖钻机进行施工,按照设计桩号进行,钻孔顺序由外圈至内圈逐个进行,每圈钻孔采用跳孔法施工。In the above-mentioned construction method of caisson sinking under hard rock geological conditions, the drilling in the step S3 is carried out using a rotary drilling rig, and is carried out according to the design pile number, and the drilling sequence is carried out one by one from the outer circle to the inner circle, and each circle Drilling is carried out using the jump hole method.
上述的一种硬岩地质情况下沉井下沉施工方法,所述步骤S4中的钻孔方式采用跳孔法,完成第一个钻孔以后隔一个钻孔继续施工,每完成一个钻孔就立即用碎石块进行回填。In the above-mentioned caisson sinking construction method under hard rock geological conditions, the drilling method in the step S4 adopts the hole-jumping method, and the construction is continued every other drilling hole after the first drilling hole is completed, and each drilling hole is completed immediately. Backfill with crushed rock.
上述的一种硬岩地质情况下沉井下沉施工方法,所述步骤S5中的旋挖钻引孔提前破碎岩层结构这种助沉方法是在沉井施工之前进行使用。In the above-mentioned caisson sinking construction method under hard rock geological conditions, the sinking-assisting method of breaking the rock formation structure in advance by the rotary drilling and pilot hole in the step S5 is used before the caisson construction.
总体而言,通过本发明所构思的以上技术方案与现有技术相比,可以达到以下有益效果:Generally speaking, compared with the prior art, the above technical solutions conceived by the present invention can achieve the following beneficial effects:
1、本发明一种硬岩地质情况下沉井下沉施工方法,在硬岩地质情况下沉井助沉施工方法能够提高硬岩地层沉井施工效率,在沉井基坑制作之前采用旋挖钻机进行引孔,提前破碎坚硬的岩层结构,减小后续长臂炮机碎岩的难度,加快后期沉井下沉掘进速度,很大程度的缩短硬岩地层沉井施工周期1. A construction method for caisson sinking under hard rock geological conditions of the present invention. The caisson sinking construction method under hard rock geological conditions can improve the construction efficiency of caissons in hard rock formations. Before the caisson foundation pit is made, a rotary drilling rig is used to carry out The introduction hole can break the hard rock structure in advance, reduce the difficulty of rock crushing by the long-arm cannon, speed up the excavation speed of caisson sinking in the later stage, and greatly shorten the construction period of caisson in hard rock formation
2、本发明所述的旋挖钻钻孔成梅花形对称布置,且设计沉井刃角位置设置在两圈钻孔之间,在沉井挖掘下沉时可有效减少沉井纠偏次数,进一步节约了工期,采用逐个钻孔逐个回填的方式,减小了相邻钻孔间的影响,提供一个稳定的支撑平面,保证了后续沉井的施工环境。2. The boreholes of the rotary drilling drill described in the present invention are symmetrically arranged in a quincunx shape, and the position of the edge angle of the caisson is designed to be set between two circles of boreholes, which can effectively reduce the number of deviation corrections of the caisson when the caisson is excavated and sinks, and further The construction period is saved, and the method of backfilling each drill hole one by one reduces the influence between adjacent drill holes, provides a stable support plane, and ensures the construction environment of the subsequent caisson.
附图说明Description of drawings
下面结合附图对本发明的具体实施方式做进一步详细的说明,其中:Below in conjunction with accompanying drawing, specific embodiment of the present invention is described in further detail, wherein:
图1为本发明一种硬岩地质情况下沉井下沉施工方法的施工工艺流程图;Fig. 1 is the construction process flowchart of caisson sinking construction method under a kind of hard rock geological situation of the present invention;
图2为本发明进行旋挖钻引孔的平面设计图;Fig. 2 is the plane design drawing that the present invention carries out rotary drilling and drilling pilot hole;
图3为本发明钻孔顺序示意图;Fig. 3 is a schematic diagram of the drilling sequence of the present invention;
图中:1-引孔施工范围,2-沉井外壁,3-沉井内壁,4-钻孔。In the figure: 1- the construction range of the lead hole, 2- the outer wall of the caisson, 3- the inner wall of the caisson, and 4- the drilling.
具体实施方式detailed description
本发明主要解决的沉井在硬岩地质条件下掘进下沉缓慢的问题,而提供一种高效的沉井施工方法。The invention mainly solves the problem of slow sinking of caissons under hard rock geological conditions, and provides an efficient caisson construction method.
一种硬岩地质情况下沉井下沉施工方法在某顶管工程的应用,该沉井施工地层自上而下岩层分别为:碎石粉质土、强风化砂砾岩、中风化砂砾岩;设计要求顶管工作井深度为13.5米,沉井尺寸为:内径7米,外径8.5米,壁厚为0.75m;采用现浇法制作沉井。Application of a caisson sinking construction method under hard rock geological conditions in a pipe jacking project. The strata for caisson construction from top to bottom are: gravel silty soil, strongly weathered glutenite, and moderately weathered glutenite; the design It is required that the depth of the pipe jacking working well is 13.5 meters, the size of the caisson is: inner diameter 7 meters, outer diameter 8.5 meters, wall thickness 0.75m; the caisson is made by cast-in-place method.
本实施例硬岩地质情况下顶管工作井快速下沉施工方法流程如图1所示,具体包括如下步骤:In this embodiment, the process flow of the rapid subsidence construction method of the pipe jacking well under the hard rock geological conditions is shown in Figure 1, which specifically includes the following steps:
步骤一:施工准备,施工之前,通过对现场进行打围,对沉井结构测量放线,确认沉井位置,对打围场地进行整平,满足设计地面标高,并达到旋挖钻机施工场地要求。Step 1: Construction preparation. Before construction, by enclosing the site, measuring and setting out the caisson structure, confirming the location of the caisson, and leveling the enclosing site to meet the design ground elevation and meet the requirements of the rotary drilling rig construction site.
步骤二:引孔定位,根据沉井设计图,确定沉井中心桩号,根据沉井内外径标记出沉井范围,由中心桩号向外散开,确定引孔桩号,引孔呈梅花形布置,设计沉井刃角尽量处于两钻孔之间,钻孔范围既要覆盖沉井范围,又要保证钻孔数量最少。Step 2: Positioning of the lead hole. According to the caisson design drawing, determine the caisson center stake number, mark the range of the caisson according to the inner and outer diameters of the caisson, spread out from the center stake number, and determine the lead hole stake number. The lead hole is plum blossom The design of the caisson bezel should be between the two boreholes as much as possible, and the range of the drilled holes should not only cover the range of the caisson, but also ensure the minimum number of drilled holes.
具体钻孔平面分布图如图2所示,选用旋挖钻头直径为1m,其中相邻孔的距离在0.4-0.5m之间,由图2可知中心为单个钻孔,内圈为6个钻孔均匀环形布置,与中心孔间距为0.45m;次内圈为12个钻孔均匀环形布置,与内圈孔间距为0.4m;外圈为18个钻孔均匀环形布置,与次内圈孔间距为0.4m。由图2可知将沉井刃角位置设置在外圈与次内圈之间。The specific drilling plan distribution diagram is shown in Figure 2. The diameter of the rotary drilling bit is 1m, and the distance between adjacent holes is between 0.4-0.5m. It can be seen from Figure 2 that the center is a single drilling hole, and the inner ring is 6 drilling holes. The holes are evenly arranged in a ring, with a distance of 0.45m from the central hole; the secondary inner ring is uniformly arranged with 12 drill holes, and the distance from the inner ring is 0.4m; The spacing is 0.4m. It can be seen from Figure 2 that the caisson edge position is set between the outer ring and the secondary inner ring.
步骤三:旋挖钻施工,采用旋挖钻机进行引孔施工,施工顺序如图3所示,其顺序为:按照由外向内钻孔施工,每圈钻孔顺序视现场情况而定。Step 3: Rotary drilling construction, use the rotary drilling rig to carry out the construction of the lead hole, the construction sequence is shown in Figure 3, and the sequence is: according to the drilling construction from the outside to the inside, the drilling sequence of each circle depends on the site conditions.
为防止成孔深度不够,钻孔设计深度比沉井底设计标高深0.5m,旋挖钻机钻头采用直径为1m的破岩钻头。In order to prevent insufficient hole depth, the design depth of the drill hole is 0.5m deeper than the design elevation of the caisson bottom, and the drill bit of the rotary drilling rig adopts a rock-breaking drill bit with a diameter of 1m.
步骤四:钻孔回填,每根完成引孔的钻孔均需用碎石块回填,然后再启动下一根钻孔引孔施工,用逐个施工逐个回填的方式一方面可以避免钻孔内无支撑造成塌孔或相邻钻孔施工时发生串孔的问题,一方面还可为后续沉井刃角支模浇筑提供一个稳定的支撑面。Step 4: Drilling and backfilling. Each drilled hole that has completed the lead hole needs to be backfilled with gravel, and then start the construction of the next drilled hole. The method of backfilling one by one can avoid the use of empty holes in the drilled hole. The support causes the collapse of the hole or the problem of stringing holes during the construction of adjacent drilling holes. On the one hand, it can also provide a stable support surface for the subsequent caisson edge formwork pouring.
步骤五:沉井制作及掘进下沉,沉井制作及掘进下沉。引孔及回填完成后,按照常规的沉井施工方案进行后续施工。Step five: caisson fabrication and excavation sinking, caisson fabrication and excavation sinking. After the introduction hole and backfilling are completed, the follow-up construction will be carried out according to the conventional caisson construction plan.
旋挖钻引孔提前破碎岩层结构这种助沉方法是在沉井施工之前进行使用,由于步骤四中将所有的钻孔用碎石块回填,保证了后续基坑开挖、垫层处理以及刃角和沉井的支模浇筑的正常开展,旋挖钻引孔的主要作用是减小在后续沉井下沉过程中破岩和开挖作业的难度。后续施工顺序为:基坑开挖→垫层施工→刃角支模浇筑→拆模养护→沉井下沉及封底。The sedimentation aid method of breaking the rock structure in advance by rotary drilling and drilling the pilot hole is used before caisson construction. Since all the drill holes are backfilled with crushed stones in
由实施例可知,该沉井采用旋挖钻引孔施工工期为9天,沉井下沉施工为22天,总工期为31天,且由于钻孔分布均匀,沉井下沉较为顺利,几乎无需进行纠偏处理。其相同地质条件下的相邻工作井施工采用长臂炮机以及长臂挖掘机掘进下沉的常规方案共耗时69天,且在掘进过程中由于岩层的不均匀性,沉井底部受力不均匀导致沉井发生倾斜,进行了多次纠偏处理。对比相同地质条件下的相邻工作井的施工工期可知,采用本发明解决了硬岩地层掘进困难以及易发生倾斜的问题,且沉井施工周期缩减了50%。It can be seen from the examples that the construction period of the caisson is 9 days by using rotary drilling and drilling the pilot hole, the construction period of the caisson sinking is 22 days, and the total construction period is 31 days, and because the drilling holes are evenly distributed, the sinking of the caisson is relatively smooth, and there is almost no need for construction. Corrective processing. Under the same geological conditions, the construction of adjacent working wells using long-arm cannons and long-arm excavators took 69 days in total, and the bottom of the caisson was stressed due to the inhomogeneity of the rock formation during the excavation process. The unevenness caused the caisson to tilt, and several deviation corrections were performed. Comparing the construction period of adjacent working wells under the same geological conditions, it can be seen that the present invention solves the problems of difficult excavation in hard rock formations and prone to inclination, and the construction period of caissons is reduced by 50%.
本领域的技术人员容易理解,以上所述仅为本发明的较佳实施例而已,并不用于限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。It is easy for those skilled in the art to understand that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention, etc., All should be included within the protection scope of the present invention.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211149849.6A CN115478552A (en) | 2022-09-21 | 2022-09-21 | A kind of caisson sinking construction method under hard rock geological conditions |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211149849.6A CN115478552A (en) | 2022-09-21 | 2022-09-21 | A kind of caisson sinking construction method under hard rock geological conditions |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115478552A true CN115478552A (en) | 2022-12-16 |
Family
ID=84392807
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211149849.6A Pending CN115478552A (en) | 2022-09-21 | 2022-09-21 | A kind of caisson sinking construction method under hard rock geological conditions |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115478552A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117868241A (en) * | 2024-03-12 | 2024-04-12 | 北京航天地基工程有限责任公司 | Rotary digging device for building foundation |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105256819A (en) * | 2015-09-29 | 2016-01-20 | 中国一冶集团有限公司 | Improving method for open caisson sinking construction in geology of sludge layer |
CN111119191A (en) * | 2019-12-18 | 2020-05-08 | 中建三局基础设施建设投资有限公司 | Rock foundation pit guide hole type non-blasting excavation method |
CN114809053A (en) * | 2022-04-15 | 2022-07-29 | 中建新疆建工(集团)有限公司 | Novel construction method for quickly treating underground obstacles by prefabricated open caisson |
-
2022
- 2022-09-21 CN CN202211149849.6A patent/CN115478552A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105256819A (en) * | 2015-09-29 | 2016-01-20 | 中国一冶集团有限公司 | Improving method for open caisson sinking construction in geology of sludge layer |
CN111119191A (en) * | 2019-12-18 | 2020-05-08 | 中建三局基础设施建设投资有限公司 | Rock foundation pit guide hole type non-blasting excavation method |
CN114809053A (en) * | 2022-04-15 | 2022-07-29 | 中建新疆建工(集团)有限公司 | Novel construction method for quickly treating underground obstacles by prefabricated open caisson |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117868241A (en) * | 2024-03-12 | 2024-04-12 | 北京航天地基工程有限责任公司 | Rotary digging device for building foundation |
CN117868241B (en) * | 2024-03-12 | 2024-05-31 | 北京航天地基工程有限责任公司 | Rotary digging device for building foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104947690B (en) | Grooving construction method for embedding underground continuous wall into rock | |
WO2021088349A1 (en) | Method for excavating tunnel shaft | |
CN113832958B (en) | Anti-slide pile construction method with mechanical cooperation with manual excavation | |
CN110735600B (en) | Mechanical pore-forming pile construction process for karst geology | |
CN110565636A (en) | steel sheet pile construction method | |
CN102535440A (en) | Method of using all-casing drilling rig with rotary drilling rig to construct rock-socketed secant pile wall | |
CN103046931A (en) | Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode | |
CN109385997A (en) | The construction method of PHC tubular pole under narrow site condition | |
CN105019431B (en) | Crush and complete alternate steep dip stratified rock masses Large Diameter Super-long Bored Piles construction method | |
CN115478552A (en) | A kind of caisson sinking construction method under hard rock geological conditions | |
CN109826201A (en) | A kind of stepped support method for foundation pit in soft soil | |
CN203821414U (en) | Structure of protecting wall of hole-digging pile | |
CN111485549A (en) | Rotary drilling and buried drilling treatment method | |
CN108071110A (en) | Rotary drilling rig Pile method under complex geological condition | |
CN113431045B (en) | Construction method for rotary drilling pore-forming karst leaking stoppage | |
CN114351774A (en) | Method for predicting and processing collapsed hole of cast-in-place pile | |
CN114592791A (en) | A kind of deep bolt ground barrier device and ground barrier hole forming method for treating easily collapsed strata | |
CN209742922U (en) | Pre-reinforced Supporting Structure of Cast-in-situ Pile for Underconsolidated Stratum Underground Tunnel | |
CN110080209A (en) | Cast-in-place pile construction method in deep backfill | |
CN110714460A (en) | A mechanical hole-forming construction method for rectangular anti-sliding piles with reduced filling coefficient | |
CN115522537A (en) | Ultra-deep punching cast-in-place pile construction system and method suitable for large-water-head soft foundation | |
CN114482078A (en) | Hole forming construction method for square slide-resistant pile | |
CN212405120U (en) | Bored concrete pile of construction is executed to underground reinforced concrete structure department | |
CN115573378A (en) | Bearing platform construction method | |
CN205100226U (en) | Underground continuous wall goes into rock grooving construction equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |